UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
IN THE MATTER OF: )
)
ASBESTOS REMOVAL SPECIALISTS ) DKT NO. 10-97-0137 CAA
OF ALASKA, INC., )
)
Respondent )
ORDER DENYING RESPONDENT'S MOTION TO DISMISS
AND IN THE ALTERNATIVE MOTION FOR ACCELERATED DECISION
On March 13, Respondent filed a Motion to Dismiss, and in
the Alternative, Motion for Accelerated Decision (Motion).
Complainant opposed the Motion on March 30, 1998 (Opposition).
For the reasons which follow, Respondent's Motion will be denied.
I. BACKGROUND
Respondent is an asbestos abatement and removal business
headquartered in Fairbanks, Alaska. Respondent contracted with
Richard Stanton Construction, Inc., to perform asbestos removal
work for the State of Alaska, at the State of Alaska's parking
garage located between Fifth and Seventh Avenues and Barnette
Street in Fairbanks, Alaska. Respondent submitted a Notice of
Demolition and Renovation to EPA on July 11, 1996, estimating the
surface area of roofing, which contains asbestos-containing
material (ACM), to be 4,500 square feet. Respondent commenced
the renovation work at the parking garage on August 8, 1996. On
that day, and on the following two days, August 9 and 10, 1996,
Roman Gray, an inspector from the Alaska Department of Labor,
Occupational Safety and Health Division, conducted inspections of
the parking garage.
Based upon information from the inspections, a Complaint
initiating this proceeding was filed on August 7, 1997, by Region
10 of the United States Environmental Protection Agency
(Complainant). The Complaint alleges that Respondent violated
Section 112 of the Clean Air Act (CAA), 42 U.S.C. § 7412, and
federal regulations promulgated thereunder, 40 C.F.R. Part 61, known as the National Emission Standards for Hazardous Air
Pollutants (NESHAP). Respondent is charged in five counts with
violating Subpart M of the NESHAP (Asbestos NESHAP), which
governs the emissions, handling and disposal of asbestos.
Complainant proposed the assessment of a penalty of $140,000 for
the alleged violations.
Answering the Complaint, Respondent denied the alleged
violations, asserted defenses and requested a hearing. The
parties exchanged prehearing information as directed by an Order
dated September 19, 1997, and thereafter this matter was set for
hearing to begin on July 14, 1998. Upon joint motion of the
parties, they were granted until March 13, 1998 to file any
motions for accelerated decision or to dismiss pursuant to 40
C.F.R. § 22.20(a). An unopposed motion to amend the Complaint
was filed by Complainant to reflect new information which more
accurately describes the quantity of the asbestos-containing
material at issue, and to reduce the proposed penalty to account
for new information regarding the economic benefit of
Respondent's alleged noncompliance with the Asbestos NESHAP. The
proposed penalty was reduced to $58,688.(1)
II. DISCUSSION
Respondent's Motion requests dismissal of the Complaint on
grounds that Complainant has not established a prima facie case
as to Respondent's liability for any of the alleged violations.
In the alternative, Respondent requests an accelerated decision
in its favor as to part of the alleged violation in Count I, all
of Count II, and part of Counts IV and V of the Complaint.
A. Motion to Dismiss
As to the request for dismissal, Respondent asserts that the
minimum threshold requirements, under which asbestos demolition
or renovation becomes subject to the Asbestos NESHAP regulations,
have not been met. The threshold is stated in terms of the
amount of regulated ACM (RACM) involved in the renovation. There
is no dispute that the renovation project at issue involved
Category I non-friable ACM, defined in 40 C.F.R. § 61.141 as
including asphalt roofing products containing more than one
percent asbestos. The question presented is whether an amount of
ACM exceeding the regulatory threshold became regulated ACM, by
becoming friable, or by being subjected to sanding, grinding,
cutting or abrading.
RACM is defined in 40 C.F.R. § 61.141 as: "(a) Friable
asbestos material; (b) Category I nonfriable ACM that has become
friable; [or] © Category I non-friable ACM that will be or has
been subjected to sanding, grinding, cutting, or abrading . . .
." Friable asbestos material is defined in 40 C.F.R. § 61.141 as
"any material containing more than 1 percent asbestos as
determined using the method . . . Polarized Light Microscopy,
that, when dry, can be crumbled, pulverized or reduced to powder
by hand pressure."
The relevant threshold, triggering regulation under
standards in 40 C.F.R. Part 61 Subpart M for facilities being
renovated, is stated in 40 C.F.R. § 61.145(a)(4) as follows:
In a facility being renovated . . . all the requirements of
paragraphs (b) and © of this section apply if the combined
amount of RACM to be stripped, cut, drilled, or similarly
disturbed is
(I) At least 80 linear meters (260 linear feet) on pipes or
at least 15 square meters (160 square feet) on other
facility components . . . .(emphasis added)
The question is whether at least 160 square feet of the
total 3,634 square feet of ACM at the site became RACM, i.e.
friable or subjected to sanding, grinding, cutting or abrading.
