UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
IN THE MATTER OF )
)
FRED J. KRONAUGE ) Docket No. 5-CAA-95-017
)
Respondent )
ORDER FINDING RESPONDENT IN DEFAULT AND ASSESSING PENALTY
By order issued by the undersigned on September 30, 1996, a
procedural schedule for the filing of prehearing exchanges was
established. Respondent was directed to file on December 10, 1996
either: (a) its prehearing exchange or (b) a statement that it
elects to conduct cross-examination of EPA witnesses and to forgo
the presentation of answering evidence. Respondent has done
neither. By order issued March 4, 1997, Respondent was directed to
show cause on or before March 27, 1997 why a default order should
not be issued against it for "failure to comply with a prehearing
or hearing order of the Presiding Officer . . .," as provided in 40
C.F.R. § 22.17. Complainant was permitted to file a response to
Respondent's pleading on or before April 10, 1997. No response to
the March 4, 1997 show cause order was received.
Section 22.17(a), 40 C.F.R. § 22.17(a), permits a default
order to be issued against a party " . . . after motion or sua
sponte, upon failure to comply with a prehearing or hearing order
of the Presiding Officer . . . ." As noted above, Respondent
failed to comply with the undersigned's September 30, 1996 order.
Nor did Respondent file an answer to the March 4, 1997 show cause
order.(1)
Accordingly, Respondent is hereby found to be in default.
Pursuant to § 22.17 (a), all facts alleged in the complaint are
deemed admitted and Respondent is deemed to have waived his right
to a hearing. The findings of fact and conclusions of law are set
forth below.
DISCUSSION
Respondent Fred J. Kronauge is a "person" as defined at
Section 302(e) of the Clean Air Act, 42 U.S.C. § 7602(e). On or
before August 10, 1993, a demolition was conducted at a commercial
facility located at 124 Cedar Avenue, formerly 125 Sunrise, Dayton,
Ohio (124 Cedar facility). The 124 Cedar facility is and was a
"facility," as defined at 40 C.F.R. § 61.141.
The 124 Cedar facility demolition involved the wrecking and
taking out of load-supporting structures, and the subsequent
removal of the materials from the 124 Cedar facility, as defined at
40 C.F.R. § 61.141. The 124 Cedar facility demolition was subject,
inter alia, to the asbestos National Emission Standards for
Hazardous Air Pollutants (NESHAP) standards for demolition and
renovation operation. 40 C.F.R. § 61.145.
Respondent Fred J. Kronauge, 600 West Third Street, Dayton,
Ohio, was the owner of the 124 Cedar facility. Respondent was an
"owner of a demolition activity," as defined at 40 C.F.R. § 61.141,
with respect to the 124 Cedar facility demotion.
On August 10, 1993, representatives of the State of Ohio
Regional Air Pollution Control Agency (RAPCA) inspected the
demolition site where the 124 Cedar facility demolition was
conducted to determine compliance with the asbestos NESHAP.
Section 112(i)(3)(A) of the Act, 42 U.S.C. § 7412(i)(3)(A),
prohibits any person from operating a source in violation of an
emission standard, including the asbestos NESHAP. Violations of
the asbestos NESHAP are violations of Section 112(i)(3)(A) of the
Act, and subjects the violator to the imposition of civil penalties
under Section 113(d) of the Act, 42 U.S.C. § 7413(d).
Respondent was required by 40 C.F.R. § 61.145(b) to submit a
notice of intent to demolish or renovate to the Administrator EPA
pertaining to the 124 Cedar facility demolition. Pursuant to 40
C.F.R. § 61.04(b)(kk)(vi), Respondent was also required to submit
a notice to the RAPCA, pertaining to the 124 Cedar facility. To
date, neither the EPA nor RAPCA has received a notification of the
124 Cedar facility demolition because Respondent never submitted
such a notification to either of the above-named Agencies.
Therefore, Respondent Fred J. Kronauge's failure to provide the EPA
and RAPCA with a notification of demolition is a violation of 40
C.F.R. § 61.145(b)(1) and therefore of Section 112(i)(3)(A) of the
Act, and Section 114(a) of the Act, 42 U.S.C. § 7412(a).
Pursuant to Section 113(d(1) of the Act, 42 U.S.C. §
7413(d)(1), the Administrator of the EPA may assess a civil penalty
of up to $25,000 per day of violation, up to a total of $200,000,
for, inter alia, violations of Section 112 of the Act,
42 U.S.C. § 7412. Section 113(e)(1) of the Act, 42 U.S.C. §
7413(e)(1), authorizes the assessment of a civil penalty based upon
consideration of the seriousness and duration of the violation
alleged, the size of the business, the economic impact of the
penalty on the business, the Respondent's full compliance history
and good faith efforts to comply, payment by Respondent of
penalties previously assessed for the same alleged violations, the
economic benefit of noncompliance, and other factors as justice may
require.
Pursuant to Section 113(d)(1) of the Act, 42 U.S.C.
§ 7413(d)(1), the Administrator of EPA and the Attorney General
have determined that an administrative penalty action against
Respondent is appropriate, although the first alleged date of
violation occurred more than 12 months prior to the initiation of
this action.
