UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
GEORGE ATKINSON,[D/B/A/] )
GEORGE'S BRITISH PETROLEUM, ) DOCKET NO.
) RCRA-(9006)-VIII-97-02
RESPONDENT )
Resource Conservation and Recovery Act - Regulation of
Underground Storage Tanks - Default Order - Determination of
Penalty
Notwithstanding provision of Consolidated Rule 22.17(a) (40
C.F.R. Part 22) to the effect that upon entry of a default order
the full amount of the penalty proposed in the complaint shall
become due and payable without further proceedings, where
Complainant's assertion that the proposed penalty was computed in
accordance with applicable penalty guidance was determined to be
inaccurate, penalty was recomputed.
Appearance for Complainant:
Dana J. Stotsky, Esq.
Senior Enforcement Attorney
U.S. EPA Region VIII
Denver, Colorado
Appearance for Respondent:
George J. Atkinson
Pro Se
Ronan, Montana
ORDER ON DEFAULT
On March 23, 1998, Complainant moved for a Default Order
against the Respondent, George Atkinson, [d/b/a] George's British
Petroleum ("Respondent"), in this proceeding under Section 9006 of
the Solid Waste Disposal Act, as amended (42 U.S.C. § 6991e(a)).
The stated basis of the motion is the failure of Respondent to file
a prehearing exchange as ordered by the ALJ. By an order, dated
June 30, 1998, Respondent was directed to show cause why it should
not be held in default for failure to comply with the prehearing
exchange order. The deadline for Respondent's response to the
order was July 24, 1998. In an unsigned letter, dated July 29,
1998, Respondent alleged that he was unable to respond prior to
July 24, because he was out of town on family business. Respondent
further alleged that he could not respond to the [order for a
prehearing exchange] because the information was unavailable to him
by the time of the previous deadline.
On August 27, 1998, Complainant filed a renewed motion for
entry of default and issuance of a default order. In accordance
with Rule 22.17 of the Rules of Practice (40 C.F.R. Part 22), a
party may be found in default "after motion or sua sponte, upon
failure to comply with a prehearing or hearing order of the
Presiding Officer..." For the reasons discussed below,
Complainant's motion is granted and Respondent is found to be in
default.
The one count complaint, filed on May 30, 1997, charged
Respondent with failure to respond to a confirmed release of a
petroleum substance, as required by 40 C.F.R. § 280.60, and failure
to replace a cracked compression fitting on copper blowback tubing
on the turbine pump for an unleaded gasoline tank, as required by
40 C.F.R. § 280.33. For these alleged violations, it was proposed
to assess Respondent a penalty of $13,700.
Respondent George Atkinson, appearing pro se, filed a letter-answer by facsimile, dated August 25, 1997, denying that any
inspection of his facility had taken place, denying the existence
of any leak, and denying Complainant's jurisdiction to enforce
Solid Waste Disposal Act provisions with respect to Respondent.(1)
Respondent alleged that the proposed penalty was excessive and
inappropriate and requested a hearing.
On September 29, 1997, the ALJ issued a prehearing order
requiring Complainant and Respondent to exchange specified
prehearing information on or before November 21, 1997. Complainant
filed its prehearing exchange by the mentioned date. Documents
contained in Complainant's submission include a report of an EPA
inspection of Respondent's facility conducted on January 22, 1997,
and its attachment, a report of a 1996 inspection of Respondent's
facility by the Montana Department of Environmental Quality (DEQ).
These documents support Complainant's assertions concerning the
release of a petroleum substance, Respondent's failure to respond
thereto and his failure to replace the cracked compression fitting.
Respondent did not respond to the order that it file a
prehearing exchange. Respondent was directed to furnish the factual
basis for the denial of the allegation that its facility was
inspected on January 22, 1997,(2) to state the factual basis for
denying the allegation that Respondent was notified of a release by
the Montana DEQ and that Respondent failed to correct the cause of
the alleged leak. Additionally, Respondent was directed to furnish
data such as financial statements or a copy of his income tax
returns, if he were contending that assessment of the proposed
penalty would jeopardize his ability to remain in business.
