UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
IN THE MATTER OF: )
)
Corporacion para el Desarrollo )
Economico y Futuro de la Isla ) Docket No. CWA-II-97-61
Nena, et al., )
)
Respondents )
ORDER ON MOTIONS FOR SUMMARY JUDGMENT,
FOR DISMISSAL, AND FOR DEFAULT
On October 21, 1997, Respondent Puerto Rico Land
Administration ("PRLA") filed a Motion for Summary Judgment
asserting it was entitled to judgment in its favor on the basis
that it was not an "owner or operator of a point source" under
the Clean Water Act. On November 28, 1997, the Complainant, the
U.S. Environmental Protection Agency ("EPA"), responded to PRLA's
Motion, by filing a Motion for Voluntary Dismissal of PRLA without
prejudice. PRLA submitted an opposition to Complainant's Motion
and requested a ruling on its Motion for Summary Judgment. On
December 11, 1997, Complainant opposed PRLA's Motion for Summary
Judgment arguing that dismissal without prejudice is more
appropriate.
Additionally, on December 4, 1997, the Complainant moved for
a default order against Respondent Isla Nena Paving Corporation
("INPC") asserting that, beyond denying liability in a letter
that was not served in accordance with the applicable rules of
procedure, INPC had not responded to the Complaint.
For the reasons that follow, PRLA's Motion for Summary
Judgment is DENIED. Complainant's Motion to Dismiss Respondent
PRLA without prejudice is GRANTED. Complainant's Motion for
Default against Respondent INPC is GRANTED, except that the
imposition of a penalty is stayed until the issue of liability of
the other Respondent is determined.
BACKGROUND
Respondent Corporacion para el Desarrollo Economico y
Futuro de la Isla Nena ("CODEFIN") is the developer of a
proposed housing project known as Quintas de Santa Elena
("Quintas" or "housing project") in Vieques, Puerto Rico. CODEFIN
alleges that it contracted INPC to construct the housing
development. PRLA, a public corporation, owns the land upon
which the housing project is to be built.
By letter dated October 18, 1996, EPA requested CODEFIN to
provide information about the development. CODEFIN provided such
information by letter dated January 21, 1997. EPA asserts that
it conducted Reconnaissance Inspections of the development on
September 5, 1996 and March 19, 1997. Complainant alleges at the
latter inspection, it found that INPC was conducting construction
activities at the site and that the site lacked erosion and
sediment controls that would prevent, reduce and/or minimize, the
discharge of pollutant to the Caribbean Sea.
Based upon information submitted by CODEFIN and found during
the inspections, on April 24, 1997, U.S. EPA's Director of the
Enforcement and Compliance Assistance Division for Region II
commenced this proceeding by filing an Administrative Complaint
against the Respondents. The Complaint alleges that Respondents
violated Section 301 of the Clean Water Act (CWA) by discharging
pollutants through a point source to the Caribbean Sea without a
National Pollutant Discharge Elimination System (NPDES) permit.
The Complaint further alleges that Respondents are in violation
of Section 308(a) of the CWA by failing to comply with
application requirements for a NPDES storm water permit.(1)
While CODEFIN filed a formal answer to the Complaint, PRLA
and INPC did not. Rather, PRLA responded by sending the
Complainant an informal letter dated May 15, 1997 and by
subsequently filing a Motion for Summary Judgment. See, PRLA
Memorandum of Law in Support of Motion for Summary Judgment,
Exhibit C. INPC also responded by letter, dated May 5, 1997,
denying any connection to the construction activities at the
Quintas project. INPC did not file its letter with the Regional
Hearing Clerk, as would be required of an Answer to the Complaint
nor has it so filed any Motion or other pleading or document in
connection with this case. See, 40 C.F.R. Part 22 (Rules of
Practice).(2)
On October 22, 1997, a Prehearing Order was issued,
requiring the parties to set forth in detail their respective
positions in the case and the witnesses and evidence they expect
to present at the hearing.(3) Complainant submitted its Prehearing
Exchange on January 14, 1998. By Order dated December 1, 1997,
the prehearing exchange between Complainant and PRLA was
suspended until the Motion for Summary Judgment was ruled upon.
