Notice of Settlement Agreement and Soliciting Comments
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: August 22, 2003 (Volume 68, Number 163)]
[Notices]
[Page 50764-50765]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr22au03-61]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Settlement Agreement and Soliciting Comments
August 13, 2003.
Take notice that the following settlement agreement has been filed
with the Commission and is available for public inspection.
a. Type of Application: Settlement Agreement.
b. Project No.: 2205-006.
c. Date Filed: July 3, 2003.
d. Applicant: Central Vermont Public Service Corporation.
e. Name of Project: Lamoille River Hydroelectric Project.
f. Location: Located on the Lamoille River, in Franklin, Lamoille,
and Chittenden Counties, Vermont.
g. Filed Pursuant to: Rule 602 of the Commission's Rules of
Practice and Procedure, 18 CFR 385.602.
h. Applicant Contact: Mr. Michael J. Scarzello, Engineer, Central
Vermont Public Service Corp., 77 Grove St., Rutland, VT 05701-3403
(802) 247-5207.
i. FERC Contact: Jack Duckworth at (202) 502-692, or by e-mail at
jack.duckworth@ferc.gov. j. Deadline for Filing Comments: The deadline for filing comments
on the Settlement Agreement is 20 days from the date of this notice.
The deadline for filing reply comments is 30 days from the date of this
notice. All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
Under the Commission's Rules of Practice, intervenors in the
relicensing proceeding filing documents with the Commission must serve
a copy of that document on each person on the official service list for
the project. Further, if an intervenor files comments or documents with
the Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
Comments may be filed electronically via the Internet in lieu of
paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions of the
Commission's Web site (http://www.ferc.gov
) under the ``e-filing''
link.
k. Central Vermont Public Service Corporation filed the
Comprehensive Settlement Agreement on behalf of itself and 5 other
stakeholders. The purpose of the Settlement Agreement is to resolve,
among the signatories, all water resource related issues of Central
Vermont Public Service Corporation's pending Application for New
License for the Lamoille River Hydroelectric Project. The relicensing
issues resolved through the settlement include requirements for
reservoir drawdowns, bypass flows, downstream flows, and fish passage.
Central Vermont Public Service Corporation requests that the Commission
approve the Settlement Agreement and incorporate the proposed project
operation restrictions and requirements in Appendix A of the
[[Page 50765]]
Settlement Agreement into a new license for the project.
l. A copy of the Settlement Agreement is available for review at
the Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov, using the eLibrary
(FERRIS) link. Enter the docket number, excluding the last three digits
in the docket number field to access the document. For assistance,
contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free
at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is also available
for inspection and reproduction at the address in item h above.
Register online at http://www.ferc.gov/esubscribenow.htm
to be notified
via e-mail of new filings and issuances related to this or other
pending projects. For assistance, contact FERC Online Support.
Linda Mitry,
Acting Secretary.
[FR Doc. 03-21502 Filed 8-21-03; 8:45 am]
BILLING CODE 6717-01-P