Approval and Promulgation of Implementation Plans; Georgia: Approval of Revisions to the Georgia State Implementation Plan

Note: EPA no longer updates this information, but it may be useful as a reference or resource.


 

[Federal Register: July 11, 2002 (Volume 67, Number 133)]
[Proposed Rules]
[Page 45947]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr11jy02-20]

=======================================================================
-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[GA-50; GA-53; GA-56; GA-58; GA-59-200230(b); FRL-7244-6]
 
Approval and Promulgation of Implementation Plans; Georgia: 
Approval of Revisions to the Georgia State Implementation Plan

AGENCY: Environmental Protection Agency (EPA).
ACTION: Proposed rule.

-----------------------------------------------------------------------

SUMMARY: The EPA proposes to approve the State Implementation Plan 
(SIP) revisions submitted by the State of Georgia on December 6, 1999, 
March 21, 2000, January 4, 2001, August 21, 2001, and December 28, 
2001. These submittals contain revisions to Georgia's Rules for Air 
Quality Control and Rules for Enhanced Inspection and Maintenance. In 
the Final Rules section of this Federal Register, the EPA is approving 
the State's SIP revisions as a direct final rule without prior proposal 
because the Agency views these as a noncontroversial submittals and 
anticipates no adverse comments. A detailed rationale for the approval 
is set forth in the direct final rule. If no adverse comments are 
received in response to this action, no further activity is 
contemplated. If EPA receives adverse comments, the direct final rule 
will be withdrawn and all public comments received will be addressed in 
a subsequent final rule based on this proposed rule. The EPA will not 
institute a second comment period on this document. Any parties 
interested in commenting on this document should do so at this time.

DATES: Written comments must be received on or before August 12, 2002.

ADDRESSES: All comments should be addressed to: Scott M. Martin at the 
EPA, Region 4 Air Planning Branch, 61 Forsyth Street, SW, Atlanta, 
Georgia 30303-8960.
    Copies of the State submittal are available at the following 
addresses for inspection during normal business hours:
    Environmental Protection Agency, Region 4, Air Planning Branch, 61 
Forsyth Street, SW., Atlanta, Georgia 30303-8960.
    Air Protection Branch, Georgia Environmental Protection Division, 
Georgia Department of Natural Resources, 4244 International Parkway, 
Suite 120, Atlanta, Georgia 30354. Telephone (404) 363-7000.

FOR FURTHER INFORMATION CONTACT: Scott Martin at (404) 562-9036. E-
mail: martin.scott@epa.gov.

SUPPLEMENTARY INFORMATION: For additional information see the direct 
final rule which is published in the Rules section of this Federal 
Register.

    Dated: June 26, 2002.
Michael V. Peyton,
Acting Regional Administrator, Region 4.
[FR Doc. 02-17317 Filed 7-10-02; 8:45 am]