Notice of Opportunity To Comment on Model Safety Evaluation on Technical Specification Improvement To Eliminate Post Accident Sampling Requirements for Boiling Water Reactors Using the Consolidated Line Item Improvement Process
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: December 27, 2001 (Volume 66, Number 248)]
[Notices]
[Page 66949-66954]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr27de01-154]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
Notice of Opportunity To Comment on Model Safety Evaluation on
Technical Specification Improvement To Eliminate Post Accident Sampling
Requirements for Boiling Water Reactors Using the Consolidated Line
Item Improvement Process
AGENCY: Nuclear Regulatory Commission.
ACTION: Request for comment.
-----------------------------------------------------------------------
SUMMARY: Notice is hereby given that the staff of the Nuclear
Regulatory Commission (NRC) has prepared a model safety evaluation (SE)
relating to the elimination of requirements on post accident sampling
imposed on licensees through orders, license conditions, or technical
specifications. The NRC staff has also prepared a model no significant
hazards consideration (NSHC) determination relating to this matter. The
purpose of these models is to permit the NRC to efficiently process
amendments that propose to remove requirements for the Post Accident
Sampling System [or Station]
(PASS) for Boiling Water Reactors (BWRs).
Licensees of nuclear power reactors to which the models apply could
request amendments conforming to the models. In such a request, a
licensee should confirm the applicability of the SE and NSHC
determination to its reactor and provide the requested plant-specific
verifications and commitments. The NRC staff is requesting comments on
the model SE and model NSHC determination before announcing their
availability for referencing in license amendment applications.
DATES: The comment period expires January 28, 2002. Comments received
after this date will be considered if it is practical to do so, but the
Commission is able to ensure consideration only for comments received
on or before this date.
ADDRESSES: Comments may be submitted either electronically or via U.S.
mail.
Submit written comments to: Chief, Rules and Directives Branch,
Division of Administrative Services, Office of Administration, Mail
Stop: T-6 D59, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001.
Hand deliver comments to: 11545 Rockville Pike, Rockville,
Maryland, between 7:45 a.m. and 4:15 p.m. on Federal workdays.
Copies of comments received may be examined at the NRC's Public
Document Room, One White Flint North, 11555 Rockville Pike (first
floor), Rockville, Maryland.
Comments may be submitted by electronic mail to CLIIP@nrc.gov.
FOR FURTHER INFORMATION CONTACT: William Reckley, Mail Stop: O-8H1,
Division of Licensing Project Management, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, telephone 301-415-1389.
SUPPLEMENTARY INFORMATION:
Background
Regulatory Issue Summary 2000-06, ``Consolidated Line Item
Improvement Process for Adopting Standard Technical Specification
Changes for Power Reactors,'' was issued on March 20, 2000. The
Consolidated Line Item Improvement Process (CLIIP) is intended to
improve the efficiency and transparency of NRC licensing processes.
This is accomplished by processing proposed changes to the Standard
Technical Specifications (STS) in a manner that supports subsequent
license amendment applications. The CLIIP includes an opportunity for
the public to comment on proposed changes to the STS following a
preliminary assessment by the NRC staff and finding that the change
will likely be offered for adoption by licensees. This notice is
soliciting comment on a proposed change to the STS that removes
requirements for the PASS for BWRs. The CLIIP directs the NRC staff to
evaluate any comments received for a proposed change to the STS and to
either reconsider the change or to proceed with announcing the
availability of the change for proposed adoption by licensees. Those
licensees opting to apply for the subject change to technical
specifications are responsible for reviewing the staff's evaluation,
referencing the applicable technical justifications, and providing any
necessary plant-specific information.
[[Page 66950]]
Each amendment application made in response to the notice of
availability would be processed and noticed in accordance with
applicable rules and NRC procedures.
This notice involves the elimination of requirements for PASS and
related administrative controls in technical specifications for BWRs.
This proposed change was proposed for incorporation into the standard
technical specifications by the BWR Owners Group (BWROG) participants
in the Technical Specification Task Force (TSTF) and is designated
TSTF-413. TSTF-413 is supported by the NRC staff's safety evaluation
dated June 12, 2001, for the BWROG topical report NEDO-32991,
``Regulatory Relaxation for BWR Post Accident Sampling Stations
(PASS),'' which was submitted to the NRC on November 30, 2000. The
BWROG request followed the staff's approval of similar requests for
elimination of PASS requirements from the Combustion Engineering Owners
Group (CEOG) and the Westinghouse Owners Group (WOG).
