Jump to main content.


[[pp. 28081-28130]] Acid Rain Program; Continuous Emission Monitoring Rule Revisions

Note: EPA no longer updates this information, but it may be useful as a reference or resource.


 


[Federal Register: May 21, 1998 (Proposed Rules)]
[Page 28081-28130]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr21my98-43]
 
[[pp. 28081-28130]] Acid Rain Program; Continuous Emission Monitoring Rule Revisions

[[Continued from page 28080]]

[[Page 28081]]

GCV value of 100,000 Btu per hundred scf, the value of the ``sulfur-to-
heat content'' ratio is 2.0 gr/mmBtu. Therefore, a candidate gaseous 
fuel would qualify to use the default SO2 emission rate of 
0.0006 lb/mmBtu for part 75 reporting purposes if the 720 hours of 
historical data demonstrate that the mean value of the sulfur-to-heat 
content ratio is 2.0 gr/mmBtu or less.
    To demonstrate that a unit qualifies to use Appendix D when 
combusting a gaseous fuel, the designated representative for the 
facility would be required to show that the gaseous fuel has a total 
sulfur content of 20 grains/100 scf or less. This demonstration would 
apply to all gaseous fuels. For gaseous fuels other than pipeline 
natural gas, the sulfur content information could come either from 
contractual information on the sulfur content based on routine vendor 
sampling and analysis or from historic fuel sampling data to show the 
gaseous fuel's sulfur content (see Docket A-97-35, Item II-I-9, Policy 
Manual, Question 2.15). For gaseous fuels that are produced in batches 
or lots with a relatively uniform sulfur content, such as liquefied 
petroleum gases, it would be sufficient to provide historical 
information on each batch over the past year. This approach was 
accepted by the Agency for six units combusting liquefied petroleum gas 
(see Docket A-97-35, Items II-C-14 and II-D-22).
    In addition to documenting the total sulfur content of the fuel, 
the owner or operator would be required to submit certain other fuel-
specific information. As previously noted, for units combusting 
pipeline natural gas, a designated representative would be required to 
provide contractual information to demonstrate that the natural gas is 
supplied under specification and has a hydrogen sulfide content less 
than or equal to 0.3 gr/100 scf. And historical data would have to be 
provided, as described above, to obtain permission to use the default 
SO2 emission rate of 0.0006 lb/mmBtu for a fuel other than 
pipeline natural gas. For other gaseous fuels that are not produced in 
batches with relatively uniform sulfur content, such as gaseous fuel 
generated through an industrial process (e.g., digester gas from a 
paper mill), since the sulfur content of the gaseous fuel could be 
highly variable, section 2.3.3.4 of today's proposed revisions to 
Appendix D would require a minimum of 720 hours of historical data 
documenting the sulfur content of the fuel under representative 
operating conditions. This information would allow the Agency to 
determine how variable the sulfur content is and if the daily sampling 
procedure under section 2.3.1 of Appendix D is sufficient to capture 
this variability without allowing the underestimation of sulfur 
content. If the sulfur variability were too great, continuous sampling 
using a gas chromatograph and hourly reporting of sulfur content would 
be required under today's proposed rule.
2. Fuel Sampling
    (a) Fuel Oil.
Background
    Diesel fuel is distillate fuel oil of grades No. 1 or 2. Diesel 
fuel is heavily refined and has a much lower sulfur content and greater 
consistency than other grades of fuel oil. Section 2.2 of Appendix D to 
the May 17, 1995 direct final rule provides three options for sampling 
of diesel fuel and two options for sampling of other fuel oils. First, 
for all fuel oils, including diesel fuel, daily manual sampling is 
allowed. Second, diesel fuel and other fuel oils may also be sampled 
continuously using an automated sampler according to ASTM D4177-82 
(Reapproved 1990), either using continuous drip sampling or flow 
proportional sampling. The samples would then be mixed to form a daily 
composite sample. Third, diesel fuel may be sampled ``as-delivered,'' 
upon receipt of a shipment. These sampling approaches were selected to 
ensure that sulfur content values would be as accurate as possible, 
would not underestimate SO2 mass emissions, and would 
account for any variability in the sulfur content of fuel.
    Many utilities have expressed concern about the cost of daily oil 
sampling (see Docket A-97-35, Items II-D-18, II-D-20, II-E-13, II-E-
14). Some utilities indicated that for a unit that burns oil every day, 
the cost of daily oil sampling is greater than the cost of 
SO2 CEMS and flow monitors. Furthermore, industry 
representatives provided information indicating that within a given 
shipment of fuel oil from a supplier, the variability in sulfur content 
is low (see Docket A-97-35, Items II-D-18 and II-D-59). Many companies 
already have state or Federal requirements for sampling of fuel from 
each truck delivery or in a storage tank on site at the plant whenever 
fuel is added to the storage tank (see Docket A-97-35, Item II-D-93). 
The storage tank is a tank at a plant that holds oil that is actually 
combusted by the unit on that day. In other words, no fuel will be 
blended between the time when a fuel lot is transferred to the storage 
tank and when the fuel is combusted in the unit. In other cases, such 
as EPA's NSPS regulations for industrial boilers under 40 CFR part 60, 
subpart Db, companies keep copies of fuel receipts from the supplier to 
indicate the sulfur content is below the required sulfur content. Based 
upon this information, EPA is proposing to reduce the required sampling 
frequency for fuel oil. This would be a significant reduction in burden 
and cost of using Appendix D, without causing underestimation of 
SO2 emissions.
Discussion of Proposed Changes
    Several utilities suggested that the Agency propose to allow 
sampling of each delivery of oil (see Docket A-97-35, Items II-D-18, 
II-D-20, II-E-13, II-E-22). Under this approach, either a facility or 
its supplier would sample each truck or barge containing oil before the 
fuel is transferred into a tank at the plant. If a delivery shipped in 
a group of trucks were purchased under the same order and were 
specified to have the same gross calorific value, density, and sulfur 
content, then only one sample would be necessary for the group of 
trucks. Samples taken by the supplier would not need to be split and 
kept on hand at the site. This approach is currently allowed only for 
diesel fuel under section 2.2.1.2 of Appendix D, but would be extended 
to apply to all fuel oils under today's proposed rule. This approach 
would be particularly useful to a facility that receives large, 
infrequent deliveries of fuel or to a facility that already has other 
State or Federal regulations requiring sampling of each truck or barge 
delivered to the plant.
    A similar approach suggested by another industry representative, 
allowing facilities to use a sample of oil taken from a tank belonging 
to the supplier before the oil is delivered, is also proposed in 
today's rulemaking. The supplier could take the sample and the facility 
would be able to use that value as long as it keeps records of the fuel 
analysis results from the supplier. This approach would be particularly 
useful to a facility that receives a delivery of oil from a single 
supplier's tank that is shipped in many different trucks. This approach 
also would be useful for a small facility that would prefer to rely on 
samples taken by the supplier rather than taking its own samples and 
paying for their analysis.
    Finally, the Agency proposes a third sampling approach, allowing a 
facility to sample oil manually from its storage tank at the plant 
whenever oil is added to the tank. This approach would yield samples 
that are more representative of the oil combusted because it would 
include any fuel remaining in the tank as well as all fuel added. 
Sampling from the storage tank at the plant would be

[[Page 28082]]

useful to a facility that burns oil infrequently and adds oil to its 
storage tank infrequently. It also would be helpful where a facility 
already has other State or Federal regulations requiring sampling after 
adding fuel to the storage tank.
    Both the ``before delivery'' and ``as delivered'' sampling 
approaches would require a sample for each ``lot'' of oil; 
consequently, a suitable definition of a ``lot'' is needed. For 
purposes of determining when an oil sample should be taken for the NSPS 
applicable to utility boilers, section 5.2.2.2 of Method 19 in Appendix 
A to 40 CFR part 60 relies on a definition of fuel ``lot'' developed by 
the American Society for Testing and Materials (ASTM). This definition 
states that ``the lot size of a product oil is the weight of product 
oil from one pretreatment facility and intended as one shipment (ship 
load, barge load, etc.).'' In essence, a lot is a single batch of oil 
that has uniform properties and is purchased from a single supplier and 
delivered to a buyer. Among those uniform fuel properties are gross 
calorific value, density, sulfur content, and viscosity. In today's 
rulemaking, EPA proposes to adopt this definition of a lot of oil for 
use in the Acid Rain Program.
    The Agency also considered whether it is appropriate to keep the 
current approach of daily manual oil sampling as an option. Although it 
seems unlikely that facilities would choose daily sampling option if 
they have the three options of sampling by lot, sampling upon addition 
of fuel to a storage tank, or continuous sampling, a utility group has 
requested that EPA retain daily manual sampling as an option. The 
agency is, therefore, proposing to retain daily manual oil sampling as 
an option in Appendix D to allow facilities this additional 
flexibility. An industry representative suggested that EPA could define 
the oil combusted during a 24-hour period as a lot. For the reasons 
discussed below and in the section addressing sulfur content, density, 
and gross calorific values used in calculations, EPA is not 
incorporating this suggestion in today's proposed rule.
    EPA also reconsidered whether it is necessary to require daily 
composite samples when samples are taken continuously with an automatic 
sampler. In today's proposal, the Agency is proposing that continuous 
samples may be composited on a weekly basis rather than daily. The 
Agency also considered allowing an even longer compositing period, such 
as a month, but is not proposing this option for the reasons discussed 
below. A weekly composite sample of oil that is sampled continuously 
would be an attractive option for a facility that wants the most 
representative and accurate sulfur content data possible. This also 
would be a useful option for those few facilities that receive oil via 
a pipeline, rather than in discrete lots.
Rationale
    Facilities wish to be able to perform less frequent fuel sampling 
in order to save money. From the information EPA has examined over the 
previous year, the Agency believes that less frequent oil sampling can 
be technically justified. Based upon information provided by utilities, 
the sulfur content of a lot of oil varies from sample to sample, with a 
standard deviation of 0.036 percent S to 0.063 percent S, or 5.62 to 
6.85 percent of the average sulfur content for all daily samples 
between deliveries (see e.g., Docket A-97-35, Item II-D-18). Density 
and gross calorific value of oil in a lot should vary even less than 
sulfur content, because sulfur is an impurity in the composition of the 
fuel and not an essential physical property of the oil, as is density. 
Furthermore, the difference between the sulfur content, density, gross 
calorific value, and carbon content of a fuel during the first daily 
sample after a new delivery is received and the average sulfur content, 
density, gross calorific value, and carbon content for all daily 
samples from between two deliveries is extremely small (see Docket A-
97-35, Items II-B-18 and II-D-18 for supporting information). 
Therefore, the Agency expects that the variability of fuel 
characteristics within a lot is low enough that only a single 
representative sample is necessary for the lot. Data have indicated 
that there could be a significant difference in sulfur content between 
shipments, however (see Docket A-97-35, Items II-B-12, II-B-18 and II-
D-18). The Agency believes that differences between lots, which could 
potentially result in the underestimation of SO2 emissions, 
can be dealt with by selecting a conservative sulfur content, density, 
or gross calorific value that would not be exceeded in any sample, 
rather than retaining more frequent sampling requirements. Therefore, 
today's proposal incorporates this approach.
    Prior to drafting today's proposed rule revisions, EPA requested 
comments on removing the option to perform daily manual oil sampling 
for Appendix D units. At least one utility group expressed interest in 
retaining the option to allow flexibility. The prime benefit to a 
facility from continuing to use daily manual sampling would appear to 
be that the facility could continue to use the same daily operating 
procedures and that reprogramming of a DAHS would not be necessary. 
Note that when using the approach of daily manual oil samples, a 
facility calculates SO2 mass emissions using the highest 
sulfur content in the previous 30 daily oil samples. Therefore, this 
approach requires more frequent analysis than either the proposed 
weekly composite sample for continuous samples or the proposed sampling 
by lot, and provides less accurate and more conservative results. The 
Agency believes it would be simpler and less confusing for both the 
Agency and for the regulated community to deal with a smaller number of 
approaches to sampling and calculating SO2 emissions. 
However, the Agency is retaining this option since at least some 
affected utilities want the flexibility to continue to use this option.
    EPA also considered the suggestion to define a 24-hour period as a 
lot in order to allow facilities to continue to perform daily manual 
sampling. EPA is not proposing this approach because of the added 
complexity, compared to keeping the current language in section 2.2.4 
of Appendix D concerning manual daily sampling of oil. If a lot were 
defined as an arbitrary 24-hour period, the other requirements in the 
current rule (e.g., conservative sulfur, gross calorific value, and 
density values used to calculate SO2 mass emission rate and 
heat input rate) would need to be retained to ensure that 
SO2 emissions were not underestimated. Furthermore, using 
the terminology of a ``lot'' for both a delivery and a period of time, 
while requiring different treatment of sample data from the two 
different types of ``lots,'' could potentially be confusing. It seems 
preferable to keep the current language for daily manual samples.
    Because the Agency now believes it is appropriate to sample each 
fuel lot instead of sampling daily, the Agency reconsidered whether 
daily composite samples are necessary when a facility performs 
automated continuous sampling. Because continuous samplers take fuel 
samples multiple times each hour, they are highly representative of the 
oil being burned. Flow proportional samplers take samples automatically 
when a certain volume or mass of fuel has passed by, rather than during 
a particular time period. Generally, automatic samplers take multiple 
samples each hour; however, only one sample per hour is required under 
section 2.2.3 of Appendix D of the current rule. Even if the 
compositing time period is extended, the composite sample will be 
representative of the sulfur content, density, and gross calorific 
value of the oil between samples. Therefore, the Agency believes

[[Page 28083]]

that the compositing period could be extended from a day to as long a 
period as a month. However, EPA believes that it is unlikely that any 
container for taking samples from an automatic sampler would be large 
enough to accommodate all automatic samples taken during a month. In 
addition, at least one industry representative suggested that weekly 
composite samples were appropriate (see Docket A-97-35, Item II-D-30). 
Therefore, in section 2.2.3 of today's proposed rule, EPA would extend 
the allowable length of the compositing period for automatic samples to 
one week. The Agency believes this will make automatic sampling less 
costly, while taking into account the physical limitations of sampling 
equipment.
    (b) Gaseous Fuels.
Background
    Section 2.3 of Appendix D, as revised in the May 17, 1995 direct 
final rule, provides only one approach for sampling gaseous fuel: under 
section 2.3.1, gaseous fuel sampling must be performed daily. 
Relatively few utilities perform daily sampling upon gaseous fuels, 
choosing instead to use a default SO2 emission rate for 
pipeline natural gas. In part, this is because the vast majority of 
gaseous fuel used by power plants is pipeline natural gas. Under 
section 2.3.2 of Appendix D, facilities may calculate SO2 
mass emissions from pipeline natural gas using a default emission rate 
instead of performing fuel sampling. Because of the difficulty and 
potential danger of sampling gaseous fuel, gas sampling is generally 
conducted by the supplier, rather than by the facility.
    Those few utilities combusting gaseous fuels other than pipeline 
natural gas have expressed concern about the difficulty and expense of 
daily sampling, particularly in comparison to the value of 
SO2 allowances for low SO2 emissions from 
relatively clean fuel (see, e.g., Docket A-97-35, Items II-E-11, II-E-
20). For gaseous fuels that are delivered in discrete batches or 
``lots,'' one would expect the gaseous fuel to behave like an ideal 
gas; sulfur should be evenly distributed throughout the batch. On this 
principle, the Ohio Environmental Protection Agency allowed a plant to 
take propane samples from each discrete delivery, rather than on a 
daily basis (see Docket A-97-35, Items II-C-14 and II-D-22).
Discussion of Proposed Changes
    Today's proposal incorporates three different sampling approaches 
for gaseous fuels: sampling by lot, daily sampling, and continuous 
sampling with a gas chromatograph. For gaseous fuel that is delivered 
in discrete lots, such as liquefied petroleum gas, the gaseous fuel 
could be sampled either daily or for each lot delivered. Any gaseous 
fuels other than pipeline natural gas that are not delivered in 
discrete lots, such as digester gas or sour natural gas pumped directly 
from a field, would, at a minimum, need to be sampled daily. The 
samples could be taken either by the supplier or by the facility. 
However, if the average sulfur content and sulfur variability of such a 
fuel were too high (i.e., mean sulfur content > 7 gr/100 scf and 
standard deviation from the mean > 5 gr/100 scf, based on 720 hours of 
representative historical data), continuous sampling with a gas 
chromatograph and hourly reporting of sulfur content would be required.
Rationale
    The approach of sampling upon a lot or discrete delivery of gaseous 
fuel is being incorporated into today's proposed rule for the following 
reasons. The Agency believes that discrete deliveries are sufficiently 
different from pipeline transmission of fuel that a different sampling 
approach is appropriate. According to the ideal gas law, all gas within 
an enclosed volume is mixed with a consistent composition; therefore, a 
single sample should be representative of all gas in the volume. 
Although gaseous fuels delivered by lot, such as liquefied petroleum 
gas, are higher in sulfur content and have a wider range of sulfur 
contents than pipeline natural gas, they still have relatively low 
sulfur contents compared to liquid and solid fuels. Thus, less frequent 
gas sampling appears appropriate, based on the small difference in the 
accuracy of calculated SO2 mass emissions. For this same 
reason, the Agency allowed as-delivered sampling for diesel fuel in the 
May 17, 1995 direct final rule (see Docket A-94-16, Item II-F-2). 
Finally, because of the difficulty of sampling gaseous fuels, EPA 
believes that it is less burdensome and less dangerous if gas sampling 
is conducted by the gas supplier. It is the Agency's understanding that 
the sampling for a gas in a discrete delivery or lot is typically 
conducted once for the lot, rather than on a daily basis. Through a 
petitioning process, EPA has already allowed one utility to perform 
sampling upon a lot or discrete delivery of gaseous fuel (see Docket A-
97-35, Items II-C-14 and II-D-22).
    EPA is proposing to require daily or continuous sampling of gaseous 
fuels other than pipeline natural gas or the equivalent that are not 
shipped in discrete lots, such as sour natural gas pumped directly from 
a field, landfill gas, or digester gas. Such gaseous fuels cannot be 
guaranteed to be stable in sulfur content. Therefore, proposed section 
2.3.3.4 in Appendix D would require a minimum of 720 hours of 
representative historical data to characterize the sulfur variability 
of such fuels. For the 720 hours of demonstration data, the mean value 
and standard deviation of the fuel sulfur content would be calculated. 
If the mean value does not exceed 7 gr/100 scf (equivalent to about 10 
ppm of SO2 emissions to the atmosphere), daily sampling 
would suffice. If the mean value is greater than 7 gr/100 scf, however, 
the variability of the sulfur content would be assessed in terms of the 
standard deviation. If the standard deviation exceeds 5 gr/100 scf, the 
sulfur variability would be considered too high and continuous sampling 
of the fuel with a gas chromatograph would be required. If continuous 
sampling were required, the owner or operator would have to implement a 
quality assurance program for the gas chromatograph. A copy of the QA 
plan would be kept on-site, suitable for inspection. For fuel with a 
low average sulfur content or a low sulfur variability, daily sampling 
would be sufficient. However, for gaseous fuel with a higher sulfur 
content, if the sulfur variability were too great, continuous sampling 
of the fuel with a gas chromatograph and hourly reporting of sulfur 
content would be required.
3. Sulfur, Density and Gross Calorific Value Used in Calculations
    (a) Fuel Oil.
Background
    The hourly SO2 mass emissions rate due to combustion of 
oil is calculated using the mass flow rate of oil combusted and a 
sulfur content value from a sample. If a unit's oil flow rate is 
measured with a volumetric fuel flowmeter rather than a mass fuel 
flowmeter, then it will be necessary to determine the mass flow rate of 
oil from the volume of fuel and a density value from an oil sample. The 
heat input rate is calculated using the flow rate of oil multiplied by 
the gross calorific value (GCV) of a sample.
    The sulfur content, density, and GCV used to calculate emissions 
and heat input depend upon the oil sampling method used. Some sampling 
methods are more accurate than others. For example, for flow 
proportional or continuous drip sampling, the actual sulfur content 
from a sample is used to calculate SO2 mass emissions. 
However,

[[Page 28084]]

when daily manual samples are taken under section 2.2.4 of Appendix D, 
a facility must use the highest fuel sulfur content recorded at that 
unit from the most recent 30 daily samples, which is not necessarily 
the sulfur content of the fuel being burned at any particular time. For 
units where diesel fuel is sampled upon delivery, section 2.2.1.2 
instructs a facility to calculate SO2 emissions using the 
highest sulfur content of any oil supply combusted in the previous 30 
days that the unit combusted oil. In daily manual sampling and as-
delivered sampling, conservative sulfur values are used to avoid the 
possibility of underestimating SO2 mass emissions due to 
variations in sulfur content. Gross calorific values are taken from the 
most recent sample, rather than using the highest value in the previous 
30 days, because, for natural gas, GCV is more consistent than sulfur 
content.
    Today's proposed rule includes changes to the sampling frequency 
for oil. Therefore, it is also necessary to make corresponding changes 
to the sulfur content, density, and GCVs to be used in calculations. 
For example, where oil samples would no longer be taken daily, it would 
be inappropriate to calculate SO2 mass emissions based upon 
a certain number of daily samples. In developing today's proposal, EPA 
considered what fuel analysis data values for sulfur content, density, 
and GCV would be appropriate and consistent with the approaches for 
taking manual samples. The appropriate sulfur content, density, and GCV 
values were considered for manual samples taken from a storage tank at 
the facility whenever fuel is added to the tank, for samples taken from 
each lot before the delivery is transferred from tank trucks or barges, 
and for samples taken from the fuel supplier's storage tank.
Discussion of Proposed Changes
    EPA has re-evaluated the sulfur content, density, and GCVs to be 
used to calculate SO2 mass emissions and heat input based 
upon the new oil sampling approaches. For daily manual oil sampling, a 
facility would continue to use the highest sulfur content from previous 
30 daily samples, and the actual density and GCV. For continuous oil 
sampling with an automatic sampler, a facility would continue to use 
the actual sulfur content, density, and GCV. For the two new methods of 
manual sampling, EPA considered whether conservative or actual values 
should be used to calculate emissions and heat input. EPA also 
considered whether the same type of calculational value should be used 
for sulfur content, density, and GCV. For example, if conservative 
sulfur content and density values are used to calculate the 
SO2 mass emission rate, should a conservative or an actual 
measured GCV be used to calculate the heat input rate?
    For manual samples taken from a storage tank at a plant whenever 
fuel is added to the tank, EPA considered the following options: (1) 
using the highest sulfur content and density from the previous three 
samples, and the actual GCV, (2) using the highest sulfur content from 
the previous three samples, and the actual density and GCV, (3) using 
the actual sulfur content, density, and GCV, (4) using the highest 
sulfur content, density, and GCV from the previous calendar year, and 
(5) using the maximum sulfur content, density, and GCV allowed by fuel 
purchase contract with the fuel supplier. The third, fourth, and fifth 
options are incorporated into today's proposal in section 2.2.4.2. 
Under this approach, a facility would take a sample from the storage 
tank whenever fuel is added to the tank. No blending of fuel would be 
allowed from the time the oil is sampled until the fuel is combusted by 
the unit. The sample would be analyzed for sulfur content, density, and 
GCV. Based on the selected option (3, 4, or 5), the appropriate values 
would then be used to calculate the SO2 mass emission rate 
and the heat input rate from the date and hour in which the transfer of 
oil is complete until the date and hour when oil is again added to the 
tank.
    EPA considered several different options for the case where a 
facility or its supplier would sample each oil delivery (or the 
supplier's storage tank) before the fuel is transferred into a tank at 
the plant. EPA considered whether or not these values needed to be 
conservative and concluded that there was a real possibility of 
underestimating SO2 emissions by using the fuel analysis 
values from a delivery. The options that EPA considered to avoid the 
underestimation were: (1) using the highest sulfur content and density 
from all samples taken from oil combusted during the previous 30 days, 
and the actual GCV, (2) using the maximum sulfur content, density, and 
GCV in the fuel purchase contract specifications, (3) using the highest 
sulfur content, density, and GCV from a sample taken in the previous 
calendar year, and (4) using the highest sulfur content, density, and 
GCV ever recorded for the unit. The second and third options are 
incorporated into today's proposed rule in section 2.2.4.3 of Appendix 
D.
    Under the selected options, a facility or its supplier would need 
to sample a delivery of fuel before it is transferred into a storage 
tank. The facility would then need to keep records of the fuel 
analytical results for three years. The facility would use the 
conservative value it selected under option (2) or (3), above, in order 
to calculate the SO2 mass emission rate and the heat input 
rate. If an as-delivered sample were ever analyzed and found to have a 
sulfur content, density, or GCV that exceeded the value being used in 
calculations (i.e., the contract specification, or the maximum value 
measured in the previous calendar year), then the new sampled value 
would be used to calculate the SO2 mass emission rate or the 
heat input rate, as follows. For a unit using a default value of the 
maximum value measured during the previous calendar year, that new 
sample value would become the new default value and would be reported 
for the remainder of the current year and the next year, unless 
superseded by a higher sampled value. For a unit using a default value 
of a contract specification, the new sample value would continue to be 
used as the new default value instead of the contract specification 
value, unless superseded by a higher sampled value or by a new 
contract.
Rationale
    EPA considers continuous sampling and the measurement of fuel from 
a storage tank at a plant after each addition of fuel to the tank to be 
highly accurate methods that will be representative of the fuel 
combusted in a unit. However, if samples are taken from the truck or 
barge used to ship the fuel, or if samples are taken ``as-delivered,'' 
the sample values will not necessarily accurately reflect the oil being 
combusted by the unit at any particular time (see Docket A-97-35, Item 
II-E-22). For example, a storage tank could contain oil with an average 
sulfur content of 0.6 percent. Then a new delivery with a sulfur 
content of 0.4 percent is received and transferred to the tank. The 
``as-delivered'' sample value from the delivery truck would 
underestimate the emissions at that time, since the fuel actually 
combusted will combine a mixture of the old fuel supply in the storage 
tank and the new fuel that is added. Thus, a more conservative sulfur 
value should be used to calculate SO2 emissions if samples 
are taken from the delivery containers or from a container used by the 
oil supplier.
    For density and GCV, today's proposal, at the suggestion of some 
industry representatives, uses conservative values determined by the 
same method for both parameters (see Docket A-97-35, Item II-E-24). 
This

[[Page 28085]]

has the advantage of being easy to remember and to program. However, if 
greater accuracy is desired, a facility would always have the option of 
using actual sulfur content, density, and GCVs if it took samples from 
its storage tank after each addition of fuel to the tank, or if it took 
continuous, automatic samples.
    EPA considered which conservative values would be appropriate for 
sulfur, density, and GCV. EPA at first considered using the maximum 
value from all oil supplies combusted in the previous 30 days. This is 
similar to the current wording of section 2.2.1.2 of Appendix D for 
calculation of SO2 emissions from diesel fuel as-delivered 
sampling. However, in the process of implementing this provision of 
part 75, EPA found this wording was somewhat confusing and issued 
policy guidance to clarify section 2.2.1.2 of Appendix D (see Docket A-
97-35, Item II-I-9, Policy Manual, Question 2.9). This policy 
essentially directs facilities to keep track of the amount of fuel used 
as well as its sulfur content. Because of the more complicated nature 
of this accounting, some industry representatives suggested that it 
would be simpler to use a conservative default value that would not 
require tracking fuel usage (see Docket A-97-35, Item II-E-24). Of the 
default values considered, EPA felt that the most appropriate default 
values would be the maximum values established by agreement with the 
fuel supplier through a contract or the maximum measured value from all 
samples in the previous calendar year. Contractual limits should be 
higher than or equal to the actual sulfur content, density, or GCV. 
Because not all units would necessarily have a fuel contract limiting 
oil sulfur content, density, or GCV, EPA is also proposing to provide 
the option of using the maximum oil sulfur content, density, or GCV in 
the previous calendar year.
    The Agency also considered whether the current provisions of 2.2.4 
of Appendix D should be retained for calculation of SO2 
emissions using the highest sulfur from the previous 30 daily samples 
when performing daily manual sampling. As discussed above in Section 
III.P.2(a) of this preamble on oil sampling frequency, the Agency is 
proposing to retain the option as requested by at least one utility 
representative.
    (b) Gaseous Fuels.
Background
    The vast majority of Acid Rain units which burn gaseous fuels 
combust pipeline natural gas. Section 2.3.2 of Appendix D contains a 
provision for calculation of SO2 mass emissions from 
pipeline natural gas using a default SO2 emission rate in 
lb/mmBtu and the heat input rate of pipeline natural gas. However, if a 
facility or its supplier is sampling gaseous fuel for sulfur content, 
either because it is not pipeline natural gas or because the facility 
chooses to use a sampled value, then Appendix D requires the facility 
to calculate the SO2 mass emission rate using the sulfur 
content of the sample and the volume of gas combusted, and to calculate 
the heat input using the GCV of the sample and the volume of gas 
combusted (see Equations D-5 and F-20). Because of the nature of 
gaseous fuels, they are always measured with a volumetric fuel 
flowmeter. The formulas for calculating the SO2 mass 
emission rate and the heat input rate use volume directly and do not 
require information on gas density. The current provisions of Appendix 
D allow a facility to calculate the SO2 mass emission rate 
and the heat input rate using the actual value from a daily sample of 
gaseous fuel.
    When the provisions of section 2.3 of Appendix D were added to part 
75 in the May 17, 1995 direct final rule, EPA presumed that virtually 
every utility combusting gaseous fuel was combusting pipeline natural 
gas. However, the Agency found that utilities were combusting other 
types of gaseous fuels. One utility submitted a monitoring plan and a 
certification application for fuel flowmeter monitoring systems that 
indicated the utility was also using propane liquefied petroleum gas 
(LPG) (see Docket A-97-35, Item II-D-6). The utility indicated that it 
wished to use the default emission rate factor reserved for pipeline 
natural gas in its monitoring plan and later petitioned the Agency 
specifically for permission to use the default emission rate factor of 
0.0006 lb/mmBtu. In conversations with utility staff, EPA found that 
the utility wanted to avoid the expense of additional daily samples and 
the trouble of entering daily sulfur values manually into its data 
acquisition and handling system (see Docket A-97-35, Items II-E-11, II-
E-20). The Agency eventually approved a revised petition for the 
utility that allowed the utility to take propane samples from each 
discrete delivery, rather than on a daily basis, where the utility 
calculates sulfur dioxide emissions from propane by using the highest 
sulfur content recorded during the previous 365 days and reports these 
data in its quarterly electronic data report (see Docket A-97-35, Items 
II-C-14 and II-D-22).
    The Agency found that there were also some utilities burning 
gaseous fuels that were by-products of an industrial process (see 
Docket A-94-16, Item II-D-71). EPA had concerns that such ``digester 
gas'' might have a more variable sulfur content than pipeline natural 
gas, since the gaseous fuel would begin with a higher sulfur content 
than pipeline natural gas and would not necessarily go through a 
process that would reduce and stabilize the sulfur content.
Discussion of Proposed Changes
    In today's proposed rule, the provisions for sampling gaseous fuels 
are found in section 2.3.1 of Appendix D. For gaseous fuels that are 
delivered in discrete lots, a facility would use conservative values 
for sulfur content and GCV to calculate the SO2 mass 
emission rate and the heat input rate. For the sulfur content value, 
the highest sampled sulfur content from the previous calendar year or 
the maximum value allowed by contract would be used to calculate the 
SO2 mass emission rate. For GCV, the highest of all sampled 
values in the previous calendar year or the maximum value allowed by 
contract would be used to calculate the heat input rate. If, for any 
gas sample, the assumed sulfur content or GCV were exceeded, the 
sampled value would become the new assumed value. For units using the 
contract value, the sampled value would continue to be used unless a 
new (higher) contract specification were put in place or unless an even 
higher sampled value is obtained. For units using the maximum value 
from the previous year, the sampled value would continue to be used for 
the remainder of the current year and for the next calendar year unless 
it was superseded by an even higher sampled value.
    For any gaseous fuel where daily fuel sampling is required, a 
facility would use the highest sulfur in the previous 30 daily samples. 
For gaseous fuels other than pipeline natural gas, where daily sampling 
of sulfur content is required, the highest GCV from the previous 30 
daily samples would be used. For pipeline natural gas, where monthly 
sampling of GCV only is required, the actual measured GCV, the highest 
of all sampled values in the previous calendar year, or the maximum 
value allowed by contract would be used.
    For a gaseous fuel that is not produced in batches and that has a 
relatively high sulfur content and a high sulfur variability, 
continuous sampling with a gas chromatograph would be required. Sulfur 
content would be reported as actual measured hourly average values. The 
GCV would also be determined on an hourly basis, or,

[[Page 28086]]

alternatively, the highest value in the previous 30 unit operating days 
could be reported.
Rationale
    For gaseous fuel supplied in discrete deliveries, EPA is proposing 
to take the same approach as for fuel oil that is being delivered to a 
plant by barge or truck. EPA has already approved this approach with 
one utility that combusts liquefied petroleum gas (see Docket A-97-35, 
Items II-C-14 and II-D-22). Because a discrete delivery of gaseous fuel 
would be maintained in an enclosed chamber with a relatively constant 
temperature and pressure, one would expect the gaseous fuel to behave 
like an ideal gas. Thus, sulfur and other constituents of the fuel 
should be evenly distributed throughout the delivery of fuel. Using 
conservative values to calculate the SO2 mass emission rate 
and the heat input rate should account for any variability between 
deliveries. Furthermore, this reduces the number of changes that would 
be made to a data acquisition and handling system to add fuel supply 
data.
    For gaseous fuel other than pipeline natural gas, where daily fuel 
sampling is required, EPA considered leaving unchanged the current 
provisions of section 2.3.1 of Appendix D that would allow a utility to 
use the actual value from a day's sample to calculate the 
SO2 mass emission rate and the heat input rate. However, the 
Agency believes that it is appropriate to change the sulfur content 
value to be a somewhat conservative historical value. This is because 
the Agency has concerns that there may be some gaseous fuels other than 
natural gas, such as digester gas, that may have significant 
variability in their sulfur content over the course of a day or a 
longer period of time. This might result in the underestimation of the 
SO2 mass emission rate.
    In the case of fuel oil, some industry representatives suggested it 
was simplest to determine the appropriate conservative values for 
sulfur content, density, and GCV by the same method (see Docket A-97-
35, Item II-E-24). With one exception (for fuels with relatively high 
sulfur content and high sulfur variability), today's proposal follows 
this suggestion for gaseous fuels. The proposal uses the highest sulfur 
content and the highest GCV from the previous 30 daily samples. This is 
currently the procedure used to determine the sulfur value used in 
calculations from daily manual oil samples. Since this algorithm for 
daily manual oil sample calculations is already being used by many 
software programmers, it is a good conservative value to use for daily 
samples in this case. The Agency notes that currently, the heat input 
is calculated using the actual sampled GCV and that this change would 
require software reprogramming for units where gaseous fuel is sampled 
daily. However, for pipeline natural gas that is sampled monthly for 
GCV, facilities could continue to use the actual GCV measured in a 
monthly sample. The other two options are more conservative and would 
require software changes. The Agency requests comment on the proposal 
to use the more conservative GCV value to determine the heat input rate 
for gas combustion when gaseous fuel is sampled daily (which differs 
from the current procedure in section 2.3.1.3 of Appendix D and section 
5.5.2 of Appendix F).
    For gaseous fuel that has a relatively high sulfur content and high 
sulfur variability, daily sampling is not considered adequate to ensure 
that SO2 emissions will not be underestimated. Therefore, 
for such fuels, continuous sampling with a gas chromatograph and hourly 
reporting of sulfur content would be required. For GCV, which is 
expected to be less variable than sulfur content, either the actual 
hourly measured value or the highest GCV value obtained in the last 30 
unit operating days could be reported.
4. Missing Data Procedures for Sulfur, Density, and Gross Calorific 
Value
Background
    (a) Fuel Oil. The May 17, 1995 direct final rule included missing 
data procedures for missing analytical information on sulfur content, 
density, and GCV in section 2.4 of Appendix D. These procedures are 
based on a daily sampling frequency. For example, missing sulfur 
content, density, or GCV data are to be calculated using the highest 
measured sulfur content, oil density, or GCV during the previous thirty 
days when the unit burned oil. This was intended to mean that the 
substitute data values are to be based on the previous thirty daily oil 
samples for which data are available.
    In order to ensure that a DAHS is capable of implementing the 
missing data procedures required by the rule, Sec. 75.20(c)(7) and 
Sec. 75.20(g)(1)(ii) require testing of each DAHS. EPA issued policy 
guidance discussing how facilities should report the results of these 
tests for units measured with fuel flowmeters. This policy guidance 
provided a form checklist that facilities could use to show the results 
of their own tests of the missing data substitution procedures (see 
Docket A-97-35, Item II-I-9, Policy Manual, Question 15.9). Some 
utilities objected to testing the DAHS missing data procedures on the 
grounds that they should never miss sample data. In part, this would be 
because the facility is required, under section 2.2.5 of Appendix D, to 
split its sample and keep a portion. One utility offered to substitute 
the maximum potential sulfur content, which would require less 
complicated DAHS programming than using the maximum sulfur content of 
the previous 30 daily samples.
    (b) Gaseous Fuels. Section 2.4.1 of Appendix D, as revised by the 
May 17, 1995 direct final rule, provides missing data substitution 
procedures for missing sulfur data from daily samples of gaseous fuel. 
The DAHS is required to substitute the highest measured sulfur content 
recorded during the previous 30 days when the unit combusted gaseous 
fuel. As for oil, this was intended to be the highest sulfur value from 
the previous 30 daily samples with available sulfur values. Section 
2.4.2 of Appendix D requires the substitution of the highest measured 
GCV recorded during the previous three months that the unit burned 
gaseous fuel when data are missing from a monthly gaseous fuel sample. 
As for fuel oil, the missing data procedures for gaseous fuels are 
linked to the frequency of fuel sampling.
    A utility indicated to EPA that because it receives gas sampling 
information from its supplier, it should never have missing data for 
GCV. The utility suggested that it should not have to go to the expense 
of programming its DAHS for missing data procedures that should never 
need to be used. This argument was similar to that used by another 
utility when referring to missing data procedures for manual samples of 
fuel oil taken upon each delivery.
Discussion of Proposed Changes
    EPA proposes to revise the missing data substitution procedures for 
both fuel oil and gaseous fuel, in order to simplify them. For any 
instance in which the sulfur content, GCV, or density value is missing, 
the maximum potential value would be reported until the results of a 
subsequent valid sulfur content analysis, GCV determination, or density 
measurement are obtained. The proposed appropriate maximum potential 
values are specified in the table below. The default values for sulfur 
content, GCV, and density of residual oil and diesel fuel were taken 
from handbook values (see Docket A-97-35, Item II-A-7). The default 
maximum sulfur content values for gaseous fuel are consistent with the 
maximum sulfur content allowed under

[[Page 28087]]

the definition of natural gas and the de facto maximum sulfur content 
of pipeline natural gas, based on the proposed definition. Thus, any 
gas with a sulfur content that did not allow it to qualify as pipeline 
natural gas (i.e., greater than 0.30 gr/100 scf) but still allowed it 
to be measured following Appendix D procedures (i.e., total sulfur 
content not exceeding 20.0 gr/100 scf) would have a default maximum 
potential sulfur content of 20.0 gr/100 scf. The default values for GCV 
of gaseous fuels were taken from handbook values (see Docket A-97-35, 
Item II-I-1). For pipeline natural gas, it is assumed that the gas is 
primarily methane (GCV of 1050 Btu/scf) with a small amount of other 
hydrocarbons with a higher GCV (see Docket A-97-35, Item II-E-19). For 
other gaseous fuels, it is assumed that they are primarily butane (GCV 
of 2100 Btu/scf), the hydrocarbon gas with the highest GCV of gases 
commercially used for fuel.

