[[pp. 28081-28130]] Acid Rain Program; Continuous Emission Monitoring Rule Revisions
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: May 21, 1998 (Proposed Rules)] [Page 28081-28130] From the Federal Register Online via GPO Access [wais.access.gpo.gov] [DOCID:fr21my98-43] [[pp. 28081-28130]] Acid Rain Program; Continuous Emission Monitoring Rule Revisions [[Continued from page 28080]] [[Page 28081]] GCV value of 100,000 Btu per hundred scf, the value of the ``sulfur-to- heat content'' ratio is 2.0 gr/mmBtu. Therefore, a candidate gaseous fuel would qualify to use the default SO2 emission rate of 0.0006 lb/mmBtu for part 75 reporting purposes if the 720 hours of historical data demonstrate that the mean value of the sulfur-to-heat content ratio is 2.0 gr/mmBtu or less. To demonstrate that a unit qualifies to use Appendix D when combusting a gaseous fuel, the designated representative for the facility would be required to show that the gaseous fuel has a total sulfur content of 20 grains/100 scf or less. This demonstration would apply to all gaseous fuels. For gaseous fuels other than pipeline natural gas, the sulfur content information could come either from contractual information on the sulfur content based on routine vendor sampling and analysis or from historic fuel sampling data to show the gaseous fuel's sulfur content (see Docket A-97-35, Item II-I-9, Policy Manual, Question 2.15). For gaseous fuels that are produced in batches or lots with a relatively uniform sulfur content, such as liquefied petroleum gases, it would be sufficient to provide historical information on each batch over the past year. This approach was accepted by the Agency for six units combusting liquefied petroleum gas (see Docket A-97-35, Items II-C-14 and II-D-22). In addition to documenting the total sulfur content of the fuel, the owner or operator would be required to submit certain other fuel- specific information. As previously noted, for units combusting pipeline natural gas, a designated representative would be required to provide contractual information to demonstrate that the natural gas is supplied under specification and has a hydrogen sulfide content less than or equal to 0.3 gr/100 scf. And historical data would have to be provided, as described above, to obtain permission to use the default SO2 emission rate of 0.0006 lb/mmBtu for a fuel other than pipeline natural gas. For other gaseous fuels that are not produced in batches with relatively uniform sulfur content, such as gaseous fuel generated through an industrial process (e.g., digester gas from a paper mill), since the sulfur content of the gaseous fuel could be highly variable, section 2.3.3.4 of today's proposed revisions to Appendix D would require a minimum of 720 hours of historical data documenting the sulfur content of the fuel under representative operating conditions. This information would allow the Agency to determine how variable the sulfur content is and if the daily sampling procedure under section 2.3.1 of Appendix D is sufficient to capture this variability without allowing the underestimation of sulfur content. If the sulfur variability were too great, continuous sampling using a gas chromatograph and hourly reporting of sulfur content would be required under today's proposed rule. 2. Fuel Sampling (a) Fuel Oil. Background Diesel fuel is distillate fuel oil of grades No. 1 or 2. Diesel fuel is heavily refined and has a much lower sulfur content and greater consistency than other grades of fuel oil. Section 2.2 of Appendix D to the May 17, 1995 direct final rule provides three options for sampling of diesel fuel and two options for sampling of other fuel oils. First, for all fuel oils, including diesel fuel, daily manual sampling is allowed. Second, diesel fuel and other fuel oils may also be sampled continuously using an automated sampler according to ASTM D4177-82 (Reapproved 1990), either using continuous drip sampling or flow proportional sampling. The samples would then be mixed to form a daily composite sample. Third, diesel fuel may be sampled ``as-delivered,'' upon receipt of a shipment. These sampling approaches were selected to ensure that sulfur content values would be as accurate as possible, would not underestimate SO2 mass emissions, and would account for any variability in the sulfur content of fuel. Many utilities have expressed concern about the cost of daily oil sampling (see Docket A-97-35, Items II-D-18, II-D-20, II-E-13, II-E- 14). Some utilities indicated that for a unit that burns oil every day, the cost of daily oil sampling is greater than the cost of SO2 CEMS and flow monitors. Furthermore, industry representatives provided information indicating that within a given shipment of fuel oil from a supplier, the variability in sulfur content is low (see Docket A-97-35, Items II-D-18 and II-D-59). Many companies already have state or Federal requirements for sampling of fuel from each truck delivery or in a storage tank on site at the plant whenever fuel is added to the storage tank (see Docket A-97-35, Item II-D-93). The storage tank is a tank at a plant that holds oil that is actually combusted by the unit on that day. In other words, no fuel will be blended between the time when a fuel lot is transferred to the storage tank and when the fuel is combusted in the unit. In other cases, such as EPA's NSPS regulations for industrial boilers under 40 CFR part 60, subpart Db, companies keep copies of fuel receipts from the supplier to indicate the sulfur content is below the required sulfur content. Based upon this information, EPA is proposing to reduce the required sampling frequency for fuel oil. This would be a significant reduction in burden and cost of using Appendix D, without causing underestimation of SO2 emissions. Discussion of Proposed Changes Several utilities suggested that the Agency propose to allow sampling of each delivery of oil (see Docket A-97-35, Items II-D-18, II-D-20, II-E-13, II-E-22). Under this approach, either a facility or its supplier would sample each truck or barge containing oil before the fuel is transferred into a tank at the plant. If a delivery shipped in a group of trucks were purchased under the same order and were specified to have the same gross calorific value, density, and sulfur content, then only one sample would be necessary for the group of trucks. Samples taken by the supplier would not need to be split and kept on hand at the site. This approach is currently allowed only for diesel fuel under section 2.2.1.2 of Appendix D, but would be extended to apply to all fuel oils under today's proposed rule. This approach would be particularly useful to a facility that receives large, infrequent deliveries of fuel or to a facility that already has other State or Federal regulations requiring sampling of each truck or barge delivered to the plant. A similar approach suggested by another industry representative, allowing facilities to use a sample of oil taken from a tank belonging to the supplier before the oil is delivered, is also proposed in today's rulemaking. The supplier could take the sample and the facility would be able to use that value as long as it keeps records of the fuel analysis results from the supplier. This approach would be particularly useful to a facility that receives a delivery of oil from a single supplier's tank that is shipped in many different trucks. This approach also would be useful for a small facility that would prefer to rely on samples taken by the supplier rather than taking its own samples and paying for their analysis. Finally, the Agency proposes a third sampling approach, allowing a facility to sample oil manually from its storage tank at the plant whenever oil is added to the tank. This approach would yield samples that are more representative of the oil combusted because it would include any fuel remaining in the tank as well as all fuel added. Sampling from the storage tank at the plant would be [[Page 28082]] useful to a facility that burns oil infrequently and adds oil to its storage tank infrequently. It also would be helpful where a facility already has other State or Federal regulations requiring sampling after adding fuel to the storage tank. Both the ``before delivery'' and ``as delivered'' sampling approaches would require a sample for each ``lot'' of oil; consequently, a suitable definition of a ``lot'' is needed. For purposes of determining when an oil sample should be taken for the NSPS applicable to utility boilers, section 5.2.2.2 of Method 19 in Appendix A to 40 CFR part 60 relies on a definition of fuel ``lot'' developed by the American Society for Testing and Materials (ASTM). This definition states that ``the lot size of a product oil is the weight of product oil from one pretreatment facility and intended as one shipment (ship load, barge load, etc.).'' In essence, a lot is a single batch of oil that has uniform properties and is purchased from a single supplier and delivered to a buyer. Among those uniform fuel properties are gross calorific value, density, sulfur content, and viscosity. In today's rulemaking, EPA proposes to adopt this definition of a lot of oil for use in the Acid Rain Program. The Agency also considered whether it is appropriate to keep the current approach of daily manual oil sampling as an option. Although it seems unlikely that facilities would choose daily sampling option if they have the three options of sampling by lot, sampling upon addition of fuel to a storage tank, or continuous sampling, a utility group has requested that EPA retain daily manual sampling as an option. The agency is, therefore, proposing to retain daily manual oil sampling as an option in Appendix D to allow facilities this additional flexibility. An industry representative suggested that EPA could define the oil combusted during a 24-hour period as a lot. For the reasons discussed below and in the section addressing sulfur content, density, and gross calorific values used in calculations, EPA is not incorporating this suggestion in today's proposed rule. EPA also reconsidered whether it is necessary to require daily composite samples when samples are taken continuously with an automatic sampler. In today's proposal, the Agency is proposing that continuous samples may be composited on a weekly basis rather than daily. The Agency also considered allowing an even longer compositing period, such as a month, but is not proposing this option for the reasons discussed below. A weekly composite sample of oil that is sampled continuously would be an attractive option for a facility that wants the most representative and accurate sulfur content data possible. This also would be a useful option for those few facilities that receive oil via a pipeline, rather than in discrete lots. Rationale Facilities wish to be able to perform less frequent fuel sampling in order to save money. From the information EPA has examined over the previous year, the Agency believes that less frequent oil sampling can be technically justified. Based upon information provided by utilities, the sulfur content of a lot of oil varies from sample to sample, with a standard deviation of 0.036 percent S to 0.063 percent S, or 5.62 to 6.85 percent of the average sulfur content for all daily samples between deliveries (see e.g., Docket A-97-35, Item II-D-18). Density and gross calorific value of oil in a lot should vary even less than sulfur content, because sulfur is an impurity in the composition of the fuel and not an essential physical property of the oil, as is density. Furthermore, the difference between the sulfur content, density, gross calorific value, and carbon content of a fuel during the first daily sample after a new delivery is received and the average sulfur content, density, gross calorific value, and carbon content for all daily samples from between two deliveries is extremely small (see Docket A- 97-35, Items II-B-18 and II-D-18 for supporting information). Therefore, the Agency expects that the variability of fuel characteristics within a lot is low enough that only a single representative sample is necessary for the lot. Data have indicated that there could be a significant difference in sulfur content between shipments, however (see Docket A-97-35, Items II-B-12, II-B-18 and II- D-18). The Agency believes that differences between lots, which could potentially result in the underestimation of SO2 emissions, can be dealt with by selecting a conservative sulfur content, density, or gross calorific value that would not be exceeded in any sample, rather than retaining more frequent sampling requirements. Therefore, today's proposal incorporates this approach. Prior to drafting today's proposed rule revisions, EPA requested comments on removing the option to perform daily manual oil sampling for Appendix D units. At least one utility group expressed interest in retaining the option to allow flexibility. The prime benefit to a facility from continuing to use daily manual sampling would appear to be that the facility could continue to use the same daily operating procedures and that reprogramming of a DAHS would not be necessary. Note that when using the approach of daily manual oil samples, a facility calculates SO2 mass emissions using the highest sulfur content in the previous 30 daily oil samples. Therefore, this approach requires more frequent analysis than either the proposed weekly composite sample for continuous samples or the proposed sampling by lot, and provides less accurate and more conservative results. The Agency believes it would be simpler and less confusing for both the Agency and for the regulated community to deal with a smaller number of approaches to sampling and calculating SO2 emissions. However, the Agency is retaining this option since at least some affected utilities want the flexibility to continue to use this option. EPA also considered the suggestion to define a 24-hour period as a lot in order to allow facilities to continue to perform daily manual sampling. EPA is not proposing this approach because of the added complexity, compared to keeping the current language in section 2.2.4 of Appendix D concerning manual daily sampling of oil. If a lot were defined as an arbitrary 24-hour period, the other requirements in the current rule (e.g., conservative sulfur, gross calorific value, and density values used to calculate SO2 mass emission rate and heat input rate) would need to be retained to ensure that SO2 emissions were not underestimated. Furthermore, using the terminology of a ``lot'' for both a delivery and a period of time, while requiring different treatment of sample data from the two different types of ``lots,'' could potentially be confusing. It seems preferable to keep the current language for daily manual samples. Because the Agency now believes it is appropriate to sample each fuel lot instead of sampling daily, the Agency reconsidered whether daily composite samples are necessary when a facility performs automated continuous sampling. Because continuous samplers take fuel samples multiple times each hour, they are highly representative of the oil being burned. Flow proportional samplers take samples automatically when a certain volume or mass of fuel has passed by, rather than during a particular time period. Generally, automatic samplers take multiple samples each hour; however, only one sample per hour is required under section 2.2.3 of Appendix D of the current rule. Even if the compositing time period is extended, the composite sample will be representative of the sulfur content, density, and gross calorific value of the oil between samples. Therefore, the Agency believes [[Page 28083]] that the compositing period could be extended from a day to as long a period as a month. However, EPA believes that it is unlikely that any container for taking samples from an automatic sampler would be large enough to accommodate all automatic samples taken during a month. In addition, at least one industry representative suggested that weekly composite samples were appropriate (see Docket A-97-35, Item II-D-30). Therefore, in section 2.2.3 of today's proposed rule, EPA would extend the allowable length of the compositing period for automatic samples to one week. The Agency believes this will make automatic sampling less costly, while taking into account the physical limitations of sampling equipment. (b) Gaseous Fuels. Background Section 2.3 of Appendix D, as revised in the May 17, 1995 direct final rule, provides only one approach for sampling gaseous fuel: under section 2.3.1, gaseous fuel sampling must be performed daily. Relatively few utilities perform daily sampling upon gaseous fuels, choosing instead to use a default SO2 emission rate for pipeline natural gas. In part, this is because the vast majority of gaseous fuel used by power plants is pipeline natural gas. Under section 2.3.2 of Appendix D, facilities may calculate SO2 mass emissions from pipeline natural gas using a default emission rate instead of performing fuel sampling. Because of the difficulty and potential danger of sampling gaseous fuel, gas sampling is generally conducted by the supplier, rather than by the facility. Those few utilities combusting gaseous fuels other than pipeline natural gas have expressed concern about the difficulty and expense of daily sampling, particularly in comparison to the value of SO2 allowances for low SO2 emissions from relatively clean fuel (see, e.g., Docket A-97-35, Items II-E-11, II-E- 20). For gaseous fuels that are delivered in discrete batches or ``lots,'' one would expect the gaseous fuel to behave like an ideal gas; sulfur should be evenly distributed throughout the batch. On this principle, the Ohio Environmental Protection Agency allowed a plant to take propane samples from each discrete delivery, rather than on a daily basis (see Docket A-97-35, Items II-C-14 and II-D-22). Discussion of Proposed Changes Today's proposal incorporates three different sampling approaches for gaseous fuels: sampling by lot, daily sampling, and continuous sampling with a gas chromatograph. For gaseous fuel that is delivered in discrete lots, such as liquefied petroleum gas, the gaseous fuel could be sampled either daily or for each lot delivered. Any gaseous fuels other than pipeline natural gas that are not delivered in discrete lots, such as digester gas or sour natural gas pumped directly from a field, would, at a minimum, need to be sampled daily. The samples could be taken either by the supplier or by the facility. However, if the average sulfur content and sulfur variability of such a fuel were too high (i.e., mean sulfur content > 7 gr/100 scf and standard deviation from the mean > 5 gr/100 scf, based on 720 hours of representative historical data), continuous sampling with a gas chromatograph and hourly reporting of sulfur content would be required. Rationale The approach of sampling upon a lot or discrete delivery of gaseous fuel is being incorporated into today's proposed rule for the following reasons. The Agency believes that discrete deliveries are sufficiently different from pipeline transmission of fuel that a different sampling approach is appropriate. According to the ideal gas law, all gas within an enclosed volume is mixed with a consistent composition; therefore, a single sample should be representative of all gas in the volume. Although gaseous fuels delivered by lot, such as liquefied petroleum gas, are higher in sulfur content and have a wider range of sulfur contents than pipeline natural gas, they still have relatively low sulfur contents compared to liquid and solid fuels. Thus, less frequent gas sampling appears appropriate, based on the small difference in the accuracy of calculated SO2 mass emissions. For this same reason, the Agency allowed as-delivered sampling for diesel fuel in the May 17, 1995 direct final rule (see Docket A-94-16, Item II-F-2). Finally, because of the difficulty of sampling gaseous fuels, EPA believes that it is less burdensome and less dangerous if gas sampling is conducted by the gas supplier. It is the Agency's understanding that the sampling for a gas in a discrete delivery or lot is typically conducted once for the lot, rather than on a daily basis. Through a petitioning process, EPA has already allowed one utility to perform sampling upon a lot or discrete delivery of gaseous fuel (see Docket A- 97-35, Items II-C-14 and II-D-22). EPA is proposing to require daily or continuous sampling of gaseous fuels other than pipeline natural gas or the equivalent that are not shipped in discrete lots, such as sour natural gas pumped directly from a field, landfill gas, or digester gas. Such gaseous fuels cannot be guaranteed to be stable in sulfur content. Therefore, proposed section 2.3.3.4 in Appendix D would require a minimum of 720 hours of representative historical data to characterize the sulfur variability of such fuels. For the 720 hours of demonstration data, the mean value and standard deviation of the fuel sulfur content would be calculated. If the mean value does not exceed 7 gr/100 scf (equivalent to about 10 ppm of SO2 emissions to the atmosphere), daily sampling would suffice. If the mean value is greater than 7 gr/100 scf, however, the variability of the sulfur content would be assessed in terms of the standard deviation. If the standard deviation exceeds 5 gr/100 scf, the sulfur variability would be considered too high and continuous sampling of the fuel with a gas chromatograph would be required. If continuous sampling were required, the owner or operator would have to implement a quality assurance program for the gas chromatograph. A copy of the QA plan would be kept on-site, suitable for inspection. For fuel with a low average sulfur content or a low sulfur variability, daily sampling would be sufficient. However, for gaseous fuel with a higher sulfur content, if the sulfur variability were too great, continuous sampling of the fuel with a gas chromatograph and hourly reporting of sulfur content would be required. 3. Sulfur, Density and Gross Calorific Value Used in Calculations (a) Fuel Oil. Background The hourly SO2 mass emissions rate due to combustion of oil is calculated using the mass flow rate of oil combusted and a sulfur content value from a sample. If a unit's oil flow rate is measured with a volumetric fuel flowmeter rather than a mass fuel flowmeter, then it will be necessary to determine the mass flow rate of oil from the volume of fuel and a density value from an oil sample. The heat input rate is calculated using the flow rate of oil multiplied by the gross calorific value (GCV) of a sample. The sulfur content, density, and GCV used to calculate emissions and heat input depend upon the oil sampling method used. Some sampling methods are more accurate than others. For example, for flow proportional or continuous drip sampling, the actual sulfur content from a sample is used to calculate SO2 mass emissions. However, [[Page 28084]] when daily manual samples are taken under section 2.2.4 of Appendix D, a facility must use the highest fuel sulfur content recorded at that unit from the most recent 30 daily samples, which is not necessarily the sulfur content of the fuel being burned at any particular time. For units where diesel fuel is sampled upon delivery, section 2.2.1.2 instructs a facility to calculate SO2 emissions using the highest sulfur content of any oil supply combusted in the previous 30 days that the unit combusted oil. In daily manual sampling and as- delivered sampling, conservative sulfur values are used to avoid the possibility of underestimating SO2 mass emissions due to variations in sulfur content. Gross calorific values are taken from the most recent sample, rather than using the highest value in the previous 30 days, because, for natural gas, GCV is more consistent than sulfur content. Today's proposed rule includes changes to the sampling frequency for oil. Therefore, it is also necessary to make corresponding changes to the sulfur content, density, and GCVs to be used in calculations. For example, where oil samples would no longer be taken daily, it would be inappropriate to calculate SO2 mass emissions based upon a certain number of daily samples. In developing today's proposal, EPA considered what fuel analysis data values for sulfur content, density, and GCV would be appropriate and consistent with the approaches for taking manual samples. The appropriate sulfur content, density, and GCV values were considered for manual samples taken from a storage tank at the facility whenever fuel is added to the tank, for samples taken from each lot before the delivery is transferred from tank trucks or barges, and for samples taken from the fuel supplier's storage tank. Discussion of Proposed Changes EPA has re-evaluated the sulfur content, density, and GCVs to be used to calculate SO2 mass emissions and heat input based upon the new oil sampling approaches. For daily manual oil sampling, a facility would continue to use the highest sulfur content from previous 30 daily samples, and the actual density and GCV. For continuous oil sampling with an automatic sampler, a facility would continue to use the actual sulfur content, density, and GCV. For the two new methods of manual sampling, EPA considered whether conservative or actual values should be used to calculate emissions and heat input. EPA also considered whether the same type of calculational value should be used for sulfur content, density, and GCV. For example, if conservative sulfur content and density values are used to calculate the SO2 mass emission rate, should a conservative or an actual measured GCV be used to calculate the heat input rate? For manual samples taken from a storage tank at a plant whenever fuel is added to the tank, EPA considered the following options: (1) using the highest sulfur content and density from the previous three samples, and the actual GCV, (2) using the highest sulfur content from the previous three samples, and the actual density and GCV, (3) using the actual sulfur content, density, and GCV, (4) using the highest sulfur content, density, and GCV from the previous calendar year, and (5) using the maximum sulfur content, density, and GCV allowed by fuel purchase contract with the fuel supplier. The third, fourth, and fifth options are incorporated into today's proposal in section 2.2.4.2. Under this approach, a facility would take a sample from the storage tank whenever fuel is added to the tank. No blending of fuel would be allowed from the time the oil is sampled until the fuel is combusted by the unit. The sample would be analyzed for sulfur content, density, and GCV. Based on the selected option (3, 4, or 5), the appropriate values would then be used to calculate the SO2 mass emission rate and the heat input rate from the date and hour in which the transfer of oil is complete until the date and hour when oil is again added to the tank. EPA considered several different options for the case where a facility or its supplier would sample each oil delivery (or the supplier's storage tank) before the fuel is transferred into a tank at the plant. EPA considered whether or not these values needed to be conservative and concluded that there was a real possibility of underestimating SO2 emissions by using the fuel analysis values from a delivery. The options that EPA considered to avoid the underestimation were: (1) using the highest sulfur content and density from all samples taken from oil combusted during the previous 30 days, and the actual GCV, (2) using the maximum sulfur content, density, and GCV in the fuel purchase contract specifications, (3) using the highest sulfur content, density, and GCV from a sample taken in the previous calendar year, and (4) using the highest sulfur content, density, and GCV ever recorded for the unit. The second and third options are incorporated into today's proposed rule in section 2.2.4.3 of Appendix D. Under the selected options, a facility or its supplier would need to sample a delivery of fuel before it is transferred into a storage tank. The facility would then need to keep records of the fuel analytical results for three years. The facility would use the conservative value it selected under option (2) or (3), above, in order to calculate the SO2 mass emission rate and the heat input rate. If an as-delivered sample were ever analyzed and found to have a sulfur content, density, or GCV that exceeded the value being used in calculations (i.e., the contract specification, or the maximum value measured in the previous calendar year), then the new sampled value would be used to calculate the SO2 mass emission rate or the heat input rate, as follows. For a unit using a default value of the maximum value measured during the previous calendar year, that new sample value would become the new default value and would be reported for the remainder of the current year and the next year, unless superseded by a higher sampled value. For a unit using a default value of a contract specification, the new sample value would continue to be used as the new default value instead of the contract specification value, unless superseded by a higher sampled value or by a new contract. Rationale EPA considers continuous sampling and the measurement of fuel from a storage tank at a plant after each addition of fuel to the tank to be highly accurate methods that will be representative of the fuel combusted in a unit. However, if samples are taken from the truck or barge used to ship the fuel, or if samples are taken ``as-delivered,'' the sample values will not necessarily accurately reflect the oil being combusted by the unit at any particular time (see Docket A-97-35, Item II-E-22). For example, a storage tank could contain oil with an average sulfur content of 0.6 percent. Then a new delivery with a sulfur content of 0.4 percent is received and transferred to the tank. The ``as-delivered'' sample value from the delivery truck would underestimate the emissions at that time, since the fuel actually combusted will combine a mixture of the old fuel supply in the storage tank and the new fuel that is added. Thus, a more conservative sulfur value should be used to calculate SO2 emissions if samples are taken from the delivery containers or from a container used by the oil supplier. For density and GCV, today's proposal, at the suggestion of some industry representatives, uses conservative values determined by the same method for both parameters (see Docket A-97-35, Item II-E-24). This [[Page 28085]] has the advantage of being easy to remember and to program. However, if greater accuracy is desired, a facility would always have the option of using actual sulfur content, density, and GCVs if it took samples from its storage tank after each addition of fuel to the tank, or if it took continuous, automatic samples. EPA considered which conservative values would be appropriate for sulfur, density, and GCV. EPA at first considered using the maximum value from all oil supplies combusted in the previous 30 days. This is similar to the current wording of section 2.2.1.2 of Appendix D for calculation of SO2 emissions from diesel fuel as-delivered sampling. However, in the process of implementing this provision of part 75, EPA found this wording was somewhat confusing and issued policy guidance to clarify section 2.2.1.2 of Appendix D (see Docket A- 97-35, Item II-I-9, Policy Manual, Question 2.9). This policy essentially directs facilities to keep track of the amount of fuel used as well as its sulfur content. Because of the more complicated nature of this accounting, some industry representatives suggested that it would be simpler to use a conservative default value that would not require tracking fuel usage (see Docket A-97-35, Item II-E-24). Of the default values considered, EPA felt that the most appropriate default values would be the maximum values established by agreement with the fuel supplier through a contract or the maximum measured value from all samples in the previous calendar year. Contractual limits should be higher than or equal to the actual sulfur content, density, or GCV. Because not all units would necessarily have a fuel contract limiting oil sulfur content, density, or GCV, EPA is also proposing to provide the option of using the maximum oil sulfur content, density, or GCV in the previous calendar year. The Agency also considered whether the current provisions of 2.2.4 of Appendix D should be retained for calculation of SO2 emissions using the highest sulfur from the previous 30 daily samples when performing daily manual sampling. As discussed above in Section III.P.2(a) of this preamble on oil sampling frequency, the Agency is proposing to retain the option as requested by at least one utility representative. (b) Gaseous Fuels. Background The vast majority of Acid Rain units which burn gaseous fuels combust pipeline natural gas. Section 2.3.2 of Appendix D contains a provision for calculation of SO2 mass emissions from pipeline natural gas using a default SO2 emission rate in lb/mmBtu and the heat input rate of pipeline natural gas. However, if a facility or its supplier is sampling gaseous fuel for sulfur content, either because it is not pipeline natural gas or because the facility chooses to use a sampled value, then Appendix D requires the facility to calculate the SO2 mass emission rate using the sulfur content of the sample and the volume of gas combusted, and to calculate the heat input using the GCV of the sample and the volume of gas combusted (see Equations D-5 and F-20). Because of the nature of gaseous fuels, they are always measured with a volumetric fuel flowmeter. The formulas for calculating the SO2 mass emission rate and the heat input rate use volume directly and do not require information on gas density. The current provisions of Appendix D allow a facility to calculate the SO2 mass emission rate and the heat input rate using the actual value from a daily sample of gaseous fuel. When the provisions of section 2.3 of Appendix D were added to part 75 in the May 17, 1995 direct final rule, EPA presumed that virtually every utility combusting gaseous fuel was combusting pipeline natural gas. However, the Agency found that utilities were combusting other types of gaseous fuels. One utility submitted a monitoring plan and a certification application for fuel flowmeter monitoring systems that indicated the utility was also using propane liquefied petroleum gas (LPG) (see Docket A-97-35, Item II-D-6). The utility indicated that it wished to use the default emission rate factor reserved for pipeline natural gas in its monitoring plan and later petitioned the Agency specifically for permission to use the default emission rate factor of 0.0006 lb/mmBtu. In conversations with utility staff, EPA found that the utility wanted to avoid the expense of additional daily samples and the trouble of entering daily sulfur values manually into its data acquisition and handling system (see Docket A-97-35, Items II-E-11, II- E-20). The Agency eventually approved a revised petition for the utility that allowed the utility to take propane samples from each discrete delivery, rather than on a daily basis, where the utility calculates sulfur dioxide emissions from propane by using the highest sulfur content recorded during the previous 365 days and reports these data in its quarterly electronic data report (see Docket A-97-35, Items II-C-14 and II-D-22). The Agency found that there were also some utilities burning gaseous fuels that were by-products of an industrial process (see Docket A-94-16, Item II-D-71). EPA had concerns that such ``digester gas'' might have a more variable sulfur content than pipeline natural gas, since the gaseous fuel would begin with a higher sulfur content than pipeline natural gas and would not necessarily go through a process that would reduce and stabilize the sulfur content. Discussion of Proposed Changes In today's proposed rule, the provisions for sampling gaseous fuels are found in section 2.3.1 of Appendix D. For gaseous fuels that are delivered in discrete lots, a facility would use conservative values for sulfur content and GCV to calculate the SO2 mass emission rate and the heat input rate. For the sulfur content value, the highest sampled sulfur content from the previous calendar year or the maximum value allowed by contract would be used to calculate the SO2 mass emission rate. For GCV, the highest of all sampled values in the previous calendar year or the maximum value allowed by contract would be used to calculate the heat input rate. If, for any gas sample, the assumed sulfur content or GCV were exceeded, the sampled value would become the new assumed value. For units using the contract value, the sampled value would continue to be used unless a new (higher) contract specification were put in place or unless an even higher sampled value is obtained. For units using the maximum value from the previous year, the sampled value would continue to be used for the remainder of the current year and for the next calendar year unless it was superseded by an even higher sampled value. For any gaseous fuel where daily fuel sampling is required, a facility would use the highest sulfur in the previous 30 daily samples. For gaseous fuels other than pipeline natural gas, where daily sampling of sulfur content is required, the highest GCV from the previous 30 daily samples would be used. For pipeline natural gas, where monthly sampling of GCV only is required, the actual measured GCV, the highest of all sampled values in the previous calendar year, or the maximum value allowed by contract would be used. For a gaseous fuel that is not produced in batches and that has a relatively high sulfur content and a high sulfur variability, continuous sampling with a gas chromatograph would be required. Sulfur content would be reported as actual measured hourly average values. The GCV would also be determined on an hourly basis, or, [[Page 28086]] alternatively, the highest value in the previous 30 unit operating days could be reported. Rationale For gaseous fuel supplied in discrete deliveries, EPA is proposing to take the same approach as for fuel oil that is being delivered to a plant by barge or truck. EPA has already approved this approach with one utility that combusts liquefied petroleum gas (see Docket A-97-35, Items II-C-14 and II-D-22). Because a discrete delivery of gaseous fuel would be maintained in an enclosed chamber with a relatively constant temperature and pressure, one would expect the gaseous fuel to behave like an ideal gas. Thus, sulfur and other constituents of the fuel should be evenly distributed throughout the delivery of fuel. Using conservative values to calculate the SO2 mass emission rate and the heat input rate should account for any variability between deliveries. Furthermore, this reduces the number of changes that would be made to a data acquisition and handling system to add fuel supply data. For gaseous fuel other than pipeline natural gas, where daily fuel sampling is required, EPA considered leaving unchanged the current provisions of section 2.3.1 of Appendix D that would allow a utility to use the actual value from a day's sample to calculate the SO2 mass emission rate and the heat input rate. However, the Agency believes that it is appropriate to change the sulfur content value to be a somewhat conservative historical value. This is because the Agency has concerns that there may be some gaseous fuels other than natural gas, such as digester gas, that may have significant variability in their sulfur content over the course of a day or a longer period of time. This might result in the underestimation of the SO2 mass emission rate. In the case of fuel oil, some industry representatives suggested it was simplest to determine the appropriate conservative values for sulfur content, density, and GCV by the same method (see Docket A-97- 35, Item II-E-24). With one exception (for fuels with relatively high sulfur content and high sulfur variability), today's proposal follows this suggestion for gaseous fuels. The proposal uses the highest sulfur content and the highest GCV from the previous 30 daily samples. This is currently the procedure used to determine the sulfur value used in calculations from daily manual oil samples. Since this algorithm for daily manual oil sample calculations is already being used by many software programmers, it is a good conservative value to use for daily samples in this case. The Agency notes that currently, the heat input is calculated using the actual sampled GCV and that this change would require software reprogramming for units where gaseous fuel is sampled daily. However, for pipeline natural gas that is sampled monthly for GCV, facilities could continue to use the actual GCV measured in a monthly sample. The other two options are more conservative and would require software changes. The Agency requests comment on the proposal to use the more conservative GCV value to determine the heat input rate for gas combustion when gaseous fuel is sampled daily (which differs from the current procedure in section 2.3.1.3 of Appendix D and section 5.5.2 of Appendix F). For gaseous fuel that has a relatively high sulfur content and high sulfur variability, daily sampling is not considered adequate to ensure that SO2 emissions will not be underestimated. Therefore, for such fuels, continuous sampling with a gas chromatograph and hourly reporting of sulfur content would be required. For GCV, which is expected to be less variable than sulfur content, either the actual hourly measured value or the highest GCV value obtained in the last 30 unit operating days could be reported. 4. Missing Data Procedures for Sulfur, Density, and Gross Calorific Value Background (a) Fuel Oil. The May 17, 1995 direct final rule included missing data procedures for missing analytical information on sulfur content, density, and GCV in section 2.4 of Appendix D. These procedures are based on a daily sampling frequency. For example, missing sulfur content, density, or GCV data are to be calculated using the highest measured sulfur content, oil density, or GCV during the previous thirty days when the unit burned oil. This was intended to mean that the substitute data values are to be based on the previous thirty daily oil samples for which data are available. In order to ensure that a DAHS is capable of implementing the missing data procedures required by the rule, Sec. 75.20(c)(7) and Sec. 75.20(g)(1)(ii) require testing of each DAHS. EPA issued policy guidance discussing how facilities should report the results of these tests for units measured with fuel flowmeters. This policy guidance provided a form checklist that facilities could use to show the results of their own tests of the missing data substitution procedures (see Docket A-97-35, Item II-I-9, Policy Manual, Question 15.9). Some utilities objected to testing the DAHS missing data procedures on the grounds that they should never miss sample data. In part, this would be because the facility is required, under section 2.2.5 of Appendix D, to split its sample and keep a portion. One utility offered to substitute the maximum potential sulfur content, which would require less complicated DAHS programming than using the maximum sulfur content of the previous 30 daily samples. (b) Gaseous Fuels. Section 2.4.1 of Appendix D, as revised by the May 17, 1995 direct final rule, provides missing data substitution procedures for missing sulfur data from daily samples of gaseous fuel. The DAHS is required to substitute the highest measured sulfur content recorded during the previous 30 days when the unit combusted gaseous fuel. As for oil, this was intended to be the highest sulfur value from the previous 30 daily samples with available sulfur values. Section 2.4.2 of Appendix D requires the substitution of the highest measured GCV recorded during the previous three months that the unit burned gaseous fuel when data are missing from a monthly gaseous fuel sample. As for fuel oil, the missing data procedures for gaseous fuels are linked to the frequency of fuel sampling. A utility indicated to EPA that because it receives gas sampling information from its supplier, it should never have missing data for GCV. The utility suggested that it should not have to go to the expense of programming its DAHS for missing data procedures that should never need to be used. This argument was similar to that used by another utility when referring to missing data procedures for manual samples of fuel oil taken upon each delivery. Discussion of Proposed Changes EPA proposes to revise the missing data substitution procedures for both fuel oil and gaseous fuel, in order to simplify them. For any instance in which the sulfur content, GCV, or density value is missing, the maximum potential value would be reported until the results of a subsequent valid sulfur content analysis, GCV determination, or density measurement are obtained. The proposed appropriate maximum potential values are specified in the table below. The default values for sulfur content, GCV, and density of residual oil and diesel fuel were taken from handbook values (see Docket A-97-35, Item II-A-7). The default maximum sulfur content values for gaseous fuel are consistent with the maximum sulfur content allowed under [[Page 28087]] the definition of natural gas and the de facto maximum sulfur content of pipeline natural gas, based on the proposed definition. Thus, any gas with a sulfur content that did not allow it to qualify as pipeline natural gas (i.e., greater than 0.30 gr/100 scf) but still allowed it to be measured following Appendix D procedures (i.e., total sulfur content not exceeding 20.0 gr/100 scf) would have a default maximum potential sulfur content of 20.0 gr/100 scf. The default values for GCV of gaseous fuels were taken from handbook values (see Docket A-97-35, Item II-I-1). For pipeline natural gas, it is assumed that the gas is primarily methane (GCV of 1050 Btu/scf) with a small amount of other hydrocarbons with a higher GCV (see Docket A-97-35, Item II-E-19). For other gaseous fuels, it is assumed that they are primarily butane (GCV of 2100 Btu/scf), the hydrocarbon gas with the highest GCV of gases commercially used for fuel. Maximum Potential Default Values for Sulfur Content, Density, and GCV Data ---------------------------------------------------------------------------------------------------------------- Parameter Fuel Maximum potential default value ---------------------------------------------------------------------------------------------------------------- Sulfur content.......................... residual oil............... 3.5 percent by weight. diesel fuel................ 1.0 percent by weight. pipeline natural gas....... 0.30 gr/100 scf. gaseous fuels with sulfur 20.0 gr/100 scf. content greater than pipeline natural gas. GCV/heat content........................ residual oil............... 19,500 Btu/lb. diesel fuel................ 20,000 Btu/lb. pipeline natural gas....... 1100 Btu/scf. gaseous fuels with sulfur 2100 Btu/scf. content greater than pipeline natural gas. Oil Density............................. residual oil............... 8.5 lb/gal, diesel fuel................ 7.4 lb/gal. ---------------------------------------------------------------------------------------------------------------- Rationale (a) Fuel Oil. It seems possible that a facility might occasionally miss a sample taken with an automatic sampler, and thus, would have missing data. Therefore, today's proposal includes a provision for substitution of missing sulfur content, density, and GCV data from continuous, automatic sampling. Based upon comments from some utilities, it seems relatively unlikely that both a facility and its supplier would miss performing a sample during a delivery. Both a facility and its fuel supplier will want to verify that the fuel delivered is actually supplying the heat content that it is supposed to, either under a contract or a fuel specification; thus, both a facility and its fuel supplier will have an incentive to ensure sampling takes place for a delivery. Furthermore, if samples taken by a facility are split, then there should generally be the ability to provide analytical data for that fuel, even if test results were somehow lost. Because the event of missing fuel samples is unlikely for as-delivered samples, EPA believes that it would be appropriate to establish a simple, conservative value that could easily be substituted in a data acquisition and handling system. This would be easier to program than using historical values that require tracking fuel usage over an extended period of time. EPA is specifically proposing the most conservative (maximum potential) values for missing data purposes. This would ensure that substituted missing data values would be less advantageous to a facility than taking samples and using sulfur content, density, and GCV data from samples. In addition, several utilities suggested to EPA that this was a reasonable approach (see Docket A-97-35, Item II-E-24). (b) Gaseous Fuels. As mentioned previously, gas sampling is generally performed by fuel suppliers because of the difficulty and potential danger of opening up a pressurized pipe containing a highly flammable gas. It seems extremely unlikely that a fuel supplier would not have information available on the sulfur content or GCV of gaseous fuel, since industrial customers will purchase fuel or agree to a contract based upon these characteristics. The exception to this might be gaseous fuel manufactured through an industrial process that is not produced specifically for sale as a fuel, such as digester gas. In today's proposed rule, EPA is using the same reasoning as above for missing manual fuel oil sample data and is using the same basic substitution approach for missing sulfur content and GCV data for gaseous fuel. EPA considered keeping the existing missing data substitution procedures from sections 2.4.1 and 2.4.2 of Appendix D for missing data from gaseous fuel. This would have the advantage of requiring no reprogramming of software for facilities already following the existing procedures. EPA also considered using the maximum sulfur content or GCV from the previous calendar year, the same procedure proposed in today's rule for calculation of SO2 mass emission rate or heat input, for discrete deliveries of gas or for manual samples of oil taken from a delivery truck or barge. However, using the proposed maximum value would require little reprogramming and would greatly simplify the missing data procedures. In policy guidance, the Agency has indicated it would accept a simplified DAHS for units using the procedures of Appendices D and E. In particular, these policies endorse manual entry of fuel analytical data, simplified missing data procedures for fuel flowmeters, and a DAHS that uses commercial spreadsheet software instead of a specialized custom software for purposes of part 75 (see Docket A-97-35, Item II-I-9, Policy Manual, Questions 14.72 and 14.73). In keeping with the policy of allowing Appendices D and E units to use commercial spreadsheet software, EPA has proposed what it believes to be the simplest possible missing data substitution procedure for missing sulfur content and GCV data. In addition, using the proposed maximum potential sulfur content or GCV would ensure that substituted missing data values are more conservative than the values normally used to calculate the SO2 mass emission rate and the heat input rate. [[Page 28088]] 5. Installation of Fuel Flowmeters for Recirculation Background The current provisions of section 2.1.1 of Appendix D require the use of an additional ``return'' fuel flowmeter when some fuel is recirculated, i.e., initially sent toward a unit and then diverted away from the unit without being burned. This additional fuel flowmeter is required, regardless of the amount of fuel being diverted. At least one utility has requested to use only the fuel flowmeter measuring fuel leaving the oil tank without a second fuel flowmeter to measure any fuel diverted away by the recirculation fuel line. The utility argued that using a single fuel flowmeter would result only in the overestimation of SO2 emissions, since the utility would measure a larger amount of fuel usage. This would allow the facility to avoid the expense of installation, certification, and quality assurance testing on a fuel flowmeter on the recirculation fuel line. Since the proportion of fuel being recirculated was minimal, the utility was willing to use a more conservative SO2 emissions calculation in exchange for devoting fewer resources for the testing and maintenance of the recirculation line fuel flowmeter. Discussion of Proposed Changes In today's proposal, EPA proposes to allow facilities to use only a fuel flowmeter on the main fuel line from the oil tank if the amount of oil recirculated is demonstrated to be less than 5.0 percent of total fuel usage for each hour during the year. Rationale EPA believes that it is reasonable not to require installation, certification and quality assurance of secondary fuel flowmeters in cases where the amount of fuel to be combusted is a small proportion of the total fuel used, and where knowing the exact volume of the recirculated fuel makes little difference in the calculation of emissions and heat input. EPA has allowed one utility to use an estimate of the maximum oil usage at start-up, rather than requiring the utility to install a return line oil flowmeter to measure the startup fuel flow rate. At first, EPA considered making the installation of a fuel flowmeter on a recirculation fuel line optional. Presumably, if the cost in lost SO2 allowances were greater than the cost of installing and maintaining a fuel flowmeter, then a facility would choose to use a fuel flowmeter on the recirculation fuel line. However, many fuel flowmeters used under Appendix D for determining the SO2 mass emission rate and the heat input rate are also used to estimate the NOX emission rate in lb/mmBtu under Appendix E to part 75. The Appendix E procedures estimate hourly NOX emission rates using a correlation between measured NOX emission rates and heat input rates. The correlation is established during a testing period. Therefore, subsequent to the test period, if the hourly heat input values should become less accurate, it could result in the estimated NOX emission rates becoming less accurate. Such loss in accuracy could occur if the heat input rates during the initial testing period were based upon subtraction of measured volumes or masses of recirculated fuel from the total fuel flow rates, and then the facility later began estimating, rather than measuring, the recirculated fuel volumes or masses. The potential inaccuracy would increase if the proportion of recirculated oil to the total flow rate of oil varies over time. The NOX emission rate can sometimes increase with increases in the heat input rate and can sometimes decrease with increases in the heat input rate, depending on the particular type of boiler; in addition, when certain types of control equipment are installed, the NOX emission rate may not have any relationship with the heat input. Thus, an overestimation of the heat input rate would sometimes result in the overestimation and sometimes result in the underestimation of the NOX emission rate under Appendix E. For these reasons, EPA believes that there needs to be some limits on the cases where a facility can choose not to use a return fuel flowmeter. In today's proposed rule, EPA is proposing that a facility may choose to use only a fuel flowmeter on the main fuel line from the oil tank and not install a return meter in those cases where the previously measured proportion of oil from the recirculation line is less than or equal to 5.0 percent of the unit's total oil usage during each hour of the year. EPA believes that an error of 5.0 percent in the heat input rate should be small enough that it will not significantly affect accounting for the NOX emission rate under Appendix E. An analysis of emissions data from a gas-fired Appendix E unit with a higher than average NOX emission rate for gas (0.157 lb/ mmBtu) showed that a 5.0 percent increase in heat input would change the quarterly average NOX emission rate by only 3.17 percent (0.152 vs. 0.157 lb/mmBtu) (see Docket A-97-35, Item II-B-19). At the same time, EPA believes that an average proportion of 5.0 percent of total fuel usage should provide relief for the most extreme situations where it might cost more to perform quality assurance testing on a return fuel flowmeter than the value of the allowances saved by monitoring with the return flowmeter. The Agency also considered whether it would be more appropriate to determine the proportion of recirculated fuel on an hourly average basis or on an annual average basis to determine if the returned fuel was less than 5.0 percent of total fuel usage. The Agency concluded that the proportion of fuel could be determined only if a return fuel flowmeter were already installed on the recirculation fuel line. Thus, there would appear to be little advantage to basing the proportion of fuel on an annual basis. Hourly average fuel flow rate would also be more directly related to the heat input rate used to calculate hourly NOX emission rate under Appendix E. EPA notes this is not fully consistent with the objective of revising this provision, i.e., to exempt facilities from installation and operation of additional fuel flowmeters. Therefore, the Agency believes it is better to base the reduced fuel flow rate monitoring requirement either on actual historical fuel flowmeter data or on some other method, as yet unknown, that would yield a reasonable estimate of the average proportion of fuel recirculated to the total amount of fuel used. At this time, the Agency is unaware of what other methods could provide a reasonable estimate of the average proportion of fuel recirculated to the total amount of fuel used, either on an hourly or an annual basis. Accordingly, the Agency would allow facilities to suggest methods through the petitioning process of Sec. 75.66. 6. Fuel Flowmeter Testing (a) Fuel Flowmeter Accuracy Tests. Background Sections 2.1.5 and 2.1.6 of Appendix D, as revised by the May 17, 1995 direct final rule, refer to calibration and recalibration of fuel flowmeters. Section 2.1.5.2 gives procedures for a test of the flowmeter accuracy by comparing a candidate flowmeter against another flowmeter that has already been calibrated according to specified procedures. If a flowmeter does not meet the specified accuracy, then it would need to be recalibrated by adjusting it, then retested to ensure it is reading accurately. Some utilities have found confusing the terminology of ``calibration'' for a test that compares measurements from two different flowmeters. Generally, the [[Page 28089]] term ``calibration'' is used to refer to adjustments made to a flowmeter to ensure it is reading accurately. However, the type of test described in section 2.1.5.2 is more like a relative accuracy test audit than a calibration, in that it checks the flowmeter accuracy by comparing the fuel flowmeter readings against readings from an outside standard. Discussion of Proposed Changes To alleviate the confusion surrounding flowmeter testing, today's proposal introduces the term ``flowmeter accuracy test.'' This terminology is used in sections 2.1.5 and 2.1.6 of Appendix D. Rationale EPA believes that the term ``flowmeter accuracy test'' more clearly reflects the nature of the test that is performed. Introducing this new term also will clarify that the word ``calibration'' refers to flowmeter adjustments, rather than to a comparative test between a candidate flowmeter and a reference meter. (b) Methods for Fuel Flowmeter Accuracy Testing. Background Section 2.1.5.1 of Appendix D, as revised by the May 17, 1995 direct final rule, includes a list of standards and procedures that may be used to determine if a flowmeter is sufficiently accurate for use under the Acid Rain Program. However, because of the large number of different brands and kinds of fuel flowmeters, there are also many manufacturers' procedures that are not explicitly permitted under part 75. Consequently, many Acid Rain certification applications for units with fuel flowmeters have contained petitions under Secs. 75.23 and 75.66 for approval of other fuel flowmeter testing procedures. Among those methods was AGA Report No. 7 for turbine flowmeters. This method was incorporated by reference into part 75 in the November 20, 1996 final rule. In addition, another standard method that EPA approved through petitions is American Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' from Chapter 4 of the Manual of Petroleum Measurement Standards, October 1988 edition (see reproduction of this document in Docket A-97-35, Item II-D-10 (Attachment B)). In the process of implementing part 75, many utilities have commented on the problems of testing and calibrating fuel flowmeters. Unlike CEMS or stack flow monitors, it is not always possible to perform an accuracy test with the fuel flowmeter remaining in the pipe where it is installed. Utilities have stated that certain fuel flowmeters are extremely difficult to remove, send out for testing, recalibrate, and then reinstall (see Docket A-97-35, Item II-E-22). In addition, removing a fuel flowmeter from in-line may require stopping flow of the fuel and possibly shutting down the unit, with negative economic consequences (see Docket A-97-35, Item II-E-8). In addition, if a facility needs to operate a unit while the flowmeter is being tested at a laboratory, then no flow data will be available for the fuel measured by the flowmeter unless the facility has a backup fuel flowmeter. Utilities have petitioned for alternative quality assurance procedures for fuel flowmeters in order to avoid the inconvenience and expense of removing the fuel flowmeter and testing it (see Docket A-97- 35, Item II-D-9). Because of this, the Agency has been evaluating various ways of testing a fuel flowmeter in-line (that is, still installed in the pipe in its regular position). Some utilities have suggested that an alternative way to check fuel flowmeter accuracy would be to compare over time the ratio of the fuel flowrate to unit output (``load''), measured either in electrical generation in MWe or in steam flow in 1000 lb/hr (see Docket A-97-35, Item II-E-21). A fuel flow-to-load comparison could be used to determine if fuel flowmeter readings are still similar to the readings obtained the last time the fuel flowmeter was tested against an outside method. A significant change in the amount of fuel used at a load level would call into question the validity of fuel flow readings from a flowmeter. A fuel flow-to-load comparison could provide this check without removal of the fuel flowmeter from its installed location, which would be of considerable benefit to facilities. Discussion of Proposed Changes EPA is proposing to incorporate by reference the standard: American Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' from Chapter 4 of the Manual of Petroleum Measurement Standards. The Agency also specifically requests comment on any other voluntary consensus standards from standard setting organizations, such as API, AGA, ASME, or ISO, that would be appropriate for incorporation by reference into part 75. Any suggested methods should also be submitted to the Agency as part of the comments to assist in the Agency's evaluation. Section 2.1.7 of Appendix D to today's proposed rule includes provisions for an optional, supplemental quality assurance test for fuel flowmeters using a ratio of the fuel flow rate and the unit load. The fuel flow rate-to-load ratio comparison test would provide an additional way to meet the requirement to periodically test fuel flowmeter accuracy. This test would serve as a supplement to more rigorous fuel flowmeter tests. These more rigorous tests include the standards incorporated by reference under section 2.1.5.1 of Appendix D that require the fuel flowmeter to be taken out of line and shipped to a laboratory, and the ``master meter'' comparison procedures under section 2.1.5.2 of Appendix D. For orifice-, nozzle-, and venturi-type flowmeters, the more rigorous tests would include an inspection of the primary element and an accuracy test on the transmitters or transducers. If a facility performed and passed regular quarterly fuel flow-to-load ratio testing, then it would need to perform the more rigorous checks on monitor performance only once every 20 calendar quarters (five years). The fuel flow-to-load ratio test would require a facility to establish a baseline period from a period of time when the fuel flowmeter is known to be operating properly. After establishing this baseline of accurate fuel flow data (or heat input rate data), a facility would calculate the fuel flow-to-load ratio (or ``gross heat rate'' (GHR)) during the baseline period. In each ``flowmeter operating quarter'' that the fuel flowmeter operates after the baseline period is completed, the facility would calculate the fuel flow-to-load ratio (or GHR) for each hour the fuel flowmeter is used to report data. The facility would compare the hourly fuel flow-to-load ratio (or GHR) to the fuel flow-to-load ratio (or GHR) during the baseline period in order to calculate the absolute value of the percentage difference for each hour. Next, the facility would calculate the average percentage difference for the quarter. If the percentage difference exceeded the specified limits for the test, the fuel flowmeter would fail the test. The key elements of the fuel flow rate-to-load evaluation are discussed in the following paragraphs. (1) Use of Gross Heat Rate-to-Load Ratio. Today's proposed rule would allow a facility the option of calculating either the ratio of the fuel flow rate to the gross generation in MWe or the steam flow rate in thousands of pounds of steam per hour (``fuel flow-to-load ratio'') or the ratio of the heat input rate to the gross generation in MWe or the steam flow rate in thousands of pounds of steam per hour (``GHR''). In order to allow a meaningful comparison, a facility would use one of these two ratios consistently, both in calculating [[Page 28090]] an initial baseline ratio and in calculating hourly ratios during a particular quarter. Equations D-1c and D-1e describe the calculation of the fuel flow-to-load ratio for the baseline period and for hourly values during a calendar quarter, respectively. For the GHR, the respective equations are Equations D-1d and D-1f. These equations are found in proposed sections 2.1.7.1 and 2.1.7.2 of Appendix D. (2) Baseline Period for Fuel Flow-to-Load Ratio. The provisions for calculating the baseline fuel flow-to-load ratio or gross heat rate are found in section 2.1.7.1 of today's proposed rule. EPA is proposing that the owner or operator of a facility would establish a baseline of fuel flow rate (or heat input rate) data following a flowmeter accuracy test under either section 2.1.5.1 or 2.1.5.2 of Appendix D, or following both a transmitter or transducer accuracy test under section 2.1.6.1 of Appendix D and an inspection of a primary element for an orifice-, nozzle-, or venturi-type fuel flowmeter under section 2.1.6.6. Throughout section 2.1.7 of today's proposed rule, these are referred to as ``the most recent quality assurance procedure(s).'' The baseline period of fuel flow rate (or heat input rate) data for a fuel flowmeter to be tested under section 2.1.7 would use the first 168 hours of quality assured data measured by that flowmeter following the most recent quality assurance procedure(s) for which: (1) only the fuel measured by that fuel flowmeter is combusted (i.e., no co-firing of fuels occurs); (2) the load is relatively stable and not ``ramping'' rapidly up or down; and (3) the load is sufficiently above the minimum safe, stable operating load (unless low-load operation is normal for the unit). Today's proposal includes a limit to the length of time over which the baseline period could extend. The baseline period of 168 hours could not extend for longer than the end of the second calendar quarter following the calendar quarter in which the most recent quality assurance procedure(s) was performed. For orifice-, nozzle-, and venturi-type fuel flowmeters, two quality assurance procedures would be required: both a transmitter or transducer accuracy test under section 2.1.6.1 of Appendix D and an inspection of a primary element, such as an orifice plate. For practical purposes, this means that the transmitter or transducer accuracy test and the primary element inspection would have to be completed either in the same calendar quarter or in consecutive calendar quarters. If there were not 168 hours of quality-assured fuel flowmeter data from hours when a single fuel is combusted, then the fuel flowmeter would not be allowed to be tested using the fuel flow-to-load ratio as a supplement to other quality assurance tests. The 168 hours of quality-assured fuel flowmeter data next would be averaged and divided by the average load, in megawatts or 1000 lb steam/hr, during the same 168 hours to determine the baseline fuel flow-to-load ratio (see Equation D-1c). Alternatively, the facility could instead calculate the gross heat rate by averaging hourly heat input rate during the 168 hours of the baseline period and by dividing the average heat input rate by the average load during the same 168 hours (see Equation D-1d). In cases where the fuel flowmeter is located on a common pipe header, one fuel flow rate measurement could be associated with the load from several units that receive fuel from the common pipe header. In order to analyze the fuel flow-to-load ratio for a flowmeter on a common pipe header, the load from all units receiving fuel from the common pipe header would have to be combined for each hour, averaged over the baseline period of 168 hours, and compared to the average fuel flow rate during the baseline period. If a single unit receives fuel from multiple pipes, each pipe with its own fuel flowmeter, then the flow rates from all fuel flowmeters would have to be added together to obtain the average fuel flowrate for the unit to be divided by the unit load. (3) Data Preparation and Analysis. In each flowmeter operating quarter following the final quarter of the baseline period, all hourly fuel flowmeter data would be compared to the load. A flowmeter operating quarter would be a calendar quarter in which the unit combusts the fuel measured by the fuel flowmeter for at least 168 hours. For each hour in which the fuel is combusted, the owner or operator would calculate the fuel flow-to-load ratio (or GHR) (see Equation D-1e for the fuel flow-to-load ratio and Equation D-1f for the GHR). Hourly fuel flow rates on common pipe headers would be compared to the sum of the loads from all units receiving fuel from the common pipe header. For units with multiple pipes and multiple fuel flowmeters, the total hourly fuel flow rate for the fuel would be compared to the unit load. Next, the facility would compare the hourly fuel flow-to-load ratios (or GHRs) to the baseline fuel flow-to-load ratio (or GHR). The absolute value of the percentage difference would be calculated for each hour using Equation D-1g. Then the facility would calculate the average value of the percentage difference for the quarter, using each hourly percentage difference in Equation D-1h. The quarterly average of the hourly percentage difference values next would be compared to the limitation. For either the fuel flow-to- load ratio or the GHR, Ef, the quarterly average of the hourly percentage difference values would need to be no greater than 10.0 percent, unless the average of the hourly loads used for the analysis was50 MWe (or 500 klb/hr of steam), in which case the limit on Ef would be 15.0 percent. If a fuel flowmeter were to fail to meet this limit when using all data in the flowmeter operating quarter, then the facility would have the option of excluding certain hours. Otherwise, a failure to meet the 10.0 percent (or 15.0 percent, if applicable) limit would be considered a failure of the fuel flow-to- load ratio test. (4) Optional Data Exclusions. As mentioned above, if a fuel flowmeter's data would not meet the 10.0 percent (or 15.0 percent, if applicable) limit on the quarterly average of the percentage difference values, then a facility could opt to exclude certain hours of unrepresentative fuel flow rate (or heat input rate) data and then reanalyze the smaller set of data. The types of data that EPA proposes as non-representative would be the same as the hours excluded during the baseline period, including: (1) hours when the unit combusts multiple fuels measured by multiple fuel flowmeters, such as co-firing of gas and residual oil or co-firing of residual oil and diesel fuel; (2) hours when the unit load is rapidly rising or falling, sometimes referred to as ``ramping,'' to such a degree that the load in a given hour differs by more than 15.0 percent from the load during either the previous hour or the hour afterwards; or (3) hours in which the unit load is in the lower 10.0 percent of the unit's operating range, unless operation at those low levels is considered normal for the unit. The facility would proceed to analyze the remaining quarterly fuel flow rate or heat input rate values, provided that there are at least 168 hours remaining for the quarter after excluding non-representative hours. If less than 168 representative hours remained after excluding the allowable hours, then a flow-to-load or GHR test would not be required for that flowmeter for that flowmeter operating quarter. If the fuel flowmeter data still failed to meet the 10.0 percent (or 15.0 percent, if applicable) limit on the quarterly average of the percentage difference values after excluding the allowable [[Page 28091]] hours, the flowmeter would fail the fuel flow-to-load ratio test. (5) Consequences of Failing Fuel Flow-to-Load Ratio or GHR Tests. There would be two primary consequences of failing a fuel flow-to-load ratio or a GHR test. First, the data from the fuel flowmeter would no longer be considered quality-assured. Thus, the facility would need to invalidate data from the fuel flowmeter following the test. Proposed section 2.1.7.4 of Appendix D specifies that the missing data procedures of section 2.4.2 of Appendix D would be used to substitute for the invalid data (unless a different fuel flowmeter is available that has been tested for accuracy and has been demonstrated to meet the accuracy specification), beginning with the first hour the fuel measured by the fuel flowmeter is used during the quarter following the flowmeter operating quarter in which the meter fails the fuel flow-to- load ratio test. Second, in order to establish that the fuel flowmeter is again operating properly and providing quality-assured data, the facility would perform a fuel flowmeter accuracy test according to sections 2.1.5.1 or 2.1.5.2 of Appendix D or, for orifice-, nozzle-, and venturi-type flowmeters, a transmitter or transducer accuracy test according to section 2.1.6.1 of Appendix D. In addition to the transmitter or transducer test, orifice-, nozzle-, and venturi-type fuel flowmeters would need to be further tested following a failed flow-to-load or GHR test in order to ensure that the problem causing the failure of the fuel flow-to-load ratio was a problem with the transmitters or transducers. Once the orifice-, nozzle-, or venturi-type flowmeter has been recalibrated and passes a transmitter or transducer accuracy test according to section 2.1.6.1 of Appendix D, the facility would perform a shortened version of the fuel flow-to-load ratio test. The shortened version of the test would use six to twelve hours of data following the passed transmitter or transducer accuracy test. If the fuel flowmeter passed the abbreviated fuel flow-to-load ratio test, then its data would be considered valid, beginning with the time and date of the passed transmitter or transducer accuracy test. However, if the fuel flowmeter were to fail the abbreviated fuel flow-to-load ratio test, then it would be necessary for the facility to inspect the primary element for corrosion or damage. Furthermore, data would be considered invalid until the orifice-, nozzle-, or venturi-type fuel flowmeter passes an inspection of the primary element. Although data from the flowmeter would be considered quality-assured after successful completion of all required accuracy testing, visual inspections and diagnostic tests, the baseline would have to be re-established no later than the end of the second flowmeter operating quarter following the quarter in which the quality assurance tests are completed. Rationale: EPA is proposing to incorporate by reference the standard: American Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' from Chapter 4 of the Manual of Petroleum Measurement Standards, October 1988 edition. The Agency has already approved this method of fuel flowmeter testing in response to a petition (see Docket A-97-35, Item II-C-6). This is also a standard agreed to by API that is traceable to NIST standards. The Agency has a general policy of approving standards from technically knowledgeable groups such as the Organization for International Standards (ISO), the American Society for Testing and Materials (ASTM), the American Society of Mechanical Engineers (ASME), the American Gas Association (AGA), the Gas Processors Association (GPA), and API. EPA would also be willing to incorporate additional standards by reference if commenters supply a copy for consideration. The Agency recognizes that it is difficult and sometimes costly to take a fuel flowmeter out from its installation location to be tested (see Docket A-97-35, Item II-E-22). Today's proposed rule would provide the flexibility of an additional approach for testing fuel flowmeters where they are installed. Today's proposal for a fuel flow rate-to-load comparison test would allow facilities to assure the quality of their fuel flow rate data without taking a fuel flowmeter out of line. Several industry representatives suggested that a fuel flow rate-to- load comparison was a useful approach to quality assuring data (see Docket A-97-35, Items II-E-22, II-E-23). Some industry representatives felt that a fuel flow rate-to-load ratio was straightforward and even more representative than a stack flow rate-to-load ratio (see Docket A- 97-35, Item II-E-23). In general, utilities have indicated that the idea of a fuel flow- to-load ratio is an appropriate quality assurance test for fuel flowmeters (see Docket A-97-35, Items II-D-30, II-D-41, II-E-33). Use of the fuel flow-to-load ratio was first suggested to the Agency as an alternative to annual orifice inspections (see Docket A-97-35, Item II- E-22). One utility mentioned that the fuel flow-to-load ratio test would be most useful if it allowed them to stretch the time between transmitter or transducer accuracy tests on orifice-, nozzle-, and venturi-type fuel flowmeters, as well as primary element inspections and fuel flowmeter accuracy tests performed in-line against a ``master meter'' or performed in a laboratory (see Docket A-97-35, Item II-D- 49). Utilities have also indicated that they would prefer the provisions of the fuel flow-to-load ratio test to be as similar as possible to the stack flow-to-load ratio test in today's proposed rule (see Docket A- 97-35, Item II-E-33). This would be easier for facilities to comply with because they would need to learn fewer new procedures, they could use the same equations and algorithms in computer software or hand calculations, and they could report information in a similar format. To the extent possible, the Agency has incorporated this suggestion in today's proposed rule. However, because monitoring with fuel flowmeters is not identical to monitoring with stack volumetric flow monitors, there are some differences in the procedures and in the data to be recorded and reported. Today's proposed rule would allow the quarterly fuel flow-to-load ratio test as an optional supplement to flowmeter accuracy tests under section 2.1.5.1 or 2.1.5.2 of Appendix D, transmitter or transducer accuracy tests under section 2.1.6.1 of Appendix D for orifice-, nozzle-, and venturi-type fuel flowmeters, and visual inspections of the primary element required under section 2.1.6.6 of Appendix D for orifice-, nozzle-and venturi-type fuel flowmeters. These more rigorous fuel flowmeter quality assurance procedures would still be required at least once every 20 calendar quarters (five years), even if the procedures of section 2.1.7 of Appendix D were followed. The Agency has proposed a quarterly fuel flow-to-load ratio test for several reasons: (1) this is consistent with the provisions of the proposed volumetric stack flow-to-load ratio test in today's proposed rule; (2) the test involves examining data more closely when preparing quarterly reports; and (3) a quarterly test allows facilities to find problems in fuel flowmeter data before an entire year has passed. The Agency also considered requiring the fuel flow-to-load ratio to be used more frequently than quarterly, perhaps daily; however, this would require facilities to spend far more time and effort in evaluating data at different times during the quarter than they may do currently, particularly for small, infrequently operated units. In addition, many utilities claim that fuel [[Page 28092]] flowmeters tend to be stable, and therefore little change would be expected over short time periods such as a day (see Docket A-97-35, Item II-E-33). EPA is proposing that the optional fuel flow-to-load ratio test could serve as a supplement to other quality assurance procedures for fuel flowmeters for up to 20 calendar quarters (five years). EPA is proposing a time period of 20 calendar quarters for the following reasons. First, it is similar to the current provision in section 2.1.5.2 of Appendix D, which allows a reference fuel flowmeter to be accuracy tested as seldom as once in five calendar years if comparison with an in-line ``master'' flowmeter shows less than a 1.0 percent difference in their flow rates. Second, a five-year test cycle offers certain administrative advantages. For instance, fuel flowmeters used to provide heat input data for the heat input-versus-load correlation of Appendix E could be accuracy-tested before each Appendix E test (i.e., once every five years). In addition, a five-year period would ensure that fuel flowmeters are tested by the time the unit's operating permit is renewed. The 20 calendar quarter (five-year) period is consistent with the provisions for reduced three-level flow RATAs for stack flow monitors. The 20 calendar quarter (five-year) period between tests is also consistent with the proposed time between quality assurance tests for fuel flowmeters that are used very infrequently. Repeating the periodic quality assurance procedures for fuel flowmeters at least every five years would catch slow, long-term changes in heat rates mentioned by a facility and would allow a facility to update its baseline data periodically (see Docket A-97-35, Item II-D-49). Finally, allowing the option of a 20 calendar quarter (five-year) period between more rigorous quality assurance procedures would be safer and less costly than annual testing, while, in coordination with quarterly fuel flow-to-load ratio testing, still providing assurance of the quality of the data. (1) Use of Gross Heat Rate or Flow-to-Load Ratio. Today's proposed rule would allow a facility the option of calculating either the ratio of the fuel flow rate to the gross generation in MWe or the steam flow rate in thousands of pounds of steam per hour (``fuel flow-to-load ratio'') or the ratio of the heat input rate to the gross generation in MWe or the steam flow rate in thousands of pounds of steam per hour (``gross heat rate'' or ``GHR''). One utility suggested that, because the load is created based upon a number of factors in addition to the fuel flow rate, such as the gas heat rate (i.e., gross calorific value), a ratio of the heat input to the unit load would be a better test than the ratio of the fuel flow rate to the unit load (see Docket A-97-35, Item II-D-50). In addition, some utilities pointed out that the Agency allows facilities to use either a stack flow-to-load ratio or a heat input-to-load ratio (gross heat rate) as a diagnostic test on stack volumetric flow monitors, through Policy Manual Question 13.15 (see Docket A-97-35, Item II-I-9). The Agency agrees that the heat input-to-load ratio (GHR) is also a technically appropriate check on the performance of fuel flowmeters. Therefore, today's proposal includes options for both the fuel flow-to-load ratio and the GHR. (2) Baseline Period for Fuel Flow-to-Load Ratio or GHR. When using this type of comparison test, it is important to establish a baseline of reliable data to which hourly data can later be compared. For the stack volumetric flow-to-load ratio, the baseline of reliable data consists of data from the reference method for flow, Method 2 of Appendix A to 40 CFR part 60. However, there is no universally applicable test for flowmeters that is performed in-line with a reference method while the unit is operating, parallel to the flow RATA. EPA asked several utilities what could be a source of baseline data to which the fuel flowmeter could later be compared. One utility suggested using fuel flowmeter readings during a time when the unit is operating at a steady load, such as when the unit undergoes Appendix E testing for a NOX-versus-heat input correlation or when a NOX CEMS undergoes a normal level RATA (see Docket A-97-35, Item II-D-41). A second utility recommended that the baseline be established just after performing a transmitter calibration, i.e., after performing a quality assurance test on the fuel flowmeter (see Docket A-97-35, Item II-D-49). The Agency believes that using fuel flowmeter data taken immediately following a flowmeter quality assurance test would be most likely to be accurate and representative of proper operation of the fuel flowmeter. Flowmeter quality assurance tests might include any of the methods incorporated by reference in section 2.1.5.1 of Appendix D; meter testing against a certifiable ``master'' meter under section 2.1.5.2 of Appendix D; or transmitter or transducer accuracy testing under section 2.1.6.1 of Appendix D, and inspection of a primary element for an orifice-, nozzle-, or venturi- type fuel flowmeter under section 2.1.6.6 of Appendix D. This approach is proposed in today's rule. The utilities supporting the idea of using fuel flowmeter data taken immediately after a flowmeter quality assurance test have suggested that it would be important to have a fairly large number of hours in the baseline, on the order of 100 or more, to ensure that the baseline period is representative of typical operation (see Docket A- 97-35, Item II-E-33). In today's rule, EPA is proposing to use the first 168 hours of quality assured data measured by that flowmeter for which: (1) only the fuel measured by that fuel flowmeter is combusted; (2) the unit load is not significantly ``ramping'' up or down; and (3) the unit load is safely above the minimum safe, stable load. The Agency believes that a baseline period containing 168 hours of data is sufficiently long to be representative of different unit operating conditions that may occur later. This specific time period is consistent with the minimum number of hours that a unit combusts a fuel before the quarter counts toward the deadline for the next quality assurance test, and with the minimum number of hours that a unit combusts a fuel before a quarter needs to be evaluated using the fuel flow-to-load ratio. Certain hours would be excluded from the baseline (i.e., periods of co-firing, unstable, or low load), because the fuel flow-to-load ratio or GHR would tend to be less reliable during those periods. Today's proposal would also limit the baseline period so that it may extend no more than two quarters beyond the quarter in which the flowmeter passes its accuracy tests. The Agency has concerns that if the baseline data were to extend longer than this, the performance of the fuel flowmeter might degrade. In order for the baseline data to reflect fuel flow rate data that are most likely to be accurate, the Agency is proposing that the fuel flow rate or heat input rate data used in the baseline period must either be obtained in the calendar quarter in which the quality assurance procedure is performed, or within two calendar quarters after the QA test. The Agency considered limiting the time period to the same calendar quarter as the quality assurance procedure or to one flowmeter operating quarter beyond the QA test. However, because a quality assurance procedure may be conducted at any time during a quarter, it could be difficult for a facility to collect 168 hours of fuel flowmeter data after a quality assurance procedure in the same calendar quarter or even (for infrequently operated units that ramp [[Page 28093]] up and down often) in the next calendar quarter. For orifice-, nozzle-, and venturi-type fuel flowmeters, two quality assurance procedures would be required prior to collecting the baseline data: (1) a transmitter or transducer accuracy test, and (2) an inspection of a primary element. The Agency considered whether these two quality assurance procedures should be separated and whether the baseline period could simply be based upon a time period after the most recent quality assurance procedure. The Agency believes that the baseline period data would be more reliable if they were taken shortly after completing both quality assurance procedures for orifice-, nozzle-, and venturi-type fuel flowmeters. Using the same time period for both tests simplifies administration of the fuel flow-to-load ratio test. EPA also notes that a unit does not need to be operating in order to perform the tests; thus, it should not be burdensome for a facility to plan to coordinate the two quality assurance procedures. (3) Data Preparation and Analysis. The proposed procedures for data preparation and analysis for the fuel flow-to-load ratio are similar to those for the volumetric stack flow-to-load ratio. Equations of the same form as those for the stack volumetric flow-to-load ratio are used to calculate the hourly fuel flow-to-load ratio, the hourly absolute value of the percentage difference between the baseline fuel flow-to- load ratio and the hourly fuel flow-to-load ratio, and the quarterly average percentage difference. Common pipe headers would be treated in the same way as common stacks. If there were multiple units associated with a single fuel flowmeter or flow monitor, the total load from all units would be summed before the flow rate data are divided by the