Jump to main content.


National Pollutant Discharge Elimination System-- Proposed Regulations To Establish Requirements for Cooling Water Intake Structures at Phase III Facilities [[pp. 68493-68542]]

Note: EPA no longer updates this information, but it may be useful as a reference or resource.


 
[Federal Register: November 24, 2004 (Volume 69, Number 226)]
[Proposed Rules]
[Page 68493-68542]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr24no04-26]
 
[[pp. 68493-68542]]
National Pollutant Discharge Elimination System--Proposed 
Regulations To Establish Requirements for Cooling Water Intake 
Structures at Phase III Facilities

[[Continued from page 68492]]
[[Page 68493]]

impingement or entrainment, or significant adverse impacts on energy 
markets. In this case, alternative requirements may be imposed in the 
permit. See the Phase I final preamble for a more detailed explanation 
of this cost-cost test which is different than the cost-cost test for 
existing sources (66 FR 65256).
    Fixed facilities with seachests and all non-fixed (or ``mobile'') 
facilities would not be required to comply with standards for 
entrainment. Fixed facilities with seachests may choose either Track I 
or Track II to comply with impingement mortality performance standards. 
Non-fixed facilities must comply with the 0.5 feet per second through-
screen design intake flow velocity performance standard for impingement 
mortality of Track I. In addition, the Director may determine 
additional design and construction technologies to minimize impingement 
mortality are necessary where there are either protected species of 
concern within the hydrologic zone of influence of the cooling water 
intake structure, or based on other information from fishery management 
services or agencies. The new mobile facility, when applying to operate 
under a general permit, would identify where it expects to be 
operating. The Director consults with the fishery management agencies, 
considers their data as well as any other relevant data, and decides 
whether to propose additional requirements based on any concerns the 
Director identifies (see Sec.  125.134(b)(4)). For example, Region 10 
has established a general permit for Cooks Inlet that established a 0.1 
feet per second through-screen design intake flow velocity performance 
standard. However, non-fixed facilities would not be required to submit 
the source water baseline biological characterization data and some 
aspects of the source water physical data requirements. Requirements 
for non-fixed facilities are described later in this section.
    EPA notes that some mobile facilities (e.g. some jack-ups) may not 
have seachests and therefore could feasibly install entrainment 
controls. EPA proposes not to require entrainment controls for these 
mobile facilities due to the transient nature of their operations and 
an expectation that they are not likely to cause significant impacts. 
EPA took a similar approach in its Phase II rule when the Agency did 
not require entrainment controls at power plants that operate less than 
15 percent of the year. EPA solicits comment and data on its proposal 
to only require impingement controls at mobile facilities that do not 
have seachests.
1. For New Offshore Oil and Gas Extraction Fixed Facilities, What 
Information Is Required To Be Collected for the NPDES Application?

Source Water Baseline Biological Characterization Data (Sec.  
122.21(r)(4)) (Both Track I and II)

    Under today's proposed rule, new offshore oil and gas extraction 
fixed facilities would be required to submit source water baseline 
biological characterization data as required under Phase I. The data 
would be used to characterize the biological community in the vicinity 
of the cooling water intake structure and to characterize the operation 
of the cooling water intake structure. The data would include existing 
data (if available) supplemented with new field studies as necessary. 
Detailed data requirements are at Sec.  122.21(r)(4). Under today's 
proposed rule, a group of fixed facilities may choose to conduct a 
regional study to collect this information as approved by the Director. 
EPA recognizes that many offshore oil and gas extraction facilities are 
regulated under NPDES general permits and that regional studies are 
typically conducted as part of the general permit requirements. EPA 
anticipates the regional studies would be conducted once each permit 
cycle. Under today's proposed rule, the regional study would also 
include annual monitoring requirements.

Velocity Information (Track I)

    Today's proposed rule would require that new offshore oil and gas 
extraction fixed facilities submit velocity information consistent with 
Sec.  125.136(b)(2). The information would be used to demonstrate to 
the Director that the facility is complying with the requirement to 
meet a maximum through-screen design intake velocity of no more than 
0.5 feet per second at the cooling water intake structure. The 
following information would be required to be submitted: (1) A 
narrative description of the design, structure, equipment, and 
operation used to meet the velocity requirement; and (2) design 
calculations showing that the velocity requirement would be met at 
minimum ambient source water surface elevations (based on best 
professional judgment using available hydrological data) and maximum 
head loss across the screens or other device or, if the facility uses 
devices other than a surface intake screen, at the point of entry to 
the device.

Source Waterbody Flow Information (Track I and II)

    Today's proposed rule would also require that new offshore oil and 
gas extraction fixed facilities submit source waterbody flow 
information in accordance with Sec.  125.136(b)(2) or (c)(1). The 
information would be used to demonstrate to the Director that the 
facility's cooling water intake structure meets the proportional flow 
requirements at Sec.  125.134(b)(3) or (c)(2). These requirements would 
include specific provisions for fixed facilities located on estuaries 
or tidal rivers to provide greater protection for these sensitive 
waters. Specifically, the proposed rule would require that the total 
design intake flow over one tidal cycle of ebb and flow must be no 
greater than one (1) percent of the volume of the water column within 
the area centered about the opening of the intake with a diameter 
defined by the distance of one tidal excursion at the mean low water 
level. Calculations and guidance on determining the tidal excursion is 
found in the preamble to the final Phase I rule at section VII.B.1.d.

Design and Construction Technology Plan (Track I)

    Today's proposed rule would also require that new offshore oil and 
gas extraction fixed facilities submit a design and construction 
technology plan consistent with Subpart N requirements at Sec.  
125.136(b)(3). The design and construction technology plan would 
demonstrate that the facility has selected and will implement the 
design and construction technologies necessary to minimize impingement 
mortality and/or entrainment in accordance with Sec.  125.134(b)(4) 
and/or (5). The design and construction technology plan would require 
delineation of the hydrologic zone of influence for the cooling water 
intake structure; a description of the technologies implemented (or to 
be implemented) at the facility; the basis for the selection of that 
technology; the expected performance of the technology, and design 
calculations, drawings and estimates to support the technology 
description and performance. The Agency recognizes that the selection 
of a specific technology or a group of technologies would depend on the 
individual facility and waterbody conditions.

Track II Comprehensive Demonstration Study (Track II)

    If a fixed facility chooses to comply under the Track II approach, 
the facility would perform and submit the results of

[[Page 68494]]

a Comprehensive Demonstration Study (Study). This information would be 
used to characterize the source water baseline in the vicinity of the 
cooling water intake structure(s); characterize operation of the 
cooling water intake(s); and to confirm that the technology(ies) 
proposed and/or implemented at the cooling water intake structure 
reduce the impacts to fish and shellfish to levels comparable to those 
the facility would achieve were it to implement the applicable 
requirements in Sec.  125.134(b)(2) and, for facilities without 
seachests, Sec.  125.134(b)(5). To meet the ``comparable level'' 
requirement, the facility would demonstrate that it has reduced both 
impingement mortality and entrainment of all life stages of fish and 
shellfish to 90 percent or greater of the reduction that would be 
achieved through the applicable requirements in Sec.  125.134(b)(2) 
and, for facilities without seachests, Sec.  125.134(b)(5).
    Similar to the Proposal for Information Collection required in 
Phase II, the facility would develop and submit a plan to the Director 
containing a proposal for how information will be collected to support 
the study. The plan would include:
    ? A description of the proposed and/or implemented 
technology(ies) to be evaluated in the Study;
    ? A list and description of any historical studies 
characterizing the physical and biological conditions in the vicinity 
of the proposed or actual intakes and their relevancy to the proposed 
Study. If the facility proposes to rely on existing source waterbody 
data, the data must be no more than 5 years old, and the facility would 
demonstrate that the existing data are sufficient to develop a 
scientifically valid estimate of potential impingement mortality and 
entrainment impacts, and provide documentation showing that the data 
were collected using appropriate quality assurance/quality control 
procedures;
    ? Any public participation or consultation with Federal or 
State agencies undertaken in developing the plan; and
    ? A sampling plan for data that will be collected using 
actual field studies in the source waterbody. The sampling plan would 
document all methods and quality assurance procedures for sampling, and 
data analysis. The sampling and data analysis methods proposed would be 
appropriate for a quantitative survey and based on consideration of 
methods used in other studies performed in the source waterbody. The 
sampling plan would include a description of the study area (including 
the area of influence of the cooling water intake structure and at 
least 100 meters beyond); taxonomic identification of the sampled or 
evaluated biological assemblages (including all life stages of fish and 
shellfish); and sampling and data analysis methods.
    The facility would submit documentation of the results of the Study 
to the Director. Documentation of the results of the Study would 
include: Source Water Biological Study, an evaluation of potential 
cooling water intake structure effects, and a verification monitoring 
plan as described below.
    Source Water Biological Study. The Source Water Biological Study 
would include:
    (1) A taxonomic identification and characterization of aquatic 
biological resources including: A summary of historical and 
contemporary aquatic biological resources; determination and 
description of the target populations of concern (those species of fish 
and shellfish and all life stages that are most susceptible to 
impingement and entrainment); and a description of the abundance and 
temporal/spatial characterization of the target populations based on 
the collection of multiple years of data to capture the seasonal and 
daily activities (e.g., spawning, feeding and water column migration) 
of all life stages of fish and shellfish found in the vicinity of the 
cooling water intake structure;
    (2) An identification of all threatened or endangered species that 
might be susceptible to impingement and entrainment by the proposed 
cooling water intake structure(s); and
    (3) A description of additional chemical, water quality, and other 
anthropogenic stresses on the source waterbody.
    Evaluation of potential cooling water intake structure effects. 
This evaluation would include:
    (1) Calculations of the reduction in impingement mortality and, if 
applicable, entrainment of all life stages of fish and shellfish that 
would need to be achieved by the technologies selected to implement to 
meet requirements under Track II. To do this, the facility would 
determine the reduction in impingement mortality and entrainment that 
would be achieved by implementing the requirements of Sec.  
125.134(b)(2) and, for facilities without seachests, Sec.  125.134(b)(5).
    (2) An engineering estimate of efficacy for the proposed and/or 
implemented technologies used to minimize impingement mortality and, if 
applicable, entrainment of all life stages of fish and shellfish and 
maximize survival of impinged life stages of fish and shellfish. The 
facility would demonstrate that the technologies reduce impingement 
mortality and, if applicable, entrainment of all life stages of fish 
and shellfish to a comparable level to that which would be achieved if 
the facility were to implement the requirements in Sec.  125.134(b)(2) 
and, for facilities without seachests, Sec.  125.134(b)(5). The 
efficacy projection would include a site-specific evaluation of 
technology(ies) suitability for reducing impingement mortality and 
entrainment based on the results of the Source Water Biological Study. 
Efficacy estimates may be determined based on case studies that have 
been conducted in the vicinity of the cooling water intake structure 
and/or site-specific technology prototype studies.
    Verification monitoring plan. The fixed facility would include in 
the Study a plan to conduct, at a minimum, two years of monitoring to 
verify the full-scale performance of the proposed or implemented 
technologies, and/or operational measures. The verification study would 
begin at the start of operations of the cooling water intake structure 
and continue for a sufficient period of time to demonstrate that the 
facility is reducing the level of impingement mortality and entrainment 
to the level documented under the evaluation of potential cooling water 
intake structure effects. The plan would describe the frequency of 
monitoring and the parameters to be monitored. The Director would use 
the verification monitoring to confirm that the facility is meeting the 
level of impingement mortality and entrainment reduction required in 
Sec.  125.134(c), and that the operation of the technology has been 
optimized.
2. As an Owner or Operator of a New Offshore Oil and Gas Extraction 
Fixed Facility, What Monitoring Is Required?
    Monitoring requirements for new offshore oil and gas extraction 
fixed facilities include impingement mortality and entrainment if the 
facility does not have a seachest. If the fixed facility has a 
seachest, monitoring requirements include impingement mortality only.
    Under today's proposal, monitoring would characterize the 
impingement and, if applicable, entrainment rates of commercial, 
recreational, and forage base fish and shellfish species identified in 
either the Source Water Baseline Biological Characterization data 
required by 40 CFR 122.21(r)(3) or the Comprehensive Demonstration 
Study required by Sec.  125.136(c)(2), depending on whether the 
facility has a seachest.

[[Page 68495]]

The monitoring methods used would be consistent with those used for the 
Source Water Baseline Biological Characterization data required in 40 
CFR 122.21(r)(4) or the Comprehensive Demonstration Study required by 
Sec.  125.136(c)(2).
    The fixed facility would be required to follow the monitoring 
frequencies identified below for at least two (2) years after the 
initial permit issuance. After that time, the Director may approve a 
request for less frequent sampling in the remaining years of the permit 
term and when the permit is reissued, if supporting data show that less 
frequent monitoring would still allow for the detection of any seasonal 
and daily variations in the species and numbers of individuals that are 
impinged or entrained.
    Impingement sampling. The facility would collect samples to monitor 
impingement rates (simple enumeration) for each species over a 24-hour 
period and no less than once per month when the cooling water intake 
structure is in operation.
    Entrainment sampling. If the fixed facility does not use a 
seachest, it would collect samples to monitor entrainment rates (simple 
enumeration) for each species over a 24-hour period and no less than 
biweekly during the primary period of reproduction, larval recruitment, 
and peak abundance identified during the Source Water Baseline 
Biological Characterization required by 40 CFR 122.21(r)(4) or the 
Comprehensive Demonstration Study required in Sec.  125.136(c)(2). 
Samples would be collected only when the cooling water intake structure 
is in operation.
    Velocity monitoring. If the facility uses a surface intake screen 
system, it would be required to monitor head loss across the screens 
and correlate the measured value with the design intake velocity. The 
head loss across the intake screen would be measured at the minimum 
ambient source water surface elevation (using best professional 
judgment based on available hydrological data). The maximum head loss 
across the screen for each cooling water intake structure would be used 
to determine compliance with the velocity requirement in Sec.  
125.134(b)(2). If the facility uses devices other than surface intake 
screens, it would monitor velocity at the point of entry through the 
device. Head loss or velocity would be monitored during initial 
facility startup, and thereafter, at the frequency specified in the 
NPDES permit, but no less than once per quarter.
    Visual or remote inspections. The facility would conduct visual 
inspections or employ remote monitoring devices during the period the 
cooling water intake structure is in operation. Visual inspections 
would be conducted at least weekly to ensure that any design and 
construction technologies required in Sec.  125.134(b)(4), (b)(5), (c), 
and/or (d) are maintained and operated to ensure that they will 
continue to function as designed. Alternatively, the facility would be 
required to inspect via remote monitoring devices to ensure that the 
impingement and entrainment technologies are functioning as designed.
3. What Recordkeeping and Reporting Is Required for New Offshore Oil 
and Gas Extraction Fixed Facilities?
    Owners and operators of new offshore oil and gas extraction fixed 
facilities would be required to keep records of all the data used to 
complete the permit application and show compliance with the 
requirements, any supplemental information developed under Sec.  
125.136, and any compliance monitoring data submitted under Sec.  
125.137, for a period of at least three years from the date of permit 
issuance. The Director may require that these records be kept for a 
longer period.
    Additionally, today's proposal would require that new offshore oil 
and gas extraction fixed facilities submit the following in a yearly 
status report:
    ? Biological monitoring records for each cooling water 
intake structure as required by Sec.  125.137(a);
    ? Velocity and head loss monitoring records for each cooling 
water intake structure as required by Sec.  125.137(b); and
    ? Records of visual or remote inspections as required in 
Sec.  125.137(c).
4. For New Non-Fixed (Mobile) Offshore Oil and Gas Extraction 
Facilities, What Information Is Required To Be Collected for the NPDES 
Application?

Velocity Information (Track I)

    Today's proposed rule would require that new nonfixed (mobile) 
offshore oil and gas extraction facilities submit velocity information 
consistent with Sec.  125.136(b)(1). The information would be used to 
demonstrate to the Director that the facility is complying with the 
requirement to meet a maximum through-screen design intake velocity of 
no more than 0.5 feet per second at the cooling water intake structure. 
The following information would be required to be submitted: (1) A 
narrative description of the design, structure, equipment, and 
operation used to meet the velocity requirement; and (2) design 
calculations showing that the velocity requirement would be met at 
minimum ambient source water surface elevations (based on best 
professional judgment using available hydrological data) and maximum 
head loss across the screens or other device.

Design and Construction Technology Plan (Track I)

    Today's proposed rule would require that new nonfixed (mobile) 
offshore oil and gas extraction facilities submit a design and 
construction technology plan only when required by the Director 
consistent with Sec.  125.134(b)(4). The design and construction 
technology plan would demonstrate that the facility has selected and 
will implement the design and construction technologies necessary to 
minimize impingement mortality in accordance with Sec.  125.134(b)(4). 
The design and construction technology plan would require delineation 
of the hydrologic zone of influence for the cooling water intake 
structure; a description of the technologies implemented (or to be 
implemented) at the facility; the basis for the selection of that 
technology; the expected performance of the technology, and design 
calculations, drawings and estimates to support the technology 
description and performance. The Agency recognizes that the selection 
of a specific technology or a group of technologies would depend on the 
individual facility and waterbody conditions.
5. As an Owner or Operator of a New Non-Fixed (Mobile) Offshore Oil and 
Gas Extraction Facility, What Monitoring Is Required?
    Under today's proposal, the Director may require monitoring to 
characterize the impingement of commercial, recreational, and forage 
base fish and shellfish species as specified by the Director in 
accordance with Sec.  125.134(b)(4) or Sec.  125.134(d).
    Velocity monitoring. If the mobile facility uses a surface intake 
screen system, it would be required to monitor head loss across the 
screens and correlate the measured value with the design intake 
velocity. The head loss across the intake screen would be measured at 
the minimum ambient source water surface elevation (using best 
professional judgment based on available hydrological data). The 
maximum head loss across the screen for each cooling water intake 
structure would be used to determine compliance with the velocity 
requirement in Sec.  125.134(b)(2). If the facility uses devices other 
than surface intake screens, it would monitor velocity at the

[[Page 68496]]

point of entry through the device. Head loss or velocity would be 
monitored during initial facility startup, and thereafter, at the 
frequency specified in the NPDES permit, but no less than once per 
quarter.
    Visual or remote inspections. The facility would conduct visual 
inspections or employ remote monitoring devices during the period the 
cooling water intake structure is in operation. Visual inspections 
would be conducted at least weekly to ensure that any design and 
construction technologies required in Sec.  125.134(b)(4), (b)(5), (c), 
and/or (d) are maintained and operated to ensure that they will 
continue to function as designed. Alternatively, the facility would be 
required to inspect via remote monitoring devices to ensure that the 
impingement technologies are functioning as designed.
6. What Recordkeeping and Reporting Is Required for New Non-Fixed 
(Mobile) Offshore Oil and Gas Extraction Facilities?
    Owners and operators of new mobile offshore oil and gas extraction 
facilities would be required to keep records of all the data used to 
complete the permit application and show compliance with the 
requirements, any supplemental information developed under Sec.  
125.136, and any compliance monitoring data submitted under Sec.  
125.137, for a period of at least three years from the date of permit 
issuance. The Director may require that these records be kept for a 
longer period.
    Additionally, today's proposal would require that new mobile 
offshore oil and gas extraction facilities submit the following in a 
yearly status report:
    ? Velocity and head loss monitoring records for each cooling 
water intake structure as required by Sec.  125.137(b); and
    ? Records of visual or remote inspections as required in 
Sec.  125.137(c).

E. What Are the Respective Federal, State, and Tribal Roles?

    Section 316(b) requirements are implemented through NPDES permits. 
Under 40 CFR 123.62(e), any existing approved State or Tribal section 
402 permitting program would be revised to be consistent with new 
program requirements within one year from the date of promulgation, 
unless the NPDES-authorized State or Tribe amends or enacts a statute 
to make the required revisions. If a State or Tribe amends or enacts a 
statute to conform with any promulgated Phase III rule, the revision 
would be required to be made within two years of promulgation. States 
and Tribes seeking new EPA authorization to implement the NPDES program 
would be required to comply with the requirements when authorization is 
requested.
    This proposed regulation would not alter State authority under 
section 510 of the Clean Water Act. EPA recognizes that some States 
have invested considerable effort in developing section 316(b) 
regulations and implementing programs. EPA is proposing regulations 
that would allow States to continue to use these programs by including 
in this national rule a provision that allows States to use their 
existing program if the State establishes that such programs would 
achieve comparable environmental performance. Specifically, the 
proposed rule would allow any State to demonstrate to the Administrator 
that it has adopted alternative regulatory requirements that would 
result in environmental performance within each relevant watershed that 
is comparable to the reductions in impingement mortality and 
entrainment that would be achieved under Sec.  125.103.
    In addition to updating their programs to be consistent with 
today's proposed rule, States and Tribes authorized to implement the 
NPDES program would be required to implement the cooling water intake 
structure requirements following promulgation of the proposed 
regulations. The requirements would have to be implemented upon the 
issuance or reissuance of permits containing the requirements of 
Subpart K or N. Duties of an authorized State or Tribe under this 
regulation may include:
    ? Review and verification of permit application materials, 
including a permit applicant's determination of source waterbody 
classification and the flow or volume of certain waterbodies at the 
point of the intake;
    ? Determination of the standards in Sec.  125.103(b) or 
Sec.  125.134 that apply to the facility, or authorize alternative 
requirements in Sec.  125.135;
    ? Verification of a permit applicant's determination of 
whether it meets or exceeds the applicable performance standards or 
requirements;
    ? Verification that a permit applicant's Design and 
Construction Technology Plan demonstrates that the proposed alternative 
technologies would reduce the impacts to fish and shellfish to levels 
required;
    ? Verification that a permit applicant meets the cost test 
and that permit conditions developed on a site-specific basis are 
justified based on documented costs, and, if applicable, benefits;
    ? Verification that a permit applicant's proposed 
restoration measures would meet regulatory standards (existing 
facilities only);
    ? Development of draft and final NPDES permit conditions for 
the applicant implementing applicable section 316(b) requirements 
pursuant to this rule; and
    ? Ensuring compliance with permit conditions based on 
section 316(b) requirements.
    EPA also will implement these requirements where States or Tribes 
are authorized to implement the NPDES program but do not have 
sufficient authority to implement these requirements.
    In the discussion of Federal, State and Tribal roles in the 
preamble to the Phase II final regulations (69 FR 41643, 3rd col.), EPA 
stated that ``EPA will implement these requirements where States or 
Tribes are not authorized to implement the NPDES program. EPA also will 
implement these requirements where States or Tribes are authorized to 
implement the NPDES program but do not have sufficient authority to 
implement these requirements.'' EPA notes that the second sentence in 
this quote incorrectly stated EPA's authority. In fact, EPA does not 
have authority to issue NPDES permits where States or Tribes are 
authorized to administer the NPDES program except after EPA vetoes a 
permit. (See Sec.  123.61(c) and Sec.  123.44(h).) Today's preamble 
correctly states that States and Tribes authorized to implement the 
NPDES program would need to have or obtain sufficient authority to 
implement final Phase III regulations. EPA intends to issue guidance to 
clarify that, pursuant to Sec.  123.25(a)(36), States and Tribes 
authorized to implement the NPDES program must have or obtain 
sufficient authority to implement the Phase II regulations.

F. Are Permits for Phase III Facilities Subject to Requirements Under 
Other Federal Statutes?

    EPA's NPDES permitting regulations at 40 CFR 122.49 contain a list 
of Federal laws that might apply to Federally issued NPDES permits. 
These include the Wild and Scenic Rivers Act, 16 U.S.C. 1273 et seq.; 
the National Historic Preservation Act of 1966, 16 U.S.C. 470 et seq.; 
the Endangered Species Act, 16 U.S.C. 1531 et seq.; the Coastal Zone 
Management Act, 16 U.S.C. 1451 et seq.; and the National Environmental 
Policy Act, 42 U.S.C. 4321 et seq. See 40 CFR 122.49 for a brief 
description of each of these laws. In addition, the provisions of the 
Magnuson-Stevens Fishery Conservation and Management Act, 16 U.S.C. 
1801 et seq., relating to essential

[[Page 68497]]

fish habitat might be relevant. Nothing in this proposed rulemaking 
would authorize activities that are not in compliance with these or 
other applicable Federal laws.

VIII. Economic Impact Analysis

    The discussion in this section summarizes EPA's analysis of total 
social cost and economic impacts for three co-proposed options for 
existing facilities: the ``50 MGD for All Waterbodies'' option, the 
``200 MGD for All Waterbodies'' option, and the ``100 MGD for Certain 
Waterbodies'' option. These options are described more fully in section 
VI. EPA also conducted analyses for other potential regulatory 
definitions, including applying requirements to all facilities with 
design intake flow of at least 2 MGD. This definition would have 
included all 683 potentially regulated Phase III facilities. This and 
other potential regulatory specifications are not being proposed 
because of economic practicability concerns, but analyses for them can 
be found in ``Economic Analysis for the Proposed Section 316(b) Rule 
for Phase III Facilities'' (hereafter referred to as the ``EA''; DCN 7-
0002). This section also presents EPA's estimates of total social cost 
and economic impacts for new offshore oil and gas extraction 
facilities. EPA's assessment of costs and economic impacts, including 
results for all analyzed regulatory definitions, can be found in the EA.

A. Existing Phase III Facilities: Manufacturers and Electric Power 
Producers

1. Overview of Affected Industry Sectors
    For the economic analyses, EPA distinguished between the types of 
facilities as follows:
    ? Manufacturing and Other Industries (``Manufacturers'')--
facilities in the paper, aluminum, steel, chemicals, petroleum and 
other industries. In addition to engaging in production activities, 
some of these facilities also generate electricity for their own use 
and occasionally for sale.
    ? Electric power producers (``Electric Generators'')--
facilities owned by investor-owned utilities, municipalities, States, 
Federal authorities, cooperatives, and non-utilities.
    Within the Manufacturers group, EPA focused its analysis on five 
manufacturing industries--Paper, Chemicals, Petroleum, Aluminum, and 
Steel (the ``Primary Manufacturing Industries'')--as the industries 
using the largest amounts of cooling water outside of the electric 
power generating industry. EPA's economic analysis for these industries 
is based on a statistically-valid survey sample of facilities in these 
five industries. This analysis also considers the effect of the 
regulation on facilities in other industries (``Other Industries'') 
that use cooling water to a lesser extent than the five Primary 
Manufacturing Industries and that are also covered by the proposal. The 
analysis for Other Industries is restricted to a limited sample of 
facilities for which EPA received detailed surveys but which are not 
part of the statistically valid sample. As a result, EPA's analysis of 
facilities in the Other Industries group is limited to the known 
facilities in this group. EPA has not specifically estimated the total 
number of facilities in the Other Industries group that may be subject 
to the regulation because EPA does not believe that this number can be 
reliably extrapolated from the number of known facilities in this 
group. However, because the six surveyed industries (including electric 
power) account for 99% of total cooling water withdrawals, EPA believes 
that few additional facilities in the Other Industries group are 
potentially subject to today's proposed regulation. EPA seeks comment 
and data on the number of facilities in the Other Industries group that 
may be subject to today's proposal.
    EPA's analysis also reflects a limited number facilities in the 
Virgin Islands and Puerto Rico for which EPA received detailed survey 
responses. These facilities have also been included in EPA's economic 
analysis. EPA is clarifying today's proposal would apply to any 
facility meeting the applicability criteria in Sec.  125.101. EPA seeks 
comment and data on the total number of facilities that may be subject 
to today's proposal.
    EPA's review of the engineering characteristics of cooling water 
intake and use in the Other Industries group indicates that cooling 
water intake and use in these industries do not differ materially from 
cooling water intake and use in the Primary Manufacturing Industries 
and the electric power industry. In addition, EPA specifically analyzed 
the economic impacts of the proposed options on known facilities in the 
Other Industries group. EPA believes that its findings of no economic 
impact to the known facilities in Other Industries and the 
practicability of the proposed options are generally applicable to the 
full breadth of industries within the regulation's scope. EPA is 
seeking comment and data on the economic impact and practicability of 
the proposed options on facilities in the Other Industries group.
    EPA estimates that as many as 566 facilities in the Manufacturers 
segment (including 537 facilities in the Primary Manufacturing 
Industries and 29 known facilities in Other Industries), and 117 
Electric Generators are potentially subject to this rulemaking, based 
on a design intake flow applicability threshold of greater than 2 MGD. 
EPA excluded from the analysis for each option those facilities that 
are below the option's design intake flow applicability threshold and 
would therefore not incur compliance costs. In addition, EPA's analyses 
identified existing facilities that are in severe financial distress 
independent of regulation. These facilities, referred to as ``baseline 
closures,'' were determined as likely to terminate business operations 
independent of the proposed options and were also excluded from the 
analyses presented in this section.
    Exhibit VIII-1 presents, by waterbody type and industry, EPA's 
estimates of (1) the number of existing facilities potentially subject 
to this rulemaking, (2) the number of baseline closures, and (3) the 
number of existing facilities subject to national requirements under 
five different design intake flow applicability thresholds.

                                   Exhibit VIII-1.--Phase III Existing Facility Counts, by Waterbody Type and Industry
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                               Facilities subject to national requirements with DIF
                                                               Potentially                applicability threshold of greater than or equal to (in MGD),
                           Industry                             subject to    Baseline                     excluding baseline closures
                                                                regulation    closure   ----------------------------------------------------------------
                                                                                              2            20           50          100          200
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                     All Waterbodies
--------------------------------------------------------------------------------------------------------------------------------------------------------
Primary Man. Industries......................................          537           73          464          290          127           58           23
Other Industries.............................................           29            4           25           12            9            5            2

[[Page 68498]]


Electric Generators..........................................          117            3          114           51            0            0            0
                                                              --------------
    Total....................................................          683           80          603          353          136           63           25
                                                              ==============
    Total DIF (MGD)..........................................       40,441        4,440       36,001       33,683       26,714       21,587       16,144
--------------------------------------------------------------
                                                                 Coastal and Great Lakes
--------------------------------------------------------------------------------------------------------------------------------------------------------
Primary Man. Industries......................................          110           17           94           67           35           17           10
Other Industries.............................................            9            3            6            5            4            2            1
Electric Generators..........................................           11            0           11            4            0            0            0
                                                              --------------
    Total....................................................          130           20          111           76           39           19           11
                                                              ==============
    Total DIF (MGD)..........................................       11,010        2,423        8,587        8,179        7,190        5,747        4,418
--------------------------------------------------------------
                                                                         Inland
--------------------------------------------------------------------------------------------------------------------------------------------------------
Primary Man. Industries......................................          427           56          371          223           92           41           13
Other Industries.............................................           20            1           19            7            5            3            1
Electric Generators..........................................          106            3          103           47            0            0            0
                                                              --------------
    Total....................................................          553           60          493          277           97           44           14
                                                              ==============
    Total DIF (MGD)..........................................       29,431        2,017       27,414       25,504       19,524       15,841       11,726
--------------------------------------------------------------------------------------------------------------------------------------------------------

2. Method for Estimating Costs to Manufacturers and Electric Generators
    EPA estimated capital costs of technologies, annual operation and 
maintenance costs, installation downtime costs, and permitting costs. 
The cost estimates reflect the incremental costs attributed only to 
today's proposal. For example, facilities with closed-cycle 
recirculating systems already meet the proposed performance standards, 
and therefore would not incur costs for new technologies, additional 
annual operational costs, or downtime costs (though such facilities 
would still incur some components of permitting costs).
    For estimating the incremental compliance costs attributable to the 
proposed options, EPA developed both facility-specific and model 
facility costs. Facility-specific compliance costs require detailed 
process information about many, if not all, facilities in the industry. 
These data typically include production, capacity, water use, 
wastewater generation, monitoring results, geographic location, 
financial conditions, technologies and practices already in place, and 
other facility-specific data. EPA used a detailed technical survey of 
Electric Generators and Manufacturers to collect these data (see 
section III for more information on EPA's detailed survey). These data 
and detailed process information were used to determine whether new 
controls would be necessary to meet the standards of the proposed rule, 
and to estimate the cost of installing any new or additional controls. 
While the Agency is confident that the suite of available technologies 
can achieve compliance with the proposed performance requirements (60-
90 percent reduction in entrainment and 80-95 percent reduction in 
impingement mortality relative to the calculation baseline), EPA lacks 
sufficient data and resources to determine the precise cost and 
performance of each technology on a site-specific basis. Therefore, EPA 
first calculated the facility-specific costs for 348 facilities for 
which detailed information was available, and applied the model 
facility approach to the remaining facilities to calculate the 
industry-level costs for the approximately 700 existing Manufacturers 
and Electric Generators.
    In costing each model facility, EPA, to a degree, departed from its 
traditional least-cost approach. The least-cost approach relies on the 
principle that the complying facility will choose the most cost-
effective compliance alternative to meet the regulatory requirements. 
In most cases, this means the facility will install the least-cost 
technology that meets the minimum standard. Instead of selecting the 
least-cost compliance alternative (see section VI for a description of 
the compliance alternatives), a best-performing technology was assigned 
to a model facility utilizing a spreadsheet program called the ``cost-
test tool.'' The cost-test tool determines one of two possible 
performance expectations: (1) Impingement requirements only or (2) both 
impingement and entrainment requirements. The cost-test tool then 
determines a compliance response for the facility/intake by accounting 
for existing technologies (such as wedgewire screens) and conditions 
(such as a shoreline intake location or the through-screen velocity). 
Next, the cost-test tool applies EPA's decision tree for assigning one 
of 12 technology modules as the best-performing technology to a site 
(see Figure 2-1 of the Phase III TDD for a schematic of this decision 
tree). This should not be construed to mean today's proposed options 
would require facilities to install the technologies selected by the 
cost-test tool. Under today's proposal, facilities could choose any 
technology, combination of technologies, or operational measures that 
would meet the requirements of the selected compliance alternative 
along with any other additional permit requirements. Finally, cost 
estimates are derived through a combination of calculations and 
functions that apply facility-specific data to the selected technology 
module. The cost outputs include capital costs, incremental operating 
and maintenance (O&M) costs, and installation downtime (in weeks).

