Jump to main content.


Blackfeet Wind Project

 [Federal Register: April 16, 2001 (Volume 66, Number 73)]
[Notices]
[Page 19473-19474]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr16ap01-45]

[[Page 19473]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Bonneville Power Administration


Blackfeet Wind Project

AGENCY: Bonneville Power Administration (BPA), Department of Energy
(DOE).

ACTION: Notice of intent to prepare an Environmental Impact Statement
(EIS).

-----------------------------------------------------------------------

SUMMARY: BPA intends to prepare an EIS on the proposed Blackfeet Wind
Project (Project), located in Glacier County, Montana, on the Blackfeet
Indian Reservation. Blackfeet I, LLC (Blackfeet I) proposes to
construct and operate the 36- to 66-megawatt (MW) wind generation
facility. BPA proposes to purchase the electrical output from the
Project. The EIS will address potential environmental impacts of the
construction and operation of the wind project itself, as well as all
related transmission facilities in accordance with the National
Environmental Policy Act. The Department of Interior, Bureau of Indian
Affairs, will be a cooperating agency because of their need to approve
the contract and associated permits between Blackfeet I and the
Blackfeet Indian Nation.

DATES: EIS scoping meetings will be held at the locations below on May
10, 2001. Written comments are due to the address below no later than
May 25, 2001.

ADDRESSES: Send comment letters and requests to be placed on the
Project mailing list to Communications, Bonneville Power
Administration--KC-7, P.O. Box 12999, Portland, Oregon, 97212. The
phone number of the Communications office is 503-230-3478 in Portland;
toll-free 1-800-622-4519 outside of Portland. Comments may also be sent
to the BPA Internet address: comment@bpa.gov.
    The May 10, 2001, EIS scoping meetings will be held at the Bureau
of Indian Affairs, Main Conference Room, 531 S.E. Boundary Street, in
Browning, Montana, from 2 p.m. to 4 p.m.; and at the Cattle Baron
Restaurant on U.S. 89 near milepost 40.5 in Babb, Montana, from 6 p.m.
to 8 p.m. At these informal meetings, Blackfeet I will provide
information, including maps, about the Project. Written information
will be available, and BPA staff will answer questions and accept oral
and written comments on the proposed scope of the Draft EIS.

FOR FURTHER INFORMATION CONTACT: Sarah T. Branum, KEC-4, Bonneville
Power Administration, PO Box 3621, Portland, Oregon 97208-3621, phone
number 503-230-5115, fax number 503-230-5699, email stbranum@bpa.gov.