load data to calculate the flow-to-load ratio. Fuel flowmeters on multiple pipes would be treated in the same way as multiple stacks associated with a single unit. If there are multiple fuel flowmeters or flow monitors associated with a single unit, the flow rates from all fuel flowmeters for the same fuel or all flow monitors would be added together before the flow rate data are divided by the load data to calculate the flow-to-load ratio. Certain aspects of the volumetric stack flow-to-load ratio test are not the same for the fuel flow-to-load ratio test. For example, the volumetric stack flow-to-load ratio test requires the facility to screen out those hours when the unit operates further than 10.0 percent away from the average load during the most recent normal-load flow RATA. As was discussed previously, there is no equivalent of an in-line flow RATA for fuel flowmeters. EPA does not believe that there is a need to screen out hours for the fuel flow-to-load test when the unit operates at a load somewhat less than or greater than normal. Some facilities have indicated that the fuel flow-to-load ratio or GHR based on fuel flow readings is less variable over different loads than the volumetric stack flow-to-load ratio (see Docket A-97-35, Items II-E-33 and II-D-98). However, preliminary evidence has also indicated that the fuel flow-to-load ratio or GHR can be significantly different at very low operating loads than at other load levels (see Docket A-97-35, Item II-A-5). For this reason, EPA is proposing to allow hours in which the unit load is within the lower 10.0 percent of the range of operation to be excluded from both the baseline data and the quarterly flow-to-load or GHR analysis, unless such low loads are considered normal for the unit. Another feature of the volumetric stack flow-to-load ratio test that differs from the fuel flow-to-load ratio test is the treatment of bias-adjusted data. Fuel flow rate data are never adjusted for bias. There is no bias test for fuel flowmeters. Bias-adjustment of data is an issue for the volumetric stack flow-to-load ratio test because bias- adjusted data has already been adjusted to make it more consistent with the value of the reference method data. Thus, bias-adjusted volumetric stack flow data must meet a stricter quarterly average percentage difference of 10.0 percent from the reference flow-to-load ratio, whereas the allowable difference is 15.0 percent when unadjusted volumetric stack flow data are used. (See discussion of stack flow-to- load test in Section III.M. of this preamble.) EPA notes that since the same fuel flow meter is used to produce both the baseline data and the quarterly data, the fuel flow-to-load ratio is more closely analogous to the use of bias-adjusted volumetric flow data. Therefore, the limit on the quarterly average percentage difference from baseline for fuel flow rate data should be at least as stringent as that for bias- adjusted volumetric flow data (10.0 percent). Information provided by facilities on the gross heat rate derived from fuel flow rate data have shown less variability than the corresponding stack heat rate (see Docket A-97-35, Item II-D-98). Based upon this information, EPA is proposing a limit of 10.0 percent on E f , the quarterly average percentage difference from the baseline for the quarterly flow rate-to-load or GHR evaluation. EPA considered whether it would be appropriate to set a different limit for smaller units, as was done for the stack flow-to-load test. Analysis of some preliminary fuel flow-to- load data has shown that for lower loads (e.g., < 50 MWe), the flow-to- load ratio is quite sensitive to small changes in load (see Docket A- 97-35, Item II-A-5). This indicates that it would be appropriate to set a higher limit for smaller units. Therefore, today's rule proposes a limit of 15.0 percent on the value of Ef when the quarterly average load used for the data analysis is 50 megawatts or less (or500 klb steam per hour). The Agency solicits comment on the 15.0 percent limit for loads less than or equal to 50 megawatts. (4) Optional Data Exclusions. As for volumetric stack flow monitors, if a fuel flowmeter's data would not meet the limit on the percentage deviation from the baseline, then a facility could opt to exclude certain hours of unrepresentative fuel flow rate (or heat input rate) data and then reanalyze the smaller set of data. The hours of data that EPA proposes to view as non-representative for fuel flowmeters are: (1) hours when the unit combusts multiple fuels; (2) hours when the unit load in a given hour would differ by more than 15.0 percent from the load during either the previous hour or the subsequent hour; or (3) hours when the load is very close to the minimum safe, stable load (unless operation in that range is normal). The baseline period for fuel flowmeters and the data used for the quarterly flow-to-load or GHR analyses would include only those hours when a single fuel is combusted--the fuel measured by the fuel flowmeter. If the quarterly fuel flow rate data included hours when multiple fuels are co-fired, the fuel flow-to-load ratio or GHR for the fuel flowmeter being tested would be biased low. This could result in a failure of the flow-to-load test or GHR evaluation. Today's proposed rule would also allow a facility to exclude from the baseline data and the quarterly analyses those hours that are not representative because the unit's load is changing rapidly. Specifically, hours could be excluded when the unit load in a given hour would differ by more than 15.0 percent from the load during either the previous hour or the hour afterwards. There will be a lag in the time between when electricity is generated and registered as load and the time that the fuel flowmeter measures the fuel that is combusted to generate the load. Therefore, during an hour when the load changes rapidly, the fuel flow rate will not necessarily be changing by the same amount or in the [[Page 28094]] same direction. At least one utility has suggested that the Agency consider such an exclusion for the proposed fuel flow-to-load ratio test (see Docket A-97-35, Item II-D-41). In general, the fuel flow is directly proportional to load, with a linear graphical relationship. However, this is not always the case at extremely low loads (see Docket A-97-35, Items II-E-33, II-D-98). Therefore, today's proposed rule would allow certain low-load hours to be excluded from the flow-to-load baseline and quarterly data analyses. Specifically, loads in the lower 10.0 percent of the ``range of operation'' of the unit, (as that term is defined in proposed section 6.5.2.1 of Appendix A in today's proposal) could be excluded, unless such loads are considered normal for the unit. Today's proposed rule, in section 2.1.7 of Appendix D, would also exempt a fuel flowmeter from the fuel flow-to-load ratio test in a quarter when a more rigorous quality assurance test is performed. This is unlike the volumetric stack flow-to-load ratio, which is required each QA operating quarter, including quarters when the flow monitor is tested with a RATA (provided, of course, that sufficient data for the analysis are obtained after the RATA). (5) Consequences of Failing the Fuel Flow-to-Load Ratio Test. The consequences of failing the fuel flow-to-load ratio test would be similar to the consequences of failing quality assurance tests in general for fuel flowmeters. Data from the fuel flowmeter would no longer be considered quality assured. Because the fuel flow-to-load ratio test is only performed at the end of a quarter, the facility would invalidate data from the fuel flowmeter beginning with the first hour in the quarter after the quarter in which the meter fails the fuel flow-to-load ratio test. In order to establish that the fuel flowmeter is operating properly and providing quality assured data again, the facility would perform a flowmeter accuracy test or (for orifice-, nozzle-, and venturi-type flowmeters) a transmitter or transducer accuracy test. The Agency believes it is appropriate to perform an accuracy test if the fuel flow-to-load ratio test is failed, because in such cases the facility has had the benefit of postponing the accuracy test based upon the assumption that the fuel flowmeter has continued to measure accurately and consistently with its operation during the baseline period. Note that for orifice-, nozzle-, and venturi-type fuel flowmeters, a transmitter/transducer test alone would not suffice to demonstrate that the flowmeter is back in control. The owner or operator would still need to ensure that the cause of the failed fuel flow-to-load ratio test was a problem with the transmitters or transducers rather than a problem with the primary element. Sudden changes in flowmeter performance are likely to be caused by a problem with transmitters (see Docket A-97-35, Item II-D-33). However, it cannot be assumed that the transmitters are solely responsible for degradation in monitor performance. In order to verify that the primary element is not contributing additional error to the fuel flow measurements because of corrosion, a facility would conduct an abbreviated (6 to 12 hour) version of the fuel flow-to-load ratio test, similar to the diagnostic test for volumetric stack flow monitors in Policy Manual Question 13.15 (see Docket A-97-35, Item II-I-9). The Agency believes that this abbreviated fuel flow-to-load ratio test would provide additional assurance that the fuel flowmeter is indeed operating properly. In addition, it would be more timely than waiting for another calendar quarter to pass to repeat the fuel flow-to-load ratio. The abbreviated test would also be less burdensome than removing the primary element from the fuel pipe. EPA believes the abbreviated fuel flow-to-load ratio test strikes a reasonable balance by providing some additional quality assurance in a timely manner. If the orifice-, nozzle-, or venturi-type fuel flowmeter failed the abbreviated fuel flow-to-load ratio test, then it would appear that the primary element may also have a problem. Therefore, upon failure of an abbreviated fuel flow-to-load ratio test, the facility would be required to inspect the primary element and to repair or replace it, as necessary. The rules for data validation upon failure of the fuel flow-to-load ratio are not parallel with the procedures for data validation following failure of the volumetric stack flow-to-load ratio test in that there is no conditional validation of data. A number of utilities have emphasized that they wish to spend less time and effort preparing and evaluating quarterly reports for units using Appendix D, which are generally smaller and less frequently operated than coal-fired units or oil-fired units that choose to use CEMS (see Docket A-97-35, Item II-E- 33). The concept of conditional data validation for fuel flowmeters is not consistent with this objective, because it would introduce additional complexity into the process, would require significantly more time and resources to quality-assure the data, and might require additional DAHS programming. Therefore, the Agency is not proposing the use of conditional data validation for fuel flowmeters. (c) Fuel Flowmeter Quality Assurance Testing Frequency Background Section 2.1.6.1 of Appendix D, as revised by the May 17, 1995 direct final rule, requires regular quality assurance ``recalibrations'' (accuracy tests) of fuel flowmeters at least annually (once every four calendar quarters). For fuel flowmeters that were not used on a regular basis, such as fuel flowmeters used to measure the usage of emergency fuel or backup fuel, or flowmeters installed on peaking units, owners or operators are allowed to do flowmeter accuracy tests once every four quarters when the unit actually combusts the fuel measured by the flowmeter, rather than once every four calendar quarters. Flowmeters can be retested either by using one of the methods incorporated by reference in section 2.1.5.1 of Appendix D to part 75 or by an in-line comparison of the fuel flowmeter against a ``master'' fuel flowmeter using the procedure in section 2.1.5.2 of Appendix D. Some utilities have expressed concern about the annual fuel flowmeter testing requirement (see Docket A-97-35, Items II-D-20, II-E- 13, II-E-14). In many cases, it is neither practical nor cost-effective to modify the fuel pipes (e.g., to install a parallel length of pipe) to allow installation of a master fuel flowmeter for comparison testing. Thus, most utilities must remove a fuel flowmeter from the pipe and return it to a laboratory or to the manufacturer to be retested. In some cases, especially for oil flowmeters, this can be difficult. Some utilities have raised the issue of whether there should be a minimum time period that a fuel flowmeter is used before a quality assurance test is required. For instance, a utility might test its unit's burners once each quarter for a few hours to ensure that the unit can be operated when needed and may not operate for the rest of the quarter. Under the current rule, the fuel flowmeter would have to be quality assurance tested after four such operating quarters, even though the flowmeter was only used for a few hours in those calendar quarters. Discussion of Proposed Changes Today's proposed rule includes a provision that only those calendar quarters in which the fuel measured by the fuel flowmeter is combusted for at least 168 hours would count toward determining the next quality assurance test deadline. The 168-hour time period [[Page 28095]] is roughly equivalent to one week of operation while combusting the fuel measured by a particular fuel flowmeter. A calendar quarter in which the fuel measured by a fuel flowmeter is combusted for 168 hours or more would be called a ``flowmeter operating quarter.'' For example, if a unit combusted oil for 200 hours in the first calendar quarter of the year, 10 hours in the second calendar quarter, 250 hours in the third calendar quarter, and 100 hours in the fourth calendar quarter, then only the first and third calendar quarters would be considered flowmeter operating quarters for the oil flowmeter. Only the first and third calendar quarters would count toward determining the deadline for the next required oil flowmeter accuracy test. In today's proposed rule, each fuel flowmeter would need to be accuracy tested at least once every four flowmeter operating quarters. However, the deadline for testing infrequently-used meters could not be extended indefinitely. No more than 20 calendar quarters (five years) would be allowed to elapse between successive flowmeter accuracy tests, regardless of the number of ``flowmeter operating quarters'' that have elapsed since the last test. The interval between successive quality assurance tests could also be extended for up to 20 calendar quarters if the quarterly fuel flow rate-to-load procedures in proposed section 2.1.7 of Appendix D were implemented. Rationale In evaluating the frequency of fuel flowmeter accuracy testing, EPA considered simply extending the less strict requirement for fuel flowmeter quality assurance testing for peaking units, backup fuel, and emergency fuel to apply to all units and all fuel flowmeters. Thus, quality assurance testing would be required once every four quarters in which the unit combusted the fuel measured by the flowmeter. One industry representative recommended that the Agency require fuel flowmeter calibrations once every four unit operating quarters, where a unit operates at least 168 hours in the quarter (see Docket A- 97-35, Item II-E-13). This approach would treat all fuel flowmeters the same, whether they were used for primary, emergency, or backup fuel. Another utility suggested that the Agency consider creating some sort of diagnostic test comparing the flow rate of the fuel flowmeter to the unit load (generation) to determine whether the fuel flowmeter readings are degrading over time, rather than specifying a particular frequency for accuracy testing (see Docket A-97-35, Item II-E-22). Although this suggestion was originally referring to problems with corrosion of an orifice plate, such a test could also be used for other types of fuel flowmeters as a check on the quality of fuel flowmeter data. The Agency also considered extending the typical time between accuracy tests to the equivalent of two years. This time was suggested by a member of the AGA subcommittee responsible for the drafting of AGA Report No. 7 for turbine-type flowmeters (see Docket A-97-35, Item II- E-17). The Agency also considered extending the typical time between accuracy testing to 12 calendar quarters--the equivalent of three years. Three years is the period of time that records must be retained in a file at the source under Sec. 75.54 (or proposed Sec. 75.57). The Agency also considered allowing fuel flowmeters to continue for up to five calendar years between accuracy tests. This is similar to the current provision in section 2.1.5.2 of Appendix D, which allows a reference fuel flowmeter to be accuracy tested as seldom as once in five calendar years, if the in-line comparison with a master fuel flowmeter shows a 1.0 percent or less difference in their flow rates. A five-year test cycle offers certain administrative advantages. For instance, fuel flowmeters used to provide heat input data for the heat input-versus-load correlation of Appendix E could be accuracy-tested before each Appendix E test (i.e., once every five years). In addition, the five calendar-year period would ensure that fuel flowmeters are tested by the time the unit's operating permit is renewed. Facilities might find this time cycle easier to determine than a time period based upon a number of calendar quarters. However, test data would need to be retained for five years, rather than for three years, the recordkeeping period for most records under part 75. However, the Agency is not proposing this option because five years is far too long a period of time to allow a unit to continue with no checks at all upon the quality of its data. Such an approach would allow the use of data from a fuel flowmeter that potentially had been reading inaccurately for the previous five years. Another option that EPA evaluated was to establish different fuel flowmeter quality-assurance testing frequencies depending on the fuel measured by the fuel flowmeter. Under this approach, oil flowmeters would need to be tested every four calendar quarters in which oil was combusted. Gas flowmeters would only need to be tested once every five years. The two fuels would be treated differently because units emit less NOX and far less SO 2 when combusting gas than when combusting oil. In addition, gaseous fuels, particularly pipeline natural gas, should be less corrosive; therefore, a gas flowmeter should be less likely to degrade than an oil flowmeter. EPA believes that today's proposed approach to reducing the fuel flowmeter quality assurance testing frequency takes into account many of the concerns raised by utilities. All unit types and fuel types would have the same frequency of testing. This would avoid confusion that could follow from an approach that set different requirements for fuels or units that are used less frequently. A group of utilities had indicated that they prefer a more consistent approach (see Docket A-97- 35, Item II-E-13). Under today's proposal, infrequently-used fuel flowmeters (e.g., meters for backup fuel or emergency fuel) would only need to be calibrated once every five years. When a facility renews its operating permit, the permitting agency could verify that all fuel flowmeters have been tested at least once in the previous five years. The minimum period of 168 hours of fuel flowmeter usage which defines a ``flowmeter operating quarter'' is consistent with the definition of a ``QA operating quarter'' in Appendix B in today's proposed rule for the quality assurance of CEMS. The Agency believes that using a consistent minimum number of hours in a calendar quarter for both CEMS and fuel flowmeters will make implementation easier for facilities and air regulatory agencies. In addition, 168 hours should be a sufficiently long period of time to ensure that short-term usage of backup fuel or emergency fuel or short-term tests of a unit do not trigger unnecessary quality assurance testing. Today's proposed rule would also provide more flexibility in the methods that could be used for fuel flowmeter quality assurance testing. As discussed above in Section III.P.2 of this preamble, a new testing procedure has been proposed that would allow a facility to test flow rate-to-load ratio of the fuel flowmeter while leaving it installed. Thus, the Agency believes that the overall burden of fuel flowmeter testing has been significantly reduced. In addition to the reduced frequency of testing discussed above, the Agency believes the less burdensome testing procedures should address concerns of the regulated community. The Agency requests comment on whether facilities would prefer to base [[Page 28096]] the frequency of fuel flowmeter quality assurance testing on the type of fuel used or the amount of time the fuel flowmeter is used. Under the first approach, gas flowmeters would receive greater regulatory relief. Under the second approach, which is being proposed in today's rule, infrequently-used flowmeters (typically oil flowmeters) would receive greater regulatory relief. (d) Orifice, Nozzle, and Venturi Visual Inspections Background Section 2.1.6 of Appendix D, as revised in the May 17, 1995 direct final rule, created special provisions for the ongoing quality assurance testing of orifice fuel flowmeters. Orifice-, nozzle-, and venturi-type fuel flowmeters are designed and installed within a set of physical specifications, such as the orifice diameter (see Docket A-97-35, Item II-D-13). Maintaining these physical specifications determines the flowmeter's ability to read accurately. Thus, it is not necessary to take an orifice-, nozzle-, or venturi-type flowmeter out of line and send it to a laboratory to determine its accuracy. After installation of an orifice-, nozzle-, or venturi-type flowmeter is complete, the two major factors that contribute to error in flow readings are: drift in the transmitters (or transducers) which determines the total pressure, differential pressure and temperature, and corrosion of the primary element (e.g., the orifice plate) itself. Quality assurance testing of the transmitters is discussed in the next section of the preamble. In order to identify cases where error might result from corrosion of the orifice plate, the May 17, 1995 direct final rule added a requirement for an annual visual inspection of the orifice plate. If an orifice plate fails the inspection, then the facility must perform a test on the transmitters during the next calendar quarter. A procedure for visual inspections is given in Appendix B of part 2 of American Gas Association (AGA) Report No. 3, which is one of the accepted standards for installation and use of orifice flowmeters. Some facilities have expressed concern with the frequency of visual inspections (see Docket A-97-35, Items II-D-20, II-E-13, II-E-14). This process must be done either with a tool, such as a boroscope, or else the primary element must be removed from the pipe and lifted out to be inspected. In the case of large, heavy orifices, it is necessary to use a crane to remove the orifice. Fuel must not be flowing through the pipe while the orifice plate is being removed (see Docket A-97-35, Item II-E-8). The current provisions of Appendix D to part 75 do not explicitly state the consequences of failing a quality assurance test. Section 2.1.5.1 of Appendix D states that if a fuel flowmeter exceeds the flowmeter accuracy of2.0 percent of the upper range value, then the flowmeter may not be used under part 75. Section 2.1.5.2 states that if a fuel flowmeter's accuracy exceeds 2.0 percent of the upper range value, then the flowmeter must be recalibrated to meet that accuracy, or it must be replaced with another flowmeter that meets the specification. Neither section explicitly states the impact upon the validity of data if a test is failed. However, if fuel flowmeter systems are to be treated parallel with continuous emission monitoring systems under Sec. 75.21(e)(2), the consequences of failing a quality assurance test for a fuel flowmeter or an inspection of the primary element should result in the monitor being considered out-of-control and the data being considered invalid. In section 2.1.6.1 of Appendix D, the specific consequence of failing a visual inspection of the primary element is that the transmitters must be tested in the following calendar quarter, rather than waiting until the regular annual calibration is required. However, no mention is made of any mandatory corrective action(s) to eliminate the corrosion problem. Discussion of Proposed Changes Section 2.1.6.6 of Appendix D in today's rulemaking proposes to require visual inspections of primary elements (i.e., orifice, nozzle or venturi) at the frequency recommended by the manufacturer or once every three years, whichever is more frequent. The Agency solicits comment on the proposed frequency of visual inspections. The proposed rule would also explicitly require repair or replacement of the primary element and invalidation of data when a visual inspection is failed. Once the primary element is replaced or repaired, the new or repaired primary element would have to demonstrate that it meets the overall flow rate accuracy of 2.0 percent of the upper range value. This could be demonstrated by showing that the new or repaired primary element meets the design and installation requirements of AGA Report No. 3 or ASME MFC-3M, the same methods required for initial certification. Alternatively, the flow rate accuracy could be demonstrated by testing the fuel flowmeter against a reference fuel flowmeter using the provisions of section 2.1.5.2 of Appendix D. Finally, whenever a primary element is repaired, the fuel flowmeter transmitters would also have to be tested before the fuel flowmeter is used to provide quality assured data. Rationale During the process of reviewing certification applications for units using orifice flowmeters, the Agency learned of one plant where orifice corrosion was a serious problem. This utility had an orifice flowmeter which had been installed in the 1960's. This utility did not have documentation of the standard used to install the orifice as a demonstration of the meter's accuracy. In order to qualify for certification, the utility inspected the orifice. The utility personnel discovered that the orifice had been completely eaten away and was incapable of reading the flow rate (see Docket A-97-35, Item II-E-22). The utility replaced the orifice before it was able to have its fuel flowmeter certified. In addition, it was required to invalidate the flow rate data from the orifice meter and substitute for the missing data. Based upon this experience, the Agency believes that corrosion of an orifice can be a problem, and that in severe cases of corrosion, replacement of the orifice is necessary. Despite this, many utilities have expressed concern over the difficulty of removing an orifice from place for visual inspection (see Docket A-97-35, Items II-D-20, II-E-13, II-E-14), because removal requires halting the flow of gas through the pipeline in order to remove the orifice, which can be expensive (see Docket A-97-35, Item II-E-8). Utilities have provided the Agency with several suggestions for reducing the frequency of primary element inspections. One industry group recommended that the Agency reduce the inspection frequency to once every five years, to be coordinated with renewal of the plant's operating permit under title V of the Act (see Docket A-97-35, Items II-D-20, II-E-13, and II-E-14). One utility representative mentioned that most orifice manufacturers recommend an inspection once every three years; thus, he recommended that the Agency require visual inspections the earlier of once every three years or the time period specified by the manufacturer (see Docket A-97-35, Item II-D-41). Another utility suggested that the Agency consider creating some sort of diagnostic test comparing the flow rate of the fuel flowmeter to unit load (generation) to determine whether the fuel flowmeter readings are degrading [[Page 28097]] over time, rather than specifying a particular time period (see Docket A-97-35, Item II-E-22). EPA agrees that it would be helpful to facilities to reduce the frequency of visual inspections from their current annual frequency. Having considered all of the options suggested by the utilities, the Agency is proposing that the primary element of all nozzle, venturi and orifice fuel flowmeters be visually inspected at the frequency recommended by the manufacturer or once every three years, whichever is the more frequent. The Agency believes that up to three years between visual inspections is a technically sound period of time that will assure the quality of fuel flow rate data, while providing regulatory relief from the current annual requirement. The Agency also has reconsidered the consequences of failure of a visual inspection. The May 17, 1995 direct final rule added a requirement to test a flowmeter's transmitters in the calendar quarter following a failed inspection, but the rule does not explicitly require that the primary element be repaired or replaced, nor does it explicitly require data from the fuel flowmeter to be invalidated. Today's proposed rule would require the primary element to be removed following a failed visual inspection and would require the problem to be corrected. The Agency believes that it is appropriate to provide two options for correcting the problem: either replace the element with a new one or repair it. This would provide flexibility to facilities, while still assuring that the fuel flowmeter will be repaired to give quality assured data. Today's proposed rule would also change the timing of the requirement for fuel flowmeter transmitter or transducer testing if a primary element fails its visual inspection. The Agency believes that it would be appropriate also to test the fuel flowmeter transmitters before the fuel flowmeter is placed into service again. This would be a more thorough quality assurance check of the entire fuel flowmeter than simply addressing the problem with the primary element. Thus, when the fuel flowmeter is placed into service again, its accuracy would be tested as fully as possible. In addition, EPA proposes to remove the requirement for a test on the flowmeter transmitters in the calendar quarter following a failed visual inspection. This requirement might be appropriate if it seemed that transmitter drift was likely to be a problem or if the Agency had no other means of assuring the quality of the data from the flowmeter after a problem with the primary element was known to have occurred. However, the Agency believes that problems with the primary element are separate from problems with drift in the transmitters. Because today's proposal would require a check on the fuel flowmeter transmitters after repair or replacement of the primary element, requiring an additional test of the transmitters in the following calendar quarter appears to be unnecessary. The proposed rule gives procedures for data validation when a primary element fails a visual inspection. The element would have to be replaced or repaired, and the transmitters would have to be tested before data would again be valid from the fuel flowmeter. During the period in which the flowmeter data are considered invalid, the appropriate missing data substitution procedures would be used. The Agency has clarified that these data validation procedures would also apply to failures of other fuel flowmeter quality assurance tests. EPA believes that this will make facilities' obligations clearer. In addition, the Agency believes that fuel flowmeter systems should be treated as consistently as possible with CEMS. Consistent treatment simplifies the part 75 requirements and is more equitable for sources using different monitoring approaches. (e) Orifice, Venturi, and Nozzle Flowmeter Transmitter Testing Background As discussed previously, once an orifice-, nozzle-, or venturi-type flowmeter has been installed, one of the major causes of error in the measured flow rates is drift in the transmitters or transducers that determines the total pressure, differential pressure, and temperature. The flow measurement error for these types of flowmeters is a combination of the errors in these individual transmitters or transducers and a constant error value associated with the physical dimensions of the primary element. The May 17, 1995 direct final rule added a requirement that flowmeter transmitters be tested at least annually. The transmitters are also required to be retested in the next calendar quarter if the overall flow rate error is greater than 1.0 percent of the upper range value of the flowmeter. For practical purposes, this requires a facility to know the error from the physical dimensions of the primary element in order to determine if the flowmeter meets the overall accuracy requirement. Some utilities asked the Agency how to determine the overall flowmeter accuracy from individual transmitter values (see Docket A-97- 35, Item II-E-31). EPA addressed this issue in Policy Guidance (see Docket A-97-35, Item II-I-9, Policy Manual, Question 10.17). This guidance included a formula for calculating total flowmeter accuracy from error in transmitter readings for differential pressure, static pressure and temperature, and error from all other sources (i.e. physical dimensions of the primary element). Some utilities indicated that they do not always have information available on the constant error from other portions of the primary element (see Docket A-97-35, Item II-E-13). The policy guidance also indicated that a facility could report test results electronically using the highest amount of error from any of the three transmitters. Provided that the highest error from an individual transmitter is 1.0 percent of the upper range value of the transmitter or less, the overall flowmeter accuracy will be less than 2.0 percent of the upper range value (see Docket A-97-35, Item II- I-10). EPA has also observed that transmitter test data reported for orifice-, nozzle-, and venturi-type flowmeters have not been consistent. Some facilities test each transmitter once at three different levels, including a low, middle, and high value (see Docket A-97-35, Item II-D-16). Others test each transmitter at five different levels, including zero, full scale, and three intermediate levels (see Docket A-97-35, Item II-D-17). The Agency had previously issued some guidance on reporting test results, both for orifice flowmeters and other flowmeters (see Docket A-97-35, Items II-I-4, p. 3-58, and II-I- 9, Policy Manual, Questions 10.17 and 12.27). However, this guidance appears to have been insufficient, as utilities have continued to request guidance in how to perform and report test results (see Docket A-97-35, Item II-D-21). Questions have included the number of levels at which transmitters should be tested, whether all of these levels must be non-zero, the number of times the transmitter should be tested at a particular level, if results may be reported in hardcopy or should be reported electronically, and how data should be reported electronically. Discussion of Proposed Changes Today's proposed rule would make the requirement to assess the total accuracy of orifice-, nozzle-, and venturi-type fuel flowmeters from the transmitter/transducer test results an option. As an alternative, proposed section 2.1.6.5 in Appendix D would allow each of the three transmitters (static pressure, differential pressure, and temperature) individually to meet [[Page 28098]] an accuracy specification of 1.0 percent of the upper range value of the transmitter. Today's rulemaking also proposes a procedure in section 2.1.6.1 of Appendix D for testing the accuracy of orifice-, nozzle-, and venturi- type fuel flowmeters. Each transmitter would be calibrated against NIST-traceable reference values at least once at the zero level and at a minimum of two other levels across the range of values that the transmitter reads during normal unit operation. Note that in many instances this would be a portion of the full-scale range of the transmitter, rather than the entire range. In addition, revised section 2.1.6.2 of today's proposed rule includes the new Equation D-1a to clarify how to calculate the error from an individual transmitter. Finally, today's proposal would clearly specify the consequences of failure of an accuracy test on transmitters in section 2.1.6.5 of Appendix D. Just as CEM data are considered invalid from the time that a quality assurance test is failed until the test is subsequently passed, data from a fuel flowmeter would be considered invalid from the date and time of a failed transmitter accuracy test until the date and time of a passed transmitter accuracy test. Rationale The Agency considered two main options for determining the accuracy of a transmitter or transducer of an orifice-, nozzle-, or venturi-type fuel flowmeter. In the first approach (which is consistent with current policy guidance), these types of fuel flowmeters would be required to meet an accuracy of 2.0 percent of the upper range value of the total flow rate of the fuel flowmeter. The accuracy would be determined using the square root of the sum of the squares of all sources of error in the fuel flowmeter, according to the following equation: [GRAPHIC] [TIFF OMITTED] TP21MY98.000 Where: dq v /qv = Error in the volumetric flow rate due to transmitter drift at a given level; K = Original error resulting from installation of orifice (including all other variables); dPf = Average difference between static pressure transmitter reading(s) and reference static pressure reading(s) at a given level; Pf = Average reference static pressure reading at a given level; dP = Average difference between differential pressure transmitter reading(s) and reference differential pressure reading(s) at a given level; P = Average reference differential pressure reading at a given level; dT f = Average difference between temperature transmitter reading(s) and reference temperature reading(s) at a given level; and Tf = Average reference temperature reading at a given level. If the error calculations for error from the primary element of the fuel flowmeter were not available, then the facility could use a default value of 1.0 percent of the upper range value error from all parts of the fuel flowmeter except for the differential pressure, static pressure, and temperature transmitters. (In other words, the factor ``K'' in the equation above would be equal to 1.0 percent of the upper range value.) However, this would almost certainly trigger the requirement for recalibration or retesting of the accuracy of the transmitters in the next calendar quarter because the fuel flowmeter accuracy would exceed 1.0 percent of the upper range value. Based upon statements from the American Gas Association, it is the Agency's understanding that for an orifice-, nozzle-, or venturi-type fuel flowmeter meeting AGA Report No. 3 or ASME MFC-3M, the maximum error from portions of the meter other than the transmitters should be 1.0 percent of the upper range value (see Docket A-94-16, Item II-F-2, and this Docket, A-97-35, Item II-E-18). In the second approach to determining error for orifice-, nozzle-, and venturi-type fuel flowmeters, each transmitter or transducer would be tested separately for accuracy, and each transmitter or transducer would be required to meet an accuracy specification of 1.0 percent of the full scale range of the transmitter. Under this approach, it would no longer be necessary to determine the total error in the flowrate from the fuel flowmeter. Because this proposal would eliminate the calculation of the total error in flowrate, there would no longer need to be a requirement to retest the accuracy of the transmitters in the next calendar quarter when the total fuel flowmeter accuracy exceeds 1.0 percent of the upper range value. In today's rule, EPA proposes to allow both of the approaches described above for calculating the total flowmeter accuracy. The second approach (i.e., calculating individual transmitter accuracy) is simpler than calculating the total error in the flow rate, although it is less directly related to the accuracy of SO2 mass emission rate and heat input measurements than the fuel flowrate. An individual transmitter accuracy specification of 1.0 percent of the full scale of each transmitter would be slightly stricter than a total fuel flowmeter accuracy specification of 2.0 percent of the upper range value of the fuel flowmeter, because one transmitter could potentially have an error greater than 1.0 percent of its full scale range while the entire error in the fuel flowrate would still be less than 2.0 of the upper range value of the fuel flowmeter. Thus, the option of calculating the total error in the fuel flowrate has been retained in today's proposal. At least one industry representative suggested allowing both approaches of calculating accuracy when testing transmitters of an orifice-, nozzle-, or venturi-type fuel flowmeter (see Docket A-97-35, Item II-E-24). The Agency considered two main methodologies for transmitter testing on orifice-, nozzle-, and venturi-type flowmeters. The first method would be to require a five-point test that checks the linearity of the transmitter. The transmitter would be tested against an NIST traceable method (e.g., testing a pressure transmitter against an NIST traceable deadweight transmitter) at the following percentages of the full scale range of the transmitter: 0.0 percent, 20.0 to 30.0 percent, 40.0 to 60.0 percent, 70.0 to 80.0 percent, and 100.0 percent. This is the general approach that was taken by many utilities that provided transmitter calibration results to EPA (see Docket A-97-35, Items II-D- 26 through 28). The second method would be to require a comparison to an NIST traceable transmitter at the zero level and at least two other levels across the range of readings on the transmitter or transducer. This would be different from the first method in that the transmitter would only need to be tested across the range where the transmitter is [[Page 28099]] actually used. For example, if a fuel flowmeter transmitter's readings never rise higher than 60.0 percent of the full scale range of the transmitter, then the transmitter could be tested at 0.0 percent, 30.0 percent, and 60.0 percent of full scale. These procedures are reflected in the proposed revised section 2.1.6.1 of Appendix D. The Agency is proposing the second method in today's rule, i.e., that each individual transmitter must be tested at three or more points across its normal range of readings. EPA realizes that it is standard industry procedure to test a fuel flowmeter at five levels across its entire range (see Docket A-97-35, Item II-E-24). However, the Agency is aware of at least one case where a fuel flowmeter failed to meet an accuracy specification of 2.0 percent of the upper range value when it was tested at 100.0 percent of the upper range value. However, the fuel flowmeter was never used to measure a rate greater than roughly 55.0 percent of the upper range value (see Docket A-97-35, Item II-D-15). If this flowmeter had only been required to test across the range where the fuel flowmeter actually measured fuel flow rates, it would have met the accuracy specification. Section 2.1.5 requires fuel flowmeters that are tested against a master fuel flowmeter to be tested across the range of measured fuel flowrate only. Requiring testing of each transmitter at three or more points across the range of all readings would still ensure that the transmitter reads accurately across all readings, while reducing the possibility that the transmitter might fail an accuracy test because of a high error reading at the high end of the transmitter's range where the transmitter is never used. At least one utility has mentioned that this would be helpful (see Docket A-97-35, Item II-E-24). The Agency solicits comment on the proposed approach. Today's proposed rule also includes Equation D-1a for calculating error from an individual flowmeter transmitter. The Agency feels that this would clarify the calculation. It also would prevent the possible confusion that would occur if a facility attempted to use the existing Equation D-1, which is designed for a fuel flowmeter that is compared to another fuel flowmeter. Finally, under today's proposal, when a transducer or transmitter test is failed, a fuel flowmeter would be considered out-of-control, and its data would be considered invalid until the date and time the transmitter is retested and meets an accuracy of 1.0 percent of its full scale. (f) Reporting of Fuel Flowmeter Testing Data Background As mentioned above in Section III.P.5 of the preamble, utilities have had questions about how to report the results of their fuel flowmeter testing data. In certification applications and quality assurance testing results, utilities have reported test data in a variety of ways. In some cases, the Agency was unable to determine the flowmeter accuracy from the testing information provided because data were not labeled as reference flow rate data, flowmeter data, or accuracy data. For example, for turbine flowmeters, data on the reproducibility of the ``K-factor'' was often presented. However, these are not flow rate data, nor is it clear what the accuracy of the flow rate is (see Docket A-97-35, Item II-D-9). Sometimes data were presented in tables. Other data were presented in graphs (see Docket A- 97-35, Item II-D-9). In many cases, Agency or state environmental agency staff needed to request additional information from utilities to determine if they had met the accuracy requirement for fuel flowmeters (see Docket A-97-35, Items II-C-3, II-C-5). To clarify the requirements for certification applications for fuel flowmeters, the Agency issued policy guidance about the type of information to provide (see Docket A-97-35, Item II-I-9, Policy Manual, Question 12.27). This guidance included a sample table with an example of how to submit information for a fuel flowmeter that is tested against a master meter or flow prover reference value. Discussion of Proposed Changes EPA proposes to add a sample table to Appendix D (Table D-1) for summarizing the results of accuracy tests of fuel flowmeters that are calibrated by comparison against other fuel flowmeters or a prover. In addition, EPA proposes to add a separate table for summarizing the results of calibrations of the transmitters or transducers of an orifice-, nozzle-, or venturi-type fuel flowmeter. Rationale In today's proposed rule, EPA would provide clarification in the form of a table for summarizing the quality assurance test results of fuel flowmeters that are compared against other fuel flowmeters or a prover. A second table is provided for summarizing the results of calibrations of transmitters or transducers of an orifice-, nozzle-, or venturi-type fuel flowmeter. This second table accounts for differences in the testing procedure for transmitters or transducers. In both cases, EPA has tried to make clear what critical information would have to be reported in order to demonstrate that the fuel flowmeter (or the transmitter of an orifice-, nozzle-, or venturi-type fuel flowmeter) meets the accuracy specification. In addition, EPA will design revised electronic record types with this type of information so that test results may be more easily reported electronically. The Agency is aware that this has been difficult or confusing for some utilities (see Docket A-97-35, Items II-D-23, and II-I-9, Policy Manual, Question 12.27). The Agency also considered adding a sample graph for reporting accuracy data. However, EPA feels that it would be easier to compare the data in tabular format and to enter it into the electronic data format than to enter values from a graph. Most of the graphs provided to EPA have been relatively easy to read, and there appears to be less of a need for an example to be included in Appendix D (see Docket A-97- 35, Item II-D-9). 