[[Page 68499]]

    Based on data from EPA's detailed technical survey, EPA believes 
that cooling water intake structures at Electric Generators are, in 
general, no different from those intake structures employed by 
Manufacturers. Therefore, the Phase II costs attributed to control 
technologies were used to calculate costs for potentially regulated 
existing Phase III Manufacturers and Electric Generators. EPA generally 
utilized the original methodology published in the Phase II NODA (68 FR 
13522; March 19, 2003), accounting for comments received from the 
public. EPA also used the costing equations it developed for the final 
Phase II rule, along with the site-specific data obtained from the 
detailed surveys. EPA requests comment, including supporting data, on 
the use of technologies and costing equations from the Phase II rule in 
the Phase III analysis.
    Permit costs, including costs for permitting, monitoring, permit 
reissuance, and recordkeeping, are not included in the cost-test tool. 
Costs for these activities were developed separately as part of the 
Information Collection Request (ICR) for Cooling Water Intake 
Structures Phase III Proposed Rule (``ICR''; DCN 7-0001). The per 
facility permit costs were added to the incremental compliance costs, 
along with installation downtime costs (where appropriate), in 
developing the total model facility cost. The per facility permit costs 
may be found in Chapter B1 of the EA.
    In addition to the capital and annual operating costs of the 
selected technology module, 16 facilities (sample-weighted, with more 
than 50 MGD intake, and excluding baseline closures) incur downtime 
costs. Downtime costs generally reflect decreased revenues due to lost 
production or costs of supplemental power purchases during the retrofit 
of existing cooling water intake structures. EPA determined that an 
additional four facilities with multiple intakes could shut off any one 
intake and still meet their average intake flow without exceeding the 
total design intake flow of the remaining intakes. Furthermore, these 
facilities all have shoreline intakes, negating the need to maintain 
costly offshore equipment necessary to retrofit one intake at a time. 
EPA assumes these four facilities could retrofit one intake at a time, 
thereby avoiding downtime costs. In all other cases, the length of 
downtime (in weeks) and the general approach to estimating the cost of 
downtime are the same as used for the Phase II analysis. See chapter 5 
of the TDD for more details. EPA solicits comment and supporting data 
on this approach to estimating downtime costs.
    Total social costs are presented in section VIII.C of this 
preamble.
    Under today's proposal, facilities have five compliance 
alternatives for meeting the performance standards. Not all of these 
compliance alternatives are addressed by the cost-test tool. The cost-
test tool, and therefore total national costs, do not specifically 
adjust for site-specific requirements developed in accordance with 
compliance alternative 5 (see also section VI of this preamble). While 
costs for facilities requesting alternative requirements based on the 
cost-cost test should be comparable to EPA's estimated costs, costs for 
facilities requesting alternative requirements based on the cost-
benefit test may be less. In addition, each model facility was costed 
for a single best-performing technology module, which does not 
necessarily reflect the most cost-effective compliance alternative. 
Thus, although EPA's costs for each model facility to install a 
specified compliance technology are believed to be accurate, the total 
national costs of today's proposal may be overstated.
    EPA solicits comment on all aspects of this costing approach.
3. Social Cost for Manufacturers and Electric Generators
    EPA calculated the social cost of the three co-proposed options for 
existing Manufacturers and Electric Generators using two discount rate 
values: 3 percent and 7 percent. All dollar values presented in this 
preamble are in 2003 dollars (average or mid-year). For the analysis of 
social costs, EPA discounted all costs to the beginning of 2007, the 
date at which this proposal is assumed to become effective. EPA assumed 
that all facilities subject to the regulation would achieve compliance 
between 2010 and 2014, and estimated the time profile of compliance and 
related costs over 30 years from the year of compliance for each 
complying facility.\42\ Costs incurred by governments for administering 
the regulation were analyzed over the same time frame. The last year 
for which costs were tallied is 2043. At a 3 percent rate, EPA 
estimated total annualized social costs of $47.3 million for the ``50 
MGD for All Waterbodies'' option, $22.8 million for the ``200 MGD for 
All Waterbodies'' option, and $17.6 million for the ``100 MGD for 
Certain Water bodies'' option. At a 7 percent rate, these values are 
$50.1 million for the 50 MGD option, $24.1 million for the 200 MGD 
option, and $18.3 million for the 100 MGD option. The largest component 
of social cost is the pre-tax cost of regulatory compliance incurred by 
complying facilities; these costs include pilot study costs, one-time 
technology costs of complying with the rule, one-time costs of 
installation downtime, annual operating and maintenance costs, and 
permitting costs (initial permit costs, annual monitoring costs, and 
permit reissuance costs). Social cost also includes implementation 
costs incurred by Federal and State governments. Exhibit VIII-2 
presents the social cost of the proposed options, by type of cost and 
type of facility, using 3 percent and 7 percent discount rates.
---------------------------------------------------------------------------

    \42\ Benefits are tallied and discounted in the same way, 
although the total time profile for recognition of benefits is 
longer than the profile for recognition of costs.

                                     Exhibit VIII-2.--Annualized Social Cost
                                              [In millions, 2003 $]
----------------------------------------------------------------------------------------------------------------
                                                                                                       100 MGD
                                                                       50 MGD all      200 MGD all     certain
                                                                       waterbodies     waterbodies   waterbodies
----------------------------------------------------------------------------------------------------------------
                                                3% Discount Rate
----------------------------------------------------------------------------------------------------------------
Direct Compliance Cost:
    Primary Manufacturing Industries...............................           $42.7           $21.7   $16.7
    Other Industries...............................................             4.1             1.0     0.7
    Electric Generators............................................             0.0             0.0     0.0
                                                                    -----------------

[[Page 68500]]

        Total Direct Compliance Cost...............................            46.8            22.6    17.5
State and Federal Administrative Cost..............................             0.6             0.1     0.2
                                                                    -----------------
    Total Social Cost..............................................            47.3            22.8    17.6
--------------------------------------------------------------------
                                                7% Discount Rate
----------------------------------------------------------------------------------------------------------------
Direct Compliance Cost:
    Primary Manufacturing Industries...............................            45.1            23.1    17.4
    Other Industries...............................................             4.4             0.9     0.7
    Electric Generators............................................             0.0             0.0     0.0
                                                                    -----------------
        Total Direct Compliance Cost...............................            49.5            24.0    18.1
State and Federal Administrative Cost..............................             0.6             0.1     0.2
                                                                    -----------------
    Total Social Cost..............................................            50.1            24.1    18.3
----------------------------------------------------------------------------------------------------------------

    As shown in Exhibit VIII-2, compliance cost in the Manufacturers 
segment accounts for the substantial majority of total social cost and 
direct compliance cost under all three options. No Electric Generators 
would be subject to the national requirements under any of the three 
co-proposed options. On a per facility basis and at a 3 percent 
discount rate, annualized pre-tax costs in the Manufacturers segment 
amount to $349,000 under the ``50 MGD for All Waterbodies'' option, 
$920,000 under the ``200 MGD for All Waterbodies'' option, and $929,000 
under the ``100 MGD for Certain Waterbodies'' option. The corresponding 
values using a 7 percent discount rate are $369,000 under the ``50 MGD 
for All Waterbodies'' option, $974,000 under the ``200 MGD for All 
Waterbodies'' option, and $962,000 under the ``100 MGD for Certain 
Waterbodies'' option. Because the 200 MGD option and the 100 MGD option 
apply national categorical requirements to a smaller number of higher 
flow facilities than the 50 MGD option, they result in a lower total 
national cost but a higher cost per regulated facility. Individual 
facilities that are subject to the requirements of the 200 MGD option 
or the 100 MGD option incur the same compliance costs as under the 50 
MGD option (in which they are also included); however, the average 
costs per regulated facility are higher under the 200 MGD and 100 MGD 
options because only the higher flow, and therefore higher cost, 
facilities incur costs under these options.
    EPA's estimate of Federal and State government costs for 
administering this proposal is comparatively minor in relation to the 
estimated direct cost of regulatory compliance. EPA estimates 
government annual administrative costs of approximately $0.6 million 
(50 MGD option), $0.1 million (200 MGD option), and $0.2 million (100 
MGD option) under both discount rates.
4. Economic Impacts for Manufacturers and Electric Generators
    The economic impact analyses assess how facilities, and the firms 
that own them, are expected to be affected financially by the analyzed 
options. The facility impact analysis starts with compliance cost 
estimates (see section VIII.A.2) and then calculates how these 
compliance costs would affect financial performance and other economic 
conditions.
a. Manufacturers (Primary Manufacturing Industries and Other Industries)
    This section presents EPA's estimated economic impacts on 
Manufacturers for the three co-proposed options. Measures of economic 
impact include facility closures and associated losses in employment, 
financial stress short of closure (``moderate impacts''), and firm-
level impacts. EPA eliminated from the analysis those facilities 
showing materially inadequate financial performance in the baseline, 
that is, in the absence of the rule. EPA judges these facilities, which 
are referred to as baseline closures, to be at substantial risk of 
financial failure regardless of any additional financial burden that 
might result from the proposed Phase III regulation.
    For the remaining facilities, EPA identified a facility as a 
regulatory closure if it would have operated under baseline conditions 
but would fall below an acceptable financial performance level under 
the new regulatory requirements. EPA's analysis of regulatory closures 
is based on the estimated change in facility after-tax cash flow (cash 
flow) as a result of the regulation and specifically examines whether 
the change in cash flow would be sufficient to cause the facility's 
going concern business value to become negative. EPA calculated 
business value using a discounted cash flow framework in which cash 
flow is discounted at an estimated cost of capital to calculate the 
going concern value of the facility. The specific definition of cash 
flow used in these analyses is after-tax free cash flow available to 
all capital--equity and debt. Correspondingly, the cost of capital 
reflects the combined cost, after-tax, of equity and debt capital. For 
its analysis of economic/financial impacts on the Manufacturers 
industry segment, EPA used 7 percent as a real, after-tax cost of capital.
    In these analyses, EPA first calculated the baseline going concern 
value of the facility using its baseline cash flow--i.e., facility cash 
flow before compliance-related outlays. For this calculation, EPA used 
the three-year average of cash flow as reported in each facility's 
survey response and adjusted to constant 2003 dollars. In addition to 
adjusting facility cash flow values for inflation to 2003, EPA adjusted 
facility baseline cash flow to reflect the estimated real change (i.e., 
independent of inflation) in business performance in the manufacturing 
industries from the time of the facility survey, 1996-1998, to the 
present. EPA also estimated an ongoing outlay for replacement of the 
facility's capital equipment and included this as an adjustment to 
baseline cash flow. EPA included an allowance of ongoing capital 
outlays in

[[Page 68501]]

the calculation of cash flow because such outlays for replacement and 
refurbishment of capital equipment occur in the ordinary course of 
business and represent a cash outlay for the business. EPA estimated 
these outlays based on an econometric analysis of actual capital 
outlays over an 11-year period by businesses in the five Manufacturers 
industry segments. This analysis accounted for national economic 
conditions, business conditions in the specific industry segments, and 
financial performance of the individual businesses (see EA, Chapter B3 
for details of this analysis and the details of the cash flow 
calculation). Using this adjusted baseline cash flow, if EPA found the 
facility's estimated going concern value to be negative, then the 
facility was judged a baseline closure--i.e., likely to fail 
financially, independent of incurrence of compliance costs--and removed 
the facility from further consideration in the impact analysis.
    As the second step in the facility impact analysis, EPA adjusted 
the baseline cash flow to reflect the expected financial effects of 
compliance technology installation and operation. For this analysis, 
EPA assumed that none of the facility's compliance costs could be 
passed on to its customers as price and revenue increase--i.e., all 
compliance costs must be absorbed within the facility's cash flow. EPA 
then recalculated the facility's business value using the adjusted 
post-compliance cash flow. If this analysis found that the facility's 
business value would become negative as a result of meeting compliance 
requirements, then EPA judged the facility to be a regulatory closure.
    EPA also identified facilities that would likely incur moderate 
financial impacts, but that are not expected to close, as a result of 
the proposed rule. EPA established thresholds for two measures of 
financial performance and condition--interest coverage ratio (ICR) and 
pre-tax return on assets (PTRA)--and compared the facilities' 
performance before and after compliance under each regulatory option 
with these thresholds. EPA calculated ICR as pre-tax operating cash 
flow--earnings before interest, taxes, and depreciation--divided by 
interest expense. This measure provides insight into a business' 
ability to service its debt on the basis of current, ongoing financial 
performance and to borrow for capital investments. EPA calculated PTRA 
as the ratio of pre-tax operating income--earnings before interest and 
taxes--to assets. This ratio measures the operating performance and 
profitability of a business' assets independent of financial structure 
and tax circumstances. For this analysis, EPA developed industry-
specific thresholds from data compiled by Risk Management Association, 
Inc. (RMA). The threshold values represent the 25th percentile values 
of PTRA and ICR for statements received by RMA for the eight years from 
1994 to 2001 within relevant industries. Thresholds by sector ranged 
from 1.8% to 2.9% for PTRA and from 2.0 to 2.4 for ICR (see EA Chapter 
B3 for additional information). EPA attributed incremental moderate 
impacts to the rule if both financial ratios exceeded threshold values 
in the baseline (i.e., there were no moderate impacts in the baseline), 
but at least one financial ratio fell below the threshold value in the 
post-compliance case.
i. Baseline Closure Analysis
    Exhibit VIII-3 presents projected baseline closures for the 
estimated facilities in the Primary Manufacturing Industries and 
additional known facilities in Other Industries.\43\ From the analysis 
as outlined above, EPA determined that 76 facilities (or 14 percent) of 
the estimated 532 regulated facilities in the five Primary 
Manufacturing Industries are baseline closures. The highest percentages 
of baseline closures occur in the Steel industry sector (43 percent) 
and Aluminum industry sector (33 percent). An additional four 
facilities (or 18 percent) of the 22 known facilities in Other 
Industries are projected to be baseline closures. These facilities were 
excluded from the post-compliance analysis of regulatory impacts.
---------------------------------------------------------------------------

    \43\ The estimated number of Manufacturers considered in the 
impact analysis (554) differs from the number reported in the 
broader analyses (566) because of the exclusion of some sample 
surveys with missing data and the rescaling of the remaining surveys 
to extrapolate national impacts. EPA determined that the survey 
responses of 14 sample facilities lacked certain financial data 
needed for the facility impact analysis while containing sufficient 
data to support estimates of facility counts and compliance costs. 
EPA therefore retained these sample facilities (37 sample weighted 
facilities) in the broader analyses but excluded them from the 
impact analysis. When these sample facilities were excluded from the 
impact analysis, the sample weights for the remaining facilities 
within the affected sample frames were adjusted upwards to account 
for their removal. The difference in the reported facility totals in 
the impact and social cost analyses reflects the removal of these 14 
facilities and the use of adjusted sample weights. The removal of 
specific sample facilities from the analysis universe and 
simultaneous adjustment of sample weights to account for their 
removal yields the same estimate of the total combined population of 
Manufacturers and Electric Generators for the analysis. However, as 
a result of the sample stratification methodology, the estimates of 
the total facility populations for Manufacturers only differ 
slightly between the two sample facility cases. Both values are 
valid statistical estimates of the same, but unknown, value of the 
Manufacturers facility population.

                         Exhibit VIII-3.--Summary of Baseline Closures for Manufacturers
----------------------------------------------------------------------------------------------------------------
                                                                     Number of     Percentage of
                     Sector                        Total number      baseline        baseline      Operating in
                                                   of facilities     closures        closures        baseline
----------------------------------------------------------------------------------------------------------------
Paper...........................................             230              32            13.9             198
Chemicals.......................................             178               4             2.2             173
Petroleum.......................................              36               5            13.9              30
Steel...........................................              68              29            42.6              40
Aluminum........................................              21               7            33.3              14
                                                 -----------------
    Total Facilities in Primary Manufacturing                532              76            14.3             456
     Industries.................................
Additional known facilities in Other Industries.              22               4            18.2              18
                                                 -----------------
    Total Manufacturers.........................             554              80            14.4             474
----------------------------------------------------------------------------------------------------------------

[[Page 68502]]

ii. Number of Facilities Passing the Baseline Closure Analysis and 
Subject to National Categorical Requirements
    As described above, the number of Manufacturers subject to national 
categorical requirements differs according to (1) the options' design 
intake flow (DIF) applicability thresholds, and (2) the type of 
waterbodies to which they would apply. Of the three co-proposed options 
presented here, the ``100 MGD for Certain Waterbodies'' option would 
apply to the smallest number of the facilities that passed the baseline 
closure analysis (``baseline-pass facilities'')--20 facilities, or 18 
facilities in the Primary Manufacturing Industries and two known 
facilities in Other Industries (see Exhibit VIII-4). The ``200 MGD for 
All Waterbodies'' option would apply to 24 baseline-pass facilities, or 
22 facilities in the Primary Manufacturing Industries and two known 
facilities in Other Industries. The ``50 MGD for All Waterbodies'' 
would apply to 133 baseline-pass facilities, or 127 facilities in the 
Primary Manufacturing Industries and 6 known facilities in Other Industries.

           Exhibit VIII-4.--Number of Baseline-Pass Manufacturing Facilities Subject to National Categorical Requirements by Option and Sector
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                  Number of facilities subject to national categorical requirements
                                                                           -----------------------------------------------------------------------------
                                                                  Total      50 MGD all waterbodies    200 MGD all waterbodies       100 MGD certain
                            Sector                              operating  ----------------------------------------------------        waterbodies
                                                               in baseline                                                     -------------------------
                                                                               Number      Percent       Number      Percent       Number      Percent
--------------------------------------------------------------------------------------------------------------------------------------------------------
Paper........................................................          198           37         18.7            3          1.5            0          0.0
Chemicals....................................................          173           52         30.1            5          2.9            7          4.0
Petroleum....................................................           30           13         43.3            3         10.0            5         16.7
Steel........................................................           40           22         55.0            9         22.5            6         15.0
Aluminum.....................................................           14            5         35.7            1          7.1            0          0.0
                                                              --------------
    Total Facilities in Primary Manufacturing Industries.....          456          127         27.9           22          4.8           18          3.9
Additional known facilities in Other Industries..............           18            6         33.3            2         11.1            2         11.1
                                                              --------------
    Total Manufacturers......................................          474          133         28.1           24          5.1           20         4.2
--------------------------------------------------------------------------------------------------------------------------------------------------------
Note: May not sum to totals due to independent rounding.

iii. Post-Compliance Impact Analysis; Summary of Impacts
    Of the 474 Manufacturers potentially subject to regulation after 
baseline closures, EPA estimated that no facilities would close or 
incur employment losses as a result of the three co-proposed options 
considered here. EPA also found that none of the 474 baseline-pass 
facilities would incur a moderate economic impact as a result of the 
three co-proposed options.
    Exhibit VIII-5 summarizes the estimated impacts of the proposed 
rule on Manufacturers by option, including facility impacts and total 
annualized compliance costs on an after-tax basis. The reported costs 
include no compliance costs for facilities assessed as baseline 
closures. The total annualized, after-tax compliance cost reported in 
Exhibit VIII-5 represents the cost actually incurred by complying 
firms, taking into account the reductions in tax liability resulting 
from compliance outlays and assuming no recovery of costs from 
customers through increased prices. The after-tax analysis uses a 
combined Federal/State tax rate, and accounts for facilities' baseline 
tax circumstances. Specifically, tax offsets to compliance costs are 
limited not to exceed facility-level tax payments as reported in 
facility questionnaire responses. The total annualized, after-tax 
compliance cost reported here is the sum of annualized, after-tax costs 
by facility at the year of compliance, using a 7 percent after-tax cost 
of capital. This cost calculation differs in concept from the 
calculation of compliance costs as included in the calculation of the 
total social costs of the regulation. For the social cost calculation, 
which is presented in section VIII.A.2, the year-by-year stream of 
total pre-tax compliance costs for all facilities is discounted to the 
assumed effectiveness date of the 316(b) Phase III final rule--
beginning of year 2007--and then annualized. Two social discount rate 
values, 3 percent and 7 percent, are used in the social cost analysis.

                               Exhibit VIII-5.--Facility Impacts for Manufacturers
----------------------------------------------------------------------------------------------------------------
                                                                                                     100 MGD
                                                                  50 MGD all      200 MGD all        certain
                                                                 waterbodies      waterbodies      waterbodies
----------------------------------------------------------------------------------------------------------------
                                        Primary Manufacturing Industries
----------------------------------------------------------------------------------------------------------------
Number of Facilities Operating in Baseline...................            456              456              456
Number of Facilities Subject to National Requirements........            127               22               18
Percentage of Facilities Subject to National Requirements....             27.9              4.8              3.9
Number of Closures (Severe Impacts)..........................              0                0                0
Percentage of Facilities Closing.............................              0.0              0.0              0.0
Number of Facilities with Moderate Impacts...................              0                0                0
Percentage of Facilities with Moderate Impacts...............              0.0              0.0              0.0
Annualized Compliance Costs (after tax, million $2003).......            $32.8            $13.7            $15.8
--------------------------------------------------------------

[[Page 68503]]

                                 Additional Known Facilities in Other Industries
----------------------------------------------------------------------------------------------------------------
Number of Facilities Operating in Baseline...................             18               18               18
Number of Facilities Subject to National Requirements........              6                2                2
Percentage of Facilities Subject to National Requirements....             33.3             11.1             11.1
Number of Closures (Severe Impacts)..........................              0                0                0
Percentage of Facilities Closing.............................              0.0              0.0              0.0
Number of Facilities with Moderate Impacts...................              0                0                0
Percentage of Facilities with Moderate Impacts...............              0.0              0.0              0.0
Annualized Compliance Costs (after tax, million $2003).......             $5.2             $0.7             $0.6
----------------------------------------------------------------------------------------------------------------

iv. Firm-Level Impact
    In addition to analyzing the impact of the regulation at the 
facility level, EPA also examined the impact of the proposed rule on 
firms that own manufacturing facilities with cooling water intake 
structures. A firm that owns multiple facilities could be adversely 
affected due to the cumulative burden of regulatory requirements over 
these facilities. EPA also used the firm-level analysis to compare 
impacts on small versus large firms, as required by the Regulatory 
Flexibility Act as amended by the Small Business Regulatory Enforcement 
Fairness Act. Section XI.C of this preamble discusses RFA/SBREFA 
issues. For the assessment of firm-level effects, EPA calculated 
annualized after-tax compliance costs as a percentage of firm revenue 
and reports here the estimated number and percentage of affected firms 
incurring compliance costs in three cost-to-revenue ranges: less than 1 
percent; at least 1 percent but less than 3 percent; and 3 percent or 
higher.
    EPA's sample-based analysis of facilities in the Primary 
Manufacturing Industries supports specific estimates of the number of 
facilities expected to be affected by the regulation and the total 
compliance costs expected to be incurred in these facilities. However, 
the sample-based analysis does not support specific estimates of the 
number of firms that own facilities in the Primary Manufacturing 
Industries. In addition, and as a corollary, the sample-based analysis 
does not support specific estimates of the number of regulated 
facilities that may be owned by a single firm, or of the total of 
compliance costs across regulated facilities that may be owned by a 
single firm. For the firm-level analysis, EPA therefore considered two 
approximate bounding cases based on the sample weights developed from 
the facility survey. These cases provide a range of estimates for the 
number of firms incurring compliance costs and the costs incurred by 
any firm owning a regulated facility. The cases are as follows:
    1. Upper bound estimate of number of firms owning facilities that 
face requirements under the regulation; lower bound estimate of total 
compliance costs that a firm may incur. For this case, EPA assumed (1) 
that a firm owns only the regulated sample facility(ies) that it is 
known to own from the sample analysis and (2) that this pattern of 
ownership, observed for sampled facilities and their owning firms, 
extends over the facility population represented by the sample 
facilities. This case minimizes the possibility of multi-facility 
ownership by a single firm and thus maximizes the count of affected 
firms, but also minimizes the potential cost burden to any single firm.
    2. Lower bound estimate of number of firms owning facilities that 
face requirements under the regulation; upper bound estimate of total 
compliance costs that a firm may incur. For this case, EPA inverted the 
prior assumption and assumed that any firm owning a regulated sample 
facility(ies), owns the known sample facility(ies) and all of the 
sample weights associated with the sample facility(ies). This case 
yields an approximate lower bound estimate of the count of affected 
firms, and an approximate upper bound estimate of the potential cost 
burden to any single firm (see EA Chapter B3 for information on the 
analysis of firm-level impacts).
    EPA included the additional known facilities in Other Industries in 
these analyses but since these facilities have no sample weight (i.e., 
they are not modeled to represent facilities other than themselves), 
the upper and lower bound estimates were not applicable to them.
    Exhibit VIII-6 summarizes the results of the firm-level analysis 
for these two analytic cases.

                                Exhibit VIII-6.--Firm-Level After-Tax Annual Compliance Costs as a Percentage of Revenue
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                        No costs          Number and percentage with after tax annual compliance costs/
                                                                 ----------------------                         annual revenue of
                                                                                       -----------------------------------------------------------------
           Number of firms in the analysis             Pot. reg.                            Less than 1%              1-3%               At Least 3%
                                                                    Number    Percent  -----------------------------------------------------------------
                                                                                          Number    Percent     Number    Percent     Number    Percent
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                            Primary Manufacturing Industries
--------------------------------------------------------------------------------------------------------------------------------------------------------
Case 1: Upper bound estimate of number of firms owning facilities that face requirements under the regulation; lower bound estimate of total compliance
 costs that a firm may incur
--------------------------------------------------------------------------------------------------------------------------------------------------------
50 MGD All Waterbodies...............................        313        208         66        105         34          0          0          0          0
200 MGD All Waterbodies..............................        313        292         93         21          7          0          0          0          0
100 MGD Certain Waterbodies..........................        313        293         94         21          7          0          0          0          0
------------------------------------------------------

[[Page 68504]]

Case 2: Lower bound estimate of number of firms owning facilities that face requirements under the regulation; upper bound estimate of total compliance
 costs that a firm may incur
--------------------------------------------------------------------------------------------------------------------------------------------------------
50 MGD All Waterbodies...............................        100         54         54         46         46          0          0          0          0
200 MGD All Waterbodies..............................        100         86         86         14         14          0          0          0          0
100 MGD Certain Waterbodies..........................        100         88         88         12         12          0          0          0          0
------------------------------------------------------
                                                                    Other Industries
--------------------------------------------------------------------------------------------------------------------------------------------------------
50 MGD All Waterbodies...............................         14         10         71          4         29          0          0          0          0
200 MGD All Waterbodies..............................         14         13         93          1          7          0          0          0          0
100 MGD Certain Waterbodies..........................         14         13         93          1          7          0          0          0          0
--------------------------------------------------------------------------------------------------------------------------------------------------------

    As presented in Exhibit VIII-6, EPA estimated that the number of 
firms owning regulated facilities in the Primary Manufacturing 
Industries range from 100 (Case 2 estimate) to 313 (Case 1 estimate), 
depending on the assumed ownership cases outlined above. An additional 
14 firms are known to own facilities in Other Industries. No firms are 
estimated to incur total compliance costs equal to or exceeding 1 
percent of revenue under any of the regulatory options.
b. Electric Generators
    All Electric Generators with a design intake flow of 50 MGD or 
greater were already covered by the final Phase II regulation. As a 
result, no Electric Generators are subject to the national categorical 
requirements of the three co-proposed options.

