Jump to main content.


Acid Rain Program:
Summary of Part 75 Administrative Processes

Revised 4/25/00

Table 7: Other Notification Requirements

Submittal Requirement Rule Citation(s) Contents of Submittal Submit to Whom? Submit When? Comments
Operation of new unit, newly affected unit, new stack or new FGD

§ 75.61 (a)(2)

Notification of date of commencement of commercial operation of new or newly-affected unit or planned date of initial use or operation of new stack or FGD CAMD, EPA Region, State > 45 days prior to the applicable date If the planned date changes, submit notice of actual date < 7 days after the actual date of initial operation or usage (as applicable).
Unit shutdown and recommencement of commercial operation

§ 75.61 (a)(3)

§ 75.4 (a) and (d)

Notice of dates of unit shutdown and recommencement of commercial operation, for a unit relying on § 75.4 (d) to postpone certification testing CAMD, EPA Region, State For planned shutdown, > 45 days prior to certification deadline in § 75.4 (a), if shutdown is planned at least 45 days ahead of deadline.Otherwise, submit notice < 7 days after scheduling is complete.

For unplanned shutdown, provide notice < 7 days following the shutdown.

If actual date differs from planned date, submit notice of actual date < 7 days following actual date of shutdown or recommencement of commercial operation (as applicable).
Postponement of Appendix E Testing for Backup Fuel § 75.61 (a)(4)

§ 75.4 (a) and (f)

For an Appendix E unit relying on

§ 75.4 (f) to postpone testing while combusting a backup fuel, provide notice of that fact.

CAMD, EPA Region, State > 45 days prior to certification deadline in § 75.4 (a) -------------
Initial Combustion of Backup Fuel for which Appendix E Testing was Postponed

§ 75.61 (a)(4)

§ 75.4 (a) and (f)

After the certification deadline in § 75.4 (a), provide notice of combustion of any fuel for which Appendix E testing was not performed prior to the deadline. CAMD, EPA Region, State No later than 7 days after first date of combustion of the fuel. Notification must include either actual or projected date of Appendix E testing after initial combustion of the fuel.
Notice of Combustion of Emergency Fuel (Appendix D or E) § 75.61 (a)(6)(i)

§ 75.4 (a) and (g)

Where the owner or operator is postponing installation or testing of a fuel flowmeter for emergency fuel under § 75.4 (g), provide notice of that fact. CAMD, EPA Region, State No later than

45 days prior to certification deadline in § 75.4 (a)

------------
Provide notice when emergency fuel is first combusted after deadline in § 75.4 (a) No later than 7 days after first date of combustion of the fuel.
Appendix E Emergency Fuel Exemptions Obtained by Petition § 75.61 (a)(6)(ii)

§ 75.66

If Appendix E exemptions for emergency fuel have been obtained under § 75.66, report dates and hours in which the fuel was combusted CAMD, EPA Region, State In the quarterly emissions report ------------

View other Part 75 administrative processes

 


Local Navigation


Jump to main content.