7. Use of Uncertified Commercial Gas Flowmeter Background Currently, a facility using Appendix D may either install its own gas flowmeter or use a commercial gas flowmeter owned by a pipeline natural gas supplier, provided that the meter meets the reporting and accuracy requirements of Appendix D, including initial certification and continuing quality assurance requirements. Some utilities have suggested to EPA that they would like to be able to use data from the commercial billing of pipeline natural gas without having to demonstrate that the gas flowmeter meets initial certification and continuing quality assurance requirements (see Docket A-97-35, Items II-D-45, II-D-49). Those utilities assert that because the amount of gas measured is already subject to market forces, the monitoring should be sufficiently accurate for the Acid Rain Program. Utilities have mentioned that gas companies often are already conducting meter calibrations as quality assurance, but utility customers generally do not have access to this information (see Docket A-97-35, Items II-D-49, II-E-33). Facilities would find it advantageous to rely upon their commercial billing charges for accounting for pipeline natural gas usage because they would need to devote less time, effort, and money to the maintenance of gas fuel flowmeters. This is particularly desirable to facilities since the SO2 emissions from pipeline [[Page 28100]] natural gas are extremely low compared to the SO2 emissions from other fuels. Discussion of Proposed Rule Changes Proposed section 2.1.4.2 of Appendix D would allow facilities to record and report the gas flow rate, the heat input rate, and emission values based on gas flowmeter readings from a flowmeter used for commercial billing of pipeline natural gas without meeting the certification requirements of section 2.1.5 of Appendix D or the quality assurance requirements of section 2.1.6 of Appendix D under specified conditions. Relief from the certification and quality assurance requirements for gas flowmeters used for commercial billing would be limited to flowmeters where the gas flowmeter is used for commercial billing under a contract with another company having no common owner with the unit(s) served by the flowmeter, which would exclude any gas flowmeters used for transfers of gas between different divisions, subsidiaries, or affiliates of the same company. If the commercial billing gas flowmeter would be used without undergoing certification or quality assurance under part 75 requirements, then the designated representative would need to report hourly records of the gas flow rate, the heat input rate, and emissions due to combustion of pipeline natural gas, as well as heat input rate for each unit if the commercial billing gas flowmeter is on a common pipe header. This would be similar to the reporting currently done for a certified gas flowmeter, but no quality assurance records would be required. The quarterly report would contain record types 303 for fuel flow rate and heat input rate, record type 314 for the SO2 mass emission rate, either record type 320 or 323 for the NOX emission rate in lb/mmBtu, and either record type 330 or 331 for CO2 mass emissions. It also would be necessary for the designated representative to identify the commercial billing gas flowmeter in Table B (electronic record type 510) of the monitoring plan for the unit. So long as the records from the commercial billing gas flowmeter are the values used for commercial billing, the designated representative would report those values from the commercial billing gas flowmeter without adjustment. If the records from the commercial billing gas flowmeter are not consistent with the values used for commercial billing because of some problem that needs to be reconciled between the gas vendor and the facility customer, then the designated representative would consider the readings from the commercial billing gas flowmeter to be invalid for that billing period and would report hourly records using the missing data procedures for fuel flowmeter data found in section 2.4 of Appendix D for all hours of gas combustion during that billing period. A facility would not be able to use the commercial billing value in the quarterly report if the commercial billing value was different from the value on the commercial billing gas flowmeter. Rationale Utilities have suggested that the purchase of pipeline natural gas from a vendor is subject to market forces that ensure accurate monitoring (see Docket A-97-35, Item II-D-49). Utilities have stated that gas vendors already have procedures for certification and meter calibration and that the gas vendors have an even greater incentive than utilities to maintain a high monitor ``uptime'' (i.e., availability) for gas fuel flowmeters. Typically, utilities will work together with their gas vendors if they believe there is any sort of discrepancy in their monthly billing for pipeline natural gas (see Docket A-97-35, Items II-D-33, II-E-33). The Agency believes that this argument is reasonable. However, EPA also understands that some utilities require their gas vendor to correct their billing values based upon the evidence of the utility's own gas flowmeters. In addition, it is likely that utilities will be combusting more pipeline natural gas in the future as they respond to current and potential future environmental requirements for reducing NOX and CO2 . Therefore, the Agency believes that there must be conditions placed upon reporting emissions and heat input for the Acid Rain Program from gas flowmeters used for commercial billing if the gas flowmeters will not be required to meet the certification and quality assurance requirements of part 75. The Agency is proposing to limit the waiver from certification and quality assurance requirements to commercial billing gas flowmeters that are used in billing transactions between companies with entirely different ownership (e.g., a pipeline natural gas vendor and a separate electric utility company with no owners in common). Some utilities requested the relief from quality assurance requirements based upon the reasoning that a gas vendor would do its own quality assurance and maintenance, and perhaps with better accuracy than a utility would be able to maintain, but the utility would not necessarily have access to the test results and would not have control over what quality assurance might occur (see Docket A-97-35, Items II-D-49, II-E-33). This reasoning is sound if the utility and the gas vendor have no common owners, but it would not necessarily be sound if a gas supplier were part of the same company as the electric utility. Also, utilities suggested that a gas vendor may have an incentive to overstate the amount of gas in order to bill more, rather than having an incentive to underestimate or under-report (see Docket A-97-35, Item II-D-49). Once again, this argument is reasonable if the gas vendor is a separate entity, but may not be reasonable if the gas supplier has common owners with the electric utility. Therefore, today's proposed rule includes a limitation on the waiver from certification and quality assurance requirements for commercial billing gas flowmeters to those gas flowmeters used for commercial billing between companies with separate ownership. EPA solicits comment on the proposed approach of allowing the use of uncertified fuel flowmeters for purposes of determining emissions and heat input in the limited circumstances described above. EPA has proposed in today's rule that a facility may only report data from a commercial billing gas flowmeter if the data are used in a commercial transaction. A group of utilities suggested that the Agency allow facilities to report quarterly SO2 emissions based on gas supplier data, including any reconciliation that has taken place (see Docket A-97-35, Item II-D-45). Such a reconciliation between a gas vendor and its customer may occur if the customer believes there is a discrepancy in their monthly billing for pipeline natural gas (see Docket A-97-35, Items II-D-33, II-E-33). If a facility and its gas vendor determined that gas supply information from a fuel flowmeter were not sufficiently accurate to purchase gas, then the Agency presumes the gas supply information is also not sufficiently accurate for emissions accounting. The Agency also considered whether a facility should be able to use the reconciled gas volumes agreed upon for billing if that value were not from the commercial billing gas flowmeter. In general in the Acid Rain Program, hand-typed corrections to emissions data are not permitted (see Docket A-97-35, Item II-I-14), with the primary exception of cases where sound engineering judgement indicates there is an obvious error that cannot exist, such as a negative concentration reading. [[Page 28101]] Allowing a facility to enter a commercial billing value by hand would contradict this basic reporting policy of the Acid Rain Program. Today's proposed rule also specifies the type and frequency of information that would be required to be reported by a facility concerning pipeline natural gas. Some utilities have requested the ability to report only a quarterly cumulative SO2 mass emission number for emissions from gas (see Docket A-97-35, Item II-D- 45). However, the Agency believes that there are several reasons for maintaining hourly heat input rate and emissions data during combustion of pipeline natural gas. First, hourly data is the most useful interval of data for air quality modeling in order to see if progress is being made in reducing emissions. Hourly data from combustion of pipeline natural gas will become even more important as more units switch to combusting pipeline natural gas in order to reduce their emissions. In addition, hourly data are easier to check for anomalous values than quarterly data. Further, hourly heat input rate data is necessary in order to determine the NOX emission rate when using the NOX-versus-heat input rate correlation of Appendix E to part 75. Also, since hourly data are already being recorded, reported, and processed by automated computer data acquisition and handling systems, a change to this requirement would require costly reprogramming for industry and for EPA. For all of these reasons, EPA is proposing that facilities continue to report hourly gas flow rates, heat input rates, and emissions from commercial billing gas flowmeters that are not required to meet the certification and quality assurance requirements of part 75. Q. Appendix G 1. Use of ASTM D5373-93 for Determining the Carbon Content of Coal Background Appendix G to part 75 provides procedures for determining CO2 emissions from fuel sampling and analysis instead of from a CO2 CEMS and a flow monitor. Section 2.1 of Appendix G includes a mass-balance equation for determining CO2 (see Equation G-1), the frequency for sampling fuel, and the specific methods for analyzing fuel for carbon content. Section 2.3 of Appendix G provides a method for determining CO2 mass emissions from a gas-fired unit from its heat input using Equation G-4. Some facilities use Appendix G procedures to determine CO2 mass emissions every day for their units. Other facilities might use the procedures of section 2.1 of Appendix G only to provide CO2 mass emissions during extended periods when CO2 data are missing from their CO2 CEMS, under the provisions of Sec. 75.36. A utility and its fuel analysis laboratory contacted EPA concerning use of an additional ASTM method for analysis of carbon content. The industry staff felt that the new infrared analysis method, ASTM D5373- 93, was the most up-to-date method and that this method should be at least as accurate as the methods specified in Appendix G to part 75 (see Docket A-97-35, Item II-D-25). Based upon the precision and bias information in the method, EPA approved its use under Sec. 75.66 (see Docket A-97-35, Item II-C-16). Discussion of Proposed Changes Today's proposed rule would allow the use of ASTM D5373-93, ``Standard Methods for Instrumental Determination of Carbon, Hydrogen, and Nitrogen in Laboratory Samples of Coal and Coke,'' for Section 2.1 of Appendix G to part 75. This method is for determining the carbon content of coal. ASTM D5373-93 would also be incorporated by reference in Sec. 75.6. Facilities would also continue to have the option to use ASTM D3178-89 to analyze coal for carbon content. Rationale EPA has previously approved the use of ASTM D5373-93 for analyzing the carbon content of coal (see Docket A-97-35, Item II-C-16). The Agency believes this method is of sufficient accuracy for use in the Acid Rain Program. In addition, EPA historically has accepted analytical methods from standard-setting organizations such as the American Society for Testing and Materials (ASTM). The Agency solicits comment on the use of ASTM D5373-93 for analyzing the carbon content of coal. 2. Changes to Fuel Sampling Frequency Background Section 2.1 of Appendix G (as revised by the May 17, 1995 direct file rule) specifies that fuel sampling should be done weekly for gas or oil for each shipment for diesel fuel and at least once per month for gaseous fuel. The sampling frequencies for diesel fuel and for gaseous fuel are consistent with the frequency for sampling under Appendix D to part 75. Most gas-fired and oil-fired units that perform fuel sampling for sulfur content under Appendix D also perform fuel sampling for carbon content. Today's proposed rule would reduce the frequency with which facilities need to sample oil or gas under Appendix D. Discussion of Proposed Changes The fuel sampling frequency specified in section 2.1 of Appendix G would be made consistent with the proposed requirements for Appendix D oil and gas sampling. Thus, all oil samples could be taken upon delivery, either from the delivery vessel itself or from the storage tank after a delivery is transferred. Gas samples would be taken monthly (for pipeline natural gas), for each shipment (for gases delivered in lots), or daily (for fuels that are analyzed daily for sulfur). Coal samples would continue to be taken weekly. Rationale Appendix D of today's proposed rule would reduce the required sampling frequency of oil and gaseous fuels delivered in lots. Based upon information provided by one utility, the variability of carbon content in oil is less than the variability of sulfur content (see Docket A-97-35, Item II-D-18). Some utilities have stated that they would prefer the procedures for sulfur and GCV to be similar (see Docket A-97-35, Item II-D-24). Based upon this statement, the Agency believes that facilities would also prefer to have consistent fuel sampling procedures for Appendices D and G. Therefore, the Agency believes it is appropriate to make the fuel sampling frequency for carbon analysis under Appendix G consistent with the fuel sampling frequency for sulfur content under Appendix D. Similarly, section 5.5 of Appendix F would be revised to make the gas sampling frequency consistent with Appendix D. The Agency solicits comment on the proposed changes to the fuel sampling frequency. 3. Addition of Missing Data Procedures for Fuel Analytical Data Background Appendix D provides procedures for substituting missing fuel analytical information, either for sulfur or GCV. However, Appendix G to part 75 does not specify what should be done if carbon content data are missing. Some software programmers asked EPA what missing data procedures should be used for carbon content data (see Docket A-97-35, Item II-E- 5). The Agency responded to this question at a public conference and in policy guidance (see Docket A-97-35, Items II-E-5, and II-I-9, Policy Manual, Question 6.3). In its policy guidance, EPA stated that facilities should ``[f]ill in the most recent carbon content . . . available for that fuel type (gas, oil or [[Page 28102]] coal) of the same grade (for oil) or rank (for coal). If at all possible, use a carbon content value from the same fuel supply.'' Discussion of Proposed Changes Today's proposed rule would allow facilities to substitute for missing carbon content prior to January 1, 2000, using either the most recent carbon content for that fuel type, grade and rank, or procedures parallel to those of Appendix D. Beginning January 1, 2000, facilities would substitute for missing carbon content data using procedures consistent with Appendix D. For gaseous fuels and for oil sampled manually, these procedures would provide for a conservative maximum carbon content value. Specifically, the permissible conservative carbon content values would be either the maximum carbon content measured in the previous calendar year or, if this information were not available, a default value based upon handbook fuel characteristics. For weekly coal samples or composite oil samples, CO2 mass emissions would be calculated using the highest carbon content from the previous four carbon samples available. Rationale Software programmers have already indicated that it is useful to have a procedure for filling in missing carbon content data for purposes of programming (see Docket A-97-35, Item II-E-5). Some utilities have stated that they would prefer the missing data procedures to be similar for both sulfur and GCV, even if both values are conservative (see Docket A-97-35, Item II-E-24). Therefore, the Agency believes that facilities would also prefer to have Appendix G missing data procedures for carbon content that are parallel with those for sulfur content and GCV in Appendix D. Thus, today's proposal would allow for missing data for manual oil samples or for gaseous fuel using the maximum carbon content measured in the previous calendar year or, if this information were not available, a default value based upon handbook fuel characteristics. In determining the conservative default carbon content values that would be used for missing data substitution in the event that no previous carbon content samples are available, the Agency consulted several handbook reference tables on fuel characteristics. Specifically, the Agency reviewed handbook values for the carbon content of coal (of various ranks), oil (of various grades), and gas (of different types). (see Docket A-97-35, Items II-I-18, II-I-19, II- I-20). In the case of coal, there was a fairly wide range of carbon content values for different ranks of coal. Therefore, today's rule would propose separate default carbon content values for Anthracite, Bituminous, and Subbituminous/Lignite. In contrast, the carbon content values for different grades of residual oil were fairly consistent. For this reason, today's rule proposes a single default carbon content value for all grades of oil. Finally, for gaseous fuels, the handbooks which were reviewed presented a fairly narrow range of values for natural gas but a much wider range of values for other types of gaseous fuels. Therefore, today's rule proposes a value for natural gas and a separate, conservative value for all other types of gaseous fuels. The Agency solicits comment on the proposed revisions to the missing data procedures under Appendix D. R. Reporting Issues 1. Partial Unit Operating Hours and Emission and Fuel Flow Rates Background For affected units that use CEMS to account for emissions under part 75, hourly emission rates of SO2 (in lb/hr), NOX (in lb/mmBtu), and CO2 (in tons/hr), and hourly heat input rates (in mmBtu/hr) are calculated using the applicable equations in Appendix F. For affected units that use fuel flow meters and fuel analysis (or default emission rates) rather than CEMS, the applicable equations in Appendices D, F and G (for certain gas-fired units) are used to determine the hourly SO2 and CO2 mass emission rates and heat input rates. For oil and gas-fired peaking units that use Appendix E to account for NOX emissions, the hourly NOX emission rates in lb/mmBtu are derived from a graph of NOX emission rate versus heat input rate, the hourly heat input rates being derived from the applicable equation in Appendix F. Under Sec. 75.54(b)(2), unit operating time is reported by rounding the actual operating time up to the nearest 15 minutes. The equations in Appendices D through G assume that each unit operating hour consists of a full 60 minutes of unit operation (or, for common stacks, that emissions are discharged through the stack for 60 minutes in each hour); the equations do not attempt to account for partial unit operating hours. This is a shortcoming in the current rule, because partial unit operating hours sometimes occur during periods of unit startup, shutdown, and malfunction. Therefore, to ensure accurate accounting of SO2 and CO2 mass emissions and unit heat input, part 75 should address the issue of partial unit operating hours. Note, that because NOX emission rates are measured with respect to heat input (lb/mmBtu), rather than with respect to time (lb/hr), this discussion is not relevant for NOX emission rate. Many vendors and utilities have asked EPA for guidance on how to calculate mass emission rates during partial unit operating hours (see, e.g., Docket A-97-35, Item II-D-4). The crux of the partial unit operating hour issue is when to adjust the emission data for unit operating time, before the reporting of hourly values or at the quarterly summation. For many units, there are very few hours of partial operation, and adjusting the data for operating time merely involves multiplying by 1, a seemingly inconsequential issue. For other units, such as peaking and cycling units, which start up and shut down often, the issue of how the data is reported is relevant because there can be a significant amount of partial unit operating hours. Definitive and standardized reporting requirements allow facilities and/or vendors to program their software such that their calculated result equals the result calculated by EPA. For SO2 and CO2 , the question is whether to report hourly emissions on a mass basis (i.e., lb or tons) or on a mass emission rate basis (i.e., lb/hr or tons/hr). For heat input, the question is whether to report the total hourly heat input (in mmBtu) or the hourly heat input rate (in mmBtu/hr). For example, suppose that a unit emits for a full 60 minutes in a particular clock hour at an SO2 concentration of 602.5 parts per million (ppm), a CO2 concentration of 10.0 percent, a volumetric flow rate of 4,000,000 standard cubic feet per hour (scfh), and a heat input rate of 300 mmBtu/hr. Suppose further that the same unit operates for only 15 minutes in the next hour and all of the parameters (i.e., SO2 and CO2 concentration, flow rate, and heat input rate) remain unchanged. If unit operating time is disregarded, the SO2 mass emission rate (calculated from Equation F-1 in Appendix F) would be the same (400 lb/hr) for both the partial operating hour and the full unit operating hour. Similarly, the CO2 mass emission rate would be the same (22.8 tons/hr) and the heat input rate would be the same (300 mmBtu/hr) for both the full and partial operating hours. The mass emission rates and heat input rate for the partial unit operating hour are the same as the full-hour values because they are based solely upon data recorded during unit operation, i.e., in [[Page 28103]] the first 15 minutes of the hour. The hourly average rates for the partial hour do not include ``zero'' values for the three 15-minute periods of unit non-operation during the clock hour (e.g., an SO2 emission rate of (400 lb/hr + 0 + 0 + 0)/4 = 100 lb/hr would not be appropriate). If the emission and heat input rates are adjusted by multiplying them by the operating time, then, for the full operating hour (i.e., operating time = 1.0), the SO2 and CO2 mass emissions and heat input would be, respectively, 400 lb SO2 , 22.8 tons CO2 , and 300 mmBtu. For the partial hour (operating time = 0.25), the corresponding values would all be divided by four, i.e., 100 lb SO2 , 5.7 tons CO2 , and 75 mmBtu, respectively. Software vendors and utilities have requested clarification as to whether hourly SO2 mass emission values should be reported as totals, in lb, or as rates, in lb/hr. As early as November of 1993, EPA stated that hourly SO2 mass emission values should be reported as rates in lb/hr. Then, when determining quarterly cumulative SO2 mass emissions, each hourly emission rate would be converted to a mass basis by multiplying it by the unit operating time (expressed as a fraction of an hour) for the same hour. Similarly, hourly heat input values would be expressed as rates, in mmBtu/hr, and hourly CO2 mass emissions would be expressed as rates, in tons/hr. Parallel issues were also addressed by the Agency's policy, for units that determine SO2 and CO2 mass emissions and heat input from fuel flow rates and fuel analyses under Appendix D to part 75 (see Docket A-97-35, Item II-I-9, Policy Manual, Questions 14.14, 14.36 and 14.37). Some utilities have requested that the Agency change its policy and allow reporting of hourly total SO2 and CO2 mass emissions and heat input instead of mass emission rates and heat input rates (see Docket A-97-35, Item II-E-14). The utilities argued that this would simplify determination of the total year-to-date SO2 mass emissions, in order to estimate the number of allowances needed to cover a unit's emissions or to prepare a report on mass emissions for a state environmental agency, because the reported values would already be multiplied by the hourly operating time. Thus, by performing the multiplication by operating time before reporting the hourly value rather than waiting until calculating the quarterly value, it might save a calculation step if a facility wanted to use the data for another purpose. For these reasons, reporting of totals is a preferred approach for some facilities. However, other utilities that have incorporated the correct rate approach into their software have indicated that they would prefer not to have to revise their software to report in totals. Partial unit operating hours must also be considered in the recording and reporting of hourly unit load. The standard missing data procedures in Sec. 75.33 require historical flow rate data to be placed in load ``bins'' (ranges) based upon the maximum operating electrical generation (or steam flow rate) of the unit. However, the recorded hourly volumetric flow rate value in scfh applies only to the fraction of the hour in which the unit operates. Therefore, the reported load for the hour should be based upon the average electrical generation during the period when the unit operates. Thus, the electrical generation should be recorded as a rate for the period when the unit operates, rather than an integrated total for the entire hour. The units for reporting hourly load should, therefore, be MWe or 1000 lb/hr of steam, and not MW-hr or 1000 lb of steam. Discussion of Proposed Changes In today's rulemaking, EPA is proposing to amend part 75 to clarify that heat input, fuel flow, SO2 mass emissions, and CO2 mass emissions are all to be reported on an hourly basis as rates. Today's proposal also would clarify that the hourly emission rates are to be based only upon data collected during periods of unit operation (i.e., for partial unit operating hours, emission rates or heat input rates of zero that are recorded during periods of non- operation are not to be included in the hourly average emission rates). These clarifications are found in proposed Sec. 75.57, and Appendices D, E and F to part 75. Today's proposed rule would also clarify that the proper units of reporting for load are MWe and lb/hr of steam. Today's proposal would also provide new options for reporting unit operating time. While the current requirement to report operating time rounded to the nearest 15 minutes would be retained as an option, the proposal would allow more flexibility by specifying that, for reporting purposes, unit operating time be rounded up to the nearest fraction of an hour (in equal increments that can range from one hundredth to one quarter of an hour, at the option of the owner or operator). Consistent with the requirement to report hourly SO2 and CO2 mass emissions and hourly heat input as rates, today's rulemaking proposes to revise the quarterly summation formulas for SO2 and CO2 and to add summation formulas for heat input in Appendix F to part 75. The proposed formulas show that hourly mass emission rates or heat input rates would be multiplied by unit operating time before summing to get total mass emissions. Today's proposal also includes new formulas in Appendix D for summing hourly SO2 mass emission rates and hourly heat input values from fuel flowmeter systems in order to determine quarterly and annual total SO2 mass emissions and total heat input. The Appendix D and F equations revised or added to address summations include Equations D- 6, D-7, D-8, D-9, F-3, F-12, F-24, and F-25. In addition, EPA is proposing optional recordkeeping provisions for determining total heat input, total SO2 mass emissions or total CO2 mass emissions for the hour. In addition to reporting the required emission and heat input rates, owners or operators could choose to report the total hourly heat input and mass emissions under this option. Rationale As stated above, some utilities have expressed a preference for reporting hourly total values for SO2 and CO2 mass emissions and heat input, rather than rates (see Docket A-97-35, Item II-E-14). They have stated that this is easier to understand and that reporting hourly total values, instead of or in addition to rates, would make it easier to determine the cumulative total mass emissions at any time during the year. One representative requested that EPA consider allowing either method of calculation (i.e., hourly rates or totals), so long as the annual mass emissions and heat inputs are correctly determined and reported. EPA notes that, although this approach may appear advantageous because it would not require some facilities to reprogram their DAHS software, it would require other facilities to reprogram their software and it would make it difficult for EPA to verify emissions calculations from reported hourly data. Because EPA considers it essential to the Acid Rain Program to be able to recalculate annual compliance values based upon hourly emission information reported by facilities, the Agency is not revising the rule to take the representative's suggestion. EPA considered using the total mass emissions (or total heat input) approach instead of the mass emission rate (or heat input rate) approach currently stated in Agency policy (see Docket A-97-35, Item II-I-9, Policy Manual, Questions 14.14 and 14.36). In fact, as discussed in section III.H. of this preamble, the Agency is proposing, under subpart H of part 75, model [[Page 28104]] reporting requirements for NOX mass emissions that would (if adopted by an applicable state or federal authority) require hourly NOX mass emissions to be reported as a total value (in lb) rather than an hourly mass emission rate (in lb/hr). However, using hourly mass emission totals for values currently reported to the Agency would have the distinct disadvantage of requiring both EPA and the utilities who correctly implemented the mass emission rate approach to reprogram software to perform the new calculations, whereas retaining the use of SO2 and CO2 emission and heat input hourly rates offers several advantages. First, using hourly mass emission rates and heat input rates instead of totals is consistent with the units of measure in which flow rate is recorded. Volumetric flow monitors measure flow rate during a given time in standard cubic feet per hour scfh, rather than total flow in standard cubic feet (scf). When SO2 concentration is multiplied by volumetric flow rate, one calculates a mass emission rate rather than a total mass of SO2 . Similarly, multiplying a volumetric flow rate by a diluent gas concentration yields a heat input rate in mmBtu/hr, rather than a total heat input in mmBtu. Second, the current missing data procedures for volumetric flow rate, which are based upon the assumption that flow is a rate that is comparable from one hour to another, rather than a total volumetric flow that will vary depending upon the unit operating time, would no longer be appropriate if volumetric flow rate were changed to a total volumetric flow. Third, for Appendix E gas-fired or oil-fired peaking units, it is critical that heat input rate, and not total heat input, be used to determine the NOX emission rate. The Appendix E correlation curve formulas are based upon heat input rate rather than total heat input. Appendix E allows a facility to create a correlation of the NOX emission rate measured in the stack during stack testing and heat input combusted during that same period of time, rather than installing CEMS on gas-fired or oil-fired peaking units. If a facility were mistakenly to use the total heat input from an hour rather than the heat input rate, it would correlate to the wrong portion of the NOX to heat input rate correlation curve and would incorrectly estimate NOX emission rate. For example, if heat input totals were used to determine NOX emission rate from the Appendix E curve, the unit would have a different NOX emission rate if it combusted 25,000 mmBtu in half an hour than if it combusted 25,000 mmBtu during a full hour. This would apply both under the current provisions of Appendix E and today's revised provisions to Appendix E. In view of the above considerations, today's proposed rule would affirm that facilities are to report SO2 and CO2 emissions and heat input as rates on an hourly basis. However, facilities would also be allowed, at their discretion, to report SO2 and CO2 emissions and heat input as hourly totals, in addition to reporting them as rates. This approach would not require reprogramming of computerized reporting software for those utilities that are following EPA's current policy, and would provide consistent reporting that allows EPA to recalculate emissions and heat input values. Those utilities that find recording and reporting of hourly total SO2 and CO2 mass emissions and heat input to be desirable would be able to do so. EPA will provide the necessary electronic record types to support this optional reporting. Although today's proposed rule would affirm that emissions and heat input are to be reported as rates, rather than totals, EPA has become concerned that for partial unit operating hours, some utilities are incorrectly calculating hourly average flow rates by including flow rates of zero in the hourly average to represent periods of non- operation, rather than basing the average flow rate solely on the minutes of operation of the affected unit during the clock hour. In one example, it appears that the software is designed to calculate the average flow rate by including data from all minutes during those fifteen-minute quadrants of an hour when the unit operates, thus including some minutes when the unit is not operating, rather than creating an average flow rate just from merely those minutes when the unit is operating and emitting (see Docket A-97-35, Item II-C-17). EPA suspects that still other utilities may be calculating an average hourly flow rate that includes flow rates of zero for whole quadrants of an hour when a unit does not operate. This can result in the flow rate values for partial operating hours being under-reported to EPA and a lowering of the average flow rates in the load ranges used to provide substitute flow rate data, both of which can cause underestimation of SO2 mass emissions. The Agency is also concerned that this same kind of improper data averaging may be occurring when hourly gas concentrations are determined during partial operating hours. EPA would, therefore, require in today's proposal that facilities base all of their reported hourly average concentrations, flow rates, emission rates, and heat input rates solely upon data that are recorded during unit operation (that is, when the unit is combusting fuel and emitting). Some utilities have indicated that the approach of averaging in readings of zero from periods of non-operation has been incorporated to compensate for having to report operating time rounded up to the nearest fifteen minutes (Note, this is not an acceptable approach). A utility representative indicated that reporting operating time to less precision can cause overestimation of emissions because the operating time is multiplied by the mass emission rate. Thus, a mass emission rate of 400 lb/hr measured over a period of 20 minutes, during an hour when the unit shut down, would be multiplied by an operating time of .5 hr (i.e., 20 minutes rounded up to the nearest fifteen minutes) and would result in 200 lb of SO2 being reported rather than the 132 lb of SO2 that was actually emitted. The utility suggested that a solution would be to allow operating time to be reported to more precision than is currently allowed. Therefore, today's proposal would allow flexibility for reporting unit operating time to greater precision. While the current requirement to report operating time rounded up to the nearest 15 minutes would be retained as an option, the proposal would allow more flexibility by specifying that unit operating time be rounded up to the nearest fraction of an hour (in equal increments that can range from one hundredth to one quarter of an hour, at the option of the owner or operator). Thus, a facility could decide whether it had enough partial operating hours (e.g., unit start-ups and shutdowns) to merit changing their software to report operating time to more precision. 