                   Maximum Potential Default Values for Sulfur Content, Density, and GCV Data                   
----------------------------------------------------------------------------------------------------------------
                Parameter                             Fuel                  Maximum potential  default value    
----------------------------------------------------------------------------------------------------------------
Sulfur content..........................  residual oil...............  3.5 percent by weight.                   
                                          diesel fuel................  1.0 percent by weight.                   
                                          pipeline natural gas.......  0.30 gr/100 scf.                         
                                          gaseous fuels with sulfur    20.0 gr/100 scf.                         
                                           content greater than                                                 
                                           pipeline natural gas.                                                
GCV/heat content........................  residual oil...............  19,500 Btu/lb.                           
                                          diesel fuel................  20,000 Btu/lb.                           
                                          pipeline natural gas.......  1100 Btu/scf.                            
                                          gaseous fuels with sulfur    2100 Btu/scf.                            
                                           content greater than                                                 
                                           pipeline natural gas.                                                
Oil Density.............................  residual oil...............  8.5 lb/gal,                              
                                          diesel fuel................  7.4 lb/gal.                              
----------------------------------------------------------------------------------------------------------------

Rationale
    (a) Fuel Oil. It seems possible that a facility might occasionally 
miss a sample taken with an automatic sampler, and thus, would have 
missing data. Therefore, today's proposal includes a provision for 
substitution of missing sulfur content, density, and GCV data from 
continuous, automatic sampling.
    Based upon comments from some utilities, it seems relatively 
unlikely that both a facility and its supplier would miss performing a 
sample during a delivery. Both a facility and its fuel supplier will 
want to verify that the fuel delivered is actually supplying the heat 
content that it is supposed to, either under a contract or a fuel 
specification; thus, both a facility and its fuel supplier will have an 
incentive to ensure sampling takes place for a delivery. Furthermore, 
if samples taken by a facility are split, then there should generally 
be the ability to provide analytical data for that fuel, even if test 
results were somehow lost. Because the event of missing fuel samples is 
unlikely for as-delivered samples, EPA believes that it would be 
appropriate to establish a simple, conservative value that could easily 
be substituted in a data acquisition and handling system. This would be 
easier to program than using historical values that require tracking 
fuel usage over an extended period of time.
    EPA is specifically proposing the most conservative (maximum 
potential) values for missing data purposes. This would ensure that 
substituted missing data values would be less advantageous to a 
facility than taking samples and using sulfur content, density, and GCV 
data from samples. In addition, several utilities suggested to EPA that 
this was a reasonable approach (see Docket A-97-35, Item II-E-24).
    (b) Gaseous Fuels. As mentioned previously, gas sampling is 
generally performed by fuel suppliers because of the difficulty and 
potential danger of opening up a pressurized pipe containing a highly 
flammable gas. It seems extremely unlikely that a fuel supplier would 
not have information available on the sulfur content or GCV of gaseous 
fuel, since industrial customers will purchase fuel or agree to a 
contract based upon these characteristics. The exception to this might 
be gaseous fuel manufactured through an industrial process that is not 
produced specifically for sale as a fuel, such as digester gas. In 
today's proposed rule, EPA is using the same reasoning as above for 
missing manual fuel oil sample data and is using the same basic 
substitution approach for missing sulfur content and GCV data for 
gaseous fuel.
    EPA considered keeping the existing missing data substitution 
procedures from sections 2.4.1 and 2.4.2 of Appendix D for missing data 
from gaseous fuel. This would have the advantage of requiring no 
reprogramming of software for facilities already following the existing 
procedures. EPA also considered using the maximum sulfur content or GCV 
from the previous calendar year, the same procedure proposed in today's 
rule for calculation of SO2 mass emission rate or heat 
input, for discrete deliveries of gas or for manual samples of oil 
taken from a delivery truck or barge. However, using the proposed 
maximum value would require little reprogramming and would greatly 
simplify the missing data procedures. In policy guidance, the Agency 
has indicated it would accept a simplified DAHS for units using the 
procedures of Appendices D and E. In particular, these policies endorse 
manual entry of fuel analytical data, simplified missing data 
procedures for fuel flowmeters, and a DAHS that uses commercial 
spreadsheet software instead of a specialized custom software for 
purposes of part 75 (see Docket A-97-35, Item II-I-9, Policy Manual, 
Questions 14.72 and 14.73). In keeping with the policy of allowing 
Appendices D and E units to use commercial spreadsheet software, EPA 
has proposed what it believes to be the simplest possible missing data 
substitution procedure for missing sulfur content and GCV data. In 
addition, using the proposed maximum potential sulfur content or GCV 
would ensure that substituted missing data values are more conservative 
than the values normally used to calculate the SO2 mass 
emission rate and the heat input rate.

[[Page 28088]]

5. Installation of Fuel Flowmeters for Recirculation
Background
    The current provisions of section 2.1.1 of Appendix D require the 
use of an additional ``return'' fuel flowmeter when some fuel is 
recirculated, i.e., initially sent toward a unit and then diverted away 
from the unit without being burned. This additional fuel flowmeter is 
required, regardless of the amount of fuel being diverted.
    At least one utility has requested to use only the fuel flowmeter 
measuring fuel leaving the oil tank without a second fuel flowmeter to 
measure any fuel diverted away by the recirculation fuel line. The 
utility argued that using a single fuel flowmeter would result only in 
the overestimation of SO2 emissions, since the utility would 
measure a larger amount of fuel usage. This would allow the facility to 
avoid the expense of installation, certification, and quality assurance 
testing on a fuel flowmeter on the recirculation fuel line. Since the 
proportion of fuel being recirculated was minimal, the utility was 
willing to use a more conservative SO2 emissions calculation 
in exchange for devoting fewer resources for the testing and 
maintenance of the recirculation line fuel flowmeter.
Discussion of Proposed Changes
    In today's proposal, EPA proposes to allow facilities to use only a 
fuel flowmeter on the main fuel line from the oil tank if the amount of 
oil recirculated is demonstrated to be less than 5.0 percent of total 
fuel usage for each hour during the year.
Rationale
    EPA believes that it is reasonable not to require installation, 
certification and quality assurance of secondary fuel flowmeters in 
cases where the amount of fuel to be combusted is a small proportion of 
the total fuel used, and where knowing the exact volume of the 
recirculated fuel makes little difference in the calculation of 
emissions and heat input. EPA has allowed one utility to use an 
estimate of the maximum oil usage at start-up, rather than requiring 
the utility to install a return line oil flowmeter to measure the 
startup fuel flow rate.
    At first, EPA considered making the installation of a fuel 
flowmeter on a recirculation fuel line optional. Presumably, if the 
cost in lost SO2 allowances were greater than the cost of 
installing and maintaining a fuel flowmeter, then a facility would 
choose to use a fuel flowmeter on the recirculation fuel line. However, 
many fuel flowmeters used under Appendix D for determining the 
SO2 mass emission rate and the heat input rate are also used 
to estimate the NOX emission rate in lb/mmBtu under Appendix 
E to part 75. The Appendix E procedures estimate hourly NOX 
emission rates using a correlation between measured NOX 
emission rates and heat input rates. The correlation is established 
during a testing period. Therefore, subsequent to the test period, if 
the hourly heat input values should become less accurate, it could 
result in the estimated NOX emission rates becoming less 
accurate. Such loss in accuracy could occur if the heat input rates 
during the initial testing period were based upon subtraction of 
measured volumes or masses of recirculated fuel from the total fuel 
flow rates, and then the facility later began estimating, rather than 
measuring, the recirculated fuel volumes or masses. The potential 
inaccuracy would increase if the proportion of recirculated oil to the 
total flow rate of oil varies over time. The NOX emission 
rate can sometimes increase with increases in the heat input rate and 
can sometimes decrease with increases in the heat input rate, depending 
on the particular type of boiler; in addition, when certain types of 
control equipment are installed, the NOX emission rate may 
not have any relationship with the heat input. Thus, an overestimation 
of the heat input rate would sometimes result in the overestimation and 
sometimes result in the underestimation of the NOX emission 
rate under Appendix E. For these reasons, EPA believes that there needs 
to be some limits on the cases where a facility can choose not to use a 
return fuel flowmeter.
    In today's proposed rule, EPA is proposing that a facility may 
choose to use only a fuel flowmeter on the main fuel line from the oil 
tank and not install a return meter in those cases where the previously 
measured proportion of oil from the recirculation line is less than or 
equal to 5.0 percent of the unit's total oil usage during each hour of 
the year. EPA believes that an error of 5.0 percent in the heat input 
rate should be small enough that it will not significantly affect 
accounting for the NOX emission rate under Appendix E. An 
analysis of emissions data from a gas-fired Appendix E unit with a 
higher than average NOX emission rate for gas (0.157 lb/
mmBtu) showed that a 5.0 percent increase in heat input would change 
the quarterly average NOX emission rate by only 3.17 percent 
(0.152 vs. 0.157 lb/mmBtu) (see Docket A-97-35, Item II-B-19). At the 
same time, EPA believes that an average proportion of 5.0 percent of 
total fuel usage should provide relief for the most extreme situations 
where it might cost more to perform quality assurance testing on a 
return fuel flowmeter than the value of the allowances saved by 
monitoring with the return flowmeter.
    The Agency also considered whether it would be more appropriate to 
determine the proportion of recirculated fuel on an hourly average 
basis or on an annual average basis to determine if the returned fuel 
was less than 5.0 percent of total fuel usage. The Agency concluded 
that the proportion of fuel could be determined only if a return fuel 
flowmeter were already installed on the recirculation fuel line. Thus, 
there would appear to be little advantage to basing the proportion of 
fuel on an annual basis. Hourly average fuel flow rate would also be 
more directly related to the heat input rate used to calculate hourly 
NOX emission rate under Appendix E. EPA notes this is not 
fully consistent with the objective of revising this provision, i.e., 
to exempt facilities from installation and operation of additional fuel 
flowmeters. Therefore, the Agency believes it is better to base the 
reduced fuel flow rate monitoring requirement either on actual 
historical fuel flowmeter data or on some other method, as yet unknown, 
that would yield a reasonable estimate of the average proportion of 
fuel recirculated to the total amount of fuel used. At this time, the 
Agency is unaware of what other methods could provide a reasonable 
estimate of the average proportion of fuel recirculated to the total 
amount of fuel used, either on an hourly or an annual basis. 
Accordingly, the Agency would allow facilities to suggest methods 
through the petitioning process of Sec. 75.66.
6. Fuel Flowmeter Testing
    (a) Fuel Flowmeter Accuracy Tests.
Background
    Sections 2.1.5 and 2.1.6 of Appendix D, as revised by the May 17, 
1995 direct final rule, refer to calibration and recalibration of fuel 
flowmeters. Section 2.1.5.2 gives procedures for a test of the 
flowmeter accuracy by comparing a candidate flowmeter against another 
flowmeter that has already been calibrated according to specified 
procedures. If a flowmeter does not meet the specified accuracy, then 
it would need to be recalibrated by adjusting it, then retested to 
ensure it is reading accurately.
    Some utilities have found confusing the terminology of 
``calibration'' for a test that compares measurements from two 
different flowmeters. Generally, the

[[Page 28089]]

term ``calibration'' is used to refer to adjustments made to a 
flowmeter to ensure it is reading accurately. However, the type of test 
described in section 2.1.5.2 is more like a relative accuracy test 
audit than a calibration, in that it checks the flowmeter accuracy by 
comparing the fuel flowmeter readings against readings from an outside 
standard.
Discussion of Proposed Changes
    To alleviate the confusion surrounding flowmeter testing, today's 
proposal introduces the term ``flowmeter accuracy test.'' This 
terminology is used in sections 2.1.5 and 2.1.6 of Appendix D.
Rationale
    EPA believes that the term ``flowmeter accuracy test'' more clearly 
reflects the nature of the test that is performed. Introducing this new 
term also will clarify that the word ``calibration'' refers to 
flowmeter adjustments, rather than to a comparative test between a 
candidate flowmeter and a reference meter.
    (b) Methods for Fuel Flowmeter Accuracy Testing.
Background
    Section 2.1.5.1 of Appendix D, as revised by the May 17, 1995 
direct final rule, includes a list of standards and procedures that may 
be used to determine if a flowmeter is sufficiently accurate for use 
under the Acid Rain Program. However, because of the large number of 
different brands and kinds of fuel flowmeters, there are also many 
manufacturers' procedures that are not explicitly permitted under part 
75. Consequently, many Acid Rain certification applications for units 
with fuel flowmeters have contained petitions under Secs. 75.23 and 
75.66 for approval of other fuel flowmeter testing procedures. Among 
those methods was AGA Report No. 7 for turbine flowmeters. This method 
was incorporated by reference into part 75 in the November 20, 1996 
final rule. In addition, another standard method that EPA approved 
through petitions is American Petroleum Institute (API) Section 2, 
``Conventional Pipe Provers,'' from Chapter 4 of the Manual of 
Petroleum Measurement Standards, October 1988 edition (see reproduction 
of this document in Docket A-97-35, Item II-D-10 (Attachment B)).
    In the process of implementing part 75, many utilities have 
commented on the problems of testing and calibrating fuel flowmeters. 
Unlike CEMS or stack flow monitors, it is not always possible to 
perform an accuracy test with the fuel flowmeter remaining in the pipe 
where it is installed. Utilities have stated that certain fuel 
flowmeters are extremely difficult to remove, send out for testing, 
recalibrate, and then reinstall (see Docket A-97-35, Item II-E-22). In 
addition, removing a fuel flowmeter from in-line may require stopping 
flow of the fuel and possibly shutting down the unit, with negative 
economic consequences (see Docket A-97-35, Item II-E-8). In addition, 
if a facility needs to operate a unit while the flowmeter is being 
tested at a laboratory, then no flow data will be available for the 
fuel measured by the flowmeter unless the facility has a backup fuel 
flowmeter. Utilities have petitioned for alternative quality assurance 
procedures for fuel flowmeters in order to avoid the inconvenience and 
expense of removing the fuel flowmeter and testing it (see Docket A-97-
35, Item II-D-9). Because of this, the Agency has been evaluating 
various ways of testing a fuel flowmeter in-line (that is, still 
installed in the pipe in its regular position).
    Some utilities have suggested that an alternative way to check fuel 
flowmeter accuracy would be to compare over time the ratio of the fuel 
flowrate to unit output (``load''), measured either in electrical 
generation in MWe or in steam flow in 1000 lb/hr (see Docket A-97-35, 
Item II-E-21). A fuel flow-to-load comparison could be used to 
determine if fuel flowmeter readings are still similar to the readings 
obtained the last time the fuel flowmeter was tested against an outside 
method. A significant change in the amount of fuel used at a load level 
would call into question the validity of fuel flow readings from a 
flowmeter. A fuel flow-to-load comparison could provide this check 
without removal of the fuel flowmeter from its installed location, 
which would be of considerable benefit to facilities.
Discussion of Proposed Changes
    EPA is proposing to incorporate by reference the standard: American 
Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' 
from Chapter 4 of the Manual of Petroleum Measurement Standards. The 
Agency also specifically requests comment on any other voluntary 
consensus standards from standard setting organizations, such as API, 
AGA, ASME, or ISO, that would be appropriate for incorporation by 
reference into part 75. Any suggested methods should also be submitted 
to the Agency as part of the comments to assist in the Agency's 
evaluation.
    Section 2.1.7 of Appendix D to today's proposed rule includes 
provisions for an optional, supplemental quality assurance test for 
fuel flowmeters using a ratio of the fuel flow rate and the unit load. 
The fuel flow rate-to-load ratio comparison test would provide an 
additional way to meet the requirement to periodically test fuel 
flowmeter accuracy. This test would serve as a supplement to more 
rigorous fuel flowmeter tests. These more rigorous tests include the 
standards incorporated by reference under section 2.1.5.1 of Appendix D 
that require the fuel flowmeter to be taken out of line and shipped to 
a laboratory, and the ``master meter'' comparison procedures under 
section 2.1.5.2 of Appendix D. For orifice-, nozzle-, and venturi-type 
flowmeters, the more rigorous tests would include an inspection of the 
primary element and an accuracy test on the transmitters or 
transducers. If a facility performed and passed regular quarterly fuel 
flow-to-load ratio testing, then it would need to perform the more 
rigorous checks on monitor performance only once every 20 calendar 
quarters (five years).
    The fuel flow-to-load ratio test would require a facility to 
establish a baseline period from a period of time when the fuel 
flowmeter is known to be operating properly. After establishing this 
baseline of accurate fuel flow data (or heat input rate data), a 
facility would calculate the fuel flow-to-load ratio (or ``gross heat 
rate'' (GHR)) during the baseline period. In each ``flowmeter operating 
quarter'' that the fuel flowmeter operates after the baseline period is 
completed, the facility would calculate the fuel flow-to-load ratio (or 
GHR) for each hour the fuel flowmeter is used to report data. The 
facility would compare the hourly fuel flow-to-load ratio (or GHR) to 
the fuel flow-to-load ratio (or GHR) during the baseline period in 
order to calculate the absolute value of the percentage difference for 
each hour. Next, the facility would calculate the average percentage 
difference for the quarter. If the percentage difference exceeded the 
specified limits for the test, the fuel flowmeter would fail the test. 
The key elements of the fuel flow rate-to-load evaluation are discussed 
in the following paragraphs.
    (1) Use of Gross Heat Rate-to-Load Ratio. Today's proposed rule 
would allow a facility the option of calculating either the ratio of 
the fuel flow rate to the gross generation in MWe or the steam flow 
rate in thousands of pounds of steam per hour (``fuel flow-to-load 
ratio'') or the ratio of the heat input rate to the gross generation in 
MWe or the steam flow rate in thousands of pounds of steam per hour 
(``GHR''). In order to allow a meaningful comparison, a facility would 
use one of these two ratios consistently, both in calculating

[[Page 28090]]

an initial baseline ratio and in calculating hourly ratios during a 
particular quarter. Equations D-1c and D-1e describe the calculation of 
the fuel flow-to-load ratio for the baseline period and for hourly 
values during a calendar quarter, respectively. For the GHR, the 
respective equations are Equations D-1d and D-1f. These equations are 
found in proposed sections 2.1.7.1 and 2.1.7.2 of Appendix D.
    (2) Baseline Period for Fuel Flow-to-Load Ratio. The provisions for 
calculating the baseline fuel flow-to-load ratio or gross heat rate are 
found in section 2.1.7.1 of today's proposed rule. EPA is proposing 
that the owner or operator of a facility would establish a baseline of 
fuel flow rate (or heat input rate) data following a flowmeter accuracy 
test under either section 2.1.5.1 or 2.1.5.2 of Appendix D, or 
following both a transmitter or transducer accuracy test under section 
2.1.6.1 of Appendix D and an inspection of a primary element for an 
orifice-, nozzle-, or venturi-type fuel flowmeter under section 
2.1.6.6. Throughout section 2.1.7 of today's proposed rule, these are 
referred to as ``the most recent quality assurance procedure(s).'' The 
baseline period of fuel flow rate (or heat input rate) data for a fuel 
flowmeter to be tested under section 2.1.7 would use the first 168 
hours of quality assured data measured by that flowmeter following the 
most recent quality assurance procedure(s) for which: (1) only the fuel 
measured by that fuel flowmeter is combusted (i.e., no co-firing of 
fuels occurs); (2) the load is relatively stable and not ``ramping'' 
rapidly up or down; and (3) the load is sufficiently above the minimum 
safe, stable operating load (unless low-load operation is normal for 
the unit).
    Today's proposal includes a limit to the length of time over which 
the baseline period could extend. The baseline period of 168 hours 
could not extend for longer than the end of the second calendar quarter 
following the calendar quarter in which the most recent quality 
assurance procedure(s) was performed. For orifice-, nozzle-, and 
venturi-type fuel flowmeters, two quality assurance procedures would be 
required: both a transmitter or transducer accuracy test under section 
2.1.6.1 of Appendix D and an inspection of a primary element, such as 
an orifice plate. For practical purposes, this means that the 
transmitter or transducer accuracy test and the primary element 
inspection would have to be completed either in the same calendar 
quarter or in consecutive calendar quarters. If there were not 168 
hours of quality-assured fuel flowmeter data from hours when a single 
fuel is combusted, then the fuel flowmeter would not be allowed to be 
tested using the fuel flow-to-load ratio as a supplement to other 
quality assurance tests.
    The 168 hours of quality-assured fuel flowmeter data next would be 
averaged and divided by the average load, in megawatts or 1000 lb 
steam/hr, during the same 168 hours to determine the baseline fuel 
flow-to-load ratio (see Equation D-1c). Alternatively, the facility 
could instead calculate the gross heat rate by averaging hourly heat 
input rate during the 168 hours of the baseline period and by dividing 
the average heat input rate by the average load during the same 168 
hours (see Equation D-1d).
    In cases where the fuel flowmeter is located on a common pipe 
header, one fuel flow rate measurement could be associated with the 
load from several units that receive fuel from the common pipe header. 
In order to analyze the fuel flow-to-load ratio for a flowmeter on a 
common pipe header, the load from all units receiving fuel from the 
common pipe header would have to be combined for each hour, averaged 
over the baseline period of 168 hours, and compared to the average fuel 
flow rate during the baseline period. If a single unit receives fuel 
from multiple pipes, each pipe with its own fuel flowmeter, then the 
flow rates from all fuel flowmeters would have to be added together to 
obtain the average fuel flowrate for the unit to be divided by the unit 
load.
    (3) Data Preparation and Analysis. In each flowmeter operating 
quarter following the final quarter of the baseline period, all hourly 
fuel flowmeter data would be compared to the load. A flowmeter 
operating quarter would be a calendar quarter in which the unit 
combusts the fuel measured by the fuel flowmeter for at least 168 
hours. For each hour in which the fuel is combusted, the owner or 
operator would calculate the fuel flow-to-load ratio (or GHR) (see 
Equation D-1e for the fuel flow-to-load ratio and Equation D-1f for the 
GHR). Hourly fuel flow rates on common pipe headers would be compared 
to the sum of the loads from all units receiving fuel from the common 
pipe header. For units with multiple pipes and multiple fuel 
flowmeters, the total hourly fuel flow rate for the fuel would be 
compared to the unit load.
    Next, the facility would compare the hourly fuel flow-to-load 
ratios (or GHRs) to the baseline fuel flow-to-load ratio (or GHR). The 
absolute value of the percentage difference would be calculated for 
each hour using Equation D-1g. Then the facility would calculate the 
average value of the percentage difference for the quarter, using each 
hourly percentage difference in Equation D-1h.
    The quarterly average of the hourly percentage difference values 
next would be compared to the limitation. For either the fuel flow-to-
load ratio or the GHR, Ef, the quarterly average of the hourly 
percentage difference values would need to be no greater than 10.0 
percent, unless the average of the hourly loads used for the analysis 
was  50 MWe (or  500 klb/hr of steam), in which 
case the limit on Ef would be 15.0 percent. If a fuel flowmeter were to 
fail to meet this limit when using all data in the flowmeter operating 
quarter, then the facility would have the option of excluding certain 
hours. Otherwise, a failure to meet the 10.0 percent (or 15.0 percent, 
if applicable) limit would be considered a failure of the fuel flow-to-
load ratio test.
    (4) Optional Data Exclusions. As mentioned above, if a fuel 
flowmeter's data would not meet the 10.0 percent (or 15.0 percent, if 
applicable) limit on the quarterly average of the percentage difference 
values, then a facility could opt to exclude certain hours of 
unrepresentative fuel flow rate (or heat input rate) data and then 
reanalyze the smaller set of data. The types of data that EPA proposes 
as non-representative would be the same as the hours excluded during 
the baseline period, including: (1) hours when the unit combusts 
multiple fuels measured by multiple fuel flowmeters, such as co-firing 
of gas and residual oil or co-firing of residual oil and diesel fuel; 
(2) hours when the unit load is rapidly rising or falling, sometimes 
referred to as ``ramping,'' to such a degree that the load in a given 
hour differs by more than  15.0 percent from the load 
during either the previous hour or the hour afterwards; or (3) hours in 
which the unit load is in the lower 10.0 percent of the unit's 
operating range, unless operation at those low levels is considered 
normal for the unit. The facility would proceed to analyze the 
remaining quarterly fuel flow rate or heat input rate values, provided 
that there are at least 168 hours remaining for the quarter after 
excluding non-representative hours. If less than 168 representative 
hours remained after excluding the allowable hours, then a flow-to-load 
or GHR test would not be required for that flowmeter for that flowmeter 
operating quarter. If the fuel flowmeter data still failed to meet the 
10.0 percent (or 15.0 percent, if applicable) limit on the quarterly 
average of the percentage difference values after excluding the 
allowable

[[Page 28091]]

hours, the flowmeter would fail the fuel flow-to-load ratio test.
    (5) Consequences of Failing Fuel Flow-to-Load Ratio or GHR Tests. 
There would be two primary consequences of failing a fuel flow-to-load 
ratio or a GHR test. First, the data from the fuel flowmeter would no 
longer be considered quality-assured. Thus, the facility would need to 
invalidate data from the fuel flowmeter following the test. Proposed 
section 2.1.7.4 of Appendix D specifies that the missing data 
procedures of section 2.4.2 of Appendix D would be used to substitute 
for the invalid data (unless a different fuel flowmeter is available 
that has been tested for accuracy and has been demonstrated to meet the 
accuracy specification), beginning with the first hour the fuel 
measured by the fuel flowmeter is used during the quarter following the 
flowmeter operating quarter in which the meter fails the fuel flow-to-
load ratio test. Second, in order to establish that the fuel flowmeter 
is again operating properly and providing quality-assured data, the 
facility would perform a fuel flowmeter accuracy test according to 
sections 2.1.5.1 or 2.1.5.2 of Appendix D or, for orifice-, nozzle-, 
and venturi-type flowmeters, a transmitter or transducer accuracy test 
according to section 2.1.6.1 of Appendix D. In addition to the 
transmitter or transducer test, orifice-, nozzle-, and venturi-type 
fuel flowmeters would need to be further tested following a failed 
flow-to-load or GHR test in order to ensure that the problem causing 
the failure of the fuel flow-to-load ratio was a problem with the 
transmitters or transducers.
    Once the orifice-, nozzle-, or venturi-type flowmeter has been 
recalibrated and passes a transmitter or transducer accuracy test 
according to section 2.1.6.1 of Appendix D, the facility would perform 
a shortened version of the fuel flow-to-load ratio test. The shortened 
version of the test would use six to twelve hours of data following the 
passed transmitter or transducer accuracy test. If the fuel flowmeter 
passed the abbreviated fuel flow-to-load ratio test, then its data 
would be considered valid, beginning with the time and date of the 
passed transmitter or transducer accuracy test. However, if the fuel 
flowmeter were to fail the abbreviated fuel flow-to-load ratio test, 
then it would be necessary for the facility to inspect the primary 
element for corrosion or damage. Furthermore, data would be considered 
invalid until the orifice-, nozzle-, or venturi-type fuel flowmeter 
passes an inspection of the primary element. Although data from the 
flowmeter would be considered quality-assured after successful 
completion of all required accuracy testing, visual inspections and 
diagnostic tests, the baseline would have to be re-established no later 
than the end of the second flowmeter operating quarter following the 
quarter in which the quality assurance tests are completed.
Rationale:
    EPA is proposing to incorporate by reference the standard: American 
Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' 
from Chapter 4 of the Manual of Petroleum Measurement Standards, 
October 1988 edition. The Agency has already approved this method of 
fuel flowmeter testing in response to a petition (see Docket A-97-35, 
Item II-C-6). This is also a standard agreed to by API that is 
traceable to NIST standards. The Agency has a general policy of 
approving standards from technically knowledgeable groups such as the 
Organization for International Standards (ISO), the American Society 
for Testing and Materials (ASTM), the American Society of Mechanical 
Engineers (ASME), the American Gas Association (AGA), the Gas 
Processors Association (GPA), and API. EPA would also be willing to 
incorporate additional standards by reference if commenters supply a 
copy for consideration.
    The Agency recognizes that it is difficult and sometimes costly to 
take a fuel flowmeter out from its installation location to be tested 
(see Docket A-97-35, Item II-E-22). Today's proposed rule would provide 
the flexibility of an additional approach for testing fuel flowmeters 
where they are installed. Today's proposal for a fuel flow rate-to-load 
comparison test would allow facilities to assure the quality of their 
fuel flow rate data without taking a fuel flowmeter out of line. 
Several industry representatives suggested that a fuel flow rate-to-
load comparison was a useful approach to quality assuring data (see 
Docket A-97-35, Items II-E-22, II-E-23). Some industry representatives 
felt that a fuel flow rate-to-load ratio was straightforward and even 
more representative than a stack flow rate-to-load ratio (see Docket A-
97-35, Item II-E-23).
    In general, utilities have indicated that the idea of a fuel flow-
to-load ratio is an appropriate quality assurance test for fuel 
flowmeters (see Docket A-97-35, Items II-D-30, II-D-41, II-E-33). Use 
of the fuel flow-to-load ratio was first suggested to the Agency as an 
alternative to annual orifice inspections (see Docket A-97-35, Item II-
E-22). One utility mentioned that the fuel flow-to-load ratio test 
would be most useful if it allowed them to stretch the time between 
transmitter or transducer accuracy tests on orifice-, nozzle-, and 
venturi-type fuel flowmeters, as well as primary element inspections 
and fuel flowmeter accuracy tests performed in-line against a ``master 
meter'' or performed in a laboratory (see Docket A-97-35, Item II-D-
49).
    Utilities have also indicated that they would prefer the provisions 
of the fuel flow-to-load ratio test to be as similar as possible to the 
stack flow-to-load ratio test in today's proposed rule (see Docket A-
97-35, Item II-E-33). This would be easier for facilities to comply 
with because they would need to learn fewer new procedures, they could 
use the same equations and algorithms in computer software or hand 
calculations, and they could report information in a similar format. To 
the extent possible, the Agency has incorporated this suggestion in 
today's proposed rule. However, because monitoring with fuel flowmeters 
is not identical to monitoring with stack volumetric flow monitors, 
there are some differences in the procedures and in the data to be 
recorded and reported.
    Today's proposed rule would allow the quarterly fuel flow-to-load 
ratio test as an optional supplement to flowmeter accuracy tests under 
section 2.1.5.1 or 2.1.5.2 of Appendix D, transmitter or transducer 
accuracy tests under section 2.1.6.1 of Appendix D for orifice-, 
nozzle-, and venturi-type fuel flowmeters, and visual inspections of 
the primary element required under section 2.1.6.6 of Appendix D for 
orifice-, nozzle-and venturi-type fuel flowmeters. These more rigorous 
fuel flowmeter quality assurance procedures would still be required at 
least once every 20 calendar quarters (five years), even if the 
procedures of section 2.1.7 of Appendix D were followed. The Agency has 
proposed a quarterly fuel flow-to-load ratio test for several reasons: 
(1) this is consistent with the provisions of the proposed volumetric 
stack flow-to-load ratio test in today's proposed rule; (2) the test 
involves examining data more closely when preparing quarterly reports; 
and (3) a quarterly test allows facilities to find problems in fuel 
flowmeter data before an entire year has passed. The Agency also 
considered requiring the fuel flow-to-load ratio to be used more 
frequently than quarterly, perhaps daily; however, this would require 
facilities to spend far more time and effort in evaluating data at 
different times during the quarter than they may do currently, 
particularly for small, infrequently operated units. In addition, many 
utilities claim that fuel

[[Page 28092]]

flowmeters tend to be stable, and therefore little change would be 
expected over short time periods such as a day (see Docket A-97-35, 
Item II-E-33).
    EPA is proposing that the optional fuel flow-to-load ratio test 
could serve as a supplement to other quality assurance procedures for 
fuel flowmeters for up to 20 calendar quarters (five years). EPA is 
proposing a time period of 20 calendar quarters for the following 
reasons. First, it is similar to the current provision in section 
2.1.5.2 of Appendix D, which allows a reference fuel flowmeter to be 
accuracy tested as seldom as once in five calendar years if comparison 
with an in-line ``master'' flowmeter shows less than a 1.0 percent 
difference in their flow rates. Second, a five-year test cycle offers 
certain administrative advantages. For instance, fuel flowmeters used 
to provide heat input data for the heat input-versus-load correlation 
of Appendix E could be accuracy-tested before each Appendix E test 
(i.e., once every five years). In addition, a five-year period would 
ensure that fuel flowmeters are tested by the time the unit's operating 
permit is renewed. The 20 calendar quarter (five-year) period is 
consistent with the provisions for reduced three-level flow RATAs for 
stack flow monitors. The 20 calendar quarter (five-year) period between 
tests is also consistent with the proposed time between quality 
assurance tests for fuel flowmeters that are used very infrequently. 
Repeating the periodic quality assurance procedures for fuel flowmeters 
at least every five years would catch slow, long-term changes in heat 
rates mentioned by a facility and would allow a facility to update its 
baseline data periodically (see Docket A-97-35, Item II-D-49). Finally, 
allowing the option of a 20 calendar quarter (five-year) period between 
more rigorous quality assurance procedures would be safer and less 
costly than annual testing, while, in coordination with quarterly fuel 
flow-to-load ratio testing, still providing assurance of the quality of 
the data.
    (1) Use of Gross Heat Rate or Flow-to-Load Ratio. Today's proposed 
rule would allow a facility the option of calculating either the ratio 
of the fuel flow rate to the gross generation in MWe or the steam flow 
rate in thousands of pounds of steam per hour (``fuel flow-to-load 
ratio'') or the ratio of the heat input rate to the gross generation in 
MWe or the steam flow rate in thousands of pounds of steam per hour 
(``gross heat rate'' or ``GHR''). One utility suggested that, because 
the load is created based upon a number of factors in addition to the 
fuel flow rate, such as the gas heat rate (i.e., gross calorific 
value), a ratio of the heat input to the unit load would be a better 
test than the ratio of the fuel flow rate to the unit load (see Docket 
A-97-35, Item II-D-50). In addition, some utilities pointed out that 
the Agency allows facilities to use either a stack flow-to-load ratio 
or a heat input-to-load ratio (gross heat rate) as a diagnostic test on 
stack volumetric flow monitors, through Policy Manual Question 13.15 
(see Docket A-97-35, Item II-I-9). The Agency agrees that the heat 
input-to-load ratio (GHR) is also a technically appropriate check on 
the performance of fuel flowmeters. Therefore, today's proposal 
includes options for both the fuel flow-to-load ratio and the GHR.
    (2) Baseline Period for Fuel Flow-to-Load Ratio or GHR. When using 
this type of comparison test, it is important to establish a baseline 
of reliable data to which hourly data can later be compared. For the 
stack volumetric flow-to-load ratio, the baseline of reliable data 
consists of data from the reference method for flow, Method 2 of 
Appendix A to 40 CFR part 60. However, there is no universally 
applicable test for flowmeters that is performed in-line with a 
reference method while the unit is operating, parallel to the flow 
RATA. EPA asked several utilities what could be a source of baseline 
data to which the fuel flowmeter could later be compared. One utility 
suggested using fuel flowmeter readings during a time when the unit is 
operating at a steady load, such as when the unit undergoes Appendix E 
testing for a NOX-versus-heat input correlation or when a 
NOX CEMS undergoes a normal level RATA (see Docket A-97-35, 
Item II-D-41). A second utility recommended that the baseline be 
established just after performing a transmitter calibration, i.e., 
after performing a quality assurance test on the fuel flowmeter (see 
Docket A-97-35, Item II-D-49). The Agency believes that using fuel 
flowmeter data taken immediately following a flowmeter quality 
assurance test would be most likely to be accurate and representative 
of proper operation of the fuel flowmeter. Flowmeter quality assurance 
tests might include any of the methods incorporated by reference in 
section 2.1.5.1 of Appendix D; meter testing against a certifiable 
``master'' meter under section 2.1.5.2 of Appendix D; or transmitter or 
transducer accuracy testing under section 2.1.6.1 of Appendix D, and 
inspection of a primary element for an orifice-, nozzle-, or venturi-
type fuel flowmeter under section 2.1.6.6 of Appendix D. This approach 
is proposed in today's rule.
    The utilities supporting the idea of using fuel flowmeter data 
taken immediately after a flowmeter quality assurance test have 
suggested that it would be important to have a fairly large number of 
hours in the baseline, on the order of 100 or more, to ensure that the 
baseline period is representative of typical operation (see Docket A-
97-35, Item II-E-33). In today's rule, EPA is proposing to use the 
first 168 hours of quality assured data measured by that flowmeter for 
which: (1) only the fuel measured by that fuel flowmeter is combusted; 
(2) the unit load is not significantly ``ramping'' up or down; and (3) 
the unit load is safely above the minimum safe, stable load. The Agency 
believes that a baseline period containing 168 hours of data is 
sufficiently long to be representative of different unit operating 
conditions that may occur later. This specific time period is 
consistent with the minimum number of hours that a unit combusts a fuel 
before the quarter counts toward the deadline for the next quality 
assurance test, and with the minimum number of hours that a unit 
combusts a fuel before a quarter needs to be evaluated using the fuel 
flow-to-load ratio. Certain hours would be excluded from the baseline 
(i.e., periods of co-firing, unstable, or low load), because the fuel 
flow-to-load ratio or GHR would tend to be less reliable during those 
periods.
    Today's proposal would also limit the baseline period so that it 
may extend no more than two quarters beyond the quarter in which the 
flowmeter passes its accuracy tests. The Agency has concerns that if 
the baseline data were to extend longer than this, the performance of 
the fuel flowmeter might degrade. In order for the baseline data to 
reflect fuel flow rate data that are most likely to be accurate, the 
Agency is proposing that the fuel flow rate or heat input rate data 
used in the baseline period must either be obtained in the calendar 
quarter in which the quality assurance procedure is performed, or 
within two calendar quarters after the QA test. The Agency considered 
limiting the time period to the same calendar quarter as the quality 
assurance procedure or to one flowmeter operating quarter beyond the QA 
test. However, because a quality assurance procedure may be conducted 
at any time during a quarter, it could be difficult for a facility to 
collect 168 hours of fuel flowmeter data after a quality assurance 
procedure in the same calendar quarter or even (for infrequently 
operated units that ramp

