Jump to main content.


Preventing Undue Discrimination and Preference in Transmission Service

Note: EPA no longer updates this information, but it may be useful as a reference or resource.


 [Federal Register: June 6, 2006 (Volume 71, Number 108)]
[Proposed Rules]
[Page 32685-32734]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr06jn06-20]
 
[[pp. 32685-32734]]
Preventing Undue Discrimination and Preference in Transmission 
Service

[[Continued from page 32684]]

[[Page 32685]]

that the transmission provider produce and examine additional powerflow 
cases or make other process changes. In order to determine the number 
of hours that the requested firm transmission capacity is unavailable, 
the transmission provider may need to model varying load conditions, 
generation and transmission planned outages, and time-contingent or 
condition-contingent generation dispatches. Generally, the greater the 
number of conditions studied, the lower the risk to the transmission 
provider of an inaccurate estimate of conditional curtailment hours. We 
recognize that there are limits to the accuracy of any prediction of 
hours of curtailment, no matter how detailed the system study.
    328. There are a number of ways for a transmission provider to 
determine the number of hours in a year when firm service is 
unavailable, i.e., the conditional curtailment hours. One method 
involves scaling down the powerflow base case. Using this method, the 
transmission provider could scale down the load and generation in the 
base case until the entire conditional firm request is available on the 
studied flowgate. For example, a base case might need to be scaled down 
to 95 percent of the summer peak demand in order to accommodate the 
conditional firm request as firm point-to-point service. The 
transmission provider would then calculate the number of hours the 
seasonal load is forecast to be 95 percent or higher to come up with 
the number of seasonal hours of curtailment for the conditional firm 
customer.
    329. Another method involves an inventory of generation and demand 
shift factors. Using this method, the transmission provider could 
determine conditional curtailment hours by adding up all the 
outstanding generation and load shift factors on the relevant flowgate. 
Once the transmission provider determines the load shift factor on the 
flowgate, it can calculate the reduction needed in regional demand to 
accommodate the conditional firm request by comparing the impact of the 
request on the power flows. The demand reduction would not necessarily 
correspond perfectly with the requested amount of service. For 
instance, a 200 MW reduction might be required to accommodate a 100 MW 
conditional firm request. Once the transmission provider determines a 
reduced load level that would accommodate the conditional firm request, 
the transmission provider would examine load forecasts to calculate the 
number of hours the load is expected to exceed this reduced load level. 
This alternative method of calculating conditional curtailment hours 
might be more burdensome than scaling down the powerflow base case 
because it requires additional data collection and analysis.
    330. Both of these methods rely on average system conditions and do 
not take into account extreme weather years or unexpected outages. 
Thus, the methods would provide an optimistic view of bulk power 
facility availability. These methods can be used to determine the 
portion of time (hours) that transmission capability will most likely 
be available and give general information on when (seasons, months) 
firm service is available.
    331. We seek comment on the most appropriate method of modeling the 
transmission system to determine the number of conditional curtailment 
hours. We also recognize that additional studies may cause additional 
costs. We seek comment on methods of ensuring recovery of these 
additional costs.
    332. We also acknowledge that provision of conditional firm service 
may require some modification to current transaction tracking 
procedures in use by the industry and require development of additional 
mechanisms. Today, transmission providers track transactions with 
curtailment priorities so that when congestion occurs transactions are 
curtailed consistent with OATT requirements, i.e., non-firm uses are 
cut before firm uses and short-term transactions are cut before longer-
term transactions. In order to implement the conditional firm service, 
transmission providers would need to determine in advance of scheduling 
deadlines whether the service should be tracked as a long-term firm use 
or to reflect the use of the conditional curtailment hours.\306\ If the 
service is treated as firm during a certain period, the transaction 
would not be cut before other firm uses. The transmission provider 
would have to perform a calculus, taking into account forecast load and 
transmission and generation availability, to determine the need to cut 
the conditional firm transaction in the next period prior to scheduling 
the transaction as conditional firm. While we do not view this as an 
insurmountable problem, we note that the decision to curtail a 
conditional firm transaction prior to other firm uses simply cannot be 
made in real time. We also note that the transmission provider would 
need to develop a mechanism to track the number of annual conditional 
curtailment hours in each service agreement and its annual or monthly 
use of those hours. Such a tracking mechanism would ensure that the 
transmission provider did not exceed the annual or monthly cap on 
conditional curtailment hours in any particular service agreement.
---------------------------------------------------------------------------

    \306\ We propose that during conditional curtailment hours, the 
transaction would be tagged with the network non-firm tag (currently 
used for secondary network service).
---------------------------------------------------------------------------

2. Hourly Firm Service
    333. The pro forma OATT contains a one-day minimum term for firm 
point-to-point service. In Order No. 888, the Commission chose a one-
day minimum over a one-hour minimum because of concerns expressed by 
commenters.\307\ There, commenters argued that comparability would not 
be achieved if some point-to-point customers were permitted to take 
service for one hour and receive the same priority as native load and 
other long-term customers that have to pay the fixed cost of the 
transmission system every hour of the year. They also expressed concern 
that a one-hour minimum term for firm point-to-point service (hourly 
firm) would promote selective use of the transmission system, impair 
the ability of a utility to plan its system, and adversely affect 
longer term transactions. Finally, some expressed concern that a one-
hour firm service may encourage speculative requests for service during 
the system peak day (a practice known as ``cream skimming'').
---------------------------------------------------------------------------

    \307\ Order No. 888 at 31,752.
---------------------------------------------------------------------------

    334. In the NOI, the Commission noted that several public utility 
transmission providers have individually filed for and received 
Commission authorization to modify their OATTs to provide hourly firm 
point-to-point service.\308\ In the NOI, the Commission sought comment 
on whether the concerns expressed in Order No. 888 remain valid, and 
whether hourly firm service should now be required. The Commission also 
asked whether hourly firm requests should be batched to allow the 
transmission provider to evaluate them as if they were a single 
request, and whether scheduling timelines for firm and non-firm hourly 
transmission service should differ.
---------------------------------------------------------------------------

    \308\ The NOI cited Entergy Services, Inc., 85 FERC 61,163 
(1998), order on reh'g, 91 FERC 61,153 (2000) and El Paso Electric 
Co., Docket No. ER04-567-000 (Apr. 9, 2004) (unpublished letter order).
---------------------------------------------------------------------------