DISCUSSION
I. PRLA's Motion for Summary Judgment
The Rules of Practice provide that an accelerated decision
may be rendered by the Presiding Judge "in favor of the
complainant or respondent as to all or any part of the
proceeding, without further hearing or upon such limited
additional evidence, such as affidavits, as he may require, if no
genuine issue of material fact exists and a party is entitled to
judgment as a matter of law, as to all or any part of the
proceeding." 40 C.F.R. § 22.20 (a). Additionally, upon motion
of the respondent, the Judge may dismiss an action on the basis
of "failure to establish a prima facie case or other grounds
which show no right to relief." Id.
A motion for accelerated decision is the administrative
analog to the motion for summary judgment under Rule 56 (c) of
the Federal Rules of Civil Procedure. See e.g., In the Matter of CWM
Chemical Services, Docket No. TSCA-PCB-91-0213, 1995 TSCA LEXIS 13,
TSCA Appeal 93-1 (EAB, Order on Interlocutory Appeal, May 15,
1995). As such, decisions establishing the procedures and
requirements of summary judgment provide guidance for accelerated
decisions under 40 C.F.R. § 22.20.
The party moving for summary judgment bears the burden of
demonstrating the absence of genuine issues of material fact.
Adickes v. Kress, 398 U.S. 144, 157 (1970). In considering such a
motion, the Court must construe the factual record and reasonable
inferences therefrom in the light most favorable to the non-moving party. Cone v. Longmont United Hospital Assoc., 14 F.3d 526, 528
(10th Cir. 1994). The mere allegation of a factual dispute will
not defeat a properly supported motion for summary judgment.
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256 (1986).
PRLA argues in its Motion for Summary Judgment that its
status as the mere owner of the land on which the construction
activities occurred is insufficient to invoke liability under the
Clean Water Act. PRLA asserts that it does not own any
improvements nor any point sources on the land. It cites Federal
Court opinions delineating various methods of establishing the
necessary degree of connection between a landowner and a point
source to incur liability, focusing on the element of control
over the point source. See, PRLA Memorandum in Support of its
Motion for Summary Judgment at 12-13. Not having authorized
CODEFIN or INPC to begin construction activities on the land,
PRLA argues, it had no control over the construction activities
or storm water runoff at issue, and, therefore, cannot be held to
be the legal cause of pollutant discharges. Id. at 2, 4-5. Since
it claims it cannot be a legal cause of the discharges, PRLA
charges it is entitled to have judgment entered in its favor.
To determine which entities are liable, the statutory and
regulatory provisions upon which this proceeding is based must be
reviewed. Section 301(a) of the CWA prohibits the discharge of
any pollutant by any person except as in compliance with, inter alia,
Section 402 of the CWA, which authorizes EPA to issue NPDES
permits for the discharge of pollutants. "Discharge of a
pollutant" means "any addition of any pollutant to navigable
waters(4) from any point source" under Section 502(12) of the CWA.
The term "point source" includes any "discernible, confined and
discrete conveyance, including . . . any pipe, ditch, channel,
tunnel, conduit, well, discrete fissure . . . ." Section
402(p)(4) authorizes the EPA to establish regulations setting
forth permit application requirements for stormwater discharges.
Accordingly, EPA promulgated requirements for storm water
discharges, which are codified at 40 C.F.R. § 122.26, and which
provide in pertinent part at paragraph (c) as follows:
Application requirements for storm water discharges associated with industrial
activity-(1) Individual application. Dischargers of storm water
associated with industrial activity are required to
apply for an individual permit, apply for a permit
through a group application, or seek coverage under a
promulgated storm water general permit. Facilities
that are required to obtain an individual permit . . .
shall submit an NPDES application in accordance with
the requirements of § 122.21 * * * *
At Section 122.26(b)(14)(x), the regulations state that the
following category of facilities is considered to be engaging in
"industrial activity": "Construction activity including clearing,
grading and excavation activities."