As noted at the outset of this order, Complainant, pointing to
Respondent's failure to respond in any way to the prehearing
exchange order, filed a motion for a default order on March 23,
1998. Respondent did not file any response to the motion. On
June 30, 1998, the ALJ issued the previously mentioned order to
show cause and on July 29, 1998, five days after the July 24 date
set by the order, Respondent filed the response recited above. The
response did not state whether the prehearing information which was
allegedly unavailable on November 21, 1997, the date it was due to
be filed, had since become available or describe the efforts made,
if any, to obtain the information. More importantly, Respondent
has not to date cured its default by submitting the information or,
given any indication that he intends to do so.
Based on the entire record, primarily the January 1997 EPA
inspection report, I make the following:
Findings of Fact
- Respondent owns and/or operates, and, at all times relevant to
the complaint in this matter, owned and/or operated nine
underground storage tanks (USTs) at a facility at 1018 Highway
93 South, Ronan, Montana. This facility, formerly known as
George's Exxon and presently known and doing business as
George's British Petroleum, is a retail outlet for motor
vehicle fuels. (EPA Inspection Report, dated January 23,
1997, at 1).
- On July 13, 1995, Montana DEQ performed an inspection of
Respondent's facility during which a release of a regulated
substance was observed. Montana DEQ issued a letter to
Respondent on July 24, 1995, noting the violations discovered.
DEQ issued a Notice of Violation to Respondent on
September 21, 1995 for failure to continue the investigation
and free product recovery at his facility. (EPA Inspection
Report, at 1).
- On June 6, 1996, Montana DEQ conducted a follow-up inspection
and found, among other things, a cracked compression fitting
on copper blowback tubing on a turbine pump for an unleaded
gasoline tank. On June 11, 1996, Montana DEQ issued Respondent
a letter requiring it to remedy listed violations, including
replacing the cracked compression fitting. (EPA Inspection
Report, at 2).
- On January 8, 1997, after receiving information indicating
continued releases from the facility, Montana DEQ re-inspected
the facility and found that the Automatic Tank Gauging (ATG)
system had not been used since the June 6, 1996 inspection.
Because the ATG system functioned, in part, as a leak
detection system, Montana DEQ and EPA inferred that the
facility might have an undetected release. (EPA Inspection
Report, at 2).
- On January 22, 1997, EPA Inspector Kristine Knutson inspected
Respondent's facility. During the inspection, Ms. Knutson
found that the ATG module was not functioning properly and
that the cracked compression fitting had not been repaired.
Ms. Knutson was told by Lisa Starkel, an agent of Respondent,
that the ATG system had not been working for a long time.
(EPA Inspection Report, at 2-5).
- As recited in the introduction to this order, Respondent has
failed to submit prehearing information as directed by the
ALJ. Information Respondent was directed to submit included
the factual basis for the denial of the substantive
allegations of the complaint, i.e., the fact of a release and
the existence of a cracked compression fitting, and financial
data, if Respondent contended that the proposed penalty
exceeded his ability to pay. Respondent's response to the
Order to Show Cause sets forth no reason for his continuing
failure to cure his default.
- The complaint alleges that the proposed penalty of $13,700 was
determined in accordance with the "U.S. EPA Penalty Guidance
for Violations of UST Regulations," OSWER Directive 9610.12
(November 1990, Complaint Exh. 5). The UST Guidance sets
forth a two-step process of determining an initial penalty
target, then making settlement adjustments, when applicable.
(Id. 5). The determination of the initial penalty target
involves the sum of two components, an economic benefit
component and a gravity-based component. The economic benefit
component is comprised of avoided costs and delayed costs (Id.
8-12). The initial gravity-based component is determined from
a matrix which shows the extent of deviation from the
requirement as major, moderate, minor on the horizontal axis
and the potential for harm as major, moderate, minor on the
vertical axis (Id. 16). After determining the level of the
violation, the penalty amount is read from the appropriate
cell, e.g., $1,500 for a major deviation from requirement and
a major potential for harm.
- After a base penalty is determined from the matrix,
adjustments are then made to the matrix value to determine the
initial penalty target figure. These adjustments include
violator specific adjustments such as the violator's
cooperation, willfulness, and history of noncompliance: an
environmental sensitivity multiplier based on the
environmental sensitivity associated with the location of the
facility: and a days of noncompliance multiplier. (Id. 14-21).
Because no compromise has been effected, settlement
adjustments are not applicable in this case.