Comments
    335. Some commenters support requiring transmission providers to

[[Page 32686]]

adopt hourly firm service.\309\ Alberta Intervenors and TransAlta argue 
that hourly firm service encourages trade and market liquidity. 
Regarding the concerns cited in Order No. 888, EPSA argues that, as a 
practical matter, daily firm service already receives an equal priority 
to native load and other long-term customers, and none of the concerns 
expressed in Order No. 888 have materialized. ``Cream skimming'' should 
not be a problem, EPSA continues, because firm transmission 
reservations are not cost-free, and transmission customers are unlikely 
to commit financial resources for speculative purposes. Constellation 
argues that there should be no concern that comparability will be 
eroded because hourly firm service provides additional flexibility to 
the competitive markets. PPL argues that in non-ISO/RTO regions like 
the western United States, hourly firm service could help to maximize 
the use of existing transmission facilities, increase efficiencies in 
wholesale markets, and allow customers to purchase only the amount of 
firm transmission service that they need.
---------------------------------------------------------------------------

    \309\ E.g., Alberta Intervenors, Alcoa, Calpine, Constellation, 
EPSA, HQ Energy, PPL, and TransAlta.
---------------------------------------------------------------------------

    336. Some commenters offer qualified support for hourly firm 
service.\310\ For example, South Carolina E&G states that before the 
Commission requires hourly firm service, it should obtain empirical 
market information on transmission providers' ability to provide such 
service. In its reply comments, Powerex explains that there is a 
potential for a detrimental effect if a transmission provider is not 
able to accurately determine its ATC, and before making hourly firm 
service mandatory, the Commission should ensure that the rights of 
long-term firm customers will not be negatively affected.
---------------------------------------------------------------------------

    \310\ E.g., APPA, Northwestern, Powerex, Public Power Council, 
Salt River, and South Carolina E&G.
---------------------------------------------------------------------------

    337. Among commenters who oppose requiring the adoption of hourly 
firm service,\311\ many repeat arguments that appeared in Order No. 
888. For example, several commenters express concern that hourly firm 
service will lead to ``cream skimming,'' result in unfairness to 
longer-term firm transmission customers who would have to be curtailed 
pro rata along with customers who have only made hourly firm 
commitments, or create inefficiencies by having a higher reservation 
priority than subsequently submitted load-based services such as 
secondary network service.\312\ But other commenters who oppose 
requiring hourly firm service state that the concerns expressed in 
Order No. 888 may no longer be a major problem, and may be addressed by 
allowing hourly firm service to be pre-empted by longer term firm 
service requests.\313\
---------------------------------------------------------------------------

    \311\ E.g., Ameren, APS, Duke, EEI, KCP&L, LG&E, LPPC, 
MidAmerican, NRECA, Progress Energy, Snohomish, Southern, TAPS, TVA, 
TDU Systems, and WAPA.
    \312\ E.g., LG&E, Progress Energy, Southern, and TAPS.
    \313\ E.g., EEI and WAPA.
---------------------------------------------------------------------------

    338. TVA argues that reservations for hourly firm service would 
nearly always end up being bumped by requests for longer service and as 
such would waste valuable time and increase administrative costs with 
no real benefit.
Processing
    339. On the issue of whether a transmission customer should be 
permitted to batch requests for service, those in favor generally state 
that batching allows for greater efficiencies.\314\ For example, 
Bonneville states that batching in the hourly market would decrease the 
response time for all requests in the hourly queue. Salt River states 
that a potential customer should be able to submit a batch of requests 
(e.g., a block of hours) that is useful in shaping the service to its 
load-serving needs. Snohomish states that in the day-ahead schedule 
submittals, batching of hourly firm transmission requests for 
evaluation as a single request should be permitted, but for periods 
prior to day-ahead, batching of hourly requests should not be allowed 
due to the potential for ``cream skimming.''
---------------------------------------------------------------------------

    \314\ E.g., Alberta Intervenors, Bonneville, Constellation, 
EPSA, and South Carolina E&G.
---------------------------------------------------------------------------

    340. Among those opposed to or expressing reservations regarding 
batching, Ameren and EEI argue that transmission providers already have 
the ability to process multiple requests from the same party, but they 
caution that batching requests for simultaneous modeling purposes 
(e.g., transmission from points A to B and B to A simultaneously) would 
be difficult to implement. WAPA states that, in its experience, the 
majority of hourly firm transmission requests must be uniquely 
identified and evaluated for potential conflicts with longer-term firm 
transmission requests.
Scheduling
    341. The pro forma OATT currently requires that schedules for firm 
and non-firm service be submitted on different timelines. Schedules for 
hourly non-firm point-to-point service must be submitted to the 
transmission provider no later than 2 p.m. the day before service is to 
commence.\315\ For all firm services, schedules must be submitted to 
the transmission provider no later than 10 a.m. the day before service 
is to commence.\316\
---------------------------------------------------------------------------

    \315\ See pro forma OATT section 14.6 (also allowing schedules to be 
submitted by a reasonable time that is generally accepted in the region).
    \316\ See pro forma OATT section 13.8 (also allowing schedules to be 
submitted by a reasonable time that is generally accepted in the region).
---------------------------------------------------------------------------

    342. Some commenters argue that firm and non-firm hourly services 
should be subject to the same scheduling timeline.\317\ To do 
otherwise, Snohomish argues, would be administratively burdensome and 
without benefit to the transmission provider or transmission customer. 
Those arguing for different scheduling timelines generally argue that 
the scheduling time-frames for firm and non-firm transmission service 
should remain different, at least on a pre-schedule or day-ahead basis, 
because the transmission provider must know the full extent of firm 
utilization before non-firm offerings can be determined.\318\
---------------------------------------------------------------------------

    \317\ E.g., Ameren, Constellation, PNM-TNMP, Powerex, Salt 
River, Snohomish, and South Carolina E&G.
    \318\ E.g., Ameren, Northwestern, and Southern.
---------------------------------------------------------------------------

Discussion
    343. The Commission proposes to add point-to-point hourly firm 
service to the pro forma OATT because it will eliminate a barrier to 
the development of markets and thereby decrease opportunities for undue 
discrimination. The terms of service we propose will ensure that hourly 
firm customers are offered service in a manner consistent with 
comparability principles, and pay their fair share of system costs. We 
conclude that hoarding and speculation should not be a major concern 
because requests for hourly firm service are subject to preemption by 
longer-term requests for service. We also conclude that the provision 
of hourly firm should have no effect on investment in the grid because 
a transmission provider does not plan its system to meet hourly firm, 
or any other short-term firm, transmission requests. In addition, the 
expected effect of hourly firm on long-term transactions is no 
different than the effect of other short-term firm services. For 
example, though commenters are correct that hourly firm will be 
curtailed pro rata with longer term firm point-to-point service, this 
is already true of daily firm point-to-point service. As noted in the 
NOI, many transmission providers already offer this service and there 
appear to be no technical impediments to offering it, nor have 
customers on these systems

