Major Investment Study/Draft Environmental Impact Statement for the Bergen-Passaic Cross County Corridor, Bergen and Passaic Counties, New Jersey
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: June 18, 2001 (Volume 66, Number 117)]
[Notices]
[Page 32865-32867]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr18jn01-152]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
Major Investment Study/Draft Environmental Impact Statement for
the Bergen-Passaic Cross County Corridor, Bergen and Passaic Counties,
New Jersey
AGENCY: Federal Transit Administration (FTA), DOT.
ACTION: Notice of intent to prepare a major investment study/draft
environmental impact statement (MIS/DEIS).
-----------------------------------------------------------------------
SUMMARY: The Federal Transit Administration (FTA) and the New Jersey
Transit Corporation (NJ TRANSIT) intend to prepare a Major Investment
Study/Draft Environmental Impact Statement (MIS/DEIS) to study
transportation access improvements along the Bergen-Passaic Cross
County Corridor (also known as the NYS&W corridor) in Bergen and
Passaic Counties, New Jersey. The MIS/DEIS is being prepared in
accordance with the National Environmental Policy Act of 1969 (NEPA),
as amended, and implemented by the Council on Environmental Quality
(CEQ) regulations (40 CFR parts 1500-1508), the FTA/Federal Highway
Administration's Environmental Impact regulations (23 CFR part 771),
and the FTA/FHWA Statewide Planning/Metropolitan Planning regulations
(23 CFR part 450). This study will also comply with the requirements of
the National Historic Preservation Act of 1966, as amended, section
4(f) of the 1966 U.S. Department of Transportation Act, the 1990 Clean
Air Act Amendments, the Executive Order 12898 on Environmental Justice,
and other applicable rules, regulations, and guidance documents.
The purpose of the Bergen-Passaic Cross County Corridor MIS/DEIS is
to examine solutions for improving mobility in Bergen and Passaic
Counties, New Jersey and to document the social, economic, and
environmental impacts of implementing identified study alternatives.
The MIS/DEIS will identify a preferred alternative that will improve
mobility within that region. The MIS/DEIS will evaluate a Baseline
Alternative and a Build Alternative. The Build Alternative under
consideration was selected as a result of the findings of the West
Shore Region Alternatives Analysis Report (December 1999). The
Alternatives Analysis Report recommended an alternative for advancement
to the MIS/DEIS phase of the project made up of the following
components: West Shore corridor commuter rail service via the
Meadowlands Sports Complex; Northern Branch corridor light rail service
via Hudson Bergen Light Rail Transit (HBLRT); and NYS&W corridor light
rail service via HBLRT. All three of these proposed new rail services
would involve construction of new transportation infrastructure,
including tracks, stations and yards. This MIS/DEIS will examine the
Bergen-Passaic Cross County Corridor (NYS&W) light rail service via
HBLRT.
DATES: Comment Due Date: Written comments on the scope of the MIS/DEIS
should be sent to NJ TRANSIT by August 15, 2001. See ADDRESSES below.
Scoping Meeting: Public scoping meetings for the Bergen-Passaic
Cross County Corridor MIS/DEIS will be held on:
Tuesday, July 10, 2001
3 p.m. to 5 p.m. and 7 p.m. to 9 p.m., Bergen County Administration
Building, Freeholders Room, 5th Floor, 1 Bergen County Plaza,
Hackensack, New Jersey 07601
Tuesday, July 17, 2001
3 p.m. to 5 p.m. and 7 p.m. to 9 p.m., Passaic County Administration
Building, Freeholders Room, Room 223, 401 Grand Street, Paterson, New
Jersey 07505
Registration to speak will begin at 2:30 p.m. and will remain open
until 4:30 for the afternoon session; registration to speak will begin
at 6:30 p.m. and will remain open until 8:30 p.m. for the evening
session. The scoping meeting will conclude at 4:30 p.m. and 8:30 p.m.,
respectively, if there are no remaining registered speakers.
People with special needs should contact Steven Jurow at NJ TRANSIT
at the address below or call the study toll-free information line at 1-
866-658-9874. The buildings are accessible to people with disabilities.