After considering these factors, it is determined that
Respondent be assessed a civil penalty of $17,000. This proposed
penalty was calculated in accordance with the "Clean Air Act
Stationary Source Civil Penalty Policy" (October 25, 1991) and the
"Asbestos Demolition and Renovation Civil Penalty Policy" (May 11,
1992) (Penalty Policies). This calculation is explained in more
detail below.
Under the Penalty Policies, the seriousness of the alleged
violations is considered. Asbestos is a hazardous air pollutant
that is known to cause death and serious irreversible illness. The
notification requirement of the Asbestos NESHAP are essential to
U.S. EPA and its delegated agents in that it provides them with the
opportunity to ensure that renovation and demolition projects are
performed in a manner consistent with the Asbestos NESHAP. The
penalty policy generates an appropriately high factor associated
with notification violations.
The Asbestos Penalty Policy recommends a penalty of $15,000
for a first-time violation of the Asbestos NESHAP notification
requirement. Asbestos Penalty Policy at 15. This is appropriate
and is adopted. Then, Complainant recommends a $2,000 increase for
a sole proprietorship with under $100,000 of net current assets.
Since this is the lowest possible size of business to assign to
Respondent, it is adopted. General CAA Penalty Policy at 14.
The CAA also requires the penalty calculation to consider "the
economic impact of the penalty on the business." 42 U.S.C.
§ 7413(e). Pursuant to the General CAA Penalty Policy, at page 20,
"The Agency will generally not request penalties that are clearly
beyond the means of the violator." The penalty guidance continues,
"At the same time, it is important that the regulated community not
see the violation of environmental requirements as a way of aiding
a financially-troubled business. EPA reserves the option, in
appropriate circumstances, of seeking a penalty that might
contribute to a company going out of business."
There is no assertion by Respondent in its Answer to the
Complaint or elsewhere, or by Complainant, that the proposed
penalty of $17,000 will have an adverse effect on its business or
that the proposed penalty is clearly beyond the means of Respondent
to pay. Thus, no adjustment to the $17,000 is appropriate to
reflect the economic impact of the penalty on the business.
Similarly, there is no assertion or evidence by either party
that an adjustment to the $17,000 to reflect other statutory
factors such as (1) an increase in the penalty to capture the
economic benefit of noncompliance, (2) any adjustment based upon
the violator's compliance history and good faith efforts to comply,
or (3) payment by the violator of penalties previously assessed for
the same violation. Accordingly, no adjustment for these factors
shall be made.
Within 60 days after a final order is issued in this docket,
Respondent shall pay the assessed penalty of $17,000 by certified
or cashier's check payable to "Treasurer, the United States of
America," and shall deliver it, with a transmittal letter
identifying the name of the case and docket number of this
Complaint to:
United States Environmental Protection Agency
Region 5
Regional Hearing Clerk
The First National Bank of Chicago
P.O. Box 70753
Chicago, Illinois 60673
Respondent also should include on the check the name of the case
and the docket number. Respondent simultaneously shall send copies
of the check and the transmittal letter to:
John Shepler
Air Enforcement and Compliance Assurance Branch (AE-17J)
Air and Radiation Division
U.S. EPA, Region 5
77 West Jackson Boulevard
Chicago, Illinois 60604-3590
Louise Gross, Esquire
Assistant Regional Counsel
Office of Regional Counsel (CA-29A)
U.S. EPA, Region 5
77 West Jackson Boulevard
Chicago, Illinois 60604-3590
Since this order, as a default order, constitutes an initial
decision, 40 C.F.R. § 22.17(b), the effectiveness and appeal
provisions of 40 C.F.R. § 22.27 and 40 C.F.R. § 22.30,
respectively, are applicable.
Charles E. Bullock
Administrative Law Judge
Dated: August 26, 1997
Washington, D.C.
IN THE MATTER OF FRED J. KRONAUGE, Respondent
Docket No. 5-CAA-95-017
CERTIFICATE OF SERVICE
I certify that the foregoing Order, dated August , 1997, was
sent in the following manner to the addressees listed below:
Original by Regular Mail to:
Ms. Sonja Brooks Regional Hearing Clerk
U.S. Environmental Protection
Agency, Region 5
77 West Jackson Boulevard
Chicago, IL 60604
Copy by Regular Mail to:
Counsel for Complainant: Louise Gross, Esquire
Assistant Regional Counsel
U.S. Environmental Protection Agency, Region 5 (CA-29A)
77 West Jackson Boulevard
Chicago, IL 60604
Copy by Certified Mail, Return
Receipt Requested and by
Regular Mail to:
Counsel for Respondent: Michael J. Long, Esquire
1401 West Dorothy Lane
Kettering, OH 45409
Respondent: Mr. Fred Kronauge
c/o American Engine & Welding
600 West Third Street
Dayton, OH 45407
Marion Walzel
Legal Assistant
Dated: August , 1997
1. A copy of the September 30, 1996 order and a copy of the
March 4, 1997 show cause order were served upon Respondent's
counsel, Michael D. Long, Esquire, at 1401 West Dorothy Drive,
Kettering, Ohio 45409.
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)