Energy Northwest; Nuclear Project No. 1 (WNP-1) Environmental Assessment and Finding of No Significant Impact
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: January 30, 2002 (Volume 67, Number 20)]
[Notices]
[Page 4475-4476]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr30ja02-94]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-460]
Energy Northwest; Nuclear Project No. 1 (WNP-1) Environmental
Assessment and Finding of No Significant Impact
The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an extension of the latest construction completion date
specified in Construction Permit No. CPPR-134 issued to Washington
Public Power Supply System (permittee) for the Nuclear Project No. 1
(WNP-1). As part of this proposed action, the staff will update the
permit to reflect an administrative change in the permit holder's name
from the Washington Public Power Supply System to Energy Northwest. The
facility is located at Energy Northwest's site on the Department of
Energy's Hanford Reservation in Benton County, Washington,
approximately eight miles north of Richland, Washington.
Environmental Assessment
Identification of Proposed Action
The proposed action would extend the latest construction completion
date of Construction Permit No. CPPR-134 from June 1, 2001 to June 1,
2011, and update the permit to reflect an administrative change in the
permit holder's name from the Washington Public Power Supply System to
Energy Northwest. The proposed action is in response to Energy
Northwest's request dated April 9, 2001.
The Need for the Proposed Action
The proposed action is needed to grant the licensee the option of
completing construction on WNP-1 in the future. Energy Northwest
requested the extension for WNP-1 because some of its stakeholders
requested that a viability study be conducted on the completion of the
facility. The request was made, in part, because of the increase in the
electrical load in the Pacific Northwest. Until the viability study is
completed and decisions on generating options to meet future load
forecasts are finalized, Energy Northwest would like to maintain
completing WNP-1 as an option.
Environmental Impacts of the Proposed Action
The environmental impacts associated with the construction of the
facility have been previously discussed and evaluated in the Final
Environmental Statement (FES), NUREG-75/012, March 1975, prepared as
part of the NRC staff's review of the construction permit application.
Because of the passage of time from the issuance of the FES, the staff
requested additional information in a June 22, 2001, letter to Energy
Northwest, to determine if the conclusions reached in the March 1975
FES remain valid. Energy Northwest responded to these questions in a
letter dated November 27, 2001.
In its November 27, 2001, response, Energy Northwest addressed the
impact of resumption of construction in the following areas: hstoric
and culturally significant sites, disturbance of land and the Columbia
River bed, socioeconomic impacts, additional cumulative impacts from
other projects in the area, threatened and endangered species, and
National Monuments. Highlights of Energy Northwest's response follow.
Energy Northwest stated that no additional historic or culturally
significant sites have been identified in areas that might be affected
by the resumption of construction activities. Regarding disturbance of
land and the Columbia River bed, Energy Northwest stated that
resumption of construction would not require disturbance of any land
that had not already been disturbed prior to the cessation of
construction in 1983, and no disturbance of the riverbed or shoreline
would be required by the resumption of construction.
Regarding the socioeconomic impacts of WNP-1 construction, Energy
Northwest noted that the population in the area has grown and the
public infrastructure has grown as well. Energy Northwest concludes
that ``[c]ompared to 1975, the estimated socioeconomic impacts of WNP-1
construction would be the same or less.'' Regarding additional
cumulative impacts from other projects in the area, Energy Northwest
noted that it has no plans for other activities that could contribute
to additional cumulative impacts. Energy Northwest did note that the
U.S. Department of Energy has plans to construct a waste vitrification
plant on the Hanford Site to process radioactive wastes presently
stored in tanks. Energy Northwest states that no cumulative impact to
the natural environment is anticipated if both construction of WNP-1
and the vitrification plant were pursued concurrently. It did note that
it is possible that there would be an incremental stress on the local
infrastructure.
Regarding threatened and endangered species, the staff provided two
tables in its June 22, 2001, letter providing a list of species
identified in the 1975 FES that have been listed as threatened or
endangered by the Fish and Wildlife Service and a list of endangered
species
[[Page 4476]]
based on information from the Environmental Protection Agency that may
occur in Benton and Franklin Counties. In its November 27, 2001,
response, Energy Northwest noted that ``[r]esumption of construction
activities at WNP-1 would not be expected to cause adverse impacts to
any listed aquatic or terrestrial species or their habitats. In-river
construction work and all significant earthmoving activities have been
completed. Experience at the neighboring Columbia Generating Station
(having the same intake and outfall design) suggest that water
withdrawals and discharges during construction and operation will not
harm aquatic species.''
