Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: November 30, 2000 (Volume 65, Number 231)]
[Notices]
[Page 71310-71311]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr30no00-45]
[[Page 71310]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepted for Filing and Soliciting Motions
To Intervene, Protests, and Comments
November 24, 2000.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 11864-000.
c. Date filed: November 13, 2000.
d. Applicant: City of Granite Falls, Minnesota.
e. Name of Project: Minnesota Falls Project.
f. Location: On Minnesota River, in Chippewa and Yellow Medicine
Counties, Minnesota. No federal land or facilities would be utilized.
g. Filed Pursuant to: Federal Power Act, 16 USC Secs. 791(a)-
825(r).
h. Applicant Contact: Mr. William P. Lavin, City of Granite Falls,
885 Prentice Street, Granite Falls, Minnesota 56241-1598, (320) 564-
3011.
i. FERC Contact: Robert Bell, (202) 219-2806.
j. Deadline for filing motions to intervene, protests and comments:
January 29, 2001.
All documents (original and eight copies) should be filed with:
David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Comments and protests may be
filed electronically via the internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's web site
at http://www.ferc.fed.us/efi/doorbell.htm.
The Commission's Rules of Practice and Procedure require all
interveners filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Project: The proposed project would consist of
(1) an existing 600-foot-long, 18-foot-high granite masonry gravity
dam; (2) an existing reservoir with a surface area of 150 acres having
a storage capacity of 735 acre-feet and normal water surface elevation
of 883.9 feet msl; (3) a proposed intake structure; (4) a proposed 200-
foot-long, 9-foot-diameter steel conduit; (4) a proposed powerhouse
containing two generating units having a total installed capacity of
1,160 kW; (5) a proposed 2-mile-long, 12.47 kV transmission line; and
(6) appurtenant facilities.
The project would have an annual generation of 3.6 GWh that would
be sold to a local utility.
l. A copy of the application is available for inspection and
reproduction at the Commission's Public Reference Room, located at 888
First Street, NE, Room 2A, Washington, DC 20426, or by calling (202)
208-1371. The application may be viewed on http://www.ferc.fed.us/
online/rims.htm (call (202) 208-2222 for assistance). A copy is also
available for inspection and reproduction at the address in item h
above.
Preliminary Permit--Anyone desiring to file a competing application
for preliminary permit for a proposed project must submit the competing
application itself, or a notice of intent to file such an application,
to the Commission on or before the specified comment date for the
particular application (see 18 CFR 4.36). Submission of a timely notice
of intent allows an interested person to file the competing preliminary
permit application no later than 30 days after the specified comment
date for the particular application. A competing preliminary permit
application must conform with 18 CFR 4.30(b) and 4.36.
Preliminary Permit--Any qualified development application desiring
to file a competing development application must submit to the
Commission, on or before a specified comment date for the particular
application, either a competing development application or a notice of
intent to file such an application. Submission of a timely notice of
intent to file a development application allows an interested person to
file the competing application no later than 120 days after the
specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
Notice of intent--A notice of intent must specify the exact name,
business address, and telephone number of the prospective applicant,
and must include an unequivocal statement of intent to submit, if such
an application may be filed, either a preliminary permit application or
a development application (specify which type of application). A notice
of intent must be served on the applicant(s) named in this public
notice.
Proposed Scope of Studies under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Filing and Service of Responsive Documents--Any filings must bear
in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT TO
FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', ``PROTEST'',
``MOTION TO INTERVENE'', as applicable, and the Project Number of the
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and the number
of copies provided by the Commission's regulations to: The Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. An additional copy must be sent to Director,
Division of Hydropower Administration and Compliance, Federal Energy
Regulatory Commission, at the above-mentioned address. A copy of any
notice of intent, competing application or motion to intervene must
also be served upon each representative of the Applicant specified in
the particular application.
Agency Comments--Federal, state, and local agencies are invited to
file comments to the described application. A copy of the application
may be obtained by agencies directly from the Applicant. If an agency
does not file comments within the time specified for filing comments,
it will be presumed to have no comments. One copy of an
[[Page 71311]]
agency's comments must also be sent to the Applicant's representatives.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 00-30480 Filed 11-29-00; 8:45 am]
BILLING CODE 6717-01-M