A sign language interpreter will be made available for the hearing
impaired by calling the study toll-free information line at 1-866-658-
9874.
Scoping material will be available at the meetings and may also be
obtained in advance of the meetings by contacting Steven Jurow at the
address below or by calling the study toll-free information line above.
Oral and written comments may be given at the scoping meetings; a
stenographer will record all comments.
ADDRESSES: Written comments on the project scope should be sent to
Steven Jurow, Project Manager, NJ TRANSIT, One Penn Plaza East, Newark,
NJ 07105-2246. The scoping meetings will be held at the locations
identified above.
FOR FURTHER INFORMATION CONTACT: If you wish to be placed on the
mailing list to receive further information as the study develops,
contact Steven Jurow at the above address or call the study toll-free
information line at 1-866-658-9874. For further information, you may
also contact: Mr. Irwin B. Kessman, Director, Office of Planning and
Program Development, Federal Transit Administration, Region II, One
Bowling Green, Room 429, New York, New York, 10004-1415; phone: 212-
668-2170, fax: 212-668-2136.
SUPPLEMENTARY INFORMATION:
I. Scoping
The FTA and NJ TRANSIT invite all interested individuals and
organizations, and federal, state, and local agencies to provide
comments on the scope of the study. During the scoping process,
comments should focus on identifying specific social, economic, or
environmental issues to be evaluated and suggesting alternatives, which
may be less costly or have less environmental impacts, while achieving
the similar transportation objectives. Comments should focus on the
issues and alternatives for analysis and not on a preference for a
particular alternative.
[[Page 32866]]
Scoping materials will be available at the meetings or in advance of
the meetings by contacting Steven Jurow at NJ TRANSIT, as indicated
above. The Bergen-Passaic Cross County Corridor MIS/DEIS will be
closely coordinated with major regional initiatives and studies that
are related to this effort, including:
Secaucus Transfer Station, a NJ TRANSIT project currently
under construction that will create a connection between the existing
Main, Bergen County, and Pascack Valley Lines with the Northeast
Corridor Line, improving access to Midtown Manhattan and other
destinations;
Hudson-Bergen Light Rail Transit (HBLRT), a NJ TRANSIT
project currently under construction that will create a new light rail
line operating from the Vince Lombardi Park-and-Ride to Bayonne. The
initial segment in Jersey City and Bayonne opened in April 2000;
Newark Airport Station/Monorail Extension, a NJ TRANSIT
project currently under construction that will connect the Northeast
Corridor Line and the Newark Airport Monorail;
West Shore Corridor MIS/DEIS, a study by NJ TRANSIT that
will examine the potential benefits, costs, and impacts of alternatives
for improving access in the West Shore study area, including a
potential commuter rail service via the Meadowlands Sports Complex;
Northern Branch Corridor MIS/DEIS, a study by NJ TRANSIT
that will examine the potential benefits, costs, and impacts of
alternatives for improving access in the Northern Branch study area,
including a potential light rail service via the Hudson Bergen Light
Rail;
West Haverstraw Extension Study, a study by Rockland
County and NJ TRANSIT examining the potential to extend the West Shore
Commuter Rail service to West Haverstraw, New York;
Access to the Region's Core Study (ARC), a joint study by
NJ TRANSIT, Port Authority of New York and New Jersey, and the
Metropolitan Transportation Authority (MTA). The ARC study continues to
study access to Midtown Manhattan from points east and west;
Penn Station Access MIS/DEIS, a study by Metro-North to
examine improving access to Penn Station to/from the Metro-North
service area; and
Conrail/CSX/Norfolk Southern Merger, a change in the
ownership of the freight network, dividing the former Conrail holdings
between CSX and Norfolk Southern.