2. Use of Bias-Adjusted Flow Rates in Heat Input Calculations. In late 1995, the first year of the Phase I SO2 allowance program, EPA conducted an audit of the Phase I-affected units. Data from the second quarter of 1995 were retrieved from the Emission Tracking System (ETS) in order to determine whether the SO2 emission rates and heat input values were being properly reported. The results of the audit showed that a number of sources were not reporting heat input correctly. The problem in most instances was that the unadjusted flow rate was being used in the heat input equation, rather than the bias-adjusted value. EPA believes that this is attributable to the fact that part 75 does not explicitly state that the bias-adjusted flow rate is to be used in heat input [[Page 28105]] calculations. The Agency has attempted to clarify this through policy guidance (see Docket A-97-35, Item II-I-9, Policy Manual, Question 14.81). To correct the situation, the necessary language would be added to section 7.6.5 of Appendix A in today's proposed rule. 3. Removing the Restriction on Using the Diluent Cap Only for Start-Up Background: Based on the May 17, 1995 direct final rule, sections 3.3.4, 4.1, 4.4.1, 5.1, 5.2.1, 5.2.2, 5.2.3, and 5.2.4 of Appendix F currently provide for the substitution of a constant CO2 or O2 value for a measured value from a CO2 or O2 monitor during unit start-up. This provision was originally created in response to concerns from some utilities that their NOX emission rate in lb/mmBtu was being overestimated during unit start-up (see Docket A-90-51, Item IV-D-220, Letter from English, Mark G., Deputy General Counsel, Kansas City Power & Light Company on EPA's Proposed Part 75 regulations; see also Docket A-94-16, Item II-F-2). During unit start-up or other periods when the unit is at a low load level, CO2 concentrations are lower than during normal operation and O2 concentrations are higher than during normal operation. The NOX emission rate equation, however, is not designed to be used in these situations because it assumes complete combustion and normal operating conditions. As a result, the NOX emission rate equation overestimates the NOX emission rate when the CO2 concentration is very low or the O2 concentration is very high, such as during start-up. The equations for calculating emission rates in lb/ mmBtu use measured CO2 concentration or the difference between ambient air's O2 concentration and the measured O2 concentration in the denominator. For example, NOX emission rate is calculated using a NOX pollutant concentration monitor and a CO2 diluent monitor using the following equation: [GRAPHIC] [TIFF OMITTED] TP21MY98.001 When a small CO2 concentration is entered into this equation, the calculated NOX emission rate will be very high and will overestimate the actual emissions. The idea of capping CO2 or O2 concentration was implemented in part 75 for determination of NOX emission rate, CO2 mass emissions, and heat input during unit start- up. The cap concentration was set at a minimum CO2 concentration of 5.0 percent CO2 and a maximum O2 concentration of 14.0 percent O2 , based upon some information provided by utilities for boilers (see Docket A-94-16, Item II-D-34). Some utilities asked EPA to consider extending this cap on diluent gas concentrations to other situations when a unit is operating at a low level (see, e.g., Docket A-97-35, Items II-D-20 and 30, and Docket A-97-35, Items II-E-13 and II-E-14). In addition to unit start-up, this might include periods of unit shutdown or unit ``banking,'' where a unit is combusting a very small amount of fuel to keep the boiler warm, but little or no electricity is generated. During these other situations where a unit operates at a low level, the CO2 concentration will be very low and the O2 concentration will be very high, resulting in high calculated NOX emission rate values like those during unit start-up. One software vendor specifically mentioned that it would be easiest to implement the diluent cap if it could be used any time the CO2 concentration would fall below or the O2 concentration would rise above the cap value (see Docket A-97-35, Item II-E-7). This could be implemented mathematically in the software, rather than having to examine the unit operation or the number of hours since the unit started operating in order to trigger use of the diluent cap. During the process of implementing the May 17, 1995 direct final rule, EPA issued guidance that explained that facilities may use the diluent cap values for calculating NOX emission rate during unit start-up whenever the CO2 concentration is below 5.0 percent or the O2 concentration is above 14.0 percent, and also may use the actual measured CO2 or O2 concentration values at all times for calculating CO2 mass emissions or heat input (see Docket A-97-35, Item II-I-9, Policy Manual, Question 14.39). In Question 14.39, EPA recommended that even if the diluent cap is used to calculate NOX emission rate, the actual diluent measurement should be used for the purpose of calculating CO2 mass emissions or heat input, because the purpose of the diluent cap was ``to avoid using an extreme diluent concentration in the denominator of the equation to calculate emission rate in lb/mmBtu.'' The formulas for calculating hourly CO2 mass emission rate or hourly heat input rate do not use the CO2 or O2 concentrations in the denominator of the equation. Thus, use of the diluent cap would tend to overestimate both CO2 mass emission rate and hourly heat input. Discussion of Proposed Changes Today's proposed rule would allow facilities to use diluent cap values of 14.0 percent O2 or 5.0 percent CO2 for boilers and 19.0 percent O2 or 1.0 percent CO2 for turbines. For the purpose of calculating NOX emission rates in lb/mmBtu, the diluent cap would be allowed to be used for any hour in which the average measured CO2 concentration is below the cap value or the average measured O2 concentration is above the cap value. Diluent cap values would still be allowed to be used to calculate CO2 mass emissions or heat input, as well as NOX (or SO2 ) emission rate in lb/mmBtu. Rationale EPA acknowledges that there are periods of low unit operation or low load in addition to unit start-up where the calculated NOX emission rate would be overestimated if it were based upon measured diluent concentrations. Therefore, the Agency believes that extending use of the diluent cap is appropriate. The Agency believes that allowing use of the diluent cap anytime when the actual measured value is above the cap (for O2 ) or below the cap (for CO2 ) is easier to program and to implement than limiting the use of the diluent cap based upon unit load, another option that EPA considered. The Agency believes that it is unlikely that a unit would ever be able to operate at a high load and still have an O2 or CO2 concentration beyond the diluent cap value. Therefore, it is not necessary to limit the use of the diluent cap value based on unit load. The Agency is also proposing new diluent cap values for turbines. Turbines tend to operate with much higher levels of excess O2 than boilers. For example, Method 20 of Appendix A, 40 CFR part 60, the procedure for testing SO2 , NOX and diluent gas from stationary gas turbines subject to the NSPS, requires testers to correct data to a typical concentration of 15.0 percent O2 . Emissions data reported to EPA confirms that for turbines, hourly concentrations of O2 are typically between 14.0 and 16.0 percent and hourly concentrations of CO2 are typically between 3.0 and 4.0 percent. Thus, a turbine's diluent gas concentration is likely to consistently exceed the diluent cap value of 14.0 percent O2 and to be consistently below the cap value of 5.0 percent CO2 promulgated in the May 17, 1995 direct final rule. If these values were allowed to be used by turbines at all times rather than just during unit start-up, a turbine [[Page 28106]] could conceivably report its NOX emission rate using only the diluent cap value and never report the actual monitored diluent concentrations, thereby consistently underestimating the NOX emission rate. Therefore, today's proposal provides diluent cap values of 19.0 percent O2 or 1.0 percent CO2 that are clearly beyond the typical O2 or CO2 concentrations measured at turbines, while still providing some relief at extreme diluent concentrations. It is EPA's observation that turbines with NOX CEMS have not reported emissions using the diluent cap thus far. Thus, no turbines should need to reprogram software in order to report the use of the new diluent cap value for turbines with a new method of determination code. EPA considered removing the option for facilities to use the diluent cap for heat input rate and CO2 concentration, as well as for NOX (and SO2 ) emission rate in lb/ mmBtu, but is not proposing to do so in today's proposal. As explained previously, the diluent cap was created in order to calculate more representative NOX emission rate data during certain unusual circumstances. However, when a diluent cap value is used to calculate the hourly CO2 mass emission rate or the heat input rate, the final calculation would often be less representative of actual emissions or heat input during those hours. The Agency also found that allowing some facilities to use the diluent cap only for NOX emission rate and others to use the diluent cap also for hourly CO2 mass emission rate and heat input rate makes it difficult to check emissions and heat input rate data to verify that calculations are performed correctly. This is because a data acquisition and handling system could use either the actual reported diluent gas concentration or the diluent cap value to calculate NOX emission rate, CO2 mass emission rate, or heat input rate, but there is currently no provision in the electronic data reporting format for a facility to indicate which value was used to calculate the heat input. However, some utilities have indicated that making a change to discontinue using the diluent cap for calculations of heat input rate and CO2 mass emission rate would require a significant change in their software calculations (see Docket A-97-35, Item II-E-25). Therefore, today's proposed rule would allow facilities the options of (1) not using the diluent cap at all, (2) using the diluent cap only for calculating NOX (or SO2 ) emission rate in lb/mmBtu, or (3) using the diluent cap for calculating NOX (or SO2 ) emission rate in lb/ mmBtu, heat input rate, and CO2 emissions. In addition, EPA is proposing to add a minor additional reporting requirement to indicate whether the diluent cap is used in calculating CO2 and heat input in the electronic data reporting format. This would allow EPA to verify facilities' calculations, while requiring less reprogramming than changing the calculations for heat input and CO2 emissions. The Agency solicits comment on the proposed revisions relating to the diluent cap. 4. Complex Stacks--General Issues Background Many power plants regulated under part 75 have relatively simple stack and monitoring configurations. Many utilities have one stack for each affected unit and have CEMS installed on the stack. Other plants have more than one unit discharging to the atmosphere through a common stack, with CEMS installed on the common stack. Still others have individual units that exhaust into multiple stacks and have CEMS installed on each stack. The monitoring requirements for these various configurations are addressed in Secs. 75.13, 75.16, 75.17, and 75.18. EPA has issued guidance to assist utilities in preparing quarterly reports for these unit and stack configurations (see Docket A-97-35, Items II-I-4 and II-I-9, Policy Manual, Section 17). For the configurations described above, the process of accounting for emissions and heat input from the units and stacks will follow simple mathematical rules. For example, for single unit-single stack configurations, the emissions and heat input for the unit are directly determined from the stack CEMS (or from an excepted methodology, where applicable). For units discharging through a common stack with CEMS on the common stack, the combined emissions and heat input are determined from the CEMS, and the heat input to each individual unit is determined by apportionment of the combined heat input, using a ratio of the unit load to the combined load of all units utilizing the common stack. For a single unit exhausting through multiple stacks, the sum of the SO2 and CO2 mass emissions and heat input for the different stacks equals the total SO2 and CO2 mass emissions and heat input for the unit. However, in implementing part 75, EPA has become aware of a number of affected units that have stack exhaust configurations which are more complex than the configurations described above. For example, one utility has a configuration in which two units can emit through two different stacks at the same time, combining their emissions in both stacks (see Docket A-97-35, Items, II-C-1, II-D-12). In this case, the stack configuration is both a common stack and a multiple stack configuration. EPA has had significant problems in determining the emissions and heat input from these units, and in one case, EPA rejected the quarterly reports for the units (see Docket A-97-35, Item II-C-8). The utility worked closely with EPA to resolve the reporting issues resulting from this unusual situation (see Docket A-97-35, Item II-D-21). Other utilities with similar situations have contacted the Agency to ensure there would not be problems with their reporting (see, e.g. Docket A-97-35, Item II-D-5). There have been other cases in which a unit that is accountable for holding SO2 allowances shares a common stack with a unit that does not hold SO2 allowances (e.g., where an affected unit and a non-affected unit share a common stack or, prior to 1/1/ 2000, where a Phase I unit and a Phase II unit share a common stack). These are termed ``subtractive stack'' situations in the following discussion. Utilities with subtractive stack situations have generally used the provisions of Sec. 75.16(a)(2)(ii)(C) or Sec. 75.16(b)(2)(ii)(B). These provisions allow a facility to monitor separately the common stack and the unit with no allowance requirement and to subtract the emissions from the non-affected or Phase II unit from the common stack emissions. In some cases, it has not been clear in the electronic quarterly reports whether a utility is reporting combined emissions from all of the units using the common stack or whether the emissions from the non-affected unit(s) have already been subtracted out of the reported emissions (see Docket A-97-35, Item II- C-18). This confusion in interpreting the quarterly emissions reports has made compliance determination difficult. The Agency found that there is a potential problem with the underestimation of emissions using this subtractive approach. In some cases, the error in the monitors' measurements might be such that a larger emissions value is subtracted from a smaller value, resulting in the reporting of false negative emissions (see Docket A-97-35, Item A- 94-16-IV-D-18, Comments from Monitor Labs). In other cases, there may be an incentive for making inaccurate measurements with the monitoring systems installed on a unit with no allowance requirement. For [[Page 28107]] example, if the SO2 pollutant concentration monitor on a unit with no allowance requirement did not operate properly and had a significant amount of missing data, the facility would calculate SO2 emissions from the unit using a conservative, high concentration value. Therefore, emissions reported for the units with allowance requirements would, as a result of the subtraction, be less than the actual emissions. Thus, a facility might have a disincentive for good monitor performance and accuracy, because it could lower the emissions reported for the units with allowance requirements. Though allowed under the current wording of Appendix A to part 75 and subpart D of part 75, this is contrary to the intent of the missing data substitution procedures, which is to encourage good monitor performance while preventing any systematic underestimation of emissions. (See Docket A-97-35, Items II-B-13, II-E-4, and II-I-12.) Discussion of Proposed Changes Today's proposed rulemaking would add a general regulatory requirement to Secs. 75.16 and 75.17 for facilities with complex stack configurations (i.e., subtractive stack situations or configurations involving combinations of common stacks and multiple stacks) to receive approval from EPA's Administrator for a method of calculating and reporting emissions from the units and stacks in the configuration. The facility would be required to reach agreement with the Agency on issues such as: identification of the stack in its quarterly report, representation of the configuration in its monitoring plan, groups of units for which cumulative emissions must be reported, testing procedures, use of the bias test, and use of the missing data substitution procedures. This would apply both to sources that already have certified monitoring equipment and are submitting quarterly reports and to units that do not yet have certified monitoring systems (e.g. new units). Rationale The Agency evaluated two basic approaches to resolving issues in these complex stack monitoring configurations. First, EPA considered resolving the issues through policy guidance and through instructions for submitting quarterly reports. Second, the Agency considered putting detailed instructions in part 75 for reporting from and testing of monitoring systems installed in these complex stack configurations. These rule provisions would have explicitly addressed missing data substitution to ensure that when emissions are reported, they are not underestimated from units with an allowance requirement or a NOX emission limitation. For example, EPA could have required, for the subtracted unit(s), that the facility only use those provisions of the standard missing data procedures that are not intended to be conservative estimates, such as the average SO2 concentration during the hour before and the hour after a missing data period. Another approach for missing data substitution could have been to count zero emissions for the unit with no allowance requirement during any missing data periods. Or perhaps creation of a site-specific missing data procedure could have been required (see Docket A-97-35, Items II-E-4 and II-I-12). To prevent a potential underestimation of emissions and a disincentive for more accurate monitoring due to application of a bias adjustment on a monitor on a unit with no allowance requirement where its emissions are subtracted from a common stack, EPA could have required that the bias calculation be based upon both the monitors on the common stack and the monitors on units with no allowance requirement, resulting in a single bias adjustment factor for the subtractive stack situation. However, EPA's experience thus far in implementing the program indicates that each complex monitoring configuration tends to be unique. Thus, the Agency has rejected the two approaches discussed above and has decided instead to make General regulatory revisions that allow for case-by-case resolution of issues in individual plant situations, rather than making extensive, detailed revisions to part 75 to address each unique situation. The Agency prefers to make regulatory revisions rather than addressing issues solely through policy and guidance. In some cases, the Agency has given advice to utilities on how to report emissions, and the utility involved has not followed the Agency guidance (see Docket A-97-35, Items II-C-7, II-C-24, and II-D-8). In another case, the current provisions of part 75 for missing data substitution and for the bias test appeared to be in conflict with guidance that the Agency wanted to issue in order to ensure that emissions are not underestimated in a subtractive stack situation (see Docket A-97-35, Item II-B-13). Therefore, today's proposed rule would require owners or operators of facilities with complex stack configurations to apply for approval of their monitoring plans and reporting methodologies from EPA's Administrator on a case-by-case basis. The Agency believes that the General regulatory provisions requiring approval of a complex monitoring situation by EPA's Administrator will give both facilities and the Agency flexibility to deal with site-specific cases, while also giving the Agency regulatory authority to resolve any case-specific problems. It is possible that any final rule resulting from today's proposal may not be promulgated until 1999. Thus, EPA is proposing to require the Administrator's approval of the monitoring plans and reporting methodologies only for those situations that will exist on and after January 1, 2000. Any subtractive stack situations that exist only during the duration of Phase I would not fall under this requirement. However, complex stack situations that exist where affected and non- affected units share a common stack would need to meet today's proposed requirement. Similarly, in situations where coal-fired units sharing a common stack have different NOX emission limitations under part 76, or situations where some units sharing a common stack have a NOX emission limitation under part 76 and others have no NOX emission limitations under part 76, any complex monitoring configuration would need to be approved by EPA's Administrator. 5. Complex Stacks--Heat Input at Common Stacks Background For a unit that utilizes a flow monitor to determine SO2 mass emissions, section 5 of Appendix F to part 75 requires heat input to be calculated using the installed flow monitor and a diluent gas (O2 or CO2 ) monitor. The January 11, 1993 final rule indicated that units with common stacks, multiple stacks, or bypass stacks should follow the same General procedures for monitoring heat input as are used for monitoring SO2 under Sec. 75.16. As written, those procedures allowed facilities to monitor their heat input either by placing individual monitors on each unit that serves a common stack or by placing monitors only on the common stack and measuring a combined heat input from all of the units sharing the common stack. The May 17, 1995 rule required the combined heat input measured by monitors on the common stack to be apportioned to the individual units, in two specific provisions. First, unit level heat input was required under Sec. 75.16(e)(2) for cases in which a knowledge of the heat input for each unit is critical to compliance determination (i.e., for situations where any units using the common stack have [[Page 28108]] a NOX emission limit). Second, Sec. 75.16(e)(3) required unit level heat input to be determined for all other common stacks, but only until the year 2000. The November 20, 1996 rule outlined the acceptable methodology for apportioning heat input, i.e., by using the ratio of the unit load in MWe or lb of steam per hour to the combined load of all units utilizing the common stack (provided that all of the units utilizing the common stack are combusting fuel with the same F- factor). Discussion of Proposed Changes Today's proposed rule would revise the existing requirements found in Sec. 75.54(b) and two specific provisions of Sec. 75.16(e) for accounting of heat input for units serving a common stack, a by-pass stack, or multiple stacks. First, EPA would require determination and reporting of the unit level heat input to be continued after the year 2000 for all affected units, rather than restricting it to certain situations after 2000. Second, EPA would clarify that the proper units of measure for load to be used in an apportionment of common stack heat input to determine unit level heat input are totals of MWe-hr and 1000 lb of steam, rather than rates of MWe and 1000 lb/hr of steam. Rationale EPA considered leaving the current provisions of Sec. 75.16(e) and Sec. 75.54(b) from the May 17, 1995 and November 20, 1996 rules unchanged. However, this would have the serious drawback of requiring the facilities to reprogram their computer software for certain units and not for others. Corresponding monitoring plan changes would also be required. Additionally, EPA would have to reprogram its emission tracking software to accommodate two different heat input reporting methodologies for common stacks. In view of these considerations, EPA is proposing to continue to receive individual heat input data from all affected units. This information is useful for developing inventories of total NOX mass emissions in tons in support of other Agency rulemakings. Without such information, the inventories would be based on assumptions about how units operate, rather than being based on unit level heat input as reported from the facility. The Agency believes that a relatively small number of sources would be affected by this proposed change. This is because (1) most coal- fired units would still need to report unit level heat input under the current provisions of Sec. 75.16(e)(2), even after the year 2000; and (2) gas-fired and oil-fired units using fuel flowmeters to determine heat input and to implement the procedures of Appendix D or Appendix E would still be required to monitor heat input for each unit under section 2.1 of Appendix D. Because of the usefulness of having heat input data for individual units, because of the burden of reprogramming software to remove the heat input apportionment by the year 2000, and because of the small number of sources that would benefit from retaining the current provisions of Sec. 75.16(e)(3), EPA believes it is reasonable to require all units that measure combined heat input at a common stack to continue to apportion heat input to the individual units. The Agency solicits comment on the number of sources that would be affected by this revision. 6. Start-Up Reporting--Units Shutdown Over the Compliance Deadline Background As currently written, part 75 requires that units which are shutdown over an applicable compliance date specified in Sec. 75.4 must submit a notice of the planned and (if different) actual shutdown date. In addition, Sec. 75.4(d) provides an extended certification deadline for such units of ``the earlier of 45 unit operating days or 180 calendar days after the date that the unit recommences commercial operation of the affected unit.'' If an owner or operator subsequently recommences commercial operation of the unit, a notice related to the planned and (if different) actual date of recommencement of commercial operation is required. In addition to these notices, Sec. 75.64 requires that after the applicable compliance date passes, the owner or operator must submit quarterly reports for such units. If the unit remains shut down and does not operate during the quarter, the quarterly report must show zero emissions. Utility commenters (see, e.g., Docket A-97-35, Items II-D-20, II-D-30) have recommended that this quarterly report requirement for shutdown units be deleted because it is unnecessary and burdensome. Discussion of Proposed Changes Section 75.64(a) would be modified so that quarterly reporting is not required until the first quarter in which a previously shutdown unit recommences commercial operation. In this case, the first quarterly report would contain data beginning with the hour in which the unit recommences commercial operation. Rationale Units that are shutdown over their applicable certification deadlines are required to submit notice, pursuant to Sec. 75.61(a)(3), of the planned date of recommencement of commercial operation and also must submit a follow-up notice if the actual date of recommencement of commercial operation is different from the planned date. As a result of these notice provisions, EPA will know whenever the status of a shutdown unit changes. Because shutdown units have no emissions, the Agency believes that quarterly reporting in addition to the notice provisions is unnecessary to fulfill the emission reporting objectives of the Act. The Agency notes, however, that the proposed revision differs from that suggested by certain utilities (see Docket A-97-35, Item II-D-30). The utilities proposed tying the reporting requirement to the certification deadline in Sec. 75.4(d). However, under Sec. 75.4(d), facilities are required to report emissions data using special provisions in that section prior to the extended certification deadline in Sec. 75.4(d). Thus, the proposed revisions would tie the obligation for quarterly reporting to the quarter in which commercial operation is recommenced. 7. Start-Up Reporting--New Units Background As currently written, Sec. 75.64(a) requires the first quarterly report for new units to be submitted for the quarter corresponding to the compliance date in Sec. 75.4. However, the current provision is unclear about which hourly emissions data need to be included in the first quarterly report if the compliance deadline does not correspond to the first hour in the quarter. Discussion of Proposed Changes Section 75.64(a) would be modified to clarify that a new unit must start reporting data beginning with the earlier of the date and time of provisional certification or the compliance deadline in Sec. 75.4(b). Rationale These proposed revisions are generally consistent with existing implementation of the new unit reporting requirements, and primarily would serve to clarify ambiguous elements of the current rule. [[Page 28109]] 8. Recordkeeping and Reporting Provisions Background Subpart F and subpart G of the existing part 75 regulation set forth the recordkeeping and reporting requirements that accompany the monitoring provisions of part 75. Specifically, in subpart F, Sec. 75.53 contains the monitoring plan requirements, Sec. 75.54 contains the general recordkeeping provisions, Sec. 75.55 lists the general recordkeeping provisions for specific situations, and Sec. 75.56 consists of the certification, quality assurance and quality control record provisions. In subpart G, Sec. 75.62 lists the monitoring plan reporting provisions, Sec. 75.62 contains the reporting requirements for initial certification and recertification applications, and Sec. 75.64 discusses the provisions for quarterly reports. Quarterly reports are electronic data files containing emissions and operating data from affected units, as well as monitoring plan information and the results of certification and quality assurance tests. Under Sec. 75.64, these electronic data reports are required to be submitted to the Agency each calendar quarter. This electronic information is used by the Agency for many different purposes, including implementation of the SO2 allowance trading program, determination of compliance with emission limits, development of reports on utility emissions, and modeling of air quality to assess the effectiveness of the Act. In order to effectively use the electronic quarterly report information, EPA created a standardized reporting format, the electronic data reporting (EDR) format. The electronic file formats and record structures of the EDR provide the vehicle by which required information is submitted to the Agency every calendar quarter. The EDR primarily defines the order, length, and placement of information within the electronic report or file. The individual tables of the EDR define the record type, type code, start column, data element description, units, range, length, and FORTRAN format for each data element in the electronic report. The information in the EDR fields mirrors the required information set forth in subparts F and G of part 75. Considering both the volume of information contained in each quarterly report (e.g, operating and emissions data for each of the hours in the quarter) and the number of reports submitted to the Agency (i.e., currently, 1765 reports are received each quarter for the 2055 affected units; some reports contain information for more than one unit if several units are interrelated, as in a common stack configuration), a standard format is critical in order for the Agency to review, verify, and use the information reported. A standard format allows the Agency to develop software to receive and verify the files and to correlate and separate out specific information for compliance determinations. A standard format also allows software vendors to create standard software which can be utilized by many affected units. This is more cost effective than developing site-specific software and thus reduces the software cost to industry. Today's rulemaking proposes a number of revisions to subparts F and G of part 75 (the reporting and recordkeeping sections of the rule). The majority of these changes are necessary to implement the proposed substantive revisions to the sections of the rule and appendices discussed elsewhere in this notice. In addition, EPA is proposingrevisions to these subparts in order to streamline implementation of the program and to coordinate reporting under the Acid Rain Program with other programs. To support the changes to the recordkeeping provisions, new Secs. 75.57, 75.58, and 75.59 would be added. These sections would replace existing Secs. 75.54, 75.55, and 75.56. The addition of new sections is necessary because the proposed revisions would not be mandatory until January 1, 2000, and to have the proposed revisions listed throughout existing effective sections could lead to confusion. However, an owner or operator would be free to follow the provisions of Secs. 75.57, 75.58, and 75.59 before January 1, 2000, if he chooses to do so. In addition, the owner or operator would be required to satisfy, prior to January 1, 2000, the elements in these sections that support a regulatory option proposed in other sections of part 75 if the owner or operator elects to implement that option prior to January 1, 2000. Because, as discussed above, the Acid Rain Program relies on a standardized electronic data reporting format, EPA has also developed draft revisions to the EDR formats and instructions (draft EDR version 2.1). The following discussion refers to both the rule sections and EDR record types (RTs) that would be affected by the proposed revisions. Discussion of Proposed Changes There are a number of proposed rule changes to the recordkeeping and reporting requirements of part 75 and corresponding draft EDR revisions that would be necessary to implement the substantive revisions proposed by EPA and discussed elsewhere in this preamble. These include the following requirements: (1) Changes to support new CO2 missing data requirements (see Sec. 75.57 and RT 202, 210, and 211); (2) Changes to support new reporting, QA and missing data requirements for moisture monitoring (see Secs. 75.53, 75.57, and 75.59, and RT 211, 212, 220, and 618); (3) Changes to support optional Appendix I (flow methodology for gas and oil units) (see Secs. 75.57 and 75.58, and RT 220, 302, 303, 608, and 609); (4) Changes to support more flexibility for units that have multiple range analyzers (see Secs. 75.53 and 75.59, and RT 230, 530, 600, 601, and 602); (5) Changes to support the use of the diluent cap during all hours (see Sec. 75.57 and RT 300 and 330); (6) Changes to support test exemptions and extensions for units that operate infrequently (see Secs. 75.59 and 75.64, and RT 301, 697, and 698); (7) Changes to support increased flexibility in fuel sampling (see Sec. 75.58 and RT 302, 303, 313, and 314); (8) Changes to allow reporting of hourly total values in addition to hourly rates (see Sec. 75.57 and RT 300, 310, and 330); (9) Changes to support the proposed re-definition of unit operating loads (see Secs. 75.53 and 75.59, and RT 535 and 611); (10) Changes to support reporting of conditional data during recertification events (see Sec. 75.59, and RT 556); (11) Changes to support a new quarterly flow-to-load QA check for flow monitors (see Sec. 75.59, and RT 605 and 606); (12) Changes to allow QA test grace periods (see Sec. 75.59, and RT 699); (13) Changes to support simplified reporting for low mass emissions units (see Secs. 75.53, 75.58, and 75.63, and RT 360, 508, and 531); (14) Changes to support fuel flow-to-load QA checks for fuel flow meters (see Sec. 75.59, and RT 628 and 629); and (15) Changes to support expanded reporting of RATA supporting information (see Sec. 75.59, and RT 614, 615, 616, 617, and 618). In addition, since the EDR version 1.3 was released, EPA has developed additional record types to aid in the implementation of the program, by allowing the designated representative to certify the validity of quarterly reports using an electronic certification statement. The proposed revisions would adopt the necessary rule language to implement these miscellaneous record types (see Sec. 75.64, and RT 900, 901, 910, and 920). [[Page 28110]] The proposed revisions would also set forth optional requirements for reporting of NOX mass emissions that states or EPA could adopt as part of a NOX mass trading program, such as the OTC NOX Budget Program. In this situation both a rule change and an EDR change would be needed (see Secs. 75.57 and 75.64 and RT 301, 307, and 328). The proposed rule revisions also include a number of changes that EPA believes will facilitate implementation of the program. These include: (1) Reporting of test numbers, reasons for tests and indicators of aborted tests (see Sec. 75.59, and RT 560, 600, 601, 602, 603, 610, and 611); (2) Changing the deadlines for reporting the RATA supporting information that was originally required on January 1, 1998 (see Sec. 75.59, and RT 614, 615, 616, 617, and 618); (3) Reporting of an optional record type that will allow facilities to provide contact person information that many facilities currently provide in quarterly report cover letters (see Sec. 75.59, and RT 999); (4) Based on comments received, the rule would be revised so that reporting the reasons for missing data as part of the quarterly report would become optional, but would still need to be maintained on-site (see Secs. 75.56 and 75.59, and RT 550); (5) Reporting of facility location, identification, and EDR version numbers to support the transition from EDR 1.3 to EDR 2.1 (see Sec. 75.64, and RT 100 and 102); (6) Reporting of information documenting the calculation of heat input (see Sec. 75.57, and RT 300); (7) Reporting of reference method backup QA data (see Sec. 75.59(a)(11), and RTs 260, 261, and 262); (8) Expanded reporting of unit definition information (see Secs. 75.53, and RTs 504, 585, 586, and 587); (9) Reporting of Appendix E segment ID information (see Sec. 75.58, and RT 323, 324, and 560); (10) Reporting of qualification data for peaking units or gas-fired units (see Sec. 75.53, and RT 507); (11) Reporting of the qualifying test for off-line calibrations (see Sec. 75.59, and RT 623); (12) Reporting of Appendix E emission rate test data (see Secs. 75.59, and RT 650-653); (13) Reporting of span effective date information and flow rate span values (see Sec. 75.53, and RT 530); and (14) Removal of the recordkeeping provisions of Secs. 75.50, 75.51, and 75.52 that are no longer effective. Rationale The majority of the proposed changes to subparts F and G are needed to support proposed substantive changes elsewhere in part 75. EPA is also proposing certain minor revisions to the order and wording of provisions in these subparts so that the records required by the rule match up consistently with the record type descriptions in the EDR. Certain utility groups previously had objected that EPA had not made the EDR format available for formal public notice and comment. The Agency maintains that it is not required to provide notice and comment for the EDR. The data included in (or proposed to be included in) the EDR are also listed in the rule (or the proposed rule revisions) as requirements under the recordkeeping and/or reporting provisions of Secs. 75.53 through 75.64, which have already undergone (or are undergoing) public notice and comment. Since the EDR simply shows how to present electronically the data whose submission is (or will be) required by the rule, it is the rule, not the EDR, that imposes the data requirements. Notice and comment on the contents of the EDR would therefore be unnecessary and duplicative. Moreover, the requirement to present the rule's data requirements in a specified format is authorized by Sec. 75.64(d), which requires a quarterly report to be submitted in the format specified by the Administrator. Like the data requirements, this format requirement in part 75 was adopted after public notice and comment. In today's rulemaking, EPA has developed draft EDR revisions simultaneously with the proposed rule revisions and is therefore including the draft EDR revisions in the docket for comment at the same time as the proposed rule revisions (see Docket A-97-35, Item II-A-12). EPA is also posting the draft EDR v2.1 revisions and draft EDR v2.1 reporting instructions on the Acid Rain Homepage (www.epa.gov/ acidrain). However, the Agency maintains that notice and comment are not necessary for revisions to the EDR so long as the data included in the EDR is the same as the data required by rule provisions that have undergone or are undergoing notice and comment. Thus, future EDR revisions may be made without prior notice and comment on the EDR in order to implement rule revisions for which notice and opportunity for comment are provided. However, the Agency will continue its informal procedures for involving the affected stakeholders in any such EDR revisions. There are a number of other proposed changes to Secs. 75.54-75.64 that have been included to implement existing provisions in other sections of part 75. First, information on test numbers and reasons for tests would be required so that quality-assurance test data can be more easily correlated and interpreted. Second, the reporting of various run-specific and point-specific RATA support information would be required (e.g., point velocity head readings, gas reference method quality-assurance data, moisture reference method data, etc.). The Agency believes that most testing companies currently either collect these data electronically or enter the data into computer programs manually to determine RATA results. By requiring the reporting of these data elements in a standard electronic format, the Agency believes that both facilities and regulatory personnel would be able to more easily interpret data that are currently provided by test contractors in many different hardcopy formats. The Agency is proposing not to require the electronic reporting of RATA support information prior to the year 2000. Sections 75.56 (a)(5)(iii)(F) and (a)(7) and Sec. 75.64(a)(1) of part 75 currently require RATA supporting information to be reported in the electronic quarterly report. EPA believes, however, that it would be more cost effective to require the more detailed RATA support records to be electronically reported beginning in the year 2000, rather than having a two-stage implementation. The Agency has notified all designated representatives that this RATA supporting information will not be required to be reported electronically, in RT612 and 613 of the quarterly report, prior to January 1, 2000. The Agency notes that certain data elements (e.g., yaw angle, pitch angle, axial velocity, wall effect point identifier, etc.) have been included in anticipation of future revisions to EPA Reference Method 2. EPA is presently evaluating a number of alternative flow rate measurement methodologies, such as the use of a 3-dimensional probe. Depending on the outcome of the Agency's evaluation, one or more of these alternative flow measurement techniques may be allowed beginning in the year 2000. Therefore, EPA believes it is appropriate to include data elements to support these anticipated Method 2 revisions in draft EDR version 2.1. Finally, by changing the requirements for reporting the results of the most recent RATA from requiring it to be reported in the quarter in which it was [[Page 28111]] performed, to requiring it to be reported in the quarter in which it was performed and each subsequent quarter in which a BAF that was calculated using the results of that RATA are used, EPA would make the individual quarterly reports more self contained and make it easier for people who are using the reported data to understand how the BAFs reported in those reports were applied. EPA considered adding a field to the hourly emissions data record for each pollutant to indicate the BAF applied in that hour. However, the Agency received requests from utilities on an early draft of the EDR revisions that the hourly emissions data record types not be revised to add a field for BAF. The Agency believes that reporting the results of the most recent RATA, including the BAF, in each quarterly report would accommodate the utilities' requests not to add the BAF to each hourly record type and would achieve the objective of making the quarterly reports easier to interpret because the BAF being applied will be found in each quarterly report. In addition, since electronic RATA results involve a relatively small amount of information that can be copied into subsequent reports and does not have to be recreated, it should not be a significant burden to reporting facilities. The proposed revisions would also remove the requirement to report the reasons for missing data and make it optional. However, even if the information is not reported, the reasons for missing data would have to be maintained on site in a manner suitable for inspection. Based on the high data availability achieved during initial implementation of the program, the Agency believes that this type of information is not needed in the review of most quarterly reports. For those situations in which the Agency may wish to review this information, the records would still be on-site for audit purposes or for submittal to the Agency. The EPA is also proposing to incorporate additions which would allow the reporting of electronic signatures and certification statements so that no hardcopy reporting of any kind (e.g., cover letters) would be necessary to meet the quarterly report requirements. Finally, the removal of recordkeeping Secs. 75.50, 75.51, and 75.52 (and the corresponding explanatory text included in Appendix J to the existing rule) is necessary because those sections were scheduled for replacement during the May 17, 1995 rule revisions. At that time, Secs. 75.54, 75.55, and 75.56 were added as replacements for Secs. 75.50, 75.51, and 75.52, effective January 1, 1996. Because the effective date is now past, the old sections and Appendix J will be removed and reserved in order to prevent any confusion. 