[[Page 32687]]

expressed any concern about the effect of hourly firm on long-term firm 
services or curtailments. Therefore, we conclude that the concerns 
expressed in Order No. 888 regarding unduly discriminatory effects of 
hourly firm service have proven unfounded, and we propose that hourly 
firm service be a required offering in the pro forma OATT.
    344. As for the pricing of hourly firm service, consistent with 
Commission precedent, we propose to use the ``IES Method'' and apply 
different pricing for hourly firm service based on whether the service 
is taken during peak or off-peak hours.\319\ Pricing for hourly firm 
service during peak periods would be based on 4,160 hours annually of 
peak usage over 52, 5-day weeks of 16-hour days (52 x 5 x 16 = 4,160), 
rather than all 8760 hours of the year. In other words, the rate is 
derived from the hours during which the facilities are likely to be 
used, rather than the total hours in the year. It is premised on the 
assumption that a customer using the transmission system for the 16 
peak hours of the day should pay the same contribution to fixed costs 
as a customer who has reserved capacity on a daily basis.\320\ But 
because hourly service is unlikely to be taken only during peak hours, 
we propose to allow pricing for hourly firm service for off-peak hours 
based on 8,760 hours of usage.\321\ This is appropriate because 
customers using short-term service during off-peak hours do not 
constrict the system during the peak period, and should pay less than 
what they pay during the peak period.\322\ To ensure that hourly 
customers do not pay more than their fair share of fixed costs, 
consistent with the pricing principles set forth in Order No. 888, the 
total charge in any day for hourly service cannot exceed the stated 
daily rate multiplied by the maximum hourly capacity reservation during 
such day.\323\ We conclude that using the IES Method to price hourly 
firm service at a higher rate during peak periods will ensure that 
hourly firm customers pay a fair share of the costs of the transmission 
system and, as a result, mitigate ``cream-skimming'' concerns.
---------------------------------------------------------------------------

    \319\ The Method is named for a proceeding in which peak and 
off-peak pricing was applied to hourly non-firm transmission 
service. IES Utilities, Inc., 81 FERC ] 61,187 at 61,833-34 (1997), 
reh'g denied, 82 FERC ] 61,089, aff'd on other grounds sub nom, 
Wisconsin Public Power Inc., v. FERC, 1999 U.S. App. LEXIS 3998 
(Feb. 23, 1999) (unpublished opinion); see New York State Electric & 
Gas Corp., 92 FERC ] 61,169 at 61,593-94(2000) (approving 
application of the IES Method for time-differentiated hourly non-
firm rate design), order on reh'g, 100 FERC ] 61,021 (2002).
    \320\ Peak period pricing is referred to as the ``Appalachian 
Method'' or ``AEP Method,'' and takes its name from the proceeding 
in which it originated. Appalachian Power Co., 30 FERC ] 61,296 
(1987). The Appalachian Method is consistent with the premise that 
firm transmission service be priced based on the system's peak 
periods of usage. See Entergy Services, Inc. 85 FERC ] 61,163, at 
61,645 (1998) (approving application of the method for firm service on an 
hourly basis during peak hours), reh'g denied, 91 FERC ] 61,153 (2000).
    \321\ See IES Utilities, Inc., 81 FERC at 61,833-34 (approving 
use of an 8,760 hour year to calculate rates for non-firm service on 
an hourly basis during off-peak hours); Entergy Services, Inc., 85 
FERC at 61,645 (approving use of an 8,760 hour year to calculate 
rates for firm service on an hourly basis during off-peak hours).
    \322\ Appalachian Power Co., 39 FERC at 61,965; see American 
Electric Power Service Corp., 88 FERC ] 61,141 at 61,453-54 (1999).
    \323\ And, in turn, the total demand charge in any week pursuant 
to a reservation for hourly or daily service cannot exceed the 
weekly rate multiplied by the maximum hourly capacity reservation in 
any hour during such week. See pro forma OATT schedules 7 and 8; see 
also Entergy Services, Inc., 85 FERC ]61,163 at 61,645 (1998) 
(applying these principles to a proposal for firm service on an 
hourly basis), reh'g denied, 91 FERC ]61,153 (2000).
---------------------------------------------------------------------------

    345. As for allowing transmission customers to batch requests for 
service, we conclude that allowing such batching creates administrative 
efficiencies for the transmission customer and transmission provider 
alike. Therefore, we propose allowing transmission customers to batch 
requests and schedules for hourly firm service that will be provided 
within the same day.
    346. The Commission also concludes that the current scheduling 
practices can accommodate the scheduling of hourly firm transmission 
service. To require that both firm and non-firm hourly services be 
scheduled at the same time would require that the existing procedures 
be revised, with no discernible benefit to the transmission customer or 
transmission provider. Even with the addition of this new service, it 
remains reasonable to require that the transmission provider have all 
firm schedules at the same time, and in advance of the deadline for 
non-firm schedules. Therefore, we propose that schedules for firm 
hourly service, like all other firm schedules, will be due by 10 a.m. 
the day before the service is to commence.
    347. Finally, we propose that, consistent with other durations of 
service, the confirmation period for hourly firm service specified in 
section 13.2 of the pro forma OATT will allow longer-term requests for 
service to preempt shorter hourly firm requests for service until one 
hour before the commencement of hourly firm service.
3. Rollover Rights
    348. Section 2.2 of the pro forma OATT allows existing firm 
transmission service customers--wholesale requirements and 
transmission-only customers with contracts of one year or more--the 
right to continue to take transmission service from the transmission 
provider when the customer's contract expires, rolls over or is 
renewed. The pro forma OATT provides that the transmission reservation 
priority is independent of whether the existing customer continues to 
purchase capacity and energy from the transmission provider or elects 
to purchase capacity from another supplier. This transmission 
reservation priority for existing firm transmission service customers, 
which is also referred to as a right of first refusal or a rollover 
right, is an ongoing right that may be exercised at the end of all firm 
contract terms of one year or longer. A transmission customer must give 
notice of whether it will exercise its right of first refusal 60 days 
before the expiration of its service agreement.
    349. In Order No. 888, the Commission provided that, if a 
transmission customer subject to the rollover right selects a new power 
supplier that substantially changes the location or direction of its 
power flows, the customer's right to continue taking service from the 
transmission provider may be affected by transmission constraints 
associated with the change.\324\ The Commission also provided that a 
transmission provider may reserve existing capacity for retail native 
load and network load growth reasonably forecasted within the 
transmission provider's current planning horizon, but that any capacity 
so reserved must be posted on the transmission provider's OASIS and 
made available to others until the capacity is needed for the 
anticipated network or retail native load use.\325\ The Commission also 
has held that a transmission provider may restrict a right of first 
refusal based on pre-existing contracts that commence in the future if 
the transmission provider knows at the time of the execution of the 
original service agreement that ATC used to serve a customer will be 
available for only a particular time period, after which time it is 
already committed to another transmission customer under a previously 
confirmed transmission request.\326\ Once a