Section 122.21, setting forth NPDES permit application
requirements, provides in pertinent part:
(a) Duty to apply. Any person who discharges or proposes to
discharge pollutants . . . shall submit a complete
application . . . to the Director in accordance with
this section and part 124.
(b) Who applies? When a facility or activity is owned by
one person but is operated by another person, it is the
operator's duty to obtain a permit.
(c) Time to apply. . . . Facilities described under §
122.26(b)(14)(x) shall submit applications at least 90
days before the date on which construction is to
commence.
The question at hand is whether PRLA has carried its burden
to demonstrate that no genuine issue of material fact exists and
that it is entitled to judgment as a matter of law that it is not
liable either for failing to comply with the NPDES storm water
permit application requirements or for discharging pollutants
from a point source without a permit. The answer to this
question cannot be answered in the affirmative upon review of the
documents submitted to date in this proceeding.
PRLA has not addressed each allegation in the Complaint
because it did not file an Answer to the Complaint in accordance
with all of the requirements of 40 C.F.R. § 22.15. PRLA also has
not filed prehearing exchange documents, which could have
provided further information as to its degree or ownership or
control over the site and its relationship with CODEFIN.
CODEFIN's response to EPA's information request stated that
"[s]torm sewer runoff had been discharged to U.S. waters through
the culvert crossing State Road 200 to the beach and eventually
to the sea. This occurred shortly after clearing the site and
continues to occur." This statement, alleged in the Complaint
and admitted in CODEFIN's Answer, indicates that discharge of
storm water occurred via a culvert used in connection with the
construction activities at the site. It is not clear which
entity owns or constructed the culvert. A reasonable inference
could be drawn in favor of Complainant that the culvert is a
point source of the discharge and that it is owned by PRLA.
Moreover, the extent of PRLA's control of the property and
activities connected therewith is not entirely clear and
immutable, upon review of documents submitted in this proceeding.
The record indicates that, on October 17, 1996, CODEFIN and PRLA
entered into an agreement for the future sale of the property on
which the Quintas project was to be built, but that PRLA has not
yet transferred title or possession over the property. PRLA
claims that it never authorized entry on its land for purposes of
commencement of construction activities, such as soil movement,
removal of vegetative cover, and/or generation of storm waters
that may require an NPDES permit. See, Motion for Summary
Judgment, Exhibit A (Conde Statement ¶¶ 5, 11; Gonzalez Statement
¶¶ 7, 12, 13), Exhibit 3. However, PRLA admits that it did
authorize the municipality (Vieques) in which the property is
located "to make those arrangements necessary for obtaining a
construction permit for the first phase" of the Quintas project,
which would consist of construction of 87 housing units. See,
Motion for Summary Judgment, Exhibits A, 2 (italics added).(5) It
is not completely clear on the record as it now stands that by
granting such permission to Vieques that PRLA did not, in fact,
implicitly authorize the activities which caused the discharge.
In sum, the parties' submissions in this case do not
establish that all material facts are undisputed as to PRLA's
control of the pollutants being discharged, which is key to
determining liability under the CWA. Friends of the Sakonnet v. Dutra, 738
F. Supp. 623, 631 (D.R.I. 1990). Any unexplained gaps in
materials submitted by the moving party, if pertinent to material
issues of fact, justify denial of a motion for summary judgment.
O'Donnell v. United States, 891 F.2d 1079 (3rd Cir. 1989). Accordingly,
PRLA's Motion for Summary Judgment is hereby, DENIED.
II. Complainant's Motion to Dismiss Without Prejudice
While Complainant agrees that PRLA should be dismissed from
this action, Complainant requests that the dismissal be without
prejudice. PRLA disagrees, maintaining that the dismissal should
be on the merits pursuant to its Motion for Summary Judgment.
