DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 11591 Alaska]
City of Wrangell (Sunrise Lake Water Supply and Hydroelectric
Project); Notice of Intent to Conduct Environmental Scoping Meetings
and a Site Visit
May 8, 1998.
The Energy Policy Act of 1992 allows applicants to prepare their
own Environmental Assessment (EA) for hydropower projects and file it
with the Federal Energy Regulatory Commission (Commission) along with
their license application as part of the applicant-prepared EA (APEA)
process. The City of Wrangell (City) intends to prepare an EA to file
with the Commission for the proposed Sunrise Lake Water Supply and
Hydroelectric Project (Sunrise Lake Project), No. 11591. The City will
hold two scoping meetings, pursuant to the National Environmental
Policy Act (NEPA) of 1969, to identify the scope of environmental
issues that should be analyzed in the EA.
Scoping Meetings
The times and locations of the two scoping meetings are:
------------------------------------------------------------------------
Agency meeting Public meeting
------------------------------------------------------------------------
Date:................. Wednesday, May 27, 1998 Wednesday, May 27, 1998
Place:................ City Hall, Wrangell, City Hall, Wrangell,
Alaska. Alaska
Time:................. 2:00 P.M............... 7:00 P.M.
------------------------------------------------------------------------
At the scoping meetings, the City will: (1) summarize the
environmental issues tentatively identified for analysis in the EA; (2)
outline any resources they believe would not require a detailed
analysis; (3) identify reasonable alternatives to be addressed in the
EA; (4) solicit from the meeting participants all available
information, especially quantitative data, on the resources at issue;
and (5) encourage statements from experts and the public on issues that
should be analyzed in the EA.
All interested individuals, organizations, and agencies are invited
and encouraged to attend either or both meetings to assist in
identifying and clarifying the scope of environmental issues that
should be analyzed in the EA.
To help focus discussions at the meetings, the City prepared and
distributed an Initial Stage Consultation Document (ISCD) in January
1998, and a Scoping Document on May 7, 1998. Copies of the ISCD and the
Scoping Document can be obtained by calling Mr. Stephen M. Hart of R.W.
Beck, Inc., the City's agent, at (206) 695-4720. Copies of both
documents will also be available at both scoping meetings.
Site Visit
For those who intend to participate in scoping, the City will also
conduct a site visit to the proposed Sunrise Lake Project on Thursday,
May 28, 1998. Those attending the site visit should meet at Wrangell
airport at 10:00 A.M. We will promptly leave for the project site, via
helicopter. Those being shuttled by helicopter to the project site may
need to sign a waiver of liability regarding helicopter use. Because of
the remoteness and difficulty of ground access at the project site,
those attending the site visit should be physically fit and must wear
appropriate clothing and
[[Page 26794]]
footgear. Participants must provide their own sack lunches.
To plan on helicopter use in advance of the visit, the City must
identify the number of individuals interested in the site visit.
Therefore, if you intend on visiting the proposed project site, you
must register with Ms. Christy Jamieson at (907) 874-2381, no later
than May 20, 1998. If inclement weather prevents a site visit on May
28, the alternative date will be May 29 at the same time and location.
Meeting Procedures
The meetings will be conducted according to the procedures used at
Commission scoping meetings. Because this meeting will be a NEPA
scoping meeting under the APEA process, the Commission will not conduct
a NEPA scoping meeting after the application and draft EA are filed
with the Commission.
Both scoping meetings will be recorded by a stenographer or tape
recorder, and will become part of the formal record of the proceedings
for this project.
Those who choose not to speak during the scoping meetings may
instead submit written comments on the project. Written comments must
be submitted by June 26, 1998, and should be mailed to: Mr. Stephen M.
Hart, P.E., R.W. Beck, Inc., 1001 Fourth Avenue, Suite 2500, Seattle,
Washington 98154-1004. All correspondence should show the following
caption on the first page:
Scoping Comments, Sunrise Lake Water Supply and Hydroelectric Project,
Project No. 11591, Alaska.
For further information please contact Stephen M. Hart at (206)
695-4720, or Nick Jayjack of the Commission at (202) 219-2825.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-12781 Filed 5-13-98; 8:45 am]