[[Page 32688]]

transmission provider evaluates the impact on its system of serving a 
long-term firm transmission customer and grants the transmission 
customer existing capacity, the transmission provider must plan and 
operate its system with the expectation that it will continue to 
provide service to the transmission customer should the transmission 
customer exercise the right of first refusal. If constraints arise 
after a transmission provider enters into a long-term agreement with 
the transmission customer (and that agreement does not contain an 
allowed restriction on the transmission customer's right of first 
refusal), the obligation is on the transmission provider to determine 
whether or not to build additional facilities to accommodate new 
transmission customers.\327\ A transmission provider is obligated to 
curtail service pursuant to its OATT or expand its system when its 
system becomes constrained such that it cannot satisfy existing 
transmission customers, including the exercise of their rollover 
rights, because it should have planned and operated its system with the 
expectation that each long-term firm transmission customer will 
exercise its rollover rights.\328\
---------------------------------------------------------------------------

    \324\ Order No. 888 at 31,665 n.176.
    \325\ Id. at 31,694.
    \326\ E.g., Southwest Power Pool, Inc., 109 FERC ] 61,041 at P 6 (2004).
    \327\ Id. at P 9.
    \328\ Id.
---------------------------------------------------------------------------

    350. If a transmission provider's transmission system cannot 
accommodate all of the requests for transmission service at the end of 
the contract term, the existing long-term transmission customer must 
agree to match the rate offered by the potential customer, up to the 
transmission provider's maximum rate, and to accept a contract term at 
least as long as that offered by the potential customer. However, a 
competitor's offer does not have to be ``substantially similar in all 
respects'' to the existing transmission customer's.\329\
---------------------------------------------------------------------------

    \329\ Idaho Power Co. v. FERC, 312 F.3d 454, 462 (D.C. Cir. 2002).
---------------------------------------------------------------------------

The NOI
    351. In the NOI, the Commission sought comment on whether 
transmission providers have hindered transmission customers under pre-
Order No. 888 agreements from rolling over their contracts that allow 
purchase of capacity and energy from another supplier. The Commission 
also asked whether the language in section 2.2 of the pro forma OATT 
needs to be reformed to ensure that rollover rights are provided when 
transmission customers are seeking access to alternative supply 
sources, or whether the issue was an enforcement matter. The Commission 
sought comment on whether the rollover right policy determinations made 
subsequent to Order No. 888 should be included in the pro forma OATT. 
The Commission inquired whether there were other problems with section 
2.2, either as written or as implemented by transmission providers, 
that need to be addressed. The Commission also asked whether potential 
transmission customers are denied transmission access by the exercise 
of rollover rights. Finally, the Commission asked whether it should 
reconsider the concept of rollover rights and whether the one-year 
service with rollover rights is consistent with the need to create 
incentives for transmission investment or should a longer minimum term 
of service be adopted to qualify for rollover rights.\330\
---------------------------------------------------------------------------

    \330\ NOI at P 18.
---------------------------------------------------------------------------

Comments
    352. Many transmission providers and APPA argue that, because a 
transmission provider may not know until 60 days prior to termination 
whether a contract would be renewed, rollover rights in contracts as 
short as one year inhibit the ability of transmission providers to plan 
their systems.\331\ Transmission providers also argue that the right of 
first refusal results in the denial of transmission that leads to an 
inefficient use of transmission capacity.\332\ They explain that the 
transmission provider must hold back capacity from the market for 
existing transmission customers that have a right of first refusal but 
that have not yet indicated whether they intend to exercise it. By the 
time the termination notice is given, other transmission customers that 
may have wanted to reserve the newly freed capacity have been turned 
away and have made other arrangements. They assert that the result is 
an inefficient use of capacity. In addition, these transmission 
providers argue that the 60-day notice provision does not allow them 
adequate time to re-market any capacity when it is freed-up by the 
terminating customer. Further, certain transmission providers argue 
that the right of first refusal unfairly gives transmission customers a 
valuable ``free call option'' on transmission capacity without any 
obligation to take the capacity at the end of the contract or to 
compensate the transmission provider for the value of the option.\333\ 
To avoid these problems, many transmission providers suggest that the 
rollover right should apply to firm transmission contracts with minimum 
terms of between two and ten years.\334\ In addition, these commenters 
suggest that, if the Commission lengthens the term of the firm 
contracts eligible for the right of first refusal, the 60-day renewal 
provision also should be extended.
---------------------------------------------------------------------------

    \331\ E.g., APPA, Bonneville, Duke, LPPC, Nevada Companies, 
Progress, and Salt River.
    \332\ E.g., Ameren, Duke, EEI, North Carolina Commission, Santa 
Clara, and South Carolina E&G.
    \333\ E.g., Ameren, Entergy, and Nevada Companies.
    \334\ E.g., APPA, Bonneville, Cinergy, LDWP, MidAmerican, Nevada 
Companies, Progress, Santee Cooper, South Carolina E&G, and Southern.
---------------------------------------------------------------------------

    353. Certain transmission customers argue that the Commission 
should retain the right of first refusal in its present form, or change 
it only after the Commission requires regional planning or other events 
occur.\335\ Transmission customers stress the need for the rollover 
rule as a means to ensure long-term service. According to 
Constellation, transmission customers subject to rollover rights are 
not temporary customers but are long-term customers that happen to take 
their service under year-to-year agreements. Likewise, EPSA asserts 
that rollover rights are important in planning for the long-term needs 
of loads and generation located on the grid and that ``the ability to 
roll over a firm transportation contract (by matching the contract term 
and the rate of competing shippers) is the only way that market 
participants can ensure that their needs will be met.''
---------------------------------------------------------------------------

    \335\ E.g., AMP-Ohio, Calpine, Constellation, and EPSA.
---------------------------------------------------------------------------

    354. Numerous commenters address the impact of native load growth 
on the right of first refusal rule. As previously indicated, the 
Commission permits transmission providers to restrict a firm 
transmission customer's right of first refusal based on the 
transmission provider's reasonable projections of native load growth. 
Several commenters argue, however, that the Commission has not provided 
adequate guidance as to the information a transmission provider must 
submit to demonstrate native load growth.\336\ Further, commenters 
argue that the Commission should allow transmission providers a means 
to update their native load data to address any load growth that was 
not anticipated at the time of the original contract. In addition, some 
commenters argue that the Commission's rejection of native load growth 
projections in prior cases, and the provision for pro rata curtailment 
of service in the event of capacity shortfalls due to the exercise of a 
right of first refusal, fail to respect the native load preference 
adopted in Order No. 888, as well as in section 217 of the FPA as added 
by section 1233 of EPAct