The Rules of Practice provide at Section 22.14(e) that
"after the filing of an answer, the complainant may withdraw the
complaint, or any part thereof, without prejudice, only upon
motion granted by the Presiding Officer." Similarly, Federal
Rule of Civil Procedure 41(a)(2) provides that once an answer or
motion for summary judgment has been filed, the plaintiff may
voluntarily dismiss an action by Order of the Court, and such
dismissal is without prejudice unless otherwise specified on the
Order. The grant or denial of a dismissal is within the sound
discretion of the trial court. See, 9 Charles A. Wright and
Arthur R. Miller, Federal Practice and Procedure, Civil 2d § 2364 (1995).
No standard is provided in the Rules of Practice upon which
to rule on such a motion. Federal courts interpreting Rule
41(a)(2) normally grant such dismissal unless the defendant would
suffer legal prejudice as a result of the dismissal. McCants v.
Ford Motor Co., 781 F.2d 855, 856-57 (11th Cir. 1986). The mere
prospect of a second lawsuit does not constitute legal prejudice.
Radiant Technology Corp. v. Electrovert USA Corp, 122 F.R.D. 201, 203 (N.D.
Tex. 1988); Chodorow v. Roswick, 160 F.R.D. 522, 523 (E.D. Pa. 1995).
Since Rule 41(a)(2) only applies when an answer or a motion for
summary judgment has been filed by the defendant, "the mere
filing of an answer or a motion for summary judgment could not,
without more, be a basis for refusing to dismiss without
prejudice." Andes v. Versant Corp., 788 F.2d 1033, 1036 n. 4 (4th Cir.
1986)(denial of motion for summary judgment was proper where
defendant incurred substantial costs of discovery).
Federal courts have looked with disfavor on motions for
voluntary dismissal without prejudice when the party seeks to
avoid an expected adverse decision on motion for summary
judgment, however. Dismissal without prejudice has been denied
where defendant was entitled to summary judgment. Radiant Technology,
122 F.R.D. at 203-204 (dismissal improper where court would be
precluded from deciding pending case or dispositive motion);
Phillips, 77 F.3d at 358 (defendant was entitled to summary
judgment); Yoder v. Oestreich, 820 F.Supp. 405, 406 (W.D. Wisc.
1993)(motion for dismissal without prejudice denied where both
parties had filed motions for summary judgment, defendant put
forth extensive efforts on preparing its motion and plaintiff did
not respond to it but instead filed motion for dismissal after
the due date for the response); Pace v. Southern Express Co., 409 F.2d
331, 334 (7th Cir. 1969).
Here, however, PRLA has not shown that, at this time, it is
entitled to summary judgment, as concluded above. Therefore,
other factors may be considered in determining whether to dismiss
without prejudice.
Other factors considered by the Federal courts in
determining whether legal prejudice exists include the following:
the opposing party's effort and expense in preparing for trial,
the excessive and duplicative expenses of defending a second
action, excessive delay and lack of diligence on the part of the
movant, and the sufficiency of the explanation for the need for a
dismissal. Ohlander v. Larson, 114 F.3d 1531, 1537 (10th Cir. 1997);
Phillips U.S.A., Inc. v. Allflex U.S.A., Inc., 77 F.3d 354, 358 (10th Cir.
1996)(dismissal properly denied where case was pending over one
year, defendant's motion for summary judgment was pending four
months, and plaintiff lacked diligence in failing to respond but
instead filing motion for dismissal with little explanation);
United States v. Outboard Marine Corp., 789 F.2d 497, 502 (7th Cir.
1986)(interest in protecting environment from further damage by
immediate cleanup by EPA of hazardous waste site, avoiding delay
of years of anticipated litigation, justified dismissal without
prejudice of EPA's action to require defendants to conduct
cleanup); Pace, 409 F.2d at 334 (dismissal properly denied where
action had been pending one and a half years, considerable
discovery had been taken at substantial cost to defendant, and
defendant had fully supported its motion for summary judgment to
which plaintiff failed to respond); Wright and Miller, § 2364; cf.
