Intent to Prepare a Draft Environmental Impact Statement for the Ca[ntilde]o Mart[iacute]n Pe[ntilde]a Rehabilitation Project Being Proposed by the Puerto Rico Highway and Transportation Authority
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: July 21, 2003 (Volume 68, Number 139)]
[Notices]
[Page 43090-43092]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr21jy03-64]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Intent to Prepare a Draft Environmental Impact Statement for the
Ca[ntilde]o Mart[iacute]n Pe[ntilde]a Rehabilitation Project Being
Proposed by the Puerto Rico Highway and Transportation Authority
AGENCY: Department of the Army, U.S. Army Corps of Engineers, DOD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: The Puerto Rico Highway and Transportation Authority (PRHTA)
is proposing the rehabilitation of Ca[ntilde]o Mart[iacute]n
Pe[ntilde]a (CMP) in the Municipality of San Juan, Puerto Rico. The
proposal includes the dredging of CMP, the establishment of
conservation strip and greenway on the CMP banks, the construction of a
vehicular, pedestrian, and cyclist transportation corridor parallel to
CMP and its conservation strips, relocation of approximately 1,100
structures, construction of a sanitary sewer and storm water system and
improvements to existing systems, and improvements to the potable water
distribution system. Portions of the project would need a permit under
Section 10 of the Rivers and Harbors Act and Section 404 of the Clean
Water Act permits.
FOR FURTHER INFORMATION CONTACT: Edwin E. Mu[ntilde]iz, (787) 729-6905/
6944, Chief, Antilles Regulatory Section, U.S. Army Corps of Engineers,
400 Fern[aacute]ndez Juncos Avenue, San Juan, PR 00901.
SUPPLEMENTARY INFORMATION: On May 2001, the Planning Division of
Jacksonville, Corps of Engineers (Corps), prepared a report titled
Dredging of
[[Page 43091]]
Ca[ntilde]o Mart[iacute]n Pe[ntilde]a, Project Design Report and
Environmental Impact Statement (EIS). This study was performed under
the Support for Others Program at the request of the Puerto Rico
Department of Natural and Environmental Resources (DNER). This report
included a description of the study area's problems, several dredging
and disposal alternatives, a detailed design for the sponsor's
preferred alternative and a preliminary draft EIS of the recommended
project. A partial list of relevant previous studies performed by
private firms and governmental agencies in the project area is included
in the report. The Project Design Report considered four alternatives
that would vary in the size and shape of the channel. According to this
report, these alternatives were evaluated on the basis of their
construction method and cost, environmental impacts, real estate
requirements, impacts to bridges and utilities, disposal of dredged
material, project operation and maintenance, tidal flow capacity, and
the recreation and navigation potential. These alternatives are as
follows:
Alternative 1: Considered dredging a trapezoidal earth channel with
a width between 150 to 230 feet and 10 feet depth. It would require the
dredging of approximately 550,000 cubic yards of mixed materials from
the CMP. The proposed channel dredging would follow the existing CMP
channel alignment beginning at San Jos[eacute]
Lagoon and extends for
about 11,600 feet to end west of the Luis Mu[ntilde]oz Rivera Avenue
Bridge.
Alternative 2: Considered vertical concrete piles with connecting
concrete panel walls with earth bottom with a width between 150 to 230
feet and 10 feet depth. It would require the dredging of approximately
750,000 cubic yards of mixed materials from the CMP. The proposed
channel dredging would follow the existing CMP channel alignment
beginning at San Jos[eacute]
Lagoon and extends for about 11,600 feet
to end west of the Luis Mu[ntilde]oz Rivera Avenue Bridge.
Alternative 3: Consisted of a very limited channel clean up,
cutting a trapezoidal channel section of 70 feet width by 3.5 feet deep
and constructing a maintenance access road along the eastern half of
CMP. It would require the dredging of about 25,000 cubic yards of mixed
materials from the CMP. The proposed channel dredging would follow the
existing CMP channel alignment beginning at San Jos[eacute]
Lagoon and
extends for about 11,200 feet to end west of the Luis Mu[ntilde]oz
Rivera Avenue Bridge.
Alternative 4: Similar to Alternative 2 with some modifications,
this was the recommended alternative. It consisted of a rectangular
channel with vertical bulkhead system. This project would require the
dredging of approximately 750,000 cubic yards of mixed material along
the existing channel between the bridge of Luis Mu[ntilde]oz Rivera
Avenue and the San Jos[eacute]
Lagoon to provide a variable width of
between 150 and 230 feet, and a depth of 10 feet. A transition from
channel depth of 10 feet to a depth of 6 feet would be provided where
the channel reaches San Jos[eacute]
Lagoon. This alternative requires
replacement of existing bridges at Luis Mu[ntilde]oz Rivera and Barbosa
Avenues.
All of these alternatives would require the relocation of people,
houses, and utilities in the area as well as the acquisition and
relocation of some structures along the channel alignment. The no-
action alternative was also considered in the project Design Report.
The report stated that no-action alternative would lead to further
environmental degradation of the San Juan Bay Estuary, to a complete
blockage of the channel by garbage and debris accumulation and
continued construction of structures on the filled up waterway, and to
continue the social stress associated with frequent flooding,
deteriorated air and water quality, and life threatening health
hazards.
The report also evaluated three alternatives for the disposal of
the dredged material, in terms of their proximity to the project area,
special handling, transportation requirements, environmental benefits,
environmental impacts, and their overall cost. The disposal
alternatives were as follows: (1) Ocean disposal; (2) land disposal;
(3) and in-bay disposal. The study recommended in-bay disposal to fill
two of the largest deep holes located at Los Corozos and San
Jos[eacute]
Lagoons.