SUPPLEMENTARY INFORMATION:
    Background. There is an increased demand in the electric utility
industry to diversify energy portfolios and include energy produced by
new renewable resources. The Northwest Power Planning Council's Fourth
Conservation and Electric Power Plan recommends that Northwest
utilities offer green power purchase opportunities as a way to help the
region integrate renewable resources into the power system in the
future. In addition, BPA has committed to increasing its supply of
conservation and renewable resources to help meet load.
    Purpose and Need. In the face of regional growth in electrical
loads and increasing constraints on the existing energy resource base,
BPA needs to acquire resources that will contribute to diversification
of the long-term power supply in the region. The purposes of acquiring
a diverse resource portfolio include:
     Protecting BPA and its utility customers against risk;
     Assuring consistency with BPA's responsibility under the
Pacific Northwest Electric Power Planning and Conservation Act to
encourage the development of renewable energy resources;
     Meeting customer demand for energy from renewable energy
resources, thereby assuring consistency with BPA's Business Plan EIS
(DOE/EIS-0183, June 1995) and Business Plan Record of Decision (ROD);
     Assuring consistency with the resource acquisition
strategy of BPA's Resource Programs EIS (DOE/EIS-0162, February 1993)
and ROD; and
     Meeting the objective in the January 2000 Strategic Plan
of BPA's Power Business Line to acquire at least 150 average MW of new
renewable resources by the end of fiscal year 2006 in order to meet
customer demand for new renewable resources.
    Proposed Action. In September 2000, Blackfeet I proposed to
construct and operate this 36- to 66-MW wind generation facility,
located in mid Glacier County, Montana, east of the town of Babb, on
the Blackfeet Indian Reservation. BPA proposes to execute one or more
power purchase and transmission services agreements to acquire the full
electrical output of Blackfeet I's proposed Blackfeet Wind Project. The
proposed site is tentatively called Duck Lake Ridge, which includes
portions of Sections 28, 29, 31, 32, T36N R13W, and portions of
Sections 5 and 6, T35N R13W, on approximately 3800 acres of tribal,
allotted, and privately owned lands. Land uses within the Project site
consist of non-irrigated agriculture--primarily cattle grazing and some
timber. No Project facilities would be constructed upon lands owned by
the State of Montana or by the United States.
    Approximately 36 to 88 wind turbines would be arranged in several
''strings,'' with generally between 250 to 425 feet between turbines in
each string. Blackfeet I is considering using either 600-kilowatt (kW)
turbines, or 1,000-kW turbines. The proposed turbine type would be an
upwind, fixed-speed turbine (i.e., the rotor always faces upwind and
turns at a constant speed), mounted on tubular steel towers installed
on a reinforced concrete foundation. The wind turbine rotors would turn
at approximately 18 to 28 revolutions per minute. The typical operating
range of wind speeds for these turbine types is 10 to 65 miles per hour
(mph). At speeds greater than 60 or 65 mph, the wind turbines
automatically cease operating and remain stationary until the wind
speeds become slower. Foundations would be either tubular or pad,
ranging from approximately 15 to 20 feet in width and extending up to
25 to 30 feet underground or anchored into bedrock. Agricultural
activities generally can continue to take place directly adjacent to
the turbine pads.
    Power from all turbines in the Project would be collected by an
underground and overhead cable loop and then fed underground to a
proposed substation to be located at the Project site. The fenced
substation site would occupy approximately one to two acres. From the
substation site, power from the Project would be transmitted by
existing above-ground transmission lines owned by Glacier Electric
Cooperative. These facilities are currently operated at 34.5 kilovolts
(kV) and would be energized at their design and constructed voltage
rating of 115 kV, which would then interconnect with the existing
Montana Power Company's 115-kV transmission facilities at Browning,
Montana, or Western Area Power Administration's 115-kV transmission
facilities at Shelby, Montana. The power would either be used locally
or be transmitted to other parts of the Northwest transmission grid to
meet Northwest loads. Other facilities required as part of the Project
are down-tower pad-mounted transformers, access roads, an operation and
maintenance building, and communications system. The Project is
scheduled to begin commercial operation late in 2002, and would operate
year-round for at least 20 years.

[[Page 19474]]

    Process to Date. Wind assessments began in October 2000. Surveys
for sensitive plant and wildlife species are being initiated in the
spring of 2001. Scoping will help identify what additional studies will
be required.
    Alternatives Proposed for Consideration. The alternatives include
the proposed action (executing a power purchase agreement with
Blackfeet I for up to 36 to 66 MW of electrical energy from the
proposed Blackfeet Wind Project and contracting for transmission), and
the No Action alternative.
    Public Participation and Identification of Environmental Issues.
For other wind projects, noise, visual impacts, impacts on cultural
resources, and effects on sensitive plant and animal species have been
identified as potential environmental issues. BPA has established a 30-
day scoping period during which affected landowners, concerned
citizens, special interest groups, local governments, and any other
interested parties are invited to comment on the scope of the EIS.
Scoping will help BPA identify the range of environmental issues that
should be addressed in the EIS. When completed, the Draft EIS will be
circulated for review and comment, and BPA will hold at least one
public comment meeting for the Draft EIS. BPA will consider and respond
in the Final EIS to comments received on the Draft EIS. The Final EIS
is expected to be published in early summer 2002. BPA's subsequent
decision will be documented in a Record of Decision. The EIS will
satisfy the requirements of the National Environmental Policy Act.

    Issued in Portland, Oregon, on April 6, 2001.
Steven G. Hickok,
Acting Administrator and Chief Executive Officer.
[FR Doc. 01-9379 Filed 4-13-01; 8:45 am]
BILLING CODE 6450-01-P 

 
 


Local Navigation


Jump to main content.