Cincinnati, Ohio
|
CINCINNATI, OHIO
Pending - Proposed Rule: (60 FR 22337, 5/5/95); Proposal
to disapprove
(62 FR 7194, 2/18/97).
Maintenance Plan - Key Features
- 1990 base year; 1993 attainment base, emissions budget through 2005
- lower fuel volatility
- FMVCP
- growth factors used to determine future year inventories based on data from the Bureau of
Economic Analysis (BEA), US Department of Commerce showing manufacturing
earnings by industry
- Stage II implemented in 1995
- on-board vapor recovery implemented in 1998
- enhanced I/M
- 11 monitors measuring ozone in the Cincinnati area
Contingency Plan Triggers
Contingency Measures
- lower RVP for gasoline
- reformulated gasoline program
- broader geographic coverage of existing regulations
- application of RACT on sources covered by new CTGs issued in response to CAAA
- application of RACT to smaller existing sources
- implementation of one or more transportation control measures sufficient to achieve at
least a 0.5 percent reduction in actual areawide VOC emissions. Measures may include
the following: trip reduction programs; transit improvements; traffic flow improvements;
or other measures.
- alternative fuel programs for fleet vehicle operations
- controls on consumer products consistent with those adopted elsewhere in the United
States
- VOC offsets for new or modified major sources
- VOC offsets for new or modified minor sources
- increased ratio of VOC offsets required for new sources
- requirement of VOC controls on new minor sources
Schedule
- After first violation
- verify a violation has occurred within 1 month
- identify VOC plan and submit schedule for implementation within 3 months
- implement VOC control program within 12 months
- After second violation
- verify a violation has occurred within 1 month
- submit schedule for implementation of NOx RACT within 3 months
- implement NOx RACT within 18 months
For further information:
William Jones
Air Programs Branch (AR-18J)
U.S. EPA, Region V
77 West Jackson Blvd.
Chicago, IL 60604
Telephone: (312) 886-6058; Email: jones.william@epamail.epa.gov
|