[[Page 32689]]

2005. They argue that new section 217 of the FPA reverses Commission 
precedent that limits the ability of transmission providers to recall 
capacity for native load once it is subject to a right of first refusal.
---------------------------------------------------------------------------

    \336\ E.g., Duke, EEI, Entergy, Nevada Companies, Progress 
Energy, Santee Cooper, and Salt River.
---------------------------------------------------------------------------

Discussion
    355. The comments filed in response to the NOI demonstrate a need 
to retain, but revise, the right of first refusal provision in the pro 
forma OATT. The Commission proposes to revise the right of first 
refusal provision in the pro forma OATT to apply to wholesale 
requirements and transmission-only contracts that have a minimum term 
of five years, rather than the current minimum term of one year. In 
addition, the Commission proposes that a transmission customer under a 
rollover agreement must provide notice of whether or not it will 
exercise its right of first refusal no less than one year prior to the 
expiration date of the transmission service agreement. We agree with 
APPA that these changes strike an appropriate balance between providing 
customers meaningful rollover rights and encouraging long-term 
contracting, new investment and long-term planning. Finally, if the 
existing customer seeks to exercise its rollover right and there is 
insufficient transmission capacity on the system at the end of the 
contract term to accommodate all of the requests for transmission 
service, the existing customer would have to agree to accept a contract 
term at least equal to a competing request by any new customer or five 
years, whichever is longer, and to pay the current just and reasonable 
rate, as approved by the Commission, for such service.
    356. The Commission's proposal is consistent with the transmission 
customers' comments that the right of first refusal should be designed 
to ensure long-term service. Extending the minimum term of the right of 
first refusal agreements to five years will encourage long-term use of 
the grid. In addition, the one-year prior notice requirement should 
allow adequate time for transmission providers to re-market unused 
capacity that may result from a transmission customer choosing not to 
roll over a service agreement. The one-year notice provision also 
should limit the instances when the transmission provider must turn 
away a transmission request only to find out that it could accommodate 
the request after the transmission customer elected not to roll over. 
These changes should result in a more efficient use of the transmission 
grid.
    357. If we adopt the proposed minimum five year/one year right of 
first refusal provision in the pro forma OATT, we propose to allow this 
provision to become effective upon Commission acceptance of the 
transmission provider's coordinated and regional planning process set 
forth in Attachment K of its OATTs. Thus, all new transmission service 
agreements executed after the effective date of Attachment K will be 
subject to the five year/one year right of first refusal rule. The 
Commission proposes that transmission service agreements subject to a 
right of first refusal entered into prior to the effective date of 
revised section 2.2, unless terminated, will become subject to the five 
year/one year right of first refusal rule on the first rollover date 
after the effective date of revised section 2.2.
    358. Our existing policy allows the transmission provider to limit 
a transmission customer's right of first refusal by reserving capacity 
to accommodate reasonably forecasted and verifiable native and network 
load growth at the time the initial service agreement is executed. Many 
transmission providers argue that this right should be extended to 
allow the transmission provider to limit the right of first refusal 
each time the right of first refusal is exercised, not only at the time 
the initial service agreement is executed. We believe that our proposal 
to extend the term of the right of first refusal from one to five years 
should address, in many respects, the concern of transmission providers 
that the existing right of first refusal is unfair to native load 
customers. Under this proposal, a right of first refusal will no longer 
be granted to users of the grid on an annual basis, but rather only to 
those making longer-term commitments to the grid, as do native load 
customers. In addition, while we expect a transmission provider to be 
continually updating its forecast for native load growth and applying 
this updated projection to new requests for service, applying this to 
contracts at rollover may require an additional change to the right of 
first refusal process. Specifically, the transmission provider would 
have to compete for the capacity rather than reclaim it through its 
rights to reserve capacity for native load growth. We seek comment on 
whether this change would be appropriate. Further, while we have 
addressed requests to limit the right of first refusal on the basis of 
native load growth on a case-by-case basis, we recognize that this 
approach has not yet resulted in a clear and transparent method for 
demonstrating forecasted native load growth. Accordingly, we seek 
comment on whether there is a sufficiently clear, consistent, and 
transparent method that could be implemented on a generic basis to 
address the need for a transmission provider to demonstrate its 
forecast of native load growth and its effect on capacity reserved by 
right of first refusal customers.
    359. Many transmission providers argue that our current right of 
first refusal policy is inconsistent with the native load protections 
contained in section 217(b) of the FPA. We disagree, but note that the 
reforms being proposed here should moot this argument. We are proposing 
to extend the minimum term of the right of first refusal to a period 
(five years) that is more consistent with the planning horizons of 
transmission providers. In addition, limiting the right of first 
refusal to agreements with terms of five years or more will ensure that 
the right of first refusal is used by customers with long-term 
obligations to purchase capacity rather than as a means for customers 
with shorter-term transactions to use capacity for non-load-serving-
entity transactions.\337\ This is consistent with FPA section 
217(b)(4), which states that the Commission shall exercise its 
authority ``in a manner that facilitates the planning and expansion of 
transmission facilities to meet the reasonable needs of load-serving 
entities to satisfy the service obligations of the load-serving 
entities.'' Our proposal also is consistent with FPA section 217(b)(2) 
because it continues to allow the transmission provider to limit the 
right of first refusal to accommodate reasonably forecasted and 
verifiable native load growth.
    360. Under the proposed rule, transmission providers still will be 
required to plan their systems with the expectation that a transmission

[[Page 32690]]

customer with a long-term transmission agreement subject to a right of 
first refusal will exercise its rollover right at the end of its term. 
We believe it is important to reiterate the obligation on transmission 
providers to maintain ATC for existing transmission customers with 
rollover rights and our expectation that transmission providers will 
include all customers with rollover rights in their long-term 
planning.\338\ We understand that some existing reliability procedures 
or practices may encourage transmission providers to exclude certain 
transmission service contracts from their base-case models, even if 
those contracts contain a rollover right. This is inconsistent with 
Commission policy and undermines the purpose of the rollover right, 
which is to facilitate system planning and reliability.
4. Modification of Receipt or Delivery Points
    361. Section 22 of the pro forma OATT provides that a transmission 
customer taking firm point-to-point service may modify its receipt and 
delivery points on either a non-firm or a firm basis. Section 22.1 
(Modifications on a Non-Firm Basis) provides that, subject to certain 
conditions, a firm point-to-point customer may request transmission 
service on a non-firm basis over receipt and delivery points other than 
those specified in its service agreement (known as secondary receipt 
and delivery points) in amounts not to exceed its firm capacity 
reservation, without incurring an additional non-firm point-to-point 
service charge or executing a new service agreement. Section 22.2 
(Modifications on a Firm Basis) provides that any request to modify 
receipt and delivery points on a firm basis shall be treated as a new 
request for service in accordance with section 17 of the pro forma OATT 
(Procedures for Arranging Firm Point-to-Point Transmission Service), 
except that the transmission customer shall not be obligated to pay any 
additional deposit if the capacity reservation does not exceed the 
amount reserved in the existing service agreement. While such new 
request is pending, the transmission customer retains its priority for 
service at the existing firm receipt and delivery points specified in 
its service agreement.
---------------------------------------------------------------------------

