Removal of the Lake City Army Ammunition Plant From the Site Decommissioning Management Plan
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: October 9, 2001 (Volume 66, Number 195)]
[Notices]
[Page 51479]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr09oc01-148]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 40-8767; License No. SUC-1380]
Removal of the Lake City Army Ammunition Plant From the Site
Decommissioning Management Plan
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of removal from the site decommissioning management
plan.
-----------------------------------------------------------------------
This notice is to inform the public that the United States Nuclear
Regulatory Commission (NRC) is removing the Lake City Army Ammunition
Plant (LCAAP) from the Site Decommissioning Management Plan (SDMP). The
SDMP is a program, created by the Commission, to ensure that the NRC
focuses special attention on certain sites to ensure timely
decommissioning of those sites. LCAAP is one of the sites included in
the SDMP.
LCAAP is located in Independence, Missouri. The U.S. Department of
the Army (the licensee) is the holder of NRC Materials License SUC-
1380, which covers a number of facilities including LCAAP. LCAAP is a
facility that was used for the production and testing of munitions
containing depleted uranium (DU). LCAAP, in addition to being included
in NRC's SDMP, is also included in the U.S. Environmental Protection
Agency's (EPA's) Superfund Program, the National Contingency Plan.
The licensee recently completed remediation of both the LCAAP 600-
Yard Bullet Catcher and the DU contaminated portion of Building 3A.
Remediation of the remaining DU contaminated areas will not be
completed for a number of years because of both Resource Conservation
and Recovery Act related issues and the continuing use of the LCAAP
firing range. EPA, the Missouri Department of Natural Resources (MDNR),
NRC, and the licensee agreed that DU remediation for the remaining
portions of LCAAP could be regulated under the provisions of
Comprehensive Environmental Response, Compensation, and Liability Act,
the LCAAP Federal Facility Agreement, and Executive Order 12580. Both
EPA and MDNR will provide regulatory oversight of the DU remediation
during this period. NRC Material License SUC-1380 will continue to
cover LCAAP until DU contamination is remediated. Once a determination
is made that the remainder of the DU contamination has been remediated,
NRC will review the documentation supporting that determination. In
addition, NRC may perform a confirmatory survey. Once NRC agrees with
that determination, NRC will remove LCAAP from NRC Materials License
SUC-1380. Based on the agreement between the agencies and successful
remediation of both the LCAAP 600-Yard Bullet Catcher and Building 3A,
NRC has determined that LCAAP no longer requires the special attention
associated with the SDMP. Therefore, LCAAP is being removed from the
SDMP.
Dated at Rockville, Maryland, this 1st day of October 2001.
For the Nuclear Regulatory Commission.
Stewart Brown,
Facilities Decommissioning Section, Decommissioning Branch, Division of
Waste Management, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 01-25187 Filed 10-5-01; 8:45 am]
BILLING CODE 7590-01-P