[[Page 28093]]

up and down often) in the next calendar quarter.
    For orifice-, nozzle-, and venturi-type fuel flowmeters, two 
quality assurance procedures would be required prior to collecting the 
baseline data: (1) a transmitter or transducer accuracy test, and (2) 
an inspection of a primary element. The Agency considered whether these 
two quality assurance procedures should be separated and whether the 
baseline period could simply be based upon a time period after the most 
recent quality assurance procedure. The Agency believes that the 
baseline period data would be more reliable if they were taken shortly 
after completing both quality assurance procedures for orifice-, 
nozzle-, and venturi-type fuel flowmeters. Using the same time period 
for both tests simplifies administration of the fuel flow-to-load ratio 
test. EPA also notes that a unit does not need to be operating in order 
to perform the tests; thus, it should not be burdensome for a facility 
to plan to coordinate the two quality assurance procedures.
    (3) Data Preparation and Analysis. The proposed procedures for data 
preparation and analysis for the fuel flow-to-load ratio are similar to 
those for the volumetric stack flow-to-load ratio. Equations of the 
same form as those for the stack volumetric flow-to-load ratio are used 
to calculate the hourly fuel flow-to-load ratio, the hourly absolute 
value of the percentage difference between the baseline fuel flow-to-
load ratio and the hourly fuel flow-to-load ratio, and the quarterly 
average percentage difference. Common pipe headers would be treated in 
the same way as common stacks. If there were multiple units associated 
with a single fuel flowmeter or flow monitor, the total load from all 
units would be summed before the flow rate data are divided by the load 
data to calculate the flow-to-load ratio. Fuel flowmeters on multiple 
pipes would be treated in the same way as multiple stacks associated 
with a single unit. If there are multiple fuel flowmeters or flow 
monitors associated with a single unit, the flow rates from all fuel 
flowmeters for the same fuel or all flow monitors would be added 
together before the flow rate data are divided by the load data to 
calculate the flow-to-load ratio.
    Certain aspects of the volumetric stack flow-to-load ratio test are 
not the same for the fuel flow-to-load ratio test. For example, the 
volumetric stack flow-to-load ratio test requires the facility to 
screen out those hours when the unit operates further than 10.0 percent 
away from the average load during the most recent normal-load flow 
RATA. As was discussed previously, there is no equivalent of an in-line 
flow RATA for fuel flowmeters. EPA does not believe that there is a 
need to screen out hours for the fuel flow-to-load test when the unit 
operates at a load somewhat less than or greater than normal. Some 
facilities have indicated that the fuel flow-to-load ratio or GHR based 
on fuel flow readings is less variable over different loads than the 
volumetric stack flow-to-load ratio (see Docket A-97-35, Items II-E-33 
and II-D-98). However, preliminary evidence has also indicated that the 
fuel flow-to-load ratio or GHR can be significantly different at very 
low operating loads than at other load levels (see Docket A-97-35, Item 
II-A-5). For this reason, EPA is proposing to allow hours in which the 
unit load is within the lower 10.0 percent of the range of operation to 
be excluded from both the baseline data and the quarterly flow-to-load 
or GHR analysis, unless such low loads are considered normal for the 
unit.
    Another feature of the volumetric stack flow-to-load ratio test 
that differs from the fuel flow-to-load ratio test is the treatment of 
bias-adjusted data. Fuel flow rate data are never adjusted for bias. 
There is no bias test for fuel flowmeters. Bias-adjustment of data is 
an issue for the volumetric stack flow-to-load ratio test because bias-
adjusted data has already been adjusted to make it more consistent with 
the value of the reference method data. Thus, bias-adjusted volumetric 
stack flow data must meet a stricter quarterly average percentage 
difference of 10.0 percent from the reference flow-to-load ratio, 
whereas the allowable difference is 15.0 percent when unadjusted 
volumetric stack flow data are used. (See discussion of stack flow-to-
load test in Section III.M. of this preamble.) EPA notes that since the 
same fuel flow meter is used to produce both the baseline data and the 
quarterly data, the fuel flow-to-load ratio is more closely analogous 
to the use of bias-adjusted volumetric flow data. Therefore, the limit 
on the quarterly average percentage difference from baseline for fuel 
flow rate data should be at least as stringent as that for bias-
adjusted volumetric flow data (10.0 percent). Information provided by 
facilities on the gross heat rate derived from fuel flow rate data have 
shown less variability than the corresponding stack heat rate (see 
Docket A-97-35, Item II-D-98). Based upon this information, EPA is 
proposing a limit of 10.0 percent on Ef, the quarterly 
average percentage difference from the baseline for the quarterly flow 
rate-to-load or GHR evaluation. EPA considered whether it would be 
appropriate to set a different limit for smaller units, as was done for 
the stack flow-to-load test. Analysis of some preliminary fuel flow-to-
load data has shown that for lower loads (e.g., < 50 MWe), the flow-to-
load ratio is quite sensitive to small changes in load (see Docket A-
97-35, Item II-A-5). This indicates that it would be appropriate to set 
a higher limit for smaller units. Therefore, today's rule proposes a 
limit of 15.0 percent on the value of Ef when the quarterly 
average load used for the data analysis is 50 megawatts or less (or 
 500 klb steam per hour). The Agency solicits comment on the 
15.0 percent limit for loads less than or equal to 50 megawatts.
    (4) Optional Data Exclusions. As for volumetric stack flow 
monitors, if a fuel flowmeter's data would not meet the limit on the 
percentage deviation from the baseline, then a facility could opt to 
exclude certain hours of unrepresentative fuel flow rate (or heat input 
rate) data and then reanalyze the smaller set of data. The hours of 
data that EPA proposes to view as non-representative for fuel 
flowmeters are: (1) hours when the unit combusts multiple fuels; (2) 
hours when the unit load in a given hour would differ by more than 
 15.0 percent from the load during either the previous hour 
or the subsequent hour; or (3) hours when the load is very close to the 
minimum safe, stable load (unless operation in that range is normal).
    The baseline period for fuel flowmeters and the data used for the 
quarterly flow-to-load or GHR analyses would include only those hours 
when a single fuel is combusted--the fuel measured by the fuel 
flowmeter. If the quarterly fuel flow rate data included hours when 
multiple fuels are co-fired, the fuel flow-to-load ratio or GHR for the 
fuel flowmeter being tested would be biased low. This could result in a 
failure of the flow-to-load test or GHR evaluation. Today's proposed 
rule would also allow a facility to exclude from the baseline data and 
the quarterly analyses those hours that are not representative because 
the unit's load is changing rapidly. Specifically, hours could be 
excluded when the unit load in a given hour would differ by more than 
 15.0 percent from the load during either the previous hour 
or the hour afterwards. There will be a lag in the time between when 
electricity is generated and registered as load and the time that the 
fuel flowmeter measures the fuel that is combusted to generate the 
load. Therefore, during an hour when the load changes rapidly, the fuel 
flow rate will not necessarily be changing by the same amount or in the

[[Page 28094]]

same direction. At least one utility has suggested that the Agency 
consider such an exclusion for the proposed fuel flow-to-load ratio 
test (see Docket A-97-35, Item II-D-41).
    In general, the fuel flow is directly proportional to load, with a 
linear graphical relationship. However, this is not always the case at 
extremely low loads (see Docket A-97-35, Items II-E-33, II-D-98). 
Therefore, today's proposed rule would allow certain low-load hours to 
be excluded from the flow-to-load baseline and quarterly data analyses. 
Specifically, loads in the lower 10.0 percent of the ``range of 
operation'' of the unit, (as that term is defined in proposed section 
6.5.2.1 of Appendix A in today's proposal) could be excluded, unless 
such loads are considered normal for the unit.
    Today's proposed rule, in section 2.1.7 of Appendix D, would also 
exempt a fuel flowmeter from the fuel flow-to-load ratio test in a 
quarter when a more rigorous quality assurance test is performed. This 
is unlike the volumetric stack flow-to-load ratio, which is required 
each QA operating quarter, including quarters when the flow monitor is 
tested with a RATA (provided, of course, that sufficient data for the 
analysis are obtained after the RATA).
    (5) Consequences of Failing the Fuel Flow-to-Load Ratio Test. The 
consequences of failing the fuel flow-to-load ratio test would be 
similar to the consequences of failing quality assurance tests in 
general for fuel flowmeters. Data from the fuel flowmeter would no 
longer be considered quality assured. Because the fuel flow-to-load 
ratio test is only performed at the end of a quarter, the facility 
would invalidate data from the fuel flowmeter beginning with the first 
hour in the quarter after the quarter in which the meter fails the fuel 
flow-to-load ratio test. In order to establish that the fuel flowmeter 
is operating properly and providing quality assured data again, the 
facility would perform a flowmeter accuracy test or (for orifice-, 
nozzle-, and venturi-type flowmeters) a transmitter or transducer 
accuracy test. The Agency believes it is appropriate to perform an 
accuracy test if the fuel flow-to-load ratio test is failed, because in 
such cases the facility has had the benefit of postponing the accuracy 
test based upon the assumption that the fuel flowmeter has continued to 
measure accurately and consistently with its operation during the 
baseline period.
    Note that for orifice-, nozzle-, and venturi-type fuel flowmeters, 
a transmitter/transducer test alone would not suffice to demonstrate 
that the flowmeter is back in control. The owner or operator would 
still need to ensure that the cause of the failed fuel flow-to-load 
ratio test was a problem with the transmitters or transducers rather 
than a problem with the primary element. Sudden changes in flowmeter 
performance are likely to be caused by a problem with transmitters (see 
Docket A-97-35, Item II-D-33). However, it cannot be assumed that the 
transmitters are solely responsible for degradation in monitor 
performance. In order to verify that the primary element is not 
contributing additional error to the fuel flow measurements because of 
corrosion, a facility would conduct an abbreviated (6 to 12 hour) 
version of the fuel flow-to-load ratio test, similar to the diagnostic 
test for volumetric stack flow monitors in Policy Manual Question 13.15 
(see Docket A-97-35, Item II-I-9). The Agency believes that this 
abbreviated fuel flow-to-load ratio test would provide additional 
assurance that the fuel flowmeter is indeed operating properly. In 
addition, it would be more timely than waiting for another calendar 
quarter to pass to repeat the fuel flow-to-load ratio. The abbreviated 
test would also be less burdensome than removing the primary element 
from the fuel pipe. EPA believes the abbreviated fuel flow-to-load 
ratio test strikes a reasonable balance by providing some additional 
quality assurance in a timely manner. If the orifice-, nozzle-, or 
venturi-type fuel flowmeter failed the abbreviated fuel flow-to-load 
ratio test, then it would appear that the primary element may also have 
a problem. Therefore, upon failure of an abbreviated fuel flow-to-load 
ratio test, the facility would be required to inspect the primary 
element and to repair or replace it, as necessary.
    The rules for data validation upon failure of the fuel flow-to-load 
ratio are not parallel with the procedures for data validation 
following failure of the volumetric stack flow-to-load ratio test in 
that there is no conditional validation of data. A number of utilities 
have emphasized that they wish to spend less time and effort preparing 
and evaluating quarterly reports for units using Appendix D, which are 
generally smaller and less frequently operated than coal-fired units or 
oil-fired units that choose to use CEMS (see Docket A-97-35, Item II-E-
33). The concept of conditional data validation for fuel flowmeters is 
not consistent with this objective, because it would introduce 
additional complexity into the process, would require significantly 
more time and resources to quality-assure the data, and might require 
additional DAHS programming. Therefore, the Agency is not proposing the 
use of conditional data validation for fuel flowmeters.
(c) Fuel Flowmeter Quality Assurance Testing Frequency
Background
    Section 2.1.6.1 of Appendix D, as revised by the May 17, 1995 
direct final rule, requires regular quality assurance 
``recalibrations'' (accuracy tests) of fuel flowmeters at least 
annually (once every four calendar quarters). For fuel flowmeters that 
were not used on a regular basis, such as fuel flowmeters used to 
measure the usage of emergency fuel or backup fuel, or flowmeters 
installed on peaking units, owners or operators are allowed to do 
flowmeter accuracy tests once every four quarters when the unit 
actually combusts the fuel measured by the flowmeter, rather than once 
every four calendar quarters. Flowmeters can be retested either by 
using one of the methods incorporated by reference in section 2.1.5.1 
of Appendix D to part 75 or by an in-line comparison of the fuel 
flowmeter against a ``master'' fuel flowmeter using the procedure in 
section 2.1.5.2 of Appendix D.
    Some utilities have expressed concern about the annual fuel 
flowmeter testing requirement (see Docket A-97-35, Items II-D-20, II-E-
13, II-E-14). In many cases, it is neither practical nor cost-effective 
to modify the fuel pipes (e.g., to install a parallel length of pipe) 
to allow installation of a master fuel flowmeter for comparison 
testing. Thus, most utilities must remove a fuel flowmeter from the 
pipe and return it to a laboratory or to the manufacturer to be 
retested. In some cases, especially for oil flowmeters, this can be 
difficult.
    Some utilities have raised the issue of whether there should be a 
minimum time period that a fuel flowmeter is used before a quality 
assurance test is required. For instance, a utility might test its 
unit's burners once each quarter for a few hours to ensure that the 
unit can be operated when needed and may not operate for the rest of 
the quarter. Under the current rule, the fuel flowmeter would have to 
be quality assurance tested after four such operating quarters, even 
though the flowmeter was only used for a few hours in those calendar 
quarters.
Discussion of Proposed Changes
    Today's proposed rule includes a provision that only those calendar 
quarters in which the fuel measured by the fuel flowmeter is combusted 
for at least 168 hours would count toward determining the next quality 
assurance test deadline. The 168-hour time period

[[Page 28095]]

is roughly equivalent to one week of operation while combusting the 
fuel measured by a particular fuel flowmeter. A calendar quarter in 
which the fuel measured by a fuel flowmeter is combusted for 168 hours 
or more would be called a ``flowmeter operating quarter.'' For example, 
if a unit combusted oil for 200 hours in the first calendar quarter of 
the year, 10 hours in the second calendar quarter, 250 hours in the 
third calendar quarter, and 100 hours in the fourth calendar quarter, 
then only the first and third calendar quarters would be considered 
flowmeter operating quarters for the oil flowmeter. Only the first and 
third calendar quarters would count toward determining the deadline for 
the next required oil flowmeter accuracy test.
    In today's proposed rule, each fuel flowmeter would need to be 
accuracy tested at least once every four flowmeter operating quarters. 
However, the deadline for testing infrequently-used meters could not be 
extended indefinitely. No more than 20 calendar quarters (five years) 
would be allowed to elapse between successive flowmeter accuracy tests, 
regardless of the number of ``flowmeter operating quarters'' that have 
elapsed since the last test. The interval between successive quality 
assurance tests could also be extended for up to 20 calendar quarters 
if the quarterly fuel flow rate-to-load procedures in proposed section 
2.1.7 of Appendix D were implemented.
Rationale
    In evaluating the frequency of fuel flowmeter accuracy testing, EPA 
considered simply extending the less strict requirement for fuel 
flowmeter quality assurance testing for peaking units, backup fuel, and 
emergency fuel to apply to all units and all fuel flowmeters. Thus, 
quality assurance testing would be required once every four quarters in 
which the unit combusted the fuel measured by the flowmeter.
    One industry representative recommended that the Agency require 
fuel flowmeter calibrations once every four unit operating quarters, 
where a unit operates at least 168 hours in the quarter (see Docket A-
97-35, Item II-E-13). This approach would treat all fuel flowmeters the 
same, whether they were used for primary, emergency, or backup fuel.
    Another utility suggested that the Agency consider creating some 
sort of diagnostic test comparing the flow rate of the fuel flowmeter 
to the unit load (generation) to determine whether the fuel flowmeter 
readings are degrading over time, rather than specifying a particular 
frequency for accuracy testing (see Docket A-97-35, Item II-E-22). 
Although this suggestion was originally referring to problems with 
corrosion of an orifice plate, such a test could also be used for other 
types of fuel flowmeters as a check on the quality of fuel flowmeter 
data.
    The Agency also considered extending the typical time between 
accuracy tests to the equivalent of two years. This time was suggested 
by a member of the AGA subcommittee responsible for the drafting of AGA 
Report No. 7 for turbine-type flowmeters (see Docket A-97-35, Item II-
E-17). The Agency also considered extending the typical time between 
accuracy testing to 12 calendar quarters--the equivalent of three 
years. Three years is the period of time that records must be retained 
in a file at the source under Sec. 75.54 (or proposed Sec. 75.57).
    The Agency also considered allowing fuel flowmeters to continue for 
up to five calendar years between accuracy tests. This is similar to 
the current provision in section 2.1.5.2 of Appendix D, which allows a 
reference fuel flowmeter to be accuracy tested as seldom as once in 
five calendar years, if the in-line comparison with a master fuel 
flowmeter shows a 1.0 percent or less difference in their flow rates. A 
five-year test cycle offers certain administrative advantages. For 
instance, fuel flowmeters used to provide heat input data for the heat 
input-versus-load correlation of Appendix E could be accuracy-tested 
before each Appendix E test (i.e., once every five years). In addition, 
the five calendar-year period would ensure that fuel flowmeters are 
tested by the time the unit's operating permit is renewed. Facilities 
might find this time cycle easier to determine than a time period based 
upon a number of calendar quarters. However, test data would need to be 
retained for five years, rather than for three years, the recordkeeping 
period for most records under part 75. However, the Agency is not 
proposing this option because five years is far too long a period of 
time to allow a unit to continue with no checks at all upon the quality 
of its data. Such an approach would allow the use of data from a fuel 
flowmeter that potentially had been reading inaccurately for the 
previous five years.
    Another option that EPA evaluated was to establish different fuel 
flowmeter quality-assurance testing frequencies depending on the fuel 
measured by the fuel flowmeter. Under this approach, oil flowmeters 
would need to be tested every four calendar quarters in which oil was 
combusted. Gas flowmeters would only need to be tested once every five 
years. The two fuels would be treated differently because units emit 
less NOX and far less SO2 when combusting gas 
than when combusting oil. In addition, gaseous fuels, particularly 
pipeline natural gas, should be less corrosive; therefore, a gas 
flowmeter should be less likely to degrade than an oil flowmeter.
    EPA believes that today's proposed approach to reducing the fuel 
flowmeter quality assurance testing frequency takes into account many 
of the concerns raised by utilities. All unit types and fuel types 
would have the same frequency of testing. This would avoid confusion 
that could follow from an approach that set different requirements for 
fuels or units that are used less frequently. A group of utilities had 
indicated that they prefer a more consistent approach (see Docket A-97-
35, Item II-E-13). Under today's proposal, infrequently-used fuel 
flowmeters (e.g., meters for backup fuel or emergency fuel) would only 
need to be calibrated once every five years. When a facility renews its 
operating permit, the permitting agency could verify that all fuel 
flowmeters have been tested at least once in the previous five years.
    The minimum period of 168 hours of fuel flowmeter usage which 
defines a ``flowmeter operating quarter'' is consistent with the 
definition of a ``QA operating quarter'' in Appendix B in today's 
proposed rule for the quality assurance of CEMS. The Agency believes 
that using a consistent minimum number of hours in a calendar quarter 
for both CEMS and fuel flowmeters will make implementation easier for 
facilities and air regulatory agencies. In addition, 168 hours should 
be a sufficiently long period of time to ensure that short-term usage 
of backup fuel or emergency fuel or short-term tests of a unit do not 
trigger unnecessary quality assurance testing.
    Today's proposed rule would also provide more flexibility in the 
methods that could be used for fuel flowmeter quality assurance 
testing. As discussed above in Section III.P.2 of this preamble, a new 
testing procedure has been proposed that would allow a facility to test 
flow rate-to-load ratio of the fuel flowmeter while leaving it 
installed. Thus, the Agency believes that the overall burden of fuel 
flowmeter testing has been significantly reduced. In addition to the 
reduced frequency of testing discussed above, the Agency believes the 
less burdensome testing procedures should address concerns of the 
regulated community.
    The Agency requests comment on whether facilities would prefer to 
base

[[Page 28096]]

the frequency of fuel flowmeter quality assurance testing on the type 
of fuel used or the amount of time the fuel flowmeter is used. Under 
the first approach, gas flowmeters would receive greater regulatory 
relief. Under the second approach, which is being proposed in today's 
rule, infrequently-used flowmeters (typically oil flowmeters) would 
receive greater regulatory relief.
(d) Orifice, Nozzle, and Venturi Visual Inspections
Background
    Section 2.1.6 of Appendix D, as revised in the May 17, 1995 direct 
final rule, created special provisions for the ongoing quality 
assurance testing of orifice fuel flowmeters. Orifice-,
nozzle-, and venturi-type fuel flowmeters are designed and installed 
within a set of physical specifications, such as the orifice diameter 
(see Docket A-97-35, Item II-D-13). Maintaining these physical 
specifications determines the flowmeter's ability to read accurately. 
Thus, it is not necessary to take an orifice-, nozzle-, or venturi-type 
flowmeter out of line and send it to a laboratory to determine its 
accuracy.
    After installation of an orifice-, nozzle-, or venturi-type 
flowmeter is complete, the two major factors that contribute to error 
in flow readings are: drift in the transmitters (or transducers) which 
determines the total pressure, differential pressure and temperature, 
and corrosion of the primary element (e.g., the orifice plate) itself. 
Quality assurance testing of the transmitters is discussed in the next 
section of the preamble. In order to identify cases where error might 
result from corrosion of the orifice plate, the May 17, 1995 direct 
final rule added a requirement for an annual visual inspection of the 
orifice plate. If an orifice plate fails the inspection, then the 
facility must perform a test on the transmitters during the next 
calendar quarter. A procedure for visual inspections is given in 
Appendix B of part 2 of American Gas Association (AGA) Report No. 3, 
which is one of the accepted standards for installation and use of 
orifice flowmeters.
    Some facilities have expressed concern with the frequency of visual 
inspections (see Docket A-97-35, Items II-D-20, II-E-13, II-E-14). This 
process must be done either with a tool, such as a boroscope, or else 
the primary element must be removed from the pipe and lifted out to be 
inspected. In the case of large, heavy orifices, it is necessary to use 
a crane to remove the orifice. Fuel must not be flowing through the 
pipe while the orifice plate is being removed (see Docket A-97-35, Item 
II-E-8).
    The current provisions of Appendix D to part 75 do not explicitly 
state the consequences of failing a quality assurance test. Section 
2.1.5.1 of Appendix D states that if a fuel flowmeter exceeds the 
flowmeter accuracy of  2.0 percent of the upper range 
value, then the flowmeter may not be used under part 75. Section 
2.1.5.2 states that if a fuel flowmeter's accuracy exceeds  
2.0 percent of the upper range value, then the flowmeter must be 
recalibrated to meet that accuracy, or it must be replaced with another 
flowmeter that meets the specification. Neither section explicitly 
states the impact upon the validity of data if a test is failed. 
However, if fuel flowmeter systems are to be treated parallel with 
continuous emission monitoring systems under Sec. 75.21(e)(2), the 
consequences of failing a quality assurance test for a fuel flowmeter 
or an inspection of the primary element should result in the monitor 
being considered out-of-control and the data being considered invalid.
    In section 2.1.6.1 of Appendix D, the specific consequence of 
failing a visual inspection of the primary element is that the 
transmitters must be tested in the following calendar quarter, rather 
than waiting until the regular annual calibration is required. However, 
no mention is made of any mandatory corrective action(s) to eliminate 
the corrosion problem.
Discussion of Proposed Changes
    Section 2.1.6.6 of Appendix D in today's rulemaking proposes to 
require visual inspections of primary elements (i.e., orifice, nozzle 
or venturi) at the frequency recommended by the manufacturer or once 
every three years, whichever is more frequent. The Agency solicits 
comment on the proposed frequency of visual inspections.
    The proposed rule would also explicitly require repair or 
replacement of the primary element and invalidation of data when a 
visual inspection is failed. Once the primary element is replaced or 
repaired, the new or repaired primary element would have to demonstrate 
that it meets the overall flow rate accuracy of  2.0 
percent of the upper range value. This could be demonstrated by showing 
that the new or repaired primary element meets the design and 
installation requirements of AGA Report No. 3 or ASME MFC-3M, the same 
methods required for initial certification. Alternatively, the flow 
rate accuracy could be demonstrated by testing the fuel flowmeter 
against a reference fuel flowmeter using the provisions of section 
2.1.5.2 of Appendix D. Finally, whenever a primary element is repaired, 
the fuel flowmeter transmitters would also have to be tested before the 
fuel flowmeter is used to provide quality assured data.
Rationale
    During the process of reviewing certification applications for 
units using orifice flowmeters, the Agency learned of one plant where 
orifice corrosion was a serious problem. This utility had an orifice 
flowmeter which had been installed in the 1960's. This utility did not 
have documentation of the standard used to install the orifice as a 
demonstration of the meter's accuracy. In order to qualify for 
certification, the utility inspected the orifice. The utility personnel 
discovered that the orifice had been completely eaten away and was 
incapable of reading the flow rate (see Docket A-97-35, Item II-E-22). 
The utility replaced the orifice before it was able to have its fuel 
flowmeter certified. In addition, it was required to invalidate the 
flow rate data from the orifice meter and substitute for the missing 
data. Based upon this experience, the Agency believes that corrosion of 
an orifice can be a problem, and that in severe cases of corrosion, 
replacement of the orifice is necessary.
    Despite this, many utilities have expressed concern over the 
difficulty of removing an orifice from place for visual inspection (see 
Docket A-97-35, Items II-D-20, II-E-13, II-E-14), because removal 
requires halting the flow of gas through the pipeline in order to 
remove the orifice, which can be expensive (see Docket A-97-35, Item 
II-E-8).
    Utilities have provided the Agency with several suggestions for 
reducing the frequency of primary element inspections. One industry 
group recommended that the Agency reduce the inspection frequency to 
once every five years, to be coordinated with renewal of the plant's 
operating permit under title V of the Act (see Docket A-97-35, Items 
II-D-20, II-E-13, and II-E-14). One utility representative mentioned 
that most orifice manufacturers recommend an inspection once every 
three years; thus, he recommended that the Agency require visual 
inspections the earlier of once every three years or the time period 
specified by the manufacturer (see Docket A-97-35, Item II-D-41). 
Another utility suggested that the Agency consider creating some sort 
of diagnostic test comparing the flow rate of the fuel flowmeter to 
unit load (generation) to determine whether the fuel flowmeter readings 
are degrading

[[Page 28097]]

over time, rather than specifying a particular time period (see Docket 
A-97-35, Item II-E-22).
    EPA agrees that it would be helpful to facilities to reduce the 
frequency of visual inspections from their current annual frequency. 
Having considered all of the options suggested by the utilities, the 
Agency is proposing that the primary element of all nozzle, venturi and 
orifice fuel flowmeters be visually inspected at the frequency 
recommended by the manufacturer or once every three years, whichever is 
the more frequent. The Agency believes that up to three years between 
visual inspections is a technically sound period of time that will 
assure the quality of fuel flow rate data, while providing regulatory 
relief from the current annual requirement.
    The Agency also has reconsidered the consequences of failure of a 
visual inspection. The May 17, 1995 direct final rule added a 
requirement to test a flowmeter's transmitters in the calendar quarter 
following a failed inspection, but the rule does not explicitly require 
that the primary element be repaired or replaced, nor does it 
explicitly require data from the fuel flowmeter to be invalidated.
    Today's proposed rule would require the primary element to be 
removed following a failed visual inspection and would require the 
problem to be corrected. The Agency believes that it is appropriate to 
provide two options for correcting the problem: either replace the 
element with a new one or repair it. This would provide flexibility to 
facilities, while still assuring that the fuel flowmeter will be 
repaired to give quality assured data.
    Today's proposed rule would also change the timing of the 
requirement for fuel flowmeter transmitter or transducer testing if a 
primary element fails its visual inspection. The Agency believes that 
it would be appropriate also to test the fuel flowmeter transmitters 
before the fuel flowmeter is placed into service again. This would be a 
more thorough quality assurance check of the entire fuel flowmeter than 
simply addressing the problem with the primary element. Thus, when the 
fuel flowmeter is placed into service again, its accuracy would be 
tested as fully as possible. In addition, EPA proposes to remove the 
requirement for a test on the flowmeter transmitters in the calendar 
quarter following a failed visual inspection. This requirement might be 
appropriate if it seemed that transmitter drift was likely to be a 
problem or if the Agency had no other means of assuring the quality of 
the data from the flowmeter after a problem with the primary element 
was known to have occurred. However, the Agency believes that problems 
with the primary element are separate from problems with drift in the 
transmitters. Because today's proposal would require a check on the 
fuel flowmeter transmitters after repair or replacement of the primary 
element, requiring an additional test of the transmitters in the 
following calendar quarter appears to be unnecessary.
    The proposed rule gives procedures for data validation when a 
primary element fails a visual inspection. The element would have to be 
replaced or repaired, and the transmitters would have to be tested 
before data would again be valid from the fuel flowmeter. During the 
period in which the flowmeter data are considered invalid, the 
appropriate missing data substitution procedures would be used. The 
Agency has clarified that these data validation procedures would also 
apply to failures of other fuel flowmeter quality assurance tests. EPA 
believes that this will make facilities' obligations clearer. In 
addition, the Agency believes that fuel flowmeter systems should be 
treated as consistently as possible with CEMS. Consistent treatment 
simplifies the part 75 requirements and is more equitable for sources 
using different monitoring approaches.
(e) Orifice, Venturi, and Nozzle Flowmeter Transmitter Testing
Background
    As discussed previously, once an orifice-, nozzle-, or venturi-type 
flowmeter has been installed, one of the major causes of error in the 
measured flow rates is drift in the transmitters or transducers that 
determines the total pressure, differential pressure, and temperature. 
The flow measurement error for these types of flowmeters is a 
combination of the errors in these individual transmitters or 
transducers and a constant error value associated with the physical 
dimensions of the primary element. The May 17, 1995 direct final rule 
added a requirement that flowmeter transmitters be tested at least 
annually. The transmitters are also required to be retested in the next 
calendar quarter if the overall flow rate error is greater than 1.0 
percent of the upper range value of the flowmeter. For practical 
purposes, this requires a facility to know the error from the physical 
dimensions of the primary element in order to determine if the 
flowmeter meets the overall accuracy requirement.
    Some utilities asked the Agency how to determine the overall 
flowmeter accuracy from individual transmitter values (see Docket A-97-
35, Item II-E-31). EPA addressed this issue in Policy Guidance (see 
Docket A-97-35, Item II-I-9, Policy Manual, Question 10.17). This 
guidance included a formula for calculating total flowmeter accuracy 
from error in transmitter readings for differential pressure, static 
pressure and temperature, and error from all other sources (i.e. 
physical dimensions of the primary element). Some utilities indicated 
that they do not always have information available on the constant 
error from other portions of the primary element (see Docket A-97-35, 
Item II-E-13). The policy guidance also indicated that a facility could 
report test results electronically using the highest amount of error 
from any of the three transmitters. Provided that the highest error 
from an individual transmitter is 1.0 percent of the upper range value 
of the transmitter or less, the overall flowmeter accuracy will be less 
than 2.0 percent of the upper range value (see Docket A-97-35, Item II-
I-10).
    EPA has also observed that transmitter test data reported for 
orifice-, nozzle-, and venturi-type flowmeters have not been 
consistent. Some facilities test each transmitter once at three 
different levels, including a low, middle, and high value (see Docket 
A-97-35, Item II-D-16). Others test each transmitter at five different 
levels, including zero, full scale, and three intermediate levels (see 
Docket A-97-35, Item II-D-17). The Agency had previously issued some 
guidance on reporting test results, both for orifice flowmeters and 
other flowmeters (see Docket A-97-35, Items II-I-4, p. 3-58, and II-I-
9, Policy Manual, Questions 10.17 and 12.27). However, this guidance 
appears to have been insufficient, as utilities have continued to 
request guidance in how to perform and report test results (see Docket 
A-97-35, Item II-D-21). Questions have included the number of levels at 
which transmitters should be tested, whether all of these levels must 
be non-zero, the number of times the transmitter should be tested at a 
particular level, if results may be reported in hardcopy or should be 
reported electronically, and how data should be reported 
electronically.
Discussion of Proposed Changes
    Today's proposed rule would make the requirement to assess the 
total accuracy of orifice-, nozzle-, and venturi-type fuel flowmeters 
from the transmitter/transducer test results an option. As an 
alternative, proposed section 2.1.6.5 in Appendix D would allow each of 
the three transmitters (static pressure, differential pressure, and 
temperature) individually to meet

[[Page 28098]]

an accuracy specification of 1.0 percent of the upper range value of 
the transmitter.
    Today's rulemaking also proposes a procedure in section 2.1.6.1 of 
Appendix D for testing the accuracy of orifice-, nozzle-, and venturi-
type fuel flowmeters. Each transmitter would be calibrated against 
NIST-traceable reference values at least once at the zero level and at 
a minimum of two other levels across the range of values that the 
transmitter reads during normal unit operation. Note that in many 
instances this would be a portion of the full-scale range of the 
transmitter, rather than the entire range. In addition, revised section 
2.1.6.2 of today's proposed rule includes the new Equation D-1a to 
clarify how to calculate the error from an individual transmitter.
    Finally, today's proposal would clearly specify the consequences of 
failure of an accuracy test on transmitters in section 2.1.6.5 of 
Appendix D. Just as CEM data are considered invalid from the time that 
a quality assurance test is failed until the test is subsequently 
passed, data from a fuel flowmeter would be considered invalid from the 
date and time of a failed transmitter accuracy test until the date and 
time of a passed transmitter accuracy test.
Rationale
    The Agency considered two main options for determining the accuracy 
of a transmitter or transducer of an orifice-, nozzle-, or venturi-type 
fuel flowmeter. In the first approach (which is consistent with current 
policy guidance), these types of fuel flowmeters would be required to 
meet an accuracy of 2.0 percent of the upper range value of the total 
flow rate of the fuel flowmeter. The accuracy would be determined using 
the square root of the sum of the squares of all sources of error in 
the fuel flowmeter, according to the following equation:
[GRAPHIC] [TIFF OMITTED] TP21MY98.000

Where: dqv/qv = Error in the volumetric flow rate 
due to transmitter drift at a given level;
K = Original error resulting from installation of orifice (including 
all other variables);
dPf = Average difference between static pressure transmitter 
reading(s) and reference static pressure reading(s) at a given level;
Pf = Average reference static pressure reading at a given 
level;
dP = Average difference between differential pressure 
transmitter reading(s) and reference differential pressure reading(s) 
at a given level;
P = Average reference differential pressure reading at a given 
level;
dTf = Average difference between temperature transmitter 
reading(s) and reference temperature reading(s) at a given level; and
Tf = Average reference temperature reading at a given level.

    If the error calculations for error from the primary element of the 
fuel flowmeter were not available, then the facility could use a 
default value of 1.0 percent of the upper range value error from all 
parts of the fuel flowmeter except for the differential pressure, 
static pressure, and temperature transmitters. (In other words, the 
factor ``K'' in the equation above would be equal to 1.0 percent of the 
upper range value.) However, this would almost certainly trigger the 
requirement for recalibration or retesting of the accuracy of the 
transmitters in the next calendar quarter because the fuel flowmeter 
accuracy would exceed 1.0 percent of the upper range value. Based upon 
statements from the American Gas Association, it is the Agency's 
understanding that for an orifice-, nozzle-, or venturi-type fuel 
flowmeter meeting AGA Report No. 3 or ASME MFC-3M, the maximum error 
from portions of the meter other than the transmitters should be 1.0 
percent of the upper range value (see Docket A-94-16, Item II-F-2, and 
this Docket, A-97-35, Item II-E-18).
    In the second approach to determining error for orifice-, nozzle-, 
and venturi-type fuel flowmeters, each transmitter or transducer would 
be tested separately for accuracy, and each transmitter or transducer 
would be required to meet an accuracy specification of 1.0 percent of 
the full scale range of the transmitter. Under this approach, it would 
no longer be necessary to determine the total error in the flowrate 
from the fuel flowmeter. Because this proposal would eliminate the 
calculation of the total error in flowrate, there would no longer need 
to be a requirement to retest the accuracy of the transmitters in the 
next calendar quarter when the total fuel flowmeter accuracy exceeds 
1.0 percent of the upper range value.
    In today's rule, EPA proposes to allow both of the approaches 
described above for calculating the total flowmeter accuracy. The 
second approach (i.e., calculating individual transmitter accuracy) is 
simpler than calculating the total error in the flow rate, although it 
is less directly related to the accuracy of SO2 mass 
emission rate and heat input measurements than the fuel flowrate. An 
individual transmitter accuracy specification of 1.0 percent of the 
full scale of each transmitter would be slightly stricter than a total 
fuel flowmeter accuracy specification of 2.0 percent of the upper range 
value of the fuel flowmeter, because one transmitter could potentially 
have an error greater than 1.0 percent of its full scale range while 
the entire error in the fuel flowrate would still be less than 2.0 of 
the upper range value of the fuel flowmeter. Thus, the option of 
calculating the total error in the fuel flowrate has been retained in 
today's proposal. At least one industry representative suggested 
allowing both approaches of calculating accuracy when testing 
transmitters of an
orifice-, nozzle-, or venturi-type fuel flowmeter (see Docket A-97-35, 
Item II-E-24).
    The Agency considered two main methodologies for transmitter 
testing on orifice-, nozzle-, and venturi-type flowmeters. The first 
method would be to require a five-point test that checks the linearity 
of the transmitter. The transmitter would be tested against an NIST 
traceable method (e.g., testing a pressure transmitter against an NIST 
traceable deadweight transmitter) at the following percentages of the 
full scale range of the transmitter: 0.0 percent, 20.0 to 30.0 percent, 
40.0 to 60.0 percent, 70.0 to 80.0 percent, and 100.0 percent. This is 
the general approach that was taken by many utilities that provided 
transmitter calibration results to EPA (see Docket A-97-35, Items II-D-
26 through 28).
    The second method would be to require a comparison to an NIST 
traceable transmitter at the zero level and at least two other levels 
across the range of readings on the transmitter or transducer. This 
would be different from the first method in that the transmitter would 
only need to be tested across the range where the transmitter is