    \337\ This is consistent with the approach suggested by TAPS, 
which argues that the current one-year minimum contract term allows 
significant capacity on constrained interfaces to be tied up in 
relatively short-term deals simply designed to hold the firm 
reservation as a path for non-firm economy purchases and to block 
competitors' firm access (e.g., inexpensive, one-year ``paper 
capacity'' deals). TAPS also argues that any restriction on the 
availability and flexibility of rollover rights be contingent on an 
expansion of the transmission grid so that transmission customers 
have reasonable access to competitive supplies. We agree that 
expansion of the grid is critical and accordingly have proposed to 
require coordinated transmission planning on both a local and 
regional level to ensure that transmission customers' needs are 
treated comparably to those of the transmission provider. This 
enhanced transmission planning, combined with other reforms proposed 
in this NOPR (e.g., improvements to the calculation of ATC), should 
mitigate TAPS's concerns by improving the ability to access 
competitive supplies.
    \338\ See, e.g., Southern Company Services, Inc., 104 FERC ]
61,140 at P 26-27 (2003).
---------------------------------------------------------------------------

    362. In the NOI, the Commission asked whether transmission 
customers have experienced undue discrimination in attempting to 
redirect to new receipt and delivery points pursuant to section 22.2 
and whether any reforms were needed. The Commission did not 
specifically ask about section 22.1, but some commenters nevertheless 
addressed this section. Most commenters, however, did not distinguish 
whether they were concerned with firm or non-firm redirects and instead 
addressed redirects generally.
Comments
    363. APPA notes that many of its members have experienced 
difficulties in changing receipt points, especially when such requests 
involve new sources of supply. In many cases, APPA asserts that 
transmission providers require major upgrades before they will grant a 
redirect to new points. The Public Power Council points out that 
redirecting to new points depends on ATC, and, therefore, the ability 
to make changes would be improved by better public knowledge of ATC at 
those points in all timeframes and by more information about ATC 
calculation methodologies. EPSA asserts that difficulty in redirecting 
to new points inhibits the ability to reassign capacity. Williams 
complains about delays by transmission providers in answering requests 
for redirects and urges the Commission to enforce OATT procedures and 
to consider a ``fast-track'' process for reviewing requests to redirect.
    364. Bonneville and EEI believe that any discrimination may be an 
unintentional result of a lack of clarity in the pro forma OATT, and 
are joined by MidAmerican, Progress Energy, and PNM-TNMP in calling for 
a number of clarifications. MidAmerican believes that these 
clarifications will provide flexibility to transmission customers and 
will enhance the ability to reassign transmission service to customers 
desiring different points of receipt or delivery.
    365. Southern and Ameren assert that because customers often make 
redirect requests at the last minute, there is often not enough time 
for the market to respond to capacity made available on an abandoned 
path. Southern also highlights the administrative burdens and 
complexity (particularly for reliability) of processing short-term 
changes in service and suggests that the Commission consider measures 
to encourage transmission customers to provide greater certainty as to 
the expected paths along which they will schedule service and to do so 
in a more timely manner. Southern, along with Bonneville, also urges 
the Commission to clarify rollover rights when service is redirected to 
new points. In general, however, Southern believes that the 
Commission's current redirect policies are reasonable and practical.
    366. A number of commenters focus on other related transmission 
issues, such as the flexibility afforded network service versus point-
to-point service or other network-service-related issues; \339\ the 
lack of flexibility with point-to-point service generally; \340\ or 
issues associated with the interconnection of network load at new 
delivery points.\341\
---------------------------------------------------------------------------

    \339\ E.g., Alberta Intervenors, Calpine, and TAPS.
    \340\ E.g., Occidental.
    \341\ E.g., NRECA and TDU Systems.
---------------------------------------------------------------------------

Discussion
    367. The Commission believes that it has already addressed many of 
the concerns raised by commenters with regard to reform of section 22 
of the pro forma OATT in Docket No. RM05-5-000.\342\ In Order No. 676, 
the Commission adopted the ``Standards for Business Practices and 
Communication Protocols for Public Utilities'' developed by the NAESB's 
Wholesale Electric Quadrant (WEQ).\343\ Order No. 676 incorporates the 
aforementioned standards by reference into the Commission's 
regulations; requires public utilities to implement the standards by 
July 1, 2006; and requires public utilities to file revisions to their 
OATTs to include these standards.\344\ The WEQ Standards recently 
adopted by the Commission include a number of standards addressing 
requirements for dealing with redirects on both a firm and non-firm 
basis.\345\ In fact, all of the WEQ Standards dealing with redirects 
were adopted by the Commission in Order No. 676, except for WEQ 
Standard 001-9.7, which addresses the impact of a firm redirect on a 
long-term firm transmission customer's rollover rights under section 
2.2 of the pro forma OATT. The Commission directed the WEQ to 
reconsider WEQ Standard 001-9.7 and to adopt a revised standard 
consistent with the Commission's

[[Page 32691]]

policies.\346\ The Commission also offered guidance to assist the WEQ 
in developing a standard that is consistent with Commission policy.\347\
---------------------------------------------------------------------------

    \342\ Standards for Business Practices and Communication 
Protocols for Public Utilities, Order No. 676, 71 FR 26199 (May 4, 
2006), FERC Stats. & Regs. ] 31,216 (2006).
    \343\ The WEQ was established by NAESB in response to a 
Commission order requesting the wholesale electric power industry to 
develop business practice standards and communication protocols by 
establishing a single consensus, industry-wide standards 
organization for the wholesale electric industry. See id. at P 3-4.
    \344\ The standards will hereinafter be referred to as the WEQ 
Standards. The Commission proposes to add a reference to the WEQ 
standards in section 4 of the pro forma OATT, which identifies the 
Commission's regulations containing the terms and conditions 
relevant to the OASIS and standards of conduct.
    \345\ The requirements for dealing with redirects on a firm 
basis are found at WEQ Standard 001-9, et seq., and the requirements 
for dealing with redirects on a non-firm basis are found at 001-10, et seq.
    \346\ Order No. 676 at P 52.
    \347\ Id. at P 53-61.
---------------------------------------------------------------------------

