Table 1: Initial Certification

Submittal Requirement Rule Citation(s) Contents of Submittal Submit to Whom? Submit When? Comments
Certification Test Notification

§ 75.61 (a)(1)(i)

§ 75.20 (g)(2)

Written notification of date(s) of initial certification tests CAMD, EPA Region, State > 21 days prior to commencement of certification testing Test date may be rescheduled if notice is provided > 7 days before the earlier of original or new date

Tests may be repeated without notification

Notification is not required for Appendix D fuel flowmeter accuracy testing

Initial Monitoring Plan Submittal § 75.53 (e), (f) , § 75.62, § 75.73 (e) Hardcopy and electronic monitoring plan in format "specified by the Administrator" Hardcopy portion to EPA Region and State

Electronic portion to CAMD

> 45 days prior to commencement of certification testing Electronic transmittal of information in hardcopy portion is acceptable
Certification Application § 75.62, § 75.63 Hardcopy test results to EPA Region, State

Electronic test results to CAMD

Complete electronic monitoring plan to CAMD

Hardcopy monitoring plan changes (if any) to EPA Region, State

< 45 days after completion of certification testing For Subpart E alternative monitoring systems, submit hardcopy test results to CAMD

For other certifications, submit hardcopy test results to CAMD only upon request

Notice of Approval or Disapproval § 75.20 (a)(4) Written notice of approval or disapproval of certification application Administrator provides notice to owner or operator < 120 days after receipt of a complete certification application 120 day clock starts upon receipt of a complete application
Notice of Incomplete Application § 75.20 (a)(4)(ii) Notification that the certification application is incomplete Administrator provides notice to owner or operator If application is found to be incomplete A reasonable time is provided to submit the missing information. Non-compliance with this notice may result in disapproval of application.