- In calculating the proposed penalty herein, Complainant
considered both the potential for harm and the extent of
deviation to be major, resulting in an initial gravity-based
penalty of $1500. (UST Guidance; UST Penalty Computation
Worksheet, Motion Exh 2). Violator specific adjustments were
plus 50% or $750 for noncooperation, i.e., failure to respond
[to notice of violations] and to make repairs; another 50% or
$750 for willfulness or negligence, i.e., although aware of
problem Respondent failed to respond appropriately; and 25% or
$375 for a history of noncompliance, a citation allegedly
having been issued to Respondent in 1997 (Penalty Computation
Worksheet). This resulted in an adjusted matrix value of
$3,375, which was multiplied by a site specific environmental
impact factor of 4.056 to reach a total of $13,687.50. This
figure was rounded to $13,700.
- The multiplier of 4.056 referred to in the previous finding,
was computed by dividing 90 into 365, the number of days the
violation is alleged to have continued. This method of
determining the Environmental Impact Factor (EIF) is not
explained and does not comport with UST Guidance. The impact
from the release was considered to be moderate which results
in an environmental sensitivity multiplier of 1.5 and the 365
days of noncompliance results in a DNM multiplier of 2.5.
(Penalty Computation Worksheet; UST Guidance at 21). The EIF
should thus have been 3.75 (1.5 x 2.5). Accordingly, the
gravity-based penalty should be $12,656 ($3,375 x 3.75).
Because the economic benefit from the violations was
determined to be minimal, no economic benefit component was
added to the proposed penalty.
Conclusions
- Information Respondent was directed to provide in the ALJ's
letter-order, dated September 29, 1997, was central to the
issue of his liability for the violations alleged in the
complaint and to a defense to the amount of the penalty based
on ability to pay. The information was thus material.
Respondent's failure and refusal to provide the information
warrants a finding of default and pursuant to 40 C.F.R. §
22.17(a), Respondent is found to be in default. Respondent's
default constitutes an admission of all facts alleged in the
complaint and a waiver of its right to a hearing on such
allegations.
- Respondent has violated Section 9003 of RCRA, 42 U.S.C. §
6991b, and 40 C.F.R. §§ 280.60 and 280.33, as set forth above
and as alleged in the complaint.
- In accordance with RCRA § 9006(d)(2)(C), 42 U.S.C. §
6991e(d)(2), Respondent is liable for a civil penalty for the
violations found herein. The penalty of $13,700 proposed by
Complainant, however, does not comport with the EPA Penalty
Guidance for Violations of UST Regulations (November 1990). As
indicated in finding 10 above, an appropriate penalty computed
in accordance with the UST Guidance totals $12,656. This is
the amount that will be assessed.
- In accordance with section 9003(h) and 9006 of RCRA, 42 U.S.C.
§§ 6991b(h) and 6991e, Respondent will be ordered to perform
the activities listed in the proposed compliance order in the
complaint. The initial step of the compliance alternative
chosen from the complaint must be completed within 60 days of
the receipt of this order. The remaining steps of the
alternative chosen must be completed within the time frame
specified in the complaint.
Discussion
Although Respondent's July 29, 1998 letter is a tardy response
to the Order to Show Cause, the assertion that information required
by the prehearing order was not available at the time the
information was to be submitted affords no reason or explanation
for failing to submit the information at a later time. Respondent
has not submitted the information or indicated in any way that the
information will be forthcoming.
In order for a default order to ensue, the ALJ must conclude
that Complainant has established a prima facie case of liability
against the respondent.(3) To establish a prima facie case of
liability, Complainant must present evidence "sufficient to
establish a given fact ... which if not rebutted or contradicted,
will remain sufficient ... to sustain judgment in favor of the
issue which it supports, but which may be contradicted by other
evidence." Black's Law Dictionary 1190 (6th. ed. 1990).
Complainant must demonstrate both the occurrence of each alleged
violation and the responsibility of each named respondent for those
violations.
As indicated in the June 30, 1998 Order to Show Cause,
Complainant's Prehearing Exchange establishes a prima facie case
that Respondent had failed to replace a cracked compression fitting
on copper blowback tubing on a turbine pump for an unleaded
gasoline tank. Additionally, the Respondent failed to respond to
the release of a regulated substance despite having been notified
of the release by the Montana DEQ. These allegations are
substantiated by the report of the EPA's January 22, 1997
inspection of Respondent's station and its attachment, the report
of the Montana DEQ's June 11, 1996 inspection. As such,
Complainant has established the prima facie case necessary for the
issuance of a default order. Moreover, by its default, Respondent
has waived his right to contest these facts.