[[Page 28099]]

actually used. For example, if a fuel flowmeter transmitter's readings 
never rise higher than 60.0 percent of the full scale range of the 
transmitter, then the transmitter could be tested at 0.0 percent, 30.0 
percent, and 60.0 percent of full scale. These procedures are reflected 
in the proposed revised section 2.1.6.1 of Appendix D.
    The Agency is proposing the second method in today's rule, i.e., 
that each individual transmitter must be tested at three or more points 
across its normal range of readings. EPA realizes that it is standard 
industry procedure to test a fuel flowmeter at five levels across its 
entire range (see Docket A-97-35, Item II-E-24). However, the Agency is 
aware of at least one case where a fuel flowmeter failed to meet an 
accuracy specification of 2.0 percent of the upper range value when it 
was tested at 100.0 percent of the upper range value. However, the fuel 
flowmeter was never used to measure a rate greater than roughly 55.0 
percent of the upper range value (see Docket A-97-35, Item II-D-15). If 
this flowmeter had only been required to test across the range where 
the fuel flowmeter actually measured fuel flow rates, it would have met 
the accuracy specification. Section 2.1.5 requires fuel flowmeters that 
are tested against a master fuel flowmeter to be tested across the 
range of measured fuel flowrate only. Requiring testing of each 
transmitter at three or more points across the range of all readings 
would still ensure that the transmitter reads accurately across all 
readings, while reducing the possibility that the transmitter might 
fail an accuracy test because of a high error reading at the high end 
of the transmitter's range where the transmitter is never used. At 
least one utility has mentioned that this would be helpful (see Docket 
A-97-35, Item II-E-24). The Agency solicits comment on the proposed 
approach.
    Today's proposed rule also includes Equation D-1a for calculating 
error from an individual flowmeter transmitter. The Agency feels that 
this would clarify the calculation. It also would prevent the possible 
confusion that would occur if a facility attempted to use the existing 
Equation D-1, which is designed for a fuel flowmeter that is compared 
to another fuel flowmeter.
    Finally, under today's proposal, when a transducer or transmitter 
test is failed, a fuel flowmeter would be considered out-of-control, 
and its data would be considered invalid until the date and time the 
transmitter is retested and meets an accuracy of 1.0 percent of its 
full scale.
(f) Reporting of Fuel Flowmeter Testing Data
Background
    As mentioned above in Section III.P.5 of the preamble, utilities 
have had questions about how to report the results of their fuel 
flowmeter testing data. In certification applications and quality 
assurance testing results, utilities have reported test data in a 
variety of ways. In some cases, the Agency was unable to determine the 
flowmeter accuracy from the testing information provided because data 
were not labeled as reference flow rate data, flowmeter data, or 
accuracy data. For example, for turbine flowmeters, data on the 
reproducibility of the ``K-factor'' was often presented. However, these 
are not flow rate data, nor is it clear what the accuracy of the flow 
rate is (see Docket A-97-35, Item II-D-9). Sometimes data were 
presented in tables. Other data were presented in graphs (see Docket A-
97-35, Item II-D-9). In many cases, Agency or state environmental 
agency staff needed to request additional information from utilities to 
determine if they had met the accuracy requirement for fuel flowmeters 
(see Docket A-97-35, Items II-C-3, II-C-5).
    To clarify the requirements for certification applications for fuel 
flowmeters, the Agency issued policy guidance about the type of 
information to provide (see Docket A-97-35, Item II-I-9, Policy Manual, 
Question 12.27). This guidance included a sample table with an example 
of how to submit information for a fuel flowmeter that is tested 
against a master meter or flow prover reference value.
Discussion of Proposed Changes
    EPA proposes to add a sample table to Appendix D (Table D-1) for 
summarizing the results of accuracy tests of fuel flowmeters that are 
calibrated by comparison against other fuel flowmeters or a prover. In 
addition, EPA proposes to add a separate table for summarizing the 
results of calibrations of the transmitters or transducers of an 
orifice-, nozzle-, or venturi-type fuel flowmeter.
Rationale
    In today's proposed rule, EPA would provide clarification in the 
form of a table for summarizing the quality assurance test results of 
fuel flowmeters that are compared against other fuel flowmeters or a 
prover. A second table is provided for summarizing the results of 
calibrations of transmitters or transducers of an orifice-, nozzle-, or 
venturi-type fuel flowmeter. This second table accounts for differences 
in the testing procedure for transmitters or transducers. In both 
cases, EPA has tried to make clear what critical information would have 
to be reported in order to demonstrate that the fuel flowmeter (or the 
transmitter of an orifice-, nozzle-, or venturi-type fuel flowmeter) 
meets the accuracy specification. In addition, EPA will design revised 
electronic record types with this type of information so that test 
results may be more easily reported electronically. The Agency is aware 
that this has been difficult or confusing for some utilities (see 
Docket A-97-35, Items II-D-23, and II-I-9, Policy Manual, Question 
12.27). The Agency also considered adding a sample graph for reporting 
accuracy data. However, EPA feels that it would be easier to compare 
the data in tabular format and to enter it into the electronic data 
format than to enter values from a graph. Most of the graphs provided 
to EPA have been relatively easy to read, and there appears to be less 
of a need for an example to be included in Appendix D (see Docket A-97-
35, Item II-D-9).
7. Use of Uncertified Commercial Gas Flowmeter
Background
    Currently, a facility using Appendix D may either install its own 
gas flowmeter or use a commercial gas flowmeter owned by a pipeline 
natural gas supplier, provided that the meter meets the reporting and 
accuracy requirements of Appendix D, including initial certification 
and continuing quality assurance requirements. Some utilities have 
suggested to EPA that they would like to be able to use data from the 
commercial billing of pipeline natural gas without having to 
demonstrate that the gas flowmeter meets initial certification and 
continuing quality assurance requirements (see Docket A-97-35, Items 
II-D-45, II-D-49). Those utilities assert that because the amount of 
gas measured is already subject to market forces, the monitoring should 
be sufficiently accurate for the Acid Rain Program. Utilities have 
mentioned that gas companies often are already conducting meter 
calibrations as quality assurance, but utility customers generally do 
not have access to this information (see Docket A-97-35, Items II-D-49, 
II-E-33). Facilities would find it advantageous to rely upon their 
commercial billing charges for accounting for pipeline natural gas 
usage because they would need to devote less time, effort, and money to 
the maintenance of gas fuel flowmeters. This is particularly desirable 
to facilities since the SO2 emissions from pipeline

[[Page 28100]]

natural gas are extremely low compared to the SO2 emissions 
from other fuels.
Discussion of Proposed Rule Changes
    Proposed section 2.1.4.2 of Appendix D would allow facilities to 
record and report the gas flow rate, the heat input rate, and emission 
values based on gas flowmeter readings from a flowmeter used for 
commercial billing of pipeline natural gas without meeting the 
certification requirements of section 2.1.5 of Appendix D or the 
quality assurance requirements of section 2.1.6 of Appendix D under 
specified conditions. Relief from the certification and quality 
assurance requirements for gas flowmeters used for commercial billing 
would be limited to flowmeters where the gas flowmeter is used for 
commercial billing under a contract with another company having no 
common owner with the unit(s) served by the flowmeter, which would 
exclude any gas flowmeters used for transfers of gas between different 
divisions, subsidiaries, or affiliates of the same company.
    If the commercial billing gas flowmeter would be used without 
undergoing certification or quality assurance under part 75 
requirements, then the designated representative would need to report 
hourly records of the gas flow rate, the heat input rate, and emissions 
due to combustion of pipeline natural gas, as well as heat input rate 
for each unit if the commercial billing gas flowmeter is on a common 
pipe header. This would be similar to the reporting currently done for 
a certified gas flowmeter, but no quality assurance records would be 
required. The quarterly report would contain record types 303 for fuel 
flow rate and heat input rate, record type 314 for the SO2 
mass emission rate, either record type 320 or 323 for the 
NOX emission rate in lb/mmBtu, and either record type 330 or 
331 for CO2 mass emissions. It also would be necessary for 
the designated representative to identify the commercial billing gas 
flowmeter in Table B (electronic record type 510) of the monitoring 
plan for the unit.
    So long as the records from the commercial billing gas flowmeter 
are the values used for commercial billing, the designated 
representative would report those values from the commercial billing 
gas flowmeter without adjustment. If the records from the commercial 
billing gas flowmeter are not consistent with the values used for 
commercial billing because of some problem that needs to be reconciled 
between the gas vendor and the facility customer, then the designated 
representative would consider the readings from the commercial billing 
gas flowmeter to be invalid for that billing period and would report 
hourly records using the missing data procedures for fuel flowmeter 
data found in section 2.4 of Appendix D for all hours of gas combustion 
during that billing period. A facility would not be able to use the 
commercial billing value in the quarterly report if the commercial 
billing value was different from the value on the commercial billing 
gas flowmeter.
Rationale
    Utilities have suggested that the purchase of pipeline natural gas 
from a vendor is subject to market forces that ensure accurate 
monitoring (see Docket A-97-35, Item II-D-49). Utilities have stated 
that gas vendors already have procedures for certification and meter 
calibration and that the gas vendors have an even greater incentive 
than utilities to maintain a high monitor ``uptime'' (i.e., 
availability) for gas fuel flowmeters. Typically, utilities will work 
together with their gas vendors if they believe there is any sort of 
discrepancy in their monthly billing for pipeline natural gas (see 
Docket A-97-35, Items II-D-33, II-E-33).
    The Agency believes that this argument is reasonable. However, EPA 
also understands that some utilities require their gas vendor to 
correct their billing values based upon the evidence of the utility's 
own gas flowmeters. In addition, it is likely that utilities will be 
combusting more pipeline natural gas in the future as they respond to 
current and potential future environmental requirements for reducing 
NOX and CO2. Therefore, the Agency believes that 
there must be conditions placed upon reporting emissions and heat input 
for the Acid Rain Program from gas flowmeters used for commercial 
billing if the gas flowmeters will not be required to meet the 
certification and quality assurance requirements of part 75.
    The Agency is proposing to limit the waiver from certification and 
quality assurance requirements to commercial billing gas flowmeters 
that are used in billing transactions between companies with entirely 
different ownership (e.g., a pipeline natural gas vendor and a separate 
electric utility company with no owners in common). Some utilities 
requested the relief from quality assurance requirements based upon the 
reasoning that a gas vendor would do its own quality assurance and 
maintenance, and perhaps with better accuracy than a utility would be 
able to maintain, but the utility would not necessarily have access to 
the test results and would not have control over what quality assurance 
might occur (see Docket A-97-35, Items II-D-49, II-E-33). This 
reasoning is sound if the utility and the gas vendor have no common 
owners, but it would not necessarily be sound if a gas supplier were 
part of the same company as the electric utility. Also, utilities 
suggested that a gas vendor may have an incentive to overstate the 
amount of gas in order to bill more, rather than having an incentive to 
underestimate or under-report (see Docket A-97-35, Item II-D-49). Once 
again, this argument is reasonable if the gas vendor is a separate 
entity, but may not be reasonable if the gas supplier has common owners 
with the electric utility. Therefore, today's proposed rule includes a 
limitation on the waiver from certification and quality assurance 
requirements for commercial billing gas flowmeters to those gas 
flowmeters used for commercial billing between companies with separate 
ownership.
    EPA solicits comment on the proposed approach of allowing the use 
of uncertified fuel flowmeters for purposes of determining emissions 
and heat input in the limited circumstances described above.
    EPA has proposed in today's rule that a facility may only report 
data from a commercial billing gas flowmeter if the data are used in a 
commercial transaction. A group of utilities suggested that the Agency 
allow facilities to report quarterly SO2 emissions based on 
gas supplier data, including any reconciliation that has taken place 
(see Docket A-97-35, Item II-D-45). Such a reconciliation between a gas 
vendor and its customer may occur if the customer believes there is a 
discrepancy in their monthly billing for pipeline natural gas (see 
Docket A-97-35, Items II-D-33, II-E-33). If a facility and its gas 
vendor determined that gas supply information from a fuel flowmeter 
were not sufficiently accurate to purchase gas, then the Agency 
presumes the gas supply information is also not sufficiently accurate 
for emissions accounting.
    The Agency also considered whether a facility should be able to use 
the reconciled gas volumes agreed upon for billing if that value were 
not from the commercial billing gas flowmeter. In general in the Acid 
Rain Program, hand-typed corrections to emissions data are not 
permitted (see Docket A-97-35, Item II-I-14), with the primary 
exception of cases where sound engineering judgement indicates there is 
an obvious error that cannot exist, such as a negative concentration 
reading.

[[Page 28101]]

Allowing a facility to enter a commercial billing value by hand would 
contradict this basic reporting policy of the Acid Rain Program.
    Today's proposed rule also specifies the type and frequency of 
information that would be required to be reported by a facility 
concerning pipeline natural gas. Some utilities have requested the 
ability to report only a quarterly cumulative SO2 mass 
emission number for emissions from gas (see Docket A-97-35, Item II-D-
45). However, the Agency believes that there are several reasons for 
maintaining hourly heat input rate and emissions data during combustion 
of pipeline natural gas. First, hourly data is the most useful interval 
of data for air quality modeling in order to see if progress is being 
made in reducing emissions. Hourly data from combustion of pipeline 
natural gas will become even more important as more units switch to 
combusting pipeline natural gas in order to reduce their emissions. In 
addition, hourly data are easier to check for anomalous values than 
quarterly data. Further, hourly heat input rate data is necessary in 
order to determine the NOX emission rate when using the 
NOX-versus-heat input rate correlation of Appendix E to part 
75. Also, since hourly data are already being recorded, reported, and 
processed by automated computer data acquisition and handling systems, 
a change to this requirement would require costly reprogramming for 
industry and for EPA. For all of these reasons, EPA is proposing that 
facilities continue to report hourly gas flow rates, heat input rates, 
and emissions from commercial billing gas flowmeters that are not 
required to meet the certification and quality assurance requirements 
of part 75.

Q. Appendix G

1. Use of ASTM D5373-93 for Determining the Carbon Content of Coal
Background
    Appendix G to part 75 provides procedures for determining 
CO2 emissions from fuel sampling and analysis instead of 
from a CO2 CEMS and a flow monitor. Section 2.1 of Appendix 
G includes a mass-balance equation for determining CO2 (see 
Equation G-1), the frequency for sampling fuel, and the specific 
methods for analyzing fuel for carbon content. Section 2.3 of Appendix 
G provides a method for determining CO2 mass emissions from 
a gas-fired unit from its heat input using Equation G-4. Some 
facilities use Appendix G procedures to determine CO2 mass 
emissions every day for their units. Other facilities might use the 
procedures of section 2.1 of Appendix G only to provide CO2 
mass emissions during extended periods when CO2 data are 
missing from their CO2 CEMS, under the provisions of 
Sec. 75.36.
    A utility and its fuel analysis laboratory contacted EPA concerning 
use of an additional ASTM method for analysis of carbon content. The 
industry staff felt that the new infrared analysis method, ASTM D5373-
93, was the most up-to-date method and that this method should be at 
least as accurate as the methods specified in Appendix G to part 75 
(see Docket A-97-35, Item II-D-25). Based upon the precision and bias 
information in the method, EPA approved its use under Sec. 75.66 (see 
Docket A-97-35, Item II-C-16).
Discussion of Proposed Changes
    Today's proposed rule would allow the use of ASTM D5373-93, 
``Standard Methods for Instrumental Determination of Carbon, Hydrogen, 
and Nitrogen in Laboratory Samples of Coal and Coke,'' for Section 2.1 
of Appendix G to part 75. This method is for determining the carbon 
content of coal. ASTM D5373-93 would also be incorporated by reference 
in Sec. 75.6. Facilities would also continue to have the option to use 
ASTM D3178-89 to analyze coal for carbon content.
Rationale
    EPA has previously approved the use of ASTM D5373-93 for analyzing 
the carbon content of coal (see Docket A-97-35, Item II-C-16). The 
Agency believes this method is of sufficient accuracy for use in the 
Acid Rain Program. In addition, EPA historically has accepted 
analytical methods from standard-setting organizations such as the 
American Society for Testing and Materials (ASTM). The Agency solicits 
comment on the use of ASTM D5373-93 for analyzing the carbon content of 
coal.
2. Changes to Fuel Sampling Frequency
Background
    Section 2.1 of Appendix G (as revised by the May 17, 1995 direct 
file rule) specifies that fuel sampling should be done weekly for gas 
or oil for each shipment for diesel fuel and at least once per month 
for gaseous fuel. The sampling frequencies for diesel fuel and for 
gaseous fuel are consistent with the frequency for sampling under 
Appendix D to part 75.
    Most gas-fired and oil-fired units that perform fuel sampling for 
sulfur content under Appendix D also perform fuel sampling for carbon 
content. Today's proposed rule would reduce the frequency with which 
facilities need to sample oil or gas under Appendix D.
Discussion of Proposed Changes
    The fuel sampling frequency specified in section 2.1 of Appendix G 
would be made consistent with the proposed requirements for Appendix D 
oil and gas sampling. Thus, all oil samples could be taken upon 
delivery, either from the delivery vessel itself or from the storage 
tank after a delivery is transferred. Gas samples would be taken 
monthly (for pipeline natural gas), for each shipment (for gases 
delivered in lots), or daily (for fuels that are analyzed daily for 
sulfur). Coal samples would continue to be taken weekly.
Rationale
    Appendix D of today's proposed rule would reduce the required 
sampling frequency of oil and gaseous fuels delivered in lots. Based 
upon information provided by one utility, the variability of carbon 
content in oil is less than the variability of sulfur content (see 
Docket A-97-35, Item II-D-18). Some utilities have stated that they 
would prefer the procedures for sulfur and GCV to be similar (see 
Docket A-97-35, Item II-D-24). Based upon this statement, the Agency 
believes that facilities would also prefer to have consistent fuel 
sampling procedures for Appendices D and G. Therefore, the Agency 
believes it is appropriate to make the fuel sampling frequency for 
carbon analysis under Appendix G consistent with the fuel sampling 
frequency for sulfur content under Appendix D. Similarly, section 5.5 
of Appendix F would be revised to make the gas sampling frequency 
consistent with Appendix D. The Agency solicits comment on the proposed 
changes to the fuel sampling frequency.
3. Addition of Missing Data Procedures for Fuel Analytical Data
Background
    Appendix D provides procedures for substituting missing fuel 
analytical information, either for sulfur or GCV. However, Appendix G 
to part 75 does not specify what should be done if carbon content data 
are missing.
    Some software programmers asked EPA what missing data procedures 
should be used for carbon content data (see Docket A-97-35, Item II-E-
5). The Agency responded to this question at a public conference and in 
policy guidance (see Docket A-97-35, Items II-E-5, and II-I-9, Policy 
Manual, Question 6.3). In its policy guidance, EPA stated that 
facilities should ``[f]ill in the most recent carbon content . . . 
available for that fuel type (gas, oil or

[[Page 28102]]

coal) of the same grade (for oil) or rank (for coal). If at all 
possible, use a carbon content value from the same fuel supply.''
Discussion of Proposed Changes
    Today's proposed rule would allow facilities to substitute for 
missing carbon content prior to January 1, 2000, using either the most 
recent carbon content for that fuel type, grade and rank, or procedures 
parallel to those of Appendix D. Beginning January 1, 2000, facilities 
would substitute for missing carbon content data using procedures 
consistent with Appendix D. For gaseous fuels and for oil sampled 
manually, these procedures would provide for a conservative maximum 
carbon content value. Specifically, the permissible conservative carbon 
content values would be either the maximum carbon content measured in 
the previous calendar year or, if this information were not available, 
a default value based upon handbook fuel characteristics. For weekly 
coal samples or composite oil samples, CO2 mass emissions 
would be calculated using the highest carbon content from the previous 
four carbon samples available.
Rationale
    Software programmers have already indicated that it is useful to 
have a procedure for filling in missing carbon content data for 
purposes of programming (see Docket A-97-35, Item II-E-5). Some 
utilities have stated that they would prefer the missing data 
procedures to be similar for both sulfur and GCV, even if both values 
are conservative (see Docket A-97-35, Item II-E-24). Therefore, the 
Agency believes that facilities would also prefer to have Appendix G 
missing data procedures for carbon content that are parallel with those 
for sulfur content and GCV in Appendix D. Thus, today's proposal would 
allow for missing data for manual oil samples or for gaseous fuel using 
the maximum carbon content measured in the previous calendar year or, 
if this information were not available, a default value based upon 
handbook fuel characteristics.
    In determining the conservative default carbon content values that 
would be used for missing data substitution in the event that no 
previous carbon content samples are available, the Agency consulted 
several handbook reference tables on fuel characteristics. 
Specifically, the Agency reviewed handbook values for the carbon 
content of coal (of various ranks), oil (of various grades), and gas 
(of different types). (see Docket A-97-35, Items II-I-18, II-I-19, II-
I-20). In the case of coal, there was a fairly wide range of carbon 
content values for different ranks of coal. Therefore, today's rule 
would propose separate default carbon content values for Anthracite, 
Bituminous, and Subbituminous/Lignite. In contrast, the carbon content 
values for different grades of residual oil were fairly consistent. For 
this reason, today's rule proposes a single default carbon content 
value for all grades of oil. Finally, for gaseous fuels, the handbooks 
which were reviewed presented a fairly narrow range of values for 
natural gas but a much wider range of values for other types of gaseous 
fuels. Therefore, today's rule proposes a value for natural gas and a 
separate, conservative value for all other types of gaseous fuels.
    The Agency solicits comment on the proposed revisions to the 
missing data procedures under Appendix D.

R. Reporting Issues

1. Partial Unit Operating Hours and Emission and Fuel Flow Rates
Background
    For affected units that use CEMS to account for emissions under 
part 75, hourly emission rates of SO2 (in lb/hr), 
NOX (in lb/mmBtu), and CO2 (in tons/hr), and 
hourly heat input rates (in mmBtu/hr) are calculated using the 
applicable equations in Appendix F. For affected units that use fuel 
flow meters and fuel analysis (or default emission rates) rather than 
CEMS, the applicable equations in Appendices D, F and G (for certain 
gas-fired units) are used to determine the hourly SO2 and 
CO2 mass emission rates and heat input rates. For oil and 
gas-fired peaking units that use Appendix E to account for 
NOX emissions, the hourly NOX emission rates in 
lb/mmBtu are derived from a graph of NOX emission rate 
versus heat input rate, the hourly heat input rates being derived from 
the applicable equation in Appendix F. Under Sec. 75.54(b)(2), unit 
operating time is reported by rounding the actual operating time up to 
the nearest 15 minutes.
    The equations in Appendices D through G assume that each unit 
operating hour consists of a full 60 minutes of unit operation (or, for 
common stacks, that emissions are discharged through the stack for 60 
minutes in each hour); the equations do not attempt to account for 
partial unit operating hours. This is a shortcoming in the current 
rule, because partial unit operating hours sometimes occur during 
periods of unit startup, shutdown, and malfunction. Therefore, to 
ensure accurate accounting of SO2 and CO2 mass 
emissions and unit heat input, part 75 should address the issue of 
partial unit operating hours. Note, that because NOX 
emission rates are measured with respect to heat input (lb/mmBtu), 
rather than with respect to time (lb/hr), this discussion is not 
relevant for NOX emission rate. Many vendors and utilities 
have asked EPA for guidance on how to calculate mass emission rates 
during partial unit operating hours (see, e.g., Docket A-97-35, Item 
II-D-4).
    The crux of the partial unit operating hour issue is when to adjust 
the emission data for unit operating time, before the reporting of 
hourly values or at the quarterly summation. For many units, there are 
very few hours of partial operation, and adjusting the data for 
operating time merely involves multiplying by 1, a seemingly 
inconsequential issue. For other units, such as peaking and cycling 
units, which start up and shut down often, the issue of how the data is 
reported is relevant because there can be a significant amount of 
partial unit operating hours. Definitive and standardized reporting 
requirements allow facilities and/or vendors to program their software 
such that their calculated result equals the result calculated by EPA.
    For SO2 and CO2, the question is whether to 
report hourly emissions on a mass basis (i.e., lb or tons) or on a mass 
emission rate basis (i.e., lb/hr or tons/hr). For heat input, the 
question is whether to report the total hourly heat input (in mmBtu) or 
the hourly heat input rate (in mmBtu/hr). For example, suppose that a 
unit emits for a full 60 minutes in a particular clock hour at an 
SO2 concentration of 602.5 parts per million (ppm), a 
CO2 concentration of 10.0 percent, a volumetric flow rate of 
4,000,000 standard cubic feet per hour (scfh), and a heat input rate of 
300 mmBtu/hr. Suppose further that the same unit operates for only 15 
minutes in the next hour and all of the parameters (i.e., 
SO2 and CO2 concentration, flow rate, and heat 
input rate) remain unchanged. If unit operating time is disregarded, 
the SO2 mass emission rate (calculated from Equation F-1 in 
Appendix F) would be the same (400 lb/hr) for both the partial 
operating hour and the full unit operating hour. Similarly, the 
CO2 mass emission rate would be the same (22.8 tons/hr) and 
the heat input rate would be the same (300 mmBtu/hr) for both the full 
and partial operating hours. The mass emission rates and heat input 
rate for the partial unit operating hour are the same as the full-hour 
values because they are based solely upon data recorded during unit 
operation, i.e., in

[[Page 28103]]

the first 15 minutes of the hour. The hourly average rates for the 
partial hour do not include ``zero'' values for the three 15-minute 
periods of unit non-operation during the clock hour (e.g., an 
SO2 emission rate of (400 lb/hr + 0 + 0 + 0)/4 = 100 lb/hr 
would not be appropriate). If the emission and heat input rates are 
adjusted by multiplying them by the operating time, then, for the full 
operating hour (i.e., operating time = 1.0), the SO2 and 
CO2 mass emissions and heat input would be, respectively, 
400 lb SO2, 22.8 tons CO2, and 300 mmBtu. For the 
partial hour (operating time = 0.25), the corresponding values would 
all be divided by four, i.e., 100 lb SO2, 5.7 tons 
CO2, and 75 mmBtu, respectively.
    Software vendors and utilities have requested clarification as to 
whether hourly SO2 mass emission values should be reported 
as totals, in lb, or as rates, in lb/hr. As early as November of 1993, 
EPA stated that hourly SO2 mass emission values should be 
reported as rates in lb/hr. Then, when determining quarterly cumulative 
SO2 mass emissions, each hourly emission rate would be 
converted to a mass basis by multiplying it by the unit operating time 
(expressed as a fraction of an hour) for the same hour. Similarly, 
hourly heat input values would be expressed as rates, in mmBtu/hr, and 
hourly CO2 mass emissions would be expressed as rates, in 
tons/hr. Parallel issues were also addressed by the Agency's policy, 
for units that determine SO2 and CO2 mass 
emissions and heat input from fuel flow rates and fuel analyses under 
Appendix D to part 75 (see Docket A-97-35, Item II-I-9, Policy Manual, 
Questions 14.14, 14.36 and 14.37).
    Some utilities have requested that the Agency change its policy and 
allow reporting of hourly total SO2 and CO2 mass 
emissions and heat input instead of mass emission rates and heat input 
rates (see Docket A-97-35, Item II-E-14). The utilities argued that 
this would simplify determination of the total year-to-date 
SO2 mass emissions, in order to estimate the number of 
allowances needed to cover a unit's emissions or to prepare a report on 
mass emissions for a state environmental agency, because the reported 
values would already be multiplied by the hourly operating time. Thus, 
by performing the multiplication by operating time before reporting the 
hourly value rather than waiting until calculating the quarterly value, 
it might save a calculation step if a facility wanted to use the data 
for another purpose. For these reasons, reporting of totals is a 
preferred approach for some facilities. However, other utilities that 
have incorporated the correct rate approach into their software have 
indicated that they would prefer not to have to revise their software 
to report in totals.
    Partial unit operating hours must also be considered in the 
recording and reporting of hourly unit load. The standard missing data 
procedures in Sec. 75.33 require historical flow rate data to be placed 
in load ``bins'' (ranges) based upon the maximum operating electrical 
generation (or steam flow rate) of the unit. However, the recorded 
hourly volumetric flow rate value in scfh applies only to the fraction 
of the hour in which the unit operates. Therefore, the reported load 
for the hour should be based upon the average electrical generation 
during the period when the unit operates. Thus, the electrical 
generation should be recorded as a rate for the period when the unit 
operates, rather than an integrated total for the entire hour. The 
units for reporting hourly load should, therefore, be MWe or 1000 lb/hr 
of steam, and not MW-hr or 1000 lb of steam.
Discussion of Proposed Changes
    In today's rulemaking, EPA is proposing to amend part 75 to clarify 
that heat input, fuel flow, SO2 mass emissions, and 
CO2 mass emissions are all to be reported on an hourly basis 
as rates. Today's proposal also would clarify that the hourly emission 
rates are to be based only upon data collected during periods of unit 
operation (i.e., for partial unit operating hours, emission rates or 
heat input rates of zero that are recorded during periods of non-
operation are not to be included in the hourly average emission rates). 
These clarifications are found in proposed Sec. 75.57, and Appendices 
D, E and F to part 75. Today's proposed rule would also clarify that 
the proper units of reporting for load are MWe and lb/hr of steam.
    Today's proposal would also provide new options for reporting unit 
operating time. While the current requirement to report operating time 
rounded to the nearest 15 minutes would be retained as an option, the 
proposal would allow more flexibility by specifying that, for reporting 
purposes, unit operating time be rounded up to the nearest fraction of 
an hour (in equal increments that can range from one hundredth to one 
quarter of an hour, at the option of the owner or operator).
    Consistent with the requirement to report hourly SO2 and 
CO2 mass emissions and hourly heat input as rates, today's 
rulemaking proposes to revise the quarterly summation formulas for 
SO2 and CO2 and to add summation formulas for 
heat input in Appendix F to part 75. The proposed formulas show that 
hourly mass emission rates or heat input rates would be multiplied by 
unit operating time before summing to get total mass emissions. Today's 
proposal also includes new formulas in Appendix D for summing hourly 
SO2 mass emission rates and hourly heat input values from 
fuel flowmeter systems in order to determine quarterly and annual total 
SO2 mass emissions and total heat input. The Appendix D and 
F equations revised or added to address summations include Equations D-
6, D-7, D-8, D-9, F-3, F-12, F-24, and F-25.
    In addition, EPA is proposing optional recordkeeping provisions for 
determining total heat input, total SO2 mass emissions or 
total CO2 mass emissions for the hour. In addition to 
reporting the required emission and heat input rates, owners or 
operators could choose to report the total hourly heat input and mass 
emissions under this option.
Rationale
    As stated above, some utilities have expressed a preference for 
reporting hourly total values for SO2 and CO2 
mass emissions and heat input, rather than rates (see Docket A-97-35, 
Item II-E-14). They have stated that this is easier to understand and 
that reporting hourly total values, instead of or in addition to rates, 
would make it easier to determine the cumulative total mass emissions 
at any time during the year.
    One representative requested that EPA consider allowing either 
method of calculation (i.e., hourly rates or totals), so long as the 
annual mass emissions and heat inputs are correctly determined and 
reported. EPA notes that, although this approach may appear 
advantageous because it would not require some facilities to reprogram 
their DAHS software, it would require other facilities to reprogram 
their software and it would make it difficult for EPA to verify 
emissions calculations from reported hourly data. Because EPA considers 
it essential to the Acid Rain Program to be able to recalculate annual 
compliance values based upon hourly emission information reported by 
facilities, the Agency is not revising the rule to take the 
representative's suggestion. EPA considered using the total mass 
emissions (or total heat input) approach instead of the mass emission 
rate (or heat input rate) approach currently stated in Agency policy 
(see Docket A-97-35, Item II-I-9, Policy Manual, Questions 14.14 and 
14.36). In fact, as discussed in section III.H. of this preamble, the 
Agency is proposing, under subpart H of part 75, model

[[Page 28104]]

reporting requirements for NOX mass emissions that would (if 
adopted by an applicable state or federal authority) require hourly 
NOX mass emissions to be reported as a total value (in lb) 
rather than an hourly mass emission rate (in lb/hr). However, using 
hourly mass emission totals for values currently reported to the Agency 
would have the distinct disadvantage of requiring both EPA and the 
utilities who correctly implemented the mass emission rate approach to 
reprogram software to perform the new calculations, whereas retaining 
the use of SO2 and CO2 emission and heat input 
hourly rates offers several advantages.
    First, using hourly mass emission rates and heat input rates 
instead of totals is consistent with the units of measure in which flow 
rate is recorded. Volumetric flow monitors measure flow rate during a 
given time in standard cubic feet per hour scfh, rather than total flow 
in standard cubic feet (scf). When SO2 concentration is 
multiplied by volumetric flow rate, one calculates a mass emission rate 
rather than a total mass of SO2. Similarly, multiplying a 
volumetric flow rate by a diluent gas concentration yields a heat input 
rate in mmBtu/hr, rather than a total heat input in mmBtu.
    Second, the current missing data procedures for volumetric flow 
rate, which are based upon the assumption that flow is a rate that is 
comparable from one hour to another, rather than a total volumetric 
flow that will vary depending upon the unit operating time, would no 
longer be appropriate if volumetric flow rate were changed to a total 
volumetric flow. Third, for Appendix E gas-fired or oil-fired peaking 
units, it is critical that heat input rate, and not total heat input, 
be used to determine the NOX emission rate. The Appendix E 
correlation curve formulas are based upon heat input rate rather than 
total heat input. Appendix E allows a facility to create a correlation 
of the NOX emission rate measured in the stack during stack 
testing and heat input combusted during that same period of time, 
rather than installing CEMS on gas-fired or oil-fired peaking units. If 
a facility were mistakenly to use the total heat input from an hour 
rather than the heat input rate, it would correlate to the wrong 
portion of the NOX to heat input rate correlation curve and 
would incorrectly estimate NOX emission rate. For example, 
if heat input totals were used to determine NOX emission 
rate from the Appendix E curve, the unit would have a different 
NOX emission rate if it combusted 25,000 mmBtu in half an 
hour than if it combusted 25,000 mmBtu during a full hour. This would 
apply both under the current provisions of Appendix E and today's 
revised provisions to Appendix E.
    In view of the above considerations, today's proposed rule would 
affirm that facilities are to report SO2 and CO2 
emissions and heat input as rates on an hourly basis. However, 
facilities would also be allowed, at their discretion, to report 
SO2 and CO2 emissions and heat input as hourly 
totals, in addition to reporting them as rates. This approach would not 
require reprogramming of computerized reporting software for those 
utilities that are following EPA's current policy, and would provide 
consistent reporting that allows EPA to recalculate emissions and heat 
input values. Those utilities that find recording and reporting of 
hourly total SO2 and CO2 mass emissions and heat 
input to be desirable would be able to do so. EPA will provide the 
necessary electronic record types to support this optional reporting.
    Although today's proposed rule would affirm that emissions and heat 
input are to be reported as rates, rather than totals, EPA has become 
concerned that for partial unit operating hours, some utilities are 
incorrectly calculating hourly average flow rates by including flow 
rates of zero in the hourly average to represent periods of non-
operation, rather than basing the average flow rate solely on the 
minutes of operation of the affected unit during the clock hour. In one 
example, it appears that the software is designed to calculate the 
average flow rate by including data from all minutes during those 
fifteen-minute quadrants of an hour when the unit operates, thus 
including some minutes when the unit is not operating, rather than 
creating an average flow rate just from merely those minutes when the 
unit is operating and emitting (see Docket A-97-35, Item II-C-17). EPA 
suspects that still other utilities may be calculating an average 
hourly flow rate that includes flow rates of zero for whole quadrants 
of an hour when a unit does not operate. This can result in the flow 
rate values for partial operating hours being under-reported to EPA and 
a lowering of the average flow rates in the load ranges used to provide 
substitute flow rate data, both of which can cause underestimation of 
SO2 mass emissions.
    The Agency is also concerned that this same kind of improper data 
averaging may be occurring when hourly gas concentrations are 
determined during partial operating hours. EPA would, therefore, 
require in today's proposal that facilities base all of their reported 
hourly average concentrations, flow rates, emission rates, and heat 
input rates solely upon data that are recorded during unit operation 
(that is, when the unit is combusting fuel and emitting).
    Some utilities have indicated that the approach of averaging in 
readings of zero from periods of non-operation has been incorporated to 
compensate for having to report operating time rounded up to the 
nearest fifteen minutes (Note, this is not an acceptable approach). A 
utility representative indicated that reporting operating time to less 
precision can cause overestimation of emissions because the operating 
time is multiplied by the mass emission rate. Thus, a mass emission 
rate of 400 lb/hr measured over a period of 20 minutes, during an hour 
when the unit shut down, would be multiplied by an operating time of .5 
hr (i.e., 20 minutes rounded up to the nearest fifteen minutes) and 
would result in 200 lb of SO2 being reported rather than the 
132 lb of SO2 that was actually emitted. The utility 
suggested that a solution would be to allow operating time to be 
reported to more precision than is currently allowed. Therefore, 
today's proposal would allow flexibility for reporting unit operating 
time to greater precision. While the current requirement to report 
operating time rounded up to the nearest 15 minutes would be retained 
as an option, the proposal would allow more flexibility by specifying 
that unit operating time be rounded up to the nearest fraction of an 
hour (in equal increments that can range from one hundredth to one 
quarter of an hour, at the option of the owner or operator). Thus, a 
facility could decide whether it had enough partial operating hours 
(e.g., unit start-ups and shutdowns) to merit changing their software 
to report operating time to more precision.
2. Use of Bias-Adjusted Flow Rates in Heat Input Calculations.
    In late 1995, the first year of the Phase I SO2 
allowance program, EPA conducted an audit of the Phase I-affected 
units. Data from the second quarter of 1995 were retrieved from the 
Emission Tracking System (ETS) in order to determine whether the 
SO2 emission rates and heat input values were being properly 
reported. The results of the audit showed that a number of sources were 
not reporting heat input correctly. The problem in most instances was 
that the unadjusted flow rate was being used in the heat input 
equation, rather than the bias-adjusted value. EPA believes that this 
is attributable to the fact that part 75 does not explicitly state that 
the bias-adjusted flow rate is to be used in heat input

[[Page 28105]]

calculations. The Agency has attempted to clarify this through policy 
guidance (see Docket A-97-35, Item II-I-9, Policy Manual, Question 
14.81). To correct the situation, the necessary language would be added 
to section 7.6.5 of Appendix A in today's proposed rule.
3. Removing the Restriction on Using the Diluent Cap Only for Start-Up
Background:
    Based on the May 17, 1995 direct final rule, sections 3.3.4, 4.1, 
4.4.1, 5.1, 5.2.1, 5.2.2, 5.2.3, and 5.2.4 of Appendix F currently 
provide for the substitution of a constant CO2 or 
O2 value for a measured value from a CO2 or 
O2 monitor during unit start-up. This provision was 
originally created in response to concerns from some utilities that 
their NOX emission rate in lb/mmBtu was being overestimated 
during unit start-up (see Docket A-90-51, Item IV-D-220, Letter from 
English, Mark G., Deputy General Counsel, Kansas City Power & Light 
Company on EPA's Proposed Part 75 regulations; see also Docket A-94-16, 
Item II-F-2). During unit start-up or other periods when the unit is at 
a low load level, CO2 concentrations are lower than during 
normal operation and O2 concentrations are higher than 
during normal operation. The NOX emission rate equation, 
however, is not designed to be used in these situations because it 
assumes complete combustion and normal operating conditions. As a 
result, the NOX emission rate equation overestimates the 
NOX emission rate when the CO2 concentration is 
very low or the O2 concentration is very high, such as 
during start-up. The equations for calculating emission rates in lb/
mmBtu use measured CO2 concentration or the difference 
between ambient air's O2 concentration and the measured 
O2 concentration in the denominator. For example, 
NOX emission rate is calculated using a NOX 
pollutant concentration monitor and a CO2 diluent monitor 
using the following equation:
[GRAPHIC] [TIFF OMITTED] TP21MY98.001