The PRHTA is now the lead from the Commonwealth of Puerto Rico for
the proposed rehabilitation of CMP in the Municipality of San Juan, PR.
The firm Moffatt and Nichol Engineers on behalf of the PRHTA prepared
the document titled ``Cano Mart[iacute]in Pena Waterway Improvements''
dated December 2002, where the above-mentioned alternatives presented
in the document Dredging of Cano Mart[iacute]in Pena, Project Design
Report and Environmental Impact Statement were also reviewed. This
document evaluated an additional alternative, it consisted of a
rectangular 10 feet deep channel with realignment and vertical steel
bulkhead system. The proposed channel width at straight and minor bends
sections is 180 feet. The proposed channel alignment follows the
existing CMP channel from the Laguna San Jos[eacute]
to the existing
oxbow, crosses the peninsula and ends west of the Luis Munoz Rivera
Avenue Bridge, a distance of approximately 10,500 feet. The recommended
alternative in this report is the same as the recommended alternative
presented in the report prepared by the Corps in May 2001.
The PRHTA's proposal includes the following elements:
a. Dredging the CMP in the segment between the bridge on Munoz
Rivera Avenue and the San Jos[eacute]
Lagoon. Approximately 750,000
cubic yards of dredge material would be removed to widen the CMP to a
variable width of between 150 and 250 feet, and a depth of 10 feet.
b. Discharge of fill material over open waters and/or wetlands.
c. A conservation strip and greenway at the CMP banks, which will
include mangrove mitigation, trails and recreational areas that will
allow pedestrians to interact with the CMP.
d. Construction of a vehicular, pedestrian and cyclist
transportation corridor parallel to the CMP and its conservation
strips.
e. Relocation of approximately 1,100 structures (family homes and
small businesses) that would be affected by the proposed project.
f. Construction of a sanitary sewer and storm water system to
eliminate the disposal of wastewater into the CMP. Improvements of
existing systems to correct the interconnections between storm water
and sewer systems.
g. Improvements to the potable water distribution system within the
perimeter of influence of the project.
The primary purpose of this project is the environmental
restoration of the eastern portion of CMP, which includes restoring the
water flow between the San Jos[eacute]
Lagoon and the San Juan Bay. It
would also benefit eight low-income communities surrounding the CMP.
However, the proposed action would cause significant impacts, including
individual and cumulative effects to the mangroves-wetlands, and
aquatic resources, human environment, and type of land use (residential
and commercial). The public health or safety could be affected since
the sediments to be dredged in the CMP were determined to be polluted.
Also, the proposed project could impact cultural resources. No
endangered or threatened species are known to exist within the project
area.
Pursuant to Section 10 of the Rivers and Harbors Act the Corps has
regulatory authority over structures and/or work in or affecting
navigable waters of the United States. Under section 404 of the Clean
Water Act, the Corps has
[[Page 43092]]
regulatory authority to permit the discharge of dredged or fill
material into wetlands and other waters of the United States. The
guidelines pursuant to Section 404(b) of the act require that impacts
to the aquatic environment be avoided and minimized to the extent
practicable.
In determining whether to issue a permit, the Corps must consider
the 404(b)(1) guidelines, a public interest review and must also comply
with other requirements including, but not limited to: The Endangered
Species Act; the National Environmental Policy Act; the Coastal Zone
Management Act; the Magnunson-Stevens Fishery Conservation Management
Act; section 401 of the Clean Water Act; and other applicable Federal
laws. Modifying land for new uses may also involve zoning, land use
planning, water management, and other regulatory/planning requirements
at the local, commonwealth, and Federal level.
Issues. The EIS will consider impacts on protected species, health,
conservation, economics, aesthetics, general environmental concerns,
wetlands (and other aquatic resources), historic properties, fish and
wildlife values, flood hazards, floodplain values, land use,
navigation, shoreline erosion and accretion, recreation, water supply
and conservation, water quality, energy needs, safety, food and fiber
production, mineral needs, considerations of property ownership, and,
in general, the needs and welfare of the people, and other issues
identified through scoping, public involvement, and interagency
coordination.
Scooping: The PRHTA has conducted numerous citizen involvement
activities and have held several meetings with representatives of
concerned Federal, State, and local agencies. At this time, there are
no plans for a public scoping meeting, if the Corps holds a public
scoping meeting, it will be announced. In addition Federal, state and
local agencies, as well as interested private organizations and
individuals are strongly encouraged to suggest additional alternatives
for consideration and otherwise submit comments on the scope of the
draft EIS.
Public Involvement: We invite the participation of affected
Federal, state, and local agencies, and other interested private
organizations and individuals by submitting written comments to the
contact information provided in this notice.
Coordination: The proposed action is being coordinated with a
number of Federal, Commonwealth, and local agencies including but not
limited to the following: U.S. Fish and Wildlife Service, National
Marine Fisheries Service, U.S. Environmental Protection Agency, U.S.
Coast Guard, Puerto Rico Department of Natural and Environmental
Resources, Puerto Rico Environmental Quality Board, Puerto Rico
Planning Board, Puerto Rico State Historic Preservation Office, and
other agencies as identified in scoping, public involvement, and agency
coordination.
Other Environmental Review and Consultation: The proposed action
would involve evaluation for compliance with guidelines pursuant to
section 404(b) of the Clean Water Act, public interest review,
application for Water Quality Certification pursuant to section 401 of
the Clean Water Act, and determination of Coastal Zone Management Act
consistency.
Draft EIS Preparation: We estimate that the DEIS will be available
to the public on or about January 15, 2004.
Luz D. Ortiz,
Army Federal Register Liaison Officer.
[FR Doc. 03-18439 Filed 7-11-03; 8:45 am]
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)