Virginia Electric and Power Company (VEPCO) Clean Air Act Settlement

The Department of Justice and the Environmental Protection Agency announced on April 21, 2003 the largest Clean Air Act settlement of an enforcement matter against a utility. Virginia Electric and Power Co. (VEPCO) has agreed to spend $1.2 billion between now and 2013 to eliminate 237,000 tons of sulfur dioxide (SO2) and nitrogen oxides (NOx) emissions each year from eight coal-fired electricity generating plants in Virginia and West Virginia.

Today's settlement is the latest in a series of cases that the Bush Administration pursued to bring the coal-fired power plant industry into full compliance with the New Source Review requirements of the Clean Air Act. This settlement resolves charges that the company violated the laws by making major modifications to its power plants without installing equipment to control pollution that causes smog, acid rain and soot. The settlement also reflects the culmination of a well-coordinated partnership between EPA, the Justice Department and the States of New York, New Jersey, Connecticut, Virginia, West Virginia and the National Park Service.

In addition to providing for major pollution reductions, VEPCO agreed to pay a $5.3 million civil penalty and spend at least $13.9 million for projects in each of the five states that participated in the case and its settlement to offset the impact of past emissions. Specifically, VEPCO agreed to projects ranging from retrofitting or otherwise reducing emissions from diesel engines, including those on school buses, to installing photovoltaic cells on municipal buildings, to purchasing conservation easements to preserve environmentally sensitive areas, and to providing alternative-fueled vehicles for use in the Shenandoah National Park.

This settlement requires VEPCO, one of the nation's largest coal-fired electric utilities, to install new pollution control equipment and upgrade existing controls on several units in its system, and will result in substantial pollution reductions. The settlement covers eight VEPCO plants, six in Virginia and two in West Virginia, comprising 20 electricity-generating units. These eight plants emitted over 350,000 tons of SO2 and NOx in 2000. The settlement will reduce these emissions by approximately 67%, to 116,000 tons by 2013.

Sulfur dioxides (SO2) and nitrogen oxides (NOx) are significant contributors to acid rain; NOx also increases low-level ozone which causes smog; fine particulate matter causes haze and can adversely impact visibility in national parks. All of these pollutants cause severe respiratory problems and contribute to childhood asthma.

The proposed consent decree will be lodged with the United States District Court in Alexandria, Virginia for a thirty day public comment period.



For additional information, contact:

Richard Alonso
U.S. Environmental Protection Agency (2242A)
1200 Pennsylvania Ave., N.W.
Washington, DC 20460-0001
(202) 564-2809