Distrigas of Massachusetts LLC; Notice of Application
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: June 10, 2003 (Volume 68, Number 111)]
[Notices]
[Page 34594]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr10jn03-38]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP03-305-000]
Distrigas of Massachusetts LLC; Notice of Application
June 2, 2003.
Take notice that on May 22, 2003, Distrigas of Massachusetts LLC
(DOMAC), One Liberty Square, 10th Floor, Boston, Massachusetts 02109,
filed in Docket No. CP03-305-000, an application pursuant to section
7(c) of the Natural Gas Act and part 157 of the Federal Energy
Regulatory Commission's regulations for authorization to construct,
install, operate, and maintain facilities (DOMAC Connection) at DOMAC's
liquefied natural gas (LNG) plant in Everett, Massachusetts in order to
connect to and deliver regasified LNG into the system of Algonquin Gas
Transmission Company (Algonquin), as more fully described in the
application. This filing is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
at http://www.ferc.gov
using the ``FERRIS'' link. Enter the
docket number excluding the last three digits in the docket number field
to access the document. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov or toll-free at (866)208-3676, or for
TTY, contact (202)502-8659.
DOMAC states that its application is related to Algonquin's pending
HubLine Phase II (or Everett Extension) proceeding, filed on February
5, 2003, in Docket No. CP01-5-003. DOMAC explains that, in the HubLine
Phase II proceeding, Algonquin proposes to construct the Everett
Extension, in part, to provide 50,000 Dth/d of firm transportation
service for DOMAC, and that the DOMAC Connection facilities are
necessary to allow such regasified LNG to be delivered into Algonquin's
Everett Extension. DOMAC states that the DOMAC Connection represents a
new avenue for the delivery of regasified LNG to the New England gas
market, while mitigating take-away constraints on its regasified LNG.
Specifically, DOMAC proposes to construct a new 300-foot send-out
line, odorant system, and metering system, and to reconfigure existing
vaporization equipment to allow higher pressure deliveries into
Algonquin's Everett Extension. The proposed facilities will be built
entirely on the LNG plant's existing property, and will cost
approximately $2.4 million.
DOMAC requests that the Commission issue a final certificate by
December 1, 2003, in order to allow DOMAC time to meet its contractual
obligation to complete the project by June 1, 2005.
Any questions regarding this application should be directed to Mr.
Robert A. Nailling, Vice President and General Counsel, Distrigas of
Massachusetts LLC, One Liberty Square, 10th Floor, Boston,
Massachusetts 02109, or call (617)526-8300 or FAX (617)526-8356.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's rules of practice and procedure (18 CFR 385.214 or
385.211) and the regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission may issue a preliminary determination on non-
environmental issues prior to the completion of its review of the
environmental aspects of the project. This preliminary determination
typically considers such issues as the need for the project and its
economic effect on existing customers of the applicant, on other
pipelines in the area, and on landowners and communities. For example,
the Commission considers the extent to which the applicant may need to
exercise eminent domain to obtain rights-of-way for the proposed
project and balances that against the non-environmental benefits to be
provided by the project. Therefore, if a person has comments on
community and landowner impacts from this proposal, it is important
either to file comments or to intervene as early in the process as
possible.
Protests and interventions may be filed electronically via the
internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site under the ``e-Filing'' link.
The Commission strongly encourages electronic filings.
If the Commission decides to set the application for a formal
hearing before an Administrative Law Judge, the Commission will issue
another notice describing that process. At the end of the Commission's
review process, a final Commission order approving or denying a
certificate will be issued.
Comment Date: June 23, 2003.
Magalie R. Salas,
Secretary.
[FR Doc. 03-14494 Filed 6-9-03; 8:45 am]
BILLING CODE 6717-01-P
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)