Applicability
This proposed change to remove requirements for PASS from technical
specifications (and other elements of the licensing bases) is
applicable to BWRs.
To efficiently process the incoming license amendment applications,
the staff requests each licensee applying for the changes addressed by
TSTF-413 using the CLIIP to address the following plant-specific
verifications and regulatory commitments. The CLIIP does not prevent
licensees from requesting an alternative approach or proposing the
changes without the requested verifications and regulatory commitments.
Variations from the approach recommended in this notice may, however,
require additional review by the NRC staff and may increase the time
and resources needed for the review. In making the requested regulatory
commitments, each licensee should address: (1) That the subject
capability exists (or will be developed) and will be maintained; (2)
where the capability or procedure will be described (e.g., severe
accident management guidelines, emergency operating procedures,
emergency plan implementing procedures); and (3) a schedule for
implementation. The amendment request need not provide details about
designs or procedures.
Each licensee should verify that it has, and make a regulatory
commitment to maintain (or make a regulatory commitment to develop and
maintain):
a. Contingency plans for obtaining and analyzing highly radioactive
samples from the reactor coolant system, suppression pool, and
containment atmosphere;
b. A capability for classifying fuel damage events at the Alert
level threshold (typically this is 300 µCi/ml dose equivalent
iodine). This capability may use a normal sampling system or
correlations of radiation readings to coolant concentrations; and
c. An I-131 site survey detection capability, including an ability
to assess radioactive iodines released to offsite environs, by using
effluent monitoring systems or portable sampling equipment.
Public Notices
In a notice in the Federal Register dated August 11, 2000 (65 FR
49271), the staff requested comment on the use of the CLIIP to process
requests to delete post-accident sampling requirements from plants with
Westinghouse and Combustion Engineering designs. Following the
disposition of comments, the staff published a notice of availability
of the staff's SE and NSHC determination for referencing using the
CLIIP (65 FR 65018, October 31, 2000). Each request to eliminate PASS
requirements by licensees for Westinghouse and CE plants using the
CLIIP has also included notices prior to issuance of the subject
license amendments and upon issuance.
This notice requests comments from interested members of the public
within 30 days of the date of publication in the Federal Register.
Following the staff's evaluation of comments received as a result of
this notice, the staff may reconsider the proposed change or may
proceed with announcing the availability of the change in a subsequent
notice (perhaps with some changes to the safety evaluation or proposed
no significant hazards consideration determination as a result of
public comments). If the staff announces the availability of the
change, licensees wishing to adopt the change will submit an
application in accordance with applicable rules and other regulatory
requirements. The staff will in turn issue for each application a
notice of consideration of issuance of amendment to facility operating
license(s), a proposed no significant hazards consideration
determination, and an opportunity for a hearing. A notice of issuance
of an amendment to operating license(s) will also be issued to announce
the elimination of the PASS requirements for each plant that applies
for and receives the requested change.
Proposed Safety Evaluation
U.S. Nuclear Regulatory Commission
Office of Nuclear Reactor Regulation
Consolidated Line Item Improvement, Technical Specification Task
Force (TSTF) Change TSTF-413, Elimination of Requirements for Post
Accident Sampling System [or Station]
(PASS)
1.0 Introduction
In the aftermath of the accident at Three Mile Island (TMI), Unit
2, the Nuclear Regulatory Commission (NRC) imposed requirements on
licensees for commercial nuclear power plants to install and maintain
the capability to obtain and analyze post-accident samples of the
reactor coolant and containment atmosphere. The desired capabilities of
the Post Accident Sampling System [or Station]
(PASS) were described in
NUREG-0737, ``Clarification of TMI Action Plan Requirements.'' The NRC
issued orders to licensees with plants operating at the time of the TMI
accident to confirm the installation of PASS capabilities (generally as
they had been described in NUREG-0737). A requirement for PASS and
related administrative controls was added to the technical
specifications (TS) of the operating plants and was included in the
initial TS for plants licensed during the 1980s and 90s. Additional
expectations regarding PASS capabilities were included in Regulatory
Guide 1.97, ``Instrumentation for Light-Water-Cooled Nuclear Power
Plants To Assess Plant and Environs Conditions During and Following an
Accident.''