When a small CO2 concentration is entered into this 
equation, the calculated NOX emission rate will be very high 
and will overestimate the actual emissions.
    The idea of capping CO2 or O2 concentration 
was implemented in part 75 for determination of NOX emission 
rate, CO2 mass emissions, and heat input during unit start-
up. The cap concentration was set at a minimum CO2 
concentration of 5.0 percent CO2 and a maximum O2 
concentration of 14.0 percent O2, based upon some 
information provided by utilities for boilers (see Docket A-94-16, Item 
II-D-34).
    Some utilities asked EPA to consider extending this cap on diluent 
gas concentrations to other situations when a unit is operating at a 
low level (see, e.g., Docket A-97-35, Items II-D-20 and 30, and Docket 
A-97-35, Items II-E-13 and II-E-14). In addition to unit start-up, this 
might include periods of unit shutdown or unit ``banking,'' where a 
unit is combusting a very small amount of fuel to keep the boiler warm, 
but little or no electricity is generated. During these other 
situations where a unit operates at a low level, the CO2 
concentration will be very low and the O2 concentration will 
be very high, resulting in high calculated NOX emission rate 
values like those during unit start-up. One software vendor 
specifically mentioned that it would be easiest to implement the 
diluent cap if it could be used any time the CO2 
concentration would fall below or the O2 concentration would 
rise above the cap value (see Docket A-97-35, Item II-E-7). This could 
be implemented mathematically in the software, rather than having to 
examine the unit operation or the number of hours since the unit 
started operating in order to trigger use of the diluent cap.
    During the process of implementing the May 17, 1995 direct final 
rule, EPA issued guidance that explained that facilities may use the 
diluent cap values for calculating NOX emission rate during 
unit start-up whenever the CO2 concentration is below 5.0 
percent or the O2 concentration is above 14.0 percent, and 
also may use the actual measured CO2 or O2 
concentration values at all times for calculating CO2 mass 
emissions or heat input (see Docket A-97-35, Item II-I-9, Policy 
Manual, Question 14.39). In Question 14.39, EPA recommended that even 
if the diluent cap is used to calculate NOX emission rate, 
the actual diluent measurement should be used for the purpose of 
calculating CO2 mass emissions or heat input, because the 
purpose of the diluent cap was ``to avoid using an extreme diluent 
concentration in the denominator of the equation to calculate emission 
rate in lb/mmBtu.'' The formulas for calculating hourly CO2 
mass emission rate or hourly heat input rate do not use the 
CO2 or O2 concentrations in the denominator of 
the equation. Thus, use of the diluent cap would tend to overestimate 
both CO2 mass emission rate and hourly heat input.
Discussion of Proposed Changes
    Today's proposed rule would allow facilities to use diluent cap 
values of 14.0 percent O2 or 5.0 percent CO2 for 
boilers and 19.0 percent O2 or 1.0 percent CO2 
for turbines. For the purpose of calculating NOX emission 
rates in lb/mmBtu, the diluent cap would be allowed to be used for any 
hour in which the average measured CO2 concentration is 
below the cap value or the average measured O2 concentration 
is above the cap value. Diluent cap values would still be allowed to be 
used to calculate CO2 mass emissions or heat input, as well 
as NOX (or SO2) emission rate in lb/mmBtu.
Rationale
    EPA acknowledges that there are periods of low unit operation or 
low load in addition to unit start-up where the calculated 
NOX emission rate would be overestimated if it were based 
upon measured diluent concentrations. Therefore, the Agency believes 
that extending use of the diluent cap is appropriate. The Agency 
believes that allowing use of the diluent cap anytime when the actual 
measured value is above the cap (for O2) or below the cap 
(for CO2) is easier to program and to implement than 
limiting the use of the diluent cap based upon unit load, another 
option that EPA considered. The Agency believes that it is unlikely 
that a unit would ever be able to operate at a high load and still have 
an O2 or CO2 concentration beyond the diluent cap 
value. Therefore, it is not necessary to limit the use of the diluent 
cap value based on unit load.
    The Agency is also proposing new diluent cap values for turbines. 
Turbines tend to operate with much higher levels of excess 
O2 than boilers. For example, Method 20 of Appendix A, 40 
CFR part 60, the procedure for testing SO2, NOX 
and diluent gas from stationary gas turbines subject to the NSPS, 
requires testers to correct data to a typical concentration of 15.0 
percent O2. Emissions data reported to EPA confirms that for 
turbines, hourly concentrations of O2 are typically between 
14.0 and 16.0 percent and hourly concentrations of CO2 are 
typically between 3.0 and 4.0 percent. Thus, a turbine's diluent gas 
concentration is likely to consistently exceed the diluent cap value of 
14.0 percent O2 and to be consistently below the cap value 
of 5.0 percent CO2 promulgated in the May 17, 1995 direct 
final rule. If these values were allowed to be used by turbines at all 
times rather than just during unit start-up, a turbine

[[Page 28106]]

could conceivably report its NOX emission rate using only 
the diluent cap value and never report the actual monitored diluent 
concentrations, thereby consistently underestimating the NOX 
emission rate. Therefore, today's proposal provides diluent cap values 
of 19.0 percent O2 or 1.0 percent CO2 that are 
clearly beyond the typical O2 or CO2 
concentrations measured at turbines, while still providing some relief 
at extreme diluent concentrations. It is EPA's observation that 
turbines with NOX CEMS have not reported emissions using the 
diluent cap thus far. Thus, no turbines should need to reprogram 
software in order to report the use of the new diluent cap value for 
turbines with a new method of determination code.
    EPA considered removing the option for facilities to use the 
diluent cap for heat input rate and CO2 concentration, as 
well as for NOX (and SO2) emission rate in lb/
mmBtu, but is not proposing to do so in today's proposal. As explained 
previously, the diluent cap was created in order to calculate more 
representative NOX emission rate data during certain unusual 
circumstances. However, when a diluent cap value is used to calculate 
the hourly CO2 mass emission rate or the heat input rate, 
the final calculation would often be less representative of actual 
emissions or heat input during those hours. The Agency also found that 
allowing some facilities to use the diluent cap only for NOX 
emission rate and others to use the diluent cap also for hourly 
CO2 mass emission rate and heat input rate makes it 
difficult to check emissions and heat input rate data to verify that 
calculations are performed correctly. This is because a data 
acquisition and handling system could use either the actual reported 
diluent gas concentration or the diluent cap value to calculate 
NOX emission rate, CO2 mass emission rate, or 
heat input rate, but there is currently no provision in the electronic 
data reporting format for a facility to indicate which value was used 
to calculate the heat input. However, some utilities have indicated 
that making a change to discontinue using the diluent cap for 
calculations of heat input rate and CO2 mass emission rate 
would require a significant change in their software calculations (see 
Docket A-97-35, Item II-E-25). Therefore, today's proposed rule would 
allow facilities the options of (1) not using the diluent cap at all, 
(2) using the diluent cap only for calculating NOX (or 
SO2) emission rate in lb/mmBtu, or (3) using the diluent cap 
for calculating NOX (or SO2) emission rate in lb/
mmBtu, heat input rate, and CO2 emissions. In addition, EPA 
is proposing to add a minor additional reporting requirement to 
indicate whether the diluent cap is used in calculating CO2 
and heat input in the electronic data reporting format. This would 
allow EPA to verify facilities' calculations, while requiring less 
reprogramming than changing the calculations for heat input and 
CO2 emissions.
    The Agency solicits comment on the proposed revisions relating to 
the diluent cap.
4. Complex Stacks--General Issues
Background
    Many power plants regulated under part 75 have relatively simple 
stack and monitoring configurations. Many utilities have one stack for 
each affected unit and have CEMS installed on the stack. Other plants 
have more than one unit discharging to the atmosphere through a common 
stack, with CEMS installed on the common stack. Still others have 
individual units that exhaust into multiple stacks and have CEMS 
installed on each stack. The monitoring requirements for these various 
configurations are addressed in Secs. 75.13, 75.16, 75.17, and 75.18. 
EPA has issued guidance to assist utilities in preparing quarterly 
reports for these unit and stack configurations (see Docket A-97-35, 
Items II-I-4 and II-I-9, Policy Manual, Section 17).
    For the configurations described above, the process of accounting 
for emissions and heat input from the units and stacks will follow 
simple mathematical rules. For example, for single unit-single stack 
configurations, the emissions and heat input for the unit are directly 
determined from the stack CEMS (or from an excepted methodology, where 
applicable). For units discharging through a common stack with CEMS on 
the common stack, the combined emissions and heat input are determined 
from the CEMS, and the heat input to each individual unit is determined 
by apportionment of the combined heat input, using a ratio of the unit 
load to the combined load of all units utilizing the common stack. For 
a single unit exhausting through multiple stacks, the sum of the 
SO2 and CO2 mass emissions and heat input for the 
different stacks equals the total SO2 and CO2 
mass emissions and heat input for the unit.
    However, in implementing part 75, EPA has become aware of a number 
of affected units that have stack exhaust configurations which are more 
complex than the configurations described above. For example, one 
utility has a configuration in which two units can emit through two 
different stacks at the same time, combining their emissions in both 
stacks (see Docket A-97-35, Items, II-C-1, II-D-12). In this case, the 
stack configuration is both a common stack and a multiple stack 
configuration. EPA has had significant problems in determining the 
emissions and heat input from these units, and in one case, EPA 
rejected the quarterly reports for the units (see Docket A-97-35, Item 
II-C-8). The utility worked closely with EPA to resolve the reporting 
issues resulting from this unusual situation (see Docket A-97-35, Item 
II-D-21). Other utilities with similar situations have contacted the 
Agency to ensure there would not be problems with their reporting (see, 
e.g. Docket A-97-35, Item II-D-5).
    There have been other cases in which a unit that is accountable for 
holding SO2 allowances shares a common stack with a unit 
that does not hold SO2 allowances (e.g., where an affected 
unit and a non-affected unit share a common stack or, prior to 1/1/
2000, where a Phase I unit and a Phase II unit share a common stack). 
These are termed ``subtractive stack'' situations in the following 
discussion. Utilities with subtractive stack situations have generally 
used the provisions of Sec. 75.16(a)(2)(ii)(C) or 
Sec. 75.16(b)(2)(ii)(B). These provisions allow a facility to monitor 
separately the common stack and the unit with no allowance requirement 
and to subtract the emissions from the non-affected or Phase II unit 
from the common stack emissions. In some cases, it has not been clear 
in the electronic quarterly reports whether a utility is reporting 
combined emissions from all of the units using the common stack or 
whether the emissions from the non-affected unit(s) have already been 
subtracted out of the reported emissions (see Docket A-97-35, Item II-
C-18). This confusion in interpreting the quarterly emissions reports 
has made compliance determination difficult.
    The Agency found that there is a potential problem with the 
underestimation of emissions using this subtractive approach. In some 
cases, the error in the monitors' measurements might be such that a 
larger emissions value is subtracted from a smaller value, resulting in 
the reporting of false negative emissions (see Docket A-97-35, Item A-
94-16-IV-D-18, Comments from Monitor Labs). In other cases, there may 
be an incentive for making inaccurate measurements with the monitoring 
systems installed on a unit with no allowance requirement. For

[[Page 28107]]

example, if the SO2 pollutant concentration monitor on a 
unit with no allowance requirement did not operate properly and had a 
significant amount of missing data, the facility would calculate 
SO2 emissions from the unit using a conservative, high 
concentration value. Therefore, emissions reported for the units with 
allowance requirements would, as a result of the subtraction, be less 
than the actual emissions. Thus, a facility might have a disincentive 
for good monitor performance and accuracy, because it could lower the 
emissions reported for the units with allowance requirements. Though 
allowed under the current wording of Appendix A to part 75 and subpart 
D of part 75, this is contrary to the intent of the missing data 
substitution procedures, which is to encourage good monitor performance 
while preventing any systematic underestimation of emissions. (See 
Docket A-97-35, Items II-B-13, II-E-4, and II-I-12.)
Discussion of Proposed Changes
    Today's proposed rulemaking would add a general regulatory 
requirement to Secs. 75.16 and 75.17 for facilities with complex stack 
configurations (i.e., subtractive stack situations or configurations 
involving combinations of common stacks and multiple stacks) to receive 
approval from EPA's Administrator for a method of calculating and 
reporting emissions from the units and stacks in the configuration. The 
facility would be required to reach agreement with the Agency on issues 
such as: identification of the stack in its quarterly report, 
representation of the configuration in its monitoring plan, groups of 
units for which cumulative emissions must be reported, testing 
procedures, use of the bias test, and use of the missing data 
substitution procedures. This would apply both to sources that already 
have certified monitoring equipment and are submitting quarterly 
reports and to units that do not yet have certified monitoring systems 
(e.g. new units).
Rationale
    The Agency evaluated two basic approaches to resolving issues in 
these complex stack monitoring configurations. First, EPA considered 
resolving the issues through policy guidance and through instructions 
for submitting quarterly reports. Second, the Agency considered putting 
detailed instructions in part 75 for reporting from and testing of 
monitoring systems installed in these complex stack configurations. 
These rule provisions would have explicitly addressed missing data 
substitution to ensure that when emissions are reported, they are not 
underestimated from units with an allowance requirement or a 
NOX emission limitation. For example, EPA could have 
required, for the subtracted unit(s), that the facility only use those 
provisions of the standard missing data procedures that are not 
intended to be conservative estimates, such as the average 
SO2 concentration during the hour before and the hour after 
a missing data period. Another approach for missing data substitution 
could have been to count zero emissions for the unit with no allowance 
requirement during any missing data periods. Or perhaps creation of a 
site-specific missing data procedure could have been required (see 
Docket A-97-35, Items II-E-4 and II-I-12). To prevent a potential 
underestimation of emissions and a disincentive for more accurate 
monitoring due to application of a bias adjustment on a monitor on a 
unit with no allowance requirement where its emissions are subtracted 
from a common stack, EPA could have required that the bias calculation 
be based upon both the monitors on the common stack and the monitors on 
units with no allowance requirement, resulting in a single bias 
adjustment factor for the subtractive stack situation.
    However, EPA's experience thus far in implementing the program 
indicates that each complex monitoring configuration tends to be 
unique. Thus, the Agency has rejected the two approaches discussed 
above and has decided instead to make General regulatory revisions that 
allow for case-by-case resolution of issues in individual plant 
situations, rather than making extensive, detailed revisions to part 75 
to address each unique situation.
    The Agency prefers to make regulatory revisions rather than 
addressing issues solely through policy and guidance. In some cases, 
the Agency has given advice to utilities on how to report emissions, 
and the utility involved has not followed the Agency guidance (see 
Docket A-97-35, Items II-C-7, II-C-24, and II-D-8). In another case, 
the current provisions of part 75 for missing data substitution and for 
the bias test appeared to be in conflict with guidance that the Agency 
wanted to issue in order to ensure that emissions are not 
underestimated in a subtractive stack situation (see Docket A-97-35, 
Item II-B-13). Therefore, today's proposed rule would require owners or 
operators of facilities with complex stack configurations to apply for 
approval of their monitoring plans and reporting methodologies from 
EPA's Administrator on a case-by-case basis. The Agency believes that 
the General regulatory provisions requiring approval of a complex 
monitoring situation by EPA's Administrator will give both facilities 
and the Agency flexibility to deal with site-specific cases, while also 
giving the Agency regulatory authority to resolve any case-specific 
problems.
    It is possible that any final rule resulting from today's proposal 
may not be promulgated until 1999. Thus, EPA is proposing to require 
the Administrator's approval of the monitoring plans and reporting 
methodologies only for those situations that will exist on and after 
January 1, 2000. Any subtractive stack situations that exist only 
during the duration of Phase I would not fall under this requirement. 
However, complex stack situations that exist where affected and non-
affected units share a common stack would need to meet today's proposed 
requirement. Similarly, in situations where coal-fired units sharing a 
common stack have different NOX emission limitations under 
part 76, or situations where some units sharing a common stack have a 
NOX emission limitation under part 76 and others have no 
NOX emission limitations under part 76, any complex 
monitoring configuration would need to be approved by EPA's 
Administrator.
5. Complex Stacks--Heat Input at Common Stacks
Background
    For a unit that utilizes a flow monitor to determine SO2 
mass emissions, section 5 of Appendix F to part 75 requires heat input 
to be calculated using the installed flow monitor and a diluent gas 
(O2 or CO2) monitor. The January 11, 1993 final 
rule indicated that units with common stacks, multiple stacks, or 
bypass stacks should follow the same General procedures for monitoring 
heat input as are used for monitoring SO2 under Sec. 75.16. 
As written, those procedures allowed facilities to monitor their heat 
input either by placing individual monitors on each unit that serves a 
common stack or by placing monitors only on the common stack and 
measuring a combined heat input from all of the units sharing the 
common stack. The May 17, 1995 rule required the combined heat input 
measured by monitors on the common stack to be apportioned to the 
individual units, in two specific provisions. First, unit level heat 
input was required under Sec. 75.16(e)(2) for cases in which a 
knowledge of the heat input for each unit is critical to compliance 
determination (i.e., for situations where any units using the common 
stack have

[[Page 28108]]

a NOX emission limit). Second, Sec. 75.16(e)(3) required 
unit level heat input to be determined for all other common stacks, but 
only until the year 2000. The November 20, 1996 rule outlined the 
acceptable methodology for apportioning heat input, i.e., by using the 
ratio of the unit load in MWe or lb of steam per hour to the combined 
load of all units utilizing the common stack (provided that all of the 
units utilizing the common stack are combusting fuel with the same F-
factor).
Discussion of Proposed Changes
    Today's proposed rule would revise the existing requirements found 
in Sec. 75.54(b) and two specific provisions of Sec. 75.16(e) for 
accounting of heat input for units serving a common stack, a by-pass 
stack, or multiple stacks. First, EPA would require determination and 
reporting of the unit level heat input to be continued after the year 
2000 for all affected units, rather than restricting it to certain 
situations after 2000. Second, EPA would clarify that the proper units 
of measure for load to be used in an apportionment of common stack heat 
input to determine unit level heat input are totals of MWe-hr and 1000 
lb of steam, rather than rates of MWe and 1000 lb/hr of steam.
Rationale
    EPA considered leaving the current provisions of Sec. 75.16(e) and 
Sec. 75.54(b) from the May 17, 1995 and November 20, 1996 rules 
unchanged. However, this would have the serious drawback of requiring 
the facilities to reprogram their computer software for certain units 
and not for others. Corresponding monitoring plan changes would also be 
required. Additionally, EPA would have to reprogram its emission 
tracking software to accommodate two different heat input reporting 
methodologies for common stacks. In view of these considerations, EPA 
is proposing to continue to receive individual heat input data from all 
affected units. This information is useful for developing inventories 
of total NOX mass emissions in tons in support of other 
Agency rulemakings. Without such information, the inventories would be 
based on assumptions about how units operate, rather than being based 
on unit level heat input as reported from the facility.
    The Agency believes that a relatively small number of sources would 
be affected by this proposed change. This is because (1) most coal-
fired units would still need to report unit level heat input under the 
current provisions of Sec. 75.16(e)(2), even after the year 2000; and 
(2) gas-fired and oil-fired units using fuel flowmeters to determine 
heat input and to implement the procedures of Appendix D or Appendix E 
would still be required to monitor heat input for each unit under 
section 2.1 of Appendix D. Because of the usefulness of having heat 
input data for individual units, because of the burden of reprogramming 
software to remove the heat input apportionment by the year 2000, and 
because of the small number of sources that would benefit from 
retaining the current provisions of Sec. 75.16(e)(3), EPA believes it 
is reasonable to require all units that measure combined heat input at 
a common stack to continue to apportion heat input to the individual 
units. The Agency solicits comment on the number of sources that would 
be affected by this revision.
6. Start-Up Reporting--Units Shutdown Over the Compliance Deadline
Background
    As currently written, part 75 requires that units which are 
shutdown over an applicable compliance date specified in Sec. 75.4 must 
submit a notice of the planned and (if different) actual shutdown date. 
In addition, Sec. 75.4(d) provides an extended certification deadline 
for such units of ``the earlier of 45 unit operating days or 180 
calendar days after the date that the unit recommences commercial 
operation of the affected unit.'' If an owner or operator subsequently 
recommences commercial operation of the unit, a notice related to the 
planned and (if different) actual date of recommencement of commercial 
operation is required. In addition to these notices, Sec. 75.64 
requires that after the applicable compliance date passes, the owner or 
operator must submit quarterly reports for such units. If the unit 
remains shut down and does not operate during the quarter, the 
quarterly report must show zero emissions. Utility commenters (see, 
e.g., Docket A-97-35, Items II-D-20, II-D-30) have recommended that 
this quarterly report requirement for shutdown units be deleted because 
it is unnecessary and burdensome.
Discussion of Proposed Changes
    Section 75.64(a) would be modified so that quarterly reporting is 
not required until the first quarter in which a previously shutdown 
unit recommences commercial operation. In this case, the first 
quarterly report would contain data beginning with the hour in which 
the unit recommences commercial operation.
Rationale
    Units that are shutdown over their applicable certification 
deadlines are required to submit notice, pursuant to Sec. 75.61(a)(3), 
of the planned date of recommencement of commercial operation and also 
must submit a follow-up notice if the actual date of recommencement of 
commercial operation is different from the planned date. As a result of 
these notice provisions, EPA will know whenever the status of a 
shutdown unit changes. Because shutdown units have no emissions, the 
Agency believes that quarterly reporting in addition to the notice 
provisions is unnecessary to fulfill the emission reporting objectives 
of the Act.
    The Agency notes, however, that the proposed revision differs from 
that suggested by certain utilities (see Docket A-97-35, Item II-D-30). 
The utilities proposed tying the reporting requirement to the 
certification deadline in Sec. 75.4(d). However, under Sec. 75.4(d), 
facilities are required to report emissions data using special 
provisions in that section prior to the extended certification deadline 
in Sec. 75.4(d). Thus, the proposed revisions would tie the obligation 
for quarterly reporting to the quarter in which commercial operation is 
recommenced.
7. Start-Up Reporting--New Units
Background
    As currently written, Sec. 75.64(a) requires the first quarterly 
report for new units to be submitted for the quarter corresponding to 
the compliance date in Sec. 75.4. However, the current provision is 
unclear about which hourly emissions data need to be included in the 
first quarterly report if the compliance deadline does not correspond 
to the first hour in the quarter.
Discussion of Proposed Changes
    Section 75.64(a) would be modified to clarify that a new unit must 
start reporting data beginning with the earlier of the date and time of 
provisional certification or the compliance deadline in Sec. 75.4(b).
Rationale
    These proposed revisions are generally consistent with existing 
implementation of the new unit reporting requirements, and primarily 
would serve to clarify ambiguous elements of the current rule.

[[Page 28109]]

8. Recordkeeping and Reporting Provisions
Background
    Subpart F and subpart G of the existing part 75 regulation set 
forth the recordkeeping and reporting requirements that accompany the 
monitoring provisions of part 75. Specifically, in subpart F, 
Sec. 75.53 contains the monitoring plan requirements, Sec. 75.54 
contains the general recordkeeping provisions, Sec. 75.55 lists the 
general recordkeeping provisions for specific situations, and 
Sec. 75.56 consists of the certification, quality assurance and quality 
control record provisions. In subpart G, Sec. 75.62 lists the 
monitoring plan reporting provisions, Sec. 75.62 contains the reporting 
requirements for initial certification and recertification 
applications, and Sec. 75.64 discusses the provisions for quarterly 
reports. Quarterly reports are electronic data files containing 
emissions and operating data from affected units, as well as monitoring 
plan information and the results of certification and quality assurance 
tests. Under Sec. 75.64, these electronic data reports are required to 
be submitted to the Agency each calendar quarter. This electronic 
information is used by the Agency for many different purposes, 
including implementation of the SO2 allowance trading 
program, determination of compliance with emission limits, development 
of reports on utility emissions, and modeling of air quality to assess 
the effectiveness of the Act.
    In order to effectively use the electronic quarterly report 
information, EPA created a standardized reporting format, the 
electronic data reporting (EDR) format. The electronic file formats and 
record structures of the EDR provide the vehicle by which required 
information is submitted to the Agency every calendar quarter. The EDR 
primarily defines the order, length, and placement of information 
within the electronic report or file. The individual tables of the EDR 
define the record type, type code, start column, data element 
description, units, range, length, and FORTRAN format for each data 
element in the electronic report. The information in the EDR fields 
mirrors the required information set forth in subparts F and G of part 
75. Considering both the volume of information contained in each 
quarterly report (e.g, operating and emissions data for each of the 
hours in the quarter) and the number of reports submitted to the Agency 
(i.e., currently, 1765 reports are received each quarter for the 2055 
affected units; some reports contain information for more than one unit 
if several units are interrelated, as in a common stack configuration), 
a standard format is critical in order for the Agency to review, 
verify, and use the information reported. A standard format allows the 
Agency to develop software to receive and verify the files and to 
correlate and separate out specific information for compliance 
determinations. A standard format also allows software vendors to 
create standard software which can be utilized by many affected units. 
This is more cost effective than developing site-specific software and 
thus reduces the software cost to industry.
    Today's rulemaking proposes a number of revisions to subparts F and 
G of part 75 (the reporting and recordkeeping sections of the rule). 
The majority of these changes are necessary to implement the proposed 
substantive revisions to the sections of the rule and appendices 
discussed elsewhere in this notice. In addition, EPA is 
proposingrevisions to these subparts in order to streamline 
implementation of the program and to coordinate reporting under the 
Acid Rain Program with other programs.
    To support the changes to the recordkeeping provisions, new 
Secs. 75.57, 75.58, and 75.59 would be added. These sections would 
replace existing Secs. 75.54, 75.55, and 75.56. The addition of new 
sections is necessary because the proposed revisions would not be 
mandatory until January 1, 2000, and to have the proposed revisions 
listed throughout existing effective sections could lead to confusion. 
However, an owner or operator would be free to follow the provisions of 
Secs. 75.57, 75.58, and 75.59 before January 1, 2000, if he chooses to 
do so. In addition, the owner or operator would be required to satisfy, 
prior to January 1, 2000, the elements in these sections that support a 
regulatory option proposed in other sections of part 75 if the owner or 
operator elects to implement that option prior to January 1, 2000.
    Because, as discussed above, the Acid Rain Program relies on a 
standardized electronic data reporting format, EPA has also developed 
draft revisions to the EDR formats and instructions (draft EDR version 
2.1). The following discussion refers to both the rule sections and EDR 
record types (RTs) that would be affected by the proposed revisions.
Discussion of Proposed Changes
    There are a number of proposed rule changes to the recordkeeping 
and reporting requirements of part 75 and corresponding draft EDR 
revisions that would be necessary to implement the substantive 
revisions proposed by EPA and discussed elsewhere in this preamble. 
These include the following requirements:
    (1) Changes to support new CO2 missing data requirements 
(see Sec. 75.57 and RT 202, 210, and 211);
    (2) Changes to support new reporting, QA and missing data 
requirements for moisture monitoring (see Secs. 75.53, 75.57, and 
75.59, and RT 211, 212, 220, and 618);
    (3) Changes to support optional Appendix I (flow methodology for 
gas and oil units) (see Secs. 75.57 and 75.58, and RT 220, 302, 303, 
608, and 609);
    (4) Changes to support more flexibility for units that have 
multiple range analyzers (see Secs. 75.53 and 75.59, and RT 230, 530, 
600, 601, and 602);
    (5) Changes to support the use of the diluent cap during all hours 
(see Sec. 75.57 and RT 300 and 330);
    (6) Changes to support test exemptions and extensions for units 
that operate infrequently (see Secs. 75.59 and 75.64, and RT 301, 697, 
and 698);
    (7) Changes to support increased flexibility in fuel sampling (see 
Sec. 75.58 and RT 302, 303, 313, and 314);
    (8) Changes to allow reporting of hourly total values in addition 
to hourly rates (see Sec. 75.57 and RT 300, 310, and 330);
    (9) Changes to support the proposed re-definition of unit operating 
loads (see Secs. 75.53 and 75.59, and RT 535 and 611);
    (10) Changes to support reporting of conditional data during 
recertification events (see Sec. 75.59, and RT 556);
    (11) Changes to support a new quarterly flow-to-load QA check for 
flow monitors (see Sec. 75.59, and RT 605 and 606);
    (12) Changes to allow QA test grace periods (see Sec. 75.59, and RT 
699);
    (13) Changes to support simplified reporting for low mass emissions 
units (see Secs. 75.53, 75.58, and 75.63, and RT 360, 508, and 531);
    (14) Changes to support fuel flow-to-load QA checks for fuel flow 
meters (see Sec. 75.59, and RT 628 and 629); and
    (15) Changes to support expanded reporting of RATA supporting 
information (see Sec. 75.59, and RT 614, 615, 616, 617, and 618).
    In addition, since the EDR version 1.3 was released, EPA has 
developed additional record types to aid in the implementation of the 
program, by allowing the designated representative to certify the 
validity of quarterly reports using an electronic certification 
statement. The proposed revisions would adopt the necessary rule 
language to implement these miscellaneous record types (see Sec. 75.64, 
and RT 900, 901, 910, and 920).

[[Page 28110]]

    The proposed revisions would also set forth optional requirements 
for reporting of NOX mass emissions that states or EPA could 
adopt as part of a NOX mass trading program, such as the OTC 
NOX Budget Program. In this situation both a rule change and 
an EDR change would be needed (see Secs. 75.57 and 75.64 and RT 301, 
307, and 328).
    The proposed rule revisions also include a number of changes that 
EPA believes will facilitate implementation of the program. These 
include:
    (1) Reporting of test numbers, reasons for tests and indicators of 
aborted tests (see Sec. 75.59, and RT 560, 600, 601, 602, 603, 610, and 
611);
    (2) Changing the deadlines for reporting the RATA supporting 
information that was originally required on January 1, 1998 (see 
Sec. 75.59, and RT 614, 615, 616, 617, and 618);
    (3) Reporting of an optional record type that will allow facilities 
to provide contact person information that many facilities currently 
provide in quarterly report cover letters (see Sec. 75.59, and RT 999);
    (4) Based on comments received, the rule would be revised so that 
reporting the reasons for missing data as part of the quarterly report 
would become optional, but would still need to be maintained on-site 
(see Secs. 75.56 and 75.59, and RT 550);
    (5) Reporting of facility location, identification, and EDR version 
numbers to support the transition from EDR 1.3 to EDR 2.1 (see 
Sec. 75.64, and RT 100 and 102);
    (6) Reporting of information documenting the calculation of heat 
input (see Sec. 75.57, and RT 300);
    (7) Reporting of reference method backup QA data (see 
Sec. 75.59(a)(11), and RTs 260, 261, and 262);
    (8) Expanded reporting of unit definition information (see 
Secs. 75.53, and RTs 504, 585, 586, and 587);
    (9) Reporting of Appendix E segment ID information (see Sec. 75.58, 
and RT 323, 324, and 560);
    (10) Reporting of qualification data for peaking units or gas-fired 
units (see Sec. 75.53, and RT 507);
    (11) Reporting of the qualifying test for off-line calibrations 
(see Sec. 75.59, and RT 623);
    (12) Reporting of Appendix E emission rate test data (see 
Secs. 75.59, and RT 650-653);
    (13) Reporting of span effective date information and flow rate 
span values (see Sec. 75.53, and RT 530); and
    (14) Removal of the recordkeeping provisions of Secs. 75.50, 75.51, 
and 75.52 that are no longer effective.
Rationale
    The majority of the proposed changes to subparts F and G are needed 
to support proposed substantive changes elsewhere in part 75. EPA is 
also proposing certain minor revisions to the order and wording of 
provisions in these subparts so that the records required by the rule 
match up consistently with the record type descriptions in the EDR. 
Certain utility groups previously had objected that EPA had not made 
the EDR format available for formal public notice and comment. The 
Agency maintains that it is not required to provide notice and comment 
for the EDR. The data included in (or proposed to be included in) the 
EDR are also listed in the rule (or the proposed rule revisions) as 
requirements under the recordkeeping and/or reporting provisions of 
Secs. 75.53 through 75.64, which have already undergone (or are 
undergoing) public notice and comment. Since the EDR simply shows how 
to present electronically the data whose submission is (or will be) 
required by the rule, it is the rule, not the EDR, that imposes the 
data requirements. Notice and comment on the contents of the EDR would 
therefore be unnecessary and duplicative. Moreover, the requirement to 
present the rule's data requirements in a specified format is 
authorized by Sec. 75.64(d), which requires a quarterly report to be 
submitted in the format specified by the Administrator. Like the data 
requirements, this format requirement in part 75 was adopted after 
public notice and comment.
    In today's rulemaking, EPA has developed draft EDR revisions 
simultaneously with the proposed rule revisions and is therefore 
including the draft EDR revisions in the docket for comment at the same 
time as the proposed rule revisions (see Docket A-97-35, Item II-A-12). 
EPA is also posting the draft EDR v2.1 revisions and draft EDR v2.1 
reporting instructions on the Acid Rain Homepage (www.epa.gov/
acidrain). However, the Agency maintains that notice and comment are 
not necessary for revisions to the EDR so long as the data included in 
the EDR is the same as the data required by rule provisions that have 
undergone or are undergoing notice and comment. Thus, future EDR 
revisions may be made without prior notice and comment on the EDR in 
order to implement rule revisions for which notice and opportunity for 
comment are provided. However, the Agency will continue its informal 
procedures for involving the affected stakeholders in any such EDR 
revisions.
    There are a number of other proposed changes to Secs. 75.54-75.64 
that have been included to implement existing provisions in other 
sections of part 75. First, information on test numbers and reasons for 
tests would be required so that quality-assurance test data can be more 
easily correlated and interpreted. Second, the reporting of various 
run-specific and point-specific RATA support information would be 
required (e.g., point velocity head readings, gas reference method 
quality-assurance data, moisture reference method data, etc.). The 
Agency believes that most testing companies currently either collect 
these data electronically or enter the data into computer programs 
manually to determine RATA results. By requiring the reporting of these 
data elements in a standard electronic format, the Agency believes that 
both facilities and regulatory personnel would be able to more easily 
interpret data that are currently provided by test contractors in many 
different hardcopy formats.
    The Agency is proposing not to require the electronic reporting of 
RATA support information prior to the year 2000. Sections 75.56 
(a)(5)(iii)(F) and (a)(7) and Sec. 75.64(a)(1) of part 75 currently 
require RATA supporting information to be reported in the electronic 
quarterly report. EPA believes, however, that it would be more cost 
effective to require the more detailed RATA support records to be 
electronically reported beginning in the year 2000, rather than having 
a two-stage implementation. The Agency has notified all designated 
representatives that this RATA supporting information will not be 
required to be reported electronically, in RT612 and 613 of the 
quarterly report, prior to January 1, 2000.
    The Agency notes that certain data elements (e.g., yaw angle, pitch 
angle, axial velocity, wall effect point identifier, etc.) have been 
included in anticipation of future revisions to EPA Reference Method 2. 
EPA is presently evaluating a number of alternative flow rate 
measurement methodologies, such as the use of a 3-dimensional probe. 
Depending on the outcome of the Agency's evaluation, one or more of 
these alternative flow measurement techniques may be allowed beginning 
in the year 2000. Therefore, EPA believes it is appropriate to include 
data elements to support these anticipated Method 2 revisions in draft 
EDR version 2.1.
    Finally, by changing the requirements for reporting the results of 
the most recent RATA from requiring it to be reported in the quarter in 
which it was

[[Page 28111]]

performed, to requiring it to be reported in the quarter in which it 
was performed and each subsequent quarter in which a BAF that was 
calculated using the results of that RATA are used, EPA would make the 
individual quarterly reports more self contained and make it easier for 
people who are using the reported data to understand how the BAFs 
reported in those reports were applied. EPA considered adding a field 
to the hourly emissions data record for each pollutant to indicate the 
BAF applied in that hour. However, the Agency received requests from 
utilities on an early draft of the EDR revisions that the hourly 
emissions data record types not be revised to add a field for BAF. The 
Agency believes that reporting the results of the most recent RATA, 
including the BAF, in each quarterly report would accommodate the 
utilities' requests not to add the BAF to each hourly record type and 
would achieve the objective of making the quarterly reports easier to 
interpret because the BAF being applied will be found in each quarterly 
report. In addition, since electronic RATA results involve a relatively 
small amount of information that can be copied into subsequent reports 
and does not have to be recreated, it should not be a significant 
burden to reporting facilities.
    The proposed revisions would also remove the requirement to report 
the reasons for missing data and make it optional. However, even if the 
information is not reported, the reasons for missing data would have to 
be maintained on site in a manner suitable for inspection. Based on the 
high data availability achieved during initial implementation of the 
program, the Agency believes that this type of information is not 
needed in the review of most quarterly reports. For those situations in 
which the Agency may wish to review this information, the records would 
still be on-site for audit purposes or for submittal to the Agency.
    The EPA is also proposing to incorporate additions which would 
allow the reporting of electronic signatures and certification 
statements so that no hardcopy reporting of any kind (e.g., cover 
letters) would be necessary to meet the quarterly report requirements.
    Finally, the removal of recordkeeping Secs. 75.50, 75.51, and 75.52 
(and the corresponding explanatory text included in Appendix J to the 
existing rule) is necessary because those sections were scheduled for 
replacement during the May 17, 1995 rule revisions. At that time, 
Secs. 75.54, 75.55, and 75.56 were added as replacements for 
Secs. 75.50, 75.51, and 75.52, effective January 1, 1996. Because the 
effective date is now past, the old sections and Appendix J will be 
removed and reserved in order to prevent any confusion.
9. Electronic Transfer of Quarterly Reports
Background
    Sections 75.64(a) and (d) of the original January 11, 1993 Acid 
Rain rule requires emissions, monitoring, and quality assurance data to 
be electronically reported to the Administrator on a quarterly basis in 
a format to be specified by the Administrator. Version 1.3 of the 
Electronic Data Reporting (EDR) format (see Docket A-97-35, Item II-I-
5) further specifies the record structures to be used to report the 
required data elements. Page 3-3 of the May 1995 Acid Rain Program CEMS 
Submission Instructions (see Docket A-97-35, Item II-I-4) further 
specifies the mode of transmission of the electronic data file to the 
Agency. Three modes of transfer are listed as options: (a) by mail on 
diskette, (b) by mail on magnetic tape, or (c) through direct 
electronic transfer.
    Since the beginning of the program, the Agency has received 
quarterly reports by mail on diskette and through direct electronic 
transfer. To date, the magnetic tape option has never been utilized. 
Based on the first four years of implementation of part 75, the Agency 
believes that the use of the direct electronic transfer mode of 
transmission has many advantages to the Agency and to the affected 
sources. In fact, more than seventy percent of the reports for sources 
currently affected by part 75 were submitted directly to the EPA 
mainframe with EPA-provided software in second quarter 1997, and the 
number of sources using this option has steadily increased over time 
(see Docket A-97-35, Item II-I-8).
Discussion of Proposed Changes
    Today's proposal would require quarterly reports to be submitted 
via direct electronic transfer unless otherwise approved by the 
Administrator. This would remove the option of sending files through 
the mail on interceding media except for hardship cases where a modem 
is not available or where technical difficulties prevent the successful 
transmission of files via modem.
    An additional revision to section 4 of Appendix A to part 75 would 
require data acquisition and handling systems (DAHS) to be capable of 
transmitting a record of measurements and other required information by 
direct computer-to-computer electronic transfer via modem and EPA-
provided software.
Rationale
    For each quarterly report submitted, the Agency performs an 
assessment which results in a feedback report for the submitting 
designated representative. This feedback report provides information to 
the facility that may be used in making trading decisions, that may 
indicate that a change is needed to the facility software, and/or that 
may indicate that the file needs to be corrected and resubmitted. A 
major advantage of submission through direct electronic transfer with a 
modem and EPA-provided software is that the designated representative 
submitting the file receives the EPA assessment of the submitted data 
much more quickly than for a file that is transmitted through the mail 
on diskette. Currently, for a file that is submitted to the Agency by 
electronic transfer via modem and EPA-provided software, the EPA 
assessment is received by the designated representative, via modem and 
EPA-provided software, immediately (typically within ten minutes) after 
the transmission of the quarterly report file. However, for files 
submitted on diskette that must travel through the mail system and be 
processed by Agency personnel, a letter containing the EPA assessment 
is currently sent to the designated representative through the mail and 
arrives 45 days or later from when the submission was originally 
received by the Agency. Therefore, with direct electronic transfer, 
potential errors get corrected and resolved more quickly and trading 
decisions can be made with assurance that submitted data meets the 
minimum quality standards acceptable to the Agency. Additionally, the 
source may electronically submit the quarterly report, via modem and 
EPA software, prior to the deadline, immediately receive the EPA 
assessment, fix any errors, and resubmit the file by the deadline. Many 
utilities have indicated that this is an important advantage over 
submission of the quarterly report by diskette.
    Another benefit of direct electronic transfer is the reduced risk 
of error in transmission to the Agency or handling at the Agency. 
Throughout the implementation of the program, many files submitted on 
diskette through the mail have been lost, returned to the sender, 
damaged in transit, or contained viruses (see Docket A-97-35, Item II-
I-8). When a file is submitted using direct electronic transfer of a 
quarterly report, the designated representative submitting the file(s) 
receives an immediate

[[Page 28112]]

confirmation that the file was received by the Agency.
    Further, immediate feedback from the agency on quarterly report 
submissions may also contribute to cost savings for facilities if a 
file submitted via direct electronic transfer is rejected and required 
to be amended and resubmitted. Utilities have indicated that submitting 
the report to EPA, receiving feedback, and making the necessary 
corrections to the file in a single work session significantly reduces 
the cost of reworks, particularly for facilities that retain their 
master file at the individual plant locations.
    An additional advantage to direct electronic transfer is the 
reduced cost to the Agency resulting from the minimized EPA labor hours 
required to process a diskette. For instance, a diskette transmitted 
through the mail must be catalogued, scanned for readability and 
viruses, uploaded to the EPA mainframe Emissions Tracking System, and 
renamed. On the other hand, transmission of a file by direct computer-
to-computer electronic transfer using EPA software eliminates all of 
those manual steps because they are performed automatically by the EPA 
software used for transmission of the report.
    A possible concern about a requirement to submit the quarterly 
report via modem is the possibility that source may not be equipped 
with a modem and electronic transfer capability. Although the Agency 
believes that most sources currently have a modem or will have a modem 
by the year 2000, the Agency understands that a very small percentage 
might not. Therefore, the Agency would accept petitions from sources 
unable to transmit files via modem in order to allow transmission via 
diskette for hardship cases.
    Additionally, a utility group representative raised a concern about 
the possibility of a computer at either the facility source or at the 
EPA being inoperative at the time of the deadline for transmission, 
preventing a source from successfully transferring the quarterly report 
to the Agency. In order to minimize the risk of this type of problem, 
there is a wide window, currently thirty days, during which EPA will 
accept quarterly report transmissions each quarter. Additionally, EPA 
has instituted preventative measures to minimize the possibility that 
the EPA computer would be inoperative for an extended length of time, 
preventing quarterly report transmission. Nevertheless, the Agency 
accepts that it is conceivable that a technical difficulty could 
prevent the successful electronic submission of a quarterly report and, 
therefore, would also approve diskette submission on an as-needed basis 
for sources unable to transfer a file via modem and EPA-provided 
software due to technical difficulties. Furthermore, EPA solicits 
comment on whether it should allow a grace period for late submissions 
due to a technical difficulty with the EPA computer.
    Finally, section 4 of Appendix A to part 75 would be amended to 
require the DAHS to be capable of transmitting the required information 
by direct electronic transfer via modem and EPA-provided software, for 
consistency with the proposed Sec. 75.64(f). In addition, section 4 of 
Appendix A to part 75 would retain the requirement for the DAHS to be 
capable of transmitting a record of measurements and other required 
information via an IBM-compatible personal computer diskette so that an 
on-site inspector could collect electronic data on a diskette for 
review.