B. New Offshore Oil and Gas Extraction Facilities

1. Overview of Affected Industry Sectors
    The proposed rule establishes requirements for new facilities that 
would apply to new offshore oil and gas extraction facilities that 
employ a cooling water intake structure (CWIS) and are designed to 
withdraw greater than 2 million gallons per day (MGD) from waters of 
the United States.\44\ Offshore oil and gas extraction facilities 
(``Oil and Gas Facilities'') are facilities primarily engaged in oil 
and gas production and drilling activities. This analysis includes oil 
and gas production platforms/structures and mobile offshore drilling 
units (MODUs). EPA estimates that 21 new oil and gas extraction 
platforms and 103 new MODUs would be subject to the national 
requirements of the proposed option, assuming a 20-year period of 
construction from 2007 (the assumed effective date of the rule) to 
2026. Each newly-constructed facility is assumed to operate for 30 
years, extending the entire analysis period over 49 years (2007 to 
2055). Different methods of discounting over time are used for the 
social cost and impact analyses. Social costs are discounted to 2007, 
the assumed effective date of the rule, and then annualized over 30 
years using 3% and 7% discount rates. For the impact analysis, 
compliance costs are discounted for each individual facility to the 
year of compliance (the year the vessel is launched or the platform/
structure comes on line, which ranges from 2007 to 2026) and then 
summed to produce an aggregate present value of compliance costs. This 
aggregate present value is then annualized over 30 years using 3% and 
7% discount rates.
---------------------------------------------------------------------------

    \44\ See section II.B for a definition of a new offshore oil and 
gas extraction facility for the purposes of this proposal.
---------------------------------------------------------------------------

2. Social Cost for New Offshore Oil and Gas Extraction Facilities
    The total annualized social cost of the proposed option for new Oil 
and Gas facilities is estimated at $3.7 million using a 3 percent 
discount rate, and $3.0 million using a 7 percent discount rate. The 
largest component of social cost is the pre-tax cost of regulatory 
compliance incurred by complying facilities; these costs include one-
time technology costs of complying with the rule, annual operating and 
maintenance costs, and permitting costs (initial permit costs, annual 
monitoring costs, and permit reissuance costs). Social cost also 
includes implementation costs incurred by the Federal government. EPA 
expects that for the most part, the proposed regulation would be 
implemented under general permits, two in the Gulf of Mexico, and one 
in Cook Inlet Alaska.\45\ States are thus not likely to be involved in 
administering the permits for new regulated offshore oil and gas 
facilities because the facilities in the Gulf of Mexico operate in non-
State waters (beyond the 3-mile limit) and Alaska does not have NPDES 
authority. EPA requests comment on its projections about the operating 
locations of new facilities.
---------------------------------------------------------------------------

    \45\ Because individual permits are not issued, costs for pre-
permitting and re-permitting studies are assumed to be shared among 
groups of new facilities expected to be covered by the general 
permits (see DCN 7-4036 for detailed information on how permitting 
costs are assumed to be shared under the general permits).
---------------------------------------------------------------------------

    EPA estimates that direct compliance costs would be $3.2 million 
and $2.7 million, using a 3 percent and 7 percent discount rate, 
respectively. The estimated Federal government cost for administering 
the rule for new facilities is comparatively minor in relation to the 
estimated direct cost of regulatory compliance. Federal administrative 
costs are estimated to be $0.4 million and $0.3 million per year under 
the 3 percent and 7 percent discount rates, respectively.
3. Economic Impacts for New Offshore Oil and Gas Extraction Facilities
    The following two subsections present economic impacts for MODUs 
and production platforms/structures, respectively. Certain aspects of 
the methodology differ between the two segments. Oil and gas production 
operations involve production of a finite resource, which limits the 
potential life of a production platform. Thus, the analysis for 
production platforms/structures must account for the production and 
resulting exhaustion of the finite oil and gas resource. Key 
considerations in the platforms analysis are: (1) When does production

[[Page 68505]]

terminate? and (2) would the year of termination change due to 
regulation? The economic life of a MODU is not limited by such 
considerations and the analysis for MODUs is accordingly simpler. The 
EA and the rulemaking record contain additional data and details on the 
methodology and assumptions used in these analyses.
a. MODUs
    EPA projects that 80 new jackups, 20 new semi-submersibles, and 
three new drill ships will be constructed over the 20 years for which 
new facility additions are analyzed. The economic impact analysis for 
these new MODUs is conducted at two levels: the vessel level and the 
firm level. EPA conducted two vessel-level analyses and one firm-level 
analysis:
    ? The first vessel-level analysis is a closure analysis, 
which assesses changes in vessel cash flow and net income. Because the 
financial condition of new vessels is unknown, EPA used financial 
information from representative existing vessels, collected in EPA's 
316(b) survey of MODUs (DCN 7-0008), to represent the financial 
characteristics of new facilities. The financial information from these 
representative vessels is used for a general assessment of how well 
these vessels would perform financially if costs of the proposed option 
applied. This analysis is used as an alternative assessment of the 
potential for a barrier to entry.
    ? The second vessel-level analysis is a standard barrier-to-
entry analysis for new facilities. This analysis computes the present 
value of estimated initial permitting costs, which are assumed to be 
incurred over five years prior to the incorporation of section 316(b) 
permit requirements in the applicable general permits (see DCN 7-4036) 
and are discounted to the year of compliance (the year the vessel is 
assumed to be launched). The one-time capital costs of compliance 
(assumed to be incurred in the year of compliance) are then added to 
this figure. These summed compliance costs are then compared to the 
baseline construction costs for each type of MODU. Neither recurring 
costs of compliance (e.g., repermitting costs or recurring capital 
costs of CWIS controls) nor recurring baseline costs (e.g., O&M, 
refitting costs) are considered in this analysis. The analysis compares 
baseline start-up costs and incremental start-up costs associated with 
the proposed rule.
    ? The firm-level analysis is a cost-to-revenue test which 
compares the annualized compliance costs for representative new vessels 
to the revenues of firms likely to construct MODUs, assuming each of 
these firms builds a share of the 103 new MODUs expected to be 
constructed over the 20-year construction time frame. This analysis was 
conducted on a pre-tax and after-tax basis.
i. Vessel-Level Closure Analysis
    To estimate potential closures (or more precisely, decisions not to 
proceed with constructing and placing a vessel into service) as a 
result of today's proposal for new MODUs, EPA used two models: (1) A 
net income model, which computes the estimated present value of 
baseline after-tax net income (i.e., without compliance costs) for 
representative MODUs (based on survey data from existing MODUs) over a 
30-year operating period for each new facility,\46\ and (2) an after-
tax cost calculation model, which estimates the present value of after-
tax compliance costs using engineering and permitting cost inputs. 
Comparing the results of these two models shows the potential effect of 
costs on vessel net income.
---------------------------------------------------------------------------

    \46\ Consistent with generally accepted methods of business 
value analysis, EPA would have preferred to use the present value of 
after-tax cash flow instead of net income as the basis for this 
analysis. However, because it could not reliably estimate all of the 
elements of cash flow, the Agency instead used the present value of 
net income for its closure test. In particular, EPA was unable to 
estimate the ongoing capital outlays (apart from those resulting 
from regulatory compliance) that MODUs would need to make as part of 
their ordinary business operations. In performing the analysis in 
this way, the Agency essentially used the facility's reported 
depreciation and amortization--which, being non-cash items, are 
normally excluded from cash flow accounting--as an approximation of 
ongoing capital outlays. How use of reported depreciation and 
amortization, instead of a reliable estimate of capital outlays, 
affects the findings from this analysis cannot be precisely known. 
For some businesses--in particular those with relatively strong 
financial performance--depreciation and amortization may be less 
than ongoing capital outlays; for these businesses, the analysis 
will tend to overstate business value and understate the potential 
effect of compliance outlays on financial performance and business 
value. On the other hand, for some businesses--in particular those 
with relatively weak financial performance--depreciation and 
amortization may exceed ongoing capital outlays; for these 
businesses, the analysis will tend to understate business value and 
overstate the potential effect of compliance outlays on financial 
performance and business value.
---------------------------------------------------------------------------

    EPA estimated after-tax net income for eight MODUs, using data 
provided by surveyed operators of existing MODUs (EPA received economic 
surveys for three semi-submersibles, three jackups, and two drill 
ships). EPA was only able to undertake financial analysis for those 
MODUs with a positive net income for the three years of financial 
information provided in the survey (2000 to 2002). EPA assumed that any 
MODU whose net income is negative over the three years is unlikely to 
be a viable operation in the baseline and cannot be analyzed with 
respect to compliance costs.
    EPA used the net income over the three years of survey data to 
create a moving cycle of net income over the period of analysis. Among 
the years of data collected (2000 to 2002), 2002 was generally a poor 
year of financial condition for the industry as a whole. EPA was thus 
able to represent industry financials in both good and bad years. The 
three-year cycle simulates the effect of volatility in oil and gas 
prices and other business conditions (e.g., rig utilization rates) over 
each facility's 30-year operating period. Future operating periods are 
likely to include major swings in the prices of oil and gas, the 
driving force behind the level of operations, rig pricing, and, thus, 
financial performance of the newly constructed vessels. EPA assumed 
that net income will be flat, on a three-year average basis, over the 
30 years of analysis and thus did not apply any factors to increase or 
decrease net income over the years of analysis. The net income figures 
from the survey, therefore, repeat every three years for 30 years. EPA 
then computed the present value of that stream of net income and 
compared it to the present value of after-tax compliance costs for the 
proposed option.
    EPA used the estimated compliance cost elements--capital, O&M, and 
permitting costs--for each new MODU to calculate the present value of 
the after-tax cost of compliance with today's proposed requirements. 
Each compliance-related cost was accounted for in the year it is 
assumed to be incurred. Tax effects of compliance outlays were based on 
the owner company's marginal tax rate as determined from the firm's 
average taxable earnings over the three years of survey data (converted 
to a mid-year 2003 basis). EPA calculated depreciation for the 
compliance capital outlay using the modified accelerated cost recovery 
system (MACRS) and included it in the pre-tax compliance cost stream. 
The compliance cost stream was then reduced by the amount of avoided 
tax liability, based on the estimated marginal tax rate, to yield the 
after-tax compliance cost stream (for more information on these 
calculations, see DCN 7-4016). The final result of these calculations 
is the present value of after-tax compliance costs.
    The present value of after-tax compliance costs was then subtracted 
from the present value of baseline net income for the vessel. If the 
present value of net income remained positive

[[Page 68506]]

after accounting for compliance costs, EPA assumed that the MODU would 
operate post-compliance. If the present value of net income became 
negative, EPA assumed that the new MODU would not be a financially 
viable project and was counted as a potential ``regulatory closure.''
    The analysis is based on the assumption that costs cannot be passed 
through to customers. Because existing MODUs will not have to meet the 
requirements of the proposal, and new MODUs must compete with these 
existing MODUs, assuming zero cost pass-through provides a realistic 
estimate of potential economic impacts on new MODUs.
    This analysis found that no new MODUs (based on an assumption that 
finances for new MODUs will look like those for existing MODUs) would 
be a regulatory closure as a result of the incremental compliance costs 
associated with the proposed option (detailed results are provided in 
the CBI portion of today's record; DCN 7-4020).
ii.Vessel-Level Barrier-to-Entry Analysis
    The barrier-to-entry analysis compares the present value of 
compliance costs (including the present value of initial permitting 
costs discounted to the compliance year and first-time capital/
installation costs, excluding recurring costs), to the costs of 
constructing a new MODU. If compliance costs comprised a small fraction 
of construction costs, EPA assumed that compliance costs would have no 
effect on the decision to build a new MODU.
    EPA developed incremental compliance costs for new MODUs using 
estimated initial permitting costs and technology cost estimates. The 
initial permitting costs are based on each new MODU's share of regional 
permitting costs (EPA expects that facilities in a particular 
geographic region would collect data from representative facilities in 
that region) and individual administrative start-up and permit 
application costs. The technology costs are based on the weighted 
average cost of installing controls at existing MODUs, by type of MODU, 
for all existing MODUs with technical data. The estimated present value 
of the initial permitting cost stream, plus the first-time capital/
installation costs of compliance costs, sum to $127,000 for semi-
submersibles, $258,000 for jackups, and $247,000 for drill ships. 
According to IADC (May/June, 2003), the cost of new MODUs planned to be 
built in the next few years averages $250 million for semi-submersibles 
and $125 million for jackups. A drill ship completed in 1998 cost 
approximately $275 million (R&B Falcon's Pathfinder). The present value 
of initial permitting costs plus one-time capital/installation 
compliance costs is therefore estimated to range from 0.05 percent to 
0.21 percent of construction costs for the three types of MODU. Because 
total up-front costs represent a very small fraction of total costs of 
construction (and even of contingency costs, which typically range from 
10 percent to 20 percent of capital costs), EPA believes that these 
costs would not have a material effect on decisions to build new MODUs.
iii. Firm-Level Cost-to-Revenue Analysis
    EPA's research showed that firms likeliest to build MODUs with a 
design intake flow of greater than 2 MGD are those that currently own 
such MODUs. EPA identified seven firms owning jackups, semi-
submersibles, or drill ships that would be subject to the proposed 
requirements for new facilities if newly constructed. They also are 
among the largest firms in the industry and are thus likely to be 
involved in new construction. EPA estimates that these seven firms 
would own the 103 new MODUs subject to the proposed national 
requirements for new facilities. To determine the potential impact of 
the proposed option on the seven firms determined likely to build new 
MODUs subject to regulation, EPA used a cost-to-revenue test, which 
compares the annualized pre-tax and after-tax costs of compliance 
(calculated for representative new MODUs), with 2002 revenues reported 
by these firms. Because nearly all of the firms (other than foreign-
owned) are publicly owned, EPA relied on revenue data compiled from 
corporate 10K reports (see Chapter C2 of the EA). EPA then assigned a 
number of MODUs potentially subject to regulation to each of the firms 
and used the average per-MODU compliance costs multiplied by the number 
of these MODUs to calculate the total compliance costs that might be 
faced by these firms.
    Estimated total annual pre-tax compliance costs are approximately 
$15,000 for a semi-submersible, $33,000 for a jackup, and $37,000 for a 
drill ship. Estimated after-tax costs are approximately $10,000, 
$21,000, and $24,000, respectively, based on a 35 percent marginal 
corporate tax rate assumption. These annualized costs are very small 
compared to the revenues a MODU might receive for drilling even one 
exploratory well in deepwater, which could approach $25 to $30 million 
(DCN 7-4017). They are also small compared to the typical day rates 
(daily charges) paid to MODUs while drilling wells. These rates can 
range from $150,000 to $250,000 per day (DCN 7-4042). Five firms are 
assumed to build 12 jackups or semi-submersibles over the time frame of 
the analysis (approximately one MODU every other year). The two 
additional firms, GlobalSantaFe and Transocean, are the dominant firms 
in the industry. These two firms are each assumed to build 20 jackup or 
semi-submersibles, plus one drill ship and two drill ships, 
respectively, over the time frame of the analysis for a total of 21 or 
22 MODUs in total. EPA used the higher cost of a jackup rig to 
represent the cost of compliance for both jackups and semi-
submersibles. For simplicity, and to be conservative, EPA assumed that 
the annualized costs of compliance for all MODUs constructed over the 
period of analysis by each firm are incurred in one year for comparison 
to one year's revenues.
    Using these assumptions, EPA estimates that the annualized pre-tax 
costs per firm range from $0.4 to $0.7 million, and the after-tax costs 
range from $0.3 to $0.5 million. The pre-tax cost-to-revenue ratio 
ranges from 0.03 percent to 0.06 percent, while the after-tax ratios 
range from 0.02 percent to 0.04 percent. Given that the highest 
estimated ratio is 0.06 percent, EPA concludes that firm-level impacts 
would not pose a barrier to entry.
b. Oil and Gas Production Platforms
    EPA projects that 20 deepwater platforms and one Alaska platform 
will be constructed over the 20 years over which new facility additions 
are analyzed. The economic impact analysis for these new platforms is 
conducted at two levels: the platform level and the firm level. EPA 
conducted two platform-level analyses and one firm-level analysis:
    ? The first platform-level analysis assesses the potential 
effects of compliance costs on platform operation. Two effects of the 
proposed option are considered: (1) A reduction in the expected 
economic value of the platform, driven by all costs of compliance, 
which could prevent oil and gas resources from being brought into 
production, and (2) earlier production shut-in, driven by the increase 
in O&M costs. The baseline operating and financial profile for this 
analysis is based on data from existing platforms whose cooling water 
intake rates would cause them to be subject to the proposed rule if 
they were being newly constructed after rule promulgation. These 
existing platforms serve as a baseline model of the

[[Page 68507]]

operating and financial conditions of new platforms that would be 
regulated under the proposal. Estimated compliance costs are added to 
the baseline cost profile in the analysis of compliance costs on 
platform operations.
    ? The second platform-level analysis is a barrier-to-entry 
analysis for new facilities. This analysis compares the present value 
of estimated initial permitting costs plus the one-time capital costs 
of compliance (excluding any recurring costs) to the construction costs 
for each type of platform.
    ? The firm-level analysis is a cost-to-revenue test, which 
compares the annualized compliance costs for representative new 
platforms to the revenues of firms likely to construct new platforms/
structures. This analysis assumes that each firm likely to build a 
deepwater platform/structure subject to regulation would bring four 
platforms/structures on line over the time frame of the analysis; and 
that only one firm will build an Alaska platform during the analysis 
period. For simplicity and to be conservative, firms assumed to bring 
four deepwater structures on line are assigned the annualized costs of 
compliance for four platforms in one year for comparison against one 
year's revenues. This analysis was conducted on a pre-tax and after-tax 
basis.
i. Platform-Level Production/Shut-In Analysis
    Compliance costs resulting from the proposed option may affect a 
platform's financial performance and related operating decisions in two 
ways. First, increased costs from regulatory compliance will reduce the 
expected economic value of an oil and gas production project, and may 
prevent an otherwise financially viable project from being undertaken. 
Second, even if a project overall remains financially viable, increased 
operating costs may lead to an earlier production shut-in than would 
occur in the baseline. Details of the analysis of these effects are 
provided below.
    For the analysis of these effects, EPA constructed a general 
platform analysis model, which simulates the operations and economics 
of oil and gas development and production. The platform model analyzes 
production over a period extending as long as 30 years. Pre-tax costs 
(including costs incurred in pre-production years, O&M, monitoring 
costs, and repermitting costs) are input into the model in the year in 
which they occur, until the model shows the platform is uneconomical to 
operate. To determine the shut-in year, projected net revenue is 
compared to operating costs in each production year. Net revenue is 
based on an assumed price of oil, current and projected production of 
oil and gas, well production decline rates, and severance and royalty 
rates. Operating costs are based on a calculated cost per barrel of oil 
equivalent (BOE) produced. The model simulates operations for the 
lesser of 30 years or to the year when operating costs exceed 
production revenue, at which point the operator is assumed to terminate 
production. The model calculates the lifetime of the project, total 
production, and the net present value of the operation (net income of 
the operation over the life of the project in terms of today's 
dollars). A comparison of the baseline model outputs to the post-
compliance model outputs yields any losses of production and project 
lifetimes and the net present value of the operation. If the net 
present value of the operation is positive in the baseline but negative 
post-compliance, the project is considered nonviable post-compliance. 
It is assumed the platform would not be built.
    The model uses as baseline data, financial information from 
representative existing platforms, collected in EPA's 316(b) survey of 
production platforms (DCN 7-0008) to represent the financial 
characteristics of future platforms that would be subject to this 
proposed regulation. EPA received an economic survey from only one 
deepwater platform with cooling water intake structure flows meeting 
the proposed regulatory criteria. EPA used data from this survey and 
from other sources of publicly available information, such as the 
Minerals Management Service, to develop a model new deepwater oil and 
gas production platform. EPA also received a survey from a platform in 
Alaska but did not include it in the analysis because the surveyed 
platform is a very old structure and at the end of its productive life. 
It is likely that it would not be representative of new platforms being 
built after the Phase III rule is finalized. The Alaska platform is 
therefore analyzed only in the barrier to entry analysis.

Analysis of Project Viability

    As noted above, any increase in costs, whether operating, capital, 
or permitting, will reduce the expected economic value of an oil and 
gas project, as represented by the present value of project net income, 
and may cause an otherwise economic oil and gas production project to 
never be undertaken. In this case, the entire economic value of the 
project and its otherwise recoverable oil and gas production are 
assumed to be lost (note: this loss need not be permanent but may only 
be delayed until higher product prices, or reduced development and 
production costs allow the project to become financially viable). For 
this potential impact, EPA analyzed whether the reduction in value from 
all regulatory compliance outlays would be sufficient to cause the 
expected discounted net income of an otherwise economically viable oil 
and gas production project to be negative--at the outset. In this case, 
the operator is assumed not to proceed with development and production. 
If the platform has a positive net present value under baseline 
conditions but a negative net present value in the post-compliance 
scenario, EPA notes an impact on the platform and estimates the lost 
production resulting from the costs of regulatory compliance.

Analysis of Production Shut-In Effects

    Although a project overall remains financially viable, the 
increased operating costs from regulatory compliance may lead to an 
earlier production shut-in than would occur in the baseline. Shut-in 
refers to lost production from non-production of producible reserves 
for reasons such as tests, repairs, or to await construction of 
gathering lines. Apart from the financial impact, an earlier shut-in 
will also lead to reduced production of otherwise economically 
recoverable oil and gas. For this analysis, projected net revenue is 
compared to operating costs at each year for the model project.\47\ Net 
revenue (after subtracting royalties and severance, which are payments 
to the lease owner and a State, if relevant) is based on an assumed 
price of oil, current and projected production of oil and gas, well 
production decline rates, and severance and royalty rates. Operating 
costs are based on a calculated cost per barrel of oil equivalent (BOE) 
produced. The model simulates operations for the lesser of 30 years or 
to the year when operating costs exceed production revenue, at which 
point the operator is assumed to terminate production. A comparison of 
total production and total project lifetime in the baseline vs. post-
compliance shows any differences in these variables following the 
imposition of compliance costs.
---------------------------------------------------------------------------

    \47\ Following engineering review of surveyed deepwater 
platforms/structures, only one was determined to have a total design 
CWIS intake flow rate meeting the proposed 316(b) thresholds for 
regulation of oil and gas facilities, had the structure been newly 
constructed, so only one model of deepwater structures was developed.

---------------------------------------------------------------------------

[[Page 68508]]

    This analysis found no impacts on deepwater oil and gas development 
or production as a result of the incremental compliance costs 
associated with the proposed option for the one platform that was 
analyzed. Impacts on net present value were very small. (Detailed 
results are included in the CBI portion of today's record; DCN 7-4038.)
ii. Platform-Level Barrier-to-Entry Analysis
    The barrier-to-entry analysis compares the present value of the 
initial permitting cost stream (discounted to the year of compliance) 
plus one-time capital/installation costs to the costs of constructing a 
new platform. If compliance costs comprise a small fraction of 
construction costs, EPA assumes that compliance costs would not have an 
effect on the decision to build a new platform.
    The estimated total present values of incremental compliance costs 
are $291,000 for deepwater projects and $685,000 for Alaska projects. 
Costs for constructing new deepwater platforms are estimated to range 
from $114 million to $2.3 billion (see EA for the Synthetic Drilling 
Fluid Effluent Limitations Guidelines in the rulemaking record, DCN 7-
4017). For Alaska, EPA used a value of $120 million (DCN 7-4028). The 
ratio of incremental compliance costs to current total construction 
costs therefore ranges from 0.01 percent to 0.3 percent for deepwater 
projects and 0.6 percent for an Alaska project. Because this represents 
a small fraction of total construction costs (and even of contingency 
costs), EPA believes that these costs would not have a material effect 
on decisions to build new platforms.
iii. Firm-Level Cost-to-Revenue Analysis
    To determine the potential impact of the proposed option on firms, 
EPA used a cost-to-revenue test, which compares the annualized pre-tax 
and after-tax costs of compliance (calculated for a representative new 
platform times the maximum number of platforms assumed built by each 
firm in any one year), with 2002 revenues reported by all firms 
determined likely to be affected by this regulation. The firms that are 
considered affected are (1) those identified as currently having 
existing deepwater platforms or structures that would be subject to 
regulation if they were newly constructed and (2) the likeliest type of 
firm to build a new Alaska platform during the time frame of the 
analysis. EPA assumed each of the five firms operating in the deepwater 
Gulf would bring on-line four platforms during the period of analysis 
(for a total of 20 platforms). For simplicity and to be conservative, 
EPA assumes the four platforms come on line in one year for comparison 
with one year's revenues at each firm. One small firm is assumed to 
build the one Alaska platform over the period of analysis, and the 
annualized compliance cost is also compared to one year's revenues at 
that firm.
    Using these assumptions, EPA estimates that the annualized pre-tax 
costs per firm are about $0.3 million, and the after-tax costs are 
about $0.2 million. The pre-tax cost-to-revenue ratio ranges from 
< 0.001 percent to 0.01 percent, while the after-tax ratios range from 
< 0.001 percent to 0.007 percent. Given that the highest estimated ratio 
is 0.01 percent, EPA concludes that firm-level impacts would not pose a 
barrier to entry.
c. Total Facility Compliance Costs and Impacts for All New Offshore Oil 
and Gas Extraction Facilities
    Exhibit VIII-7 summarizes the total facility compliance costs and 
impacts associated with the proposed option for Phase III new offshore 
oil and gas extraction facilities. Annualized after-tax costs total 
$1.8 million per year for MODUs and $1.2 million per year for 
platforms, or a total of $3.1 million per year for all affected new oil 
and gas operations estimated to be constructed over the period of the 
analysis (using a 7 percent discount rate).\48\
---------------------------------------------------------------------------

    \48\ Costs are incurred assuming 20 years of new facility 
construction, with each facility incurring costs over a 30-year 
operating period, discounted to the year the facility is launched or 
comes on-line. The present value of private after-tax costs is less 
than the previously described present value of social costs, which 
are based on pre-tax costs, because of differences in the 
discounting for private costs and social costs. Private costs are 
discounted, for each analysis, only to the first year of compliance. 
In contrast, for the social cost calculation, all costs are 
discounted to the beginning of 2007, regardless of when new 
facilities come into operations. Because new facilities are 
scheduled to begin operation for a 20 year period following rule 
promulgation, the total effect of discounting is much greater for 
the present value of social cost calculation than for the private 
cost calculation. As a result, the present value of social costs, 
even though based on pre-tax costs, is less than the present value 
of private, after-tax cost.

              Exhibit VIII-7.--Summary of Private Costs and Impacts for New Oil and Gas Facilities
----------------------------------------------------------------------------------------------------------------
                                                                    Annualized
                                                                  private after-
                                                   Number of new  tax compliance     Facility
              Type of O&G facility                  facilities      costs  (in        impacts      Firm impacts
                                                                  millions, 2003
                                                                        $)
----------------------------------------------------------------------------------------------------------------
MODUs...........................................             103            $1.8               0               0
Platforms.......................................              21             1.2               0               0
                                                 -----------------
    Total.......................................             124             3.1               0              0
----------------------------------------------------------------------------------------------------------------
Note: Component values may not sum to the reported total due to independent rounding.

C. Summary of Total Social Costs and Impacts

    As discussed earlier, EPA is proposing national categorical 
requirements for existing Phase III facilities, as defined by one of 
the three co-proposed flow-threshold-based options, and is proposing 
requirements similar to certain provisions of the rule for new offshore 
oil and gas extraction facilities. EPA estimated a total annualized 
social cost for the ``50 MGD for All Waterbodies'' option for existing 
facilities and the proposed option for new oil and gas extraction 
facilities of $51.0 million at a 3 percent discount rate, and $53.1 
million, at a 7 percent discount rate. EPA estimates that 260 
facilities would be subject to national requirements and that none of 
these facilities would experience adverse impacts. Exhibit VIII-8 
summarizes these findings.

[[Page 68509]]

  Exhibit VIII-8.--Summary of Economic Analysis: ``50 MGD for All Waterbodies'' Option for Existing Facilities
                                Plus New Offshore Oil and Gas Facilities > 2 MGD
----------------------------------------------------------------------------------------------------------------
                                                    Annualized social cost  (in      Number of
                                                         millions, 2003 $)          facilities       Number of
                                                 --------------------------------   subject to      facilities
                                                    3% Discount     7% Discount      national      with impacts*
                                                       rate            rate        requirements
----------------------------------------------------------------------------------------------------------------
Direct Compliance Cost:
    Manufacturing Industries....................           $42.7           $45.1             127               0
    Other Industries............................             4.1             4.4               9               0
    Electric Generators.........................             N/A             N/A             N/A             N/A
    New O&G Facilities..........................             3.2             2.7             124               0
                                                 -----------------
        Total...................................            50.0            52.2             260               0
State and Federal Administrative Cost...........             1.0             0.9  ..............  ..............
                                                 -----------------
    Total Social Cost...........................            51.0            53.1  ..............  ..............
----------------------------------------------------------------------------------------------------------------
 * The impact measures for existing Manufacturers are facility closure and moderate financial impact (see also
  section VIII.A.3.a). The two impact measures for new Oil and Gas facilities are facility closures and barrier
  to entry (see also section VIII.B.3). Numbers may not add up to totals due to independent rounding.

    EPA estimated a total annualized social cost for the ``200 MGD for 
All Waterbodies'' option for existing facilities and the proposed 
option for new oil and gas extraction facilities of $26.4 million at a 
3 percent discount rate, and $27.2 million, at a 7 percent discount 
rate. EPA estimates that 149 facilities would be subject to national 
requirements and that none of these facilities would experience adverse 
impacts. Exhibit VIII-9 summarizes these findings.

  Exhibit VIII-9.--Summary of Economic Analysis: ``200 MGD for All Waterbodies'' Option for Existing Facilities
                               Plus New Offshore Oil and Gas Extraction Facilities
----------------------------------------------------------------------------------------------------------------
                                                    Annualized social cost  (in      Number of
                                                         millions, 2003 $)          facilities       Number of
                                                 --------------------------------   subject to      facilities
                                                    3% Discount     7% Discount      national      with impacts*
                                                       rate            rate        requirements
----------------------------------------------------------------------------------------------------------------
Direct Compliance Cost:
    Manufacturing Industries....................           $21.7           $23.1              23               0
    Other Industries............................             1.0             0.9               2               0
    Electric Generators.........................             N/A             N/A             N/A             N/A
    New O&G Facilities..........................             3.2             2.7             124               0
                                                 -----------------
        Total...................................            25.9            26.7             149               0
State and Federal Administrative Cost...........             0.5             0.4  ..............  ..............
                                                 -----------------
    Total Social Cost...........................            26.4            27.2  ..............  ..............
----------------------------------------------------------------------------------------------------------------
* The impact measures for existing Manufacturers are facility closure and moderate financial impact (see also
  section VIII.A.3.a). The two impact measures for new Oil and Gas facilities are facility closures and barrier
  to entry (see also section VIII.B.3). Numbers may not add up to totals due to independent rounding.

    EPA estimated a total annualized social cost for the ``100 MGD for 
Certain Waterbodies'' option for existing facilities and the proposed 
option for new oil and gas extraction facilities of $21.3 million at 
both a 3 percent and 7 percent discount rate. EPA estimates that 143 
facilities would be subject to national requirements and that none of 
these facilities would experience adverse impacts. Exhibit VIII-10 
summarizes these findings.

     Exhibit VIII-10.--Summary of Economic Analysis: ``100 MGD for Certain Waterbodies'' Option for Existing
                         Facilities Plus New Offshore Oil and Gas Extraction Facilities
----------------------------------------------------------------------------------------------------------------
                                                    Annualized social cost  (in      Number of
                                                         millions, 2003 $)          facilities       Number of
                                                 --------------------------------   subject to      facilities
                                                    3% Discount     7% Discount      national      with impacts*
                                                       rate            rate        requirements
----------------------------------------------------------------------------------------------------------------
Direct Compliance Cost:
    Manufacturing Industries....................           $16.7           $17.4              17               0
    Other Industries............................             0.7             0.7               2               0
    Electric Generators.........................             N/A             N/A             N/A             N/A
    New O&G Facilities..........................             3.2             2.7             124               0
                                                 -----------------

[[Page 68510]]

        Total...................................            20.7            20.8             143               0
State and Federal Administrative Cost...........             0.6             0.5  ..............  ..............
                                                 -----------------
    Total Social Cost...........................            21.3            21.3  ..............  ..............
----------------------------------------------------------------------------------------------------------------
* The impact measures for existing Manufacturers are facility closure and moderate financial impact (see also
  section VIII.A.3.a). The two impact measures for new Oil and Gas facilities are facility closures and barrier
  to entry (see also section VIII.B.3). Numbers may not add up to totals due to independent rounding.

IX. Benefits Analysis

A. Introduction

    This section presents EPA's estimates of the national economic 
benefits of the three co-proposed regulatory options for the section 
316(b) regulation for Phase III existing facilities: The ``50 MGD for 
All Waterbodies'' option, the ``200 MGD for All Waterbodies'' option, 
and the ``100 MGD for Certain Waterbodies'' option. The benefits occur 
due to the reduction in impingement mortality and entrainment at 
cooling water intake structures affected by this rulemaking (see 
section II for a description of the facilities to which this rulemaking 
potentially applies). By reducing impingement mortality and 
entrainment, the co-proposed options would increase the number of fish, 
shellfish, and other aquatic life in local aquatic ecosystems. This, in 
turn, will directly and indirectly generate use benefits such as those 
associated with recreational and commercial fishing. Other types of 
benefits that are independent of any current or anticipated uses of the 
resource could also be realized; these are known as non-use values. 
Section IX.D provides an overview of types and sources of benefits 
anticipated, how these benefits were estimated, and what level of 
benefits have been estimated for each of the three co-proposed options. 
For a comparison of social benefits and total social costs, refer to 
Section X.
    To estimate the economic benefits of reducing impingement mortality 
and entrainment at cooling water intake structures, all the beneficial 
outcomes need to be identified and, where possible, quantified and 
assigned appropriate monetary values. Estimating economic benefits can 
be challenging because of the many steps of analysis that are necessary 
to link a reduction in impingement mortality and entrainment to changes 
in impacted fisheries and other aspects of relevant aquatic ecosystems, 
and then to link these ecosystem changes to the resulting changes in 
quantities and values for the associated environmental goods and 
services that ultimately are linked to human welfare. The methodologies 
used in the estimation of benefits of the proposed regulatory options 
are largely built upon those used for estimating benefits of the final 
rule for Phase II facilities (see 69 FR 41576). The Regional Benefits 
Assessment for the Proposed Section 316(b) Rule for Phase III 
Facilities (see DCN 7-0003), hereafter known as the Regional Analysis 
Document, provides EPA's analyses for the benefit assessment for the 
proposed options.
    The benefit estimates for this rule are derived from a series of 
regional studies for a range of waterbody types throughout the U.S. 
Section IX.B provides detail on the regional study design. Sections 
IX.C and IX.D describe the methods EPA used to estimate impingement 
mortality and entrainment impacts at potentially regulated existing 
facilities and to derive an economic value of such losses. National 
benefits were estimated using a set of statistical weights for each 
potentially regulated facility. The weights were developed as part of 
EPA's design of the survey of the industries.
    The benefit estimates presented in the following sections reflect 
changes in impingement mortality and entrainment reductions at existing 
facilities only. EPA was unable to assess benefits of reducing 
impingement and entrainment at new offshore oil and gas extraction 
facilities due to significant data gaps at the time of proposal. 
Therefore, the benefits estimates presented in this section should be 
compared only to the cost estimates for existing Phase III facilities. 
EPA solicits submission of data on impingement mortality and 
entrainment impacts at offshore oil and gas extraction facilities.