The roof of the parking garage was composed of a four-inch
layer of concrete, followed by a one-inch layer of rigid foam
insulation, followed by built-up roofing (BUR), followed by a
three-inch layer of rigid insulation and another four-inch layer
of concrete (Stipulations, dated April 30, 1998 ("Stip.") ¶ 8).
The BUR is composed of asbestos-containing roofing felt, tar and
asphalt. On August 8, 1996, Respondent attempted to use a RB
cutter to cut a 12" by 16" piece of roofing felt, but the RB
cutter stalled and could not be restarted (Stip. ¶ 15). On
August 9, Respondent's crew cut the roof with axes to manually
remove the BUR (Stip. ¶ 28).
Respondent's position is that the methods it used in
removing the ACM did not create 160 square feet of RACM by
sanding, grinding, cutting or abrading. In support of the latter
argument, Respondent cites to Appendix A of Subpart M, the
"Interpretive Rule Governing Roof Removal Operations,"
(Interpretive Rule) which states in pertinent part of Section
1.A.1.:
EPA has determined that where a rotating blade (RB) roof
cutter or equipment that similarly damages the roofing
material is used to remove Category I non-friable asbestos-containing roofing material, the removal of 5580 ft2 of that
material will create 160 ft2 of RACM . . . .
Therefore, it is EPA's interpretation that when an RB roof
cutter or equipment that similarly damages the roofing
material is used to remove Category I non-friable asbestos-containing roofing material in a roof removal project that
is less than 5580 ft2, the project is not subject to the
NESHAP . . . .
Respondent points out that only 3,634 square feet of ACM was
to be removed at the parking garage, which would produce less
than 160 square feet of RACM if removed by use of an RB roof
cutter.
Respondent argues further that it used manual methods to
remove the ACM which did not create any RACM, and cites to the
Interpretive Rule at Sections 1.A.1. and 1.C.1:
EPA further construes the NESHAP to mean that if slicing or
other methods that do not sand, grind, cut or abrade will be
used on Category I non-friable ACM, the NESHAP does not
apply, regardless of the area of roof to be removed.
* * * *
As EPA interprets the NESHAP, the use of certain manual
methods (using equipment such as axes, hatchets, or knives .
. .) or methods that slice, shear or punch . . . does not
constitute "cutting, sanding, grinding or abrading." This
is because these methods do not destroy the structural
matrix or integrity of the material such that the material
is crumbled, pulverized, or reduced to powder. Hence, it is
EPA's interpretation that when such methods are used,
assuming the roof material is not friable, the removal
operation is not subject to the regulation.
Respondent asserts therefore, that under the Interpretive
Rule, the ACM did not become RACM, so the Asbestos NESHAP did not
apply regardless of the amount of BUR removed. Respondent
asserts further, that even assuming the RB cutter was used to
remove the BUR, the project did not meet the threshold amount of
RACM to trigger application of the Asbestos NESHAP.
As to the issue of friability, Respondent argues that
Complainant also has not established that the BUR was regulated
as RACM on the basis of being friable. In its prehearing
exchange, Respondent submitted affidavits of employees who were
working at the site on the days in question, who stated therein
that the BUR was not friable (Respondent's Prehearing Exchange
Exhibits ("RX") A, B, C, D, E, F). Respondent points out the
absence in the inspection report of any statement that the
roofing material was friable, and the lack of any friability
testing. (Complainant's Prehearing Exchange, Exhibit ("CX") 1).
Thus, Respondent concludes that there is no reliable evidence
that the BUR was friable, and therefore it was not subject to
regulation under the Asbestos NESHAP.
The Rules of Practice applicable to this proceeding, 40
C.F.R. Part 22, provide at Section 22.20(a) that an action may be
dismissed "on the basis of failure to establish a prima facie
case or other grounds which show no right to relief on the part
of the complainant." In determining whether to dismiss a
complaint, "all factual allegations in the complaint should be
presumed true, and all reasonable inferences therefrom should be
made in favor of the complainant." Commercial Cartage Company,
Inc., 5 E.A.D. 112, 117 (EAB, Feb. 22, 1994); citing, Bank v.
Pitt, 928 F.2d 1108, 1109 (11th Cir. 1991).