Radiant, 122 F.R.D. at 204 n. 5 (refusing to evaluate the
sufficiency of plaintiff's explanation for dismissal). The
Courts acknowledge that not all of the factors must be resolved
in favor of one party for either dismissing or denying dismissal.
Ohlander, 114 F.3d at 1537; Phillips, 77 F.3d at 358.
The future uncertainty as to title to land and resultant
jeopardy to development of a project thereon also has been
considered as prejudice. Paulucci v. City of Duluth, 826 F.2d 780 (8th
Cir. 1987)(millions of dollars already expended, and future
financing on paper mill on the land allegedly jeopardized, no
explanation provided for voluntary dismissal) citing, Ferguson v. Eakle,
492 F.2d 26, 29 (3d Cir. 1974). However, a more recent decision
considering uncertainty over water rights resulting from
dismissal without prejudice has held that "the threat of future
litigation which causes uncertainty is insufficient to establish
plain legal prejudice." Westlands Water District v. United States, 100 F.3d
94, 96 (9th Cir. 1996).
This matter has been pending for less than a year. Although
Complainant has filed its Prehearing Exchange, PRLA, due to the
stay, has not, although it has submitted significant briefing
with its Motion for Summary Judgment. It does not appear that
Complainant has excessively delayed in filing its Motion for
Voluntary Dismissal.
Complainant's response to PRLA's Motion for Summary Judgment
was delayed, however, and not well supported. PRLA's Motion for
Summary Judgment was filed October 21, 1997. Pursuant to a
Motion for Extension of Time, Complainant was granted until
November 28, 1997 to respond to PRLA's Motion. Rather than
filing a response, Complainant submitted the Motion for Voluntary
Dismissal on November 28, 1997. It was not until December 11,
1997, thirteen days after the filing deadline, that Complainant
filed its opposition to PRLA's Motion. Moreover, Complainant
does not explain therein why dismissal should be without
prejudice or point to specific facts that are disputed.
Complainant merely alleges that it "has never agreed with the
PRLA's position that it is not liable under the CWA" and states
that there is no provision in the Rules of Practice for a
dismissal with prejudice. See, Complainant's Motion Opposing
Summary Judgment Motion, dated December 11, 1997.(6) Complainant
notes that CODEFIN informed EPA that it has no position on the
Complainant's Motion.
It is conceivable that dismissal without prejudice may
result in uncertainty as to title to the site and future
development of the housing project due to the potential for
Complainant to bring a future enforcement action against PRLA.
However, neither PRLA nor CODEFIN have challenged Complainant's
Motion on that basis.
Considering the factors discussed above, PRLA has not shown
that it would suffer legal prejudice if the Motion for Voluntary
Dismissal is granted. Therefore, Complainant's Motion for
Voluntary Dismissal is hereby GRANTED, and the Complainant
against PRLA dismissed without prejudice.
III. Complainant's Motion for a Default Order Against INPC
On March 31, 1997, INPC was served with the Complaint in
this action alleging that INPC violated the CWA. On May 5, 1997,
INPC sent to Complainant an informal letter, which was not filed
with the Regional Hearing Clerk, asserting no connection to the
Quintas housing project and denying any liability under the Clean
Water Act. Complainant responded to INPC's letter informally on
August 19, 1997, disagreeing with INPC's denial of liability.
INPC offered no response to Complainant's August 19, 1997 letter
and, to date, has not filed an answer to the Complaint or any
other document in this proceeding with the Regional Hearing
Clerk.