9. Electronic Transfer of Quarterly Reports Background Sections 75.64(a) and (d) of the original January 11, 1993 Acid Rain rule requires emissions, monitoring, and quality assurance data to be electronically reported to the Administrator on a quarterly basis in a format to be specified by the Administrator. Version 1.3 of the Electronic Data Reporting (EDR) format (see Docket A-97-35, Item II-I- 5) further specifies the record structures to be used to report the required data elements. Page 3-3 of the May 1995 Acid Rain Program CEMS Submission Instructions (see Docket A-97-35, Item II-I-4) further specifies the mode of transmission of the electronic data file to the Agency. Three modes of transfer are listed as options: (a) by mail on diskette, (b) by mail on magnetic tape, or (c) through direct electronic transfer. Since the beginning of the program, the Agency has received quarterly reports by mail on diskette and through direct electronic transfer. To date, the magnetic tape option has never been utilized. Based on the first four years of implementation of part 75, the Agency believes that the use of the direct electronic transfer mode of transmission has many advantages to the Agency and to the affected sources. In fact, more than seventy percent of the reports for sources currently affected by part 75 were submitted directly to the EPA mainframe with EPA-provided software in second quarter 1997, and the number of sources using this option has steadily increased over time (see Docket A-97-35, Item II-I-8). Discussion of Proposed Changes Today's proposal would require quarterly reports to be submitted via direct electronic transfer unless otherwise approved by the Administrator. This would remove the option of sending files through the mail on interceding media except for hardship cases where a modem is not available or where technical difficulties prevent the successful transmission of files via modem. An additional revision to section 4 of Appendix A to part 75 would require data acquisition and handling systems (DAHS) to be capable of transmitting a record of measurements and other required information by direct computer-to-computer electronic transfer via modem and EPA- provided software. Rationale For each quarterly report submitted, the Agency performs an assessment which results in a feedback report for the submitting designated representative. This feedback report provides information to the facility that may be used in making trading decisions, that may indicate that a change is needed to the facility software, and/or that may indicate that the file needs to be corrected and resubmitted. A major advantage of submission through direct electronic transfer with a modem and EPA-provided software is that the designated representative submitting the file receives the EPA assessment of the submitted data much more quickly than for a file that is transmitted through the mail on diskette. Currently, for a file that is submitted to the Agency by electronic transfer via modem and EPA-provided software, the EPA assessment is received by the designated representative, via modem and EPA-provided software, immediately (typically within ten minutes) after the transmission of the quarterly report file. However, for files submitted on diskette that must travel through the mail system and be processed by Agency personnel, a letter containing the EPA assessment is currently sent to the designated representative through the mail and arrives 45 days or later from when the submission was originally received by the Agency. Therefore, with direct electronic transfer, potential errors get corrected and resolved more quickly and trading decisions can be made with assurance that submitted data meets the minimum quality standards acceptable to the Agency. Additionally, the source may electronically submit the quarterly report, via modem and EPA software, prior to the deadline, immediately receive the EPA assessment, fix any errors, and resubmit the file by the deadline. Many utilities have indicated that this is an important advantage over submission of the quarterly report by diskette. Another benefit of direct electronic transfer is the reduced risk of error in transmission to the Agency or handling at the Agency. Throughout the implementation of the program, many files submitted on diskette through the mail have been lost, returned to the sender, damaged in transit, or contained viruses (see Docket A-97-35, Item II- I-8). When a file is submitted using direct electronic transfer of a quarterly report, the designated representative submitting the file(s) receives an immediate [[Page 28112]] confirmation that the file was received by the Agency. Further, immediate feedback from the agency on quarterly report submissions may also contribute to cost savings for facilities if a file submitted via direct electronic transfer is rejected and required to be amended and resubmitted. Utilities have indicated that submitting the report to EPA, receiving feedback, and making the necessary corrections to the file in a single work session significantly reduces the cost of reworks, particularly for facilities that retain their master file at the individual plant locations. An additional advantage to direct electronic transfer is the reduced cost to the Agency resulting from the minimized EPA labor hours required to process a diskette. For instance, a diskette transmitted through the mail must be catalogued, scanned for readability and viruses, uploaded to the EPA mainframe Emissions Tracking System, and renamed. On the other hand, transmission of a file by direct computer- to-computer electronic transfer using EPA software eliminates all of those manual steps because they are performed automatically by the EPA software used for transmission of the report. A possible concern about a requirement to submit the quarterly report via modem is the possibility that source may not be equipped with a modem and electronic transfer capability. Although the Agency believes that most sources currently have a modem or will have a modem by the year 2000, the Agency understands that a very small percentage might not. Therefore, the Agency would accept petitions from sources unable to transmit files via modem in order to allow transmission via diskette for hardship cases. Additionally, a utility group representative raised a concern about the possibility of a computer at either the facility source or at the EPA being inoperative at the time of the deadline for transmission, preventing a source from successfully transferring the quarterly report to the Agency. In order to minimize the risk of this type of problem, there is a wide window, currently thirty days, during which EPA will accept quarterly report transmissions each quarter. Additionally, EPA has instituted preventative measures to minimize the possibility that the EPA computer would be inoperative for an extended length of time, preventing quarterly report transmission. Nevertheless, the Agency accepts that it is conceivable that a technical difficulty could prevent the successful electronic submission of a quarterly report and, therefore, would also approve diskette submission on an as-needed basis for sources unable to transfer a file via modem and EPA-provided software due to technical difficulties. Furthermore, EPA solicits comment on whether it should allow a grace period for late submissions due to a technical difficulty with the EPA computer. Finally, section 4 of Appendix A to part 75 would be amended to require the DAHS to be capable of transmitting the required information by direct electronic transfer via modem and EPA-provided software, for consistency with the proposed Sec. 75.64(f). In addition, section 4 of Appendix A to part 75 would retain the requirement for the DAHS to be capable of transmitting a record of measurements and other required information via an IBM-compatible personal computer diskette so that an on-site inspector could collect electronic data on a diskette for review. S. Revised Traceability Protocol for Calibration Gases Background Currently, Appendix H to part 75 requires affected units to follow a 1987 version of EPA Protocol procedures for developing calibration gases. This protocol document has been superseded by a later version, the ``EPA Traceability Protocol for Assay and Certification of Gaseous Calibration Standards,'' September 1997, EPA 600/R-97/121. The 1997 document is actually five protocols. Two of these protocols (formerly known as Protocols 1 and 2) have been combined to allow both CEMS and ambient air analyzers to be calibrated from gases produced either without dilution (Procedure G1) or with dilution (Procedure G2). The remaining three protocols (Procedures P1, P2, and P3) describe procedures that are mandatory for ambient air quality analyzers (not continuous emission monitoring systems). The 1997 Protocol document, described above, is required by other parts of the CFR, such as the NSPS provisions in part 60. Because the old and new protocols specify different certification periods (i.e., useful shelf lives) for most calibration gases, some affected units that must comply with both part 60 and part 75 have been forced to replace calibration gas cylinders more frequently because of the shorter certification period in the 1987 Protocol procedures required by part 75. Under the 1987 Protocol document, affected units with low SO2 emission rates occasionally had difficulty finding calibration gases that were within the concentration ranges required by Appendix A to part 75. The 1997 Protocol document allows calibration gases to be developed over a wider range of concentrations than was previously allowed. Under the current part 75 rule, ``Protocol 1 gases must be vendor- certified to be within 2.0 percent of the concentration specified on the cylinder label (tag value).'' However, no method is specified to determine the uncertainty value. The overall uncertainty in the concentration estimated for a calibration gas comes from many different sources, including uncertainty in the reference standards, uncertainty in the analyzer multi-point calibration, uncertainty in the zero/span correction factors, and measurement imprecision. Discussion of Proposed Changes and Rationale Today's rule proposes to remove Appendix H and revise parts 72 and 75 to be consistent with the 1997 Protocol document. The following sections of part 75 would be revised: Secs. 72.2 and 72.3; sections 5.1.1 through 5.1.6, 6.2, and 6.3.1 of Appendix A; and all of Appendix H. The final rule would incorporate by reference the 1997 Protocol document. This is the preferred option for the following reasons: (a) calibration gas certification periods would be identical under parts 60 and 75, thereby allowing affected units to reduce expenditures on calibration gas without sacrificing accuracy or performance; (b) lower emitting affected units would more easily be able to comply with the required range of calibration gas concentrations; (c) improved assaying procedures and accuracy determinations would be allowed; and (d) a wider selection of calibration gases would be allowed. While today's proposal would retain the requirement for EPA protocol gases to be within 2.0 percent of the tag value, section 5.1.3 in Appendix A would be revised to specify the use of the uncertainty calculation procedure in section 2.1.8 of the 1997 Protocol document for estimating the analytical uncertainty associated with the assay of the calibration gas. This uncertainty estimate includes the uncertainty of the reference standard and any gas manufacturer's intermediate standard (GMIS) and interference correction equation that may be used in developing the calibration gas. EPA proposes to change the term ``Protocol 1 gas'' to ``EPA protocol gas'' because the 1997 Protocol document combines the Protocol 1 and Protocol 2 [[Page 28113]] procedures; therefore, the term ``Protocol 1 gas'' would no longer be used. Today's proposal would also continue to allow a ``research gas mixture'' to be used as a calibration gas. However, an RGM would need to meet the same 2.0 percent uncertainty requirement that a protocol gas would meet. The proposed rule would explicitly allow GMISs to be used as calibration gas for two reasons. First, an EPA protocol gas may be made from a GMIS. Therefore, GMISs are at least as accurate as EPA protocol gases. Second, GMISs are more readily available and less expensive than standard reference material or National Institute of Standards and Technology (NIST) traceable reference material, both of which are allowable as calibration gas under part 75. Today's proposal clarifies that NIST/EPA-approved certified reference materials (CRMs) would be acceptable as calibration gas by adding those CRMs to the definition of ``calibration gas'' in Sec. 72.2. The 1997 Protocol document accepts primary reference standards from the Netherlands Measurement Institute as being equivalent to standard reference materials from the NIST. As a result, today's proposal adds ``standard reference material-equivalent compressed gas primary reference material'' to the ``calibration gas'' definition in Sec. 72.2 and to section 5.1.2 of Appendix A. Finally, the definition of ``zero air material'' would be revised to accommodate other acceptable procedures. Major differences between the 1987 Protocol procedures and the 1997 Protocol procedures are explained on pages 1-1 through 1-3 of the 1993 Protocol document and on pages 1-1 through 1-2 of the 1997 Protocol document (see Docket A-97-35, Items II-I-23 and 24). T. Appendix I--New Optional Stack Flow Monitoring Methodology Background Section 412 of the Act requires that units subject to title IV install SO2 concentration monitors and volumetric flow monitors for the purpose of determining SO2 emissions. The purpose of the volumetric flow requirement is to enable a unit to convert SO2 concentrations into mass emission rates of pounds per hour (lbs/hr). Volumetric flow is also used to determine heat input rate in mmBtu/hr and CO2 mass emission rate in ton/hr. In December 1991, 56 FR 63002 (December 3, 1991), EPA proposed an exception to the requirement to install SO2 concentration monitors and volumetric flow monitors at oil- and gas-fired units in Appendix D to part 75. The exception relies on fuel flowmeters and fuel sampling and analysis to determine SO2 emissions from oil- and gas-fired units. In comments on the December 1991 proposed rule, some industry commenters also advocated allowing oil- and gas-fired units to use a diluent monitor, an F-factor, and a fuel flowmeter as an alternative to a volumetric flow monitor. An F-factor is a fuel- specific constant that relates the heat content of a fuel and the volume of gases given off upon combustion. It is used to convert pollutant concentrations into units of pounds of pollutant per million British thermal units of heat input (lb/mmBtu). EPA already allows the use of F-factors in emissions monitoring under part 75 and under 40 CFR part 60, subparts Da and Db. Method 19 of Appendix A to part 60 uses F- factors as the reference methods for calculating SO2 and NOX emissions in terms of lb/mmBtu for subpart Da and Db units. F-factors also are used in the performance tests for certain pollutants required under Sec. 60.8 to determine if a source is in compliance with a particular emission standard in lb/mmBtu. Part 75 also uses F-factors in conjunction with diluent gas and volumetric flow data to determine heat input under section 5 of Appendix F to part 75. Table 19-1 of Method 19 in Appendix A to part 60 and Table 1 in section 3.3.5 of Appendix F to part 75 list the appropriate F-factors for different types of fuel, including oil and natural gas. Although the commenters supported the two exceptions included in Appendix D, some commenters did not believe the exceptions would be economical at all oil- and gas-fired units. According to one commenter, fuel sampling protocols have an inherently high bias because they assume a 100 percent conversion of fuel sulfur into SO2 , which results in higher emissions reporting from fuel sampling protocols than from CEMS. The commenter claimed that the high bias appears to be in the range of 5 to 10 percent. According to the commenter, the higher emissions reporting ``penalty'' that is inherent in fuel sampling protocols would justify installing SO2 CEMS at some oil- and gas-fired units, particularly large, base-loaded oil- fired units. In addition, the commenter claimed that, for oil- and gas- fired units which install SO2 CEMS, use of the ``F-factor/ fuel flow method''--which includes use of an F-factor, a fuel flowmeter, fuel sampling data, and a diluent (CO2 or O2) concentration monitor--would provide much more accurate and precise information than volumetric flow monitors (see Docket A-90-51, Item IV- D-184). In a four-day experiment performed in 1991 by one commenter, measurements from the F-factor/fuel flow method were compared to those generated by a combined SO2 CEMS and a volumetric flow monitor. However, EPA did not believe that four consecutive days of data were sufficient to support a conclusive equivalency determination. Instead, in the January 11, 1993 final rule (58 FR 3590, 3643), EPA reserved Appendix I to part 75 for the F-factor/fuel flow method and stated that, to be approved, the method would have to meet the criteria for alternative methods as required by section 412 of the Act and the provisions of Sec. 75.40 in a 30-day (720 hour) trial. Section 412 of the Act requires that an alternative monitoring system provide information with ``the same precision, reliability, accessibility, and timeliness as that provided by CEMS . . .'' 42 U.S.C. 7651k. To be approved, the alternative monitoring system must meet the criteria for alternative methods in a 720 hour trial as required by the provisions of subpart E of part 75. The rule designates a certified CEMS or a reference method according to Appendix A to part 60 as the reference for evaluating the alternative monitoring system's performance. In order to meet the precision and reliability criteria, an alternative monitoring system must achieve performance specifications and quality assurance requirements equivalent to those for CEMS. In addition, to demonstrate precision, an alternative monitoring system must pass three statistical tests evaluating the flow CEMS and alternative method in terms of their respective systematic error, random error, and correlation. Additionally, to meet the reliability criterion, the alternative monitoring system is required to match a certified CEMS in terms of annual availability. Finally, to meet the accessibility and timeliness criteria, an alternative monitoring system must match the CEMS' ability to record requisite emissions data on an hourly basis and report results within 24 hours. In 1995, Long Island Lighting Company (LILCO) sponsored an ``alternative flow monitor demonstration project'' to demonstrate the equivalency of fuel flow measurements and F-factor calculations to stack instrument flue gas measurements for the determination of volumetric flow. The project was [[Page 28114]] performed by Entropy at LILCO's Port Jefferson Unit 4, a 180 MW oil- fired unit that burns residual oil with a maximum sulfur content of one percent. The components of the alternative method consisted of a fuel flowmeter and a CO2 CEMS. The alternative F-factor/fuel flow method was compared to a flue gas volumetric flow CEMS. Testing of the F-factor/fuel flow method took place in April-May 1995, and 739 hours of data were collected over a wide range of operating loads (40 MW--190 MW). Fuel oil samples were taken daily and analyzed for density and carbon content. The alternative method successfully passed statistical tests but showed statistically significant bias (see Docket A-97-35, Item II-D-14). Due to the bias uncovered during the test, EPA concluded that the alternative flow monitor demonstration project did not meet the requirements of subpart E of part 75 for an alternative monitoring system. However, EPA is proposing that a default multiplier, derived from the demonstration data, be incorporated into the equations used under Appendix I to compensate for the detected systematic bias and thereby help to ensure that emissions are not underestimated when using the F-factor/fuel flow method. With these provisions, EPA proposes to include the F-factor/ fuel flow method as an excepted method for determining flow in Appendix I to part 75. The proposed default multiplier, 1.12, is based on the data and results of the LILCO demonstration and is supported by EPA and the Class of `85 Regulatory Response Group. The default multiplier would be incorporated into the equations used under Appendix I whenever a relative accuracy test audit is performed on a component-by-component basis as was proposed in the LILCO demonstration. Discussion of Proposed Changes EPA proposes to include the F-factor/fuel flow method in Appendix I as an excepted method for use in place of a volumetric flow monitor for oil- and gas-fired units that burn only natural gas and/or fuel oil. The F-factor/fuel flow method uses fuel flow measurement, fuel sampling data, CO2 (or O2 ) CEMS data and F-factors to determine the flow rate of the stack gas. EPA proposes limiting use of the F-factor/fuel flow method to oil- and gas-fired units that burn only natural gas and/or fuel oil because of the greater fuel consistency of oil and natural gas and because the fuel flow rates of oil and natural gas can be monitored accurately with a fuel flowmeter, unlike the feed rate of coal. Appendix I flow monitoring would be done using any of the following combinations of components: a CO2 monitor and a volumetric oil flowmeter, a CO2 monitor and a mass oil flowmeter, a CO2 monitor and a volumetric gas flowmeter, an O2 monitor and a volumetric oil flowmeter, an O2 monitor and a mass oil flowmeter, or an O2 monitor and a volumetric gas flowmeter. Today's proposal would amend Sec. 75.20, ``Certification and Recertification Procedures,'' to add certification and recertification procedures for units using Appendix I flow monitoring systems. Initial certification of the components of the F-factor/fuel flow method would be performed either component by component or on a system basis. If each component is tested separately, then the fuel flowmeter would be tested in accordance with section 2.1.5 of Appendix D, and the CO2 or O2 monitor would have to pass a 7-day calibration test, a linearity check, a cycle time test and a relative accuracy test audit (RATA) using Method 3A from Appendix A to part 60. A bias test would also have to be conducted. If the excepted Appendix I flow monitoring system is tested as an entire system, then the following tests would be performed: a 7-day calibration error test, a linearity check, and a cycle time test on the CO2 or O2 monitor, and a relative accuracy test audit on the entire excepted flow monitoring system using Method 2 from Appendix A to part 60, and a bias test. The owner or operator would also test the data acquisition and handling system. Upon successful completion of all certification tests, the Appendix I system would be considered provisionally certified. Today's proposal would amend Sec. 75.21, ``Quality Assurance and Quality Control Requirements,'' to include Appendix I flow monitoring systems. A unit utilizing the optional F-factor/fuel flow method would have to meet ongoing quality assurance testing requirements. First, the daily and quarterly assessment requirements for a CO2 or O2 monitor in sections 2.1 and 2.2 of Appendix B would have to be followed. Second, one of the following would have to be met, depending on whether the owner or operator chooses to test the method on a component-by-component basis or on a system level: (1) the fuel flow meter quality assurance requirements and a separate RATA on the CO2 (or O2 ) monitor; or (2) a system level flow RATA. If the components are tested separately, the applicable procedures in section 2.1.6 of Appendix D would have to be followed for the fuel flowmeter quality assurance (i.e., a flow meter accuracy test, a transmitter accuracy test and primary element inspection, and/or the supplemental quarterly fuel flow-to-load quality assurance testing) and the applicable RATA procedures in sections 6.5 through 6.5.2.2 of Appendix A for the CO2 (or O2 ) monitor would be followed. In addition, the bias test would have to be performed on the CO2 (or O2 ) monitor and, if the bias test is failed, a bias adjustment factor (BAF) would have to be calculated and applied to hourly data. If the entire system is tested, the applicable procedures in sections 6.5 through 6.5.2.2 of Appendix A would have to be used to meet the performance specifications for flow relative accuracy in section 3.3.4 of Appendix A. The bias test would have to be performed on the volumetric flow data and, if the bias test is failed, a BAF would have to be calculated using the procedures in section 7.6 of Appendix A. Several other sections of the rule would be modified or added in order to incorporate the new excepted method described in Appendix I, including Secs. 75.30, 75.57, 75.58, and 75.59. Section 75.30, ``General Provisions'' (for missing data substitution procedures), would be modified by adding quality assured data from a certified excepted flow monitoring system under Appendix I to the list of monitoring systems that measure flow rate data, for which the missing data substitution procedures of subpart D are required. If fuel sampling data, fuel flow rate data, and diluent gas data are missing, then the data acquisition and handling system would have to substitute for missing volumetric flow data. In addition, Sec. 75.57, would include additional information that Appendix I flow monitoring systems must record. This includes fuel flow rate data and data from component monitors. Section 75.58(g) would be added to address specific volumetric flow rate record provisions for units using the optional protocol in Appendix I. Section 75.59, ``Certification, Quality Assurance and Quality Control Record Provisions,'' would also include certification and quality assurance information that facilities must record for Appendix I flow monitoring system tests. Finally, the new proposed Appendix I would describe the applicability, procedures, calculations, missing data, and recordkeeping and reporting requirements for units using Appendix I to determine flow. The Appendix I formulas are more complex if an O2 monitor is used. EPA proposes to allow the use of an O2 monitor for Appendix I; however, the [[Page 28115]] initial programming of the formulas and monitoring plan development may take longer for Appendix I flow monitoring systems that use an O2 monitor. Volumetric stack flow rate during oil combustion would be calculated from (1) a bias adjustment factor from the applicable bias test results; (2) the fuel flow rate (in gal/hr); (3) the fuel density (in lb/gal); (4) the percent carbon by weight; (5) the CO2 (or O2 ) concentration percent by volume; and (6) the appropriate conversion factor. The carbon content of the fuel would have to be determined according to the procedures in section 2.1 of Appendix G and the density of the oil would have to be determined according to the procedures in section 2.2 of Appendix D. Rationale: EPA is proposing an F-factor/fuel flow method in Appendix I to part 75 as an excepted method to measure volumetric flow directly with a flow monitor because this method would allow fuel flow measurement with a gas or oil flowmeter, fuel sampling data, CO2 (or O2 ) CEMS data, and F-factors to determine the flow rate of the stack gas rather than a volumetric flow monitor. The F-factor/fuel flow method would be available for use by oil-fired and gas-fired units, as defined under Sec. 72.2, provided that they only burn natural gas and/or fuel oil. For these units, EPA believes that the proposed method would provide acceptably accurate measurements of volumetric flow, while affording cost savings that some industry representatives estimate could be substantial. The Agency solicits comment on the proposed Appendix I and associated changes to part 75. Appendix I may offer cost savings to some oil and gas fired units. Representatives from oil- and gas-fired units have estimated that the costs of operating, maintaining and testing volumetric flow monitors range from approximately $15,000 to $25,000 per year. In contrast, using the F-factor/fuel flow method is estimated to result in costs of only approximately $5,000 to $7,000 per year due to elimination of the operating, maintenance, testing and fuel costs associated with the volumetric flow monitor. U. The Use of Predictive Emissions Modeling Systems (PEMS) A number of parties have submitted preliminary field test data designed to demonstrate that EPA should set forth specific requirements for alternative monitoring methodologies that predict NOX emission rates at gas-fired units. These ``predictive emissions modeling systems'' (PEMS) use mathematical models to predict NOX emission rates based on sensor readings of key operating parameters. The agency is evaluating the submitted data and will consider taking further action under a future rulemaking if additional study demonstrates the equivalency of PEMS to CEMS for well defined classes of units. IV. Administrative Requirements A. Public Hearing If requested as specified in the DATES section of this preamble, a public hearing will be held to discuss the proposed regulations. Persons wishing to make oral presentations at the public hearing should contact EPA at the address given in the ADDRESSES section of this preamble. If necessary, oral presentations will be limited to 15 minutes each. Any member of the public may file a written statement with EPA before, during, or within 30 days of the hearing. Written statements should be addressed to the Air Docket address given in the ADDRESSES section of this preamble. A verbatim transcript of the public hearing, if held, and all written statements will be available for public inspection and copying during normal working hours at EPA's Air Docket in Washington, DC (see the ADDRESSES section of this preamble). B. Public Docket The Docket for this regulatory action is A-97-35. The docket is an organized and complete file of all the information submitted to or otherwise considered by EPA in the development of this proposed rulemaking. The principal purposes of the docket are: (1) to allow interested parties a means to identify and locate documents so that they can effectively participate in the rulemaking process, and (2) to serve as the record in case of judicial review. The docket is available for public inspection at EPA's Air Docket, which is listed under the ADDRESSES section of this preamble. C. Executive Order 12866 Under Executive Order 12866 (58 FR 51735, October 4, 1993), the Administrator must determine whether the regulatory action is ``significant'' and therefore subject to Office of Management and Budget (OMB) review and the requirements of the Executive Order. The Order defines ``significant regulatory action'' as one that is likely to result in a rule that may: (1) Have an annual effect on the economy of $100 million or more or adversely affect in a material way the economy, a sector of the economy, productivity, competition, jobs, the environment, public health or safety, or State, local or tribal governments or communities; (2) Create a serious inconsistency or otherwise interfere with an action taken or planned by another agency; (3) Materially alter the budgetary impact of entitlements, grants, user fees, or loan programs or the rights and obligations of recipients thereof; or (4) Raise novel legal or policy issues arising out of legal mandates, the President's priorities, or the principles set forth in the Executive Order. This proposed rule is not expected to have an annual effect on the economy of $100 million or more. However, pursuant to the terms of Executive Order 12866, it has been determined that this proposed rule is a significant action because it raises novel policy issues. As such, the proposed rule has been submitted for OMB review. Any written comments from OMB and any EPA response to OMB comments are in the public docket for this proposal. D. Unfunded Mandates Reform Act Title II of the Unfunded Mandates Reform Act of 1995 (UMRA), P.L. 104-4, establishes requirements for Federal agencies to assess the effects of their regulatory actions on State, local, and tribal governments and the private sector. Under section 202 of the UMRA, EPA generally must prepare a written statement, including a cost-benefit analysis, for proposed and final rules with ``Federal mandates'' that may result in expenditures to State, local, and tribal governments, in the aggregate, or to the private sector, of $100 million or more in any one year. Before promulgating an EPA rule for which a written statement is needed, section 205 of the UMRA generally requires EPA to identify and consider a reasonable number of regulatory alternatives and adopt the least costly, most cost-effective, or least burdensome alternative that achieves the objectives of the rule. The provisions of section 205 do not apply when they are inconsistent with applicable law. Moreover, section 205 allows EPA to adopt an alternative other than the least costly, most cost-effective, or least burdensome alternative if the Administrator publishes with the final rule an explanation why that alternative was not adopted. Before EPA establishes any regulatory requirements that may significantly or uniquely affect small governments, including tribal governments, it must have developed under section 203 of the UMRA a small government agency plan. The plan must provide for notifying potentially affected small governments, enabling officials of affected small governments [[Page 28116]] to have meaningful and timely input in the development of EPA regulatory proposals with significant Federal intergovernmental mandates, and informing, educating, and advising small governments on compliance with the regulatory requirements. This proposed rule is not expected to result in expenditures of more than $100 million in any one year and, as such, is not subject to section 202 of the UMRA. Although the proposed rule is not expected to significantly or uniquely affect small governments, the Agency has notified all potentially affected small governments that own or operate units potentially affected by the proposal in order to assure that they have the opportunity to have meaningful and timely input on the proposed rule. EPA will continue to use its outreach efforts related to part 75 implementation, including a policy manual that is generally updated on a quarterly basis, to inform, educate, and advise all potentially impacted small governments about compliance with part 75. E. Paperwork Reduction Act The information collection requirements in this proposal have been submitted for approval to the OMB under the Paperwork Reduction Act, 44 U.S.C. 3501, et seq. An Information Collection Request (ICR) document has been prepared by EPA (ICR No. 1835.01), and a copy may be obtained from Sandy Farmer, OPPE Regulatory Information Division; U.S. Environmental Protection Agency (2137); 401 M Street, SW, Washington, DC 20460, by calling (202) 260-2740, or via the Internet at www.gov/ icr. Currently, all affected utilities are required to keep records and submit electronic quarterly reports under the provisions of part 75. The proposed rule includes several new options for compliance with part 75 which have been requested by affected utilities. To implement these options, EPA would have to modify the existing recordkeeping and reporting requirements. In some circumstances, these changes would result in significant reductions in the reporting and recordkeeping burdens or costs for some units (such as low mass emissions units). However, these changes would require modifications to the software used to generate electronic reports. In addition, there would be some increased burden or costs for certain units to fulfill the new quality assurance procedures proposed in these proposed revisions. Finally, several other technical revisions to the existing reporting and recordkeeping requirements have been proposed to clarify existing provisions or to facilitate reporting for other regulatory programs in the context of Acid Rain Program reporting. Although these one-time software changes would tend to increase the short-term burdens allocated to the Acid Rain Program, such changes should reduce a source's overall long-term burden by streamlining the source's reporting obligations under both the Acid Rain Program and the Act. The average annual projected hour burden is 2,608,836, which is based on an estimated 835 likely respondents (on a per utility basis). The projected cost burden resulting from the collection of information is $47,555,000, which includes a total projected capital and start-up cost of $1,436,000 (for monitoring equipment/software), and a total projected operation and maintenance cost (which includes purchase of testing contractor services and total projected fuel sampling and analysis cost of $716,000) of $46,119,000. Burden means the total time, effort, or financial resources expended by persons to generate, maintain, retain, disclose, or provide information to or for a Federal agency. This includes the time needed to review instructions; develop, acquire, install, and utilize technology and systems for purposes of collecting, validating, and verifying information, processing and maintaining information, and disclosing and providing information; adjust the existing ways to comply with any previously applicable instructions and requirements; train personnel to be able to respond to a collection of information; search data sources; complete and review the collection of information; and transmit or otherwise disclose the information. An agency may not conduct or sponsor and a person is not required to respond to a collection of information, unless it displays a currently valid OMB control number. The OMB control numbers for EPA's regulations are listed in 40 CFR part 9 and 48 CFR chapter 15. Comments are requested on the Agency's need for this information, the accuracy of the provided burden estimates, and any suggested methods for minimizing respondent burden, including through the use of automated collection techniques. Send comments on the ICR to the Director, OPPE Regulatory Information Division; U.S. Environmental Protection Agency (2137); 401 M Street, SW, Washington, DC 20460; and to the Office of Information and Regulatory Affairs, Office of Management and Budget, 725 17th Street, NW, Washington, DC 20503, marked ``Attention: Desk Officer for EPA.'' Include the ICR number in any correspondence. Since OMB is required to make a decision concerning the ICR between 30 and 60 days after May 21, 1998, a comment to OMB is best assured of having its full effect if OMB receives it by June 22, 1998. The final rule will respond to any OMB or public comments on the information collection requirements contained in this proposal. F. Regulatory Flexibility Act The Regulatory Flexibility Act (RFA), 5 U.S.C. 601, et seq., generally requires an agency to conduct a regulatory flexibility analysis of any rule subject to notice and comment rulemaking requirements unless the agency certifies that the rule will not have a significant economic impact on a substantial number of small entities. Small entities include small businesses, small not-for-profit enterprises, and governmental jurisdictions. This proposed rule would not have a significant impact on a substantial number of small entities. Today's proposed revisions to part 75 result in a net cost reduction to utilities affected by the Acid Rain Program, including small entities. Most importantly, the proposed changes to Appendix D and the addition of an optional calculation procedure instead of actual monitoring for oil- and gas-fired units with low mass emissions would significantly reduce the cost of complying with part 75 for oil-and gas-fired units, many of which are owned or operated by small entities. Therefore, I certify this action will not have a significant economic impact on a substantial number of small entities. G. National Technology Transfer and Advancement Act Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (``ANTTAA''), Pub L. No. 104-113 15 USC 272 note, directs EPA to use voluntary consensus standards in its regulatory activities unless to do so would be inconsistent with applicable law or otherwise impractical. Voluntary consensus standards are technical standards (e.g., materials specifications, test methods, sampling procedures, business practices, etc.) that are developed or adopted by voluntary consensus standards bodies. The NTTAA requires EPA to provide Congress, through OMB, explanations when the Agency decides not to use available and applicable voluntary consensus standards. This regulatory action proposes to incorporate by reference voluntary consensus standards pursuant to Sec. 12(d) of the NTTAA. The EPA has adopted the general policy of using voluntary [[Page 28117]] consensus standards from technically knowledgeable groups such as the Organization for International Standards (ISO), the American Society for Testing and Materials (ASTM), the American Society of Mechanical Engineers (ASME), the American Gas Association (AGA), the Gas Processors Association (GPA), and the American Petroleum Institute (API). EPA invites public comment on the voluntary consensus standards which are proposed to be incorporated by reference for use in part 75. EPA has not identified any additional voluntary consensus standards which might be applicable to this rulemaking. This does not indicate that other applicable standards do not exist or that any other standards should not be allowed. Therefore, EPA also invites public comment on any other voluntary consensus standards which may be appropriate for the proposed regulatory action. Further, if additional applicable voluntary consensus standards are identified in the future, the designated representative may petition under Sec. 75.66(c) to use an alternative to any standard incorporated by reference and prescribed in this part. EPA proposes to incorporate by reference the following voluntary consensus standards for use under part 75: a. ASTM D5373-93 ``Standard Methods for Instrumental Determination of Carbon, Hydrogen and Nitrogen in laboratory samples of Coal and Coke.'' This standard is proposed to be incorporated by reference for use under section 2.1 of Appendix G to part 75 and is discussed further in section III.Q.1 of this preamble. b. API Section 2 ``Conventional Pipe Provers'' from Chapter 4 of the Manual of Petroleum Measurement Standards, October 1988 edition. This standard is proposed to be incorporated by reference for use under paragraph (g)(1)(i) of Sec. 75.20 and under section 2.1.5.1 of Appendix D to part 75. The proposal to incorporate this standard by reference is discussed further in section III.P.6.