Complainant believes that Respondent has not met such
standard for dismissal. Complainant asserts that it is
reasonable to assume that at least 160 square feet of roofing
felt was removed(2) (Complainant's Opposition, dated March 30,
1998, p. 5). Complainant asserts further that an amount of ACM
exceeding 160 square feet was subjected to grinding, cutting, and
abrading during the renovation operation. Documents in
Complainant's prehearing exchange indicate that Respondent used a
front-end loader ("bobcat") to lift, cut, smash and tear the
roofing felt (CX 1, 5, 31 ¶ 4). The parties stipulated that the
front-end loader was used to "break up wet roofing material in
the center of the roof and dump it" into an elevated scissor
truck (Stip. ¶ 16). Respondent admitted, "Mr. Johnson began the
work day at 8:00 a.m. by wetting and cutting the last of the BUR
manually with an axe and cutting it into smaller pieces with the
bobcat" (Respondent's Memorandum of Law in Support of its Motion,
p. 8). Complainant points to documents and photographs showing
that Respondent used a buffer to grind off debris, which resulted
in "grinding" of ACM roofing material, according to Complainant
(CX 1, 23, 32 ¶ 12). Thus, methods other than hand axes were
used to remove ACM, which resulted in grinding, cutting, abrading
of ACM, rendering it RACM.
Complainant supports its argument that the ACM was friable
with an affidavit of the inspector stating that by using hand
pressure he easily broke off roofing materials in order to obtain
split samples, and that he observed small particles broken off in
the sample bag resulting from his handling of the bag (CX 31 ¶
14). Complainant also cites to an affidavit in its prehearing
exchange of the laboratory analyst who describes therein the
samples taken from the site. She states that she rubbed her
finger across the surface of a sample, dislodging white tiny-fiber bundles, and that the matrix of a sample easily crumbled
beneath her fingers, and concludes that the samples are friable.
(CX 33 ¶¶ 6, 7, 10).
Complainant has established prima facie that some amount of
the ACM was friable and that some amount of the ACM was subjected
to grinding, cutting and/or abrading. The amount of such RACM
cannot presently be determined. However, Complainant has alleged
that the amount of RACM exceeds the regulatory threshold
(Complaint ¶¶ 16, 18). Presuming that it is true, and drawing
reasonable inferences in favor of Complainant from documents and
information in the prehearing exchange, dismissal of the
Complaint is not warranted. Although the presence and amount of
RACM is contested by Respondent, this issue cannot be resolved on
the record as it now stands.
B. Motion for Accelerated Decision
Count I alleges that when Respondent's employees used a
shovel and front-end loader to drop ACM into a dumpster, they
failed to "[c]arefully lower each unit or section [of facility
component that contains RACM] to the floor and to ground level,
not dropping, throwing, sliding, or otherwise damaging or
disturbing the RACM" as required by 61.145(c)(2)(ii). Respondent
requests an accelerated decision in its favor as to the
allegation in Count I that this violation occurred on August 8,
1996. The inspector took no bulk samples until the next day,
August 9, 1996 (Stip. ¶ 25). Because no samples were taken on
August 8, Respondent asserts, there is no evidence that the
material going into the dumpster on August 8 was RACM.
Respondent may be entitled to an accelerated decision only
if there are no genuine issues of material fact. 40 C.F.R. §
22.20(a). Complainant asserts that such issues exist as to Count
I on the basis, inter alia, of photographs taken by the inspector
on August 8 showing roofing debris being dumped and shoveled into
the dumpster, and the inspector's identification, in the
photographs of materials in the dumpster, of roofing felts
similar to those which were later sampled and tested positive for
asbestos (CX 1A, 31 ¶ 5). Complainant has established that
genuine issues of material fact exist and therefore Respondent's
request for accelerated decision as to Count I is denied.
Count II of the Complaint alleges that on August 8 and 9,
1996, Respondent discharged visible emissions coming from RACM or
asbestos-containing waste material. Respondent asserts that
there is no evidence, including the inspection report and
inspector's photographs, suggesting that anyone saw any visible
emissions on the dates at issue. Respondent points to its
employees' affidavits stating that the weather was rainy on
August 8 and 9, and that they never observed any dust or fibers
of asbestos in the air. Respondent cites to air monitoring
records taken at the site showing, it asserts, no significant
change in air quality, and to its proposed expert witness'
opinion that the records indicate that the minimal amounts of
fibers detected would not create visible emissions (CX 5; RX F).
In response, Complainant cites to the inspection report,
which lists as an apparent violation, "discharge no visible
emissions to the outside air," and describes dumping of ACM with
front-loader and shovel into the dumpster, scattering of debris,
and debris not protected from spilling out of trucks (CX 1). The
inspection report does not state specifically that "visible
emissions were observed." Only in the affidavit of the
inspector, dated March 27, 1998, submitted after the Respondent's
Motion, appear statements specifically describing visible
emissions. The affidavit states that on August 8, 1996, the
inspector observed and photographed "particulate matter emitted
into the air as roofing debris was being dumped" via front-end
loader and shovels into the dumpster, and on August 9 he observed
and photographed "particles of asbestos roofing debris emitted
through the air" (CX 31 ¶¶ 6, 10).