Significant improvements have been achieved since the TMI accident
in the areas of understanding risks associated with nuclear plant
operations and developing better strategies for managing the response
to potentially severe accidents at nuclear plants. Recent insights
about plant risks and alternate severe accident assessment tools have
led the NRC staff to conclude that some TMI Action Plan items can be
revised without reducing the ability of licensees to respond to severe
accidents. The NRC's efforts to oversee the risks associated with
nuclear technology more effectively and to eliminate undue regulatory
costs to licensees and the public have prompted the NRC to consider
eliminating the requirements for PASS in TS and other parts of the
licensing bases of operating reactors.
The staff has completed its review of the topical report submitted
by the Boiling Water Reactor (BWR) Owners Group (BWROG) that proposed
the elimination of PASS. The justifications for the proposed
elimination of PASS
[[Page 66951]]
requirements center on evaluations of the various radiological and
chemical sampling and their potential usefulness in responding to a
severe reactor accident or making decisions regarding actions to
protect the public from possible releases of radioactive materials. As
explained in more detail in the staff's safety evaluations for the
topical report, the staff has reviewed the available sources of
information for use by decision-makers in developing protective action
recommendations and assessing core damage. Based on this review, the
staff found that the information provided by PASS is either unnecessary
or is effectively provided by other indications of process parameters
or measurement of radiation levels. The staff agrees, therefore, with
the owners group that licensees can remove the TS requirements for
PASS, revise (as necessary) other elements of the licensing bases, and
pursue possible design changes to alter or remove existing PASS
equipment.
2.0 Background
In its letter dated November 30, 2000, the BWROG submitted for the
NRC staff's review Topical Report NEDO-32991, ``Regulatory Relaxation
for BWR Post Accident Sampling Stations (PASS),'' for eliminating PASS
requirements from BWRs. The NRC staff's safety evaluation for the BWROG
topical report is dated June 12, 2001 (ADAMS Accession Number
ML011630016). The BWROG proposed that relaxation of the PASS
requirements be incorporated into the standard technical specifications
by submitting TSTF-413.
The NRC staff prepared this model safety evaluation (SE) relating
to the elimination of requirements on post accident sampling for BWRs
and solicited public comment [ FR ]
in accordance with the CLIIP. The
use of the CLIIP in this matter is intended to help the NRC to
efficiently process amendments that propose to remove the PASS
requirements from TS. Licensees of nuclear power reactors to which this
model apply were informed [ FR ]
that they could request amendments
conforming to the model, and, in such requests, should confirm the
applicability of the SE to their reactors and providing the requested
plant-specific verifications and commitments.
3.0 Evaluation
The ways in which the requirements and recommendations for PASS
were incorporated into the licensing bases of commercial nuclear power
plants varied as a function of when plants were licensed. Plants that
were operating at the time of the TMI accident are likely to have been
the subject of confirmatory orders that imposed the PASS functions
described in NUREG-0737 as obligations. The issuance of plant specific
amendments to adopt this change, which would remove PASS and related
administrative controls from TS, would also supercede the PASS specific
requirements imposed by post-TMI confirmatory orders.
The technical evaluations for the elimination of PASS sampling
requirements are provided in the safety evaluation dated June 12, 2001,
for BWROG topical report NEDO-32991. As described in its safety
evaluation for the topical report, the staff finds that the post-
accident sampling requirements for the following may be eliminated for
BWR plants:
1. Reactor coolant dissolved gases.
2. Reactor coolant hydrogen.
3. Reactor coolant oxygen.
4. Reactor coolant chlorides.
5. Reactor coolant pH.
6. Reactor coolant boron.
7. Reactor coolant conductivity.
8. Radioisotopes in the reactor coolant.
9. Containment hydrogen.
10. Containment oxygen.
11. Radioisotopes in the containment atmosphere.
12. Suppression pool pH.
13. Chlorides in the suppression pool.
14. Boron in the suppression pool.
15. Radioisotopes in the suppression pool.
The staff agrees that sampling of radioisotopes is not required to
support emergency response decision making during the initial phases of
an accident because the information provided by PASS is either
unnecessary or is effectively provided by other indications of process
parameters or measurement of radiation levels. Therefore, it is not
necessary to have dedicated equipment to obtain this sample in a prompt
manner.