(b) of this preamble. List of Subjects in 40 CFR Parts 72 and 75 Air pollution control, Carbon dioxide, Continuous emission monitors, Electric utilities, Environmental protection, Nitrogen oxides, Reporting and recordkeeping requirements, Sulfur dioxide. Dated: April 27, 1998. Carol M. Browner, Administrator, U.S. Environmental Protection Agency. For the reasons set out in the preamble, title 40 chapter 1 of the Code of Federal Regulations is proposed to be amended as follows: PART 72--PERMITS REGULATION 1. The authority for part 72 continues to read as follows: Authority: 42 U.S.C. 7601 and 7651, et seq. 2. Section 72.2 is amended by revising the definitions of ``calibration gas,'' ``excepted monitoring system,'' ``gas-fired,'' ``pipeline natural gas,'' ``span,'' ``stationary gas turbine,'' and ``zero air material''; by revising paragraph (2) of ``oil-fired'' and paragraph (2) of the ``peaking unit''; by adding paragraph (3) to the definition of ``peaking unit''; by adding new definitions for ``conditionally valid data,'' ``EPA protocol gas,'' ``gas manufacturer's intermediate standard,'' ``low mass emissions unit,'' ``maximum rated hourly heat input,'' ``ozone season,'' ``probationary calibration error test,'' ``research gas mixture (RGM)'', and ``standard reference material-equivalent compressed gas primary reference material''; and by removing the definition of ``protocol 1 gas,'' to read as follows: Sec. 72.2 Definitions. * * * * * Calibration gas means: (1) A standard reference material; (2) A standard reference material-equivalent compressed gas primary reference material; (3) A NIST traceable reference material; (4) NIST/EPA-approved certified reference materials; (5) A gas manufacturer's intermediate standard; (6) An EPA protocol gas; (7) Zero air material; or (8) A research gas mixture. * * * * * Conditionally valid data means data from a continuous monitoring system that are not quality assured, but which may become quality assured if certain conditions are met. Examples of data that may qualify as conditionally valid are: data recorded by an uncertified monitoring system prior to its initial certification; or data recorded by a certified monitoring system following a significant change to the system that may affect its ability to accurately measure and record emissions. A monitoring system must pass a probationary calibration error test, in accordance with section 2.1.1 of appendix B of part 75 of this chapter, to initiate the conditionally valid data status. In order for conditionally valid emission data to become quality assured, one or more quality assurance tests or diagnostic tests must be passed within a specified time period. * * * * * EPA protocol gas means a calibration gas mixture prepared and analyzed according to section 2 of the ``EPA Traceability Protocol for Assay and Certification of Gaseous Calibration Standards,'' September 1997, EPA-600/R-97/121 or such revised procedure as approved by the Administrator. * * * * * Excepted monitoring system means a monitoring system that follows the procedures and requirements of Sec. 75.19 of this chapter or of appendix D or E to part 75 for approved exceptions to the use of continuous emission monitoring systems. * * * * * Gas-fired means: (1) For all purposes under the Acid Rain Program, except for part 75 of this chapter, the combustion of: (i) Natural gas or other gaseous fuel (including coal-derived gaseous fuel), for at least 90.0 percent of the unit's average annual heat input during the previous three calendar years and for at least 85.0 percent of the annual heat input in each of those calendar years; and (ii) Any fuel, except coal or solid or liquid coal-derived fuel for the remaining heat input, if any. (2) For purposes of part 75 of this chapter, the combustion of: (i) Natural gas or other gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas (including coal-derived gaseous fuel) for at least 90.0 percent of the unit's average annual heat input during the previous calendar years and for at least 85.0 percent of the annual heat input in each of those calendar years; and (ii) Fuel oil, for the remaining heat input, if any. (3) For purposes of part 75 of this chapter, a unit may initially qualify as gas-fired if the designated representative demonstrates to the satisfaction of the Administrator that the requirements of paragraph (2) of this definition are met, or will in the future be met, through one of the following submissions: (i) For a unit for which a monitoring plan has not been submitted under Sec. 75.62 of this chapter, (A) The designated representative submits fuel usage data for the unit for [[Page 28118]] the three calendar years immediately preceding the date of initial submission of the monitoring plan for the unit under Sec. 75.62; or (B) For a unit that does not have fuel usage data for one or more of the three calendar years immediately preceding the date of initial submission of the monitoring plan for the unit under Sec. 75.62, if the designated representative submits: the unit's designated fuel usage; all available fuel usage data (including the percentage of the unit's heat input derived from the combustion of gaseous fuels), beginning with the date on which the unit commenced commercial operation; and the unit's projected fuel usage. (ii) For a unit for which a monitoring plan has already been submitted under Sec. 75.62, that has not qualified as gas-fired under paragraph (3)(i) of this definition, and whose fuel usage changes, the designated representative submits either: (A) Three calendar years of data following the change in the unit's fuel usage, showing that no less than 90.0 percent of the unit's average annual heat input during the previous three calendar years, and no less than 85.0 percent of the unit's annual heat input during any one of the previous three calendar years is from the combustion of gaseous fuels with a total sulfur content no greater than the total sulfur content of natural gas and the remaining heat input is from the combustion of fuel oil; or (B) A minimum of 720 hours of unit operating data following the change in the unit's fuel usage, showing that no less than 90.0 percent of the unit's heat input is from the combustion of gaseous fuels with a total sulfur content no greater than the total sulfur content of natural gas and the remaining heat input is from the combustion of fuel oil, and a statement that this changed pattern of fuel usage is considered permanent and is projected to continue for the foreseeable future. (iii) If a unit qualifies as gas-fired under paragraph (2)(i) or (ii) of this definition, the unit is classified as gas-fired as of the date of the submission under such paragraph. (4) For purposes of part 75 of this chapter, a unit that initially qualifies as gas-fired must meet the criteria in paragraph (2) of this definition each year in order to continue to qualify as gas-fired. If such a unit fails to meet such criteria for a given year, the unit no longer qualifies as gas-fired starting January 1 of the year after the first year for which the criteria are not met. If a unit failing to meet the criteria in paragraph (2) of this definition initially qualified as a gas-fired unit under paragraph (3)(ii) of this definition, the unit may qualify as a gas-fired unit for a subsequent year only under paragraph (3)(i) of this definition. * * * * * Gas manufacturer's intermediate standard (GMIS) means a compressed gas calibration standard that has been assayed and certified by direct comparison to a standard reference material (SRM), an SRM-equivalent PRM, a NIST/EPA-approved certified reference material (CRM), or a NIST traceable reference material (NTRM), in accordance with section 2.1.2.1 of the ``EPA Traceability Protocol for Assay and Certification of Gaseous Calibration Standards,'' September 1997, EPA-600/R-97/121. * * * * * Low mass emissions unit means a gas-fired or oil-fired unit that burns only natural gas and/or fuel oil and that qualifies under Secs. 75.19(a) and (b) of this chapter. * * * * * Maximum rated hourly heat input means a unit-specific maximum hourly heat input (mmBtu) which is the higher of the manufacturer's maximum rated hourly heat input or the highest observed hourly heat input. Oil-fired means: * * * * * (2) For purposes of part 75 of this chapter, a unit may qualify as oil-fired if the unit burns only fuel oil and gaseous fuels with a total sulfur content no greater than the total sulfur content of natural gas and if the unit does not meet the definition of gas-fired. * * * * * Ozone season means the period of time from May 1st to September 30th, inclusive. * * * * * Peaking unit means: * * * * * (2) For purposes of part 75 of this chapter, a unit may initially qualify as a peaking unit if the designated representative demonstrates to the satisfaction of the Administrator that the requirements of paragraph (1) of this definition are met, or will in the future be met, through one of the following submissions: (i) For a unit for which a monitoring plan has not been submitted under Sec. 75.62, (A) The designated representative submits capacity factor data for the unit for the three calendar years immediately preceding the date of initial submission of the monitoring plan for the unit under Sec. 75.62; or (B) For a unit that does not have capacity factor data for one or more of the three calendar years immediately preceding the date of initial submission of the monitoring plan for the unit under Sec. 75.62, the designated representative submits: all available capacity factor data, beginning with the date on which the unit commenced commercial operation; and projected capacity factor. (ii) For a unit for which a monitoring plan has already been submitted under Sec. 75.62, that has not qualified as a peaking unit under paragraph (2)(i) of this definition, and where capacity factor changes, the designated representative submits either: (A) Three calendar years of data following the change in the unit's capacity factor showing an average capacity factor of no more than 10.0 percent during the three previous calendar years and a capacity factor of no more than 20.0 percent in each of those calendar years; or (B) One calendar year of data following the change in the unit's capacity factor showing a capacity factor of no more than 10.0 percent and a statement that this changed pattern of operation resulting in a capacity factor less than 10.0 percent is considered permanent and is projected to continue for the foreseeable future. (3) For purposes of part 75 of this chapter, a unit that initially qualifies as a peaking unit must meet the criteria in paragraph (1) of this definition each year in order to continue to qualify as a peaking unit. If such a unit fails to meet such criteria for a given year, the unit no longer qualifies as a peaking unit starting January 1 of the year after the year for which the criteria are not met. If a unit failing to meet the criteria in paragraph (1) of this definition initially qualified as a gas-fired unit under paragraph (2)(ii) of this definition, the unit may qualify as a peaking unit for a subsequent year only under paragraph (2)(i) of this definition. * * * * * Pipeline natural gas means natural gas that is provided by a supplier through a pipeline and that contains 0.3 grains or less of hydrogen sulfide per 100 standard cubic feet. The hydrogen sulfide content of the natural gas must be documented either through quality characteristics specified by a purchase contract or pipeline transportation contract, through certification of the gas vendor, based on routine vendor sampling and analysis, or through at least one year's worth of analytical data on the fuel hydrogen sulfide content from samples taken at least monthly, demonstrating that all samples contain [[Page 28119]] 0.3 grains or less of hydrogen sulfide per 100 standard cubic feet. * * * * * Probationary calibration error test means an on-line calibration error test performed in accordance with section 2.1.1 of appendix B of part 75 of this chapter that is used to initiate a conditionally valid data period. * * * * * Research gas mixture (RGM) means a calibration gas mixture developed by agreement of a requestor and NIST that NIST analyzes and certifies as ``NIST traceable.'' RGMs may have concentrations different from those of standard reference materials. * * * * * Span means the highest pollutant or diluent concentration or flow rate that a monitor component is required to be capable of measuring under part 75 of this chapter. * * * * * Standard reference material-equivalent compressed gas primary reference material (SRM-equivalent PRM) means those gas mixtures listed in a declaration of equivalence in accordance with section 2.1.2 of the ``EPA Traceability Protocol for Assay and Certification of Gaseous Calibration Standards,'' September 1997, EPA-600/R-97/121. * * * * * Stationary gas turbine means a turbine that is not self-propelled and that combusts natural gas, other gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas, or fuel oil in order to heat inlet combustion air and thereby turn a turbine, in addition to or instead of producing steam or heating water. * * * * * Zero air material means either: (1) A calibration gas certified by the gas vendor not to contain concentrations of SO2 , NOX, or total hydrocarbons above 0.1 parts per million (ppm), a concentration of CO above 1 ppm, a concentration of CO2 above 400 ppm; or (2) Ambient air conditioned and purified by a CEMS for which the CEMS manufacturer or vendor certifies that the particular CEMS model produces conditioned gas that does not contain concentrations of SO2 , NOX, or total hydrocarbons above 0.1 ppm, a concentration of CO above 1 ppm, or a concentration of CO2 above 400 ppm; or (3) For dilution-type CEMS, conditioned and purified ambient air provided by a conditioning system concurrently supplying dilution air to the CEMS; or (4) A multicomponent mixture certified by the supplier of the mixture that the concentration of the component being zeroed is less than or equal to the applicable concentration specified in paragraph (1) of this definition, and that the mixture's other components do not interfere with the specific CEM readings or cause the CEM being zeroed to read concentrations of the gas being zeroed. 3. Section 72.3 is amended by adding in alphabetical order, new acronyms for kacfm, kscfh, and NIST to read as follows: Sec. 72.3 Measurements, abbreviations, and acronyms. * * * * * kacfm--thousands of cubic feet per minute at actual conditions. kscfh--thousands of cubic feet per hour at standard conditions. NIST--National Institute of Standards and Technology. * * * * * Sec. 72.6 [Amended] 4. Section 72.6 is amended by removing from paragraph (b)(1) the word ``operation'' and adding, in its place, the words ``commercial operation.'' 5. Section 72.90 is amended by revising paragraph (c)(3) to read as follows: Sec. 72.90 Annual compliance certification report. * * * * * (c) * * * (3) Whether all the emissions from the unit, or a group of units (including the unit) using a common stack, were monitored or accounted for through the missing data procedures and reported in the quarterly monitoring reports, including whether conditional data were reported in the quarterly report. If conditional data were reported, the owner or operator shall indicate whether the status of all conditional data has been resolved and all necessary quarterly report resubmissions have been made. * * * * * PART 75--CONTINUOUS EMISSION MONITORING 6. The authority citation for part 75 continues to read as follows: Authority: 42 U.S.C. 7601 and 7651k. 7. Section 75.1 is amended by revising paragraph (a) to read as follows: Sec. 75.1 Purpose and scope. (a) Purpose. The purpose of this part is to establish requirements for the monitoring, recordkeeping, and reporting of sulfur dioxide, nitrogen oxides, and carbon dioxide emissions, volumetric flow, and opacity data from affected units under the Acid Rain Program pursuant to Sections 412 and 821 of the Clean Air Act, 42 U.S.C. 7401-7671q as amended by Public Law 101-549 (November 15, 1990) (the Act). In addition, this part sets forth provisions for the monitoring, recordkeeping, and reporting of NOX mass emissions with which EPA, individual States, or groups of States may require sources to comply in order to demonstrate compliance with a NOX mass emission reduction program, if these provisions are adopted as requirements under such a program. * * * * * 8. Section 75.2 is amended by revising paragraph (a) and adding a new paragraph (c) to read as follows: Sec. 75.2 Applicability. (a) Except as provided in paragraphs (b) and (c) of this section, the provisions of this part apply to each affected unit subject to Acid Rain emission limitations or reduction requirements for SO2 or NOX. * * * * * (c) The provisions of this part may apply to sources subject to a State or federal NOX mass emission reduction program, if these provisions are adopted as requirements under such a program. 9. Section 75.4 is amended by revising paragraphs (a) introductory text and (d)(1) and adding a new paragraph (i) to read as follows: Sec. 75.4 Compliance dates. (a) The provisions of this part apply to each existing Phase I and Phase II unit on February 10, 1993. For substitution or compensating units that are so designated under the Acid Rain permit which governs that unit and contains the approved substitution or reduced utilization plan, pursuant to Sec. 72.41 or Sec. 72.43 of this chapter, the provisions of this part become applicable upon the issuance date of the Acid Rain permit. For combustion sources seeking to enter the Opt-in Program in accordance with part 74 of this chapter, the provisions of this part become applicable upon the submission of an Opt-in permit application in accordance with Sec. 74.14 of this chapter. The provisions of this part for the monitoring, recording, and reporting of NOX mass emissions become applicable on the deadlines specified in the applicable State or federal NOX mass emission reduction program, if these provisions are adopted as requirements under such a program. In accordance with Sec. 75.20, the owner or operator of each existing affected unit shall ensure that all monitoring systems required by [[Page 28120]] this part for monitoring SO2 , NOX, CO2 , opacity, and volumetric flow are installed and that all certification tests are completed no later than the following dates (except as provided in paragraphs (d) through (h) of this section): * * * * * (d) * * * (1) The maximum potential concentration of SO2 , the maximum potential NOX emission rate, the maximum potential flow rate, as defined in section 2.1 of appendix A to this part, or the maximum potential CO2 concentration, as defined in section 2.1.3.1 of appendix A to this part. * * * * * (i) In accordance with Sec. 75.20, the owner or operator of each affected unit at which SO2 concentration is measured on a dry basis or at which moisture corrections are required to account for CO2 emissions, NOX emission rate in lb/mmBtu, or heat input, shall ensure that the continuous moisture monitoring system required by this part is installed and that all applicable initial certification tests required under Sec. 75.20(c)(5), (c)(6), or (c)(7) for the continuous moisture monitoring system are completed no later than the following dates: (1) January 1, 2000, for a unit that is existing and has commenced commercial operation by October 3, 1999; or (2) For a new affected unit which has not commenced commercial operation by October 4, 1999, not later than 90 days after the date the unit commences commercial operation; or (3) For an existing unit that is shutdown and is not yet operating by January 1, 2000, not later than the earlier of 45 unit operating days or 180 calendar days after the date that the unit recommences commercial operation. 10. Section 75.5 is amended by revising paragraph (f)(2) to read as follows: Sec. 75.5 Prohibitions. * * * * * (f) * * * (2) The owner or operator is monitoring emissions from the unit with another certified monitoring system or an excepted methodology approved by the Administrator for use at that unit that provides emission data for the same pollutant or parameter as the retired or discontinued monitoring system; or * * * * * 11. Section 75.6 is amended by redesignating paragraph (a)(40) as paragraph (a)(41) and by adding new paragraphs (a)(40) and (f) to read as follows: Sec. 75.6 Incorporation by reference. * * * * * (a) * * * (40) ASTM D5373-93, ``Standard Methods for Instrumental Determination of Carbon, Hydrogen, and Nitrogen in Laboratory Samples of Coal and Coke,'' for appendix G to this part. * * * * * (f) The following materials are available for purchase from the following address: American Petroleum Institute, Publications Department, 1220 L Street NW, Washington, DC 20005-4070: American Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' from Chapter 4 of the Manual of Petroleum Measurement Standards, October 1988 (Reaffirmed 1993), for Sec. 75.20 and appendix D to this part. 12. Section 75.10 is amended by revising paragraphs (d)(3) and (f) to read as follows: Sec. 75.10 General operating requirements. * * * * * (d) * * * (3) Failure of an SO2 , CO2 , or O2 pollutant concentration monitor, flow monitor, or NOX continuous emission monitoring system to acquire the minimum number of data points for calculation of an hourly average in paragraph (d)(1) of this section, shall result in the failure to obtain a valid hour of data and the loss of such component data for the entire hour. An hourly average NOX or SO2 emission rate in lb/mmBtu is valid only if the minimum number of data points is acquired by both the pollutant concentration monitor (NOX or SO2 ) and the diluent monitor (O2 or CO2 ). For a moisture monitoring system consisting of one or more oxygen analyzers capable of measuring O2 on a wet-basis and a dry-basis, an hourly average percent moisture value is valid only if the minimum number of data points is acquired for both the wet-and dry-basis measurements. Except for SO2 emission rate data in lb/mmBtu, if a valid hour of data is not obtained, the owner or operator shall estimate and record emission, moisture, or flow data for the missing hour by means of the automated data acquisition and handling system, in accordance with the applicable procedure for missing data substitution in subpart D of this part. * * * * * (f) Minimum measurement capability requirement. The owner or operator shall ensure that each continuous emission monitoring system and component thereof is capable of accurately measuring, recording, and reporting data, and shall not incur a full scale exceedance, except as provided in sections 2.1.1.5, 2.1.2.5, and 2.1.4.3 of appendix A to this part. * * * * * 13. Section 75.11 is amended by revising paragraphs (a), (b), (d)(1), (d)(2), (e)(2), (e)(3) introductory text, (e)(3)(ii), (e)(3)(iv), and (e)(4) and by adding paragraph (d)(3), to read as follows: Sec. 75.11 Specific provisions for monitoring SO2 emissions (SO2 and flow monitors). (a) Coal-fired units. The owner or operator shall meet the general operating requirements in Sec. 75.10 for an SO2 continuous emission monitoring system and a flow monitoring system for each affected coal-fired unit while the unit is combusting coal and/or any other fuel, except as provided in paragraph (e) of this section, in Sec. 75.16, and in subpart E of this part. During hours in which only natural gas or gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas (i.e.,20 grains per 100 standard cubic feet (gr/100 scf)) is combusted in the unit, the owner or operator shall comply with the applicable provisions of paragraph (e)(1), (e)(2), or (e)(3) of this section. (b) Moisture correction. Where SO 2 concentration is measured on a dry basis, the owner or operator shall install, operate, maintain, and quality assure a continuous moisture monitoring system for measuring and recording the moisture content of the flue gases, in order to correct the measured hourly volumetric flow rates for moisture when calculating SO2 mass emissions (in lb/hr) using the procedures in appendix F to this part. The following continuous moisture monitoring systems are acceptable: a continuous moisture sensor; an oxygen analyzer (or analyzers) capable of measuring O2 both on a wet basis and on a dry basis; or a stack temperature sensor and a moisture look-up table, i.e., a psychrometric chart (for saturated gas streams following wet scrubbers, only). The moisture monitoring system shall include as a component the automated data acquisition and handling system (DAHS) for recording and reporting both the raw data (e.g., hourly average wet and dry-basis O2 values) and the hourly average values of the stack gas moisture content derived from those data. When a moisture look-up table is used, the moisture monitoring system shall be represented as a single component, the certified DAHS, in the monitoring plan for the unit or common stack. * * * * * (d) * * * (1) By meeting the general operating requirements in Sec. 75.10 for an SO2 continuous emission monitoring system [[Page 28121]] and flow monitoring system. If this option is selected, the owner or operator shall comply with the applicable provisions in paragraph (e)(1), (e)(2), or (e)(3) of this section during hours in which the unit combusts only natural gas (or gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas); (2) By providing other information satisfactory to the Administrator using the applicable procedures specified in appendix D to this part for estimating hourly SO2 mass emissions. Appendix D shall not, however, be used when the unit combusts gaseous fuel with a total sulfur content greater than the total sulfur content of natural gas (i.e., > 20 gr/100 scf); when such fuel is burned, the owner or operator shall comply with the provisions of paragraph (e)(4) of this section; or (3) By using the low mass emissions excepted methodology in Sec. 75.19(c) for estimating hourly SO2 mass emissions if the affected unit qualifies as a low mass emissions unit under Sec. 75.19(a) and (b). (e) * * * (2) When gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas (i.e.,20 gr/100 scf) is combusted in the unit, the owner or operator may, in lieu of operating and recording data from the SO 2 monitoring system, determine SO2 emissions by certifying an excepted monitoring system in accordance with Sec. 75.20 and with appendix D to this part, by following the fuel sampling and analysis procedures in section 2.3.1 of appendix D to this part, by meeting the recordkeeping requirements of Sec. 75.55 or Sec. 75.58, as applicable, and by meeting all quality control and quality assurance requirements for fuel flowmeters in appendix D to this part. If this compliance option is selected, the hourly unit heat input reported under Sec. 75.54(b)(5) or Sec. 75.57(b)(5), as applicable, shall be determined using a certified flow monitoring system and a certified diluent monitor, in accordance with the procedures in section 5.2 of appendix F of this part. The flow monitor and diluent monitor shall meet all of the applicable quality control and quality assurance requirements of appendix B of this part. (3) When gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas (i.e.,20 gr/100 scf) is burned in the unit, the owner or operator may determine SO 2 mass emissions by using a certified SO2 continuous monitoring system, in conjunction with a certified flow rate monitoring system. However, on and after January 1, 2000, the SO2 monitoring system shall be subject to the following provisions; prior to January 1, 2000, the owner or operator may comply with these provisions: * * * * * (ii) The calibration response of the SO2 monitoring system shall be adjusted, either automatically or manually, in accordance with the procedures for routine calibration adjustments in section 2.1.3 of appendix B to this part, whenever the zero-level calibration response during a required daily calibration error test exceeds the applicable performance specification of the instrument in section 3.1 of appendix A to this part (i.e.,2.5 percent of the span value or 5 ppm, whichever is less restrictive). This calibration adjustment is optional if gaseous fuel is burned in the affected unit only during unit startup. * * * * * (iv) In accordance with the requirements of section 2.1.1.2 of appendix A to this part, for units that sometimes burn natural gas (or gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas) and at other times burn higher-sulfur fuel(s) such as coal or oil, a second low-scale SO 2 measurement range is not required when natural gas (or gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas) is combusted. For units that burn only natural gas (or gaseous fuel with a total sulfur content no greater than the total sulfur content of natural gas) and burn no other type(s) of fuel(s), the owner or operator shall set the span of the SO2 monitoring system to a value no greater than 200 ppm. (4) During any hours in which a unit combusts only gaseous fuel(s) with a total sulfur content no greater than the total sulfur content of natural gas (i.e.,20 gr/100 scf), the owner or operator shall meet the general operating requirements in Sec. 75.10 for an SO 2 continuous emission monitoring system and a flow monitoring system. * * * * * 14. Section 75.12 is amended by revising the title; by redesignating existing paragraphs (b), (c), and (d) as paragraphs (c), (d), and (f), respectively; by adding new paragraphs (b) and (e); and by revising the newly designated paragraph (c), to read as follows: Sec. 75.12 Specific provisions for monitoring NOX emission rate (NOX and diluent gas monitors). * * * * * (b) Moisture correction. If a correction for the stack gas moisture content is needed to properly calculate the NOX emission rate in lb/mmBtu, i.e., if the NOX pollutant concentration monitor measures on a different moisture basis from the diluent monitor, the owner or operator shall install, operate, maintain, and quality assure a continuous moisture monitoring system, as defined in Sec. 75.11(b). (c) Determination of NOX emission rate. The owner or operator shall calculate hourly, quarterly, and annual NOX emission rates (in lb/mmBtu) by combining the NOX concentration (in ppm), diluent concentration (in percent O2 or CO2 ), and percent moisture (if applicable) measurements according to the procedures in appendix F to this part. * * * * * (e) Low mass emissions units. Notwithstanding the requirements of Secs. 75.12(a) and (c), the owner or operator of an affected unit that qualifies as a low mass emissions unit under Sec. 75.19(a) and (b) shall comply with one of the following: (1) Meet the general operating requirements in Sec. 75.10 for a NOX continuous emission monitoring system; (2) Meet the requirements specified in paragraph (d)(2) of this section for using the excepted monitoring procedures in appendix E to this part, if applicable; or (3) Use the low mass emissions excepted methodology in Sec. 75.19(c) for estimating hourly NOX emission rate and hourly NOX mass emissions. * * * * * 15. Section 75.13 is amended by revising paragraphs (a) and (c) and by adding paragraph (d) to read as follows: Sec. 75.13 Specific provisions for monitoring CO2 emissions. (a) CO2 continuous emission monitoring system. If the owner or operator chooses to use the continuous emission monitoring method, then the owner or operator shall meet the general operating requirements in Sec. 75.10 for a CO2 continuous emission monitoring system and flow monitoring system for each affected unit. The owner or operator shall comply with the applicable provisions specified in Secs. 75.11(a) through (e) or Sec. 75.16, except that the phrase ``SO2 continuous emission monitoring system'' is replaced with ``CO2 continuous emission monitoring system,'' the phrase ``SO2 concentration'' is replaced with ``CO2 concentration,'' the term ``maximum potential concentration of SO2 '' is replaced with ``maximum potential concentration of CO2 ,'' and the phrase ``SO2 mass emissions'' is replaced with ``CO2 mass emissions.'' * * * * * (c) Determination of CO2 mass emissions using an O2 monitor [[Page 28122]] according to appendix F. If the owner or operator chooses to use the appendix F method, then the owner or operator may determine hourly CO2 concentration and mass emissions with a flow monitoring system; a continuous O2 concentration monitor; fuel F and Fc factors; and, where O2 concentration is measured on a dry basis, a continuous moisture monitoring system, as defined in Sec. 75.11(b), using the methods and procedures specified in appendix F to this part. For units using a common stack, multiple stack, or bypass stack, the owner or operator may use the provisions of Sec. 75.16, except that the phrase ``SO2 continuous emission monitoring system'' is replaced with ``CO2 continuous emission monitoring system,'' the term ``maximum potential concentration of SO2 '' is replaced with ``maximum potential concentration of CO2 ,'' and the phrase ``SO2 mass emissions'' is replaced with ``CO2 mass emissions.'' (d) Determination of CO2 mass emissions from low mass emissions units. The owner or operator of a unit that qualifies as a low mass emissions unit under Secs. 75.19(a) and (b) shall comply with one of the following: (1) Meet the general operating requirements in Sec. 75.10 for a CO2 continuous emission monitoring system and flow monitoring system; (2) Meet the requirements specified in paragraph (b) or (c) of this section for use of the methods in appendix G or F to this part, respectively; or (3) Use the low mass emissions excepted methodology in Sec. 75.19(c) for estimating hourly CO2 mass emissions. 16. Section 75.16 is amended by: a. Revising paragraphs (b)(2)(ii)(B), (b)(2)(ii)(D), (d)(2), and (e)(1); b. Removing paragraphs (e)(2) and (e)(3); c. Redesignating existing paragraphs (e)(4) and (e)(5) as paragraphs (e)(2) and (e)(3), respectively; d. Revising the last sentence and adding a new sentence to the end of the newly designated paragraph (e)(3); and e. Adding a new paragraph (e)(4), to read as follows: Sec. 75.16 Special provisions for monitoring emissions from common, bypass, and multiple stacks for SO2 emissions and heat input determinations. * * * * * (b) * * * (2) * * * (ii) * * * (B) Install, certify, operate, and maintain an SO2 continuous emission monitoring system and flow monitoring system in the duct from each nonaffected unit; determine SO2 mass emissions from the affected units as the difference between SO2 mass emissions measured in the common stack and SO2 mass emissions measured in the ducts of the nonaffected units, not to be reported as an hourly average value less than zero; combine emissions for the Phase I and Phase II affected units for recordkeeping and compliance purposes; calculate and report SO2 mass emissions from the Phase I and Phase II affected units, pursuant to an approach approved by the Administrator, such that these emissions are not underestimated; or * * * * * (D) Petition through the designated representative and provide information satisfactory to the Administrator on methods for apportioning SO2 mass emissions measured in the common stack to each of the units using the common stack and on reporting the SO2 mass emissions. The Administrator may approve such demonstrated substitute methods for apportioning and reporting SO2 mass emissions measured in a common stack whenever the demonstration ensures that there is a complete and accurate accounting of all emissions regulated under this part and, in particular, that the emissions from any affected unit are not underestimated. * * * * * (d) * * * (2) Install, certify, operate, and maintain an SO2 continuous emission monitoring system and flow monitoring system in each stack. Determine SO2 mass emissions from each affected unit as the sum of the SO2 mass emissions recorded for each stack. Notwithstanding the prior sentence, if another unit also exhausts flue gases to one or more of the stacks, the owner or operator shall also comply with the applicable common stack requirements of this section to determine and record SO2 mass emissions from the units using that stack and shall calculate and report SO2 mass emissions from the affected units and stacks, pursuant to an approach approved by the Administrator, such that these emissions are not underestimated. (e) * * * (1) The owner or operator of an affected unit using a common stack, bypass stack, or multiple stack with a diluent monitor and a flow monitor on each stack may choose to install monitors to determine the heat input for the affected unit, wherever flow and diluent monitor measurements are used to determine the heat input, using the procedures specified in paragraphs (a) through (d) of this section, except that the terms ``SO2 mass emissions'' and ``emissions'' are replaced with the term ``heat input'' and the phrase ``SO2 continuous emission monitoring system and flow monitoring system'' is replaced with the phrase ``a diluent monitor and a flow monitor.'' The applicable equation in appendix F to this part shall be used to calculate the heat input from the hourly flow rate, diluent monitor measurements, and (if the equation in appendix F requires a correction for the stack gas moisture content) hourly moisture measurements. Notwithstanding the options for combining heat input in paragraphs (a)(1)(ii), (a)(2)(ii), (b)(1)(ii), and (b)(2)(ii) of this section, the owner or operator of an affected unit with a diluent monitor and a flow monitor installed on a common stack to determine the combined heat input at the common stack shall also determine and report heat input to each individual unit. * * * * * (3) * * * The heat input may be apportioned either by using the ratio of load (in MWe-hr) for each individual unit to the total load for all units utilizing the common stack or by using the ratio of steam flow (in 1000 lb) for each individual unit to the total steam flow for all units utilizing the common stack. The heat input should be apportioned according to the procedures in appendix F to this part. (4) Notwithstanding paragraph (e)(1) of this section, any affected unit that is using the procedures in this part to meet the monitoring and reporting requirements of a State or federal NOX mass emission reduction program must also meet the requirements for monitoring heat input in Secs. 75.71 and 75.72. 17. Section 75.17 is amended by adding introductory text before paragraph (a) and by revising paragraph (a)(2)(i)(C) to read as follows: Sec. 75.17 Specific provisions for monitoring emissions from common, by-pass, and multiple stacks for NOX emission rate. Notwithstanding the provisions of paragraphs (a), (b), and (c) of this section, the owner or operator of an affected unit that is using the procedures in this part to meet the monitoring and reporting requirements of a State or federal NOX mass emission reduction program must also meet the provisions for monitoring NOX emission rate in Secs. 75.71 and 75.72. (a) * * * (2) * * * (i) * * * (C) Each unit's compliance with the applicable NOX emission limit will be determined by a method satisfactory to [[Page 28123]] the Administrator for apportioning to each of the units the combined NOX emission rate (in lb/mmBtu) measured in the common stack and for reporting the NOX emission rate, as provided in a petition submitted by the designated representative. The Administrator may approve such demonstrated substitute methods for apportioning and reporting NOX emission rate measured in a common stack whenever the demonstration ensures that there is a complete and accurate estimation of all emissions regulated under this part and, in particular, that the emissions from any unit with a NOX emission limitation are not underestimated. * * * * * 18. Section 75.19 is added to subpart B to read as follows: Sec. 75.19 Optional SO2 , NOX, and CO2 emissions calculation for low mass emissions units. (a) Applicability. (1) Consistent with the requirements of paragraphs (a)(2) and (b) of this section, the low mass emissions excepted methodology in paragraph (c) of this section may be used in lieu of continuous emission monitoring systems or, if applicable, in lieu of excepted methods under appendix D or E to this part, for the purpose of determining hourly heat input, hourly NOX emission rate, and hourly NOX, SO2 , and CO2 mass emissions from a low mass emissions unit. A low mass emissions unit is a gas-fired or oil-fired unit that burns only natural gas and/or fuel oil and that: (i) Emits no more than 25 tons of SO2 annually and no more than 25 tons of NOX annually; and (ii) Has calculated emissions of no more than 25 tons of SO2 annually and no more than 25 tons of NOX annually based on the maximum rated hourly heat input, the actual operating time for each fuel burned, and the low mass emissions excepted methodology, calculations, and values in paragraph (c) of this section. (2) A unit may initially qualify as a low mass emissions unit only under the following circumstances: (i) The designated representative provides historical actual and calculated emissions data from the previous three calendar years immediately prior to the submission of an application to use the low mass emissions excepted methodology, and the data demonstrates to the satisfaction of the Administrator that the unit meets the criteria in paragraphs (a)(1)(i) and (ii) of this section; or (ii) If a unit does not have the historical data required in paragraph (a)(2)(i) of this section for any one or more of the previous three calendar years, the designated representative submits: (A) Any historical annual emissions and operating data, as required in paragraphs (a)(1)(i) and (a)(1)(ii) of this section, beginning with the unit's first calendar year of commercial operation, and the data demonstrates to the satisfaction of the Administrator that the unit meets the criteria in paragraphs (a)(1)(i) and (a)(1)(ii) of this section; and (B) A demonstration satisfactory to the Administrator that the unit will continue to qualify as a low mass emissions unit under the requirements of this paragraph (a). The demonstration shall include any historical emissions and operating data for less than a calendar year for the unit and projected emissions information for the unit, as determined using projected operating hours and fuel usage, and the low mass emissions excepted methodology, calculations, and values in paragraph (c) of this section. (b) Disqualification. If a unit that initially qualifies as a low mass emissions units under this section changes the fuel that is burned in the unit such that a fuel other than natural gas or fuel oil is combusted in the unit, the unit is disqualified from using the low mass emissions excepted methodology as of the first hour that the new fuel is combusted in the unit. In addition, if a unit that initially qualifies as a low mass emissions unit under this section emits more than 25 tons of SO2 or 25 tons of NOX in any calendar year or has calculated emissions greater than 25 tons of SO2 or 25 tons of NOX in any calendar year, as determined using the low mass emission equations in paragraph (c) of this section, the owner or operator of the unit shall have two quarters from the end of the quarter in which the exceedance occurs to install, certify, and report SO2 , NOX, and CO2 from monitoring systems that meet the requirements of Secs. 75.11, 75.12, and 75.13, respectively. The unit shall be disqualified as a low mass emissions unit as of the end of the second quarter following the quarter in which either of the 25 ton limits was exceeded. A unit that has been disqualified from using the low mass emissions excepted methodology may subsequently qualify again as a low mass emissions unit under paragraph (a)(2) of this section, provided that if such unit qualified under paragraph (a)(2)(ii) of this section, the unit may subsequently qualify again if the unit meets the requirements of paragraph (a)(2)(i) of this section. (c) Low mass emissions excepted methodology, calculations, and values.--(1) Operating time. (i) Report an hourly record if the unit operated for any portion of the hour or if records are missing, as to whether or not the unit operated for any portion of that hour. (ii) Quarterly operating time (hr) is equal to the sum of all of the reported operating hours in the quarter, such that any hour in which the unit combusted fuel for any portion of the hour is considered a full hour. (iii) Year-to-date cumulative operating time (hr) is equal to the sum of all of the reported operating hours in the year to date, such that any hour in which the unit combusted fuel for any portion of the hour is considered a full hour. (2) Heat input. (i) Hourly heat input (mmBtu) is equal to the maximum rated hourly heat input, as defined in Sec. 72.2 of this chapter. However, the owner or operator of an affected unit may petition the Administrator under Sec. 75.66 for a lower value for maximum rated hourly heat input than that defined in Sec. 72.2 of this chapter. The Administrator may approve such lower value if the owner or operator demonstrates that either the maximum hourly heat input specified by the manufacturer or the highest observed hourly heat input, or both, are not representative of the unit's current capabilities because modifications have been made to the unit, limiting its capacity permanently. (ii) Calculate the quarterly total heat input (mmBtu) using Equation 7a as follows: HIqtr = Tqtr x HIhr (Eq. 7a) where: Tqtr = Actual number of operating hours in the quarter, in hr. HIhr = Hourly heat input under paragraph (c)(2)(i) of this section, in mmBtu. (iii) Calculate the year-to-date cumulative heat input (mmBtu) as the sum of all of the hourly heat input values in the year to date. (3) SO2 . (i) Calculate the hourly total SO2 mass emissions (lbs) using Equation 7b and the appropriate fuel-based SO2 emission factor from Table 1a for the fuel being burned in that hour. If more than one fuel is burned in the hour, use the highest emission factor for all of the fuels burned in the hour. If records are missing as to which fuel was burned in the hour, use the highest emission factor for all of the fuels capable of being burned in that unit. Table 1a.--SO2 Emission Factors (lb/mmBtu) for Various Fuel Types ------------------------------------------------------------------------ Fuel type SO 2 Emission factors ------------------------------------------------------------------------ Pipeline Natural Gas...................... 0.0006 lb/mmBtu. [[Page 28124]] Natural Gas............................... 0.06 lb/mmBtu. Residual Oil.............................. 2.1 lb/mmBtu. Diesel Fuel............................... 0.5 lb/mmBtu. ------------------------------------------------------------------------ W SO2 = EFSO2 x HIhr (Eq. 7b) Where: WSO2 = SO2 mass emissions, in lbs. EFSO 2 = Fuel-based SO2 emission factor from Table 1a of this section, in lb/mmBtu. HIhr = Hourly heat input under paragraph (c)(2)(i) of this section, in mmBtu. (ii) Calculate the quarterly total SO2 mass emissions (tons) by summing all of the hourly SO2 mass emissions under paragraph (c)(3)(i) of this section in the quarter and dividing by 2000 lb/ton. (iii) Calculate the year-to-date cumulative SO2 mass emissions (tons) by summing all of the SO2 mass emissions under paragraph (c)(3)(i) of this section in the year to date. (4) NOX. (i) Determine the hourly NOX emission rate (lb/mmBtu) by using the appropriate fuel and boiler type default NOX emission rate in Table 1b for the fuel being burned in that hour. If more than one fuel is burned in the hour, use the highest emission rate for all of the fuels burned in the hour. If records are missing as to which fuel was burned in the hour, use the highest emission factor for all of the fuels capable of being burned in that unit. Table 1b.--NOX Emission Rates (lb/mmBtu) for Various Boiler/Fuel Types ------------------------------------------------------------------------ NO X Boiler type Fuel type Emission rate ------------------------------------------------------------------------ Tangentially fired................. Oil................... 0.366 Tangentially fired................. Gas................... 0.290 Dry Bottom Wall fired.............. Oil................... 0.490 Dry Bottom Wall fired.............. Gas................... 0.400 Combustion Turbine................. Oil................... 0.258 Combustion Turbine................. Gas................... 0.172 Combined Cycle..................... Oil................... 0.273 Combined Cycle..................... Gas................... 0.273 ------------------------------------------------------------------------ (ii) Calculate the hourly total NOX mass emissions (lbs) as the product of the NOX emission rate (lb/mmBtu) and hourly heat input (mmBtu), using Equation 7c as follows: W NOX = EFNOX x HIhr (Eq. 7c) where: WNOX = NOX mass emissions, in lbs. EFNOX = Boiler-type and fuel-type NOX emission factor from Table 1b of this section, in lb/mmBtu. HIhr = Hourly heat input under paragraph (c)(2)(i) of this section, in mmBtu. (iii) Calculate the quarterly average NOX emission rate (lb/mmBtu) by summing all of the hourly NOX emission rates for the quarter and dividing the total by the number of reported operating hours under paragraph (c)(1)(i) of this section in the quarter. (iv) Calculate the quarterly total NOX mass emissions (tons) by summing all of the hourly NOX mass emissions under paragraph (c)(4)(ii) of this section in the quarter and dividing the total by 2000 lb/ton. (v) Calculate the year-to-date cumulative average NOX emission rate (lb/mmBtu) by summing all of the hourly NOX emission rates for all of the hours in the year to date and dividing the total by the number of reported operating hours under paragraph (c)(1)(i) of this section in the year to date. (vi) Calculate the year-to-date cumulative NOX mass emissions total (tons) by summing all of the hourly NOX mass emissions under paragraph (c)(4)(ii) of this section in the year to date. (5) CO2 . (i) Calculate the hourly total CO2 mass emissions (tons) using Equation 7d and the appropriate fuel-based CO2 emission factor from Table 1c for the fuel being burned in that hour. If more than one fuel is burned in the hour, use the highest emission factor for all of the fuels burned in the hour. If records are missing as to which fuel was burned in the hour, use the highest emission factor for all of the fuels capable of being burned in that unit. Table 1c.