Entergy Nuclear Generation Company; Pilgrim Nuclear Power Station Environmental Assessment and Finding of No Significant Impact
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: March 30, 2000 (Volume 65, Number 62)]
[Notices]
[Page 16972-16973]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr30mr00-123]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-293]
Entergy Nuclear Generation Company; Pilgrim Nuclear Power Station
Environmental Assessment and Finding of No Significant Impact
The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an exemption for Facility Operating License No. DPR-35,
issued to Entergy Nuclear Generation Company (Entergy/the licensee),
for operation of Pilgrim Nuclear Power Station, (Pilgrim), located in
Plymouth County, Massachusetts.
Environmental Assessment
Identification of the Proposed Action
The proposed action would exempt the licensee from the requirements
of 10 CFR Part 50, Appendix E, Item IV.F.2.c regarding conduct of a
full-participation exercise of the offsite emergency plan biennially.
Under the proposed exemption, the licensee would reschedule the
Federally-observed full-participation emergency exercise from December
2001 to May 2002 and all future Nuclear Regulatory Commission (NRC)--
and Federal Emergency Management Agency (FEMA)--evaluated exercises
would occur biennially from the year 2002.
The proposed action is in accordance with the licensee's
application for exemption dated July 30, 1999, as supplemented on
September 23, 1999.
The Need for the Proposed Action
Title 10 of the Code of Federal Regulation, (10 CFR) Part 50,
Appendix E, Item IV.F.2.c requires each licensee at each site to
conduct an exercise of its offsite emergency plan biennially. The NRC
and FEMA observe these exercises and evaluate the performance of the
licensee, State, and local authorities having a role under the
emergency plan.
The licensee would be required to conduct an exercise of its onsite
and offsite emergency plans in December 2001, which is at the end of
the required interval. To support the efficient and effective use of
Federal resources, as discussed during the annual NRC Region I and FEMA
(Regions I, II, and
[[Page 16973]]
III) exercise scheduling meeting held in White Plains, New York, in
December 1998, the planned December 2001 exercise for Pilgrim was
shifted to May 2002, which is beyond the required interval.
Environmental Impacts of the Proposed Action
The Commission has completed its evaluation of the proposed action
and concludes that the proposed action involves an administrative
activity (a schedular change in conducting an exercise) unrelated to
plant operations.
The proposed action will not significantly increase the probability
or consequences of accidents, no changes are being made in the types of
any effluents that may be released off site, and there is no
significant increase in occupational or public radiation exposure.
Therefore, there are no significant radiological environmental impacts
associated with the proposed action.
With regard to potential non-radiological impacts, the proposed
action does not involve any historic sites. It does not affect non-
radiological plant effluents and has no other environmental impact.
Therefore, there are no significant non-radiological environmental
impacts associated with the proposed action.
Accordingly, the NRC concludes that there are no significant
environmental impacts associated with the proposed action.
Alternatives to the Proposed Action
As an alternative to the proposed action, the staff considered
denial of the proposed action (i.e., the ``no-action'' alternative).
Denial of the application would result in no change in current
environmental impacts. The environmental impacts of the proposed action
and the alternative action are similar.
Alternative Use of Resources
This action does not involve the use of any resources not
previously considered in the ``Final Environmental Statement Related to
the Operation of Pilgrim Nuclear Power Station, Boston Edison
Company,'' dated May 1972 .
Agencies and Persons Consulted
In accordance with its stated policy, on August 5, 1999, the staff
consulted with the Massachusetts State official, Mr. James Muckerhide
of the Massachusetts Emergency Management Agency, regarding the
environmental impact of the proposed action. The State official had no
comments. In addition, staff members of NRC Region I and FEMA were
contacted by phone and provided favorable recommendations to approve
the requested exemption.
Finding of No Significant Impact
On the basis of the environmental assessment, the NRC concludes
that the proposed action will not have a significant effect on the
quality of the human environment. Accordingly, the NRC has determined
not to prepare an environmental impact statement for the proposed
action.
For further details with respect to the proposed action, see the
licensee's letter dated July 30, 1999, as supplemented on September 23,
1999, which is available for public inspection at the Commission's
Public Document Room, The Gelman Building, 2120 L Street, NW.,
Washington, DC. Publically available records will be accessible
electronically from the ADAMS Public Library component on the NRC Web
site, http://www.nrc.gov (The Electronic Reading Room).
Dated at Rockville, Maryland, this 24 day of March 2000.
For the Nuclear Regulatory Commission.
Alan B. Wang,
Project Manager, Section 2, Project Directorate I, Division of
Licensing Project Management, Office of Nuclear Reactor Regulation.
[FR Doc. 00-7829 Filed 3-29-00; 8:45 am]