Nevertheless, well before the Motion was filed, Complainant
stated that the inspector was expected to testify at the hearing
that he observed visible emissions from the renovation operation
on August 8 and 9 (Complainant's Prehearing Exchange statement,
dated November 26, 1997). It is concluded that there is
sufficient documentation in the record to show prima facie that
visible emissions were observed by the inspector on the dates at
issue. Respondent's challenge to Complainant's case shows that
there are genuine issues of material fact as to whether visible
emissions from RACM were observed. Therefore, an accelerated
decision as to Count II is not warranted.
Count IV alleges that Respondent failed to mark, with EPA
asbestos hazard warning signs, the vehicles used to transport
waste ACM during the loading and unloading of waste on August 8,
9, and 10, in violation of 40 C.F.R. § 61.150(c). Respondent
contends that there is no evidence that the inspector saw an
unmarked vehicle during loading and unloading. Respondent
asserts that the inspector saw the scissor truck at Respondent's
shop facility, located at 1189 Van Horn Avenue in Fairbanks, at
least four hours after it had been loaded at the parking garage
site, which does not prove that it was not properly marked at the
site when being loaded.
Complainant characterizes the Respondent's implication that
an asbestos hazard warning sign was present during loading and
then removed afterward as an "unlikely scenario." The inspection
report notes that two days later (August 10), Respondent's
foreman at the site placed Department of Transportation placards
on the truck when the inspector pointed out the lack of warning
labels on the truck; the foreman did not place any asbestos
warning labels as required by EPA regulations (CX 1). The
inspection report notes further that during conversation with the
inspector, the foreman demonstrated that he was unfamiliar with
the labeling and transportation regulations (CX 1).
There exist genuine issues of material fact as to whether
the scissor truck was marked with the required asbestos hazard
warning while it was being loaded on August 8, 1996. Thus,
accelerated decision as to Count IV will be denied.
The final count upon which Respondent requests accelerated
decision is Count V, which alleges that there were no waste
shipment records for transporting loose ACM on August 8, or for
bagged ACM debris on August 10, and that waste shipment records
for August 9 and 13 were incomplete. Waste shipment records are
required by 40 C.F.R. § 61.150(d)(1) for all ACM waste
transported off-site. Respondent requests accelerated decision
as to August 8, 9 and 13 on the basis that waste shipment records
for those dates, presented in the prehearing exchange as
Respondent's exhibit L, were complete.
Complainant contends that the records in Respondent's
Exhibit L do not accurately reflect all of the ACM that
Respondent disposed of. Complainant cites to discrepancies
between Exhibit L and the Respondent's daily log of the
renovation, in Complainant's Exhibit 5. Complainant points to
specific items in the waste ACM listed in the daily log for
August 8, 9 and 13 which were not accounted for in the waste
shipment records for August 8, 9 and 13. Complainant has shown
specific facts in the record which establish that genuine issues
of material fact exist as to the violation alleged in Count V.
In sum, as supported by documents submitted in the
prehearing exchange, Complainant has shown prima facie that the
Asbestos NESHAP regulations applied to the renovation project at
issue. Respondent has not established any grounds which show
that Complainant has no right to relief. Furthermore, genuine
issues of material fact exist as to Counts I, II, IV and V, and
therefore Respondent is not entitled to an accelerated decision.
Accordingly, IT IS ORDERED THAT:
1. Respondent's Motion for Extension of Time to File Motion to Dismiss is GRANTED.
2. Respondents' Motion to Dismiss is DENIED.
3. Respondents' Motion in the Alternative for Accelerated
Decision is DENIED.
4. The parties shall report on the status of settlement of this
proceeding within thirty (30) days from the date of this
Order.
________________________________
Susan L. Biro
Chief Administrative Law Judge
Dated: May 6,1998
Washington D.C.
1. The amount of ACM to be removed was amended, based upon
information provided by Respondent, to an area of approximately
3,634 square feet rather than the Respondent's earlier estimate
of 4,500 square feet. The economic benefit component of the
penalty was reduced on the basis of information from Respondent
that it was paid $8,688 to conduct asbestos renovation and
disposal. Respondent filed an Amended Answer to the Complaint on
April 13, 1998, which is substantially similar to the original
Answer.
2. It is observed that Respondent's Notification of Demolition
and Renovation, dated July 15, 1996, lists in Part VII that the
approximate amount of "RACM To Be Removed" is 4,500 square feet,
describing "Surface Area Roofing Felts" (CX 2, 3).
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)