--CO2 Emission Factors (ton/mmBtu) for Gas and Oil ------------------------------------------------------------------------ Fuel type CO 2 emission factors ------------------------------------------------------------------------ Natural Gas............................... 0.059 ton/mmBtu. Oil....................................... 0.081 ton/mmBtu. ------------------------------------------------------------------------ W CO2 =EFCO2 x HIhr (Eq. 7d) Where: WCO2 = CO2 mass emissions, in tons. EFCO2 = Fuel-based CO2 emission factor from Table 1c, in ton/mmBtu. HIhr = Hourly heat input under paragraph (c)(2)(i) of this section, in mmBtu. (ii) Calculate the quarterly total CO2 mass emissions (tons) by summing all of the hourly CO2 mass emissions under paragraph (c)(5)(i) of this section in the quarter. (iii) Calculate the year-to-date cumulative CO2 mass emissions (tons) by summing all of the hourly CO2 mass emissions under paragraph (c)(5)(i) of this section in the year to date. (d) The quality control and quality assurance requirements in Sec. 75.21 are not required for a low mass emissions unit for which the optional low mass emissions excepted methodology in paragraph (c) of this section is being used in lieu of a continuous emission monitoring system or an excepted monitoring system under appendix D or E to this part. Subpart C--[Amended] 19. Section 75.20 is amended by: a. Revising the title of the section; b. Revising the titles of paragraphs (a)(3), (a)(4), (c), (d), (g), (g)(1), (g)(2), (g)(4), and (g)(5); c. Revising paragraphs (a) introductory text, (a)(1), (a)(3), (a)(4) introductory text, (a)(4)(i), (a)(4)(ii), (a)(4)(iii), (a)(5)(i), (b), (c) introductory text, (c)(1)(iii), (d)(1), (d)(2), (g) introductory text, (g)(1) introductory text, (g)(1)(i), (g)(2), (g)(4), and (g)(5); d. Removing existing paragraph (c)(3); e. Revising and redesignating existing paragraphs (c)(4), (c)(5), (c)(6), (c)(7), and (c)(8) as paragraphs (c)(3), (c)(4), (c)(8), (c)(9), and (c)(10), respectively; and revising newly designated paragraphs (c)(4) introductory text, (c)(8) introductory text, (c)(8)(i), [[Page 28125]] (c)(9)(ii), and (c)(10) introductory text; and f. Adding new paragraphs (c)(5), (c)(6), (c)(7), (g)(6), (g)(7), (h), and (i), to read as follows: Sec. 75.20 Initial certification and recertification procedures. (a) Initial certification approval process. The owner or operator shall ensure that each continuous emission or opacity monitoring system required by this part, which includes the automated data acquisition and handling system, and, where applicable, the CO2 continuous emission monitoring system, meets the initial certification requirements of this section and shall ensure that all applicable initial certification tests under paragraph (c) of this section are completed by the deadlines specified in Sec. 75.4 and prior to use in the Acid Rain Program. In addition, whenever the owner or operator installs a continuous emission or opacity monitoring system in order to meet the requirements of Secs. 75.13 through 75.18, where no continuous emission or opacity monitoring system was previously installed, initial certification is required. (1) Notification of initial certification test dates. The owner or operator or designated representative shall submit a written notice of the dates of initial certification testing at the unit as specified in Sec. 75.61(a)(1). * * * * * (3) Provisional approval of certification (or recertification) applications. Upon the successful completion of the required certification (or recertification) procedures of this section for each continuous emission or opacity monitoring system or component thereof, each continuous emission or opacity monitoring system or component thereof shall be deemed provisionally certified (or recertified) for use under the Acid Rain Program for a period not to exceed 120 days following receipt by the Administrator of the complete certification (or recertification) application under paragraph (a)(4) of this section, provided that no continuous emission or opacity monitor systems for a combustion source seeking to enter the Opt-in Program in accordance with part 74 of this chapter shall be deemed provisionally certified (or recertified) for use under the Acid Rain Program. Data measured and recorded by a provisionally certified (or recertified) continuous emission or opacity monitoring system or component thereof, in accordance with the requirements of appendix B to this part, will be considered valid quality-assured data (retroactive to the date and time of provisional certification or recertification)), provided that the Administrator does not invalidate the provisional certification (or recertification) by issuing a notice of disapproval within 120 days of receipt by the Administrator of the complete certification (or recertification) application. Note that if the data validation procedures of paragraph (b)(3) of this section are applied to the initial certification (or recertification) of a continuous emissions monitoring system, it is possible for data recorded by the CEMS during the certification (or recertification) test period to be quality assured retrospectively, upon completion of all of the certification (or recertification) tests. Therefore, in certain instances, the date and time of provisional certification (or recertification) of the CEMS may be earlier than the date and time of completion of the required certification (or recertification) tests. (4) Certification (or recertification) application formal approval process. The Administrator will issue a notice of approval or disapproval of the certification (or recertification) application to the owner or operator within 120 days of receipt of the complete certification (or recertification) application. In the event the Administrator does not issue such a written notice within 120 days of receipt, each continuous emission or opacity monitoring system which meets the performance requirements of this part and is included in the certification (or recertification) application will be deemed certified (or recertified) for use under the Acid Rain Program. (i) Approval notice. If the certification (or recertification) application is complete and shows that each continuous emission or opacity monitoring system meets the performance requirements of this part, then the Administrator will issue a written notice of approval of the certification (or recertification) application within 120 days of receipt. (ii) Incomplete application notice. A certification (or recertification) application will be considered complete when all of the applicable information required to be submitted in Sec. 75.63 has been received by the Administrator, the EPA Regional Office, and the appropriate State and/or local air pollution control agency. If the certification (or recertification) application is not complete, then the Administrator will issue a written notice of incompleteness that provides a reasonable timeframe for the designated representative to submit the additional information required to complete the certification (or recertification) application. If the designated representative has not complied with the notice of incompleteness by a specified due date, then the Administrator may issue a notice of disapproval specified under paragraph (a)(4)(iii) of this section. The 120-day review period shall not begin prior to receipt of a complete application. (iii) Disapproval notice. If the certification (or recertification) application shows that any continuous emission or opacity monitoring system or component thereof does not meet the performance requirements of this part, or if the certification (or recertification) application is incomplete and the requirement for disapproval under paragraph (a)(4)(ii) of this section has been met, the Administrator shall issue a written notice of disapproval of the certification (or recertification) application within 120 days of receipt. By issuing the notice of disapproval, the provisional certification (or recertification) is invalidated by the Administrator, and the data measured and recorded by each uncertified continuous emission or opacity monitoring system or component thereof shall not be considered valid quality-assured data beginning with the following time: from the hour of the probationary calibration error test that began the initial certification (or recertification) test period, if the data validation procedures of paragraph (b)(3) of this section were used to retrospectively validate data; or from the date and time of completion of the invalid certification tests until the date and time that the owner or operator completes subsequently approved initial certification tests, if the data validation procedures of paragraph (b)(3) of this section were not used. The owner or operator shall follow the procedures for loss of initial certification in paragraph (a)(5) of this section for each continuous emission or opacity monitoring system or component thereof which is disapproved for initial certification. For each disapproved recertification, the owner or operator shall follow the procedures of paragraph (b)(5) of this section. * * * * * (5) * * * (i) Until such time, date, and hour as the continuous emission monitoring system or component thereof can be adjusted, repaired, or replaced and certification tests successfully completed, the owner or operator shall substitute the following values, as applicable, for each hour of unit operation during the period of invalid [[Page 28126]] data specified in paragraph (a)(4)(iii) of this section or in Sec. 75.21: the maximum potential concentration of SO2 as defined in section 2.1.1.1 of appendix A to this part to report SO2 concentration; the maximum potential NOX emission rate, as defined in Sec. 72.2 of this chapter to report NOX emissions; the maximum potential flow rate, as defined in section 2.1.4.1 of appendix A to this part to report volumetric flow; or the maximum potential concentration of CO2 , as defined in section 2.1.3.1 of appendix A to this part to report CO2 concentration data; and * * * * * (b) Recertification approval process. Whenever the owner or operator makes a replacement, modification, or change in a certified continuous emission monitoring system or continuous opacity monitoring system that is determined by the Administrator to significantly affect the ability of the system to accurately measure or record the SO2 or CO2 concentration, stack gas volumetric flow rate, NOX emission rate, or opacity, or to meet the requirements of Sec. 75.21 or appendix B to this part, the owner or operator shall recertify the continuous emission monitoring system or continuous opacity monitoring system, according to the procedures in this paragraph. Furthermore, whenever the owner or operator makes a replacement, modification, or change to the flue gas handling system or the unit operation that is determined by the Administrator to significantly change the flow or concentration profile, the owner or operator shall recertify the monitoring system according to the procedures in this paragraph. Examples of changes which require recertification include: replacement of the analyzer; change in location or orientation of the sampling probe or site; changing of flow rate monitor polynomial coefficients; and complete replacement of an existing continuous emission monitoring system or continuous opacity monitoring system. The owner or operator shall recertify a continuous opacity monitoring system whenever the monitor path length changes or as required by an applicable State or local regulation or permit. Any change to a stack flow rate or gas monitoring system for which the Administrator determines that a RATA is not necessary shall not be considered a recertification event. In such cases, any other tests that the Administrator determines to be necessary (linearity checks, calibration error tests, DAHS verifications, etc.) shall be performed as diagnostic tests, rather than recertification tests. The data validation procedures in paragraph (b)(3) of this section shall be applied to linearity checks, 7-day calibration error tests, and cycle time tests when these are required as diagnostic tests. When the data validation procedures of paragraph (b)(3) of this section are applied in this manner, replace the word ``recertification'' with the word ``diagnostic.'' (1) Tests required. For recertification testing after changing the flow rate monitor polynomial coefficients, the owner or operator shall complete a 3-level RATA. For all other recertification testing, the owner or operator shall complete all initial certification tests in paragraph (c) of this section that are applicable to the monitoring system, except as otherwise approved by the Administrator. (2) Notification of recertification test dates. The owner, operator, or designated representative shall submit notice of testing dates for recertification under this paragraph as specified in Sec. 75.61(a)(1)(ii), unless all of the tests in paragraph (c) of this section are required for recertification, in which case the owner or operator shall provide notice in accordance with the notice provisions for initial certification testing in Sec. 75.61(a)(1)(i). (3) Recertification test period requirements and data validation. (i) In the period extending from the hour of the replacement, modification or change made to a monitoring system that triggers the need to perform recertification test(s) of the CEMS to the hour of successful completion of a probationary calibration error test (according to paragraph (b)(3)(ii) of this section) following the replacement, modification, or change to the CEMS, the owner or operator shall either substitute for missing data, according to the standard missing data procedures in Secs. 75.33 through 75.37, or report emission data using a reference method or another monitoring system that has been certified or approved for use under this part. (ii) Once the modification or change to the CEMS has been completed and all of the associated repairs, component replacements, adjustments, linearization, and reprogramming of the CEMS have been completed, a probationary calibration error test is required to establish the beginning point of the recertification test period. In this instance, the first successful calibration error test of the monitoring system following completion of all necessary repairs, component replacements, adjustments, reprogramming, and any preliminary tests (e.g., trial RATA runs or a challenge of the monitor with calibration gases other than those used to perform the daily calibration error test) shall be the probationary calibration error test. The probationary calibration error test must be passed before any of the required recertification tests are commenced. (iii) Beginning with the hour of commencement of a recertification test period, emission data recorded by the CEMS are considered to be conditionally valid, contingent upon the results of the subsequent recertification tests. (iv) Each required recertification test shall be completed no later than the following number of unit operating hours after the probationary calibration error test that initiates the test period: (A) For a linearity test and/or cycle time test, 168 consecutive unit operating hours; (B) For a RATA (whether normal-load or multiple-load), 720 consecutive unit operating hours; and (C) For a 7-day calibration error test, 21 consecutive unit operating days. (v) All recertification tests shall be performed hands-off, as follows. No adjustments to the calibration of the CEMS, other than the adjustments described in section 2.1.3 of appendix B to this part, are permitted prior to or during the recertification test period. Routine daily calibration error tests shall be performed throughout the recertification test period, in accordance with section 2.1.1 of appendix B to this part. The additional calibration error test requirements in section 2.1.3 of appendix B to this part shall also apply during the recertification test period. (vi) If all of the required recertification tests and required daily calibration error tests are successfully completed in succession with no failures, and if each recertification test is completed within the time period specified in paragraph (b)(3)(iv)(A), (B), or (C) of this section, then all of the conditionally valid emission data recorded by the CEMS shall be considered quality assured, from the hour of commencement of the recertification test period until the hour of completion of the required test(s). (vii) If a required recertification test is failed or aborted due to a problem with the CEMS, or if a calibration error test is failed during a recertification test period, data validation shall be done as follows: (A) If any required recertification test is failed, it shall be repeated. If any recertification test other than a 7-day calibration error test is failed or aborted due to a problem with the CEMS, the original recertification test period is ended, and a new recertification test period must be commenced with a [[Page 28127]] probationary calibration error test. The tests that are required in this new recertification test period will include any tests that were required for the initial recertification event which were not successfully completed and any recertification or diagnostic tests that are required as a result of changes made to the monitoring system to correct the problems that caused the failure of the recertification test. The new recertification test sequence shall not be commenced until all necessary maintenance activities, adjustments, linearizations, and reprogramming of the CEMS have been completed; (B) If a linearity test, RATA, or cycle time test is failed or aborted due to a problem with the CEMS, all conditionally valid emission data recorded by the CEMS are invalidated, from the hour of commencement of the recertification test period to the hour in which the test is failed or aborted. Data from the CEMS remain invalid until the hour in which a new recertification test period is commenced, following corrective action, and a probationary calibration error test is passed, at which time the conditionally valid status of emission data from the CEMS begins; (C) If a 7-day calibration error test is failed within the recertification test period, previously-recorded conditionally valid emission data from the CEMS are not invalidated, provided that the calibration error on the day of the failed 7-day calibration error test does not exceed twice the performance specification in section 3 of appendix A to this part; and (D) If a calibration error test is failed (i.e., the results of the test exceed twice the performance specification in section 3 of appendix A to this part) during a recertification test period, the CEMS is out-of-control as of the hour in which the calibration error test is failed. Emission data from the CEMS shall be invalidated prospectively from the hour of the failed calibration error test until the hour of completion of a subsequent successful calibration error test following corrective action, at which time the conditionally valid status of data from the monitoring system resumes. Failure to perform a required daily calibration error test during a recertification test period shall also cause data from the CEMS to be invalidated prospectively, from the hour in which the calibration error test was due until the hour of completion of a subsequent successful calibration error test. Previously-passed recertification tests in the sequence and previously- recorded conditionally valid data shall not be affected by a late calibration error test. Whenever a calibration error test is failed or missed during a recertification test period, no further recertification tests shall be performed until the required subsequent calibration error has been passed, re-establishing the conditionally valid status of data from the monitoring system. (viii) If any required recertification test is not completed within its allotted time period, data validation shall be done as follows. For a late linearity test, RATA, or cycle time test that is passed on the first attempt, data from the monitoring system shall be invalidated from the hour of expiration of the recertification test period until the hour of completion of the late test. For a late 7-day calibration error test, whether or not it is passed on the first attempt, data from the monitoring system shall also be invalidated from the hour of expiration of the recertification test period until the hour of completion of the late test. For a late linearity test, RATA, or cycle time test that is failed on the first attempt or aborted on the first attempt due to a problem with the monitor, all conditionally valid data from the monitoring system shall be considered invalid back to the hour of the first probationary calibration error test which initiated the recertification test period. Data from the monitoring system shall remain invalid until the hour of successful completion of the late recertification test and any additional recertification or diagnostic tests that are required as a result of changes made to the monitoring system to correct problems that caused failure of the late recertification test. (ix) If any required recertification test of a monitoring system has not been completed by the end of a calendar quarter and if data contained in the quarterly report is conditionally valid pending the results of test(s) to be completed in a subsequent quarter, the owner or operator shall indicate this by means of a suitable conditional data flag in the electronic quarterly report for that quarter. The owner or operator shall resubmit the report for that quarter if the required recertification test is subsequently failed. In the resubmitted report, the owner or operator shall use the appropriate missing data routine in Sec. 75.31 or Sec. 75.33 to replace with substitute data each hour of conditionally valid data that was invalidated by the failed recertification test. In addition, if the owner or operator submits any conditionally valid data (as defined in Sec. 72.2 of this chapter) in any of the four quarterly reports for a given year, the owner or operator shall indicate the status of the conditionally valid data (i.e., resolved or unresolved) in the annual compliance certification report required under Sec. 72.90 of this chapter for that year. Alternatively, if any required recertification test is not completed by the end of a particular calendar quarter but is completed no later than 30 days after the end of that quarter (i.e., prior to the deadline for submitting the quarterly report under Sec. 75.64), the test data and results may be submitted with the earlier quarterly report even though the test date(s) are from the next calendar quarter. In such instances, if the recertification test(s) are passed in accordance with the provisions of paragraph (b)(3) of this section, conditionally valid data may be reported as quality-assured, in lieu of reporting a conditional data flag. If the recertification test(s) is failed and if conditionally valid data are replaced, as appropriate, with substitute data, then neither the reporting of a conditional data flag nor resubmission is required. (x) If the replacement, modification, or change requiring recertification of the CEMS is such that the data collected by the prior certified monitoring system are no longer representative, such as after a change to the flue gas handling system or unit operation that requires changing the span value to be consistent with section 2.1 of appendix A to this part, the owner or operator shall substitute for missing data as follows, in the period extending from the hour of commencement of the replacement, modification, or change requiring recertification of the CEMS to the hour of commencement of the recertification test period: (A) For a change that results in a significantly higher concentration or flow rate, substitute maximum potential values according to the procedures in paragraph (a)(5) of this section; or (B) For a change that results in a significantly lower concentration or flow rate, substitute data using the standard missing data procedures. (C) The owner or operator shall then use the initial missing data procedures in Sec. 75.31, beginning with the first hour of quality assured data obtained with the recertified monitoring system, unless otherwise provided by Sec. 75.34 for units with add-on emission controls. (4) Recertification application. The designated representative shall apply for recertification of each continuous emission or opacity monitoring system used under the Acid Rain Program. The owner or operator shall submit the recertification application in accordance with Sec. 75.60, and each complete recertification application shall include the information specified in Sec. 75.63. (5) Approval or disapproval of request for recertification. The procedures for [[Page 28128]] provisional certification in paragraph (a)(3) of this section shall apply to recertification applications. The Administrator will issue a written notice of approval or disapproval according to the procedures in paragraph (a)(4) of this section. In the event that a recertification application is disapproved, data from the monitoring system are invalidated and the applicable missing data procedures in Sec. 75.31 or Sec. 75.33 shall be used from the date and hour of receipt of such notice back to the hour of the probationary calibration error test that began the recertification test period. Data from the monitoring system remain invalid until a subsequent probationary calibration error test is passed, beginning a new recertification test period. The owner or operator shall repeat all recertification tests or other requirements, as indicated in the Administrator's notice of disapproval, no later than 30 unit operating days after the date of issuance of the notice of disapproval. The designated representative shall submit a notification of the recertification retest dates, as specified in Sec. 75.61(a)(1)(ii), and shall submit a new recertification application according to the procedures in paragraph (b)(4) of this section. (c) Initial certification and recertification procedures. Prior to the deadline in Sec. 75.4, the owner or operator shall conduct initial certification tests and in accordance with Sec. 75.63, the designated representative shall submit an application to demonstrate that the continuous emission or opacity monitoring system and components thereof meet the specifications in appendix A to this part. The owner or operator shall compare reference method values with output from the automated data acquisition and handling system that is part of the continuous emission monitoring system being tested. Except as specified in paragraphs (b)(1), (d), and (e) of this section, the owner or operator shall perform the following tests for initial certification or recertification of continuous emission or opacity monitoring systems or components according to the requirements of appendix A to this part: (1) * * * (iii) A relative accuracy test audit. For the NOX- diluent system, the RATA shall be done on a system basis, in units of lb/mmBtu. * * * * * (3) The initial certification test data from an O2 -or a CO2 -diluent gas monitor certified for use in a NOX continuous emission monitoring system may be submitted to meet the requirements of paragraph (c)(4) of this section. Also, for a diluent monitor that is used both as a CO2 monitoring system and to determine heat input, only one set of diluent monitor certification data need be submitted (under the component and system identification numbers of the CO2 monitoring system). (4) For each CO2 pollutant concentration monitor, each O2 monitor which is part of a CO2 continuous emission monitoring system, each diluent monitor used to monitor heat input and each SO2 -diluent continuous emission monitoring system: * * * * * (5) For each continuous moisture monitoring system consisting of wet-and dry-basis O2 analyzers: (i) A 7-day calibration error test of each O2 analyzer; (ii) A cycle time test of each O2 analyzer; (iii) A linearity test of each O2 analyzer; and (iv) A RATA, directly comparing the percent moisture measured by the monitor to a reference method. (6) For each continuous moisture sensor: (i) A 7-day calibration error test; and (ii) A RATA, directly comparing the percent moisture measured by the monitor sensor to a reference method. (7) For a continuous moisture monitoring system consisting of a temperature sensor and a data acquisition and handling system (DAHS) software component programmed with a moisture lookup table: (i) A demonstration that the correct moisture value for each hour is being taken from the moisture lookup tables and applied to the emission calculations. At a minimum, the demonstration shall be made at three different temperatures covering the normal range of stack temperatures. (ii) [Reserved] (8) The owner or operator shall ensure that initial certification or recertification of a continuous opacity monitor for use under the Acid Rain Program is conducted according to one of the following procedures: (i) Performance of the tests for initial certification or recertification, according to the requirements of Performance Specification 1 in appendix B to part 60 of this chapter; or * * * * * (9) * * * (ii) Proper computation and application of the missing data substitution procedures in subpart D of this part and the bias adjustment factors in section 7 of appendix A to this part. (10) The owner or operator shall provide, or cause to be provided, adequate facilities for initial certification or recertification testing that include: * * * * * (d) Initial certification and recertification and quality assurance procedures for optional backup continuous emission monitoring systems. (1) Redundant backups. The owner or operator of an optional redundant backup continuous emission monitoring system shall comply with all the requirements for initial certification and recertification according to the procedures specified in paragraphs (a), (b), and (c) of this section. The owner or operator shall operate the redundant backup continuous emission monitoring system during all periods of unit operation, except for periods of calibration, quality assurance, maintenance, or repair. The owner or operator shall perform upon the redundant backup continuous emission monitoring system all quality assurance and quality control procedures specified in appendix B to this part, except that the daily assessments in section 2.1 of appendix B to this part are optional for days on which the redundant backup monitoring system is not used to report emission data under this part. For any day on which a redundant backup monitoring system is used to report emission data, the system must meet all of the applicable daily assessment criteria in appendix B to this part. (2) Non-redundant backups. The owner or operator of an optional non-redundant backup continuous emission monitoring system shall comply with all of the following requirements for initial certification, quality assurance, recertification, and data reporting: (i) For a non-redundant backup gas monitoring system that has its own separate probe, sample interface, and analyzer or for a non- redundant backup flow monitor, all of the tests in paragraph (c) of this section are required for initial certification of the system, except for the 7-day calibration error test. (ii) For a non-redundant backup gas monitoring system consisting of one or more like-kind replacement analyzers that use the same probe and sample interface as a primary monitoring system, no initial certification of the non-redundant backup monitoring system is required. Note that a non-redundant backup analyzer, connected to the same probe and interface as a primary analyzer in order to satisfy the dual span requirements of section [[Page 28129]] 2.1.1.4 or 2.1.2.4 of appendix A to this part, shall be considered a like-kind, non-redundant backup analyzer. (iii) Each non-redundant backup monitoring system shall comply with the daily and quarterly quality assurance and quality control requirements in appendix B to this part for each day and quarter that the non-redundant backup monitoring system is used to report data, except that the requirements for when a linearity test must be performed are superseded by the requirements of this section. The owner or operator shall ensure that each non-redundant backup continuous emission monitoring system passes a linearity check (for pollutant concentration and diluent gas monitors) or a calibration error test (for flow monitors) prior to each use for recording and reporting emissions. For a non-redundant backup NOX-diluent or SO2 -diluent monitoring system consisting of a primary pollutant analyzer and a like-kind replacement diluent analyzer (or vice-versa), provided that the primary analyzer is operating and is not out-of-control with respect to any of its quality assurance requirements, only the like-kind replacement analyzer must pass a linearity check before the system is used for data reporting. When a non-redundant backup monitoring system is brought into service prior to conducting the linearity test, a probationary calibration error test (as described in paragraph (b)(3)(ii) of this section), which will begin a period of conditionally valid data, may be performed in order to allow the use of data retrospectively, as follows. Conditionally valid data from the CEMS are validated back to the hour of completion of the probationary calibration error test if the following conditions are met: if no adjustments are made to the monitor other than those specified in section 2.1.3 of appendix B to this part between the probationary calibration error test and the successful completion of the linearity test, and if the linearity test is passed within 168 unit operating hours of the probationary calibration error test. However, if the linearity test is either failed, aborted due to a problem with the CEMS, or not completed as required, then all of the conditionally valid data are invalidated back to the hour of the probationary calibration error test, and data from the CEMS remain invalid until the hour of completion of a successful linearity test. (iv) When data are reported from a non-redundant backup monitoring system, the appropriate bias adjustment factor (BAF) shall be determined as follows: (A) Apply the BAF from the most recent RATA of the non-redundant backup system (even if that RATA was done more than 12 months previously); or (B) If no RATA results are available for the non-redundant backup system (e.g., for a non-redundant backup gas monitoring system that uses the same probe and sample interface as the primary monitoring system), apply the primary monitoring system BAF. (v) A non-redundant backup system may not be used for reporting data from a particular affected unit or common stack for more than 720 hours in any one calendar year, unless the monitoring system passes a RATA at that same unit or stack. (vi) For each non-redundant backup gas monitoring system that has its own separate probe, sample interface, and analyzer and for each non-redundant backup flow monitor, no more than eight successive calendar quarters shall elapse following the quarter in which the last RATA of the monitoring system was done at a particular unit or stack, without performing a subsequent RATA. Otherwise, the monitoring system may not be used to report data from that unit or stack until the hour of completion of a successful RATA at that location. * * * * * (g) Initial certification and recertification procedures for excepted monitoring systems under appendices D and E. The owner or operator of a gas-fired unit, oil-fired unit, or diesel-fired unit using the optional protocol under appendix D or E to this part shall ensure that an excepted monitoring system under appendix D or E to this part meets the applicable general operating requirements of Sec. 75.10, the applicable requirements of appendices D and E to this part, and the initial certification or recertification requirements of this paragraph. (1) Initial certification and recertification testing. The owner or operator shall use the following procedures for initial certification and recertification of an excepted monitoring system under appendix D or E to this part. (i) When the optional SO2 mass emissions estimation procedure in appendix D to this part or the optional NOX emissions estimation protocol in appendix E to this part is used, the owner or operator shall provide data from a flowmeter accuracy test (or shall provide a statement of calibration if the flowmeter meets the accuracy standard by design) for each fuel flowmeter, according to the appropriate calibration procedures using one of the following standard methods: ASME MFC-3M-1989 with September 1990 Errata, ``Measurement of Fluid Flow in Pipes Using Orifice, Nozzle, and Venturi''; ASME MFC-4M- 1986 (Reaffirmed 1990) ``Measurement of Gas Flow by Turbine Meters''; ASME MFC-5M-1985, ``Measurement of Liquid Flow in Closed Conduits Using Transit-Time Ultrasonic Flowmeters''; ASME MFC-6M-1987 with June 1987 Errata, ``Measurement of Fluid Flow in Pipes Using Vortex Flow Meters''; ASME MFC-7M-1987 (Reaffirmed 1992), ``Measurement of Gas Flow by Means of Critical Flow Venturi Nozzles''; ASME MFC-9M-1988 with December 1989 Errata, ``Measurement of Liquid Flow in Closed Conduits by Weighing Method''; ISO 8316: 1987(E) ``Measurement of Liquid Flow in Closed Conduits--Method by Collection of the Liquid in a Volumetric Tank''; Section 8, Calibration from American Gas Association Transmission Measurement Committee Report No. 7: Measurement of Gas by Turbine Meters (1985 Edition); American Gas Association Report No. 3: Orifice Metering of Natural Gas and Other Related Hydrocarbon Fluids Part 1: General Equations and Uncertainty Guidelines (October 1990 Edition), Part 2: Specification and Installation Requirements (February 1991 Edition), and Part 3: Natural Gas Applications (August 1992 Edition), excluding the modified calculation procedures of Part 3; or American Petroleum Institute (API) Section 2, ``Conventional Pipe Provers,'' from Chapter 4 of the Manual of Petroleum Measurement Standards, October 1988 (Reaffirmed 1993), as required by appendices D and E to this part (all methods incorporated by reference under Sec. 75.6). * * * * * (2) Initial certification and recertification testing notification. The designated representative shall provide initial certification testing notification and periodic retesting notification for an excepted monitoring system under appendix E to this part as specified in Sec. 75.61. The designated representative shall submit recertification testing notification, as specified in Sec. 75.61, for quality assurance related NOX emission rate testing under section 2.3 of appendix E to this part for an excepted monitoring system under appendix E to this part. Initial certification testing notification or periodic retesting notification is not required for testing of a fuel flowmeter or for testing of an excepted monitoring system under appendix D to this part. * * * * * [[Page 28130]] (4) Initial certification or recertification application. The designated representative shall submit an initial certification or recertification application in accordance with Secs. 75.60 and 75.63. (5) Provisional approval of initial certification and recertification applications. Upon the successful completion of the required initial certification or recertification procedures for each excepted monitoring system under appendix D or E to this part, each excepted monitoring system under appendix D or E to this part shall be deemed provisionally certified for use under the Acid Rain Program during the period for the Administrator's review. The provisions for the initial certification or recertification application formal approval process in paragraph (a)(4) of this section shall apply, except that ``continuous emission or opacity monitoring system'' shall be replaced with ``excepted monitoring system'' and except that ``shall follow the procedures for loss of initial certification in paragraph (a)(5)'' or ``shall follow the procedures of paragraph (b)(5)'' shall be replaced with ``shall follow the procedures for loss of certification in paragraph (g)(7)''. Data measured and recorded by a provisionally certified excepted monitoring system under appendix D or E to this part will be considered quality assured data from the date and time of completion of the last initial certification or recertification test, provided that the Administrator does not revoke the provisional certification by issuing a notice of disapproval in accordance with the provisions in paragraph (a)(4) or (b)(5) of this section. (6) Recertification requirements. Recertification of an excepted monitoring system under appendix D or E to this part is required for any modification to the system or change in operation that could significantly affect the ability of the system to accurately account for emissions and for which the Administrator determines that an accuracy test of the fuel flowmeter or a retest under appendix E to this part to re-establish the NOX correlation curve is required. Examples of such changes or modifications include fuel flowmeter replacement, changes in unit configuration, or exceedance of operating parameters. (7) Procedures for loss of certification or recertification for excepted monitoring systems under appendices D and E to this part. In the event that a certification or recertification application is disapproved for an excepted monitoring system, data from the monitoring system are invalidated, and the applicable missing data procedures in section 2.4 of appendix D or section 2.5 of appendix E to this part shall be used from the date and hour of receipt of such notice back to the hour of the provisional certification. Data from the excepted monitoring system remain invalid until all required tests are repeated and the excepted monitoring system is again provisionally certified. The owner or operator shall repeat all certification or recertification tests or other requirements, as indicated in the Administrator's notice of disapproval, no later than 30 unit operating days after the date of issuance of the notice of disapproval. The designated representative shall submit a notification of the certification or recertification retest dates if required under paragraph (g)(2) of this section and shall submit a new certification or recertification application according to the procedures in paragraph (g)(4) of this section. (h) Initial certification and recertification procedures for low mass emission units using the excepted methodologies under Sec. 75.19. The owner or operator of a gas-fired, oil-fired, or diesel-fired unit using the optional low mass emissions excepted methodologies under Sec. 75.19 shall meet the applicable general operating requirements of Sec. 75.10, the applicable requirements of Sec. 75.19, and the applicable certification requirements of this paragraph (h). (1) Monitoring plan. The designated representative shall submit a monitoring plan in accordance with Secs. 75.53 and 75.62. (2) Certification application. The designated representative shall submit a certification application in accordance with Sec. 75.63(a)(1)(iii). (3) Approval of certification applications. Upon submission of the required certification application for approval to use the low mass emissions excepted methodology under Sec. 75.19, the excepted methodology shall be deemed provisionally certified for use under the Acid Rain Program during the period for the Administrator's review. The provisions for the certification application formal approval process in the introductory text of paragraph (a)(4) and in paragraphs (a)(4)(i), (ii), and (iv) of this section shall apply, except that ``continuous emission or opacity monitoring system'' shall be replaced with ``excepted methodology.'' (4) Disapproval of certification applications. If the Administrator determines that the certification application does not demonstrate that the unit meets the requirements of Secs. 75.19(a) and (b), the Administrator shall issue a written notice of disapproval of the certification application within 120 days of receipt. By issuing the notice of disapproval, the provisional certification is invalidated by the Administrator, and the data recorded under the excepted methodology shall not be considered valid. The owner or operator shall follow the procedures for loss of certification: (i) The owner or operator shall substitute the following values, as applicable, for each hour of unit operation during the period of invalid data specified in paragraph (a)(4)(iii) of this section or in Secs. 75.21(e) (introductory paragraph) and 75.21(e)(1): the maximum potential concentration of SO2 , as defined in section 2.1 of appendix A to this part to report SO2 concentration; the maximum potential NOX emission rate, as defined in Sec. 72.2 of this chapter to report NOX emissions; the maximum potential flow rate, as defined in section 2.1 of appendix A to this part to report volumetric flow; or the maximum CO2 concentration used to determine the maximum potential concentration of SO2 in section 2.1.1.1 of appendix A to this part to report CO2 concentration data until such time, date, and hour as a continuous emission monitoring system or excepted monitoring system, where applicable, is installed and provisionally certified; (ii) The designated representative shall submit a notification of certification test dates, as specified in Sec. 75.61(a)(1)(ii), and a new certification application according to the procedures in paragraph (a)(2) of this section; and (iii) The owner or operator shall install and provisionally certify continuous emission monitoring systems or excepted monitoring systems, where applicable, no later than 180 unit operating days after the date of issuance of the notice of disapproval. (i) Initial certification and recertification procedures for excepted flow monitoring systems under appendix I. The owner or operator of a gas-fired unit, oil-fired unit, or diesel-fired unit using the optional protocol under appendix I to this part shall ensure that an excepted flow monitoring system under appendix I to this part meets the applicable general operating requirements of Sec. 75.10, the applicable requirements of appendix I to this part, and the initial certification and recertification requirements of this paragraph. (1) Initial certification and recertification testing. The owner or operator shall, where applicable, use the [[Continued on page 28131]]
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)