The staff does, however, believe that there could be significant
benefits to having information about the radioisotopes existing post-
accident in order to address public concerns and plan for long-term
recovery operations. As stated in the safety evaluation for the topical
report, the staff has found that licensees could satisfy this function
by developing contingency plans to describe existing sampling
capabilities and what actions (e.g., assembling temporary shielding)
may be necessary to obtain and analyze highly radioactive samples from
the reactor coolant system (RCS), suppression pool, and containment
atmosphere. (See item 4.1 under Verifications and Commitments.) The
contingency plans for obtaining samples from the RCS, suppression pool,
and containment atmosphere may also enable a licensee to derive
information on parameters such as hydrogen concentrations in
containment and the pH of water in the suppression pool. The staff
considers the sampling of the suppression pool to be potentially useful
in confirming calculations of pH and confirming that potentially
unaccounted for acid sources have been sufficiently neutralized. The
use of the contingency plans for obtaining samples would depend on the
plant conditions and the need for information by the decision-makers
responsible for responding to the accident.
In addition, the staff considers radioisotope sampling information
to be useful in classifying certain types of events (such as a
reactivity excursion or mechanical damage) that could cause fuel damage
without having an indication of a loss of reactor coolant inventory.
However, the staff agrees with the topical report's contentions that
other indicators of failed fuel, such as radiation monitors, can be
correlated to the degree of failed fuel. (See item 4.2 under
Verifications and Commitments.)
In lieu of the information that would have been obtained from PASS,
the staff believes that licensees should maintain or develop the
capability to monitor radioactive iodines that have been released to
offsite environs. This information would be useful for decision makers
trying to assess a release of and limit the public's exposure to
radioactive materials. (See item 4.3 under Verifications and
Commitments.)
The staff believes that the changes related to the elimination of
PASS that are described in the topical report, related safety
evaluation and this proposed change to TS are unlikely to result in a
decrease in the effectiveness of a licensee's emergency plan. Each
licensee, however, must evaluate possible changes to its emergency plan
in accordance with 10 CFR 50.54(q) to determine if the change decreases
the effectiveness of its site-specific plan. Evaluations and reporting
of changes to emergency plans should be performed in accordance with
applicable regulations and procedures.
The staff notes that redundant, safety-grade, containment hydrogen
concentration monitors are required by 10 CFR 50.44(b)(1), are
addressed in NUREG-0737 Item II.F.1 and Regulatory Guide 1.97, and are
relied upon to meet the data reporting requirements of 10 CFR part 50,
Appendix E, Section VI.2.a.(ii)(3). The staff concludes that during the
early phases of an accident,
[[Page 66952]]
the safety-grade hydrogen monitors provide an adequate capability for
monitoring containment hydrogen concentration. The staff sees value in
maintaining the capability to obtain grab samples for complementing the
information from the hydrogen monitors in the long term (i.e., by
confirming the indications from the monitors and providing hydrogen
measurements for concentrations outside the range of the monitors). As
previously mentioned, the licensee's contingency plan (see item 4.1)
for obtaining highly radioactive samples will include sampling of the
containment atmosphere and may, if deemed necessary and practical by
the appropriate decision-makers, be used to supplement the safety-
related hydrogen monitors.
Note 1: Each licensee should specify a desired implementation
period for its specific amendment request. The implementation period
would be that period necessary to develop and implement the items in
4.1 through 4.3 and, as necessary, to make other changes to
documentation or equipment to support the elimination of PASS
requirements. As an alternative, the licensee may choose to have a
shorter implementation period and include the scheduling of items
4.1 through 4.3 as part of the regulatory commitments associated
with this amendment request. Amendment requests that include
commitments for implementation of the items in Section 4 within 6
months of the implementation of the revised TS will remain within
the CLIIP.
Note 2: There may be some collateral changes to the TS as a
result of the removal of the administrative controls section for
PASS. The following paragraphs address three potential changes that
the staff is aware of (editorial changes, mention of PASS as a
potential leakage source outside containment, and revision of the
bases section for post accident monitoring instrumentation).
(A) The elimination of the TS and other regulatory requirements
for PASS would result in additional changes to TS such as [e.g., the
renumbering of sections or pages or the removal of references]. The
changes are included in the licensee's application to revise the TS
in order to take advantage of the CLIIP. The staff has reviewed the
changes and agrees that the revisions are necessary due to the
removal of the TS section on PASS. The changes do not revise
technical requirements beyond that reviewed by the NRC staff in
connection with the supporting topical reports or the preparation of
the TS improvement incorporated into the CLIIP.
