Acid Rain Program:
Summary of Part 75 Administrative Processes
Revised 12/15/03
Table 1: Initial Certification
| Submittal Requirement | Rule Citation(s) | Contents of Submittal | Submit to Whom? | Submit When? | Comments |
|---|---|---|---|---|---|
| Certification Test Notification | § 75.61 (a)(1)(i) § 75.20 (g)(2) |
Written notification of date(s) of initial certification tests | CAMD, EPA Region, State | > 21 days prior to commencement of certification testing | Test date may be rescheduled if notice is provided > 7 days before the earlier of original or new date
Tests may be repeated without notification Notification is not required for Appendix D fuel flowmeter accuracy testing |
| Initial Monitoring Plan Submittal | § 75.53 (e), (f) , § 75.62, § 75.73 (e) | Hardcopy and electronic monitoring plan in format "specified by the Administrator" | Hardcopy portion to EPA Region and State | > 45 days prior to commencement of certification testing | Electronic transmittal of information in hardcopy portion is acceptable |
| Certification Application | § 75.62, § 75.63 | Hardcopy test results to EPA Region, State
Electronic test results to CAMD Complete electronic monitoring plan to CAMD Hardcopy monitoring plan changes (if any) to EPA Region, State |
< 45 days after completion of certification testing | For Subpart E alternative monitoring systems, submit hardcopy test results to CAMD
For other certifications, submit hardcopy test results to CAMD only upon request |
|
| Notice of Approval or Disapproval | § 75.20 (a)(4) | Written notice of approval or disapproval of certification application | Administrator provides notice to owner or operator | < 120 days after receipt of a complete certification application | 120 day clock starts upon receipt of a complete application |
| Notice of Incomplete Application | § 75.20 (a)(4)(ii) | Notification that the certification application is incomplete | Administrator provides notice to owner or operator | If application is found to be incomplete | A reasonable time is provided to submit the missing information. Non-compliance with this notice may result in disapproval of application. |