Alabama Electric Cooperative, Inc.; Application and Applicant- Prepared EA Accepted for Filing, Soliciting Motions To Intervene and Protests, and Soliciting Comments, and Final Recommendations, Terms and Conditions, and Prescriptions
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: October 5, 2004 (Volume 69, Number 192)]
[Notices]
[Page 59588-59589]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr05oc04-45]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2586-024]
Alabama Electric Cooperative, Inc.; Application and Applicant-
Prepared EA Accepted for Filing, Soliciting Motions To Intervene and
Protests, and Soliciting Comments, and Final Recommendations, Terms and
Conditions, and Prescriptions
September 28, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New major license.
b. Project No.: 2586-024.
c. Date Filed: April 29, 2003.
d. Applicant: Alabama Electric Cooperative, Inc.
e. Name of Project: Conecuh River Project.
f. Location: The Conecuh River Project is located on the Conecuh
River in Andalusia, AL. The project does not affect Federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Scott Wright (Engineering contact) or Mike
Noel (Environmental contact), Alabama Electric Cooperative, Inc., 2027
East Three Notch Street, P.O. Box 550, Andalusia, AL 36420-0550.
i. FERC Contact: Sean Murphy at (202) 502-6145 or
sean.murphy@ferc.gov.
[[Page 59589]]
j. Deadline for filing motions to intervene and protests, comments,
and final recommendations, terms and conditions, and prescriptions: 60
days from the issuance of this notice
All documents (original and eight copies) should be filed with:
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Comments, recommendations, terms and conditions, and prescriptions
may be filed electronically via the Internet in lieu of paper. The
Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(http://www.ferc.gov
) under the ``e-Filing'' link.
k. This application and environmental assessment has been accepted,
and is ready for environmental analysis at this time.
l. The 8.25-megawatt (MW) project consists of two developments the
Gant Dam Development and the Point A Development
The Point ``A'' Development consists of the following existing
facilities: (1) A 2,800-foot-long earthen dam comprised of a gated
concrete spillway section; (2) a 700-acre reservoir at a normal water
surface elevation of 170 feet msl; (3) a powerhouse, integral with the
dam, containing three generating units with a total installed capacity
of 5,200 kW, (4) a 0.39-mile-long, 46-kV transmission line; and (5)
other appurtenances.
The Gantt Development consists of the following existing
facilities: (1) A 1,562-foot-long earthen dam comprised of a gated
concrete spillway section; (2) a 2,767-acre reservoir at a normal water
surface elevation of 198 feet msl; (3) a powerhouse, integral with the
dam, containing two generating units with a total installed capacity of
3,050 kW, and (4) other appurtenances.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov
using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For assistance,
contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free
at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is also available
for inspection and reproduction at the address in item h above.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at: http://www.ferc.gov/docs-filing/
esubscription.asp
to be notified via e-mail of new filings
and issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. The tentative schedule for processing the application follows:
------------------------------------------------------------------------
Milestone Date
------------------------------------------------------------------------
Deadline for Agency Recommendations....... November 1, 2004
Deadline for Reply Comments............... December 1, 2004
Issuance of EA............................ January 2005
Public Comments on EA due................. February 2005
Ready for Commission Decision on the March 2005
Application.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 45 days from the issuance date of this notice.
Magalie R. Salas,
Secretary.
[FR Doc. E4-2482 Filed 10-4-04; 8:45 am]
BILLING CODE 6717-01-P