(B) The TS include an administrative requirement for a program
to minimize to levels as low as practicable the leakage from those
portions of systems outside containment that could contain highly
radioactive fluids during a serious transient or accident. The
program includes preventive maintenance, periodic inspections, and
leak tests for the identified systems. PASS is specifically listed
in TS [5.5.2]
as falling under the scope of this requirement. The
applicability of this specification depends on whether or not PASS
is maintained as a system that is a potential leakage path. [Note
that several options (see following) exist for handling the impact
that eliminating PASS requirements would have on the specification
for the program to control leakage outside containment.
(i) The licensee has stated that a plant change would be
implemented such that PASS would not be a potential leakage path
outside containment for highly radioactive fluids (e.g., the PASS
piping that penetrates the containment would be cut and capped). The
modification would be made during the implementation period for this
amendment such that it is appropriate to delete the reference to PASS
in TS [5.5.2]. Requirements in NRC regulations (e.g., 10 CFR part 50,
Appendix J) and other TS provide adequate regulatory controls over the
licensee's proposed modification to eliminate PASS as a potential
leakage path.
(ii) The licensee has stated that a plant change might be
implemented such that PASS would not be a potential leakage path
outside containment for highly radioactive fluids (e.g., the PASS
piping that penetrates the containment might be cut and capped). The
modification would not be made during the implementation period for
this amendment. The licensee has proposed to add the following phrase
to the reference to PASS in TS [5.5.2]:
``(until such time as a modification eliminates the PASS
penetration as a potential leakage path).''
The above phrase would make clear that TS [5.5.2]
remains
applicable to the PASS as long as it is a possible leakage path and
reflects that the actual modification of the piping system may be
scheduled beyond the implementation period for this amendment.
Requirements in NRC regulations (10 CFR part 50, Appendix J) and other
TS provide adequate regulatory control over the licensee's modification
to eliminate PASS as a potential leakage path. Following the
modification to eliminate PASS as a potential leakage path, the
licensee may elect (in order to maintain clarity and simplicity of the
requirement) to revise TS [5.5.2]
to remove the reference to PASS,
including the phrase added by this amendment.
(iii) The licensee has stated that the configuration of the PASS
will continue to be a potential leakage path outside containment for
highly radioactive fluids (e.g., the PASS piping will penetrate the
containment with valves or other components in the system from which
highly radioactive fluid could leak). The licensee has [not proposed to
change TS (5.5.2) or has changed TS (5.5.2) to revise the reference to
this system from PASS to ( )]. The staff agrees [that TS 5.5.2 is not
affected or that the change to revise the reference from PASS to ( )]
is acceptable. A separate amendment request will be required if the
licensee, subsequent to this amendment, decides to modify the plant to
eliminate this potential leakage path and proposes to change the
requirements of TS [5.5.2].
(C) [Note-optional section if licensee provides markup of affected
Bases pages]
The elimination of PASS requires that the licensee revise
the discussion in the Bases section for TS [3.3.3, ``Post Accident
Monitoring Instrumentation']. The current Bases mention the
capabilities of PASS as part of the justification for allowing both
hydrogen monitor channels to be out of service for a period of up to 72
hours. Although the licensee's application included possible wording
for the revised Bases discussion for TS [3.3.3], the licensee will
formally address the change to the Bases in accordance with [the Bases
Control Program or its administrative procedure for revising Bases].
The staff does not believe that the Bases change will require prior NRC
approval when evaluated against the criteria in 10 CFR 50.59,
``Changes, tests, and experiments,'' and, therefore, agrees that the
revision of the Bases to TS [3.3.3]
should be addressed separately from
this amendment and should be included in a future update of the TS
Bases in accordance with [the Bases Control Program or the licensee's
administrative controls].
4.0 Verifications and Commitments
As requested by the staff in the notice of availability for this TS
improvement, the licensee has addressed the following plant-specific
verifications and commitments.
4.1 Each licensee should verify that it has, and make a regulatory
commitment to maintain (or make a regulatory commitment to develop and
maintain), contingency plans for obtaining and analyzing highly
radioactive samples of reactor coolant, suppression pool, and
containment atmosphere.
The licensee has [verified that it has or made a regulatory
commitment to develop]
contingency plans for obtaining and analyzing
highly radioactive samples from the RCS, suppression pool, and
containment atmosphere. The licensee has committed to maintain the
contingency plans within its [specified document or
[[Page 66953]]
program]. The licensee has [implemented this commitment or will
implement this commitment by (specified date)].