Energy Northwest also responded to a question regarding a recent
Presidential Action to create a National Monument in the area near the
WNP-1 construction site. In its November 27, 2001, response, Energy
Northwest described the boundaries of the Hanford Reach National
Monument that was designated by Presidential proclamation on June 9,
2000, noting that the monument generally includes a 1/4 mile corridor
along the river in the vicinity of the WNP-1 site. In addition to the
river corridor, the monument designation includes about 305 square
miles that nearly circumscribe central Hanford. The areas leased by
Energy Northwest for intake structures for WNP-1 and the Columbia
Generating Station are included in the monument. Energy Northwest notes
that construction activities at WNP-1 would not occur on or near the
monument. However, there would be typical maintenance type activities
within the WNP-1 makeup water pumphouse area. Based on Energy
Northwest's November 27, 2001, response, the staff has determined that
the conclusions reached in the March 1975 FES remain valid.
The construction of WNP-1 is approximately 65 percent complete;
therefore, most of the construction impacts discussed in the FES have
already occurred. This action would extend the period of construction
as described in the FES and update the name of the construction permit
holder. It does not involve any different impacts as described and
analyzed in the environmental report and will not involve any different
impacts from those described and analyzed in the environmental report.
The proposed amendment will not allow any work to be performed that is
not already allowed by the existing construction permit. The extension
will grant Energy Northwest more time to complete construction in
accordance with the previously approved construction permit. The change
in the corporate name from the Washington Public Power Supply System to
Energy Northwest is administrative in nature. The legal corporate
status of the construction permit holder has not changed.
Based on the foregoing, the NRC staff has concluded that the
proposed action would have no significant environmental impact. Because
this action would only extend the period of construction activities
described in the FES, it does not involve any different impacts or a
significant change to those impacts described and analyzed in the
environmental report. Consequently, an environmental impact statement
addressing the proposed action is not required.
Alternatives to the Proposed Action
A possible alternative to the proposed action would be to deny the
request. This would result in expiration of the construction permit for
WNP-1. This option would require submittal of another application for
construction in order to allow the permittee to complete construction
of the facility with no significant environmental benefit. The
environmental impacts of the proposed action and alternative action are
similar.
Alternative Use of Resources
This action does not involve the use of resources not previously
considered in the FES for WNP-1.
Agencies and Persons Contacted
In accordance with its stated policy, on January 17, 2002, the
staff consulted with the Washington State Official, Mr. Michael Mills
of the Energy Facility Site Evaluation Council regarding the
environmental impact of the proposed action. The State official had the
following comment: ``Energy Northwest has an active Site Certification
Agreement with the State of Washington that would allow, subject to
amendment, WNP-1 to be constructed and operated. The State also
maintains regulatory oversight of activities at the site.''
Finding of No Significant Impact
On the basis of the environmental assessment, the NRC concludes
that this action will not have a significant effect on the quality of
the human environment. Accordingly, the NRC has determined not to
prepare an environmental impact statement for this action.
For further details with respect to this action, see the licensee's
request for extension dated April 9, 2001, and its response to the
staff's request for additional information dated November 27, 2001.
Documents may be examined, and/or copied for a fee, at the NRC's Public
Document Room, located at One White Flint North, 11555 Rockville Pike
(first floor), Rockville, Maryland. Publicly available records will be
accessible electronically from the ADAMS Public Library component on
the NRC Web site, http://www.nrc.gov
(the Electronic Reading Room).
Dated at Rockville, Maryland this 24th day of January 2002.
For the Nuclear Regulatory Commission.
Marsha K. Gamberoni,
Deputy Director, New Reactor Licensing Project Office, Office of
Nuclear Reactor Regulation.
[FR Doc. 02-2204 Filed 1-29-02; 8:45 am]
BILLING CODE 7590-01-P
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)