B. Study Design and Methods

    EPA's evaluation of impingement mortality and entrainment data had 
four main objectives: (1) To develop a national estimate of the 
magnitude of impingement and entrainment at potentially regulated 
facilities; (2) to standardize impingement and entrainment rates using 
common biological metrics so that rates could be compared across 
species, years, facilities, and geographical regions; (3) to estimate 
changes in these metrics as a result of projected reductions in 
impingement and entrainment under the proposed rule options; and (4) to 
obtain data that can be used to estimate the national economic benefits 
of reduced impingement and entrainment.
    Harvested species were the main focus of EPA's analysis, primarily 
because of the availability of economic methods for valuing these 
species. EPA's approach to estimating changes in harvest assumed that 
impingement and entrainment losses result in a reduction in the number 
of harvestable adults in the years following the time that individual 
fish are killed by impingement and entrainment and that future 
reductions in impingement and entrainment will lead to future increases 
in fish harvest. This approach only estimates the incremental yield 
that is foregone because of the number of deaths due to impingement and 
entrainment and is not intended to provide an estimate of absolute 
population levels. EPA intends to investigate the feasibility of 
applying a population modeling approach to estimate expected changes in 
harvest levels and fish population sizes. Such an approach would use 
available data and life-stage specific estimates of natural mortality, 
impingement and entrainment mortality, and fishing mortality, plus an 
explicit function describing density-dependent reproductive success to 
attempt to estimate long-term changes in average

[[Page 68511]]

harvest levels and stock sizes. A population model could serve as a 
supplement or as an alternative to the current modeling approach based 
on age one equivalent losses. EPA invites comment on ways that it might 
develop a population model to support an estimate of the national 
benefits of this rulemaking.
1. Extrapolation of Impingement and Entrainment Rates
    To obtain a national estimate of losses at all potentially 
regulated facilities, it was necessary to extrapolate impingement and 
entrainment rates from facilities with data (model facilities) to 
facilities without data. Extrapolation of impingement and entrainment 
rates was necessary because not all potentially regulated facilities 
within a given region have conducted impingement and entrainment 
studies. Model facilities included both Phase II facilities and 
potentially regulated Phase III facilities,\49\ based on the assumption 
that impingement and entrainment rates at Phase II and Phase III 
facilities are similar after normalization by intake flow. Phase II 
facilities were included to make use of the largest possible data set 
and to accommodate the lack of impingement and entrainment data from 
potentially regulated Phase III facilities in some regions. Impingement 
and entrainment data from 72 Phase II facilities and 16 potentially 
regulated Phase III facilities were evaluated.
---------------------------------------------------------------------------

    \49\ ``Potentially regulated Phase III facilities'' refers to 
all existing facilities with design intake flows greater than 2 MGD, 
not regulated in the Phase II rule.
---------------------------------------------------------------------------

    Impingement and entrainment data were extrapolated on the basis of 
operational intake flow in millions of gallons per day (MGD), where MGD 
is the average operational flow over the period 1996-1998 as reported 
by facilities in response to EPA's survey of the industry. Operational 
flow at each facility was rescaled using factors reflecting the 
relative effectiveness of currently in-place technologies for reducing 
impingement and entrainment. The extrapolation procedure is described 
in Chapter A1 of Part A of the Regional Analysis Document. While there 
may be variations from these estimates in the actual losses (and 
benefits) per MGD across individual facilities, EPA believes that this 
method of extrapolation is a reasonable basis for developing an 
estimate of national-level benefits.
2. Study Regions and Facilities
    EPA's analysis examined cooling water intake structure impacts and 
regulatory benefits at the regional scale, and then combined regional 
results to develop national estimates. The Agency evaluated the 
benefits of the proposed regulatory options in six study regions based 
on the locations of potentially regulated Phase III facilities and 
similarities in the affected ecosystems, aquatic species present, and 
characteristics of commercial and recreational fishing activities 
within each region. The four coastal regions (California, North 
Atlantic, Mid-Atlantic, and Gulf of Mexico) correspond to those of the 
National Oceanographic and Atmospheric Association (NOAA) Fisheries 
agency (formerly the National Marine Fisheries Service). The Great 
Lakes region includes all potentially regulated Phase III facilities 
that withdraw water from Lakes Ontario, Erie, Michigan, Huron, and 
Superior, or are located on a waterway with open fish passage to a 
Great Lake and within 30 miles of the lake. The Inland region includes 
the remaining facilities that withdraw water from freshwater lakes, 
rivers, and reservoirs. Exhibit IX-1 indicates the number of 
potentially regulated Phase III facilities in each study region. The 
exhibit also shows the number of facilities subject to national 
technology requirements under each of the co-proposed regulatory options.

                               Exhibit IX-1.--Phase III Facilities in Each Region
----------------------------------------------------------------------------------------------------------------
                                                     Number of       Number of facilities subject to national
                                                    potentially       technology requirements under proposed
                                                     regulated           regulatory options \b\ (weighted)
                     Region                       existing phase -----------------------------------------------
                                                        III                                           100 MGD
                                                  facilities \a\    50 MGD all      200 MGD all       certain
                                                     (weighted)     waterbodies     waterbodies     waterbodies
----------------------------------------------------------------------------------------------------------------
California......................................               9               1               0               0
North Atlantic..................................               5               4               1               3
Mid-Atlantic....................................              13               3               2               2
South Atlantic..................................               4               0               0               0
Gulf of Mexico..................................              11               7               2               7
Great Lakes.....................................              68              19               5               6
Inland..........................................             493              69              12               0
                                                 -----------------
    Total, Study Regions........................             599             103              22              18
                                                 -----------------
    National total \c\..........................             603             103              22             18
----------------------------------------------------------------------------------------------------------------
\a\ Potentially regulated existing Phase III facilities include electric generators with CWIS that withdraw more
  than 2 MGD but less than 50 MGD and manufacturers with CWIS that withdraw more than 2 MGD, that use at least
  25% of the water for cooling purposes.
\b\ Numbers of facilities reflect only those that are subject to technology requirements; those facilities that
  only have permitting costs are excluded.
\c\ Eighty potentially regulated facilities estimated to close under the baseline scenario are excluded from
  this analysis.

3. Species Groups
    Life history data are very limited for many of the species that are 
impinged and entrained, and as a result, there are many data gaps for 
individual species. To overcome this limitation in its national benefit 
analysis, EPA used available life history data to construct 
representative life histories for groups of closely related species. 
Aggregation of species into groups of similar species with a common 
life history type facilitated parameterization of the fisheries models 
used by EPA to evaluate facility impingement and entrainment monitoring 
data. Groups were based on family groups and groups used by NOAA 
Fisheries for landings

[[Page 68512]]

data. For example, bay goby, blackeye goby, yellowfin goby, and other 
gobies were grouped together as ``gobies.'' An exception was made for 
species of exceptionally high commercial or recreational value (e.g., 
striped bass), which were evaluated as single species.

C. Impingement and Entrainment

    EPA's analysis is based on facility-provided biological monitoring 
data. As discussed in Chapter A2 of Part A of the Regional Analysis 
Document, there are several types of uncertainty associated with these 
data. Major sources of uncertainty are the imperfect precision and 
accuracy of impingement and entrainment data reported by facilities and 
of growth and mortality rates obtained from the scientific literature. 
This results from unavoidable sampling and measurement errors. While 
these uncertainties may lead to imprecision in impingement and 
entrainment estimates, EPA found no evidence of statistical bias. Given 
the goal of its benefit analysis, EPA believes that the data available 
from facility studies are sufficiently robust for developing estimates 
of the relative magnitude of impingement and entrainment nationwide.
    Using standard fishery modeling techniques,\50\ EPA constructed 
models that combined facility-derived impingement and entrainment 
counts with relevant life history data to derive estimates of (1) age-
one equivalent losses (the number of individuals of different ages 
impinged and entrained by facility intakes expressed as an equivalent 
number of age-one fish), and (2) foregone fishery yield (pounds of 
commercial harvest and numbers of recreational fish and shellfish that 
are not harvested due to impingement and entrainment). In addition to 
direct losses of harvested species, estimates of foregone fishery yield 
include the yield of harvested species that is lost due to losses of 
forage species, which provide food for harvested species. Details of 
the methods used to calculate these metrics are provided in Chapter A1 
of Part A of the Regional Analysis Document. For all analyses, EPA used 
the impingement and entrainment estimates provided by the facility and 
assumed 100 percent entrainment mortality based on the analysis of 
entrainment survival studies presented in Chapter A7 of Part A of the 
Regional Analysis Document. If there is some entrainment survival, this 
last assumption may lead to some overestimate of baseline entrainment 
losses.
---------------------------------------------------------------------------

    \50\ Ricker, W.E. 1975. Computation and interpretation of 
biological statistics of fish populations. Fisheries Research Board 
of Canada, Bulletin 191; Hilbourn, R. and C.J. Walters. 1992. 
Quantitative Fisheries Stock Assessment, Choice, Dynamics and 
Uncertainty. Chapman and Hall, London and New York; Quinn, T.J., II. 
and R.B. Deriso. 1999. Quantitative Fish Dynamics. Oxford University 
Press, Oxford and New York; Dixon, D.A. 1999. Catalog of Assessment 
Methods for Evaluating the Effects of Power Plant Operations on 
Aquatic Communities. Final Report. Report number TR-112013.
---------------------------------------------------------------------------

1. Summary of Current Annual Impingement and Entrainment by Region
    Exhibit IX-2 presents EPA's estimates of current annual impingement 
and entrainment (I&E) in the study regions.

                                          Exhibit IX-2.--Current Annual Impingement and Entrainment, by Region
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                    Impingement                     Entrainment                     Total I & E
                                                         -----------------------------------------------------------------------------------------------
                         Region                                              Foregone                        Foregone                        Foregone
                                                               Age-1       fishery yield       Age-1       fishery yield       Age-1       fishery yield
                                                            equivalents        (lbs)        equivalents        (lbs)        equivalents        (lbs)
--------------------------------------------------------------------------------------------------------------------------------------------------------
California..............................................          21,000             701       1,290,000          95,100       1,310,000          95,800
North Atlantic..........................................          20,100             141       2,320,000          44,800       2,340,000          45,000
Mid-Atlantic............................................       3,890,000         540,000      19,400,000         381,000      23,200,000         920,000
South Atlantic..........................................         423,000          49,100       1,090,000          73,700       1,520,000         123,000
Gulf of Mexico..........................................       6,140,000         623,000       6,580,000       1,370,000      12,700,000       1,990,000
Great Lakes.............................................      31,800,000         413,000       2,570,000          76,400      34,400,000         489,000
Inland..................................................      28,600,000         232,000      15,700,000         263,000      44,200,000         495,000
                                                         -----------------
    National total a....................................      70,900,000       1,860,000      48,900,000       2,300,000     120,000,000       4,160,000
--------------------------------------------------------------------------------------------------------------------------------------------------------

    The estimates in Exhibit IX-2 make use of data from available 
impingement and entrainment studies conducted at both Phase II and 
Phase III facilities. Using data solely from the limited number of 
Phase III studies available (4 studies for the Great Lakes region and 
11 studies for the Inland region), estimates of loss of age-1 
equivalents to impingement and entrainment are 5,160,000 at Great Lakes 
facilities and 14,700,000 at Inland facilities. Estimates of foregone 
fishery yield are 16,500 pounds at Great Lakes facilities and 250,000 
pounds at Inland facilities.
2. Summary of Annual Reductions in Impingement and Entrainment for 
Three Options
    Exhibit IX-3 presents EPA's estimates of annual impingement and 
entrainment reductions under the ``50 MGD for All Waterbodies'' option. 
Exhibit IX-4 presents EPA's estimates of annual impingement and 
entrainment reductions under the ``200 MGD for All Waterbodies'' 
option. Exhibit IX-5 presents results for the ``100 MGD for Certain 
Waterbodies'' option.
a. Reductions in Annual Impingement and Entrainment for the ``50 MGD 
for All Waterbodies'' Option
    See Exhibit IX-3 for reductions in annual impingement and 
entrainment for the ``50 MGD for All Waterbodies'' option.

[[Page 68513]]

 Exhibit IX-3.--Reductions In Annual Impingement and Entrainment for the
            ``50 MGD for All Waterbodies'' Option, by Region
------------------------------------------------------------------------
                                                             Foregone
                 Region                        Age-1       fishery yield
                                            equivalents        (lbs)
------------------------------------------------------------------------
California..............................         383,000          28,000
North Atlantic..........................         930,000          17,900
Mid-Atlantic............................      13,400,000         600,000
Gulf of Mexico..........................       8,380,000       1,250,000
Great Lakes.............................      11,600,000         169,000
Inland..................................      14,800,000         157,000
                                         -----------------
    National total......................      49,500,000       2,220,000
------------------------------------------------------------------------

    The estimates in Exhibit IX-3 make use of data from available 
impingement and entrainment studies conducted at both Phase II and 
Phase III facilities. Using data solely from the limited number of 
Phase III studies available (4 studies for the Great Lakes region and 
11 studies for the Inland region), estimates of reductions in loss of 
age-1 equivalents to impingement and entrainment are 1,700,000 at Great 
Lakes facilities and 5,450,000 at Inland facilities. Estimates of 
reductions of foregone fishery yield are 5,570 pounds at Great Lakes 
facilities and 93,000 pounds at Inland facilities.
    b. Reductions in Annual Impingement and Entrainment for the ``200 
MGD for All Waterbodies'' Option
    See Exhibit IX-4 for reductions in annual impingement and 
entrainment for the ``200 MGD for All Waterbodies'' option.

 Exhibit IX-4.--Reductions In Annual Impingement and Entrainment for the
            ``200 MGD for All Waterbodies'' Option, by Region
------------------------------------------------------------------------
                                                             Foregone
                 Region                        Age-1       fishery yield
                                            equivalents        (lbs)
------------------------------------------------------------------------
California..............................               0               0
North Atlantic..........................         198,000           3,800
Mid Atlantic............................      11,900,000         534,000
Gulf of Mexico..........................       4,580,000         682,000
Great Lakes.............................       7,710,000         116,000
Inland..................................       9,650,000         107,000
                                         -----------------
    National total......................      34,000,000       1,440,000
------------------------------------------------------------------------

    The estimates in Exhibit IX-4 make use of data from available 
impingement and entrainment studies conducted at both Phase II and 
Phase III facilities. Using data solely from the limited number of 
Phase III studies available (4 studies for the Great Lakes region and 
11 studies for the Inland region), estimates of reductions in loss of 
age-1 equivalents to impingement and entrainment are 1,100,000 at Great 
Lakes facilities and 3,270,000 at Inland facilities. Estimates of 
reductions in foregone fishery yield are 3,690 pounds at Great Lakes 
facilities and 55,700 pounds at Inland facilities.
c. Reductions in Annual Impingement and Entrainment for the ``100 MGD 
for Certain Waterbodies'' Option
    See Exhibit IX-5 for reductions in annual impingement and 
entrainment for the ``100 MGD for Certain Waterbodies'' option.

 Exhibit IX-5.--Reductions In Annual Impingement and Entrainment for the
          ``100 MGD for Certain Waterbodies'' Option, by Region
------------------------------------------------------------------------
                                                             Foregone
                 Region                        Age-1       fishery yield
                                            equivalents        (lbs)
------------------------------------------------------------------------
California..............................               0               0
North Atlantic..........................         754,000          14,500
Mid Atlantic............................      11,900,000         534,000
Gulf of Mexico..........................       8,380,000       1,250,000
Great Lakes.............................       8,740,000         130,000
                                         -----------------
    National total......................      29,800,000       1,930,000
------------------------------------------------------------------------

    The estimates in Exhibit IX-5 make use of data from available 
impingement and entrainment studies conducted at both Phase II and 
Phase III facilities. Using data solely from the limited number of 
Phase III studies available (4 studies for the Great Lakes region), the 
estimate of reductions in loss of age-1 equivalents to impingement and

[[Page 68514]]

entrainment is 1,260,000 and the estimate of reductions in foregone 
fishery yield is 4,190 pounds at Great Lakes facilities.
d. Reductions in Annual Impingement and Entrainment for Other Policy 
Options
    EPA considered a wide range of policy options in developing the 
proposed section 316(b) regulation for the Phase III facilities. The 
Regional Analysis Document provides results for all evaluated options 
considered in this rulemaking.

D. National Benefits

1. Overview
    Economic benefits of the co-proposed options for the section 316(b) 
regulation for Phase III existing facilities can be broadly defined 
according to categories of goods and services provided by the species 
affected by impingement and entrainment by cooling water intake 
structures.
    The first category includes benefits that pertain to the use 
(direct or indirect) of the affected fishery resources. Use value 
reflects the value of all current direct and indirect physical uses of 
a good or service (Mitchell and Carson, 1989; DCN 5-1287). The direct 
use benefits can be further categorized according to whether or not 
affected goods and services are traded in the market. The ``direct 
use'' benefits of the section 316(b) regulation stem both 
from''market'' commodities (e.g., commercial fisheries) and from 
``nonmarket'' goods (e.g., recreational angling). Indirect use benefits 
also can be linked to either market or nonmarket goods and services--
for example, the manner in which reduced impingement and entrainment-
related losses of forage species leads through the aquatic ecosystem 
food web to enhance the biomass of species targeted for commercial 
(market) and recreational (nonmarket) uses.
    The second category includes benefits that are independent of any 
current or anticipated use of the resource; these are known as ``non-
use'' or ``passive use'' values.\51\ Non-use values include 
``nonmarketed'' goods and services, which reflect human values 
associated with existence, bequest, and altruistic motives. Existence 
value is the value that individuals may hold for simply knowing that a 
particular good exists regardless of their present or expected use. For 
example, ecological goods and services such as diversity of aquatic and 
terrestrial species and habitat for threatened and endangered species 
are often valued for their existence. Bequest value exists when someone 
gains utility through the knowledge that an amenity will be available 
for others (family or future generations) in the future (Fisher and 
Raucher, 1984; DCN 4-0043). Altruistic values arise from interpersonal 
concerns (valuing the happiness that others get from enjoying the resource).
---------------------------------------------------------------------------

    \51\ The benefits analysis of the proposed options for 
potentially regulated Phase III facilities does not assess option 
value as a distinct component of value because it is increasingly 
recognized that option value ``cannot be a separate component of 
value'' (Freeman, 2003; p. 249).
---------------------------------------------------------------------------

    The economic value of benefits from the proposed options for Phase 
III facilities is estimated using a range of valuation methods, with 
the specific approach being dependent on the type of benefit category, 
data availability, and other suitable factors. Commercial fishery 
benefits are valued using market data. Recreational angling benefits 
are valued using a combination of primary and secondary research 
methods. Methodologies for estimating use values for recreational (non-
market values) and commercial (market values) species are well 
developed, and some of these species have been extensively studied. As 
a result, these values are relatively easy to estimate. A detailed 
description of the approaches used for valuing commercial and 
recreational benefits of the proposed options can be found in Chapters 
A4 and A5 of the Regional Analysis Document.
    Estimating benefits from reduced impingement and entrainment of 
forage species is more challenging because these species are not 
targeted directly by commercial or recreational anglers and have no 
direct use values that can be observed in markets or inferred from 
revealed actions of anglers. To estimate a portion of the indirect use 
benefits from reducing impingement and entrainment losses to forage 
species, EPA used a trophic transfer model that translates changes in 
impingement and entrainment losses of forage fish into changes in the 
harvest of commercial and recreational species that are subject to 
impingement and entrainment (i.e., not the whole food web). This method 
is described in Chapter A1 of Part A of the Regional Analysis Document.
    Stated preference methods, or benefit transfer based on stated 
preference studies, are the generally accepted techniques for 
estimating non-use values.
    Stated preference methods rely on carefully designed surveys, which 
ask people either to state their willingness to pay for particular 
ecological improvements, such as increased protection of aquatic 
species or habitats with particular attributes; or to choose between 
competing hypothetical ``packages'' of ecological improvements and 
household cost. In either case, analysis of survey responses allows 
estimation of values.
    Economists generally consider non-use values more difficult to 
assess than use values for several reasons:
    a. Non-use values are not associated with easily observable 
behavioral trails;
    b. Non-use values may be held by both users and non-users of a 
resource, and non-users may be less familiar with particular services 
provided by affected resources;
    c. The development of a defensible stated preference survey that 
meets the NOAA blue ribbon panel requirements is often a time and 
resource intensive process,\52\ and
---------------------------------------------------------------------------

    \52\ The NOAA blue ribbon panel provided an extensive set of 
guidelines for survey construction, administration, and analysis to 
ensure that ``* * * CV produces estimates reliable enough to be the 
starting point of a judicial process of damage assessment, including 
passive-use values [i.e. non-use values]'' (see FR 58:10 pp.4601-4614, 1993).
---------------------------------------------------------------------------

    d. Even carefully designed surveys may be subject to certain biases 
associated with the hypothetical nature of survey responses (Mitchell 
and Carson 1989).
    Reducing impingement and entrainment losses of fish and shellfish 
may result in both use and non-use benefits. Of the organisms which are 
anticipated to be protected by the proposed options for the section 
316(b) regulation for Phase III facilities, approximately 3.3 percent 
will eventually be harvested by commercial and recreational fishers and 
therefore can be valued with direct use valuation techniques. 
Unharvested fish, which have no direct use value, represent 96.7 
percent of the total loss. These unlanded fish include forage fish and 
the unlanded portion of the stock of harvested species. Because 
unlanded fish contribute to the yield of harvested fish, they have an 
indirect use value that is captured by the direct use value of the fish 
that are caught. However, this indirect use value represents only a 
portion of the total value of unlanded fish. In fact, society may value 
both landed and unlanded fish for reasons unrelated to their use value. 
Such non-use values include the value that people may hold simply for 
knowing these fish exist. While non-use values are difficult to 
quantify, EPA believes it is important to consider such values, 
particularly since 96.7 percent of impinged and entrained organisms 
have no direct use value.
    EPA considered several approaches to quantifying non-use values for the

[[Page 68515]]

proposed rule, including a stated preference study and meta-analysis of 
surface water valuation studies. The Agency has begun exploring the 
development of a stated preference survey that would measure non-use 
benefits from reduced impingement and entrainment attributable to the 
proposed options for the section 316(b) regulation for Phase III 
facilities. Although this primary study effort could not be completed 
in time for the publication of the proposed regulation, EPA expects to 
complete the study in time to rely on its findings for the final 
regulation. A number of studies have found that meta-analysis has 
considerable promise in benefits transfer and that meta-analysis can 
produce more reliable results than other benefit transfer methods 
(Bergstrom and De Civita, 1999, DCN 6-3109; Florax et al., 2002, pp. 
117-135, DCN 7-5132). However, the usefulness of meta-analysis results 
is dependent on both the quality of the underlying studies and their 
applicability to the policy question at hand. Given the difficulties in 
estimating non-use benefits at the national level using benefit 
transfer methods and the small number of studies that have attempted to 
value fish losses, particularly those related to impingement and 
entrainment at cooling water intake sites, EPA has not included 
monetary measures of non-use values in the benefit analysis for the 
proposed options. Instead, the Agency analyzed potential non-use 
benefits of the proposed options qualitatively.
2. Timing of Benefits
    Discounting is the economic conversion of future benefits and costs 
to their present values, accounting for the fact that individuals tend 
to value future outcomes less than comparable near-term outcomes. 
Discounting is important when the value of benefits (or costs) may vary 
from year to year and when the time profiles of benefits and costs are 
not the same. Discounting enables a consistent comparison of benefits 
to costs across time periods.
    For the section 316(b) rulemaking, the difference in timing in 
costs and benefits arises from two sources. First, facilities are not 
expected to achieve compliance with the regulation until several years 
after its promulgation. Benefits are equal to zero from the 
promulgation of the rule (i.e., beginning of 2007) until facilities 
reach compliance. Thus, EPA discounted the benefits from each facility 
by the number of years between the year in which the rule is 
promulgated and the year in which the facility complies. Since benefits 
were estimated on a regional basis, EPA estimated benefits from each 
facility by multiplying total regional benefits by the percentage of 
total regional flow that is attributable to each facility. EPA used 
current permit expiration information for model facilities to identify 
the projected year of compliance for each facility in the analysis.
    The second difference in timing in costs and benefits arises from 
the fact that additional time will pass between implementation of best 
technology available and resulting increased fishery yields. This is 
because one or more years may pass between the time an organism is 
spared impingement and entrainment and the time of its ultimate 
harvest. For example, a larval fish spared from entrainment (in effect, 
at age 0) may be caught by a recreational angler at age 3, meaning that 
a 3-year time lag arises between the installation of best technology 
available and the realization of the estimated recreational benefit. 
Likewise, if a 1-year old fish is spared from impingement and is then 
harvested by a commercial fisherman at age 2, there is a 1-year lag 
between the installation of best technology available and the 
subsequent commercial fishery benefit.
    Recognizing that avoided fish deaths occur mainly in fish that are 
younger than harvestable age (eggs, larvae and juveniles), and that the 
benefits from avoided impingement and entrainment of these fish would 
be realized typically 3-4 years after their avoided death, EPA 
developed a benefits recognition schedule for facilities in each 
region. The benefits schedule is based on an estimate of benefit delay 
that reflects the estimated age and species composition of impingement 
and entrainment losses, by region. Following achievement of compliance, 
benefits from facilities in most regions are assumed to increase over a 
7-year period to a long-term, steady State average, equal to the 
approximated per-facility benefit value discussed above, according to a 
numerical profile of < 0.0, 0.1, 0.2, 0.8, 0.9, 0.95, 1.0 >. This 
profile indicates the fraction of the steady State benefit value that 
is realized in each of the first seven years following the achievement 
of compliance at a facility. After seven years, this fraction remains 
1.0 for 23 additional years. After these combined 30 years the facility 
is assumed to cease compliance, which is consistent with the time 
period over which costs are evaluated. In the same way that the 
benefits profile builds up over time following compliance, the benefits 
profile declines at the end of the compliance period. Specifically, in 
the seven years following the end of compliance, the fraction of the 
steady State benefit value achieved follows the profile of <  1.0, 0.9, 
0.8, 0.2, 0.1, 0.05, 0.0 >. Therefore, the analysis of benefits 
encompasses a 37-year period starting with the first year of 
compliance. There are 35 years when benefits do not equal zero for a 
facility; 25 years when benefits are 100%; 10 years when benefits are a 
percentage of the total. These profile values are approximations based 
on a review of the age-specific fishing mortality rates that were used 
in the impingement and entrainment analysis and best professional 
judgment. Although EPA believes this approach is sufficient for this 
analysis, EPA could potentially refine these profile values through the 
use of a population model and will consider the feasibility of doing so.
    For regions with a relatively high contribution of impingement to 
total impingement and entrainment (Inland, Great Lakes, and the Gulf of 
Mexico regions), EPA used an adjusted benefits profile of <  0.1, 0.2, 
0.8, 0.9, 0.95, 1.0 >. This adjusted profile reflects that impinged 
fish are usually larger and older than entrained fish and thus benefits 
will be realized sooner in these regions.
    EPA used these profiles of benefits to calculate a total present 
value of benefits and then to calculate a constant annual equivalent 
value (annualized value) of the present value. EPA performed the 
calculations of present value and annualized value using two discount 
rate values: a rate of 3% and a rate of 7%. As described above, the 
time profile of benefits, and therefore the discounting analysis, 
varies by facility. For all facilities, the first year of the analysis 
is 2007 (the promulgation of the rule). However, the first year in 
which benefits are realized varies by facility. Following this year, as 
outlined above, benefits increase over a six-or seven-year period, 
remain constant until the 30th year, and then decline over a six-or 
seven-year period. For a detailed discussion of the discounting 
methodology, refer to Chapter A8, ``Discounting Benefits'' and for a 
discussion of the time line of benefits, refer to Chapter H1, ``Total 
National Benefits'' in the Regional Analysis Document (DCN 7-0003).
3. Recreational Fishing Valuation
    The recreational fishing benefits of the proposed options for the 
section 316(b) rule for Phase III facilities were estimated for six 
study regions (North Atlantic, Mid-Atlantic, Gulf of Mexico, 
California, Great Lakes, Inland) based on similarities in the affected 
ecosystems, aquatic species present, and characteristics of 
recreational fishing

[[Page 68516]]

activities within each of the six regions. To estimate recreational 
benefits of the proposed options for Phase III facilities, EPA 
developed a benefit transfer approach based on a meta-analysis of 
recreational fishing valuation studies designed to measure the various 
factors that determine willingness-to-pay for catching an additional 
fish per trip. To validate the meta-analysis results, EPA also used 
regional models of recreational fishing behavior developed for the 
Phase II analysis (DCN 6-0003) to estimate benefits from reduced 
impingement and entrainment at potentially regulated Phase III 
facilities for the four coastal regions and the Great Lakes region.\53\
---------------------------------------------------------------------------

    \53\ No RUM model was generated in the Phase II analysis for the 
Inland region because of a lack of data for that region so we could 
not verify the meta-analysis results for the Inland region.
---------------------------------------------------------------------------

a. Valuation Methods for Recreational Fishing
    As the first step in its recreational fishing analysis, EPA 
conducted a comprehensive review of recreational fishing valuation 
literature to identify prior estimates of recreational use benefits 
that may be applicable to the section 316(b) regulation. Based on this 
review, EPA identified 48 studies that use established economic 
estimation techniques to measure the value of changes in marine or 
freshwater recreational catch (DCN 7-0003). All of these studies 
provide estimates of the marginal value to fishermen of catching an 
additional fish, or provide enough information for EPA to calculate 
such a value.
    To examine the relative influence of methodology, sample, and 
fishery characteristics on the marginal value of catching an additional 
fish, EPA conducted a regression-based meta-analysis of these 48 
studies. Although the valuation studies include estimates for a large 
number of different species, for the purposes of the model these 
species were aggregated into groups of similar species, including four 
saltwater species groups (big game, small game, flatfish, and other 
saltwater), two anadromous species groups (salmon and steelhead trout), 
and six freshwater species groups (panfish, bass, walleye/pike, 
muskellunge, rainbow trout, and other trout). The other saltwater group 
includes bottom fish species, species caught by anglers not targeting 
any particular species, and species that did not clearly fit in one of 
the other groups. The panfish group includes freshwater species such as 
yellow perch, catfish, and other warm water species. For the meta-
analysis, some species groups were modeled interactively with regional 
variables to allow for variation in species value across different 
geographic regions.
    The regression results from this analysis reveal both statistically 
significant and intuitively correct patterns in the way that factors 
influence the value to fishermen of catching an additional fish. These 
results allow for calculation of the marginal value per fish for 
different species based on resource and policy context characteristics. 
Additional detail on the methods EPA used in this analysis can be found 
in Chapter A5 of the Regional Analysis Document.
b. Validating the Recreational Analysis Based on the Region-Specific 
RUM Models
    EPA also analyzed recreational fishing benefits from reduced 
impingement and entrainment based on region-specific random utility 
models (RUM) of recreational anglers' behavior for the four coastal 
regions and the Great Lakes region. These models were initially 
developed by the Agency for analysis of the final section 316(b) 
regulation for Phase II facilities.\54\ For that regulation, EPA 
developed original RUM models for three of the four coastal regions 
(California, the Mid-Atlantic, and the Gulf of Mexico) and the Great 
Lakes region. For the North Atlantic region, EPA used a model developed 
by the National Marine Fisheries Service (NMFS) by Hicks et al. (Hicks, 
Steinback, Gautam, and Thunberg, 1999. Volume II: The Economic Value of 
New England and Mid-Atlantic Sportfishing in 1994--DCN 5-1271). Chapter 
A11 of the Phase II Regional Analysis Document provide more detailed 
discussion of the methodology used in EPA's RUM analysis (DCN 7-0003).
---------------------------------------------------------------------------