S. Revised Traceability Protocol for Calibration Gases

Background
    Currently, Appendix H to part 75 requires affected units to follow 
a 1987 version of EPA Protocol procedures for developing calibration 
gases. This protocol document has been superseded by a later version, 
the ``EPA Traceability Protocol for Assay and Certification of Gaseous 
Calibration Standards,'' September 1997, EPA 600/R-97/121. The 1997 
document is actually five protocols. Two of these protocols (formerly 
known as Protocols 1 and 2) have been combined to allow both CEMS and 
ambient air analyzers to be calibrated from gases produced either 
without dilution (Procedure G1) or with dilution (Procedure G2). The 
remaining three protocols (Procedures P1, P2, and P3) describe 
procedures that are mandatory for ambient air quality analyzers (not 
continuous emission monitoring systems).
    The 1997 Protocol document, described above, is required by other 
parts of the CFR, such as the NSPS provisions in part 60. Because the 
old and new protocols specify different certification periods (i.e., 
useful shelf lives) for most calibration gases, some affected units 
that must comply with both part 60 and part 75 have been forced to 
replace calibration gas cylinders more frequently because of the 
shorter certification period in the 1987 Protocol procedures required 
by part 75.
    Under the 1987 Protocol document, affected units with low 
SO2 emission rates occasionally had difficulty finding 
calibration gases that were within the concentration ranges required by 
Appendix A to part 75. The 1997 Protocol document allows calibration 
gases to be developed over a wider range of concentrations than was 
previously allowed.
    Under the current part 75 rule, ``Protocol 1 gases must be vendor-
certified to be within 2.0 percent of the concentration specified on 
the cylinder label (tag value).'' However, no method is specified to 
determine the uncertainty value. The overall uncertainty in the 
concentration estimated for a calibration gas comes from many different 
sources, including uncertainty in the reference standards, uncertainty 
in the analyzer multi-point calibration, uncertainty in the zero/span 
correction factors, and measurement imprecision.
Discussion of Proposed Changes and Rationale
    Today's rule proposes to remove Appendix H and revise parts 72 and 
75 to be consistent with the 1997 Protocol document. The following 
sections of part 75 would be revised: Secs. 72.2 and 72.3; sections 
5.1.1 through 5.1.6, 6.2, and 6.3.1 of Appendix A; and all of Appendix 
H.
    The final rule would incorporate by reference the 1997 Protocol 
document. This is the preferred option for the following reasons: (a) 
calibration gas certification periods would be identical under parts 60 
and 75, thereby allowing affected units to reduce expenditures on 
calibration gas without sacrificing accuracy or performance; (b) lower 
emitting affected units would more easily be able to comply with the 
required range of calibration gas concentrations; (c) improved assaying 
procedures and accuracy determinations would be allowed; and (d) a 
wider selection of calibration gases would be allowed.
    While today's proposal would retain the requirement for EPA 
protocol gases to be within 2.0 percent of the tag value, section 5.1.3 
in Appendix A would be revised to specify the use of the uncertainty 
calculation procedure in section 2.1.8 of the 1997 Protocol document 
for estimating the analytical uncertainty associated with the assay of 
the calibration gas. This uncertainty estimate includes the uncertainty 
of the reference standard and any gas manufacturer's intermediate 
standard (GMIS) and interference correction equation that may be used 
in developing the calibration gas.
    EPA proposes to change the term ``Protocol 1 gas'' to ``EPA 
protocol gas'' because the 1997 Protocol document combines the Protocol 
1 and Protocol 2

[[Page 28113]]

procedures; therefore, the term ``Protocol 1 gas'' would no longer be 
used.
    Today's proposal would also continue to allow a ``research gas 
mixture'' to be used as a calibration gas. However, an RGM would need 
to meet the same 2.0 percent uncertainty requirement that a protocol 
gas would meet.
    The proposed rule would explicitly allow GMISs to be used as 
calibration gas for two reasons. First, an EPA protocol gas may be made 
from a GMIS. Therefore, GMISs are at least as accurate as EPA protocol 
gases. Second, GMISs are more readily available and less expensive than 
standard reference material or National Institute of Standards and 
Technology (NIST) traceable reference material, both of which are 
allowable as calibration gas under part 75.
    Today's proposal clarifies that NIST/EPA-approved certified 
reference materials (CRMs) would be acceptable as calibration gas by 
adding those CRMs to the definition of ``calibration gas'' in 
Sec. 72.2.
    The 1997 Protocol document accepts primary reference standards from 
the Netherlands Measurement Institute as being equivalent to standard 
reference materials from the NIST. As a result, today's proposal adds 
``standard reference material-equivalent compressed gas primary 
reference material'' to the ``calibration gas'' definition in Sec. 72.2 
and to section 5.1.2 of Appendix A.
    Finally, the definition of ``zero air material'' would be revised 
to accommodate other acceptable procedures.
    Major differences between the 1987 Protocol procedures and the 1997 
Protocol procedures are explained on pages 1-1 through 1-3 of the 1993 
Protocol document and on pages 1-1 through 1-2 of the 1997 Protocol 
document (see Docket A-97-35, Items II-I-23 and 24).

T. Appendix I--New Optional Stack Flow Monitoring Methodology

Background
    Section 412 of the Act requires that units subject to title IV 
install SO2 concentration monitors and volumetric flow 
monitors for the purpose of determining SO2 emissions. The 
purpose of the volumetric flow requirement is to enable a unit to 
convert SO2 concentrations into mass emission rates of 
pounds per hour (lbs/hr). Volumetric flow is also used to determine 
heat input rate in mmBtu/hr and CO2 mass emission rate in 
ton/hr.
    In December 1991, 56 FR 63002 (December 3, 1991), EPA proposed an 
exception to the requirement to install SO2 concentration 
monitors and volumetric flow monitors at oil- and gas-fired units in 
Appendix D to part 75. The exception relies on fuel flowmeters and fuel 
sampling and analysis to determine SO2 emissions from oil- 
and gas-fired units. In comments on the December 1991 proposed rule, 
some industry commenters also advocated allowing oil- and gas-fired 
units to use a diluent monitor, an F-factor, and a fuel flowmeter as an 
alternative to a volumetric flow monitor. An F-factor is a fuel-
specific constant that relates the heat content of a fuel and the 
volume of gases given off upon combustion. It is used to convert 
pollutant concentrations into units of pounds of pollutant per million 
British thermal units of heat input (lb/mmBtu). EPA already allows the 
use of F-factors in emissions monitoring under part 75 and under 40 CFR 
part 60, subparts Da and Db. Method 19 of Appendix A to part 60 uses F-
factors as the reference methods for calculating SO2 and 
NOX emissions in terms of lb/mmBtu for subpart Da and Db 
units. F-factors also are used in the performance tests for certain 
pollutants required under Sec. 60.8 to determine if a source is in 
compliance with a particular emission standard in lb/mmBtu. Part 75 
also uses F-factors in conjunction with diluent gas and volumetric flow 
data to determine heat input under section 5 of Appendix F to part 75. 
Table 19-1 of Method 19 in Appendix A to part 60 and Table 1 in section 
3.3.5 of Appendix F to part 75 list the appropriate F-factors for 
different types of fuel, including oil and natural gas.
    Although the commenters supported the two exceptions included in 
Appendix D, some commenters did not believe the exceptions would be 
economical at all oil- and gas-fired units. According to one commenter, 
fuel sampling protocols have an inherently high bias because they 
assume a 100 percent conversion of fuel sulfur into SO2, 
which results in higher emissions reporting from fuel sampling 
protocols than from CEMS. The commenter claimed that the high bias 
appears to be in the range of 5 to 10 percent. According to the 
commenter, the higher emissions reporting ``penalty'' that is inherent 
in fuel sampling protocols would justify installing SO2 CEMS 
at some oil- and gas-fired units, particularly large, base-loaded oil-
fired units. In addition, the commenter claimed that, for oil- and gas-
fired units which install SO2 CEMS, use of the ``F-factor/
fuel flow method''--which includes use of an F-factor, a fuel 
flowmeter, fuel sampling data, and a diluent (CO2 or O2) 
concentration monitor--would provide much more accurate and precise 
information than volumetric flow monitors (see Docket A-90-51, Item IV-
D-184).
    In a four-day experiment performed in 1991 by one commenter, 
measurements from the F-factor/fuel flow method were compared to those 
generated by a combined SO2 CEMS and a volumetric flow 
monitor. However, EPA did not believe that four consecutive days of 
data were sufficient to support a conclusive equivalency determination. 
Instead, in the January 11, 1993 final rule (58 FR 3590, 3643), EPA 
reserved Appendix I to part 75 for the F-factor/fuel flow method and 
stated that, to be approved, the method would have to meet the criteria 
for alternative methods as required by section 412 of the Act and the 
provisions of Sec. 75.40 in a 30-day (720 hour) trial.
    Section 412 of the Act requires that an alternative monitoring 
system provide information with ``the same precision, reliability, 
accessibility, and timeliness as that provided by CEMS . . .'' 42 
U.S.C. 7651k. To be approved, the alternative monitoring system must 
meet the criteria for alternative methods in a 720 hour trial as 
required by the provisions of subpart E of part 75. The rule designates 
a certified CEMS or a reference method according to Appendix A to part 
60 as the reference for evaluating the alternative monitoring system's 
performance.
    In order to meet the precision and reliability criteria, an 
alternative monitoring system must achieve performance specifications 
and quality assurance requirements equivalent to those for CEMS. In 
addition, to demonstrate precision, an alternative monitoring system 
must pass three statistical tests evaluating the flow CEMS and 
alternative method in terms of their respective systematic error, 
random error, and correlation. Additionally, to meet the reliability 
criterion, the alternative monitoring system is required to match a 
certified CEMS in terms of annual availability. Finally, to meet the 
accessibility and timeliness criteria, an alternative monitoring system 
must match the CEMS' ability to record requisite emissions data on an 
hourly basis and report results within 24 hours.
    In 1995, Long Island Lighting Company (LILCO) sponsored an 
``alternative flow monitor demonstration project'' to demonstrate the 
equivalency of fuel flow measurements and F-factor calculations to 
stack instrument flue gas measurements for the determination of 
volumetric flow. The project was

[[Page 28114]]

performed by Entropy at LILCO's Port Jefferson Unit 4, a 180 MW oil-
fired unit that burns residual oil with a maximum sulfur content of one 
percent. The components of the alternative method consisted of a fuel 
flowmeter and a CO2 CEMS. The alternative F-factor/fuel flow 
method was compared to a flue gas volumetric flow CEMS.
    Testing of the F-factor/fuel flow method took place in April-May 
1995, and 739 hours of data were collected over a wide range of 
operating loads (40 MW--190 MW). Fuel oil samples were taken daily and 
analyzed for density and carbon content. The alternative method 
successfully passed statistical tests but showed statistically 
significant bias (see Docket A-97-35, Item II-D-14). Due to the bias 
uncovered during the test, EPA concluded that the alternative flow 
monitor demonstration project did not meet the requirements of subpart 
E of part 75 for an alternative monitoring system. However, EPA is 
proposing that a default multiplier, derived from the demonstration 
data, be incorporated into the equations used under Appendix I to 
compensate for the detected systematic bias and thereby help to ensure 
that emissions are not underestimated when using the F-factor/fuel flow 
method. With these provisions, EPA proposes to include the F-factor/
fuel flow method as an excepted method for determining flow in Appendix 
I to part 75. The proposed default multiplier, 1.12, is based on the 
data and results of the LILCO demonstration and is supported by EPA and 
the Class of `85 Regulatory Response Group. The default multiplier 
would be incorporated into the equations used under Appendix I whenever 
a relative accuracy test audit is performed on a component-by-component 
basis as was proposed in the LILCO demonstration.
Discussion of Proposed Changes
    EPA proposes to include the F-factor/fuel flow method in Appendix I 
as an excepted method for use in place of a volumetric flow monitor for 
oil- and gas-fired units that burn only natural gas and/or fuel oil. 
The F-factor/fuel flow method uses fuel flow measurement, fuel sampling 
data, CO2 (or O2) CEMS data and F-factors to 
determine the flow rate of the stack gas. EPA proposes limiting use of 
the F-factor/fuel flow method to oil- and gas-fired units that burn 
only natural gas and/or fuel oil because of the greater fuel 
consistency of oil and natural gas and because the fuel flow rates of 
oil and natural gas can be monitored accurately with a fuel flowmeter, 
unlike the feed rate of coal.
    Appendix I flow monitoring would be done using any of the following 
combinations of components: a CO2 monitor and a volumetric 
oil flowmeter, a CO2 monitor and a mass oil flowmeter, a 
CO2 monitor and a volumetric gas flowmeter, an O2 
monitor and a volumetric oil flowmeter, an O2 monitor and a 
mass oil flowmeter, or an O2 monitor and a volumetric gas 
flowmeter.
    Today's proposal would amend Sec. 75.20, ``Certification and 
Recertification Procedures,'' to add certification and recertification 
procedures for units using Appendix I flow monitoring systems. Initial 
certification of the components of the F-factor/fuel flow method would 
be performed either component by component or on a system basis. If 
each component is tested separately, then the fuel flowmeter would be 
tested in accordance with section 2.1.5 of Appendix D, and the 
CO2 or O2 monitor would have to pass a 7-day 
calibration test, a linearity check, a cycle time test and a relative 
accuracy test audit (RATA) using Method 3A from Appendix A to part 60. 
A bias test would also have to be conducted. If the excepted Appendix I 
flow monitoring system is tested as an entire system, then the 
following tests would be performed: a 7-day calibration error test, a 
linearity check, and a cycle time test on the CO2 or 
O2 monitor, and a relative accuracy test audit on the entire 
excepted flow monitoring system using Method 2 from Appendix A to part 
60, and a bias test. The owner or operator would also test the data 
acquisition and handling system. Upon successful completion of all 
certification tests, the Appendix I system would be considered 
provisionally certified.
    Today's proposal would amend Sec. 75.21, ``Quality Assurance and 
Quality Control Requirements,'' to include Appendix I flow monitoring 
systems. A unit utilizing the optional F-factor/fuel flow method would 
have to meet ongoing quality assurance testing requirements. First, the 
daily and quarterly assessment requirements for a CO2 or 
O2 monitor in sections 2.1 and 2.2 of Appendix B would have 
to be followed. Second, one of the following would have to be met, 
depending on whether the owner or operator chooses to test the method 
on a component-by-component basis or on a system level: (1) the fuel 
flow meter quality assurance requirements and a separate RATA on the 
CO2 (or O2) monitor; or (2) a system level flow 
RATA. If the components are tested separately, the applicable 
procedures in section 2.1.6 of Appendix D would have to be followed for 
the fuel flowmeter quality assurance (i.e., a flow meter accuracy test, 
a transmitter accuracy test and primary element inspection, and/or the 
supplemental quarterly fuel flow-to-load quality assurance testing) and 
the applicable RATA procedures in sections 6.5 through 6.5.2.2 of 
Appendix A for the CO2 (or O2) monitor would be 
followed. In addition, the bias test would have to be performed on the 
CO2 (or O2) monitor and, if the bias test is 
failed, a bias adjustment factor (BAF) would have to be calculated and 
applied to hourly data.
    If the entire system is tested, the applicable procedures in 
sections 6.5 through 6.5.2.2 of Appendix A would have to be used to 
meet the performance specifications for flow relative accuracy in 
section 3.3.4 of Appendix A. The bias test would have to be performed 
on the volumetric flow data and, if the bias test is failed, a BAF 
would have to be calculated using the procedures in section 7.6 of 
Appendix A.
    Several other sections of the rule would be modified or added in 
order to incorporate the new excepted method described in Appendix I, 
including Secs. 75.30, 75.57, 75.58, and 75.59. Section 75.30, 
``General Provisions'' (for missing data substitution procedures), 
would be modified by adding quality assured data from a certified 
excepted flow monitoring system under Appendix I to the list of 
monitoring systems that measure flow rate data, for which the missing 
data substitution procedures of subpart D are required. If fuel 
sampling data, fuel flow rate data, and diluent gas data are missing, 
then the data acquisition and handling system would have to substitute 
for missing volumetric flow data. In addition, Sec. 75.57, would 
include additional information that Appendix I flow monitoring systems 
must record. This includes fuel flow rate data and data from component 
monitors. Section 75.58(g) would be added to address specific 
volumetric flow rate record provisions for units using the optional 
protocol in Appendix I. Section 75.59, ``Certification, Quality 
Assurance and Quality Control Record Provisions,'' would also include 
certification and quality assurance information that facilities must 
record for Appendix I flow monitoring system tests.
    Finally, the new proposed Appendix I would describe the 
applicability, procedures, calculations, missing data, and 
recordkeeping and reporting requirements for units using Appendix I to 
determine flow.
    The Appendix I formulas are more complex if an O2 
monitor is used. EPA proposes to allow the use of an O2 
monitor for Appendix I; however, the

[[Page 28115]]

initial programming of the formulas and monitoring plan development may 
take longer for Appendix I flow monitoring systems that use an 
O2 monitor.
    Volumetric stack flow rate during oil combustion would be 
calculated from (1) a bias adjustment factor from the applicable bias 
test results; (2) the fuel flow rate (in gal/hr); (3) the fuel density 
(in lb/gal); (4) the percent carbon by weight; (5) the CO2 
(or O2) concentration percent by volume; and (6) the 
appropriate conversion factor. The carbon content of the fuel would 
have to be determined according to the procedures in section 2.1 of 
Appendix G and the density of the oil would have to be determined 
according to the procedures in section 2.2 of Appendix D.
    Rationale: EPA is proposing an F-factor/fuel flow method in 
Appendix I to part 75 as an excepted method to measure volumetric flow 
directly with a flow monitor because this method would allow fuel flow 
measurement with a gas or oil flowmeter, fuel sampling data, 
CO2 (or O2) CEMS data, and F-factors to determine 
the flow rate of the stack gas rather than a volumetric flow monitor. 
The F-factor/fuel flow method would be available for use by oil-fired 
and gas-fired units, as defined under Sec. 72.2, provided that they 
only burn natural gas and/or fuel oil. For these units, EPA believes 
that the proposed method would provide acceptably accurate measurements 
of volumetric flow, while affording cost savings that some industry 
representatives estimate could be substantial. The Agency solicits 
comment on the proposed Appendix I and associated changes to part 75.
    Appendix I may offer cost savings to some oil and gas fired units. 
Representatives from oil- and gas-fired units have estimated that the 
costs of operating, maintaining and testing volumetric flow monitors 
range from approximately $15,000 to $25,000 per year. In contrast, 
using the F-factor/fuel flow method is estimated to result in costs of 
only approximately $5,000 to $7,000 per year due to elimination of the 
operating, maintenance, testing and fuel costs associated with the 
volumetric flow monitor.

U. The Use of Predictive Emissions Modeling Systems (PEMS)

    A number of parties have submitted preliminary field test data 
designed to demonstrate that EPA should set forth specific requirements 
for alternative monitoring methodologies that predict NOX 
emission rates at gas-fired units. These ``predictive emissions 
modeling systems'' (PEMS) use mathematical models to predict 
NOX emission rates based on sensor readings of key operating 
parameters. The agency is evaluating the submitted data and will 
consider taking further action under a future rulemaking if additional 
study demonstrates the equivalency of PEMS to CEMS for well defined 
classes of units.

IV. Administrative Requirements

A. Public Hearing

    If requested as specified in the DATES section of this preamble, a 
public hearing will be held to discuss the proposed regulations. 
Persons wishing to make oral presentations at the public hearing should 
contact EPA at the address given in the ADDRESSES section of this 
preamble. If necessary, oral presentations will be limited to 15 
minutes each. Any member of the public may file a written statement 
with EPA before, during, or within 30 days of the hearing. Written 
statements should be addressed to the Air Docket address given in the 
ADDRESSES section of this preamble.
    A verbatim transcript of the public hearing, if held, and all 
written statements will be available for public inspection and copying 
during normal working hours at EPA's Air Docket in Washington, DC (see 
the ADDRESSES section of this preamble).

B. Public Docket

    The Docket for this regulatory action is A-97-35. The docket is an 
organized and complete file of all the information submitted to or 
otherwise considered by EPA in the development of this proposed 
rulemaking. The principal purposes of the docket are: (1) to allow 
interested parties a means to identify and locate documents so that 
they can effectively participate in the rulemaking process, and (2) to 
serve as the record in case of judicial review. The docket is available 
for public inspection at EPA's Air Docket, which is listed under the 
ADDRESSES section of this preamble.

C. Executive Order 12866

    Under Executive Order 12866 (58 FR 51735, October 4, 1993), the 
Administrator must determine whether the regulatory action is 
``significant'' and therefore subject to Office of Management and 
Budget (OMB) review and the requirements of the Executive Order. The 
Order defines ``significant regulatory action'' as one that is likely 
to result in a rule that may:

    (1) Have an annual effect on the economy of $100 million or more 
or adversely affect in a material way the economy, a sector of the 
economy, productivity, competition, jobs, the environment, public 
health or safety, or State, local or tribal governments or 
communities;
    (2) Create a serious inconsistency or otherwise interfere with 
an action taken or planned by another agency;
    (3) Materially alter the budgetary impact of entitlements, 
grants, user fees, or loan programs or the rights and obligations of 
recipients thereof; or
    (4) Raise novel legal or policy issues arising out of legal 
mandates, the President's priorities, or the principles set forth in 
the Executive Order.

    This proposed rule is not expected to have an annual effect on the 
economy of $100 million or more. However, pursuant to the terms of 
Executive Order 12866, it has been determined that this proposed rule 
is a significant action because it raises novel policy issues. As such, 
the proposed rule has been submitted for OMB review. Any written 
comments from OMB and any EPA response to OMB comments are in the 
public docket for this proposal.

D. Unfunded Mandates Reform Act

    Title II of the Unfunded Mandates Reform Act of 1995 (UMRA), P.L. 
104-4, establishes requirements for Federal agencies to assess the 
effects of their regulatory actions on State, local, and tribal 
governments and the private sector. Under section 202 of the UMRA, EPA 
generally must prepare a written statement, including a cost-benefit 
analysis, for proposed and final rules with ``Federal mandates'' that 
may result in expenditures to State, local, and tribal governments, in 
the aggregate, or to the private sector, of $100 million or more in any 
one year. Before promulgating an EPA rule for which a written statement 
is needed, section 205 of the UMRA generally requires EPA to identify 
and consider a reasonable number of regulatory alternatives and adopt 
the least costly, most cost-effective, or least burdensome alternative 
that achieves the objectives of the rule. The provisions of section 205 
do not apply when they are inconsistent with applicable law. Moreover, 
section 205 allows EPA to adopt an alternative other than the least 
costly, most cost-effective, or least burdensome alternative if the 
Administrator publishes with the final rule an explanation why that 
alternative was not adopted. Before EPA establishes any regulatory 
requirements that may significantly or uniquely affect small 
governments, including tribal governments, it must have developed under 
section 203 of the UMRA a small government agency plan. The plan must 
provide for notifying potentially affected small governments, enabling 
officials of affected small governments

[[Page 28116]]

to have meaningful and timely input in the development of EPA 
regulatory proposals with significant Federal intergovernmental 
mandates, and informing, educating, and advising small governments on 
compliance with the regulatory requirements.
    This proposed rule is not expected to result in expenditures of 
more than $100 million in any one year and, as such, is not subject to 
section 202 of the UMRA. Although the proposed rule is not expected to 
significantly or uniquely affect small governments, the Agency has 
notified all potentially affected small governments that own or operate 
units potentially affected by the proposal in order to assure that they 
have the opportunity to have meaningful and timely input on the 
proposed rule. EPA will continue to use its outreach efforts related to 
part 75 implementation, including a policy manual that is generally 
updated on a quarterly basis, to inform, educate, and advise all 
potentially impacted small governments about compliance with part 75.

E. Paperwork Reduction Act

    The information collection requirements in this proposal have been 
submitted for approval to the OMB under the Paperwork Reduction Act, 44 
U.S.C. 3501, et seq. An Information Collection Request (ICR) document 
has been prepared by EPA (ICR No. 1835.01), and a copy may be obtained 
from Sandy Farmer, OPPE Regulatory Information Division; U.S. 
Environmental Protection Agency (2137); 401 M Street, SW, Washington, 
DC 20460, by calling (202) 260-2740, or via the Internet at www.gov/
icr.
    Currently, all affected utilities are required to keep records and 
submit electronic quarterly reports under the provisions of part 75. 
The proposed rule includes several new options for compliance with part 
75 which have been requested by affected utilities. To implement these 
options, EPA would have to modify the existing recordkeeping and 
reporting requirements. In some circumstances, these changes would 
result in significant reductions in the reporting and recordkeeping 
burdens or costs for some units (such as low mass emissions units). 
However, these changes would require modifications to the software used 
to generate electronic reports. In addition, there would be some 
increased burden or costs for certain units to fulfill the new quality 
assurance procedures proposed in these proposed revisions. Finally, 
several other technical revisions to the existing reporting and 
recordkeeping requirements have been proposed to clarify existing 
provisions or to facilitate reporting for other regulatory programs in 
the context of Acid Rain Program reporting. Although these one-time 
software changes would tend to increase the short-term burdens 
allocated to the Acid Rain Program, such changes should reduce a 
source's overall long-term burden by streamlining the source's 
reporting obligations under both the Acid Rain Program and the Act.
    The average annual projected hour burden is 2,608,836, which is 
based on an estimated 835 likely respondents (on a per utility basis). 
The projected cost burden resulting from the collection of information 
is $47,555,000, which includes a total projected capital and start-up 
cost of $1,436,000 (for monitoring equipment/software), and a total 
projected operation and maintenance cost (which includes purchase of 
testing contractor services and total projected fuel sampling and 
analysis cost of $716,000) of $46,119,000. Burden means the total time, 
effort, or financial resources expended by persons to generate, 
maintain, retain, disclose, or provide information to or for a Federal 
agency. This includes the time needed to review instructions; develop, 
acquire, install, and utilize technology and systems for purposes of 
collecting, validating, and verifying information, processing and 
maintaining information, and disclosing and providing information; 
adjust the existing ways to comply with any previously applicable 
instructions and requirements; train personnel to be able to respond to 
a collection of information; search data sources; complete and review 
the collection of information; and transmit or otherwise disclose the 
information.
    An agency may not conduct or sponsor and a person is not required 
to respond to a collection of information, unless it displays a 
currently valid OMB control number. The OMB control numbers for EPA's 
regulations are listed in 40 CFR part 9 and 48 CFR chapter 15.
    Comments are requested on the Agency's need for this information, 
the accuracy of the provided burden estimates, and any suggested 
methods for minimizing respondent burden, including through the use of 
automated collection techniques. Send comments on the ICR to the 
Director, OPPE Regulatory Information Division; U.S. Environmental 
Protection Agency (2137); 401 M Street, SW, Washington, DC 20460; and 
to the Office of Information and Regulatory Affairs, Office of 
Management and Budget, 725 17th Street, NW, Washington, DC 20503, 
marked ``Attention: Desk Officer for EPA.'' Include the ICR number in 
any correspondence. Since OMB is required to make a decision concerning 
the ICR between 30 and 60 days after May 21, 1998, a comment to OMB is 
best assured of having its full effect if OMB receives it by June 22, 
1998. The final rule will respond to any OMB or public comments on the 
information collection requirements contained in this proposal.

F. Regulatory Flexibility Act

    The Regulatory Flexibility Act (RFA), 5 U.S.C. 601, et seq., 
generally requires an agency to conduct a regulatory flexibility 
analysis of any rule subject to notice and comment rulemaking 
requirements unless the agency certifies that the rule will not have a 
significant economic impact on a substantial number of small entities. 
Small entities include small businesses, small not-for-profit 
enterprises, and governmental jurisdictions. This proposed rule would 
not have a significant impact on a substantial number of small 
entities.
    Today's proposed revisions to part 75 result in a net cost 
reduction to utilities affected by the Acid Rain Program, including 
small entities. Most importantly, the proposed changes to Appendix D 
and the addition of an optional calculation procedure instead of actual 
monitoring for oil- and gas-fired units with low mass emissions would 
significantly reduce the cost of complying with part 75 for oil-and 
gas-fired units, many of which are owned or operated by small entities. 
Therefore, I certify this action will not have a significant economic 
impact on a substantial number of small entities.

G. National Technology Transfer and Advancement Act

    Section 12(d) of the National Technology Transfer and Advancement 
Act of 1995 (``ANTTAA''), Pub L. No. 104-113 15 USC 272 note, directs 
EPA to use voluntary consensus standards in its regulatory activities 
unless to do so would be inconsistent with applicable law or otherwise 
impractical. Voluntary consensus standards are technical standards 
(e.g., materials specifications, test methods, sampling procedures, 
business practices, etc.) that are developed or adopted by voluntary 
consensus standards bodies. The NTTAA requires EPA to provide Congress, 
through OMB, explanations when the Agency decides not to use available 
and applicable voluntary consensus standards.
    This regulatory action proposes to incorporate by reference 
voluntary consensus standards pursuant to Sec. 12(d) of the NTTAA. The 
EPA has adopted the general policy of using voluntary

[[Page 28117]]

consensus standards from technically knowledgeable groups such as the 
Organization for International Standards (ISO), the American Society 
for Testing and Materials (ASTM), the American Society of Mechanical 
Engineers (ASME), the American Gas Association (AGA), the Gas 
Processors Association (GPA), and the American Petroleum Institute 
(API).
    EPA invites public comment on the voluntary consensus standards 
which are proposed to be incorporated by reference for use in part 75. 
EPA has not identified any additional voluntary consensus standards 
which might be applicable to this rulemaking. This does not indicate 
that other applicable standards do not exist or that any other 
standards should not be allowed. Therefore, EPA also invites public 
comment on any other voluntary consensus standards which may be 
appropriate for the proposed regulatory action. Further, if additional 
applicable voluntary consensus standards are identified in the future, 
the designated representative may petition under Sec. 75.66(c) to use 
an alternative to any standard incorporated by reference and prescribed 
in this part.
    EPA proposes to incorporate by reference the following voluntary 
consensus standards for use under part 75:
    a. ASTM D5373-93 ``Standard Methods for Instrumental Determination 
of Carbon, Hydrogen and Nitrogen in laboratory samples of Coal and 
Coke.'' This standard is proposed to be incorporated by reference for 
use under section 2.1 of Appendix G to part 75 and is discussed further 
in section III.Q.1 of this preamble.
    b. API Section 2 ``Conventional Pipe Provers'' from Chapter 4 of 
the Manual of Petroleum Measurement Standards, October 1988 edition. 
This standard is proposed to be incorporated by reference for use under 
paragraph (g)(1)(i) of Sec. 75.20 and under section 2.1.5.1 of Appendix 
D to part 75. The proposal to incorporate this standard by reference is 
discussed further in section III.P.6.(b) of this preamble.

List of Subjects in 40 CFR Parts 72 and 75

    Air pollution control, Carbon dioxide, Continuous emission 
monitors, Electric utilities, Environmental protection, Nitrogen 
oxides, Reporting and recordkeeping requirements, Sulfur dioxide.

    Dated: April 27, 1998.
Carol M. Browner,
Administrator, U.S. Environmental Protection Agency.

    For the reasons set out in the preamble, title 40 chapter 1 of the 
Code of Federal Regulations is proposed to be amended as follows:

PART 72--PERMITS REGULATION

    1. The authority for part 72 continues to read as follows:

    Authority: 42 U.S.C. 7601 and 7651, et seq.

    2. Section 72.2 is amended by revising the definitions of 
``calibration gas,'' ``excepted monitoring system,'' ``gas-fired,'' 
``pipeline natural gas,'' ``span,'' ``stationary gas turbine,'' and 
``zero air material''; by revising paragraph (2) of ``oil-fired'' and 
paragraph (2) of the ``peaking unit''; by adding paragraph (3) to the 
definition of ``peaking unit''; by adding new definitions for 
``conditionally valid data,'' ``EPA protocol gas,'' ``gas 
manufacturer's intermediate standard,'' ``low mass emissions unit,'' 
``maximum rated hourly heat input,'' ``ozone season,'' ``probationary 
calibration error test,'' ``research gas mixture (RGM)'', and 
``standard reference material-equivalent compressed gas primary 
reference material''; and by removing the definition of ``protocol 1 
gas,'' to read as follows:


Sec. 72.2  Definitions.