4.2 Each licensee should verify that it has, and make a regulatory
commitment to maintain (or make a regulatory commitment to develop and
maintain), a capability for classifying fuel damage events at the Alert
level threshold (typically this is 300 µCi/ml dose equivalent
iodine). This capability may utilize the normal sampling system and/or
correlations of radiation readings to radioisotope concentrations in
the reactor coolant.
The licensee has [verified that it has or made a regulatory
commitment to develop]
a capability for classifying fuel damage events
at the Alert level threshold. The licensee has committed to maintain
the capability for the Alert classification within its [specified
document or program]. The licensee has [implemented this commitment or
will implement this commitment by (specified date)].
4.3 Each licensee should verify that it has, and make a regulatory
commitment to maintain (or make a regulatory commitment to develop and
maintain), an I-131 site survey detection capability, including an
ability to assess radioactive iodines released to offsite environs, by
using effluent monitoring systems or portable sampling equipment.
The licensee has [verified that it has or made a regulatory
commitment to develop]
an I-131 site survey detection capability,
including an ability to assess radioactive iodines released to offsite
environs, by using effluent monitoring systems or portable sampling
equipment. The licensee has committed to maintain the capability for
monitoring iodines within its [specified document or program]. The
licensee has [implemented this commitment or will implement this
commitment by (specified date)].
The NRC staff finds that reasonable controls for the implementation
and for subsequent evaluation of proposed changes pertaining to the
above regulatory commitments are provided by the licensee's
administrative processes, including its commitment management program.
Should the licensee choose to incorporate a regulatory commitment into
the emergency plan, final safety analysis report, or other document
with established regulatory controls, the associated regulations would
define the appropriate change-control and reporting requirements. The
staff has determined that the commitments do not warrant the creation
of regulatory requirements, which would require prior NRC approval of
subsequent changes. The NRC staff has agreed that NEI 99-04, Revision
0, ``Guidelines for Managing NRC Commitment Changes,'' provides
reasonable guidance for the control of regulatory commitments made to
the NRC staff. (See Regulatory Issue Summary 2000-17, Managing
Regulatory Commitments Made by Power Reactor Licensees to the NRC
Staff, dated September 21, 2000 [ADAMS Accession Number ML003741774].)
The commitments should be controlled in accordance with the industry
guidance or comparable criteria employed by a specific licensee. The
staff may choose to verify the implementation and maintenance of these
commitments in a future inspection or audit.
5.0 State Consultation
In accordance with the Commission's regulations, the [ ]
State
official was notified of the proposed issuance of the amendments. The
State official had [(1) no comments or (2) the following comments--with
subsequent disposition by the staff].
6.0 Environmental Consideration
The amendments change a requirement with respect to the
installation or use of a facility component located within the
restricted area as defined in 10 CFR part 20 and change surveillance
requirements. The NRC staff has determined that the amendments involve
no significant increase in the amounts and no significant change in the
types of any effluents that may be released offsite, and that there is
no significant increase in individual or cumulative occupational
radiation exposure. The Commission has previously issued a proposed
finding that the amendments involve no significant hazards
consideration, and there has been no public comment on such finding (
FR ). Accordingly, the amendments meet the eligibility criteria for
categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10
CFR 51.22(b) no environmental impact statement or environmental
assessment need be prepared in connection with the issuance of the
amendments.
7.0 Conclusion
The Commission has concluded, based on the considerations discussed
above, that (1) there is reasonable assurance that the health and
safety of the public will not be endangered by operation in the
proposed manner, (2) such activities will be conducted in compliance
with the Commission's regulations, and (3) the issuance of the
amendments will not be inimical to the common defense and security or
to the health and safety of the public.
Proposed No Significant Hazards Consideration Determination
Description of Amendment Request: The proposed amendments delete
requirements from the Technical Specifications (and, as applicable,
other elements of the licensing bases) to maintain a Post Accident
Sampling System [or Station]
(PASS). Licensees were generally required
to implement PASS upgrades as described in NUREG-0737, ``Clarification
of TMI [Three Mile Island]
Action Plan Requirements,'' and Regulatory
Guide 1.97, ``Instrumentation for Light-Water-Cooled Nuclear Power
Plants to Assess Plant and Environs Conditions During and Following an
Accident.'' Implementation of these upgrades was an outcome of the
lessons learned from the accident that occurred at TMI, Unit 2.