    \54\ The RUM models for the North Atlantic, Mid-Atlantic, Gulf 
of Mexico, and California have not changed from the Phase II 
analysis. The Great Lakes RUM model was slightly refined for the 
Phase III analysis. The main differences between the Phase III and 
Phase II models include: (1) The ability to estimate separate values 
for yellow perch and bass and (2) the inclusion of site amenity 
effects in the site choice model (Besedin et al., 2004: DCN 7-5000).
---------------------------------------------------------------------------

    The regional recreational fishing studies used information on 
recreational anglers' behavior to infer anglers' economic value for the 
quality of fishing in the case study areas. The models' main assumption 
is that anglers will get greater satisfaction, and thus greater 
economic value, from sites where the catch rate is higher due to 
reduced impingement and entrainment, all else being equal. This benefit 
may occur in two ways: first, an angler may get greater enjoyment from 
a given fishing trip when catch rates are higher, and thus get a 
greater value per trip; second, anglers may take more fishing trips 
when catch rates are higher, resulting in greater overall value for 
fishing in the region. EPA modeled an angler's decision to visit a site 
as a function of site-specific cost, fishing trip quality, and 
additional site attributes such as presence of boat launching 
facilities or fish stocking at the site.
    The Agency used 5-year historical catch rates per hour of fishing 
as a measure of baseline fishing quality in the regional studies. Catch 
rate is a policy variable of concern because catch rate is a function 
of fish abundance, which is affected by fish mortality caused by 
impingement and entrainment.
    The Agency used the estimated model coefficients in conjunction 
with the estimated changes in impingement and entrainment in a given 
region to estimate per-day welfare gain to recreational anglers due to 
the proposed regulatory options for Phase III facilities. For the North 
Atlantic region, EPA used model coefficients estimated by Hicks et al. 
(1999) (DCN 5-1271).
    To estimate the total economic value to recreational anglers for 
changes in catch rates resulting from changes in impingement and 
entrainment in a given region, EPA multiplied the total number of 
fishing days for a given region by the estimated per-day welfare gain 
due to the regulation. EPA estimated that the proposed regulatory 
options for Phase III facilities would cause only negligible changes in 
recreational fishing participation due to the improved quality of the 
fishing sites. Therefore, the welfare estimates for the four coastal 
regions and the Great Lakes are based on estimates of baseline 
recreational fishing participation provided by NOAA Fisheries and the 
Fish and Wildlife Service's Annual Survey of Fishing, Hunting, and 
Wildlife-Related Recreation (U.S. Department of the Interior, 2001, DCN 
6-3231).
    Results of the RUM models are presented in Chapter B4 through F4 of 
the Regional Analysis Document. In general, the RUM-based results fall 
within the range of values estimated based on the meta-model.\55\ That 
the values from the two independent analyses are relatively close 
corroborates the use of meta-analysis in

[[Page 68517]]

estimating the value of incremental recreational fishing improvments 
resulting from the proposed section 316(b) regulation for Phase III 
facilities.
---------------------------------------------------------------------------

    \55\ The RUM models produced lower estimated recreational 
benefits in the Gulf of Mexico, Mid-Atlantic, and California 
regions, and higher estimates in the Great Lakes and North Atlantic 
regions. But no RUM estimates were outside of the lower and upper 
bound meta analysis values computed using the Krinksy and Robb 
approach.
---------------------------------------------------------------------------

c. Application of the Meta-Analysis Results to the Analysis of 
Recreational Benefits of the Proposed 316(b) Rule
    This section briefly discusses the use of the meta-analysis results 
to estimate the recreational benefits of the regulatory options 
evaluated for the proposed rule. Additional detail on this analysis, 
including EPA's treatment of uncertainty in per fish values, can be 
found in the Regional Analysis Document in Chapter A5. EPA began by 
calculating per fish values from the meta-analysis regression 
coefficients, based on regional and species specific values of the 
input variables. Because estimates from regression meta-models are 
subject to uncertainty, EPA used the Krinksy and Robb approach to 
estimate lower and upper bound marginal values for each species (DCN 6-
3160). EPA also conducted a sensitivity analysis to determine how per 
fish values could change based on different selections for the 
independent variables. The per fish values and bounds used in this 
analysis of the recreational benefits of the regulatory options are 
based on EPA's best estimates of values for independent variables. The 
resulting per fish values are presented in Exhibit IX-6.

                    Exhibit IX-6.--Estimated Marginal Value per Fish to Recreational Anglers
----------------------------------------------------------------------------------------------------------------
                                     Marginal value per fish caught, by region: saltwater fish \a\ (June 2003 $)
                                   -----------------------------------------------------------------------------
              Region                                             Other
                                     Small game    Flatfish    saltwater
                                                                  \b\
----------------------------------------------------------------------------------------------------------------
California........................       $12.57       $15.61        $4.52
North Atlantic....................         7.64         8.06         4.20
Mid-Atlantic......................         6.87         6.91         3.73
Gulf of Mexico....................         5.32  ...........         2.88
-----------------------------------
                                    Marginal value per fish caught, by region: freshwater fish \a\ (June 2003 $)
                                   --------------
              Region                 Small game    Walleye/       Bass       Panfish       Salmon     Trout \d\
                                        \c\          Pike
-----------------------------------
Great Lakes.......................  ...........        $4.58        $5.90        $1.06       $11.19        $7.99
Inland............................        $7.38         5.15         6.96         0.97  ...........        2.79
----------------------------------------------------------------------------------------------------------------
\a\ Marginal values per fish are presented only for species in regions in which they are affected by one of the
  regulatory options evaluated for the proposed rule.
\b\ Other saltwater species include bottom fish and other miscellaneous species.
\c\ Anadromous species such as striped bass and American shad can be found in freshwater coastal rivers as well
  as in saltwater.
\d\ The trout category includes all trout species except rainbow trout and lake trout.

    To estimate the benefits of the alternative regulatory options, EPA 
multiplied the per fish values from Exhibit IX-6 by the number of 
additional fish that would be caught by anglers under each regulatory 
option due to reductions in impingement and entrainment, compared to 
current levels of recreational catch. Exhibits IX-7, IX-8, and IX-9 
present the results of these calculations for the ``50 MGD for All 
Waterbodies,'' ``200 MGD for All Waterbodies,'' and ``100 MGD for 
Certain Waterbodies'' options. The proportion of impingement and 
entrainment losses of fishery species that were valued as lost 
recreational catch was determined from stock-specific fishing mortality 
rates, which indicate the fraction of a stock that is harvested by 
recreational anglers. Because fishing mortality rates are typically 
less than 20 percent, a proportion of the losses of fishery species 
were not valued in the recreational benefits analysis.
    Exhibit IX-7 shows the annual increase in total recreational catch 
and resulting monetized benefits resulting from the ``50 MGD for All 
Waterbodies'' option. The exhibit shows that compared to the current 
national level of recreational catch, anglers would catch 620,000 
additional fish per year under this option, resulting in total 
undiscounted benefits of $2.12 million per year. The annualized value 
of these additional fish is $1.77 million and $1.39 million, evaluated 
at 3 percent and 7 percent discount rates, respectively. Increased 
recreational catch is largest in the Gulf of Mexico region, where the 
rule would increase annual recreational catch by 183,000 fish, 
resulting in an undiscounted recreational welfare gain of $0.67 million.
    Exhibit IX-7 also presents lower and upper confidence bounds for 
the benefits of the ``50 MGD for All Waterbodies'' option. These bounds 
are based on using the Krinsky and Robb technique to estimate the 95th 
and 5th confidence limits on the marginal value per fish predicted by 
the meta-analysis. Undiscounted national benefits of this option range 
from $1.02 million to $4.47 million per year, and benefits in the Gulf 
of Mexico region range from $0.30 million to $1.50 million per year, 
based on 90 percent confidence limits on the marginal value per fish 
predicted by the meta-analysis.

              Exhibit IX-7.--Recreational Benefits Under the ``50 MGD for All Waterbodies'' Option
----------------------------------------------------------------------------------------------------------------
                                                    Increase in    Annualized benefits  (thousands, 2003 $) \a\
                                                      annual     -----------------------------------------------
                                                   recreational
                                                  catch compared
                     Region                         to current
                                                   recreational         Low            Mean            High
                                                       catch
                                                   (thousands of
                                                       fish)
----------------------------------------------------------------------------------------------------------------
California......................................               5             $12             $28             $66

[[Page 68518]]

North Atlantic..................................              13              36              77             169
Mid-Atlantic....................................             159             290             612           1,301
Gulf of Mexico..................................             183             298             667           1,499
Great Lakes.....................................              92             192             385             756
Inland..........................................             167             189             358             675

National total (evaluated at 3%) \c\............             620             843           1,765           3,704
National total (evaluated at 7%) \c\............             620             665           1,391          2,919
----------------------------------------------------------------------------------------------------------------
\a\ Lower and upper bounds are calculated using the Krinsky and Robb technique to estimate the 95th and 5th
  percentile limits on the marginal value per fish predicted by the meta-analysis.
\b\ Undiscounted benefits are calculated from the annual increase in recreational catch, evaluated at a steady
  State condition. All regional results presented in this table are undiscounted. Undiscounted benefits are not
  directly comparable to cost.
\c\ Annualized benefits represent the value of all recreational benefits generated over the time frame of the
  analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of
  the discounting methodology, refer to section IX.D.2 of this preamble.

    Exhibit IX-8 shows the annual increase in recreational catch and 
resulting monetized benefits resulting from the ``200 MGD for All 
Waterbodies'' option. The exhibit shows that compared to the current 
national level of recreational catch, anglers would catch 419,000 
additional fish per year under this option, resulting in total 
undiscounted benefits of $1.43 million per year. The annualized value 
of these additional fish is $1.18 million and $0.92 million, evaluated 
at 3 percent and 7 percent, respectively. Increased recreational catch 
is largest in the Mid-Atlantic region, where this option would increase 
annual recreational catch by 141,000 fish, resulting in an undiscounted 
welfare gain of $0.55 million.
    The exhibit also presents lower and upper confidence bounds for the 
benefits of the ``200 MGD for All Waterbodies'' option. Undiscounted 
national benefits of this option range from $0.69 million to $2.99 
million per year, and benefits in the Mid-Atlantic region range from 
$0.26 million to $1.16 million per year, based on 90 percent confidence 
limits on the marginal value per fish predicted by the meta-analysis.

              Exhibit IX-8.--Recreational Benefits Under the ``200 MGD for All Waterbodies'' Option
----------------------------------------------------------------------------------------------------------------
                                                    Increase in     Annualized benefits (thousands, 2003 $) \a\
                                                      annual     -----------------------------------------------
                                                   recreational
                                                  catch compared
                     Region                         to current
                                                   recreational         Low            Mean            High
                                                       catch
                                                   (thousands of
                                                       fish)
----------------------------------------------------------------------------------------------------------------
California......................................               0              $0              $0              $0
North Atlantic..................................               3               8              16              36
Mid-Atlantic....................................             141             258             545           1,158
Gulf of Mexico..................................             100             163             364             819
Great Lakes.....................................              64             132             266             523
Inland..........................................             111             128             242             456

National total (evaluated at 3%) \c\............             419             567           1,181           2,463
National total (evaluated at 7%) \c\............             419             443             922          1,922
----------------------------------------------------------------------------------------------------------------
\a\ Lower and upper bounds are calculated using the Krinsky and Robb technique to estimate the 95th and 5th
  percentile limits on the marginal value per fish predicted by the meta-analysis.
\b\ Undiscounted benefits are calculated from the annual increase in recreational catch, evaluated at a steady
  State condition. All regional results presented in this table are undiscounted. Undiscounted benefits are not
  directly comparable to cost.
\c\ Annualized benefits represent the value of all recreational benefits generated over the time frame of the
  analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of
  the discounting methodology, refer to section IX.D.2 of this preamble.

    Exhibit IX-9 shows the annual increase in recreational catch and 
resulting monetized benefits resulting from the ``100 MGD for Certain 
Waterbodies'' option. The exhibit shows that compared to the current 
national level of recreational catch, anglers would catch 407,000 
additional fish per year under this option, resulting in total 
undiscounted benefits of $1.57 million per year. The annualized value 
of these additional fish is $1.29 million and $1.01 million, evaluated 
at 3 percent and 7 percent, respectively. Increased recreational catch 
is largest in the Gulf of Mexico, where this option would increase 
annual recreational catch by 183,000 fish, resulting in an

[[Page 68519]]

undiscounted welfare gain of $0.67 million.
    The exhibit also presents lower and upper confidence bounds for the 
benefits of the ``100 MGD for Certain Waterbodies'' option. 
Undiscounted national benefits of this option range from $0.73 million 
to $3.38 million per year, and benefits in the Gulf of Mexico region 
range from $0.30 million to $1.50 million per year, based on 90 percent 
confidence limits on the marginal value per fish predicted by the meta-
analysis.

            Exhibit IX-9.--Recreational Benefits Under the ``100 MGD for Certain Waterbodies'' Option
----------------------------------------------------------------------------------------------------------------
                                                    Increase in    Annualized benefits  (thousands, 2003 $) \a\
                                                      annual     -----------------------------------------------
                                                   recreational
                                                  catch compared
                     Region                         to current
                                                   recreational         Low            Mean            High
                                                       catch
                                                   (thousands of
                                                       fish)
----------------------------------------------------------------------------------------------------------------
California......................................               0              $0              $0              $0
North Atlantic..................................              11              29              63             137
Mid-Atlantic....................................             141             258             545           1,158
Gulf of Mexico..................................             183             298             667           1,499
Great Lakes.....................................              72             148             299             586
Inland..........................................               0               0               0               0
                                                 -----------------
National total (undiscounted) \b\...............             407             733           1,573           3,380
National total (evaluated at 3%) \c\............             407             602           1,292           2,779
National total (evaluated at 7%) \c\............             407             468           1,006          2,164
----------------------------------------------------------------------------------------------------------------
\a\ Lower and upper bounds are calculated using the Krinsky and Robb technique to estimate the 95th and 5th
  percentile limits on the marginal value per fish predicted by the meta-analysis.
\b\ Undiscounted benefits are calculated from the annual increase in recreational catch, evaluated at a steady
  State condition. All regional results presented in this table are undiscounted. Undiscounted benefits are not
  directly comparable to cost.
\c\ Annualized benefits represent the value of all recreational benefits generated over the time frame of the
  analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of
  the discounting methodology, refer to section IX.D.2 of this preamble.

d. Limits and Uncertainties
    Benefit transfers by definition are characterized by a difference 
between the context in which resource values are estimated and that in 
which benefit estimates are desired. The ability of meta-analysis to 
adjust for the influence of study, economic, and resource 
characteristics on recreational values can minimize, but not eliminate, 
potential biases. The meta-analysis model presented here provides a 
close but not perfect match to the context in which values are desired. 
Some of the key limitations inherent to the meta-model and the 
subsequent benefit transfer are the following:
    A. The per fish values estimated from the model depend on the 
values of the input variables in the meta-analysis. EPA assigned values 
to the input variables based on established economic theory and 
characteristics of the affected species and regions. However, because 
the input values for some variables are uncertain, the resulting per 
fish values and benefits estimates are also uncertain.
    B. As mentioned above, the economic and resource characteristics of 
the 48 studies used in the meta-analysis are not perfectly matched to 
the economic and resource characteristics of sites affected by the 
regulatory options evaluated for the proposed rule. In particular, 
although most of the Inland studies take place in the Great Lakes 
region, the regulatory options affect sites all across the Inland 
region. However, EPA believes that regional differences in per fish 
values for specific Inland species are relatively small.
    C. By aggregating species into categories, EPA was able to improve 
the fit of the meta-analysis model. However, this aggregation results 
in a lower level of detail in the values that can be predicted. In 
particular, the panfish category and other saltwater category include 
relatively diverse species.
    D. Projected changes in recreational catch may be overestimated 
because potential compensatory effects in affected species' 
reproduction or survival rates were not taken into account.
    E. In estimating recreational fishery losses, EPA used impingement 
and entrainment data provided by the facilities. While EPA used the 
most current data available, in some cases these data are 20 years old 
or older. Thus, they may not reflect current conditions. Also, data 
from Phase II facilities may not be representative of Phase III facilities.
    F. Impingement and entrainment estimates include only individuals 
directly lost to impingement and entrainment, not their progeny, and 
may therefore be underestimates.
    G. In estimating the benefits of improved recreational angling, the 
Agency only assigned a monetary benefit to the increases in consumer 
surplus for the baseline number of fishing days. Thus, benefits will be 
understated if participation increases in response to increased 
availability of fishery species as a result of reduced impingement and 
entrainment. This approach omits the portion of recreational fishing 
benefits that arise when improved conditions lead to higher levels of 
participation. Empirical evidence suggests that the omission of 
increased angling days can lead to an underestimate of total 
recreational fishing benefits. However, the magnitude of this error is 
likely to be small.
4. Commercial Fishing Valuation
    Reductions in impingement and entrainment at cooling water intake 
structures are expected to benefit the commercial fishing industry. The 
effect is straightforward: Reducing the number of fish killed will 
probably increase the number of fish available for harvest. Measuring 
the benefits of this effect is less straightforward. This section 
presents the methods EPA used to estimate commercial benefits, as well 
as the resulting benefits estimates.
a. Methods
    EPA estimated commercial benefits by first estimating the value of 
total losses under current impingement and entrainment conditions (or 
the total

[[Page 68520]]

benefits of eliminating all impingement and entrainment). Then, based 
on review of the empirical literature, EPA assumed that producer 
surplus is equal to 40 percent of baseline losses. Finally, EPA 
estimated benefits under different options for the proposed section 
316(b) rule for Phase III facilities by applying the estimated 
percentage reduction in impingement and entrainment to the estimated 
producer surplus to obtain the estimated increase in producer surplus 
attributable to the option. This methodology was applied in each region 
except the Inland region (which does not include any significant 
commercial fishing). See Chapter A4 of the Regional Analysis Document 
for details about EPA's methodology.
    To determine regional losses and benefits, EPA conducted several 
analyses. EPA estimated losses to commercial harvest (in pounds of 
fish) attributable to impingement and entrainment under current 
conditions by modeling these fish losses by applying a linear stock-to-
harvest assumption (i.e., a 10 percent change in the stock would result 
in a 10 percent change in harvest). The percentage of fish harvested is 
based on data on historical fishing mortality rates. EPA estimated 
gross revenue of lost commercial catch (i.e., the increase in gross 
revenue that would be expected if all current impingement and 
entrainment were eliminated) by using landings and dockside prices ($/
lb) as reported by the NOAA Fisheries for the period 1991-2001. The 
conceptually suitable measure of benefits is the sum of any changes in 
producer and consumer surplus. The methods used for estimating the 
change in surplus depend on whether the physical impact on the 
commercial fishery market appears sufficiently small such that it is 
reasonable to assume there will be no appreciable price changes in the 
markets for the impacted fisheries.
    For the regions and magnitude of losses included in this analysis, 
it is reasonable to assume no change in price, which implies that the 
welfare change is limited to changes in producer surplus. This change 
in producer surplus is assumed to be equivalent to a portion of the 
change in gross revenues. EPA assumes a range of 0 percent to 40 
percent of the estimated gross revenue losses as a means of estimating 
the change in producer surplus. This is based on a review of empirical 
literature and is consistent with recommendations made in comments on 
the Phase II proposal.
    EPA believes this is a reasonable approach to estimating producer 
surplus when there are no anticipated price changes. EPA's (2000) 
Guidelines for Preparing Economic Analyses (EPA 240-R-00-003) describes 
options for estimating ecological benefits for fisheries, and notes 
that ``if changes in service flows are small, current market prices can 
be used as a proxy for expected benefit * * * a change in the 
commercial fish catch might be valued using the market price for the 
affected species.'' In EPA's review of the commercial fishing 
literature two alterative methods for computing producer surplus as a 
percentage of gross revenues also came to the fore. The more common 
approach to calculating benefits relies on estimating normal profit as 
a percentage of gross revenue. In the surveyed studies this percentage 
of gross review ranges from -5 percent to 91.2 percent. The second 
approach to estimating commercial benefits, which may produce the more 
appropriate measure of welfare, computes the producer surplus as a 
percentage of gross revenue. The studies that use this method return 
percentages that range from 0 to 37, due to reduced profit estimates 
that include a return to the owners as part of costs. In light of these 
findings EPA has chosen to use 0 percent to 40 percent as the estimated 
range of percent of gross revenue that best captures the additional 
benefit that will accrue to commercial fishers.
    Once the commercial surplus losses associated with impingement and 
entrainment under baseline conditions have been estimated, EPA 
estimates the percentage reduction in impingement and entrainment at 
each facility under each regulatory option. This analysis is conducted 
for each region.
b. Results
    Exhibit IX-10 presents the estimated annualized commercial fishing 
benefits attributable to three co-proposed options: The ``50 MGD for 
All Waterbodies'' option (50 MGD All); the ``200 MGD for All 
Waterbodies'' option (200 MGD All); and the ``100 MGD for Certain 
Waterbodies'' option (100 MGD oceans, estuaries, tidal rivers, or one 
of the Great Lakes). The results reported include the total reduction 
in losses in pounds of fish and the value of this reduction discounted 
at 0 percent, 3 percent, and 7 percent. Total annualized commercial 
fishing benefits, applying a 3 percent discount rate, are estimated to 
be $0 to $132,000 per year for the 50 MGD option, $0 to $79,000 per 
year for the 200 MGD option, and $0 to $118,000 per year for the 100 
MGD for certain waterbodies option. When a 7 percent discount rate is 
applied, the total annualized commercial fishing benefits for the 50 
MGD option are estimated to be $0 to $104,000, under the 200 MGD option 
benefits equal $0 to $79,000, and for the 100 MGD for certain 
waterbodies option the discounted benefits are $0 to $93,000.

  Exhibit IX-10.--Annualized Commercial Fishing Benefits for Impinged and Entrained Fish Expected Under the Co-
                                               Proposed Options a
----------------------------------------------------------------------------------------------------------------
                                    Reduction in lost yield (thousands of     Benefits (thousands; $ 2003) c d
                                                     lbs)                 --------------------------------------
                                   ---------------------------------------
            Region \b\                                          100 MGD                                100 MGD
                                    50 MGD  all  200 MGD all    certain    50 MGD  all  200 MGD all    certain
                                                              waterbodies                            waterbodies
----------------------------------------------------------------------------------------------------------------
California........................           16            0            0           $6           $0           $0
North Atlantic....................            8            2            6            4            1            3
Mid-Atlantic......................          459          408          408           31           27           27
Gulf of Mexico....................          313          171          313           93           51           93
Great Lakes.......................           86           59           66           25           17           19
                                   --------------
National total,\e\ (undiscounted).          882          640          794          159           96          143
National total, (evaluated at 3%).          882          640          794          132           79          118
National total, (evaluated at 7%).          882          640          794          104           62          93
----------------------------------------------------------------------------------------------------------------
\a\ Benefits are upper bound benefits based on 40% of gross revenue. The lower bound is $0.
\b\ No significant commercial fishing takes place in the Inland region, and thus this region is excluded from
  this analysis.
\c\ Discounted to account for lag in implementation and lag in time required for fish lost to I&E to reach a
  harvestable age.

[[Page 68521]]

\d\ Annualized benefits represent the value of all commercial benefits generated over the time frame of the
  analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of
  the discounting methodology, refer to Section IX.D.2 of this preamble.
\e\ Undiscounted benefits are not comparable to costs.

c. Limitations and Uncertainties
    Some of the major uncertainties and assumptions of EPA's commercial 
fishing analysis include:
    A. The analysis only includes individuals that are directly killed 
by impingement and entrainment, not their progeny and may therefore 
underestimate projected changes in harvest.
    B. Projected changes in commercial catch may be overestimated 
because potential compensatory effects in affected species' 
reproduction or survival rates were not taken into account.
    C. Projected changes in harvest may be too high or too low because 
interactions with other stressors are not considered.
    D. EPA used impingement and entrainment data provided by the 
facilities. While EPA used the most current data available, in some 
cases these data are 20 years old or older. Thus, they may not reflect 
current conditions. Also data from Phase II facilities may not be 
representative of Phase III facilities.
    E. EPA assumes a linear stock to harvest relationship (i.e., a 10 
percent change in stock would have a 10 percent change in landings); 
this may be low or high, depending on the condition of the stocks. 
Region-specific fisheries regulations also will affect the validity of 
the linear assumption.
    F. EPA assumes that NOAA Fisheries landings data are accurate and 
complete. However, in some cases prices and/or quantities may be 
reported incorrectly.
    G. EPA currently estimates that the increase in producer surplus as 
a result of the rule will be between 0 percent and 40 percent of the 
estimated change in gross revenues. The research used to develop this 
range is not region-specific; thus the true value may fall outside this 
range for some regions and species.
5. Non-Use Benefits
    To assess public policy significance or importance of the 
ecological gains from the proposed regulation for Phase III facilities, 
EPA developed the relevant information and considered non-use benefits 
of the proposed options qualitatively. This assessment is discussed below.
a. Qualitative Assessment
    EPA is able to assign direct use value to only a very small 
fraction of the fish lost to impingement and entrainment. As shown in 
Exhibit IX-11, fish with a direct use value, which include only those 
fish that are harvested, account for only 3.3 percent of the total age-
1 equivalent impingement and entrainment loss. Unharvested fish (i.e., 
forage fish and the unlanded portion of the stock of harvested 
species), which have no direct use value, represent 96.7 percent of the 
total loss. A portion of the total benefits of these unharvested 
commercial, recreational, and forage species, can be derived indirectly 
from the estimated use values of the harvested animals. As noted in 
section IX.D.1, society may value both landed and unlanded fish for 
reasons unrelated to their use value. Such non-use values include the 
value that people may hold simply for knowing these fish exist. EPA 
believes it is important to consider such values, at least 
qualitatively, particularly since such a large percentage of impinged 
and entrained organisms have no direct use value.

    Exhibit IX-11.--Number and Percentage of Baseline Impingement and Entrainment Losses by Species Category
----------------------------------------------------------------------------------------------------------------
                                                              Age-1 adult equivalents  (millions)
                                              ------------------------------------------------------------------
                                                                                                        I&E of
                                                                          Commercial     Harvested    harvested
                    Region                                     Forage         and       commercial    species as
                                               All species    species    recreational       and       percentage
                                                                            species    recreational    of total
                                                                                          species        I&E
----------------------------------------------------------------------------------------------------------------
California...................................         1.31        0.666         0.642        0.0594         4.54
North Atlantic...............................         2.34        1.77          0.572        0.0542         2.32
Mid-Atlantic.................................        23.2        14.8           8.47         1.46           6.29
South Atlantic...............................         1.52        0.78          0.74          .011          7.41
Gulf of Mexico...............................        12.7         3.71          9.01         1.2            9.43
Great Lakes..................................        34.4        32.8           1.54         0.543          1.58
Inland.......................................        44.2        35.6           8.6          0.511          1.15
                                              --------------
    National total \a\.......................       120          90.2          29.6          3.94          3.29
----------------------------------------------------------------------------------------------------------------
\a\ The national total includes baseline impingement and entrainment losses at four sample-weighted potentially
  regulated facilities in the South Atlantic region.