* * * * *
    Calibration gas means:
    (1) A standard reference material;
    (2) A standard reference material-equivalent compressed gas primary 
reference material;
    (3) A NIST traceable reference material;
    (4) NIST/EPA-approved certified reference materials;
    (5) A gas manufacturer's intermediate standard;
    (6) An EPA protocol gas;
    (7) Zero air material; or
    (8) A research gas mixture.
* * * * *
    Conditionally valid data means data from a continuous monitoring 
system that are not quality assured, but which may become quality 
assured if certain conditions are met. Examples of data that may 
qualify as conditionally valid are: data recorded by an uncertified 
monitoring system prior to its initial certification; or data recorded 
by a certified monitoring system following a significant change to the 
system that may affect its ability to accurately measure and record 
emissions. A monitoring system must pass a probationary calibration 
error test, in accordance with section 2.1.1 of appendix B of part 75 
of this chapter, to initiate the conditionally valid data status. In 
order for conditionally valid emission data to become quality assured, 
one or more quality assurance tests or diagnostic tests must be passed 
within a specified time period.
* * * * *
    EPA protocol gas means a calibration gas mixture prepared and 
analyzed according to section 2 of the ``EPA Traceability Protocol for 
Assay and Certification of Gaseous Calibration Standards,'' September 
1997, EPA-600/R-97/121 or such revised procedure as approved by the 
Administrator.
* * * * *
    Excepted monitoring system means a monitoring system that follows 
the procedures and requirements of Sec. 75.19 of this chapter or of 
appendix D or E to part 75 for approved exceptions to the use of 
continuous emission monitoring systems.
* * * * *
    Gas-fired means:
    (1) For all purposes under the Acid Rain Program, except for part 
75 of this chapter, the combustion of:
    (i) Natural gas or other gaseous fuel (including coal-derived 
gaseous fuel), for at least 90.0 percent of the unit's average annual 
heat input during the previous three calendar years and for at least 
85.0 percent of the annual heat input in each of those calendar years; 
and
    (ii) Any fuel, except coal or solid or liquid coal-derived fuel for 
the remaining heat input, if any.
    (2) For purposes of part 75 of this chapter, the combustion of:
    (i) Natural gas or other gaseous fuel with a total sulfur content 
no greater than the total sulfur content of natural gas (including 
coal-derived gaseous fuel) for at least 90.0 percent of the unit's 
average annual heat input during the previous calendar years and for at 
least 85.0 percent of the annual heat input in each of those calendar 
years; and
    (ii) Fuel oil, for the remaining heat input, if any.
    (3) For purposes of part 75 of this chapter, a unit may initially 
qualify as gas-fired if the designated representative demonstrates to 
the satisfaction of the Administrator that the requirements of 
paragraph (2) of this definition are met, or will in the future be met, 
through one of the following submissions:
    (i) For a unit for which a monitoring plan has not been submitted 
under Sec. 75.62 of this chapter,
    (A) The designated representative submits fuel usage data for the 
unit for

[[Page 28118]]

the three calendar years immediately preceding the date of initial 
submission of the monitoring plan for the unit under Sec. 75.62; or
    (B) For a unit that does not have fuel usage data for one or more 
of the three calendar years immediately preceding the date of initial 
submission of the monitoring plan for the unit under Sec. 75.62, if the 
designated representative submits: the unit's designated fuel usage; 
all available fuel usage data (including the percentage of the unit's 
heat input derived from the combustion of gaseous fuels), beginning 
with the date on which the unit commenced commercial operation; and the 
unit's projected fuel usage.
    (ii) For a unit for which a monitoring plan has already been 
submitted under Sec. 75.62, that has not qualified as gas-fired under 
paragraph (3)(i) of this definition, and whose fuel usage changes, the 
designated representative submits either:
    (A) Three calendar years of data following the change in the unit's 
fuel usage, showing that no less than 90.0 percent of the unit's 
average annual heat input during the previous three calendar years, and 
no less than 85.0 percent of the unit's annual heat input during any 
one of the previous three calendar years is from the combustion of 
gaseous fuels with a total sulfur content no greater than the total 
sulfur content of natural gas and the remaining heat input is from the 
combustion of fuel oil; or
    (B) A minimum of 720 hours of unit operating data following the 
change in the unit's fuel usage, showing that no less than 90.0 percent 
of the unit's heat input is from the combustion of gaseous fuels with a 
total sulfur content no greater than the total sulfur content of 
natural gas and the remaining heat input is from the combustion of fuel 
oil, and a statement that this changed pattern of fuel usage is 
considered permanent and is projected to continue for the foreseeable 
future.
    (iii) If a unit qualifies as gas-fired under paragraph (2)(i) or 
(ii) of this definition, the unit is classified as gas-fired as of the 
date of the submission under such paragraph.
    (4) For purposes of part 75 of this chapter, a unit that initially 
qualifies as gas-fired must meet the criteria in paragraph (2) of this 
definition each year in order to continue to qualify as gas-fired. If 
such a unit fails to meet such criteria for a given year, the unit no 
longer qualifies as gas-fired starting January 1 of the year after the 
first year for which the criteria are not met. If a unit failing to 
meet the criteria in paragraph (2) of this definition initially 
qualified as a gas-fired unit under paragraph (3)(ii) of this 
definition, the unit may qualify as a gas-fired unit for a subsequent 
year only under paragraph (3)(i) of this definition.
* * * * *
    Gas manufacturer's intermediate standard (GMIS) means a compressed 
gas calibration standard that has been assayed and certified by direct 
comparison to a standard reference material (SRM), an SRM-equivalent 
PRM, a NIST/EPA-approved certified reference material (CRM), or a NIST 
traceable reference material (NTRM), in accordance with section 2.1.2.1 
of the ``EPA Traceability Protocol for Assay and Certification of 
Gaseous Calibration Standards,'' September 1997, EPA-600/R-97/121.
* * * * *
    Low mass emissions unit means a gas-fired or oil-fired unit that 
burns only natural gas and/or fuel oil and that qualifies under 
Secs. 75.19(a) and (b) of this chapter.
* * * * *
    Maximum rated hourly heat input means a unit-specific maximum 
hourly heat input (mmBtu) which is the higher of the manufacturer's 
maximum rated hourly heat input or the highest observed hourly heat 
input.
    Oil-fired means:
* * * * *
    (2) For purposes of part 75 of this chapter, a unit may qualify as 
oil-fired if the unit burns only fuel oil and gaseous fuels with a 
total sulfur content no greater than the total sulfur content of 
natural gas and if the unit does not meet the definition of gas-fired.
* * * * *
    Ozone season means the period of time from May 1st to September 
30th, inclusive.
* * * * *
    Peaking unit means:
* * * * *
    (2) For purposes of part 75 of this chapter, a unit may initially 
qualify as a peaking unit if the designated representative demonstrates 
to the satisfaction of the Administrator that the requirements of 
paragraph (1) of this definition are met, or will in the future be met, 
through one of the following submissions:
    (i) For a unit for which a monitoring plan has not been submitted 
under Sec. 75.62,
    (A) The designated representative submits capacity factor data for 
the unit for the three calendar years immediately preceding the date of 
initial submission of the monitoring plan for the unit under 
Sec. 75.62; or
    (B) For a unit that does not have capacity factor data for one or 
more of the three calendar years immediately preceding the date of 
initial submission of the monitoring plan for the unit under 
Sec. 75.62, the designated representative submits: all available 
capacity factor data, beginning with the date on which the unit 
commenced commercial operation; and projected capacity factor.
    (ii) For a unit for which a monitoring plan has already been 
submitted under Sec. 75.62, that has not qualified as a peaking unit 
under paragraph (2)(i) of this definition, and where capacity factor 
changes, the designated representative submits either:
    (A) Three calendar years of data following the change in the unit's 
capacity factor showing an average capacity factor of no more than 10.0 
percent during the three previous calendar years and a capacity factor 
of no more than 20.0 percent in each of those calendar years; or
    (B) One calendar year of data following the change in the unit's 
capacity factor showing a capacity factor of no more than 10.0 percent 
and a statement that this changed pattern of operation resulting in a 
capacity factor less than 10.0 percent is considered permanent and is 
projected to continue for the foreseeable future.
    (3) For purposes of part 75 of this chapter, a unit that initially 
qualifies as a peaking unit must meet the criteria in paragraph (1) of 
this definition each year in order to continue to qualify as a peaking 
unit. If such a unit fails to meet such criteria for a given year, the 
unit no longer qualifies as a peaking unit starting January 1 of the 
year after the year for which the criteria are not met. If a unit 
failing to meet the criteria in paragraph (1) of this definition 
initially qualified as a gas-fired unit under paragraph (2)(ii) of this 
definition, the unit may qualify as a peaking unit for a subsequent 
year only under paragraph (2)(i) of this definition.
* * * * *
    Pipeline natural gas means natural gas that is provided by a 
supplier through a pipeline and that contains 0.3 grains or less of 
hydrogen sulfide per 100 standard cubic feet. The hydrogen sulfide 
content of the natural gas must be documented either through quality 
characteristics specified by a purchase contract or pipeline 
transportation contract, through certification of the gas vendor, based 
on routine vendor sampling and analysis, or through at least one year's 
worth of analytical data on the fuel hydrogen sulfide content from 
samples taken at least monthly, demonstrating that all samples contain

[[Page 28119]]

0.3 grains or less of hydrogen sulfide per 100 standard cubic feet.
* * * * *
    Probationary calibration error test means an on-line calibration 
error test performed in accordance with section 2.1.1 of appendix B of 
part 75 of this chapter that is used to initiate a conditionally valid 
data period.
* * * * *
    Research gas mixture (RGM) means a calibration gas mixture 
developed by agreement of a requestor and NIST that NIST analyzes and 
certifies as ``NIST traceable.'' RGMs may have concentrations different 
from those of standard reference materials.
* * * * *
    Span means the highest pollutant or diluent concentration or flow 
rate that a monitor component is required to be capable of measuring 
under part 75 of this chapter.
* * * * *
    Standard reference material-equivalent compressed gas primary 
reference material (SRM-equivalent PRM) means those gas mixtures listed 
in a declaration of equivalence in accordance with section 2.1.2 of the 
``EPA Traceability Protocol for Assay and Certification of Gaseous 
Calibration Standards,'' September 1997, EPA-600/R-97/121.
* * * * *
    Stationary gas turbine means a turbine that is not self-propelled 
and that combusts natural gas, other gaseous fuel with a total sulfur 
content no greater than the total sulfur content of natural gas, or 
fuel oil in order to heat inlet combustion air and thereby turn a 
turbine, in addition to or instead of producing steam or heating water.
* * * * *
    Zero air material means either:
    (1) A calibration gas certified by the gas vendor not to contain 
concentrations of SO2, NOX, or total hydrocarbons 
above 0.1 parts per million (ppm), a concentration of CO above 1 ppm, a 
concentration of CO2 above 400 ppm; or
    (2) Ambient air conditioned and purified by a CEMS for which the 
CEMS manufacturer or vendor certifies that the particular CEMS model 
produces conditioned gas that does not contain concentrations of 
SO2, NOX, or total hydrocarbons above 0.1 ppm, a 
concentration of CO above 1 ppm, or a concentration of CO2 
above 400 ppm; or
    (3) For dilution-type CEMS, conditioned and purified ambient air 
provided by a conditioning system concurrently supplying dilution air 
to the CEMS; or
    (4) A multicomponent mixture certified by the supplier of the 
mixture that the concentration of the component being zeroed is less 
than or equal to the applicable concentration specified in paragraph 
(1) of this definition, and that the mixture's other components do not 
interfere with the specific CEM readings or cause the CEM being zeroed 
to read concentrations of the gas being zeroed.
    3. Section 72.3 is amended by adding in alphabetical order, new 
acronyms for kacfm, kscfh, and NIST to read as follows:


Sec. 72.3  Measurements, abbreviations, and acronyms.

* * * * *
    kacfm--thousands of cubic feet per minute at actual conditions.
    kscfh--thousands of cubic feet per hour at standard conditions.
    NIST--National Institute of Standards and Technology.
* * * * *


Sec. 72.6  [Amended]

    4. Section 72.6 is amended by removing from paragraph (b)(1) the 
word ``operation'' and adding, in its place, the words ``commercial 
operation.''
    5. Section 72.90 is amended by revising paragraph (c)(3) to read as 
follows:


Sec. 72.90  Annual compliance certification report.

* * * * *
    (c) * * *
    (3) Whether all the emissions from the unit, or a group of units 
(including the unit) using a common stack, were monitored or accounted 
for through the missing data procedures and reported in the quarterly 
monitoring reports, including whether conditional data were reported in 
the quarterly report. If conditional data were reported, the owner or 
operator shall indicate whether the status of all conditional data has 
been resolved and all necessary quarterly report resubmissions have 
been made.
* * * * *

PART 75--CONTINUOUS EMISSION MONITORING

    6. The authority citation for part 75 continues to read as follows:

    Authority: 42 U.S.C. 7601 and 7651k.

    7. Section 75.1 is amended by revising paragraph (a) to read as 
follows:


Sec. 75.1  Purpose and scope.

    (a) Purpose. The purpose of this part is to establish requirements 
for the monitoring, recordkeeping, and reporting of sulfur dioxide, 
nitrogen oxides, and carbon dioxide emissions, volumetric flow, and 
opacity data from affected units under the Acid Rain Program pursuant 
to Sections 412 and 821 of the Clean Air Act, 42 U.S.C. 7401-7671q as 
amended by Public Law 101-549 (November 15, 1990) (the Act). In 
addition, this part sets forth provisions for the monitoring, 
recordkeeping, and reporting of NOX mass emissions with 
which EPA, individual States, or groups of States may require sources 
to comply in order to demonstrate compliance with a NOX mass 
emission reduction program, if these provisions are adopted as 
requirements under such a program.
* * * * *
    8. Section 75.2 is amended by revising paragraph (a) and adding a 
new paragraph (c) to read as follows:


Sec. 75.2 Applicability.

    (a) Except as provided in paragraphs (b) and (c) of this section, 
the provisions of this part apply to each affected unit subject to Acid 
Rain emission limitations or reduction requirements for SO2 
or NOX.
* * * * *
    (c) The provisions of this part may apply to sources subject to a 
State or federal NOX mass emission reduction program, if 
these provisions are adopted as requirements under such a program.
    9. Section 75.4 is amended by revising paragraphs (a) introductory 
text and (d)(1) and adding a new paragraph (i) to read as follows:


Sec. 75.4  Compliance dates.

    (a) The provisions of this part apply to each existing Phase I and 
Phase II unit on February 10, 1993. For substitution or compensating 
units that are so designated under the Acid Rain permit which governs 
that unit and contains the approved substitution or reduced utilization 
plan, pursuant to Sec. 72.41 or Sec. 72.43 of this chapter, the 
provisions of this part become applicable upon the issuance date of the 
Acid Rain permit. For combustion sources seeking to enter the Opt-in 
Program in accordance with part 74 of this chapter, the provisions of 
this part become applicable upon the submission of an Opt-in permit 
application in accordance with Sec. 74.14 of this chapter. The 
provisions of this part for the monitoring, recording, and reporting of 
NOX mass emissions become applicable on the deadlines 
specified in the applicable State or federal NOX mass 
emission reduction program, if these provisions are adopted as 
requirements under such a program. In accordance with Sec. 75.20, the 
owner or operator of each existing affected unit shall ensure that all 
monitoring systems required by

[[Page 28120]]

this part for monitoring SO2, NOX, 
CO2, opacity, and volumetric flow are installed and that all 
certification tests are completed no later than the following dates 
(except as provided in paragraphs (d) through (h) of this section):
* * * * *
    (d) * * *
    (1) The maximum potential concentration of SO2, the 
maximum potential NOX emission rate, the maximum potential 
flow rate, as defined in section 2.1 of appendix A to this part, or the 
maximum potential CO2 concentration, as defined in section 
2.1.3.1 of appendix A to this part.
* * * * *
    (i) In accordance with Sec. 75.20, the owner or operator of each 
affected unit at which SO2 concentration is measured on a 
dry basis or at which moisture corrections are required to account for 
CO2 emissions, NOX emission rate in lb/mmBtu, or 
heat input, shall ensure that the continuous moisture monitoring system 
required by this part is installed and that all applicable initial 
certification tests required under Sec. 75.20(c)(5), (c)(6), or (c)(7) 
for the continuous moisture monitoring system are completed no later 
than the following dates:
    (1) January 1, 2000, for a unit that is existing and has commenced 
commercial operation by October 3, 1999; or
    (2) For a new affected unit which has not commenced commercial 
operation by October 4, 1999, not later than 90 days after the date the 
unit commences commercial operation; or
    (3) For an existing unit that is shutdown and is not yet operating 
by January 1, 2000, not later than the earlier of 45 unit operating 
days or 180 calendar days after the date that the unit recommences 
commercial operation.
    10. Section 75.5 is amended by revising paragraph (f)(2) to read as 
follows:


Sec. 75.5  Prohibitions.

* * * * *
    (f) * * *
    (2) The owner or operator is monitoring emissions from the unit 
with another certified monitoring system or an excepted methodology 
approved by the Administrator for use at that unit that provides 
emission data for the same pollutant or parameter as the retired or 
discontinued monitoring system; or
* * * * *
    11. Section 75.6 is amended by redesignating paragraph (a)(40) as 
paragraph (a)(41) and by adding new paragraphs (a)(40) and (f) to read 
as follows:


Sec. 75.6  Incorporation by reference.

* * * * *
    (a) * * *
    (40) ASTM D5373-93, ``Standard Methods for Instrumental 
Determination of Carbon, Hydrogen, and Nitrogen in Laboratory Samples 
of Coal and Coke,'' for appendix G to this part.
* * * * *
    (f) The following materials are available for purchase from the 
following address: American Petroleum Institute, Publications 
Department, 1220 L Street NW, Washington, DC 20005-4070: American 
Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' 
from Chapter 4 of the Manual of Petroleum Measurement Standards, 
October 1988 (Reaffirmed 1993), for Sec. 75.20 and appendix D to this 
part.
    12. Section 75.10 is amended by revising paragraphs (d)(3) and (f) 
to read as follows:


Sec. 75.10  General operating requirements.

* * * * *
    (d) * * *
    (3) Failure of an SO2, CO2, or O2 
pollutant concentration monitor, flow monitor, or NOX 
continuous emission monitoring system to acquire the minimum number of 
data points for calculation of an hourly average in paragraph (d)(1) of 
this section, shall result in the failure to obtain a valid hour of 
data and the loss of such component data for the entire hour. An hourly 
average NOX or SO2 emission rate in lb/mmBtu is 
valid only if the minimum number of data points is acquired by both the 
pollutant concentration monitor (NOX or SO2) and 
the diluent monitor (O2 or CO2). For a moisture 
monitoring system consisting of one or more oxygen analyzers capable of 
measuring O2 on a wet-basis and a dry-basis, an hourly 
average percent moisture value is valid only if the minimum number of 
data points is acquired for both the wet-and dry-basis measurements. 
Except for SO2 emission rate data in lb/mmBtu, if a valid 
hour of data is not obtained, the owner or operator shall estimate and 
record emission, moisture, or flow data for the missing hour by means 
of the automated data acquisition and handling system, in accordance 
with the applicable procedure for missing data substitution in subpart 
D of this part.
* * * * *
    (f) Minimum measurement capability requirement. The owner or 
operator shall ensure that each continuous emission monitoring system 
and component thereof is capable of accurately measuring, recording, 
and reporting data, and shall not incur a full scale exceedance, except 
as provided in sections 2.1.1.5, 2.1.2.5, and 2.1.4.3 of appendix A to 
this part.
* * * * *
    13. Section 75.11 is amended by revising paragraphs (a), (b), 
(d)(1), (d)(2), (e)(2), (e)(3) introductory text, (e)(3)(ii), 
(e)(3)(iv), and (e)(4) and by adding paragraph (d)(3), to read as 
follows:


Sec. 75.11  Specific provisions for monitoring SO2 emissions 
(SO2 and flow monitors).

    (a) Coal-fired units. The owner or operator shall meet the general 
operating requirements in Sec. 75.10 for an SO2 continuous 
emission monitoring system and a flow monitoring system for each 
affected coal-fired unit while the unit is combusting coal and/or any 
other fuel, except as provided in paragraph (e) of this section, in 
Sec. 75.16, and in subpart E of this part. During hours in which only 
natural gas or gaseous fuel with a total sulfur content no greater than 
the total sulfur content of natural gas (i.e.,  20 grains 
per 100 standard cubic feet (gr/100 scf)) is combusted in the unit, the 
owner or operator shall comply with the applicable provisions of 
paragraph (e)(1), (e)(2), or (e)(3) of this section.
    (b) Moisture correction. Where SO2 concentration is 
measured on a dry basis, the owner or operator shall install, operate, 
maintain, and quality assure a continuous moisture monitoring system 
for measuring and recording the moisture content of the flue gases, in 
order to correct the measured hourly volumetric flow rates for moisture 
when calculating SO2 mass emissions (in lb/hr) using the 
procedures in appendix F to this part. The following continuous 
moisture monitoring systems are acceptable: a continuous moisture 
sensor; an oxygen analyzer (or analyzers) capable of measuring 
O2 both on a wet basis and on a dry basis; or a stack 
temperature sensor and a moisture look-up table, i.e., a psychrometric 
chart (for saturated gas streams following wet scrubbers, only). The 
moisture monitoring system shall include as a component the automated 
data acquisition and handling system (DAHS) for recording and reporting 
both the raw data (e.g., hourly average wet and dry-basis O2 
values) and the hourly average values of the stack gas moisture content 
derived from those data. When a moisture look-up table is used, the 
moisture monitoring system shall be represented as a single component, 
the certified DAHS, in the monitoring plan for the unit or common 
stack.
* * * * *
    (d) * * *
    (1) By meeting the general operating requirements in Sec. 75.10 for 
an SO2 continuous emission monitoring system

[[Page 28121]]

and flow monitoring system. If this option is selected, the owner or 
operator shall comply with the applicable provisions in paragraph 
(e)(1), (e)(2), or (e)(3) of this section during hours in which the 
unit combusts only natural gas (or gaseous fuel with a total sulfur 
content no greater than the total sulfur content of natural gas);
    (2) By providing other information satisfactory to the 
Administrator using the applicable procedures specified in appendix D 
to this part for estimating hourly SO2 mass emissions. 
Appendix D shall not, however, be used when the unit combusts gaseous 
fuel with a total sulfur content greater than the total sulfur content 
of natural gas (i.e., > 20 gr/100 scf); when such fuel is burned, the 
owner or operator shall comply with the provisions of paragraph (e)(4) 
of this section; or
    (3) By using the low mass emissions excepted methodology in 
Sec. 75.19(c) for estimating hourly SO2 mass emissions if 
the affected unit qualifies as a low mass emissions unit under 
Sec. 75.19(a) and (b).
    (e) * * *
    (2) When gaseous fuel with a total sulfur content no greater than 
the total sulfur content of natural gas (i.e.,  20 gr/100 
scf) is combusted in the unit, the owner or operator may, in lieu of 
operating and recording data from the SO2 monitoring system, 
determine SO2 emissions by certifying an excepted monitoring 
system in accordance with Sec. 75.20 and with appendix D to this part, 
by following the fuel sampling and analysis procedures in section 2.3.1 
of appendix D to this part, by meeting the recordkeeping requirements 
of Sec. 75.55 or Sec. 75.58, as applicable, and by meeting all quality 
control and quality assurance requirements for fuel flowmeters in 
appendix D to this part. If this compliance option is selected, the 
hourly unit heat input reported under Sec. 75.54(b)(5) or 
Sec. 75.57(b)(5), as applicable, shall be determined using a certified 
flow monitoring system and a certified diluent monitor, in accordance 
with the procedures in section 5.2 of appendix F of this part. The flow 
monitor and diluent monitor shall meet all of the applicable quality 
control and quality assurance requirements of appendix B of this part.
    (3) When gaseous fuel with a total sulfur content no greater than 
the total sulfur content of natural gas (i.e.,  20 gr/100 
scf) is burned in the unit, the owner or operator may determine 
SO2 mass emissions by using a certified SO2 
continuous monitoring system, in conjunction with a certified flow rate 
monitoring system. However, on and after January 1, 2000, the 
SO2 monitoring system shall be subject to the following 
provisions; prior to January 1, 2000, the owner or operator may comply 
with these provisions:
* * * * *
    (ii) The calibration response of the SO2 monitoring 
system shall be adjusted, either automatically or manually, in 
accordance with the procedures for routine calibration adjustments in 
section 2.1.3 of appendix B to this part, whenever the zero-level 
calibration response during a required daily calibration error test 
exceeds the applicable performance specification of the instrument in 
section 3.1 of appendix A to this part (i.e.,  2.5 percent 
of the span value or  5 ppm, whichever is less 
restrictive). This calibration adjustment is optional if gaseous fuel 
is burned in the affected unit only during unit startup.
* * * * *
    (iv) In accordance with the requirements of section 2.1.1.2 of 
appendix A to this part, for units that sometimes burn natural gas (or 
gaseous fuel with a total sulfur content no greater than the total 
sulfur content of natural gas) and at other times burn higher-sulfur 
fuel(s) such as coal or oil, a second low-scale SO2 
measurement range is not required when natural gas (or gaseous fuel 
with a total sulfur content no greater than the total sulfur content of 
natural gas) is combusted. For units that burn only natural gas (or 
gaseous fuel with a total sulfur content no greater than the total 
sulfur content of natural gas) and burn no other type(s) of fuel(s), 
the owner or operator shall set the span of the SO2 
monitoring system to a value no greater than 200 ppm.
    (4) During any hours in which a unit combusts only gaseous fuel(s) 
with a total sulfur content no greater than the total sulfur content of 
natural gas (i.e.,  20 gr/100 scf), the owner or operator 
shall meet the general operating requirements in Sec. 75.10 for an 
SO2 continuous emission monitoring system and a flow 
monitoring system.
* * * * *
    14. Section 75.12 is amended by revising the title; by 
redesignating existing paragraphs (b), (c), and (d) as paragraphs (c), 
(d), and (f), respectively; by adding new paragraphs (b) and (e); and 
by revising the newly designated paragraph (c), to read as follows:


Sec. 75.12  Specific provisions for monitoring NOX emission 
rate (NOX and diluent gas monitors).

* * * * *
    (b) Moisture correction. If a correction for the stack gas moisture 
content is needed to properly calculate the NOX emission 
rate in lb/mmBtu, i.e., if the NOX pollutant concentration 
monitor measures on a different moisture basis from the diluent 
monitor, the owner or operator shall install, operate, maintain, and 
quality assure a continuous moisture monitoring system, as defined in 
Sec. 75.11(b).
    (c) Determination of NOX emission rate. The owner or 
operator shall calculate hourly, quarterly, and annual NOX 
emission rates (in lb/mmBtu) by combining the NOX 
concentration (in ppm), diluent concentration (in percent O2 
or CO2), and percent moisture (if applicable) measurements 
according to the procedures in appendix F to this part.
* * * * *
    (e) Low mass emissions units. Notwithstanding the requirements of 
Secs. 75.12(a) and (c), the owner or operator of an affected unit that 
qualifies as a low mass emissions unit under Sec. 75.19(a) and (b) 
shall comply with one of the following:
    (1) Meet the general operating requirements in Sec. 75.10 for a 
NOX continuous emission monitoring system;
    (2) Meet the requirements specified in paragraph (d)(2) of this 
section for using the excepted monitoring procedures in appendix E to 
this part, if applicable; or
    (3) Use the low mass emissions excepted methodology in 
Sec. 75.19(c) for estimating hourly NOX emission rate and 
hourly NOX mass emissions.
* * * * *
    15. Section 75.13 is amended by revising paragraphs (a) and (c) and 
by adding paragraph (d) to read as follows:


Sec. 75.13  Specific provisions for monitoring CO2 
emissions.

    (a) CO2 continuous emission monitoring system. If the 
owner or operator chooses to use the continuous emission monitoring 
method, then the owner or operator shall meet the general operating 
requirements in Sec. 75.10 for a CO2 continuous emission 
monitoring system and flow monitoring system for each affected unit. 
The owner or operator shall comply with the applicable provisions 
specified in Secs. 75.11(a) through (e) or Sec. 75.16, except that the 
phrase ``SO2 continuous emission monitoring system'' is 
replaced with ``CO2 continuous emission monitoring system,'' 
the phrase ``SO2 concentration'' is replaced with 
``CO2 concentration,'' the term ``maximum potential 
concentration of SO2'' is replaced with ``maximum potential 
concentration of CO2,'' and the phrase ``SO2 mass 
emissions'' is replaced with ``CO2 mass emissions.''
* * * * *
    (c) Determination of CO2 mass emissions using an O2 
monitor

[[Page 28122]]

according to appendix F. If the owner or operator chooses to use the 
appendix F method, then the owner or operator may determine hourly 
CO2 concentration and mass emissions with a flow monitoring 
system; a continuous O2 concentration monitor; fuel F and 
Fc factors; and, where O2 concentration is 
measured on a dry basis, a continuous moisture monitoring system, as 
defined in Sec. 75.11(b), using the methods and procedures specified in 
appendix F to this part. For units using a common stack, multiple 
stack, or bypass stack, the owner or operator may use the provisions of 
Sec. 75.16, except that the phrase ``SO2 continuous emission 
monitoring system'' is replaced with ``CO2 continuous 
emission monitoring system,'' the term ``maximum potential 
concentration of SO2'' is replaced with ``maximum potential 
concentration of CO2,'' and the phrase ``SO2 mass 
emissions'' is replaced with ``CO2 mass emissions.''
    (d) Determination of CO2 mass emissions from low mass 
emissions units. The owner or operator of a unit that qualifies as a 
low mass emissions unit under Secs. 75.19(a) and (b) shall comply with 
one of the following:
    (1) Meet the general operating requirements in Sec. 75.10 for a 
CO2 continuous emission monitoring system and flow 
monitoring system;
    (2) Meet the requirements specified in paragraph (b) or (c) of this 
section for use of the methods in appendix G or F to this part, 
respectively; or
    (3) Use the low mass emissions excepted methodology in 
Sec. 75.19(c) for estimating hourly CO2 mass emissions.
    16. Section 75.16 is amended by:
    a. Revising paragraphs (b)(2)(ii)(B), (b)(2)(ii)(D), (d)(2), and 
(e)(1);
    b. Removing paragraphs (e)(2) and (e)(3);
    c. Redesignating existing paragraphs (e)(4) and (e)(5) as 
paragraphs (e)(2) and (e)(3), respectively;
    d. Revising the last sentence and adding a new sentence to the end 
of the newly designated paragraph (e)(3); and
    e. Adding a new paragraph (e)(4), to read as follows:


Sec. 75.16  Special provisions for monitoring emissions from common, 
bypass, and multiple stacks for SO2 emissions and heat input 
determinations.

* * * * *
    (b) * * *
    (2) * * *
    (ii) * * *
    (B) Install, certify, operate, and maintain an SO2 
continuous emission monitoring system and flow monitoring system in the 
duct from each nonaffected unit; determine SO2 mass 
emissions from the affected units as the difference between 
SO2 mass emissions measured in the common stack and 
SO2 mass emissions measured in the ducts of the nonaffected 
units, not to be reported as an hourly average value less than zero; 
combine emissions for the Phase I and Phase II affected units for 
recordkeeping and compliance purposes; calculate and report 
SO2 mass emissions from the Phase I and Phase II affected 
units, pursuant to an approach approved by the Administrator, such that 
these emissions are not underestimated; or
* * * * *
    (D) Petition through the designated representative and provide 
information satisfactory to the Administrator on methods for 
apportioning SO2 mass emissions measured in the common stack 
to each of the units using the common stack and on reporting the 
SO2 mass emissions. The Administrator may approve such 
demonstrated substitute methods for apportioning and reporting 
SO2 mass emissions measured in a common stack whenever the 
demonstration ensures that there is a complete and accurate accounting 
of all emissions regulated under this part and, in particular, that the 
emissions from any affected unit are not underestimated.
* * * * *
    (d) * * *
    (2) Install, certify, operate, and maintain an SO2 
continuous emission monitoring system and flow monitoring system in 
each stack. Determine SO2 mass emissions from each affected 
unit as the sum of the SO2 mass emissions recorded for each 
stack. Notwithstanding the prior sentence, if another unit also 
exhausts flue gases to one or more of the stacks, the owner or operator 
shall also comply with the applicable common stack requirements of this 
section to determine and record SO2 mass emissions from the 
units using that stack and shall calculate and report SO2 
mass emissions from the affected units and stacks, pursuant to an 
approach approved by the Administrator, such that these emissions are 
not underestimated.
    (e) * * *
    (1) The owner or operator of an affected unit using a common stack, 
bypass stack, or multiple stack with a diluent monitor and a flow 
monitor on each stack may choose to install monitors to determine the 
heat input for the affected unit, wherever flow and diluent monitor 
measurements are used to determine the heat input, using the procedures 
specified in paragraphs (a) through (d) of this section, except that 
the terms ``SO2 mass emissions'' and ``emissions'' are 
replaced with the term ``heat input'' and the phrase ``SO2 
continuous emission monitoring system and flow monitoring system'' is 
replaced with the phrase ``a diluent monitor and a flow monitor.'' The 
applicable equation in appendix F to this part shall be used to 
calculate the heat input from the hourly flow rate, diluent monitor 
measurements, and (if the equation in appendix F requires a correction 
for the stack gas moisture content) hourly moisture measurements. 
Notwithstanding the options for combining heat input in paragraphs 
(a)(1)(ii), (a)(2)(ii), (b)(1)(ii), and (b)(2)(ii) of this section, the 
owner or operator of an affected unit with a diluent monitor and a flow 
monitor installed on a common stack to determine the combined heat 
input at the common stack shall also determine and report heat input to 
each individual unit.
* * * * *
    (3) * * * The heat input may be apportioned either by using the 
ratio of load (in MWe-hr) for each individual unit to the total load 
for all units utilizing the common stack or by using the ratio of steam 
flow (in 1000 lb) for each individual unit to the total steam flow for 
all units utilizing the common stack. The heat input should be 
apportioned according to the procedures in appendix F to this part.
    (4) Notwithstanding paragraph (e)(1) of this section, any affected 
unit that is using the procedures in this part to meet the monitoring 
and reporting requirements of a State or federal NOX mass 
emission reduction program must also meet the requirements for 
monitoring heat input in Secs. 75.71 and 75.72.
    17. Section 75.17 is amended by adding introductory text before 
paragraph (a) and by revising paragraph (a)(2)(i)(C) to read as 
follows:


Sec. 75.17  Specific provisions for monitoring emissions from common, 
by-pass, and multiple stacks for NOX emission rate.

    Notwithstanding the provisions of paragraphs (a), (b), and (c) of 
this section, the owner or operator of an affected unit that is using 
the procedures in this part to meet the monitoring and reporting 
requirements of a State or federal NOX mass emission 
reduction program must also meet the provisions for monitoring 
NOX emission rate in Secs. 75.71 and 75.72.
    (a) * * *
    (2) * * *
    (i) * * *
    (C) Each unit's compliance with the applicable NOX 
emission limit will be determined by a method satisfactory to

[[Page 28123]]

the Administrator for apportioning to each of the units the combined 
NOX emission rate (in lb/mmBtu) measured in the common stack 
and for reporting the NOX emission rate, as provided in a 
petition submitted by the designated representative. The Administrator 
may approve such demonstrated substitute methods for apportioning and 
reporting NOX emission rate measured in a common stack 
whenever the demonstration ensures that there is a complete and 
accurate estimation of all emissions regulated under this part and, in 
particular, that the emissions from any unit with a NOX 
emission limitation are not underestimated.
* * * * *
    18. Section 75.19 is added to subpart B to read as follows:


Sec. 75.19  Optional SO2, NOX, and CO2 
emissions calculation for low mass emissions units.

    (a) Applicability. (1) Consistent with the requirements of 
paragraphs (a)(2) and (b) of this section, the low mass emissions 
excepted methodology in paragraph (c) of this section may be used in 
lieu of continuous emission monitoring systems or, if applicable, in 
lieu of excepted methods under appendix D or E to this part, for the 
purpose of determining hourly heat input, hourly NOX 
emission rate, and hourly NOX, SO2, and 
CO2 mass emissions from a low mass emissions unit. A low 
mass emissions unit is a gas-fired or oil-fired unit that burns only 
natural gas and/or fuel oil and that:
    (i) Emits no more than 25 tons of SO2 annually and no 
more than 25 tons of NOX annually; and
    (ii) Has calculated emissions of no more than 25 tons of 
SO2 annually and no more than 25 tons of NOX 
annually based on the maximum rated hourly heat input, the actual 
operating time for each fuel burned, and the low mass emissions 
excepted methodology, calculations, and values in paragraph (c) of this 
section.
    (2) A unit may initially qualify as a low mass emissions unit only 
under the following circumstances:
    (i) The designated representative provides historical actual and 
calculated emissions data from the previous three calendar years 
immediately prior to the submission of an application to use the low 
mass emissions excepted methodology, and the data demonstrates to the 
satisfaction of the Administrator that the unit meets the criteria in 
paragraphs (a)(1)(i) and (ii) of this section; or
    (ii) If a unit does not have the historical data required in 
paragraph (a)(2)(i) of this section for any one or more of the previous 
three calendar years, the designated representative submits:
    (A) Any historical annual emissions and operating data, as required 
in paragraphs (a)(1)(i) and (a)(1)(ii) of this section, beginning with 
the unit's first calendar year of commercial operation, and the data 
demonstrates to the satisfaction of the Administrator that the unit 
meets the criteria in paragraphs (a)(1)(i) and (a)(1)(ii) of this 
section; and
    (B) A demonstration satisfactory to the Administrator that the unit 
will continue to qualify as a low mass emissions unit under the 
requirements of this paragraph (a). The demonstration shall include any 
historical emissions and operating data for less than a calendar year 
for the unit and projected emissions information for the unit, as 
determined using projected operating hours and fuel usage, and the low 
mass emissions excepted methodology, calculations, and values in 
paragraph (c) of this section.
    (b) Disqualification. If a unit that initially qualifies as a low 
mass emissions units under this section changes the fuel that is burned 
in the unit such that a fuel other than natural gas or fuel oil is 
combusted in the unit, the unit is disqualified from using the low mass 
emissions excepted methodology as of the first hour that the new fuel 
is combusted in the unit. In addition, if a unit that initially 
qualifies as a low mass emissions unit under this section emits more 
than 25 tons of SO2 or 25 tons of NOX in any 
calendar year or has calculated emissions greater than 25 tons of 
SO2 or 25 tons of NOX in any calendar year, as 
determined using the low mass emission equations in paragraph (c) of 
this section, the owner or operator of the unit shall have two quarters 
from the end of the quarter in which the exceedance occurs to install, 
certify, and report SO2, NOX, and CO2 
from monitoring systems that meet the requirements of Secs. 75.11, 
75.12, and 75.13, respectively. The unit shall be disqualified as a low 
mass emissions unit as of the end of the second quarter following the 
quarter in which either of the 25 ton limits was exceeded. A unit that 
has been disqualified from using the low mass emissions excepted 
methodology may subsequently qualify again as a low mass emissions unit 
under paragraph (a)(2) of this section, provided that if such unit 
qualified under paragraph (a)(2)(ii) of this section, the unit may 
subsequently qualify again if the unit meets the requirements of 
paragraph (a)(2)(i) of this section.
    (c) Low mass emissions excepted methodology, calculations, and 
values.--(1) Operating time. (i) Report an hourly record if the unit 
operated for any portion of the hour or if records are missing, as to 
whether or not the unit operated for any portion of that hour.
    (ii) Quarterly operating time (hr) is equal to the sum of all of 
the reported operating hours in the quarter, such that any hour in 
which the unit combusted fuel for any portion of the hour is considered 
a full hour.
    (iii) Year-to-date cumulative operating time (hr) is equal to the 
sum of all of the reported operating hours in the year to date, such 
that any hour in which the unit combusted fuel for any portion of the 
hour is considered a full hour.
    (2) Heat input. (i) Hourly heat input (mmBtu) is equal to the 
maximum rated hourly heat input, as defined in Sec. 72.2 of this 
chapter. However, the owner or operator of an affected unit may 
petition the Administrator under Sec. 75.66 for a lower value for 
maximum rated hourly heat input than that defined in Sec. 72.2 of this 
chapter. The Administrator may approve such lower value if the owner or 
operator demonstrates that either the maximum hourly heat input 
specified by the manufacturer or the highest observed hourly heat 
input, or both, are not representative of the unit's current 
capabilities because modifications have been made to the unit, limiting 
its capacity permanently.
    (ii) Calculate the quarterly total heat input (mmBtu) using 
Equation 7a as follows:

HIqtr = Tqtr  x  HIhr

(Eq. 7a)
where:

Tqtr = Actual number of operating hours in the quarter, in 
hr.
HIhr = Hourly heat input under paragraph (c)(2)(i) of this 
section, in mmBtu.

    (iii) Calculate the year-to-date cumulative heat input (mmBtu) as 
the sum of all of the hourly heat input values in the year to date.
    (3) SO2. (i) Calculate the hourly total SO2 
mass emissions (lbs) using Equation 7b and the appropriate fuel-based 
SO2 emission factor from Table 1a for the fuel being burned 
in that hour. If more than one fuel is burned in the hour, use the 
highest emission factor for all of the fuels burned in the hour. If 
records are missing as to which fuel was burned in the hour, use the 
highest emission factor for all of the fuels capable of being burned in 
that unit.

    Table 1a.--SO2 Emission Factors (lb/mmBtu) for Various Fuel Types   
------------------------------------------------------------------------
                 Fuel type                      SO2 Emission factors    
------------------------------------------------------------------------
Pipeline Natural Gas......................  0.0006 lb/mmBtu.            

[[Page 28124]]

                                                                        
Natural Gas...............................  0.06 lb/mmBtu.              
Residual Oil..............................  2.1 lb/mmBtu.               
Diesel Fuel...............................  0.5 lb/mmBtu.               
------------------------------------------------------------------------

WSO2 = EFSO2 x HIhr

(Eq. 7b)

Where:

WSO2 = SO2 mass emissions, in lbs.
EFSO2 = Fuel-based SO2 emission factor 
from Table 1a of this section, in lb/mmBtu.
HIhr = Hourly heat input under paragraph (c)(2)(i) of this 
section, in mmBtu.

    (ii) Calculate the quarterly total SO2 mass emissions 
(tons) by summing all of the hourly SO2 mass emissions under 
paragraph (c)(3)(i) of this section in the quarter and dividing by 2000 
lb/ton.
    (iii) Calculate the year-to-date cumulative SO2 mass 
emissions (tons) by summing all of the SO2 mass emissions 
under paragraph (c)(3)(i) of this section in the year to date.
    (4) NOX. (i) Determine the hourly NOX 
emission rate (lb/mmBtu) by using the appropriate fuel and boiler type 
default NOX emission rate in Table 1b for the fuel being 
burned in that hour. If more than one fuel is burned in the hour, use 
the highest emission rate for all of the fuels burned in the hour. If 
records are missing as to which fuel was burned in the hour, use the 
highest emission factor for all of the fuels capable of being burned in 
that unit.

 Table 1b.--NOX Emission Rates (lb/mmBtu) for Various Boiler/Fuel Types 
------------------------------------------------------------------------
                                                                 NOX    
            Boiler type                     Fuel type          Emission 
                                                                 rate   
------------------------------------------------------------------------
Tangentially fired.................  Oil...................        0.366
Tangentially fired.................  Gas...................        0.290
Dry Bottom Wall fired..............  Oil...................        0.490
Dry Bottom Wall fired..............  Gas...................        0.400
Combustion Turbine.................  Oil...................        0.258
Combustion Turbine.................  Gas...................        0.172
Combined Cycle.....................  Oil...................        0.273
Combined Cycle.....................  Gas...................        0.273
------------------------------------------------------------------------

    (ii) Calculate the hourly total NOX mass emissions (lbs) 
as the product of the NOX emission rate (lb/mmBtu) and 
hourly heat input (mmBtu), using Equation 7c as follows:

WNOX = EFNOX  x  HIhr

(Eq. 7c)
where:

WNOX = NOX mass emissions, in lbs.
EFNOX = Boiler-type and fuel-type NOX emission 
factor from Table 1b of this section, in lb/mmBtu.
HIhr = Hourly heat input under paragraph (c)(2)(i) of this 
section, in mmBtu.