Requirements related to PASS were imposed by Order for many facilities
and were added to or included in the technical specifications (TS) for
nuclear power reactors currently licensed to operate. Lessons learned
and improvements implemented over the last 20 years have shown that the
information obtained from PASS can be readily obtained through other
means or is of little use in the assessment and mitigation of accident
conditions.
Basis for proposed no significant hazards consideration
determination: As required by 10 CFR 50.91(a), an analysis of the issue
of no significant hazards consideration is presented below:
Criterion 1--The Proposed Change Does Not Involve a Significant
Increase in the Probability or Consequences of an Accident Previously
Evaluated.
The PASS was originally designed to perform many sampling and
analysis functions. These functions were designed and intended to be
used in post accident situations and were put into place as a result of
the TMI-2 accident. The specific intent of the PASS was to provide a
system that has the capability to obtain and analyze samples of plant
fluids containing potentially high levels of radioactivity, without
exceeding plant personnel radiation exposure limits. Analytical results
of these samples would be used largely for verification purposes in
aiding the plant staff in assessing the extent of core damage and
subsequent offsite radiological dose projections. The system was not
intended to and does not serve a function for preventing
[[Page 66954]]
accidents and its elimination would not affect the probability of
accidents previously evaluated.
In the 20 years since the TMI-2 accident and the consequential
promulgation of post accident sampling requirements, operating
experience has demonstrated that a PASS provides little actual benefit
to post accident mitigation. Past experience has indicated that there
exists in-plant instrumentation and methodologies available in lieu of
a PASS for collecting and assimilating information needed to assess
core damage following an accident. Furthermore, the implementation of
Severe Accident Management Guidance (SAMG) emphasizes accident
management strategies based on in-plant instruments. These strategies
provide guidance to the plant staff for mitigation and recovery from a
severe accident. Based on current severe accident management strategies
and guidelines, it is determined that the PASS provides little benefit
to the plant staff in coping with an accident.
The regulatory requirements for the PASS can be eliminated without
degrading the plant emergency response. The emergency response, in this
sense, refers to the methodologies used in ascertaining the condition
of the reactor core, mitigating the consequences of an accident,
assessing and projecting offsite releases of radioactivity, and
establishing protective action recommendations to be communicated to
offsite authorities. The elimination of the PASS will not prevent an
accident management strategy that meets the initial intent of the post-
TMI-2 accident guidance through the use of the SAMGs, the emergency
plan (EP), the emergency operating procedures (EOP), and site survey
monitoring that support modification of emergency plan protective
action recommendations (PARs).
Therefore, the elimination of PASS requirements from Technical
Specifications (TS) (and other elements of the licensing bases) does
not involve a significant increase in the consequences of any accident
previously evaluated.
Criterion 2--The Proposed Change Does Not Create the Possibility of a
New or Different Kind of Accident from any Previously Evaluated.
The elimination of PASS related requirements will not result in any
failure mode not previously analyzed. The PASS was intended to allow
for verification of the extent of reactor core damage and also to
provide an input to offsite dose projection calculations. The PASS is
not considered an accident precursor, nor does its existence or
elimination have any adverse impact on the pre-accident state of the
reactor core or post accident confinement of radioisotopes within the
containment building.
Therefore, this change does not create the possibility of a new or
different kind of accident from any previously evaluated.
Criterion 3--The Proposed Change Does Not Involve a Significant
Reduction in the Margin of Safety.
The elimination of the PASS, in light of existing plant equipment,
instrumentation, procedures, and programs that provide effective
mitigation of and recovery from reactor accidents, results in a neutral
impact to the margin of safety. Methodologies that are not reliant on
PASS are designed to provide rapid assessment of current reactor core
conditions and the direction of degradation while effectively
responding to the event in order to mitigate the consequences of the
accident. The use of a PASS is redundant and does not provide quick
recognition of core events or rapid response to events in progress. The
intent of the requirements established as a result of the TMI-2
accident can be adequately met without reliance on a PASS.
Therefore, this change does not involve a significant reduction in
the margin of safety.
Based upon the reasoning presented above and the previous
discussion of the amendment request, the requested change does not
involve a significant hazards consideration.
Dated at Rockville, Maryland, this 18th day of December 2001.
For the Nuclear Regulatory Commission.
William D. Beckner,
Chief, Technical Specification Branch, Division of Regulatory
Improvement Programs, Office of Nuclear Reactor Regulation.
[FR Doc. 01-31803 Filed 12-26-01; 8:45 am]
BILLING CODE 7590-01-P
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)