    Changes in cooling water intake system design or operations 
resulting from the proposed section 316(b) regulations for Phase III 
facilities are expected to reduce impingement and entrainment losses of 
fish, shellfish, and other aquatic organisms and, as a result, are 
expected to increase the numbers of individuals present and benefit 
local and regional fishery populations. Depending on the nature and 
magnitude of the reduced losses and of conditions at a given site, this 
may ultimately contribute to the enhanced environmental functioning of 
affected waterbodies (rivers, lakes, estuaries, and oceans) and 
associated ecosystems. EPA does not have the data to determine whether 
reducing impingement and entrainment losses at Phase III facilities 
will have significant ecological benefits. However, the discussion that 
follows describes benefits that may result from reducing impingement 
and entrainment losses generally.
    EPA believes that reducing fish mortality from impingement and

[[Page 68522]]

entrainment would contribute to the health and sustainability of the 
affected fish populations by reducing the overall level of mortality 
for those populations. Fish populations suffer from numerous sources of 
mortality; some are natural and others are anthropogenic. Natural 
sources include weather, predation by other fish, and the availability 
of food. Human impacts that affect fish populations include fishing, 
pollution, habitat changes, and impingement and entrainment losses at 
cooling water intake structures. Fish populations decline when they are 
unable to sufficiently compensate for their overall level of mortality. 
Lowering the overall mortality level increases the probability that a 
population will be able to compensate for mortality at a level 
sufficient to maintain the long-term health of the population.
    In addition to their importance in providing food and other goods 
of direct use to humans, the organisms lost to impingement and 
entrainment may be critical to the continued functioning of the 
ecosystems of which they are a part depending on the magnitude of the 
actual impingement and mortality losses attributable to Phase III 
facilities. The discussion that follows describes the kinds of impacts 
that EPA believes may be due to impingement mortality and entrainment 
losses generally, not necessarily those at Phase III facilities. Fish 
are essential for energy transfer in aquatic food webs, regulation of 
food web structure, nutrient cycling, maintenance of sediment 
processes, redistribution of bottom substrates, the regulation of 
carbon fluxes from water to the atmosphere, and the maintenance of 
aquatic biodiversity (Peterson and Lubchenco, 1997; Postel and 
Carpenter, 1997; Holmlund and Hammer, 1999; Wilson and Carpenter, 
1999). Examples of impacts on ecological conditions, functions and 
services that may result from impingement and entrainment include: (1) 
Decreased numbers of ecological keystone, rare, sensitive, or 
threatened and endangered species; (2) decreased numbers of popular 
commercial and recreational fish species that are not fished, perhaps 
because the fishery is closed; (3) increased numbers of exotic or 
disruptive species that compete well in the absence of species lost to 
impingement and entrainment (impingement and entrainment may also help 
remove some exotic or disruptive organisms); (4) disruption of 
ecological niches and ecological strategies used by aquatic species; 
(5) disruption of energy transfer through the food web; (6) decreased 
local biodiversity; (7) disruption of predator-prey relationships; (8) 
disruption of age class structures of species; (9) disruption of 
natural succession processes. Many of these functions and services can 
only be maintained by the continued presence of all life stages of fish 
and other aquatic species in their natural habitats. While some 
ecological services of aquatic species have been studied, other 
ecosystems services, relationships, and interrelationships are unknown 
or poorly understood. To the extent that the latter are not captured in 
the benefits analyses, total benefits may be underestimated.
    Scientific and public interest in protecting ecosystem services is 
increasing with the recognition that these services are vulnerable to a 
wide range of human activities and are difficult, if not impossible, to 
replace with human technologies (Meffe, 1992; DCN 7-5250). Reducing 
impingement and entrainment losses could contribute to restoring (or 
preserving) the biological integrity of the ecosystems of substantial 
national importance.
    In the 1987 amendments to the CWA, Congress established the 
National Estuary Program because the ``Nation's estuaries are of great 
importance to fish and wildlife resources and recreation and economic 
opportunity * * * [, and]
maintaining the health and ecological 
integrity of these estuaries is in the national interest (Water Quality 
Act of 1987 (Pub. L. 100-4), Sec.  317(a)(1)(A) and (B) adding Sec.  
320 to the CWA, 33 US.C. 1330). So far, there are 28 estuaries 
designated under the National Estuary Program (NEP). In addition, the 
largest estuary in the United States, Chesapeake Bay, is protected 
under its own Federally mandated program, separate but related to NEP. 
Of the 15 estuaries from which the potentially regulated Phase III 
facilities withdraw cooling water, 12 are nationally significant 
estuaries designated under NEP or the Chesapeake Bay Program.
    Substantial Federal and State resources have been directed to NEP 
to enhance conservation and knowledge about the estuaries designated 
under this program. Since 1998, more than $95 million dollars has been 
devoted to NEP to benefit the health of the nationally significant 
estuaries (NEP, 2004, DCN 7-5125).
    Reducing impingement and entrainment at potentially regulated Phase 
III facilities may also benefit freshwater ecosystems of national 
significance, including the Great Lakes Basin, Mississippi River, and 
Columbia River. These waterbodies are subject to large-scale ecosystem 
restoration efforts that are good indicators of great public interest 
in restoring the ecological health of these ecosystems (U.S. Fish and 
Wildlife Service, 2004, DCN 7-5126; U.S. Department of the Interior, 
2004, DCN 7-5127; Northeast Midwest Institute, 2004, DCN 7-5128; The 
Upper Mississippi River Basin Association, 2004, DCN 7-5129). The 
ecosystem restoration efforts focus on many issues, including coastal 
habitat restoration, protection of fish species, conservation of 
migratory birds and endangered species. For example, between 1992 and 
2001, more than $17 million was devoted to projects to restore and 
conserve the Great Lakes ecosystem, and $102 million was spent on 
improving the Mississippi River ecosystem (U.S. EPA, 2004, DCN 7-5130; 
and Brescia, 2002, DCN 7-5131). Reducing impingement and entrainment of 
aquatic organisms may improve the quality of aquatic habitat and 
contribute to improvement of the biological integrity and health of 
these ecosystems.
    Finally, reducing impingement and entrainment in waterbodies that 
do not have national significance may contribute to restoration or 
protection of ecosystems of regional or local importance.
    Today's proposed rule may also help preserve threatened and 
endangered species by reducing the number of individuals lost to 
impingement and entrainment. Threatened and endangered (T&E) and other 
special status species directly affected by impingement and entrainment 
include, pallid sturgeon, delta smelt, Sacramento splittail, and 
longfin smelt. Threatened and endangered species can also suffer 
indirect impacts if impingement and entrainment at cooling water intake 
structures disrupts their food source or their critical habitat. The 
loss of individuals of listed species from impingement and entrainment 
is particularly important because, by definition, these species are 
already rare and at risk of irreversible decline because of other 
stressors. EPA explored several methods for valuing reductions in 
threatened and endangered species losses. However, EPA has not included 
quantitative measures of non-use values associated with protection of 
threatened and endangered species in the proposed section 316(b) rule 
for Phase III facilities benefit analysis due to current uncertainty 
about the extent of Phase III facilities' impact on threatened and 
endangered species at the national level and EPA's inability to 
monetize such benefits given the available economic valuation 
literature. Details about possible non-use benefits valuation 
approaches are presented in Chapter A9

[[Page 68523]]

of the 316(b) Regional Analysis Document (DCN 7-0003).
6. National Benefits
    Quantifying and monetizing reduction in impingement and entrainment 
losses due to today's proposed rule is challenging, and the preceding 
sections discuss specific limitations and uncertainties associated with 
estimation of commercial, recreational, and non-use benefit categories. 
National benefit estimates are subject to uncertainties inherent in 
valuation approaches used for assessing the three benefits categories. 
The combined effect of these uncertainties is of unknown magnitude or 
direction (i.e., the estimates may over or under state the anticipated 
national-level benefits); however, EPA has no data to indicate that the 
results for each benefit category are atypical or unreasonable. Since 
the Agency was unable to monetize non-use benefits, the estimates of 
total benefits reflect use values only.
    Exhibit IX-13 presents EPA's estimates of the total monetized 
benefits from impingement and entrainment reduction under the ``50 MGD 
for All Waterbodies'' option. The annualized use benefits from 
impingement and entrainment reduction post regulation are $1.90 million 
per year (2003$), with lower and upper bounds of $0.98 million and 
$3.84 million, discounted at three percent. Discounted at seven 
percent, annualized use benefits are $1.50 million per year, with lower 
and upper bounds of $0.77 million and $3.02 million.

                               Exhibit IX-13.--Summary of Monetized Social Benefits ``50 MGD for All Waterbodies'' Option
                                                                 [Thousands; 2003 $]
\a\
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                               Annualized recreational fishing     Total annualized value of monetizable
                                                                Annualized                 benefits                     impingement and entrainment
                            Region                              commercial ---------------------------------------             reductions \b\
                                                                 fishing                                          --------------------------------------
                                                                 benefits       Low          Mean         High         Low          Mean         High
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                         Evaluated at a 3 percent discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California...................................................        $0-$5          $10          $24          $57          $16          $29          $62
North Atlantic...............................................          0-3           29           63          138           32           66          141
Mid-Atlantic.................................................         0-25          235          497        1,057          260          522        1,082
Gulf of Mexico...............................................         0-78          249          558        1,254          327          636        1,332
Great Lakes..................................................         0-20          157          316          621          178          337          641
Inland \c\...................................................            0          162          306          577          162          306          577
                                                              --------------
    National total...........................................        0-132          843        1,765        3,704          975        1,897        3,836
--------------------------------------------------------------
                                                         Evaluated at a 7 percent discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California...................................................          0-4            9           20           47           13           24           51
North Atlantic...............................................          0-2           22           49          107           25           51          109
Mid-Atlantic.................................................         0-19          181          382          811          200          401          830
Gulf of Mexico...............................................         0-62          198          444          998          260          506        1,061
Great Lakes..................................................         0-16          122          246          483          138          262          499
Inland \c\...................................................            0          133          251          473          133          251          473
                                                              --------------
    National total...........................................        0-104          665        1,391        2,919          769        1,495       3,023
--------------------------------------------------------------------------------------------------------------------------------------------------------
 \a\ All benefits presented in this exhibit are annualized. These annualized benefits represent the value of all benefits generated over the time frame
  of the analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of the discounting methodology,
  refer to section IX.D.2 of this preamble.
 \b\ The total monetizable value of impingement and entrainment reductions includes use benefits only. EPA evaluated non-use benefits only
  qualitatively. A range of recreational fishing benefits is provided, based on the Krinsky and Robb technique to estimate the 95th and 5th percentile
  limits on the marginal value per fish predicted by the meta-analysis. Commercial fishing benefits are computed based on a range from 0 percent to 40
  percent of the change in gross revenue, as explained in the text. To calculate the total monetizable value columns (low, mean, and high), the high end
  value for commercial fishing benefits is added to the low, medium and high values for recreational fishing benefits respectively.
 \c\ There are no commercial fishing benefits in the Inland region.

    Exhibit IX-14 presents EPA's estimates of the total monetized 
benefits from impingement and entrainment reduction under the ``200 MGD 
for All Waterholes'' option. The annualized use benefits from 
impingement and entrainment reduction post regulation are $1.26 million 
per year (2003$), with lower and upper bounds of $0.65 million and 
$2.54 million, discounted at three percent. Discounted at seven 
percent, annualized use benefits are $0.98 million per year, with lower 
and upper bounds of $0.51 million and $1.98 million.

[[Page 68524]]



                               Exhibit IX-14.--Summary of Monetized Social Benefits ``200 MGD for All Waterbodies'' Option
                                                                 [Thousands; 2003 $]
\a\
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                               Annualized recreational fishing     Total annualized value of monetizable
                                                                Annualized                 benefits                     impingement and entrainment
                            Region                              commercial ---------------------------------------             reductions \b\
                                                                 fishing                                          --------------------------------------
                                                                 benefits       Low          Mean         High         Low          Mean         High
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                         Evaluated at a 3 percent discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California...................................................           $0           $0           $0           $0           $0           $0           $0
North Atlantic...............................................          0-1            6           13           28            7           14           29
Mid-Atlantic.................................................         0-22          208          440          934          230          462          956
Gulf of Mexico...............................................         0-43          136          305          685          179          347          728
Great Lakes..................................................         0-14          108          216          425          122          230          439
Inland \c\...................................................            0          110          207          390          110          207          390
                                                              --------------
    National total...........................................         0-79          567        1,181        2,463          647        1,260        2,542
--------------------------------------------------------------
                                                          Evaluated at a 7 percent discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California...................................................            0            0            0            0            0            0            0
North Atlantic...............................................            0            4           10           21            5           10           21
Mid-Atlantic.................................................         0-17          158          334          709          175          350          726
Gulf of Mexico...............................................         0-34          108          243          545          142          277          579
Great Lakes..................................................         0-11           83          166          326           93          177          337
Inland \c\...................................................            0           90          170          321           90          170          321
                                                              --------------
    National total...........................................           62          443          922        1,922          505          984       1,984
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ All benefits presented in this exhibit are annualized. These annualized benefits represent the value of all benefits generated over the time frame
  of the analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of the discounting methodology,
  refer to section IX.D.2 of this preamble.
\b\ The estimate of the total monetizable value of impingement and entrainment reductions includes use benefits only.
\c\ There are no commercial fishing benefits in the Inland region.

    Exhibit IX-15 presents EPA's estimates of the total monetized 
benefits from impingement and entrainment reduction under the ``100 MGD 
for Certain Waterbodies'' option. The annualized use benefits from 
impingement and entrainment reduction post regulation are $1.41 million 
per year (2003$), with lower and upper bounds of $0.72 million and 
$2.90 million, discounted at three percent. Discounted at seven 
percent, annualized use benefits are $1.10 million per year, with lower 
and upper bounds of $0.56 million and $2.26 million.

                             Exhibit IX-15.--Summary of Monetized Social Benefits ``100 MGD for Certain Waterbodies'' Option
                                                                 [Thousands; 2003 $]
\a\
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                               Annualized recreational fishing     Total annualized value of monetizable
                                                                Annualized                 benefits                     impingement and entrainment
                            Region                              commercial ---------------------------------------             reductions \b\
                                                                 fishing                                          --------------------------------------
                                                                 benefits       Low          Mean         High         Low          Mean         High
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                         Evaluated at a 3 percent discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California...................................................           $0           $0           $0           $0           $0           $0           $0
North Atlantic...............................................          0-2           24           52          113           26           54          115
Mid-Atlantic.................................................         0-22          208          440          934          230          462          956
Gulf of Mexico...............................................         0-78          249          558        1,254          327          636        1,332
Great Lakes..................................................         0-16          121          243          478          137          259          494
Inland \c\...................................................            0            0            0            0            0            0            0
                                                              --------------
    National total...........................................        0-118          602        1,292        2,779          720        1,411        2,897
--------------------------------------------------------------
                                                         Evaluated at a 7 percent discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California...................................................            0            0            0            0            0            0            0
North Atlantic...............................................          0-2           19           40           88           20           42           90
Mid-Atlantic.................................................         0-17          158          334          709          175          350          726
Gulf of Mexico...............................................         0-62          198          444          998          260          506        1,061
Great Lakes..................................................         0-12           93          188          368          105          200          381
Inland \c\...................................................            0            0            0            0            0            0            0
                                                              --------------

[[Page 68525]]

    National total...........................................         0-93          468        1,006        2,164          561        1,099       2,257
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ All benefits presented in this exhibit are annualized. These annualized benefits represent the value of all benefits generated over the time frame
  of the analysis, discounted to 2007, and then annualized over a thirty year period. For a more detailed discussion of the discounting methodology,
  refer to section IX.D.2 of this preamble.
\b\ The estimate of the total monetizable value of impingement and entrainment reductions includes use benefits only.
\c\ There are no commercial fishing benefits in the Inland region.

    EPA considered a wide range of policy options in developing the 
proposed section 316(b) regulation for the Phase III facilities. The 
Regional Analysis Document provides EPA's complete benefit assessment 
for the alternative policy options considered in this rulemaking.

X. Comparison of Benefits and Costs

    This section presents two measures that compare the benefits and 
costs of the regulatory options: (1) A benefit-cost analysis, and (2) a 
break-even analysis of the minimum non-use benefits required for total 
annualized benefits to equal total annualized costs, on a per household 
basis. Each measure is presented by study region.

A. Benefit-Cost Analysis

    The benefit-cost analysis for each of the co-proposed regulatory 
options compares total annualized use benefits to total annualized pre-
tax costs (social costs) at existing facilities that remain open in the 
baseline.\56\ Benefits and costs were discounted using both a 3 percent 
and 7 percent discount rate. The cost estimates include costs of 
compliance to facilities subject to the proposed rule as well as 
administrative costs incurred by State and local governments and by the 
Federal government. The benefits estimates include monetized benefits 
to commercial and recreational fishing. The total monetizable benefits 
include only use benefits. The non-use benefits were evaluated 
qualitatively. Thus, the benefit-cost analysis compares a generally 
complete measure of social costs with an incomplete measure of social 
benefits and should be interpreted bearing in mind this inconsistency.
---------------------------------------------------------------------------

    \56\ This section only includes benefits and costs for existing 
facilities because EPA was unable to assess benefits of reducing 
impringement mortality and entrainment at new offshore oil and gas 
facilities.
---------------------------------------------------------------------------

1. Benefit-Cost Analysis Results
    Exhibit X-1 presents a summary of total annualized use benefits, 
total annualized costs, and net benefits for the ``50 MGD for All 
Waterbodies'' option. Under this option, 136 facilities (excluding 
baseline closures) are subject to the regulation. Of those facilities, 
it is assumed that 103 are required to install technologies to reduce 
impingement mortality and entrainment, and 32 will incur permitting 
costs only. The exhibit shows that the use benefits of the 50 MGD 
option are not projected to exceed the costs in any of the study 
regions. In the California region, costs exceed use benefits by $0.8 
million or $0.9 million when discounted at 3 percent and 7 percent 
respectively. In the Inland region, costs are $19.4 million or $20.4 
million greater than the use benefits. At the national level, EPA 
projects the costs of this option to exceed its use benefits by $45.4 
million per year, discounted at 3 percent, or by $48.6 million per 
year, discounted at 7 percent.

                                Exhibit X-1.--Summary of Social Benefits and Costs ``50 Mgd for All Waterbodies'' Option
                                                                   [Millions; $ 2003]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                       Number of   Total annualized use value                     Net benefits \c\
                                                           Number of  facilities     of I&E  reductions \a\        Total   -----------------------------
                      Study region                        facilities             ------------------------------ annualized
                                                          subject to  installing                                 costs \b\     Low      Mean      High
                                                            option    technology     Low      Mean      High
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                             Evaluated at a 3% discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California..............................................          1           1      $0.02     $0.03     $0.06       $0.8      -$0.8     -$0.8     -$0.8
North Atlantic..........................................          5           4       0.03      0.07      0.14        4.6       -4.5      -4.5      -4.5
Mid-Atlantic............................................          3           3       0.26      0.52      1.08        2.6       -2.3      -2.0      -1.5
Gulf of Mexico..........................................          7           7       0.33      0.64      1.33        9.1       -8.7      -8.4      -7.7
Great Lakes.............................................         23          19       0.18      0.34      0.64       10.1       -9.9      -9.7      -9.4
Inland..................................................         97          69       0.16      0.31      0.58       19.7      -19.5     -19.4     -19.1
                                                         -------------
    National total......................................        136         103       0.97      1.90      3.84       47.3      -46.4     -45.4     -43.5
---------------------------------------------------------
                                                              Evaluated at a 7% discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California..............................................          1           1       0.01      0.02      0.05        1.0       -1.0      -0.9      -0.9
North Atlantic..........................................          5           4       0.02      0.05      0.11        5.0       -5.0      -5.0      -4.9
Mid-Atlantic............................................          3           3       0.20      0.40      0.83        2.4       -2.2      -2.0      -1.6

[[Page 68526]]

Gulf of Mexico..........................................          7           7       0.26      0.51      1.06       10.2       -9.9      -9.7      -9.1
Great Lakes.............................................         23          19       0.14      0.26      0.50       10.2      -10.1      -9.9      -9.7
Inland..................................................         97          69       0.13      0.25      0.47       20.6      -20.5     -20.4     -20.2
                                                         -------------
    National total......................................        136         103       0.77      1.50      3.02       50.1      -49.3     -48.6    -47.1
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ The total monetizable value of I&E reductions includes use benefits only. EPA evaluated non-use benefits only qualitatively. The ranges (low,
  medium, and high) for annualized use value is computed by adding the high end value for commercial fishing benefits (based on assumed producer surplus
  of 40% of gross revenue) to the low, mean, and high values for recreational fishing benefits respectively (see Section IX).
\b\ Total costs are based on pre-tax facility costs. National total costs also include State, local, and Federal administrative costs of $0.6 million
  that cannot be attributed to individual study regions.
\c\ Net benefits are computed by subtracting total annualized costs from total annual use values. The net benefits presented here are based on the
  comparison of a generally complete measure of social costs with an incomplete measure of social benefits, and should be interpreted with caution.

    Exhibit X-2 presents a summary of total annualized benefits, total 
annualized costs, and net benefits for the ``200 MGD for All 
Waterbodies'' option. Under this option, 25 facilities (excluding 
baseline closures) are subject to the regulation. Of those facilities, 
it is assumed that 22 are required to install technologies to reduce 
impingement mortality and entrainment. The exhibit shows that the use 
benefits of the 200 MGD option are not projected to exceed the costs in 
any of the study regions. In the North Atlantic region, costs exceed 
use benefits by $0.5 million, evaluated at both the 3 percent and 7 
percent discount rates. In the Inland region, costs are $12.1 million 
or $13.5 million greater than the use benefits. At the national level, 
EPA projects the costs of this option to exceed its use benefits by 
$21.5 million per year, discounted at 3 percent, or by $23.1 million 
per year, discounted at 7 percent.

                                Exhibit X-2.--Summary of Social Benefits and Costs ``200 MGD for All Waterbodies'' Option
                                                                    [Millions; $2003]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                     Number of   Number of   Total annualized use value of                       Net benefits \c\
                                                    facilities  facilities         I&E reductions \a\           Total   --------------------------------
                   Study region                     subject to  installing --------------------------------- annualized
                                                      option    technology     Low        Mean       High     costs \b\     Low        Mean       High
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                             Evaluated at a 3% discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California........................................           0           0      $0.00      $0.00      $0.00        $0.0       $0.0       $0.0       $0.0
North Atlantic....................................           1           1       0.01       0.01       0.03         0.5       -0.5       -0.5       -0.5
Mid-Atlantic......................................           2           2       0.23       0.46       0.96         2.0       -1.7       -1.5       -1.0
Gulf of Mexico....................................           2           2       0.18       0.35       0.73         3.8       -3.6       -3.5       -3.1
Great Lakes.......................................           5           5       0.12       0.23       0.44         4.1       -3.9       -3.8       -3.6
Inland............................................          14          12       0.11       0.21       0.39        12.3      -12.2      -12.1      -11.9
                                                   -------------
    National total................................          25          22       0.65       1.26       2.54        22.8      -22.1      -21.5      -20.2
---------------------------------------------------
                                                             Evaluated at a 7% discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California........................................           0           0      $0.00      $0.00      $0.00        $0.0       $0.0       $0.0       $0.0
North Atlantic....................................           1           1       0.00       0.01       0.02         0.5       -0.5       -0.5       -0.4
Mid-Atlantic......................................           2           2       0.17       0.35       0.73         1.8       -1.6       -1.4       -1.1
Gulf of Mexico....................................           2           2       0.14       0.28       0.58         4.4       -4.2       -4.1       -3.8
Great Lakes.......................................           5           5       0.09       0.18       0.34         3.7       -3.6       -3.5       -3.3
Inland............................................          14          12       0.09       0.17       0.32        13.7      -13.6      -13.5      -13.4
                                                   -------------
    National total................................          25          22       0.51       0.98       1.98        24.1      -23.6      -23.1     -22.1
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ The total monetizable value of I&E reductions includes use benefits only. EPA did not estimate non-use benefits quantitatively. The low and high use
  values reflect the range of recreational fishing values presented in Section 9 of the preamble. They were calculated using the Krinsky and Robb
  technique to estimate the 95th and 5th percentile limits on the marginal value per fish predicted by the meta-analysis.
\b\ Total costs are based on pre-tax facility costs. National total costs also include State, local, and Federal administrative costs of $0.1 million
  that cannot be attributed to individual study regions.
\c\ The net benefits presented here are based on the comparison of a generally complete measure of social costs with an incomplete measure of social
  benefits, and should be interpreted with caution.

[[Page 68527]]

    Exhibit X-3 presents a summary of total annualized benefits, total 
annualized costs, and net benefits for the regulatory option with a 
design intake flow of 100 MGD or more for facilities withdrawing from 
oceans, estuaries, and tidal rivers, or the Great Lakes (``100 MGD for 
Certain Waterbodies''). Under this option, 19 facilities (excluding 
baseline closures) are subject to the regulation. Of those facilities, 
it is assumed that 18 are required to install technologies to reduce 
impingement mortality and entrainment, and one will incur permitting 
costs only. The exhibit shows that the use benefits of the 100 MGD for 
certain waterbodies option are not projected to exceed the costs in any 
of the study regions. In the Mid-Atlantic region, costs exceed use 
benefits by $1.5 million or $1.4 million, evaluated at 3 percent and 7 
percent discount rates. In the Gulf of Mexico region, costs are $8.4 
million or $9.7 million greater than the use benefits. At the national 
level, EPA projects the costs of this option to exceed its use benefits 
by $16.2 million per year, discounted at 3 percent, or by $17.2 million 
per year, discounted at 7 percent.

                               Exhibit X-3.--Summary of Social Benefits and Costs 100 MGD for Certain Waterbodies'' Option
                                                                    [millions; $2003]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                      Number of   Number of   Total annualized use value of                       Net benefits c
                                                     facilities  facilities          I&E reductions a           Total   --------------------------------
                    Study region                     subject to  installing --------------------------------- annualize
                                                       option    technology     Low        Mean       High    d Costs b     Low        Mean       High
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                             Evaluated at a 3% discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California.........................................           0           0      $0.00      $0.00      $0.00       $0.0       $0.0       $0.0       $0.0
North Atlantic.....................................           3           3       0.03       0.05       0.12        2.0       -2.0       -1.9       -1.9
Mid Atlantic.......................................           2           2       0.23       0.46       0.96        2.0       -1.7       -1.5       -1.0
Gulf of Mexico.....................................           7           7       0.33       0.64       1.33        9.1       -8.7       -8.4       -7.7
Great Lakes........................................           8           6       0.14       0.26       0.49        4.5       -4.3       -4.2       -4.0
Inland.............................................           0           0       0.00       0.00       0.00        0.0        0.0        0.0        0.0
                                                    -------------
    National total.................................          19          18       0.72       1.41       2.90       17.6      -16.9      -16.2      -14.7
----------------------------------------------------
                                                             Evaluated at a 7% discount rate
--------------------------------------------------------------------------------------------------------------------------------------------------------
California.........................................           0           0      $0.00      $0.00      $0.00       $0.0       $0.0       $0.0       $0.0
North Atlantic.....................................           3           3       0.02       0.04       0.09        2.0       -2.0       -2.0       -1.9
Mid Atlantic.......................................           2           2       0.17       0.35       0.73        1.8       -1.6       -1.4       -1.1
Gulf of Mexico.....................................           7           7       0.26       0.51       1.06       10.2       -9.9       -9.7       -9.1
Great Lakes........................................           8           6       0.11       0.20       0.38        4.1       -4.0       -3.9       -3.7
Inland.............................................           0           0       0.00       0.00       0.00        0.0        0.0        0.0        0.0
                                                    -------------
    National total.................................          19          18       0.56       1.10       2.26       18.3      -17.7      -17.2     -16.0
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ The total monetizable value of I&E reductions includes use benefits only. EPA did not estimate non-use benefits quantitatively. The low and high use
  values reflect the range of recreational fishing values presented in Section 9 of the preamble. They were calculated using the Krinsky and Robb
  technique to estimate the 95th and 5th percentile limits on the marginal value per fish predicted by the meta-analysis.
\b\ Total costs are based on pre-tax facility costs. National total costs also include State, local, and Federal administrative costs of $0.2 million
  that cannot be attributed to individual study regions.
\c\ The net benefits presented here are based on the comparison of a generally complete measure of social costs with an incomplete measure of social
  benefits, and should be interpreted with caution.

B. Break-even Analysis

    Estimating non-use values is an extremely challenging and uncertain 
exercise, particularly when, due to time and resource constraints, 
primary research using stated preference methods was not a feasible 
option for this proposed rule. In Section IX.D.5 above, EPA described 
possible alternative approaches for developing non-use benefit 
estimates based on benefits transfer and associated methods. Due to the 
uncertainties of providing estimates of the magnitude of non-use values 
associated with the regulatory options considered for this proposal, 
this section provides an alternative approach for evaluating the 
significance of non-use values. The approach used here applies a 
``break-even'' analysis to identify what non-use values would have to 
be in order for the options to have monetized benefits that are equal 
to costs.
    The break-even approach uses EPA's estimated commercial and 
recreational use benefits for the regulatory options and subtracts them 
from the estimated annual compliance costs incurred by existing 
facilities subject to the regulatory options. The resulting ``net 
cost'' enables one to work backwards to estimate what non-use values 
would need to be in order for total annual benefits to equal annualized 
costs. EPA computed the per household willingness-to-pay for all three 
options proposed today and found that the non-use values necessary to 
equate total annual benefits with total annual social cost ranged from 
$1.43 per household, for the ``100 MGD for Certain Waterbodies'' option 
discounted at 3 percent, to $2.13 per household for the ``50 MDG for 
All Water bodies'' option discounted at 7 percent. EPA also calculated 
the break-even non-use value per (age-1 equivalent) fish saved. The per 
fish value necessary to have the total annual costs and benefits of the 
proposed options equate range from $0.54 for the ``100 MGD for Certain 
Waterbodies'' option, discounted at 3 percent, to $0.98 for the ``50 
MDG for All Water bodies'' option, discounted at 7 percent. For a 
detailed discussion of the estimation and results of both the per 
household and per fish break-even values see the Regional Analysis Document.

[[Page 68528]]

XI. Statutory and Executive Order Reviews

A. E.O. 12866: Regulatory Planning and Review

    Under Executive Order 12866 (58 FR 51735, October 4, 1993), the 
Agency must determine whether the regulatory action is ``significant'' 
and therefore subject to Office of Management and Budget (OMB) review 
and the requirements of the Executive Order. The order defines a 
``significant regulatory action'' as one that is likely to result in a 
rule that may:
    ? Have an annual effect on the economy of $100 million or 
more or adversely affect in a material way the economy, a sector of the 
economy, productivity, competition, jobs, the environment, public 
health or safety, or State, local, or Tribal governments or 
communities;
    ? Create a serious inconsistency or otherwise interfere with 
an action taken or planned by another agency;
    ? Materially alter the budgetary impact of entitlements, 
grants, user fees, or loan programs or the rights and obligations of 
recipients thereof; or
    ? Raise novel legal or policy issues arising out of legal 
mandates, the President's priorities, or the principles set forth in 
the Executive Order.
    Pursuant to the terms of Executive Order 12866, it has been 
determined that this proposed rule is a ``significant regulatory 
action.'' As such, this action was submitted to OMB for review. Changes 
made in response to OMB suggestions or recommendations will be 
documented in the public record.