    368. As noted above, we believe that a number of concerns raised by 
commenters are addressed by the WEQ Standards. For example, we believe 
that the request of commenters for clarification that redirect service 
may be requested for only a portion of the original quantity of service 
is addressed for firm and non-firm service by WEQ Standards 001-9.2 and 
001-10.2, respectively, which provide that the transmission customer 
``shall be allowed to request a Redirect on a [Firm/Non-Firm] basis for 
a portion or all of the Capacity Available to Redirect.'' Likewise, the 
request of commenters for clarification that it is not necessary for a 
customer to redirect its service for the entire remaining term of 
service is addressed for firm and non-firm service by WEQ Standards 
001-9.3 and 001-10.3, respectively, which provide that the transmission 
customer ``shall be allowed to request a Redirect on a [Firm/Non-Firm]
basis for a portion or all of the time period of the Parent 
Reservation.'' While we believe that many concerns expressed by 
commenters with regard to redirects in this proceeding have been 
addressed by Order No. 676, we request that each commenter reconsider 
its concerns in this area with the benefit of Order No. 676's adoption 
of the WEQ Standards, and inform us if additional concerns remain. The 
Commission notes that several of the most active commenters addressing 
redirects in this proceeding also were commenters in Docket No. RM05-5-
000 and therefore should be familiar with whether a particular WEQ 
Standard addresses the issues raised in the comments submitted in this 
proceeding.\348\
---------------------------------------------------------------------------

    \348\ For example, Bonneville, EEI, NRECA, and Southern each 
commented in Docket No. RM05-5-000.
---------------------------------------------------------------------------

    369. The Commission anticipates that a number of other concerns, 
while perhaps not yet addressed (or addressed fully) by a WEQ Standard, 
are nevertheless the types of issues appropriate for the WEQ process. 
The Commission therefore proposes that each commenter that continues to 
believe additional reform is necessary in this area also evaluate 
whether its concerns would more appropriately be addressed by the WEQ 
as it considers its next version of its standards.\349\ Specifically, 
as noted above, the WEQ is in the process of reevaluating WEQ Standard 
001-9.7, dealing with redirects and rollovers, so that it is consistent 
with the Commission's guidance given in Order No. 676. The Commission 
requests comment on whether the WEQ process, along with the guidance 
provided by the Commission in Order No. 676, is sufficient to address 
the concerns of commenters that seek clarification on the interplay 
between redirects and rollovers.
---------------------------------------------------------------------------

    \349\ The Commission notes in this regard that the WEQ's 
procedures ensure that all industry members can have input into the 
development of a business practice standard, whether or not they are 
members of NAESB, and each standard it adopts is supported by a 
consensus of the five industry segments: Transmission, generation, 
marketers/brokers, distribution/load-serving entities, and end-
users. See Order No. 676 at P 5 & n.5.
---------------------------------------------------------------------------

    370. The Commission understands, however, that there are also more 
fundamental concerns with regard to section 22 that were raised in the 
NOI. Many comments reflect concerns about the inability of transmission 
customers to effectively redirect their transmission service to new 
receipt and delivery points in order to accommodate a new transaction, 
the reassignment of capacity, or the designation of a new supply 
source. Generally, these commenters argue that their ability to 
redirect to new points is stymied by a lack of ATC at the new points or 
the need for major upgrades at the new points; or that the transmission 
provider takes too long to process its redirect request. Transmission 
providers, on the other hand, complain of the administrative burdens 
and complexity (particularly with regard to reliability) of processing 
transmission customers' short-term changes in service, and also assert 
that there is often not enough time for the market to respond to 
capacity made available on customers' original paths.
    371. The ability to redirect to new points is a function of whether 
there is ATC at the new points. The Commission believes that its 
proposed reforms requiring coordinated transmission planning between 
transmission providers and their customers, as well as regional 
transmission planning open to all stakeholders, will lead to a more 
rationally planned transmission system that will result in fewer 
transmission constraints and more ATC available to accommodate requests 
to redirect to new points.\350\ Additionally, the Commission's proposed 
reforms regarding the calculation of ATC and increased transparency 
over the process will engender increased confidence among transmission 
customers in their transmission providers' ATC postings.\351\ In short, 
transmission customers will have more accurate and complete ATC 
information to utilize in evaluating their redirect options. Moreover, 
through increased transparency, transmission customers will have the 
information they need to question a transmission provider's denial of a 
request to redirect. Thus, we believe that our reforms in the area of 
transmission planning and ATC calculation should go a long way toward 
addressing transmission customer concerns in this area. Should 
commenters believe that our proposed reforms in this area will not 
address their concerns effectively, or that there is a better way of 
addressing them, we encourage them to submit a specific proposal, along 
with proposed revised pro forma OATT language.
---------------------------------------------------------------------------

    \350\ Supra Part V.B.
    \351\ Supra Part V.A.
---------------------------------------------------------------------------

    372. We believe that redirects should be as customer-friendly as 
possible. Other pro forma OATT reforms proposed in this rulemaking 
should improve the ability to redirect transmission service to new 
points pursuant to section 22. For example, the modifications to firm 
point-to-point service discussed above will be applicable to a request 
to redirect on a firm basis, as such requests are treated as a new 
request for service under pro forma OATT section 22.2. In addition, 
reforms related to the acquisition of service discussed below (e.g., 
with regard to making and processing requests for service, queuing, and 
reservation priority) should, among other things, help to address 
transmission customer concerns that transmission providers are too slow 
in processing redirect requests. These reforms also should help to 
address transmission provider concerns that customers do not respond 
completely and in a timely manner and that there is insufficient time 
to re-market capacity on the original paths.
5. Acquisition of Transmission Service
a. Processing of Service Requests
    373. The pro forma OATT includes requirements that transmission 
providers process requests for transmission service in a timely 
fashion. Section 17.5 (Response to a Completed Application) and section 
18.4 (Determination of Available Transmission Capability) of the pro 
forma OATT provide that following the receipt of a completed 
application for service, the transmission provider must respond to 
transmission customer requests for determinations of the availability 
of firm and non-firm

