Tennessee Gas Pipeline Company and Distrigas of Massachusett
Tennessee Gas Pipeline Company and Distrigas of Massachusett
[Federal Register: May 23, 1996 (Volume 61, Number 101)] [Notices]
[Page 25863-25865]
>From the Federal Register Online via GPO Access [wais.access.gpo.gov]
DEPARTMENT OF ENERGY
[Docket Nos. CP96-164-000 and CP96-254-000]Tennessee Gas Pipeline Company and Distrigas of Massachusetts Corporation; Notice of Intent To Prepare an Environmental Assessment for the Proposed Tennessee Domac Projects; Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting
May 17, 1996.
The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the construction and operation of the facilities proposed in the Tennessee DOMAC Projects.\1\ This EA will be used by the Commission in its decision-making process to determine whether an environmental impact statement is necessary and whether to approve the projects.
\1\ Tennessee Gas Pipeline Company's and Distrigas of Massachusetts Corporation's applications were filed with the Commission under Section 7 of the Natural Gas Act and Part 157 of the Commission's regulations.
Summary of the Proposed Projects
Tennessee Gas Pipeline Company (Tennessee) wants to expand the capacity of its existing facilities to transport up to 90,000 dekatherms of natural gas per day on a firm basis for Distrigas of Massachusetts Corporation (DOMAC). Tennessee requests Commission authorization, in Docket No. CP96-164-000, to construct, operate, and abandon upon the termination of Tennessee's contractual obligations to DOMAC, the following facilities needed to transport those volumes:
[[Page 25864]]
DOMAC stated in its application that although the proposed vaporization facilities are necessary to deliver vaporized LNG into Tennessee's proposed pipeline, its need for additional vaporization capacity is independent of Tennessee's proposal. Therefore, DOMAC proposes to construct the vaporization facilities regardless of Tennessee's action. The Commission staff has elected to analyze the two proposals in the same EA because the Tennessee and DOMAC facilities would be physically connected and would be built within the same general timeframe.
The location of the proposed facilities is shown in appendix 1.\2\
\2\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies are available from the
Commission's Public Reference and Files Maintenance Branch, Room
3104, 888 First Street, NE, Room 2A, Washington, DC 20426, or call
(202) 208-1371. Copies of the appendices were sent to all those
receiving this notice in the mail.
Land Requirements for Construction
Construction of Tennessee's facilities would require about 67.8 acres of land. About 90 percent of this land is within existing Conrail, Massachusetts Bay Transportation Authority (MBTA), or New England Power Company (NEPCO) rights-of-way. The railroad rights-of-way range in width from 42.5 feet to 122 feet. Tennessee proposes to use all available space in these rights-of-way during construction. The NEPCO right-of-way is about 150 feet wide in the project area. In this area, and where the proposed pipeline would be outside existing rightsof -way, Tennessee proposes to use a 55-foot-wide construction right-ofway. In addition, temporary extra work spaces would be required at various locations adjacent to the construction right-of-way. Following construction, about 15.0 acres, nearly all of which is within existing rights-of-way, would be maintained as new permanent right-of-way for the pipeline or aboveground facilities. The width of the permanent easement within the railroad rights-of-way would be determined based on negotiations with the MBTA and Conrail. Tennessee proposes to maintain a 30-foot-wide permanent easement within the NEPCO right-of-way and where the pipeline is outside existing rights-of-way. The remaining land would be restored and allowed to revert to its former use. DOMAC's proposed facilities would be constructed within the existing fence lien of DOMAC's LNG facility.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
We call this ``scoping''. The main goal of the scoping process is to
focus the analysis in the EA on the important environmental issues. By
this Notice of Intent, the Commission staff requests public comments on
the scope of the issues it will address in the EA. The staff also
requests public comments on its decision to evaluate Tennessee's and
DOMAC's proposed facilities in the same EA. All comments received are
considered during the preparation of the EA. State and local government
representatives are encouraged to notify their constituents of this
proposed action and encourage them to comment on their areas of
concern.
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed projects under these general
headings:
Currently Identified Environmental Issues
We have already identified several issues that we think deserve attention based on a preliminary review of the proposed facilities; our attendance at the Massachusetts Energy Facility Siting Board public hearings in Saugus, Revere, Malden, and Everett; and the environmental information provided by Tennessee and DOMAC. This is a preliminary list of issues and may be added to, subtracted from, or changed based on your comments and our analysis. Issues are:
Public Participation and Scoping Meeting
You can make a difference by sending a letter addressing your specific comments or concerns about the projects. You should focus on the potential environmental effects of the proposal, alternatives to the proposal (including alternative pipeline routes), and measures to avoid or lessen environmental impact. The more specific your comments the more useful they will be. Please follow the instructions below to ensure that your comments are received and properly recorded:
[[Page 25865]]
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceedings or become an
``intervenor''. Among other things, intervenors have the right to
receive copies of case-related Commission documents and filings by
other intervenors. Likewise, each intervenor must provide copies of its
filings to all other parties. If you want to become an intervenor you
must file a motion to intervene according to Rule 214 of the
Commission's Rules of Practice and Procedure (18 CFR 385.214) (see
appendix 2).
Secretary.
[FR Doc. 96-12915 Filed 5-22-96; 8:45 am] BILLING CODE 6717-01-M
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)