Following the public scoping process, public outreach activities
will include meetings with a Community Liaison Committee (CLC)
established for the study and comprised of community leaders; public
meetings and hearings; distribution of study newsletter(s); and use of
other outreach mechanisms. Every effort will be made to ensure that the
widest possible range of public participants has the opportunity to
attend general public meetings (e.g., scoping meetings and public
hearing(s)) held by NJ TRANSIT to solicit input on the Bergen--Passaic
Cross County Corridor MIS/DEIS. Attendance will be sought through
mailings, notices, advertisements, and press releases.
II. Description of Study Area and Transportation Needs
The study area includes the NYS&W corridor through Ridgefield,
Ridgefield Park, Bogota, Hackensack, Maywood, Rochelle Park, Saddle
Brook, Elmwood Park, Paterson and Hawthorne in New Jersey. The purpose
of the Bergen--Passaic Cross County Corridor MIS/DEIS is to examine
solutions for addressing mobility issues in Bergen and Passaic
Counties, New Jersey, and to identify a preferred alternative that will
improve mobility within that region. The MIS/DEIS will be conducted in
coordination with other major network expansion proposals under study
or construction within the region. The MIS/DEIS will examine and
document the social, economic, and environmental impacts of
implementing identified study alternatives.
Provision of new transportation service in the Bergen--Passaic
Cross County corridor would address:
Commuting to New York City (trans-Hudson), from Bergen and
Passaic Counties;
Inter- and intra-corridor commuting, both to employment
centers within the study corridors, and from the study corridors to
employment locations in other areas of New Jersey; and,
Non-work trips including business, shopping, recreational,
and education to New York City, within the corridor, and to
destinations outside the corridor in New Jersey.
III. Alternatives
The alternatives proposed for evaluation include:
(1) The Baseline Alternative, which includes no-build conditions,
plus any cost-effective transit improvements that can be implemented,
short of the proposed new start alternative. The no-build conditions
involve the current infrastructure of highways, trains, and bus
services, in addition to all ongoing, committed and funded roadway and
transit projects outlined in the State Transportation Improvement
Program (STIP) including projects under construction such as the
Secaucus Transfer Station and the Hudson-Bergen Light Rail Transit
(HBLRT). Transit improvements lower in cost than the proposed new start
alternative were also identified for inclusion in the Baseline
Alternative, including a bus component, from Bergen County to the East
Midtown Manhattan; and a rail component, a new rail station in Saddle
Brook on the Bergen County Line.
(2) The Build Alternative, Bergen--Passaic Cross County Corridor
light rail service via HBLRT. The Build Alternative will involve
construction of new transportation infrastructure, including tracks,
stations and yards. Additional reasonable Build alternatives suggested
during the scoping process, including those involving other modes, may
be considered.
IV. Probable Effects
The FTA and NJ TRANSIT will evaluate all potential changes to the
social, economic, and physical environment, including air quality,
noise and vibration, traffic, parking, transit, pedestrians and freight
rail, energy and potential for conservation, electric and magnetic
fields, safety and security, water quality, wetlands, flooding,
navigable waterways and coastal zones, ecologically sensitive areas,
endangered species, hazardous waste, land acquisition and
displacements, land use, zoning and economic development, consistency
with local plans, historic properties and resources, parkland,
archaeology, aesthetics, community disruption, environmental justice,
construction impacts, and cumulative impacts. Key areas of
environmental concern would be in the areas of potential new
construction (e.g. new stations, new track, etc.). The impacts will be
evaluated both for the construction period and for the long-term period
of operation of each alternative. Measures to mitigate any significant
adverse impacts will be identified.
V. FTA Procedures
The DEIS will be prepared in conjunction with a major investment
study and will document the results of that study, including an
evaluation of the potential social, economic, and environmental impacts
of the alternatives. Upon completion, the MIS/DEIS will be available
for public and agency review and comment. Public hearing(s) will be
held within the study area. On the basis of the MIS/DEIS and
[[Page 32867]]
the public and agency comments received, a locally preferred
alternative will be selected, to be further detailed in the final EIS.
Issued on: June 13, 2001.
Letitia Thompson,
Regional Administrator, TRO-II, Federal Transit Administration.
[FR Doc. 01-15328 Filed 6-15-01; 8:45 am]
BILLING CODE 4910-57-P
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)