Although Rule 22.17(a) provides that upon entry of an order of
default, the penalty proposed in the complaint shall become due and
payable without further proceedings within 60 days, the propriety
of the proposed penalty of $13,700 warrants further scrutiny. The
courts have made it clear that notwithstanding a respondent's
default, the statutory factors in determining the amount of the
penalty must be considered. Katzson Brothers, Inc. v. U.S. EPA, 839
F.2d 1396 (10th Cir. 1988). Moreover, the Environmental Appeals
Board has held that, notwithstanding the cited proviso of Rule
22.17(a), the Board is under no obligation to blindly assess the
penalty proposed in the complaint. Rybond, Inc., RCRA (3008)
Appeal No. 95-3, 6 E.A.D. 614 (EAB, November 8, 1996).
Section 6991e(c) of the Act, 42 U.S.C. § 6991e(c), sets forth
two factors the Administrator is to consider in determining a
"reasonable" penalty, i.e., the seriousness of the violation and
any good faith efforts to comply with the applicable requirements.
It is concluded that the initial gravity-based penalty of $3,375
was determined in accordance with the EPA Penalty Guidance For
Violations of UST Regulations and appropriately considers the
presence [absence] of Respondent's good faith efforts to comply
with the applicable requirements. It is further concluded that the
environmental impact factor multiplier of 3.75 as calculated herein
is in accordance with the UST Guidance and properly takes into
account the seriousness of the violations. This results in a
penalty of $12,656, which is considered to be reasonable.
Remaining for consideration is Respondent's ability
[inability] to pay the penalty so determined. Although the Act
does not require consideration of this factor, inability to pay is
discussed in the UST Guidance (Id. 23). The EPA inspection report
refers to Respondent's claims of financial problems and it may well
be that Respondent could have demonstrated his inability to pay the
$12,656 penalty or some portion thereof had he chosen to actively
defend the complaint. However, the record before me affords no
evidentiary basis for any such a reduction and Respondent, by its
default, has waived the right to present evidence contesting the
penalty. The penalty of $12,656 will be assessed.
Order
Respondent, George Atkinson (d/b/a George's British
Petroleum), having violated Section 9003 of RCRA, 42 U.S.C. §
6991b, and 40 C.F.R. §§ 280.60 and 280.33 as alleged in the
complaint, a penalty of $12,656 is assessed against him in
accordance with Section 9006(d)(2) of the Act (42 U.S.C.
6991e(d)(2)). Additionally, Respondent is ordered to complete the
requirements of one of the alternate compliance orders specified in
the complaint. Respondent is to inform Complainant of the
alternative chosen and the initial step of the compliance
alternative chosen from the complaint must be completed within 60
days of the receipt of this order. The remaining steps of the
alternative chosen must be completed within the time frame
specified in the complaint.(4) Complainant is to make itself
available to facilitate Respondent's efforts to comply with the
alternative chosen. Payment of the full amount of the penalty
shall be made by sending a certified or cashier's check in the
amount of $12,656 payable to the Treasurer of the United States to
the following address within 60 days of the date of this order:
Regional Hearing Clerk
EPA - Region VIII
P.O. Box 360859
Pittsburgh, PA 15251-6859
Dated this 26TH day of October 1998.
Original signed by undersigned
_________________________
Spencer T. Nissen
Administrative Law Judge
1. Although the answer does not elaborate on the bases for the
alleged jurisdictional deficiencies in the complaint, Respondent
presumably was referring to the fact that the facility is located
on an Indian reservation.
2. Inasmuch as the complaint alleges that the inspection was
with the consent of the Respondent, it is probable that the denial
was directed to that allegation rather than to the fact an
inspection occurred.
3. A default order must include "findings of fact showing the
grounds for the order, conclusions regarding all material issues of
law or discretion, and the penalty which is recommended to be
assessed." 40 C.F.R. § 22.17(c).
4. In accordance with Rule 22.17(b) (40 C.F.R. Part 22), this
order constitutes an initial decision, which unless appealed to the
Environmental Appeals Board in accordance with Rule 22.30 or unless
the EAB elects to review the same sua sponte as therein provided,
will become the final decision of the EAB and of the Agency in
accordance with Rule 22.27(c).
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)