B. Paperwork Reduction Act

    The information collection requirements in this proposed rule have 
been submitted for approval to the Office of Management and Budget 
(OMB) under the Paperwork Reduction Act, 44 U.S.C. 3501 et seq. The 
Information Collection Request (ICR) document prepared by EPA has been 
assigned EPA ICR number 2169.01.
    The information collected under today's proposed rule would assist 
EPA in regulating environmental impacts, namely impingement mortality 
and entrainment, at cooling water intake structures at Phase III 
facilities and new offshore oil and gas extraction facilities. This 
information would be used by these parties to prepare comprehensive 
demonstration studies, monitor impingement mortality and entrainment, 
verify compliance, and prepare annual/biennial reports as required 
under today's proposal. The information collected would be reviewed by 
EPA and State Directors to ensure that appropriate National Pollutant 
Discharge Elimination System (NPDES) permit conditions regulating 
cooling water intake structures would be developed. Compliance with the 
applicable information collection requirements imposed under this 
proposed rule is mandatory (see Sec. Sec.  122.21(r), 125.136, 125.137, 
125.138, 125.104, 125.105, 125.106, 125.107, 125.108).
    EPA does not consider the specific data that would be collected 
under this proposed rule to be confidential business information. 
However, if a respondent does consider this information to be 
confidential, the respondent may request that such information be 
treated as confidential. All confidential data will be handled in 
accordance with 40 CFR 122.7, 40 CFR Part 2, and EPA's Security Manual 
Part III, Chapter 9, dated August 9, 1976.
    Today's proposed rule would modify regulations at Sec.  122.21 to 
require existing Phase III facilities and new offshore oil and gas 
extraction facilities to prepare and submit some of the same 
information required for Phase I and Phase II facilities. The proposed 
application requirements would require owners or operators of Phase III 
existing facilities to submit two general categories of information 
when they apply for a reissued NPDES permit. The general categories of 
information would include (1) permit application information, and (2) 
verification monitoring data. A detailed list of required data items is 
provided below.
    As discussed in section II of the preamble, EPA is proposing three 
regulatory options for existing facilities in today's proposed rule 
based on design intake flow including: (1) A 50 MGD option for 
facilities withdrawing water from all waterbody types; (2) a 200 MGD 
option for facilities withdrawing water from all waterbody types; and 
(3) a 100 MGD option for facilities which withdraw water specifically 
from an ocean, estuary, tidal river, or one of the Great Lakes. Under 
the co-proposed 50 MGD threshold-based option, the total average annual 
burden, during the first three years after promulgation of the rule, of 
the information collection requirements associated with today's 
proposed rule is estimated at 215,885 hours. The corresponding 
estimates of average annual cost other than labor (labor and non-labor 
costs are included in the total cost of the proposed rule discussed in 
section VIII of this preamble) is $2.81 million for 87 facilities (56 
existing manufacturers and 31 new offshore oil and gas facilities) and 
45 States and one Territory during the first three years after 
promulgation of the rule. Under the co-proposed 200 MGD threshold-based 
option, the total average annual burden, during the first three years 
after promulgation of the rule, of the information collection 
requirements is estimated at 62,280 hours. The corresponding average 
annual non-labor cost is $1.46 million for 44 facilities (13 existing 
manufacturers and 31 new offshore oil and gas facilities), and 45 
States and one Territory during the first three years after 
promulgation of the rule. Under the co-proposed 100 MGD threshold-based 
option, the total average annual burden, during the first three years 
after promulgation of the rule, of the information collection 
requirements is estimated at 85,622 hours. The corresponding average 
annual non-labor cost is $1.62 million for 42 facilities (11 existing 
manufacturers and 31 new offshore oil and gas facilities), and 45 
States and one Territory during the first three years after 
promulgation of the rule.
    Non-labor costs include activities such as capital costs for remote 
monitoring devices, laboratory services, photocopying, and the purchase 
of supplies. The burden and costs are for the information collection, 
reporting, and recordkeeping requirements for the three-year period 
beginning with the assumed effective date of today's rule. Additional 
information collection requirements will occur after this initial 
three-year period as existing facilities continue to be issued permit 
renewals, new offshore oil and gas extraction facilities are issued 
permits, and such requirements will be counted in a subsequent 
information collection request.
    Burden means the total time, effort, or financial resources 
expended by persons to generate, maintain, retain, or disclose or 
provide information to or for a Federal agency. This includes the time 
needed to review instructions; develop, acquire, install, and utilize 
technology and systems for the purposes of collecting, validating, and 
verifying information, processing and maintaining information, and 
disclosing and providing information; adjust the existing ways to 
comply with any previously applicable instructions and requirements; 
train personnel to be able to respond to a collection of information; 
search data sources; complete and review the collection of information; 
and transmit or otherwise disclose the information.
    Studies to be submitted by both Phase III existing facilities and 
new offshore oil and gas extraction facilities under today's proposed 
rule are listed below. Both Phase III existing facilities and

[[Page 68529]]

new offshore oil and gas fixed platforms would be required to collect 
the general information listed below.
    ? Source Water Physical Data (Sec.  122.21(r)(2)) (both 
Phase III existing facilities and new offshore oil and gas facilities)
    ? Cooling Water Intake Structure Data (Sec.  122.21(r)(3)) 
((both Phase III existing facilities and new offshore oil and gas facilities)
    ? Cooling Water System Description (Sec.  122.21(r)(5)) 
(Phase III existing facilities only)
    Depending on the compliance alternative selected by the individual 
facility, Phase III existing facilities may be required to submit the 
following information:
    ? Proposal for Information Collection (Sec.  125.104(b)(1))
    ? Source Waterbody Flow Information (Sec.  125.104(b)(2))
    ? Impingement Mortality and/or Entrainment Characterization 
Study (Sec.  125.104(b)(3))
    ? Technology Compliance and Assessment Information (Sec.  125.104(b)(4))
    ? Restoration Plan (Sec.  125.104(b)(5))
    ? Information to Support Site-specific Determination of Best 
Technology Available for Minimizing Adverse Environmental Impact (Sec.  
125.104(b)(6))
    ? Verification Monitoring Plan (Sec.  125.104(b)(7))
    New offshore oil and gas extraction facilities would be required to 
submit the following information under Track I:
    ? Source Water Baseline Biological Characterization Data 
(Sec.  122.21(r)(4)) (not required for non-fixed facilities)
    ? Velocity Information (Sec.  125.136(b)(2))
    ? Source Waterbody Flow Information (Sec.  125.136(b)(3)) 
(not required for non-fixed facilities)
    ? Design and Construction Technology Plan (Sec.  
125.136(b)(4))
    In addition to the information requirements of the permit renewal 
application, NPDES permits normally specify monitoring and reporting 
requirements to be met by the permitted entity. Existing facilities 
that fall within the scope of this proposed rule would be required to 
perform biological monitoring as required by the Director to 
demonstrate compliance. New offshore oil and gas extraction fixed 
facilities would be required to perform monitoring as determined by the 
Track I or Track II requirements in Sec.  125.136. Additional ambient 
water quality monitoring may also be required of facilities depending 
on the specifications of their permits. New offshore oil and gas 
extraction facilities would be expected to analyze the results from 
their monitoring efforts and provide these results in an annual status 
report to the permitting authority. Existing Phase III facilities would 
be required to submit a status report every two years that included 
appropriate monitoring data and any other information specified by the 
Director. Finally, facilities would be required to maintain records of 
all submitted documents, supporting materials, and monitoring results 
for at least three years. (Note that the Director may require that 
records be kept for a longer period to coincide with the life of the 
NPDES permit.)
    All impacted facilities would carry out the specific activities 
necessary to fulfill the general information collection requirements. 
The estimated burden includes developing a water balance diagram that 
can be used to identify the proportion of intake water used for 
cooling, make-up, and process water. Facilities would also gather data 
to calculate the reduction in impingement mortality and entrainment of 
all life stages of fish and shellfish that would be achieved by the 
technologies and operational measures they select. The burden estimates 
include sampling, assessing the source waterbody, estimating the 
magnitude of impingement mortality and entrainment, and reporting 
results in a comprehensive demonstration study. The burden may also 
include conducting a pilot study to evaluate the suitability of the 
technologies and operational measures based on the species that are 
found at the site.
    Some of the Phase III existing facilities (those choosing to use 
restoration measures to maintain fish and shellfish) would need to 
prepare a plan documenting the restoration measures they would 
implement and how they would demonstrate that the restoration measures 
were effective. However, for purposes of this paperwork burden 
analysis, EPA assumed all facilities would comply using design and 
construction technologies.
    Some facilities may choose to request a site-specific determination 
of best technology available because of costs significantly greater 
than those EPA considered in establishing the performance standards or 
because costs are significantly greater than the benefits of complying 
with the performance standards. These facilities would be required to 
perform a comprehensive cost evaluation study and, if applicable, a 
valuation of the monetized benefits of reducing impingement mortality 
and entrainment, as well as submitting a site-specific technology plan 
characterizing the design and construction technologies, operational 
measures and restoration measures they have selected. However, for 
purposes of this paperwork burden estimate, EPA assumed all facilities 
would comply by meeting the applicable performance standards.
    The assumption that facilities will not use restoration or request 
a site-specific determination of best technology available may lead to 
an underestimate of paperwork burden, since there are additional 
documentation requirements associated with both of these approaches. 
However, since both are optional, EPA assumes that facilities would not 
choose them unless total burden, including both paperwork burden and 
compliance costs is less than the total burden under the approach EPA 
assumed for its PRA analysis.
    Exhibits XI-1 through 3 present a summary of the average burden 
estimates for a facility to prepare a permit application and monitor 
and report on cooling water intake structure operations for the three 
options for existing manufacturers as required by this proposed rule. 
Exhibit XI-4 presents a summary of the average burden estimates for a 
facility to prepare a permit application and monitor and report on 
cooling water intake structure operations for new offshore oil and gas 
extraction facilities as required by this proposed rule. For the 
purpose of estimating the average burden for new offshore oil and gas 
extraction facilities, EPA assumed all facilities would pursue Track I 
of today's proposed rule. It is unknown how many facilities would 
select Track I versus Track II so the actual burden estimate may be 
slightly higher or lower than that presented in this section.

[[Page 68530]]

       Exhibit XI-1.--Average Annual Reporting Burden and Costs per Facility for NPDES Permit Application and Monitoring and Reporting Activities
                                                             [50 MGD all waterbodies option]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                     Annual       Annual       Annual     Annual O&M   Three year     annual      Average      Average
                   Activities                      hours per    labor cost    capital      cost per    respondent   frequency      annual    annual cost
                                                    facility       per        cost per    facility a     total          of         hours          b
                                                                 facility     facility                              responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Start-up Activities.............................           43        2,121            0           50           56           19          803       40,527
Permit Application Activities...................          247        9,951            0          510           56           19        4,611      195,279
Proposal for Collection of Information for                272       12,344            0          770           43           14        3,899      187,964
 Comprehensive Demonstration Study..............
FW River/Stream Source Water Body Flow                    100        3,381            0          200           15            5          500       17,904
 Information....................................
FW Lake/Reservoir Source Water Body Flow                  112        3,946            0          200            2            1           75        2,764
 Information....................................
Design and Construction Technology Plan                    31        1,368            0            0           31           10          320       14,132
 (Impingement)..................................
Design and Construction Technology Plan                    31        1,368            0            0           20            7          207        9,117
 (Entrainment)..................................
Design and Construction Technology Plan (All)...           30          922            0          380           33           11          330       14,322
Freshwater Baseline Monitoring for Impingement          2,210      102,549            0        1,538           23           13       29,460    1,387,834
 Mortality and/or Entrainment Study.............
Freshwater Monitoring for Impingement Mortality         1,105       51,544            0          773           23           13       14,727      697,560
 Study..........................................
Freshwater Monitoring for Entrainment Study.....          845       39,727            0       39,596            4            3        2,252      211,527
Marine Baseline Monitoring for Impingement              2,841      131,350            0        1,970           20           19       53,041    2,488,651
 Mortality and/or Entrainment Study.............
Marine Monitoring for Impingement Mortality             1,414       65,430            0          981           16           15       21,680    1,018,309
 Study..........................................
Marine Monitoring for Entrainment Study.........        1,076       50,083            0       51,451           20           19       20,090    1,895,311
Impingement Mortality & Entrainment                       373       22,042            0            0           43           14        5,346      315,931
 Characterization Study Initial Analysis........
Impingement Mortality & Entrainment                       399       18,875            0          614           33           11        4,389      214,381
 Characterization Study Final Report............
Pilot Study Impingement Monitoring (Freshwater)           661       33,927      804,252            0            1            0          220      279,393
 for Pilot Study................................
Pilot Study Entrainment Monitoring (Freshwater)           541       28,473            0        6,000            1            0          180       11,491
 for Pilot Study................................
Pilot Study Impingement Monitoring (Marine) for           831       41,572      189,062            0           10            3        2,768      768,781
 Pilot Study....................................
Pilot Study Entrainment Monitoring (Marine) for           675       34,482            0        7,800           10            3        2,248      140,941
 Pilot Study....................................
Pilot Study Entrainment Monitoring (All) for              354       17,487            0        1,020           11            4        1,298       67,858
 Pilot Study....................................
Technology Installation and Operation Plan......           52        2,372            0           80           35           12          607       28,611

[[Page 68531]]

Verification Monitoring Plan....................          128        5,918            0          410           35           12        1,493       73,827
                                                 --------------
    Total for NPDES Permit Application            ...........  ...........  ...........  ...........           56          227      170,544   10,082,416
     Activities.................................
-------------------------------------------------
                                  Average Burden and Costs per Facility for Annual Monitoring and Reporting Activities
--------------------------------------------------------------------------------------------------------------------------------------------------------
Annual Monitoring for Impingement (Freshwater)..          379       18,504            0          510           11            5        2,021      101,406
Annual Monitoring for Impingement (Marine)......          482       23,564            0          660           12            5        2,569      129,193
Annual Monitoring for Entrainment (Freshwater)..          614       30,376            0        8,310            4            2        1,228       77,371
Annual Monitoring for Entrainment (Marine)......          776       38,069            0       10,800           14            7        5,173      325,790
Biannual Status Report Activities...............          324       16,618            0          770           27            9        2,916      156,492
Verification Study..............................          118        6,772            0          510           27            9        1,062       65,540
                                                 --------------
    Total for Annual Activities.................  ...........  ...........  ...........  ...........           27           37       14,969     855,792
--------------------------------------------------------------------------------------------------------------------------------------------------------
a Cost of supplies, filing cabinets, photocopying, boat renting, etc.
b Costs for restoration activities and site-specific studies were not estimated as EPA cannot determine how many facilities would choose to select this
  option and the option is voluntary.


       Exhibit XI-2.--Average Annual Reporting Burden and Costs per Facility for NPDES Permit Application and Monitoring and Reporting Activities
                                                            [200 MGD all waterbodies option]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                     Annual       Annual       Annual     Annual O&M   Three year     annual      Average
                    Activity                       hours per    labor cost    capital      cost per    respondent   frequency      annual      Average
                                                    facility       per        cost per    facilitya      total          of         hours     annual cost
                                                                 facility     facility                              responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Start-up Activities.............................           43       $2,121           $0          $50           13            4          186       $9,408
Permit Application Activities...................          247        9,951            0          510           13            4        1,070       45,333
Proposal for Collection of Information for                272       12,344            0          770            9            3          816       39,341
 Comprehensive Demonstration Study..............
FW River/Stream Source Water Body Flow                    100        3,381            0          200            1            0           33        1,194
 Information....................................
FW Lake/Reservoir Source Water Body Flow          ...........            0            0          200  ...........            0            0            0
 Information....................................
Design and Construction Technology Plan                    31        1,368            0            0            5            2           52        2,279
 (Impingement)..................................
Design and Construction Technology Plan                    31        1,368            0            0            4            1           41        1,823
 (Entrainment)..................................
Design and Construction Technology Plan (All)...           30          922            0          380            5            2           50        2,170
Freshwater Baseline Monitoring for Impingement          2,210      102,549            0        1,538            2            1        2,210      104,088
 Mortality and/or Entrainment Study.............
Freshwater Monitoring for Impingement Mortality         1,105       51,544            0          773            2            1        1,105       52,317
 Study..........................................
Freshwater Monitoring for Entrainment Study.....  ...........            0            0       39,596  ...........            0            0            0

[[Page 68532]]

Marine Baseline Monitoring for Impingement              2,841      131,350            0        1,970            7            6       17,049      799,923
 Mortality and/or Entrainment Study.............
Marine Monitoring for Impingement Mortality             1,414       65,430            0          981            6            5        7,541      354,194
 Study..........................................
Marine Monitoring for Entrainment Study.........        1,076       50,083            0       51,451            7            6        6,458      609,207
Impingement Mortality & Entrainment                       373       22,042            0            0            9            3        1,119       66,125
 Characterization Study Initial Analysis........
Impingement Mortality & Entrainment                       399       18,875            0          614            5            2          665       32,482
 Characterization Study Final Report............
Pilot Study Impingement Monitoring (Freshwater)           661       33,927      804,252            0            1            0          220      279,393
 for Pilot Study................................
Pilot Study Entrainment Monitoring (Freshwater)           541       28,473            0        6,000            1            0          180       11,491
 for Pilot Study................................
Pilot Study Impingement Monitoring (Marine) for           831       41,572      183,241            0            4            1        1,107      299,751
 Pilot Study....................................
Pilot Study Entrainment Monitoring (Marine) for           675       34,482            0        7,800            4            1          899       56,376
 Pilot Study....................................
Pilot Study Entrainment Monitoring (All) for              354       17,487            0        1,020            5            2          590       30,845
 Pilot Study....................................
Technology Installation and Operation Plan......           52        2,372            0           80            6            2          104        4,905
Verification Monitoring Plan....................          128        5,918            0          410            6            2          256       12,656
                                                 --------------
    Total for NPDES Permit Application            ...........  ...........  ...........  ...........           13           50       41,752    2,815,302
     Activities.................................
-------------------------------------------------
                                  Average Burden and Costs per Facility for Annual Monitoring and Reporting Activities
--------------------------------------------------------------------------------------------------------------------------------------------------------
Annual Monitoring for Impingement (Freshwater)..          379       18,504            0          510            1            1          253       12,676
Annual Monitoring for Impingement (Marine)......          482       23,564            0          660            3            1          482       24,224
Annual Monitoring for Entrainment (Freshwater)..          614       30,376            0        8,310            1            0          205       12,895
Annual Monitoring for Entrainment (Marine)......          776       38,069            0       10,800            3            1          776       48,869
Biannual Status Report Activities...............          324       16,618            0          770            5            2          540       28,980
Verification Study..............................          118        6,772            0          510            5            2          197       12,137
                                                 --------------
    Total for Annual Activities.................  ...........  ...........  ...........  ...........            5            7        2,452     139,780
--------------------------------------------------------------------------------------------------------------------------------------------------------
a Cost of supplies, filing cabinets, photocopying, boat renting, etc.

[[Page 68533]]

       Exhibit XI-3.--Average Annual Reporting Burden and Costs per Facility for NPDES Permit Application and Monitoring and Reporting Activities
                                                          [100 MGD certain waterbodies option]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                     Annual       Annual       Annual     Annual O&M   Three year     annual       Aveage
                    Activity                       hours per    labor cost    capital      cost per    respondent   frequency      annual      Average
                                                    facility       per        cost per     facility      total          of         hours     annual cost
                                                                 facility     facility       \a\                    responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Start-up Activities.............................           43       $2,121           $0          $50           11            4          158       $7,961
Permit Application Activities...................          247        9,951            0          510           11            4          906       38,358
Proposal for Collection of Information for                272       12,344            0          770           11            4          997       48,084
 Comprehensive Demonstration Study..............
FW River/Stream Source Water Body Flow                     --            0            0            0           --            0            0            0
 Information....................................
FW Lake/Reservoir Source Water Body Flow                   --            0            0            0           --            0            0            0
 Information....................................
Design and Construction Technology Plan                    31        1,368            0            0            8            3           83        3,647
 (Impingement)..................................
Design and Construction Technology Plan                    31        1,368            0            0            8            3           83        3,647
 (Entrainment)..................................
Design and Construction Technology Plan (All)...           30          922            0          380            8            3           80        3,472
Freshwater Baseline Monitoring for Impingement             --            0            0        1,538           --            0            0            0
 Mortality and/or Entrainment Study.............
Freshwater Monitoring for Impingement Mortality            --            0            0          773           --            0            0            0
 Study..........................................
Freshwater Monitoring for Entrainment Study.....           --            0            0      039,596           --            0            0            0
Marine Baseline Monitoring for Impingement              2,841      131,350            0        1,970           11           10       28,415    1,333,206
 Mortality and/or Entrainment Study.............
Marine Monitoring for Impingement Mortality             1,414       65,430            0          981           10            9      13,1976       19,840
 Study..........................................
Marine Monitoring for Entrainment Study.........        1,076       50,083            0      051,451           11           10       10,763    1,015,345
Impingement Mortality & Entrainment                       373       22,042            0            0           11            4        1,368       80,820
 Characterization Study Initial Analysis........
Impingement Mortality & Entrainment                       399       18,875            0          614            8            3        1,064       51,971
 Characterization Study Final Report............
Pilot Study Impingement Monitoring (Freshwater)            --            0            0            0           --            0            0            0
 for Pilot Study................................
Pilot Study Entrainment Monitoring (Freshwater)            --            0            0        6,000           --            0            0            0
 for Pilot Study................................
Pilot Study Impingement Monitoring (Marine) for           831       41,572      221,548            0            6            2        1,661      526,240
 Pilot Study....................................
Pilot Study Entrainment Monitoring (Marine) for           675       34,482            0        7,800            6            2        1,349       84,564
 Pilot Study....................................
Pilot Study Entrainment Monitoring (All) for              354       17,487            0        1,020            6            2          708       37,014
 Pilot Study....................................
Technology Installation and Operation Plan......           52        2,372            0           80            8            3          139        6,540

[[Page 68534]]

Verification Monitoring Plan....................          128        5,918            0          410            8            3          341       16,875
                                                 --------------
    Total for NPDES Permit Application            ...........  ...........  ...........  ...........           11           66       61,310    3,877,583
     Activities.................................
-------------------------------------------------
                                  Average Burden and Costs per Facility for Annual Monitoring and Reporting Activities
--------------------------------------------------------------------------------------------------------------------------------------------------------
Annual Monitoring for Impingement (Freshwater)..           --            0            0          510           --            0            0            0

Annual Monitoring for Impingement (Marine)......          482       23,564            0          660            7            3        1,284       64,596
Annual Monitoring for Entrainment (Freshwater)..           --            0            0        8,310           --            0            0            0
Annual Monitoring for Entrainment (Marine)......          776       38,069            0       10,800            7            3        2,069      130,316
Biannual Status Report Activities...............          324       16,618            0          770            7            2          756       40,572
Verification Study..............................          118        6,772            0          510            7            2          275       16,992
                                                 --------------
    Total for Annual Activities.................  ...........  ...........  ...........  ...........            7           10        4,385     252,476
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ Cost of supplies, filing cabinets, photocopying, boat renting, etc.


       Exhibit XI-4.--Average Annual Reporting Burden and Costs per Facility for NPDES Permit Application and Monitoring and Reporting Activities
                                                  [New offshore oil and gas extraction facilities \a\]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                     Annual       Annual    Annuallized   Annual O&M   Three year     annual      Average
                    Activity                       hours per    labor cost    capital      cost per    respondent   frequency      annual      Average
                                                    facility       per        cost per   facilitya b     total          of         hours     annual cost
                                                                 facility     facility                              responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Start-up Activities.............................           43       $2,121           $0          $50           31           10          444      $22,435
Permit Application Activities...................           25          795            0          130           19            6          158        5,857
Source Water Body Flow Information..............           38        1,341            0           75           19            6          241        8,968
CWIS Velocity Information.......................           --            0            0            0           --            0            0            0
Design and Construction Technology Plan                    35        1,021            0          120           15            5          175        5,706
 (Impingement Only).............................
Design and Construction Technology Plan                    35        1,021            0          120            1            0           12          380
 (Entrainment Only).............................
Design and Construction Technology Plan                    38        1,162            0          120            3            1           38        1,282
 (Impingement & Entrainment)....................
Develop Regional Study Design and Submit to                78        5,007            0            0            2            1           52        3,338
 Director.......................................
Deep Water Baseline Monitoring for Source Water           309       17,260            0       43,200            9            9        2,778      544,137
 Baseline Biological Characterization Study.....
Deep Water Impingement Monitoring for Source              144        7,987        7,621          667            9            9        1,296      146,473
 Water Baseline Biological Characterization
 Study..........................................

[[Page 68535]]

Deep Water Entrainment Monitoring for Source              144        7,987            0        3,120            3            3          432       33,321
 Water Baseline Biological Characterization
 Study..........................................
Alaska Basline Monitoring for Source Water                384       20,337            0       49,200            1            1          384       69,537
 Baseline Biological Characterization Study.....
Alaska Entrainment Monitoring for Source Water            192       10,169            0        3,120            1            1          192       13,289
 Baseline Biological Characterization Study.....
Initial Sourcewater Baseline Biological                   366       20,584            0            0           10            3        1,220       68,613
 Characterization Data..........................
Sourcewater Baseline Biological Characterization          288       18,389            0            0            2            1          192       12,259
 Data Study Final Regional Report...............
Use Regional Study Results for Individual                 166        7,591            0            0           19            6        1,051       48,079
 Facility Studies...............................
Source Water Baseline Biological                           --            0            0       13,270            9            3            0       39,810
 Characterization Study Other Direct Costs for
 Deep Water.....................................
Source Water Baseline Biological                           --            0            0       19,910            1            0            0        6,637
 Characterization Study Other Direct Costs for
 Alaska.........................................
                                                 --------------
    Total for NPDES Permit Application            ...........  ...........  ...........  ...........           31           67        8,665    1,030,123
     Activities.................................
-------------------------------------------------
                                  Average Burden and Costs per Facility for Annual Monitoring and Reporting Activities
--------------------------------------------------------------------------------------------------------------------------------------------------------
Biological Monitoring for Impingement...........          530       25,823            0        1,660           --            0            0            0
Biological Monitoring for Entrainment...........          370       17,647            0       15,780           --            0            0            0
Biological Monitoring for Entrainment (Alaska)..          516       24,298            0       21,780           --            0            0            0
Velocity Monitoring.............................          163        5,692            0          500           13            7        1,087       41,283
Yearly Status Report Activities.................          223       11,304            0          770           13            7        1,487       80,495
                                                 --------------
    Total for Annual Activities.................  ...........  ...........  ...........  ...........           13           14        2,573     121,778
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ Track I requirements only estimated.
\b\ Cost of supplies, filing cabinets, photocopying, boat renting, etc.

    EPA believes that all 45 States and one Territory with NPDES 
permitting authority would undergo start-up activities in preparation 
for administering the provisions of the proposed rule. As part of these 
start-up activities, States and Territories would be expected to train 
junior technical staff to review materials submitted by facilities, and 
then use these materials to evaluate compliance with the specific 
conditions of each facility's NPDES permit.
    Each State's/Territory's actual burden associated with reviewing 
submitted materials, writing permits, and tracking compliance would 
depend on the number of in-scope facilities that would come up for 
permit renewal in the State/Territory during the ICR approval period 
and which flow threshold-based option EPA selects for Phase III 
existing facilities. EPA expects that State and Territory technical and 
clerical staff will spend time gathering, preparing, and submitting the 
various documents. EPA's burden estimates reflect the general staffing 
and level of expertise that is typical in States/Territories that 
administer the NPDES permitting program. EPA considered the time and 
qualifications necessary to complete various tasks such as reviewing

[[Page 68536]]

submitted documents and supporting materials, verifying data sources, 
planning responses, determining specific permit requirements, writing 
the actual permit, and conferring with facilities and the interested 
public. Exhibits XI-5 through 7 provide a summary of the average burden 
estimates for States/Territories performing various activities for 
existing manufacturing facilities required by the proposed rule. 
States/Territories are not involved in administering the permits for 
new offshore oil and gas extraction facilities since the offshore oil 
and gas industry is currently permitted under general permits at the 
regional EPA level. This practice is likely to continue in the 
forseeable future.

                                    Exhibit XI-5.--Estimating State/Territory Average Burden and Costs for Activities
                                                             [50 MGD all waterbodies option]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                    Average       Annual       Annual     Annual O&M   Three year     annual      Average
                    Activity                         annual     labor cost    capital      cost per    respondent   frequency      annual      Average
                                                   hours per       per        cost per     facility      total          of         hours     annual cost
                                                    facility     facility     facility       \a\                    responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Director Start-up Activities....................          100       $3,894           $0          $50           46           15        1,533      $60,475
Director Permit Issuance Activities.............          803       35,979            0          310           56           19       14,989      677,398
Verification Study Review.......................           --            0            0           10           --            0            0            0
Annual Director Activities......................           50        1,851            0           30           27            9          450       16,932
                                                 --------------
    Total for Director Activities...............  ...........  ...........  ...........  ...........           46           43       16,972      754,804
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ Cost of supplies, filing cabinets, photocopying, boat renting, etc.


                                    Exhibit XI-6.--Estimating State/Territory Average Burden and Costs for Activities
                                                            [200 MGD all waterbodies option]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                    Average       Annual       Annual     Annual O&M   Three year     annual      Average
                    Activity                         annual     labor cost    capital      cost per    respondent   frequency      annual      Average
                                                   hours per       per        cost per     facility      total          of         hours     annual cost
                                                    facility     facility     facility       \a\                    responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Director Start-up Activities....................          100       $3,894           $0          $50           46           15        1,533      $60,475
Director Permit Issuance Activities.............          706       31,417            0          310           13  ...........       43,060      137,482
Verification Study Review.......................           --            0            0           10           --            0            0            0
Annual Director Activities......................           50        1,851            0           30            5            2           83        3,136
                                                 --------------
    Total for Director Activities...............  ...........  ...........  ...........  ...........           46           21        4,677      201,092
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ Cost of supplies, filing cabinets, photocopying, boat renting, etc.


                                    Exhibit XI-7.--Estimating State/Territory Average Burden and Costs for Activities
                                                            [100 MGD All Waterbodies Option]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Average
                                                    Average       Annual       Annual     Annual O&M   Three year     annual      Average
                    Activity                         annual     labor cost    capital      cost per    respondent   frequency      annual      Average
                                                   hours per       per        cost per     facility      total          of         hours     annual cost
                                                    facility     facility     facility       \a\                    responses
--------------------------------------------------------------------------------------------------------------------------------------------------------
Director Start-up Activities....................          100       $3,894           $0          $50           46           15        1,533      $60,475
Director Permit Issuance Activities.............         1330       60,163            0          310           11            4        4,878      221,733
Verification Study Review.......................           --            0            0           10           --            0            0            0
Annual Director Activities......................           50        1,851            0           30            7            2          117        4,390
                                                 --------------
    Total for Director Activities...............  ...........  ...........  ...........  ...........           46           21        6,528      286,598
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ Cost of supplies, filing cabinets, photocopying, boat renting, etc.

    An Agency may not conduct or sponsor, and a person is not required 
to respond to a collection of information unless it displays a 
currently valid OMB control number. The OMB control numbers for EPA's 
regulations in 40 CFR are listed in 40 CFR Part 9.
    To comment on the Agency's need for this information, the accuracy 
of the provided burden estimates, and any suggested methods for 
minimizing respondent burden, including the use of automated collection 
techniques, EPA has established a public docket for this rule, which 
includes this ICR, under Docket ID number OW-2003-0005. Submit any 
comments related to the ICR for this proposed rule to EPA and OMB. See 
``Addresses'' section at the beginning of this notice for where to 
submit comments to EPA. Send comments to OMB at the Office of 
Information and Regulatory Affairs,

[[Page 68537]]

Office of Management and Budget, 725 17th Street, NW., Washington, DC 
20503, Attention: Desk Office for EPA. Since OMB is required to make a 
decision concerning the ICR between 30 and 60 days after November 24, 
2004, a comment to OMB is best assured of having its full effect if OMB 
receives it by December 27, 2004. The final rule will respond to any 
OMB or public comments on the information collection requirements 
contained in this proposal.