    (iii) Calculate the quarterly average NOX emission rate 
(lb/mmBtu) by summing all of the hourly NOX emission rates 
for the quarter and dividing the total by the number of reported 
operating hours under paragraph (c)(1)(i) of this section in the 
quarter.
    (iv) Calculate the quarterly total NOX mass emissions 
(tons) by summing all of the hourly NOX mass emissions under 
paragraph (c)(4)(ii) of this section in the quarter and dividing the 
total by 2000 lb/ton.
    (v) Calculate the year-to-date cumulative average NOX 
emission rate (lb/mmBtu) by summing all of the hourly NOX 
emission rates for all of the hours in the year to date and dividing 
the total by the number of reported operating hours under paragraph 
(c)(1)(i) of this section in the year to date.
    (vi) Calculate the year-to-date cumulative NOX mass 
emissions total (tons) by summing all of the hourly NOX mass 
emissions under paragraph (c)(4)(ii) of this section in the year to 
date.
    (5) CO2. (i) Calculate the hourly total CO2 
mass emissions (tons) using Equation 7d and the appropriate fuel-based 
CO2 emission factor from Table 1c for the fuel being burned 
in that hour. If more than one fuel is burned in the hour, use the 
highest emission factor for all of the fuels burned in the hour. If 
records are missing as to which fuel was burned in the hour, use the 
highest emission factor for all of the fuels capable of being burned in 
that unit.

       Table 1c.--CO2 Emission Factors (ton/mmBtu) for Gas and Oil      
------------------------------------------------------------------------
                 Fuel type                      CO2 emission factors    
------------------------------------------------------------------------
Natural Gas...............................  0.059 ton/mmBtu.            
Oil.......................................  0.081 ton/mmBtu.            
------------------------------------------------------------------------

WCO2=EFCO2  x  HIhr

(Eq. 7d)

Where:

WCO2 = CO2 mass emissions, in tons.
EFCO2 = Fuel-based CO2 emission factor from Table 
1c, in ton/mmBtu.
HIhr = Hourly heat input under paragraph (c)(2)(i) of this 
section, in mmBtu.

    (ii) Calculate the quarterly total CO2 mass emissions 
(tons) by summing all of the hourly CO2 mass emissions under 
paragraph (c)(5)(i) of this section in the quarter.
    (iii) Calculate the year-to-date cumulative CO2 mass 
emissions (tons) by summing all of the hourly CO2 mass 
emissions under paragraph (c)(5)(i) of this section in the year to 
date.
    (d) The quality control and quality assurance requirements in 
Sec. 75.21 are not required for a low mass emissions unit for which the 
optional low mass emissions excepted methodology in paragraph (c) of 
this section is being used in lieu of a continuous emission monitoring 
system or an excepted monitoring system under appendix D or E to this 
part.

Subpart C--[Amended]

    19. Section 75.20 is amended by:
    a. Revising the title of the section;
    b. Revising the titles of paragraphs (a)(3), (a)(4), (c), (d), (g), 
(g)(1), (g)(2), (g)(4), and (g)(5);
    c. Revising paragraphs (a) introductory text, (a)(1), (a)(3), 
(a)(4) introductory text, (a)(4)(i), (a)(4)(ii), (a)(4)(iii), 
(a)(5)(i), (b), (c) introductory text, (c)(1)(iii), (d)(1), (d)(2), (g) 
introductory text, (g)(1) introductory text, (g)(1)(i), (g)(2), (g)(4), 
and (g)(5);
    d. Removing existing paragraph (c)(3);
    e. Revising and redesignating existing paragraphs (c)(4), (c)(5), 
(c)(6), (c)(7), and (c)(8) as paragraphs (c)(3), (c)(4), (c)(8), 
(c)(9), and (c)(10), respectively; and revising newly designated 
paragraphs (c)(4) introductory text, (c)(8) introductory text, 
(c)(8)(i),

[[Page 28125]]

(c)(9)(ii), and (c)(10) introductory text; and
    f. Adding new paragraphs (c)(5), (c)(6), (c)(7), (g)(6), (g)(7), 
(h), and (i), to read as follows:


Sec. 75.20  Initial certification and recertification procedures.

    (a) Initial certification approval process. The owner or operator 
shall ensure that each continuous emission or opacity monitoring system 
required by this part, which includes the automated data acquisition 
and handling system, and, where applicable, the CO2 
continuous emission monitoring system, meets the initial certification 
requirements of this section and shall ensure that all applicable 
initial certification tests under paragraph (c) of this section are 
completed by the deadlines specified in Sec. 75.4 and prior to use in 
the Acid Rain Program. In addition, whenever the owner or operator 
installs a continuous emission or opacity monitoring system in order to 
meet the requirements of Secs. 75.13 through 75.18, where no continuous 
emission or opacity monitoring system was previously installed, initial 
certification is required.
    (1) Notification of initial certification test dates. The owner or 
operator or designated representative shall submit a written notice of 
the dates of initial certification testing at the unit as specified in 
Sec. 75.61(a)(1).
* * * * *
    (3) Provisional approval of certification (or recertification) 
applications. Upon the successful completion of the required 
certification (or recertification) procedures of this section for each 
continuous emission or opacity monitoring system or component thereof, 
each continuous emission or opacity monitoring system or component 
thereof shall be deemed provisionally certified (or recertified) for 
use under the Acid Rain Program for a period not to exceed 120 days 
following receipt by the Administrator of the complete certification 
(or recertification) application under paragraph (a)(4) of this 
section, provided that no continuous emission or opacity monitor 
systems for a combustion source seeking to enter the Opt-in Program in 
accordance with part 74 of this chapter shall be deemed provisionally 
certified (or recertified) for use under the Acid Rain Program. Data 
measured and recorded by a provisionally certified (or recertified) 
continuous emission or opacity monitoring system or component thereof, 
in accordance with the requirements of appendix B to this part, will be 
considered valid quality-assured data (retroactive to the date and time 
of provisional certification or recertification)), provided that the 
Administrator does not invalidate the provisional certification (or 
recertification) by issuing a notice of disapproval within 120 days of 
receipt by the Administrator of the complete certification (or 
recertification) application. Note that if the data validation 
procedures of paragraph (b)(3) of this section are applied to the 
initial certification (or recertification) of a continuous emissions 
monitoring system, it is possible for data recorded by the CEMS during 
the certification (or recertification) test period to be quality 
assured retrospectively, upon completion of all of the certification 
(or recertification) tests. Therefore, in certain instances, the date 
and time of provisional certification (or recertification) of the CEMS 
may be earlier than the date and time of completion of the required 
certification (or recertification) tests.
    (4) Certification (or recertification) application formal approval 
process. The Administrator will issue a notice of approval or 
disapproval of the certification (or recertification) application to 
the owner or operator within 120 days of receipt of the complete 
certification (or recertification) application. In the event the 
Administrator does not issue such a written notice within 120 days of 
receipt, each continuous emission or opacity monitoring system which 
meets the performance requirements of this part and is included in the 
certification (or recertification) application will be deemed certified 
(or recertified) for use under the Acid Rain Program.
    (i) Approval notice. If the certification (or recertification) 
application is complete and shows that each continuous emission or 
opacity monitoring system meets the performance requirements of this 
part, then the Administrator will issue a written notice of approval of 
the certification (or recertification) application within 120 days of 
receipt.
    (ii) Incomplete application notice. A certification (or 
recertification) application will be considered complete when all of 
the applicable information required to be submitted in Sec. 75.63 has 
been received by the Administrator, the EPA Regional Office, and the 
appropriate State and/or local air pollution control agency. If the 
certification (or recertification) application is not complete, then 
the Administrator will issue a written notice of incompleteness that 
provides a reasonable timeframe for the designated representative to 
submit the additional information required to complete the 
certification (or recertification) application. If the designated 
representative has not complied with the notice of incompleteness by a 
specified due date, then the Administrator may issue a notice of 
disapproval specified under paragraph (a)(4)(iii) of this section. The 
120-day review period shall not begin prior to receipt of a complete 
application.
    (iii) Disapproval notice. If the certification (or recertification) 
application shows that any continuous emission or opacity monitoring 
system or component thereof does not meet the performance requirements 
of this part, or if the certification (or recertification) application 
is incomplete and the requirement for disapproval under paragraph 
(a)(4)(ii) of this section has been met, the Administrator shall issue 
a written notice of disapproval of the certification (or 
recertification) application within 120 days of receipt. By issuing the 
notice of disapproval, the provisional certification (or 
recertification) is invalidated by the Administrator, and the data 
measured and recorded by each uncertified continuous emission or 
opacity monitoring system or component thereof shall not be considered 
valid quality-assured data beginning with the following time: from the 
hour of the probationary calibration error test that began the initial 
certification (or recertification) test period, if the data validation 
procedures of paragraph (b)(3) of this section were used to 
retrospectively validate data; or from the date and time of completion 
of the invalid certification tests until the date and time that the 
owner or operator completes subsequently approved initial certification 
tests, if the data validation procedures of paragraph (b)(3) of this 
section were not used. The owner or operator shall follow the 
procedures for loss of initial certification in paragraph (a)(5) of 
this section for each continuous emission or opacity monitoring system 
or component thereof which is disapproved for initial certification. 
For each disapproved recertification, the owner or operator shall 
follow the procedures of paragraph (b)(5) of this section.
* * * * *
    (5) * * *
    (i) Until such time, date, and hour as the continuous emission 
monitoring system or component thereof can be adjusted, repaired, or 
replaced and certification tests successfully completed, the owner or 
operator shall substitute the following values, as applicable, for each 
hour of unit operation during the period of invalid

[[Page 28126]]

data specified in paragraph (a)(4)(iii) of this section or in 
Sec. 75.21: the maximum potential concentration of SO2 as 
defined in section 2.1.1.1 of appendix A to this part to report 
SO2 concentration; the maximum potential NOX 
emission rate, as defined in Sec. 72.2 of this chapter to report 
NOX emissions; the maximum potential flow rate, as defined 
in section 2.1.4.1 of appendix A to this part to report volumetric 
flow; or the maximum potential concentration of CO2, as 
defined in section 2.1.3.1 of appendix A to this part to report 
CO2 concentration data; and
* * * * *
    (b) Recertification approval process. Whenever the owner or 
operator makes a replacement, modification, or change in a certified 
continuous emission monitoring system or continuous opacity monitoring 
system that is determined by the Administrator to significantly affect 
the ability of the system to accurately measure or record the 
SO2 or CO2 concentration, stack gas volumetric 
flow rate, NOX emission rate, or opacity, or to meet the 
requirements of Sec. 75.21 or appendix B to this part, the owner or 
operator shall recertify the continuous emission monitoring system or 
continuous opacity monitoring system, according to the procedures in 
this paragraph. Furthermore, whenever the owner or operator makes a 
replacement, modification, or change to the flue gas handling system or 
the unit operation that is determined by the Administrator to 
significantly change the flow or concentration profile, the owner or 
operator shall recertify the monitoring system according to the 
procedures in this paragraph. Examples of changes which require 
recertification include: replacement of the analyzer; change in 
location or orientation of the sampling probe or site; changing of flow 
rate monitor polynomial coefficients; and complete replacement of an 
existing continuous emission monitoring system or continuous opacity 
monitoring system. The owner or operator shall recertify a continuous 
opacity monitoring system whenever the monitor path length changes or 
as required by an applicable State or local regulation or permit. Any 
change to a stack flow rate or gas monitoring system for which the 
Administrator determines that a RATA is not necessary shall not be 
considered a recertification event. In such cases, any other tests that 
the Administrator determines to be necessary (linearity checks, 
calibration error tests, DAHS verifications, etc.) shall be performed 
as diagnostic tests, rather than recertification tests. The data 
validation procedures in paragraph (b)(3) of this section shall be 
applied to linearity checks, 7-day calibration error tests, and cycle 
time tests when these are required as diagnostic tests. When the data 
validation procedures of paragraph (b)(3) of this section are applied 
in this manner, replace the word ``recertification'' with the word 
``diagnostic.''
    (1) Tests required. For recertification testing after changing the 
flow rate monitor polynomial coefficients, the owner or operator shall 
complete a 3-level RATA. For all other recertification testing, the 
owner or operator shall complete all initial certification tests in 
paragraph (c) of this section that are applicable to the monitoring 
system, except as otherwise approved by the Administrator.
    (2) Notification of recertification test dates. The owner, 
operator, or designated representative shall submit notice of testing 
dates for recertification under this paragraph as specified in 
Sec. 75.61(a)(1)(ii), unless all of the tests in paragraph (c) of this 
section are required for recertification, in which case the owner or 
operator shall provide notice in accordance with the notice provisions 
for initial certification testing in Sec. 75.61(a)(1)(i).
    (3) Recertification test period requirements and data validation. 
(i) In the period extending from the hour of the replacement, 
modification or change made to a monitoring system that triggers the 
need to perform recertification test(s) of the CEMS to the hour of 
successful completion of a probationary calibration error test 
(according to paragraph (b)(3)(ii) of this section) following the 
replacement, modification, or change to the CEMS, the owner or operator 
shall either substitute for missing data, according to the standard 
missing data procedures in Secs. 75.33 through 75.37, or report 
emission data using a reference method or another monitoring system 
that has been certified or approved for use under this part.
    (ii) Once the modification or change to the CEMS has been completed 
and all of the associated repairs, component replacements, adjustments, 
linearization, and reprogramming of the CEMS have been completed, a 
probationary calibration error test is required to establish the 
beginning point of the recertification test period. In this instance, 
the first successful calibration error test of the monitoring system 
following completion of all necessary repairs, component replacements, 
adjustments, reprogramming, and any preliminary tests (e.g., trial RATA 
runs or a challenge of the monitor with calibration gases other than 
those used to perform the daily calibration error test) shall be the 
probationary calibration error test. The probationary calibration error 
test must be passed before any of the required recertification tests 
are commenced.
    (iii) Beginning with the hour of commencement of a recertification 
test period, emission data recorded by the CEMS are considered to be 
conditionally valid, contingent upon the results of the subsequent 
recertification tests.
    (iv) Each required recertification test shall be completed no later 
than the following number of unit operating hours after the 
probationary calibration error test that initiates the test period:
    (A) For a linearity test and/or cycle time test, 168 consecutive 
unit operating hours;
    (B) For a RATA (whether normal-load or multiple-load), 720 
consecutive unit operating hours; and
    (C) For a 7-day calibration error test, 21 consecutive unit 
operating days.
    (v) All recertification tests shall be performed hands-off, as 
follows. No adjustments to the calibration of the CEMS, other than the 
adjustments described in section 2.1.3 of appendix B to this part, are 
permitted prior to or during the recertification test period. Routine 
daily calibration error tests shall be performed throughout the 
recertification test period, in accordance with section 2.1.1 of 
appendix B to this part. The additional calibration error test 
requirements in section 2.1.3 of appendix B to this part shall also 
apply during the recertification test period.
    (vi) If all of the required recertification tests and required 
daily calibration error tests are successfully completed in succession 
with no failures, and if each recertification test is completed within 
the time period specified in paragraph (b)(3)(iv)(A), (B), or (C) of 
this section, then all of the conditionally valid emission data 
recorded by the CEMS shall be considered quality assured, from the hour 
of commencement of the recertification test period until the hour of 
completion of the required test(s).
    (vii) If a required recertification test is failed or aborted due 
to a problem with the CEMS, or if a calibration error test is failed 
during a recertification test period, data validation shall be done as 
follows:
    (A) If any required recertification test is failed, it shall be 
repeated. If any recertification test other than a 7-day calibration 
error test is failed or aborted due to a problem with the CEMS, the 
original recertification test period is ended, and a new 
recertification test period must be commenced with a

[[Page 28127]]

probationary calibration error test. The tests that are required in 
this new recertification test period will include any tests that were 
required for the initial recertification event which were not 
successfully completed and any recertification or diagnostic tests that 
are required as a result of changes made to the monitoring system to 
correct the problems that caused the failure of the recertification 
test. The new recertification test sequence shall not be commenced 
until all necessary maintenance activities, adjustments, 
linearizations, and reprogramming of the CEMS have been completed;
    (B) If a linearity test, RATA, or cycle time test is failed or 
aborted due to a problem with the CEMS, all conditionally valid 
emission data recorded by the CEMS are invalidated, from the hour of 
commencement of the recertification test period to the hour in which 
the test is failed or aborted. Data from the CEMS remain invalid until 
the hour in which a new recertification test period is commenced, 
following corrective action, and a probationary calibration error test 
is passed, at which time the conditionally valid status of emission 
data from the CEMS begins;
    (C) If a 7-day calibration error test is failed within the 
recertification test period, previously-recorded conditionally valid 
emission data from the CEMS are not invalidated, provided that the 
calibration error on the day of the failed 7-day calibration error test 
does not exceed twice the performance specification in section 3 of 
appendix A to this part; and
    (D) If a calibration error test is failed (i.e., the results of the 
test exceed twice the performance specification in section 3 of 
appendix A to this part) during a recertification test period, the CEMS 
is out-of-control as of the hour in which the calibration error test is 
failed. Emission data from the CEMS shall be invalidated prospectively 
from the hour of the failed calibration error test until the hour of 
completion of a subsequent successful calibration error test following 
corrective action, at which time the conditionally valid status of data 
from the monitoring system resumes. Failure to perform a required daily 
calibration error test during a recertification test period shall also 
cause data from the CEMS to be invalidated prospectively, from the hour 
in which the calibration error test was due until the hour of 
completion of a subsequent successful calibration error test. 
Previously-passed recertification tests in the sequence and previously-
recorded conditionally valid data shall not be affected by a late 
calibration error test. Whenever a calibration error test is failed or 
missed during a recertification test period, no further recertification 
tests shall be performed until the required subsequent calibration 
error has been passed, re-establishing the conditionally valid status 
of data from the monitoring system.
    (viii) If any required recertification test is not completed within 
its allotted time period, data validation shall be done as follows. For 
a late linearity test, RATA, or cycle time test that is passed on the 
first attempt, data from the monitoring system shall be invalidated 
from the hour of expiration of the recertification test period until 
the hour of completion of the late test. For a late 7-day calibration 
error test, whether or not it is passed on the first attempt, data from 
the monitoring system shall also be invalidated from the hour of 
expiration of the recertification test period until the hour of 
completion of the late test. For a late linearity test, RATA, or cycle 
time test that is failed on the first attempt or aborted on the first 
attempt due to a problem with the monitor, all conditionally valid data 
from the monitoring system shall be considered invalid back to the hour 
of the first probationary calibration error test which initiated the 
recertification test period. Data from the monitoring system shall 
remain invalid until the hour of successful completion of the late 
recertification test and any additional recertification or diagnostic 
tests that are required as a result of changes made to the monitoring 
system to correct problems that caused failure of the late 
recertification test.
    (ix) If any required recertification test of a monitoring system 
has not been completed by the end of a calendar quarter and if data 
contained in the quarterly report is conditionally valid pending the 
results of test(s) to be completed in a subsequent quarter, the owner 
or operator shall indicate this by means of a suitable conditional data 
flag in the electronic quarterly report for that quarter. The owner or 
operator shall resubmit the report for that quarter if the required 
recertification test is subsequently failed. In the resubmitted report, 
the owner or operator shall use the appropriate missing data routine in 
Sec. 75.31 or Sec. 75.33 to replace with substitute data each hour of 
conditionally valid data that was invalidated by the failed 
recertification test. In addition, if the owner or operator submits any 
conditionally valid data (as defined in Sec. 72.2 of this chapter) in 
any of the four quarterly reports for a given year, the owner or 
operator shall indicate the status of the conditionally valid data 
(i.e., resolved or unresolved) in the annual compliance certification 
report required under Sec. 72.90 of this chapter for that year. 
Alternatively, if any required recertification test is not completed by 
the end of a particular calendar quarter but is completed no later than 
30 days after the end of that quarter (i.e., prior to the deadline for 
submitting the quarterly report under Sec. 75.64), the test data and 
results may be submitted with the earlier quarterly report even though 
the test date(s) are from the next calendar quarter. In such instances, 
if the recertification test(s) are passed in accordance with the 
provisions of paragraph (b)(3) of this section, conditionally valid 
data may be reported as quality-assured, in lieu of reporting a 
conditional data flag. If the recertification test(s) is failed and if 
conditionally valid data are replaced, as appropriate, with substitute 
data, then neither the reporting of a conditional data flag nor 
resubmission is required.
    (x) If the replacement, modification, or change requiring 
recertification of the CEMS is such that the data collected by the 
prior certified monitoring system are no longer representative, such as 
after a change to the flue gas handling system or unit operation that 
requires changing the span value to be consistent with section 2.1 of 
appendix A to this part, the owner or operator shall substitute for 
missing data as follows, in the period extending from the hour of 
commencement of the replacement, modification, or change requiring 
recertification of the CEMS to the hour of commencement of the 
recertification test period:
    (A) For a change that results in a significantly higher 
concentration or flow rate, substitute maximum potential values 
according to the procedures in paragraph (a)(5) of this section; or
    (B) For a change that results in a significantly lower 
concentration or flow rate, substitute data using the standard missing 
data procedures.
    (C) The owner or operator shall then use the initial missing data 
procedures in Sec. 75.31, beginning with the first hour of quality 
assured data obtained with the recertified monitoring system, unless 
otherwise provided by Sec. 75.34 for units with add-on emission 
controls.
    (4) Recertification application. The designated representative 
shall apply for recertification of each continuous emission or opacity 
monitoring system used under the Acid Rain Program. The owner or 
operator shall submit the recertification application in accordance 
with Sec. 75.60, and each complete recertification application shall 
include the information specified in Sec. 75.63.
    (5) Approval or disapproval of request for recertification. The 
procedures for

[[Page 28128]]

provisional certification in paragraph (a)(3) of this section shall 
apply to recertification applications. The Administrator will issue a 
written notice of approval or disapproval according to the procedures 
in paragraph (a)(4) of this section. In the event that a 
recertification application is disapproved, data from the monitoring 
system are invalidated and the applicable missing data procedures in 
Sec. 75.31 or Sec. 75.33 shall be used from the date and hour of 
receipt of such notice back to the hour of the probationary calibration 
error test that began the recertification test period. Data from the 
monitoring system remain invalid until a subsequent probationary 
calibration error test is passed, beginning a new recertification test 
period. The owner or operator shall repeat all recertification tests or 
other requirements, as indicated in the Administrator's notice of 
disapproval, no later than 30 unit operating days after the date of 
issuance of the notice of disapproval. The designated representative 
shall submit a notification of the recertification retest dates, as 
specified in Sec. 75.61(a)(1)(ii), and shall submit a new 
recertification application according to the procedures in paragraph 
(b)(4) of this section.
    (c) Initial certification and recertification procedures. Prior to 
the deadline in Sec. 75.4, the owner or operator shall conduct initial 
certification tests and in accordance with Sec. 75.63, the designated 
representative shall submit an application to demonstrate that the 
continuous emission or opacity monitoring system and components thereof 
meet the specifications in appendix A to this part. The owner or 
operator shall compare reference method values with output from the 
automated data acquisition and handling system that is part of the 
continuous emission monitoring system being tested. Except as specified 
in paragraphs (b)(1), (d), and (e) of this section, the owner or 
operator shall perform the following tests for initial certification or 
recertification of continuous emission or opacity monitoring systems or 
components according to the requirements of appendix A to this part:
    (1) * * *
    (iii) A relative accuracy test audit. For the NOX-
diluent system, the RATA shall be done on a system basis, in units of 
lb/mmBtu.
* * * * *
    (3) The initial certification test data from an O2-or a 
CO2-diluent gas monitor certified for use in a 
NOX continuous emission monitoring system may be submitted 
to meet the requirements of paragraph (c)(4) of this section. Also, for 
a diluent monitor that is used both as a CO2 monitoring 
system and to determine heat input, only one set of diluent monitor 
certification data need be submitted (under the component and system 
identification numbers of the CO2 monitoring system).
    (4) For each CO2 pollutant concentration monitor, each 
O2 monitor which is part of a CO2 continuous 
emission monitoring system, each diluent monitor used to monitor heat 
input and each SO2-diluent continuous emission monitoring 
system:
* * * * *
    (5) For each continuous moisture monitoring system consisting of 
wet-and dry-basis O2 analyzers:
    (i) A 7-day calibration error test of each O2 analyzer;
    (ii) A cycle time test of each O2 analyzer;
    (iii) A linearity test of each O2 analyzer; and
    (iv) A RATA, directly comparing the percent moisture measured by 
the monitor to a reference method.
    (6) For each continuous moisture sensor:
    (i) A 7-day calibration error test; and
    (ii) A RATA, directly comparing the percent moisture measured by 
the monitor sensor to a reference method.
    (7) For a continuous moisture monitoring system consisting of a 
temperature sensor and a data acquisition and handling system (DAHS) 
software component programmed with a moisture lookup table:
    (i) A demonstration that the correct moisture value for each hour 
is being taken from the moisture lookup tables and applied to the 
emission calculations. At a minimum, the demonstration shall be made at 
three different temperatures covering the normal range of stack 
temperatures.
    (ii) [Reserved]
    (8) The owner or operator shall ensure that initial certification 
or recertification of a continuous opacity monitor for use under the 
Acid Rain Program is conducted according to one of the following 
procedures:
    (i) Performance of the tests for initial certification or 
recertification, according to the requirements of Performance 
Specification 1 in appendix B to part 60 of this chapter; or
* * * * *
    (9) * * *
    (ii) Proper computation and application of the missing data 
substitution procedures in subpart D of this part and the bias 
adjustment factors in section 7 of appendix A to this part.
    (10) The owner or operator shall provide, or cause to be provided, 
adequate facilities for initial certification or recertification 
testing that include:
* * * * *
    (d) Initial certification and recertification and quality assurance 
procedures for optional backup continuous emission monitoring systems.
    (1) Redundant backups. The owner or operator of an optional 
redundant backup continuous emission monitoring system shall comply 
with all the requirements for initial certification and recertification 
according to the procedures specified in paragraphs (a), (b), and (c) 
of this section. The owner or operator shall operate the redundant 
backup continuous emission monitoring system during all periods of unit 
operation, except for periods of calibration, quality assurance, 
maintenance, or repair. The owner or operator shall perform upon the 
redundant backup continuous emission monitoring system all quality 
assurance and quality control procedures specified in appendix B to 
this part, except that the daily assessments in section 2.1 of appendix 
B to this part are optional for days on which the redundant backup 
monitoring system is not used to report emission data under this part. 
For any day on which a redundant backup monitoring system is used to 
report emission data, the system must meet all of the applicable daily 
assessment criteria in appendix B to this part.
    (2) Non-redundant backups. The owner or operator of an optional 
non-redundant backup continuous emission monitoring system shall comply 
with all of the following requirements for initial certification, 
quality assurance, recertification, and data reporting:
    (i) For a non-redundant backup gas monitoring system that has its 
own separate probe, sample interface, and analyzer or for a non-
redundant backup flow monitor, all of the tests in paragraph (c) of 
this section are required for initial certification of the system, 
except for the 7-day calibration error test.
    (ii) For a non-redundant backup gas monitoring system consisting of 
one or more like-kind replacement analyzers that use the same probe and 
sample interface as a primary monitoring system, no initial 
certification of the non-redundant backup monitoring system is 
required. Note that a non-redundant backup analyzer, connected to the 
same probe and interface as a primary analyzer in order to satisfy the 
dual span requirements of section

[[Page 28129]]

2.1.1.4 or 2.1.2.4 of appendix A to this part, shall be considered a 
like-kind, non-redundant backup analyzer.
    (iii) Each non-redundant backup monitoring system shall comply with 
the daily and quarterly quality assurance and quality control 
requirements in appendix B to this part for each day and quarter that 
the non-redundant backup monitoring system is used to report data, 
except that the requirements for when a linearity test must be 
performed are superseded by the requirements of this section. The owner 
or operator shall ensure that each non-redundant backup continuous 
emission monitoring system passes a linearity check (for pollutant 
concentration and diluent gas monitors) or a calibration error test 
(for flow monitors) prior to each use for recording and reporting 
emissions. For a non-redundant backup NOX-diluent or 
SO2-diluent monitoring system consisting of a primary 
pollutant analyzer and a like-kind replacement diluent analyzer (or 
vice-versa), provided that the primary analyzer is operating and is not 
out-of-control with respect to any of its quality assurance 
requirements, only the like-kind replacement analyzer must pass a 
linearity check before the system is used for data reporting. When a 
non-redundant backup monitoring system is brought into service prior to 
conducting the linearity test, a probationary calibration error test 
(as described in paragraph (b)(3)(ii) of this section), which will 
begin a period of conditionally valid data, may be performed in order 
to allow the use of data retrospectively, as follows. Conditionally 
valid data from the CEMS are validated back to the hour of completion 
of the probationary calibration error test if the following conditions 
are met: if no adjustments are made to the monitor other than those 
specified in section 2.1.3 of appendix B to this part between the 
probationary calibration error test and the successful completion of 
the linearity test, and if the linearity test is passed within 168 unit 
operating hours of the probationary calibration error test. However, if 
the linearity test is either failed, aborted due to a problem with the 
CEMS, or not completed as required, then all of the conditionally valid 
data are invalidated back to the hour of the probationary calibration 
error test, and data from the CEMS remain invalid until the hour of 
completion of a successful linearity test.
    (iv) When data are reported from a non-redundant backup monitoring 
system, the appropriate bias adjustment factor (BAF) shall be 
determined as follows:
    (A) Apply the BAF from the most recent RATA of the non-redundant 
backup system (even if that RATA was done more than 12 months 
previously); or
    (B) If no RATA results are available for the non-redundant backup 
system (e.g., for a non-redundant backup gas monitoring system that 
uses the same probe and sample interface as the primary monitoring 
system), apply the primary monitoring system BAF.
    (v) A non-redundant backup system may not be used for reporting 
data from a particular affected unit or common stack for more than 720 
hours in any one calendar year, unless the monitoring system passes a 
RATA at that same unit or stack.
    (vi) For each non-redundant backup gas monitoring system that has 
its own separate probe, sample interface, and analyzer and for each 
non-redundant backup flow monitor, no more than eight successive 
calendar quarters shall elapse following the quarter in which the last 
RATA of the monitoring system was done at a particular unit or stack, 
without performing a subsequent RATA. Otherwise, the monitoring system 
may not be used to report data from that unit or stack until the hour 
of completion of a successful RATA at that location.
* * * * *
    (g) Initial certification and recertification procedures for 
excepted monitoring systems under appendices D and E. The owner or 
operator of a gas-fired unit, oil-fired unit, or diesel-fired unit 
using the optional protocol under appendix D or E to this part shall 
ensure that an excepted monitoring system under appendix D or E to this 
part meets the applicable general operating requirements of Sec. 75.10, 
the applicable requirements of appendices D and E to this part, and the 
initial certification or recertification requirements of this 
paragraph.
    (1) Initial certification and recertification testing. The owner or 
operator shall use the following procedures for initial certification 
and recertification of an excepted monitoring system under appendix D 
or E to this part.
    (i) When the optional SO2 mass emissions estimation 
procedure in appendix D to this part or the optional NOX 
emissions estimation protocol in appendix E to this part is used, the 
owner or operator shall provide data from a flowmeter accuracy test (or 
shall provide a statement of calibration if the flowmeter meets the 
accuracy standard by design) for each fuel flowmeter, according to the 
appropriate calibration procedures using one of the following standard 
methods: ASME MFC-3M-1989 with September 1990 Errata, ``Measurement of 
Fluid Flow in Pipes Using Orifice, Nozzle, and Venturi''; ASME MFC-4M-
1986 (Reaffirmed 1990) ``Measurement of Gas Flow by Turbine Meters''; 
ASME MFC-5M-1985, ``Measurement of Liquid Flow in Closed Conduits Using 
Transit-Time Ultrasonic Flowmeters''; ASME MFC-6M-1987 with June 1987 
Errata, ``Measurement of Fluid Flow in Pipes Using Vortex Flow 
Meters''; ASME MFC-7M-1987 (Reaffirmed 1992), ``Measurement of Gas Flow 
by Means of Critical Flow Venturi Nozzles''; ASME MFC-9M-1988 with 
December 1989 Errata, ``Measurement of Liquid Flow in Closed Conduits 
by Weighing Method''; ISO 8316: 1987(E) ``Measurement of Liquid Flow in 
Closed Conduits--Method by Collection of the Liquid in a Volumetric 
Tank''; Section 8, Calibration from American Gas Association 
Transmission Measurement Committee Report No. 7: Measurement of Gas by 
Turbine Meters (1985 Edition); American Gas Association Report No. 3: 
Orifice Metering of Natural Gas and Other Related Hydrocarbon Fluids 
Part 1: General Equations and Uncertainty Guidelines (October 1990 
Edition), Part 2: Specification and Installation Requirements (February 
1991 Edition), and Part 3: Natural Gas Applications (August 1992 
Edition), excluding the modified calculation procedures of Part 3; or 
American Petroleum Institute (API) Section 2, ``Conventional Pipe 
Provers,'' from Chapter 4 of the Manual of Petroleum Measurement 
Standards, October 1988 (Reaffirmed 1993), as required by appendices D 
and E to this part (all methods incorporated by reference under 
Sec. 75.6).
* * * * *
    (2) Initial certification and recertification testing notification. 
The designated representative shall provide initial certification 
testing notification and periodic retesting notification for an 
excepted monitoring system under appendix E to this part as specified 
in Sec. 75.61. The designated representative shall submit 
recertification testing notification, as specified in Sec. 75.61, for 
quality assurance related NOX emission rate testing under 
section 2.3 of appendix E to this part for an excepted monitoring 
system under appendix E to this part. Initial certification testing 
notification or periodic retesting notification is not required for 
testing of a fuel flowmeter or for testing of an excepted monitoring 
system under appendix D to this part.
* * * * *

[[Page 28130]]

    (4) Initial certification or recertification application. The 
designated representative shall submit an initial certification or 
recertification application in accordance with Secs. 75.60 and 75.63.
    (5) Provisional approval of initial certification and 
recertification applications. Upon the successful completion of the 
required initial certification or recertification procedures for each 
excepted monitoring system under appendix D or E to this part, each 
excepted monitoring system under appendix D or E to this part shall be 
deemed provisionally certified for use under the Acid Rain Program 
during the period for the Administrator's review. The provisions for 
the initial certification or recertification application formal 
approval process in paragraph (a)(4) of this section shall apply, 
except that ``continuous emission or opacity monitoring system'' shall 
be replaced with ``excepted monitoring system'' and except that ``shall 
follow the procedures for loss of initial certification in paragraph 
(a)(5)'' or ``shall follow the procedures of paragraph (b)(5)'' shall 
be replaced with ``shall follow the procedures for loss of 
certification in paragraph (g)(7)''. Data measured and recorded by a 
provisionally certified excepted monitoring system under appendix D or 
E to this part will be considered quality assured data from the date 
and time of completion of the last initial certification or 
recertification test, provided that the Administrator does not revoke 
the provisional certification by issuing a notice of disapproval in 
accordance with the provisions in paragraph (a)(4) or (b)(5) of this 
section.
    (6) Recertification requirements. Recertification of an excepted 
monitoring system under appendix D or E to this part is required for 
any modification to the system or change in operation that could 
significantly affect the ability of the system to accurately account 
for emissions and for which the Administrator determines that an 
accuracy test of the fuel flowmeter or a retest under appendix E to 
this part to re-establish the NOX correlation curve is 
required. Examples of such changes or modifications include fuel 
flowmeter replacement, changes in unit configuration, or exceedance of 
operating parameters.
    (7) Procedures for loss of certification or recertification for 
excepted monitoring systems under appendices D and E to this part. In 
the event that a certification or recertification application is 
disapproved for an excepted monitoring system, data from the monitoring 
system are invalidated, and the applicable missing data procedures in 
section 2.4 of appendix D or section 2.5 of appendix E to this part 
shall be used from the date and hour of receipt of such notice back to 
the hour of the provisional certification. Data from the excepted 
monitoring system remain invalid until all required tests are repeated 
and the excepted monitoring system is again provisionally certified. 
The owner or operator shall repeat all certification or recertification 
tests or other requirements, as indicated in the Administrator's notice 
of disapproval, no later than 30 unit operating days after the date of 
issuance of the notice of disapproval. The designated representative 
shall submit a notification of the certification or recertification 
retest dates if required under paragraph (g)(2) of this section and 
shall submit a new certification or recertification application 
according to the procedures in paragraph (g)(4) of this section.
    (h) Initial certification and recertification procedures for low 
mass emission units using the excepted methodologies under Sec. 75.19. 
The owner or operator of a gas-fired, oil-fired, or diesel-fired unit 
using the optional low mass emissions excepted methodologies under 
Sec. 75.19 shall meet the applicable general operating requirements of 
Sec. 75.10, the applicable requirements of Sec. 75.19, and the 
applicable certification requirements of this paragraph (h).
    (1) Monitoring plan. The designated representative shall submit a 
monitoring plan in accordance with Secs. 75.53 and 75.62.
    (2) Certification application. The designated representative shall 
submit a certification application in accordance with 
Sec. 75.63(a)(1)(iii).
    (3) Approval of certification applications. Upon submission of the 
required certification application for approval to use the low mass 
emissions excepted methodology under Sec. 75.19, the excepted 
methodology shall be deemed provisionally certified for use under the 
Acid Rain Program during the period for the Administrator's review. The 
provisions for the certification application formal approval process in 
the introductory text of paragraph (a)(4) and in paragraphs (a)(4)(i), 
(ii), and (iv) of this section shall apply, except that ``continuous 
emission or opacity monitoring system'' shall be replaced with 
``excepted methodology.''
    (4) Disapproval of certification applications. If the Administrator 
determines that the certification application does not demonstrate that 
the unit meets the requirements of Secs. 75.19(a) and (b), the 
Administrator shall issue a written notice of disapproval of the 
certification application within 120 days of receipt. By issuing the 
notice of disapproval, the provisional certification is invalidated by 
the Administrator, and the data recorded under the excepted methodology 
shall not be considered valid. The owner or operator shall follow the 
procedures for loss of certification:
    (i) The owner or operator shall substitute the following values, as 
applicable, for each hour of unit operation during the period of 
invalid data specified in paragraph (a)(4)(iii) of this section or in 
Secs. 75.21(e) (introductory paragraph) and 75.21(e)(1): the maximum 
potential concentration of SO2, as defined in section 2.1 of 
appendix A to this part to report SO2 concentration; the 
maximum potential NOX emission rate, as defined in Sec. 72.2 
of this chapter to report NOX emissions; the maximum 
potential flow rate, as defined in section 2.1 of appendix A to this 
part to report volumetric flow; or the maximum CO2 
concentration used to determine the maximum potential concentration of 
SO2 in section 2.1.1.1 of appendix A to this part to report 
CO2 concentration data until such time, date, and hour as a 
continuous emission monitoring system or excepted monitoring system, 
where applicable, is installed and provisionally certified;
    (ii) The designated representative shall submit a notification of 
certification test dates, as specified in Sec. 75.61(a)(1)(ii), and a 
new certification application according to the procedures in paragraph 
(a)(2) of this section; and
    (iii) The owner or operator shall install and provisionally certify 
continuous emission monitoring systems or excepted monitoring systems, 
where applicable, no later than 180 unit operating days after the date 
of issuance of the notice of disapproval.
    (i) Initial certification and recertification procedures for 
excepted flow monitoring systems under appendix I. The owner or 
operator of a gas-fired unit, oil-fired unit, or diesel-fired unit 
using the optional protocol under appendix I to this part shall ensure 
that an excepted flow monitoring system under appendix I to this part 
meets the applicable general operating requirements of Sec. 75.10, the 
applicable requirements of appendix I to this part, and the initial 
certification and recertification requirements of this paragraph.
    (1) Initial certification and recertification testing. The owner or 
operator shall, where applicable, use the


[[Continued on page 28131]]



 
 


Local Navigation


Jump to main content.