The Rules of Practice require that a written answer to the
complaint "must be filed with the Regional Hearing Clerk within
twenty (20) days after service of the complaint." 40 C.F.R. §
22.15(a). The Rules provide further that "[a] party may be found
to be in default (1) after motion, upon failure to file a timely
answer to the complaint." 40 C.F.R. § 22.17(a). Although INPC
sent a brief letter to the Complainant, denying any connection to
the Quintas project, the letter does not constitute "fil[ing] a
timely answer to the complaint." The Complaint having been
served on March 31, 1997, INPC's answer was due to be filed by
April 20, 1997. 40 C.F.R. § 22.15(a). INPC clearly has failed
to file a timely answer to the Complaint and is therefore in
default.
In the case of a default order, the Rules of Practice state
that "the penalty proposed in the complaint shall become due and
payable by respondent without further proceedings sixty (60) days
after a final order issued upon default." 40 C.F.R. § 22.17(a).
In this instance, however, considering the continued
participation of Respondent CODEFIN, the penalty cannot be fairly
apportioned until the liability and roles of all parties are
determined. Accordingly, the amount of the penalty to be issued
against INPC will be stayed until full resolution of the
dispute.(7)
ORDER
1. Respondent PRLA's Motion for Summary Judgment is DENIED.
2. Complainant's Motion to Dismiss Respondent PRLA Without Prejudice is GRANTED and the Complaint against PRLA is
hereby dismissed, without prejudice.
3. Complainant's Motion for a Default Order against Respondent
INPC is GRANTED. The imposition of a penalty against INPC
is STAYED until resolution of the issue of liability as to
the other Respondent in this proceeding.
4. Any document which has been submitted or will be submitted
by the parties to this proceeding, and which is in any non-English language, must be accompanied by a direct written
translation in English provided by a certified translator.
_____________________________
Susan L. Biro
Chief Administrative Law Judge
Dated: February 3, 1998
Washington D.C.
1. Section 308(a) authorizes EPA to require the owner or
operator of any point source to, inter alia, establish and maintain
records and make reports. Regulations promulgated at 40 C.F.R.
§§ 122.21 and 122.26, cited in the Complaint, require permit
applications for discharge of stormwater. Paragraph 402(p)(4) of
the CWA, which was not cited in the Complaint, authorizes EPA to
establish regulations setting forth permit application
requirements for stormwater discharges.
2. Section 22.15(a), 40 C.F.R. provides with respect to service of the
Answer, in pertinent part, "Where respondent (1) Contests any
material fact upon which the complaint is based . . . or (3)
contends that he is entitled to judgment as a matter of law, he
shall file a written answer to the complaint with the Regional
Hearing Clerk. Any such answer to the complaint must be filed
with the Regional Hearing Clerk within twenty (20) days after
service of the complaint."
3. The Prehearing Order specifically noted that the record
evidenced that Respondents PRLA and INPC had not filed answers to
the Complaint and instructed the Complainant to file evidence of
service so default orders could issue. At that time, the
undersigned was unaware that the day before, PRLA had filed a
Motion for Summary Judgment.
4. "Navigable waters" is defined in Section 502(7) of the CWA as
the waters of the United States, including the territorial seas.
5. This document is written in Spanish. A certified direct translation in
English should have accompanied the document. The parties may
not assume that the Judges who preside over this case have the
ability to accurately translate documents written in any non-English language.
6. While the Rules of Practice at 22.14(e) refer only to a
withdrawal of a complaint or part thereof without prejudice, they
do not preclude a complainant from moving to dismiss with
prejudice. Such a motion is permitted in Federal court, under
Federal Rule of Civil Procedure 41(a), which provides that
voluntary dismissal is without prejudice unless otherwise stated
in the notice or order of dismissal.
7. Although this ruling contravenes the literal language of
Section 22.17(a), the rule appears to have contemplated default
scenarios with only one respondent. Penalizing a defaulting
respondent when other respondents still remain active may lead to
an unjust allocation of the penalty. In the face of such
uncertainty, Section 22.01(c) provides, "Questions arising at any
stage of the proceeding which are not addressed in these rules or
in the relevant supplementary procedures shall be resolved at the
discretion of the . . . Presiding Officer."
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)