C. Regulatory Flexibility Act

    The Regulatory Flexibility Act (RFA) as amended by the Small 
Business Regulatory Flexibility Act generally requires an agency to 
prepare a regulatory flexibility analysis of any rule subject to notice 
and comment rulemaking requirements under the Administrative Procedure 
Act or any other statute unless the agency certifies that the rule will 
not have a significant economic impact on a substantial number of small 
entities. This section summarizes EPA's analyses in compliance with the 
RFA.
1. Definition of Small Entity
    Small entities include small businesses, small organizations, and 
small governmental jurisdictions. For assessing the impacts of today's 
proposal on small entities, a small entity is defined as: (1) A small 
business as defined by the Small Business Administration's (SBA) 
regulations at 13 CFR 121.201; (2) a small governmental jurisdiction 
that is a government of a city, county, town, school district or 
special district with a population of less than 50,000; and (3) a small 
organization that is any not-for-profit enterprise which is 
independently owned and operated and is not dominant in its field.
    The SBA small business size standards changed from a SIC code-based 
system to a NAICS code-based system on October 1, 2000. Since EPA 
conducted its data collection effort for existing facilities before 
this change, EPA performed the small entity analysis for existing 
facilities based on SIC codes. EPA then conducted a subsequent analysis 
to determine if the size standards based on NAICS codes would have any 
effect on the results of the small entity analysis. This analysis 
showed that for the three co-proposed options, there would be no 
changes to the small entity determination, and therefore to small 
entity impacts, as a result of switching from SIC-based size standards 
to NAICS-based size standards.
2. Certification Statement
    After considering the economic impacts of today's proposal on small 
entities, I certify that this action will not have a significant 
economic impact on a substantial number of small entities. This 
proposal applies to existing facilities that employ a cooling water 
intake structure and are designed to withdraw either (1) 50 MGD or more 
from all waterbodies, (2) 100 MGD or more from certain waterbodies, or 
(3) 200 MGD or more from all waterbodies that are waters of the United 
States. It also applies to new offshore oil and gas extraction 
facilities that withdraw greater than 2 MGD from waters of the United 
States.
3. Statement of Basis
    EPA estimates that this proposal will not apply national 
categorical standards to any small entities in the Manufacturers or 
Electric Generators industry segments (entities that operate facilities 
subject to permitting based on best professional judgement are excluded 
from this analysis). In the new offshore oil and gas extraction 
industry segment, EPA estimates that the proposed option will apply 
national standards to only one small entity, a new offshore oil and gas 
platform. EPA estimates that this entity would incur annualized, after-
tax compliance costs of less than 0.1 percent of annual revenue. EPA 
does not know precisely which firms would be undertaking construction 
of new offshore oil and gas extraction facilities. However, based on 
the firms that are currently active in building the types of facilities 
representative of those covered by the rulemaking, EPA believes that 
the small firm analyzed represents the smallest firm that would be 
involved in such activities over the period of the analysis.
4. Summary of Small Business Advocacy Review Panel
    Although the RFA does not require a Small Business Advocacy Review 
(SBAR) Panel for this rule (because EPA has determined that this 
proposal would not have a significant economic impact on a substantial 
number of small entities), EPA convened a panel to obtain advice and 
recommendations from small entity representatives (SERs) potentially 
subject to this proposed rule's requirements because at the time EPA 
had not yet determined the scope of the proposed rule and thus the 
potential for small entity impacts. This section summarizes EPA's small 
entity outreach and information on the composition, process, and 
findings of the SBAR panel.
a. Summary of Small Entity Outreach
    EPA actively involved stakeholders, including small entities, in 
the development of the proposed rule in order to ensure the quality of 
information, identify and understand potential implementation and 
compliance issues, and explore regulatory alternatives. EPA conducted 
numerous meetings with the electric power industry over the past six 
years and met twice with manufacturing industry representatives in the 
past two years; during these meetings, EPA received direct input about 
the impacts of the proposed rule on the industry.
    In the past three years, EPA held two conference calls with small 
entity representatives from the manufacturing and electric power 
industries to improve the Agency's understanding of cooling water 
intakes in these industries, and of the potential impacts of new 
requirements from an economic and business perspective. Before 
convening the Panel, EPA held a conference call/meeting on October 1, 
2002, and another on January 22, 2004, to receive information from 
prospective SERs about plans for convening the Panel and their early 
concerns about the planned proposed regulation.
b. Panel Members
    The Panel consisted of EPA's Small Business Advocacy Chairperson, 
the Director of the Engineering and Analysis Division of the Office of 
Science and Technology (EPA/OW), the Administrator of the Office of 
Information and Regulatory Affairs within the Office of Management and 
Budget (OMB), and the Chief Counsel for Advocacy of the Small Business 
Administration (SBA).
c. SERs
    After consultation with the Small Business Administration Office of 
Advocacy, EPA invited six municipal power plant representatives and six 
representatives from manufacturing industries to serve as potential 
SERs during the pre-panel outreach process. Ultimately, three municipal 
power plant representatives and four representatives from manufacturing 
industries provided comments to the Panel.
d. Summary of Panel Process
    The Panel convened on February 27, 2004. The Panel held an outreach 
meeting and telephone conference for SERs on March 16, 2004. Materials 
were provided to SERs in advance of the meeting and additional 
materials on specific topics of interest to SERs were provided during 
the Panel process. SERs provided comments to the Panel on (1)

[[Page 68538]]

the number and types of small entities affected; (2) potential 
reporting, record keeping, and compliance requirements; (3) related 
Federal rules; (4) regulatory flexibility alternatives; and (5) 
methodological issues.
    The Panel evaluated the assembled materials and small entity 
comments on issues related to the elements of the initial regulatory 
flexibility analysis (IRFA). A copy of the Panel report, ``Final Report 
of the Small Business Advocacy Review Panel on EPA's Planned Proposed 
Rule for Cooling Water Intake Structures at Section 316(b) Phase III 
Facilities,'' is included in the docket for this proposed rule (DCN 7-
0006).
e. Panel Recommendations
    The Panel provided several recommendations pertaining to reporting, 
record keeping, and compliance requirements; regulatory flexibility 
alternatives; and methodological issues relevant to the assessment of 
the impacts of a Phase III rule on small entities. The following is a 
summary of the Panel's recommendations and EPA's responses:
    ? Recommendation: The Panel noted that significant 
implementation flexibility was included in the Phase II rule. For 
example, facilities were allowed up to three and one half years 
following rule promulgation to submit their initial demonstration study 
and related application materials. The Panel recommended that this 
level of flexibility be provided for Phase III requirements. The Panel 
also recommended that EPA consider the availability of contractor 
resources as it develops the implementation schedule for Phase III.
    Response: EPA has provided in the proposed rule the same 
implementation flexibility contained in the Phase II rule. EPA will 
consider the availability of contractor resources and would like to 
receive comments on this issue.
    ? Recommendation: The Panel recommended that EPA analyze a 
range of potential applicability thresholds, particularly those between 
20 MGD and 50 MGD. The Panel believed that an effective way to 
substantially reduce potential economic impacts on small entities would 
be to set an applicability threshold of 20 MGD. Facilities below 20 MGD 
represent a small proportion of the total flow associated with the 
Phase III rulemaking.
    Response: In response to the Panel's recommendations, EPA analyzed 
several policy options with different regulatory requirements and 
applicability thresholds based on flow range categories. As a result of 
these analyses, EPA is co-proposing three options with minimum 
applicability thresholds of 50 MGD, 100 MGD, and 200 MGD, respectively. 
Under these thresholds, no Phase III existing facilities owned by small 
entities would be subject to national categorical requirements.
    ? Recommendation: The Panel recognized the implementation 
challenges associated with using actual flows instead of design flows 
to structure regulatory requirements. However, the Panel believed that 
this approach merits further consideration.
    Response: EPA notes that since the proposed thresholds exclude 
existing small entities, no implementation challenges to small entities 
would result. With regard to facilities within the scope of the 
proposed rule, EPA believes that it would be most appropriate to be 
consistent with the regulatory approach taken in Phase II.
    ? Recommendation: The American Public Power Association 
(APPA) raised several methodological issues regarding EPA's analysis of 
the impacts of a Phase III rule on small entities, including alternate 
estimates of the number of regulated small electric utilities and 
issues concerning the downtime required for retrofitting. The Panel 
recommended that EPA seek further information from APPA to identify any 
necessary modifications to the assumptions used for its cost and 
economic impact analyses. The Panel also recommended that EPA review 
its assumptions used to develop costs and economic impacts to ensure 
that these assumptions are appropriate for facilities with smaller 
budgets and staffs.
    Response: Because of the choice EPA made to propose larger design 
intake flow thresholds (i.e., 50 MGD, 100 MGD, and 200 MGD), all 
electric power producers not covered by Phase II will be exempt from 
the national categorical requirements of this proposed rule, but will 
continue to be subject to site-specific 316(b) requirements based on 
the best professional judgment of the permit writer.
5. Small Entity Flexibility Analysis
    Despite the determination that this rule would not have a 
significant economic impact on a substantial number of small entities, 
EPA prepared a Small Entity Flexibility Analysis that has all the 
components of an Initial Regulatory Flexibility Analysis (IRFA). An 
IRFA examines the impact of a proposed rule on small entities along 
with regulatory alternatives that could reduce that impact. The Small 
Entity Flexibility Analysis (which is described in detail in the 
Economic Analysis document) is available for review in the docket.
    Under the three co-proposed options, EPA estimates that only one 
small entity (a new offshore oil and gas extraction facility) would be 
subject to the national categorical requirements. Under these 
thresholds, no Phase III existing facilities owned by small entities 
would be subject to national categorical requirements. This facility is 
estimated to have a cost-to-revenue ratio of less than 0.1 percent.
    EPA continues to be interested in the potential impacts of this 
proposal on small entities and welcomes comments on issues related to 
such impacts.

D. Unfunded Mandates Reform Act

    Title II of the Unfunded Mandates Reform Act of 1995 (UMRA), Pub. 
L. 104-4, establishes requirements for Federal agencies to assess the 
effects of their regulatory actions on State, local, and Tribal 
governments and the private sector. Under section 202 of the UMRA, EPA 
generally must prepare a written statement, including a cost-benefit 
analysis, for proposed and final rules with ``Federal mandates'' that 
may result in expenditures to State, local, and Tribal governments, in 
the aggregate, or to the private sector, of $100 million or more in any 
one year. Before promulgating an EPA rule for which a written statement 
is needed, section 205 of the UMRA generally requires EPA to identify 
and consider a reasonable number of regulatory alternatives and adopt 
the least costly, most cost-effective, or least burdensome alternative 
that achieves the objectives of the rule. The provisions of section 205 
do not apply when they are inconsistent with applicable law. Moreover, 
section 205 allows EPA to adopt an alternative other than the least 
costly, most cost-effective, or least burdensome alternative if the 
Administrator publishes with the final rule an explanation why that 
alternative was not adopted. Before EPA establishes any regulatory 
requirements that may significantly or uniquely affect small 
governments, including Tribal governments, it must have developed under 
section 203 of the UMRA, a small government agency plan. The plan must 
provide for notifying potentially affected small governments, enabling 
officials of affected small governments to have meaningful and timely 
input in the development of EPA regulatory proposals with significant 
intergovernmental mandates, and informing, educating, and advising 
small governments on compliance with regulatory requirements.

[[Page 68539]]

    The following subsections present a brief summary of UMRA 
considerations for the proposed rule. Each subsection includes the 
results of the proposed option for new offshore oil and gas extraction 
facilities together with one of the three co-proposed options for 
existing facilities.\57\
---------------------------------------------------------------------------

    \57\ These sections exclude facilities estimated to be baseline 
closures and their costs (see discussion in section VIII.B.2) and 
administrative costs for Federal agencies.
---------------------------------------------------------------------------

    ? 2 MGD Option for new facilities and 50 MGD All Waterbodies 
Option for existing facilities: EPA estimates the total annualized 
after-tax costs of compliance to be $44.8 million (2003$). All of these 
direct facility costs are incurred by the private sector (including 136 
manufacturing facilities and 124 offshore oil and gas extraction 
facilities). No facility owned by State or local governments is subject 
to the national requirements under this proposed option. Additionally, 
State and local permitting authorities are estimated to incur $0.5 
million annually to administer this option, including labor costs to 
write permits and to conduct compliance monitoring and enforcement 
activities. As required per section 202 of the UMRA, EPA estimates that 
the highest undiscounted after-tax cost incurred by the private sector 
in any one year is approximately $280 million in 2011.
    ? 2 MGD Option for new facilities and 200 MGD All 
Waterbodies Option for existing facilities: EPA estimates the total 
annualized after-tax costs of compliance to be $21.4 million (2003$). 
All of these direct facility costs are incurred by the private sector 
(including 25 manufacturing facilities and 124 offshore oil and gas 
extraction facilities). No facility owned by State or local governments 
is subject to the national requirements under this proposed option. 
Additionally, State and local permitting authorities are estimated to 
incur $0.1 million annually to administer this option, including labor 
costs to write permits and to conduct compliance monitoring and 
enforcement activities. As required per section 202 of the UMRA, EPA 
estimates that the highest undiscounted after-tax cost incurred by the 
private sector in any one year is approximately $91 million in 2010.
    ? 2 MGD Option for new facilities and 100 MGD for Certain 
Waterbodies Option for existing facilities: EPA estimates the total 
annualized after-tax costs of compliance to be $17.4 million (2003$). 
All of these direct facility costs are incurred by the private sector 
(including 19 manufacturing facilities and 124 offshore oil and gas 
extraction facilities). No facility owned by State or local governments 
is subject to the national requirements under this proposed option. 
Additionally, State and local permitting authorities are estimated to 
incur $0.1 million annually to administer this option, including labor 
costs to write permits and to conduct compliance monitoring and 
enforcement activities. As required per section 202 of the UMRA, EPA 
estimates that the highest undiscounted after-tax cost incurred by the 
private sector in any one year is approximately $236 million in 2011.
    Thus, EPA has determined that this proposal contains a Federal 
mandate that may result in expenditures of $100 million or more for 
State, local, and Tribal governments, in the aggregate, or the private 
sector in any one year. Accordingly, EPA prepared a written statement 
under section 202 of the UMRA, which is summarized below. (See Economic 
Analysis, Chapter D2: UMRA Analysis, for more detailed information.)
1. Summary of Written Statement
a. Authorizing Legislation
    This proposal is issued under the authority of sections 101, 301, 
304, 306, 308, 316, 401, 402, 501, and 510 of the Clean Water Act 
(CWA), 33 U.S.C. 1251, 1311, 1314, 1316, 1318, 1326, 1341, 1342, 1361, 
and 1370. This proposal fulfills an obligation of the U.S. 
Environmental Protection Agency (EPA) under a consent decree in 
Riverkeeper, Inc. et al. v. Leavitt, United States District Court, 
Southern District of New York, No. 93 Civ. 0314 (AGS). See section II 
of this preamble for detailed information on the legal authority of 
this regulation.
b. Cost-Benefit Analysis
    For the analysis of costs and benefits to society of this proposal, 
the Agency calculated a total present value of estimated costs and 
benefits and then calculated the constant annual equivalent value 
(annualized value) of these present values. The Agency calculated these 
present values and annualized values using two social discount rate 
values: 3 percent and 7 percent. Since benefits for new offshore oil 
and gas extraction facilities could not be estimated, EPA's comparison 
of costs and benefits includes only costs associated with Phase III 
existing facilities (i.e., the Manufacturers industry segments--no 
Electric Generators are subject to the national requirements under any 
of the co-proposed options).\58\ Benefit-cost relationships for Phase 
III existing facilities under the three co-proposed options are as 
follows:\59\
---------------------------------------------------------------------------

    \58\ Total social costs of this proposal, including existing and 
new facilities, are presented in section VIII.C of this preamble.
    \59\ Benefits include only use benefits from commercial and 
recreational fishing. EPA was unable to monetize non-use benefits.
---------------------------------------------------------------------------

    ? 50 MGD All Waterbodies Option: Total annualized social 
costs are estimated at $47.3 (3 percent discount rate) and $50.1 
million (7 percent discount rate). Total mean value of annualized use 
benefits are estimated at $1.9 million (3 percent discount rate) and 
$1.5 million (7 percent discount rate). Thus, social costs exceed total 
use benefits by $45.4 million (3 percent discount rate) and $48.6 
million (7 percent discount rate).
    ? 200 MGD All Waterbodies Option: Total annualized social 
costs are estimated at $22.8 (3 percent discount rate) and $24.1 
million (7 percent discount rate). Total mean value of annualized use 
benefits are estimated at $1.3 million (3 percent discount rate) and 
$1.0 million (7 percent discount rate). Thus, social costs exceed total 
use benefits by $21.5 million (3 percent discount rate) and $23.1 
million (7 percent discount rate)
    ? 100 MGD for Certain Waterbodies Option: Total annualized 
social costs are estimated at $17.6 (3 percent discount rate) and $18.3 
million (7 percent discount rate). Total mean value of annualized use 
benefits are estimated at $1.4 million (3 percent discount rate) and 
$1.1 million (7 percent discount rate). Thus, social costs exceed total 
use benefits by $16.2 million (3 percent discount rate) and $17.2 
million (7 percent discount rate).
    It should be noted that this cost-benefit analysis compares a 
relatively complete measure of social costs with an incomplete measure 
of benefits, and should be interpreted with caution. For a more 
detailed comparison of the costs and benefits of the proposed rule, 
including a qualitative discussion and ``break-even'' analysis of non-
use benefits, refer to section X of this preamble.
    EPA notes that States may be able to use existing sources of 
financial assistance to revise permits and implement the proposed 
options, when promulgated. Section 106 of the Clean Water Act 
authorizes EPA to award grants to States, Tribes, intertribal 
consortia, and interstate agencies for administering programs for the 
prevention, reduction, and elimination of water pollution. These grants 
may be used for various activities to develop

[[Page 68540]]

and carry out a water pollution control program, including permitting, 
monitoring, and enforcement. Thus, State and Tribal NPDES permit 
programs represent one type of State program that can be funded by 
section 106 grants.
c. Macro-Economic Effects
    EPA estimates that this proposal would not measurably affect the 
national economy, including productivity, economic growth, employment 
and job creation, and international competitiveness of U.S. goods and 
services. Macroeconomic effects on the economy are generally not 
considered to be measurable unless the total economic impact of a rule 
reaches at least 0.25 percent to 0.5 percent of Gross Domestic Product 
(GDP). In 2003, the Bureau of Economic Analysis reported the nominal 
U.S. GDP at $11.0 trillion. Thus, in order to be considered measurable, 
this proposal would have to generate annualized costs of at least $27 
billion to $55 billion. Since EPA estimates that total social costs 
(including existing and new facilities) under the most costly of the 
three proposed options for existing facilities, the 50 MGD All 
Waterbodies option, would be $51 million at a 3 percent discount rate 
and $53 million at a 7 percent discount rate, the Agency believes that 
this proposal would not perceptibly affect the national economy.
d. Summary of State, Local, and Tribal Government Input
    EPA consulted with State governments and representatives of local 
governments in developing the regulation. The outreach activities are 
discussed in section III of this preamble.
e. Least Burdensome Option
    EPA considered and analyzed several alternative regulatory options 
for existing facilities to determine the best technology available for 
minimizing adverse environmental impact. These regulatory options are 
discussed in section VI of this preamble. EPA is co-proposing these 
three options because they would meet the requirement of section 316(b) 
of the CWA--that the location, design, construction, and capacity of 
cooling water intake structures reflect the best technology available 
for minimizing adverse environmental impact--and because they are 
economically achievable, address a large percentage of flow (in 
combination with the Phase II rule), are highly flexible, and impact a 
minimal number of small businesses. EPA believes the three co-proposed 
options would reflect the most cost-effective and flexible approaches 
among the options considered. They regulate 74 percent (50 MGD All 
Waterbodies Option), 45 percent (200 MGD All Waterbodies Option), and 
16 percent (100 MGD for Certain Waterbodies Option), respectively, of 
total design intake flow potentially covered under Phase III, result in 
no closures, and affect only one small entity (a new offshore oil and 
gas facility). By providing five compliance alternatives, this proposal 
would offer Phase III existing facilities a high degree of flexibility 
in selecting the most cost-effective approach to meeting section 316(b) 
requirements. Under the proposal, these facilities would be able to 
demonstrate that existing flow or cooling water intake structure 
technologies fulfill section 316(b), by identifying impingement and 
entrainment design and control technologies, and/or use operational 
measures or restoration measures to fulfill the proposal's 
requirements. The proposal would also ensure that any applicable 
requirements are economically practicable through the inclusion of the 
site-specific compliance alternative at Sec.  125.103(a)(5). EPA 
further notes that the compliance alternative specified in Sec.  
125.103(a)(4) and 125.108(a) and (b) would be included in part to 
provide additional flexibility to Phase III existing facilities, as 
well as to reduce the burden of determining, implementing, and 
administering section 316(b) requirements among all relevant parties. 
Finally, the Agency believes that the three co-proposed options would 
extend additional flexibility to States by providing that where a State 
has adopted alternative regulatory requirements that achieve 
environmental performance comparable to that required under the rule, 
the Administrator would approve such alternative requirements.
2. Impact on Small Governments
    EPA has determined that this proposal would contain no regulatory 
requirements that might significantly or uniquely affect small 
governments. No government-owned facility would be subject to the 
national categorical requirements of the three co-proposed options.

E. Executive Order 13132: Federalism

    Executive Order 13132 (64 FR 43255, August 10, 1999) requires EPA 
to develop an accountable process to ensure ``meaningful and timely 
input by State and local officials in the development of regulatory 
policies that have federalism implications.'' ``Policies that have 
federalism implications'' are defined in the Executive Order to include 
regulations that have ``substantial direct effects on the States, on 
the relationship between the national government and the States, or on 
the distribution of power and responsibilities among the various levels 
of government.''
    Under section 6 of Executive Order 13132, EPA may not issue a 
regulation that has federalism implications, that imposes substantial 
direct compliance costs, and that is not required by statute unless the 
Federal government provides the funds necessary to pay the direct 
compliance costs incurred by State and local governments or EPA 
consults with State and local officials early in the process of 
developing the proposed regulation. EPA also may not issue a regulation 
that has federalism implications and that preempts State law, unless 
the Agency consults with State and local officials early in the process 
of developing the proposed regulation.
    This proposed rule would not have federalism implications. It would 
not have substantial direct effects on the States, on the relationship 
between the Federal government and the States, or on the distribution 
of power and responsibilities among the various levels of government, 
as specified in Executive Order 13132. Rather, this proposed rule would 
result in minimal administrative costs to States that have an 
authorized NPDES program. Under the co-proposed 50 MGD All Waterbodies 
Option, EPA expects an annual burden of 16,972 hours with an annual 
cost of $6,823 (non-labor costs) for States to collectively administer 
this proposed rule. Under the co-proposed 200 MGD All Waterbodies 
Option, EPA expects an annual burden of 4,677 hours with an annual cost 
of $2,160 (non-labor costs) for States to collectively administer this 
proposed rule. Under the co-proposed 100 MGD Certain Waterbodies 
Option, EPA expects an annual burden of 6,528 hours with an annual cost 
of $1,973 (non-labor costs) for States to collectively administer this 
proposed rule. It is noted that States do not incur any burden hours 
and non-labor costs to administer the proposed rule for new offshore 
oil and gas extraction facilities since these facilities are outside of 
the jurisdiction of the States. EPA has identified zero Phase III 
existing facilities that are owned by federal, state or local 
government entities; therefore, the annual impacts on these facilities 
is zero.
    The proposed national cooling water intake structure requirements 
would be implemented through permits issued under the NPDES program. 
Forty-five

[[Page 68541]]

States and the Virgin Islands are currently authorized pursuant to 
section 402(b) of the Clean Water Act to implement the NPDES program. 
In States not authorized to implement the NPDES program, EPA issues 
NPDES permits. Under the Clean Water Act, States are not required to 
become authorized to administer the NPDES program. Rather, such 
authorization is available to States if they operate their programs in 
a manner consistent with section 402(b) and applicable regulations. 
Generally, these provisions require that State NPDES programs include 
requirements that are as stringent as Federal program requirements. 
States retain the ability to implement requirements that are broader in 
scope or more stringent than Federal requirements. (See section 510 of 
the Clean Water Act.)
    Today's proposed rule would not have substantial direct effects on 
either authorized or nonauthorized States or on local governments 
because it would not change how EPA and the States and local 
governments interact or their respective authority or responsibilities 
for implementing the NPDES program. Today's proposed rule would 
establish national requirements for Phase III facilities with cooling 
water intake structures. NPDES-authorized States that currently do not 
comply with the regulations based on today's proposal might need to 
amend their regulations or statutes to ensure that their NPDES programs 
are consistent with Federal section 316(b) requirements. See 40 CFR 
123.62(e). For purposes of this proposed rule, the relationship and 
distribution of power and responsibilities between the Federal 
government and the States and local governments are established under 
the Clean Water Act (e.g., sections 402(b) and 510); nothing in this 
proposed rule would alter that. Thus, the requirements of section 6 of 
the Executive Order do not apply to this rule.
    Although section 6 of Executive Order 13132 does not apply to this 
rule, EPA did consult with State governments and representatives of 
local governments in developing the proposed rule. During the 
development of the proposed and final Phase I and Phase II section 
316(b) rules, EPA conducted several outreach activities through which 
State and local officials were informed about this proposal and they 
provided information and comments to the Agency. The outreach 
activities were intended to provide EPA with feedback on issues such as 
adverse environmental impact, best technology available, and the 
potential cost associated with various regulatory alternatives. These 
outreach activities are discussed in section I.C of the preamble to 
today's proposed rule.
    In the spirit of this Executive Order and consistent with EPA 
policy to promote communications between EPA and State and local 
governments, EPA specifically solicits comment on this proposed rule 
from State and local officials.

F. E.O. 13175: Consultation and Coordination With Indian Tribal 
Governments

    Executive Order 13175, entitled ``Consultation and Coordination 
with Indian Tribal Governments'' (59 FR 22951, November 6, 2000), 
requires EPA to develop an accountable process to ensure ``meaningful 
and timely input by tribal officials in the development of regulatory 
policies that have tribal implications.'' ``Policies that have tribal 
implications'' is defined in the Executive Order to include regulations 
that have ``substantial direct effects on one or more Indian Tribes, on 
the relationship between the Federal government and the Indian Tribes, 
or on the distribution of power and responsibilities between the 
Federal government and Indian Tribes.''
    This proposed rule would not have tribal implications. It would not 
have substantial direct effects on tribal governments, on the 
relationship between the Federal government and Indian Tribes, or on 
the distribution of power and responsibilities between the Federal 
government and Indian Tribes, as specified in Executive Order 13175. 
EPA's analyses show that no facility subject to this proposed rule is 
owned by tribal governments. This proposed rule would not affect Tribes 
in any way in the foreseeable future. Accordingly, the requirements of 
Executive Order 13175 do not apply to this rule.

G. E.O. 13045: Protection of Children From Environmental Health Risks 
and Safety Risks

    Executive Order 13045 (62 FR 19885, April 23, 1997) applies to any 
rule that (1) is determined to be ``economically significant'' as 
defined under Executive Order 12866, and (2) concerns an environmental 
health or safety risk that EPA has reason to believe might have a 
disproportionate effect on children. If the regulatory action meets 
both criteria, the Agency must evaluate the environmental health and 
safety effects of the planned rule on children, and explain why the 
planned regulation is preferable to other potentially effective and 
reasonably feasible alternatives considered by the Agency. This 
proposed rule is not an economically significant rule as defined under 
Executive Order 12866 ($100 million threshold). Further, it does not 
concern an environmental health or safety risk that would have a 
disproportionate effect on children. Therefore, it is not subject to 
Executive Order 13045.

H. Executive Order 13211: Actions That Significantly Affect Energy 
Supply, Distribution, or Use

    This proposal is not a ``significant energy action'' as defined in 
Executive Order 13211, (``Actions Concerning Regulations That 
Significantly Affect Energy Supply, Distribution, or Use'' (66 FR 
28355, May 22, 2001)) because it is not likely to have a significant 
adverse effect on the supply, distribution, or use of energy. Based on 
our analysis (see section VIII), EPA has determined that the proposal 
contains no compliance requirements that would:
    ? Reduce crude oil supply in excess of 10,000 barrels per day;
    ? Reduce fuel production in excess of 4,000 barrels per day;
    ? Reduce coal production in excess of 5 million tons per day;
    ? Reduce electricity production in excess of 1 billion 
kilowatt hours per day or in excess of 500 megawatts of installed 
capacity;
    ? Increase energy prices in excess of 10 percent;
    ? Increase the cost of energy distribution in excess of 10 percent;
    ? Significantly increase dependence on foreign supplies of energy; or
    ? Have other similar adverse outcomes, particularly unintended ones.
    EPA analyzed the potential for impacts of the three co-proposed 
options and the proposed rule for new offshore oil and gas extraction 
facilities and found that none of them would lead to adverse outcomes. 
From these analyses, EPA concludes that this proposal would have 
minimal energy effects at a national and regional level. As a result, 
EPA did not prepare a Statement of Energy Effects. For more detail on 
the potential energy effects of this proposal, see the ``Economic 
Analysis for the Proposed Section 316(b) Rule for Phase III 
Facilities'' (DCN 7-0002). EPA requests comments on these determinations.

I. National Technology Transfer and Advancement Act

    Section 12(d) of the National Technology Transfer and Advancement 
Act (NTTAA) of 1995, Public Law 104-113, Sec. 12(d) directs EPA to use 
voluntary consensus standards in its regulatory activities unless to do 
so would be inconsistent with applicable law or otherwise impractical. 
Voluntary consensus standards are technical

[[Page 68542]]

standards (e.g., materials specifications, test methods, sampling 
procedures, and business practices) that are developed or adopted by 
voluntary consensus standard bodies. The NTTAA directs EPA to provide 
Congress, through the Office of Management and Budget (OMB), 
explanations when the Agency decides not to use available and 
applicable voluntary consensus standards.
    This proposed rule does not involve such technical standards. 
Therefore, EPA is not considering the use of any voluntary consensus 
standards. EPA welcomes comments on this aspect of the proposed rule 
and, specifically, invites the public to identify potentially 
applicable voluntary consensus standards and to explain why such 
standards should be used in this proposed rule.

J. E.O. 12898: Federal Actions To Address Environmental Justice in 
Minority Populations and Low-Income Populations

    Executive Order 12898 requires that, to the greatest extent 
practicable and permitted by law, each Federal agency must make 
achieving environmental justice part of its mission. E.O. 12898 
provides that each Federal agency must conduct its programs, policies, 
and activities that substantially affect human health or the 
environment in a manner that ensures such programs, policies, and 
activities do not have the effect of excluding persons (including 
populations) from participation in, denying persons (including 
populations) the benefits of, or subjecting persons (including 
populations) to discrimination under such programs, policies, and 
activities because of their race, color, or national origin.
    Today's proposed rule would require that the location, design, 
construction, and capacity of cooling water intake structures at Phase 
III existing facilities reflect the best technology available for 
minimizing adverse environmental impact. For several reasons, EPA does 
not expect that this proposed rule would have an exclusionary effect, 
deny persons the benefits of the participating in a program, or subject 
persons to discrimination because of their race, color, or national origin.
    To assess the impact of the rule on low-income and minority 
populations, EPA calculated the poverty rate and the percentage of the 
population classified as non-white for populations living within a 50-
mile radius of each of the 348 (unweighted) facilities in the Phase III 
universe. The results of the analysis, presented in the Economic 
Analysis, show that the populations affected by the in-scope facilities 
have poverty levels and racial compositions that are quite similar to 
the U.S. population as a whole. Based on these results, EPA does not 
believe that this rule would have an exclusionary effect, deny persons 
the benefits of the NPDES program, or subject persons to discrimination 
because of their race, color, or national origin.
    In fact, because EPA expects that this proposed rule would help to 
preserve the health of aquatic ecosystems located in reasonable 
proximity to Phase III existing facilities, it believes that all 
populations, including minority and low-income populations, would 
benefit from improved environmental conditions as a result of this rule.

K. E.O. 13158: Marine Protected Areas

    Executive Order 13158 (65 FR 34909, May 31, 2000) requires EPA to 
``expeditiously propose new science-based regulations, as necessary, to 
ensure appropriate levels of protection for the marine environment.'' 
EPA may take action to enhance or expand protection of existing marine 
protected areas and to establish or recommend, as appropriate, new 
marine protected areas. The purpose of the Executive Order is to 
protect the significant natural and cultural resources within the 
marine environment, which means ``those areas of coastal and ocean 
waters, the Great Lakes and their connecting waters, and submerged 
lands thereunder, over which the United States exercises jurisdiction, 
consistent with international law.''
    This proposed rule recognizes the biological sensitivity of tidal 
rivers, estuaries, oceans, and the Great Lakes and their susceptibility 
to adverse environmental impact from cooling water intake structures. 
This proposal provides requirements for reducing both impingement and 
entrainment using technologies to minimize adverse environmental impact 
for cooling water intake structures located on these types of 
waterbodies.
    EPA expects that this proposed rule would reduce impingement and 
entrainment at Phase III existing facilities. The rule would afford 
protection of aquatic organisms at individual, population, community, 
or ecosystem levels of ecological structures. Therefore, EPA expects 
today's proposed rule would advance the objective of the Executive 
Order to protect marine areas.

L. Plain Language Directive

    Executive Order 12866 and the President's memorandum of June 1, 
1998, require each agency to write all rules in plain language. We 
invite your comments on how to make this proposed rule easier to 
understand. For example: Have we organized the material to suit your 
needs? Are the requirements in the rule clearly stated? Does the rule 
contain technical language or jargon that is not clear? Would a 
different format (grouping and order of sections, use of headings, 
paragraphing) make the rule easier to understand? Would more (but 
shorter) sections be better? Could we improve clarity by adding tables, 
lists, or diagrams? What else could we do to make the rule easier to 
understand?

List of Subjects

40 CFR Part 9

    Environmental protection, Reporting and recordkeeping requirements.

40 CFR Part 122

    Environmental protection, Administrative practice and procedure, 
Confidential business information, Hazardous substances, Reporting and 
recordkeeping requirements, Water pollution control.

40 CFR Part 123

    Environmental protection, Administrative practice and procedure, 
Confidential business information, Hazardous substances, Indians-lands, 
Intergovernmental relations, Penalties, Reporting and recordkeeping 
requirements, Water pollution control.

40 CFR Part 124

    Environmental protection, Administrative practice and procedure, 
Air pollution control, Hazardous waste, Indians-lands, Reporting and 
recordkeeping requirements, Water pollution control, Water supply.

40 CFR Part 125

    Environmental protection, Cooling water intake structure, Reporting 
and recordkeeping requirements, Waste treatment and disposal, Water 
pollution control.

    Dated: November 1, 2004.
Michael O. Leavitt,
Administrator.
    For the reasons set forth in the preamble, chapter I of title 40 of 
the Code of Federal Regulations is proposed to be amended as follows:

PART 9--OMB APPROVALS UNDER THE PAPERWORK REDUCTION ACT

    1. The authority citation for part 9 continues to read as follows:

    Authority: 7 U.S.C. 135 et seq., 136-136y; 15 U.S.C. 2001, 2003, 
2005, 2006, 2601-2671,

[[Continued on page 68543]] 

 
 


Local Navigation


Jump to main content.