[[Page 32692]]

transmission capacity on a timely basis. The transmission provider must 
make the determination as soon as reasonably practicable after receipt 
but no later than certain specified time periods (or such time periods 
generally accepted in the region). Section 19 (Additional Study 
Procedures for Firm Point-to-Point Transmission Service Requests) of 
the pro forma OATT provides deadlines that transmission providers must 
adhere to in issuing system impact study agreements and facilities 
studies agreements and that transmission customers must abide by in 
responding to these study agreements. Section 19 requires transmission 
providers to use due diligence to complete system impact studies and 
facilities studies within 60 days. Section 32 of the pro forma OATT 
(Additional Study Procedures for Network Integration Transmission 
Service Requests) contains similar due diligence deadlines for 
completing system impact studies and facilities studies associated with 
requests for network service.
    374. In the NOI, the Commission sought comment on problems 
transmission customers and transmission providers have experienced 
regarding the timely processing of requests for transmission service. 
In particular, the Commission sought comment regarding whether 
transmission customers have experienced delays by transmission 
providers in responding to requests for transmission service in general 
and, in particular, what problems commenters have experienced as 
transmission providers process the queue for requests for transmission 
service that cannot be immediately granted due to a lack of ATC. We 
also asked about the type of remedies the Commission should impose on 
public utility transmission providers for missing deadlines set forth 
in their OATTs. Another issue we sought comment on was whether 
commenters have identified blocking issues, such as where a customer 
submits multiple requests intending to proceed with a single request 
specifically to keep others out of the queue; and if so, whether 
allowing transmission providers to charge a processing fee would reduce 
the incentive to submit multiple self-competing requests. Finally, we 
sought comment on whether the Commission should require transmission 
providers to study transmission requests as a group.
Comments
    375. A number of merchant generators articulated general concerns 
regarding the time it takes transmission providers to process requests 
for transmission service.\352\ EPSA notes that timeliness in responding 
to transmission requests is a consistent problem. Constellation states 
that the untimely processing of requests for transmission service is a 
persistent problem under the OATT, particularly with respect to long-
term point-to-point service, network service, and modification of 
network resource designations. Arkansas Cities adds that, under the 
current OATT, utilities' lenient application of time periods needed for 
the system impact study process and facilities study process cause 
transmission customers to endure significant amounts of time to obtain 
confirmed firm delivery service at a reasonable cost.
---------------------------------------------------------------------------

    \352\ E.g., Constellation, EPSA, Powerex, and Williams.
---------------------------------------------------------------------------

    376. A number of commenters suggest that transmission providers 
should inform the Commission when they miss the target deadlines for 
completing system impact studies and facilities studies and/or post 
performance statistics on their OASIS sites that detail the time it 
takes them to process system impact studies and facilities 
studies.\353\ EPSA states that it strongly believes that the new OATT 
should require the transmission provider to notify the Commission when 
it is not able to meet deadlines. TDU Systems suggests that one way to 
address the difficulty of determining acceptable delays is to require 
transmission providers to post statistics on their OASIS sites 
providing information as to the length of time it might take to process 
requests for transmission service. Cinergy proposes that adopting 
specific reporting metrics that require transmission providers to 
report certain statistics regarding their performance could result in 
an improved quality of service.
---------------------------------------------------------------------------

    \353\ E.g., Cinergy, Constellation, EPSA, MidAmerican, Powerex, 
and TDU Systems.
---------------------------------------------------------------------------

    377. A number of merchant generators propose that the Commission 
assess operational penalties on transmission providers that fail to 
meet the study deadlines detailed in the pro forma OATT.\354\ LG&E 
recommends that the Commission consistently enforce the established 
deadlines through penalties or other remedies unless good cause for 
failure to comply can be shown, so as to promote nondiscriminatory 
adherence to established deadlines. Powerex suggests that the 
Commission: (a) Identify a threshold percentage rate of acceptable 
compliance with response timelines, (b) require transmission providers 
to monitor and post their own rates of compliance with Commission-
required timelines on a path-specific basis, as well as the reasons for 
delays, (c) require transmission providers whose rate of compliance on 
a particular path falls below the Commission's threshold to file a 
compliance report with the Commission identifying the problem(s) and 
corrective measures that will be undertaken (including a timeline for 
implementation of the corrective measures), and (d) use a progressive 
penalty system that begins with reporting and auditing requirements for 
non-compliant transmission providers and then moves toward monetary 
penalties in cases where a transmission provider exhibits a pattern of 
uncorrected noncompliance, as well as in any case where actual bad 
faith, discrimination or preferential treatment has occurred.
---------------------------------------------------------------------------

    \354\ E.g., EPSA, Powerex, and Williams.
---------------------------------------------------------------------------

    378. A number of transmission providers state that transmission 
service request processing is slowed by excessive requests for 
transmission service from the same transmission customer with 
essentially the same service attributes (e.g., point of receipt, point 
of delivery, start time, end time, firmness).\355\ A number of other 
commenters also argue that some transmission customers submit multiple 
requests for transmission service with no intent to confirm most of the 
requests if and when the requests are accepted.\356\ MidAmerican states 
that it is aware of cases where customers have submitted multiple 
requests for service associated with a new generator where the location 
of the new generator is not known but queue priority is being sought by 
the transmission customer. MidAmerican adds that the submission of such 
multiple requests for service affects the processing of other lower 
queued transmission requests. South Carolina E&G states that there are 
instances when a transmission customer submits multiple requests 
intending to proceed with a single request, seemingly with the purpose 
of keeping others out of the queue. AWEA states that transmission 
queues are frequently jammed with many projects holding each other up. 
AWEA asserts that there often are ``zombie'' projects blocking the 
queue, without a power purchase agreement or other indication that they 
are serious projects. Suez Energy NA responds that there are blocking 
issues when a transmission customer submits multiple requests for 
transmission

[[Page 32693]]

service but intends to proceed with a single request.
---------------------------------------------------------------------------

    \355\ E.g., MidAmerican, Progress Energy, South Carolina E&G, 
and Southern.
    \356\ E.g., Alberta Intervenors, AWEA, Public Power Council, and 
Suez Energy NA.
---------------------------------------------------------------------------

    379. Several federal power agencies suggest that charging a fee on 
transmission service requests could provide the right incentive to 
transmission customers to limit requests for transmission service to 
only those requests they expect to confirm.\357\ Several other 
commenters suggest a similar fee.\358\ Bonneville supports the 
imposition of a processing fee for multiple requests to provide a 
disincentive to blocking behavior. Bonneville suggests that the fee 
should provide a disincentive for making multiple, ``self-competing'' 
requests. Bonneville suggests that, at a minimum, requests with the 
same point of receipt, point of delivery, source, sink, and time-frame 
should be considered ``self-competing.'' In addition, Bonneville 
contends that transmission providers should be allowed to define 
parameters to identify additional instances of ``self-competing'' 
requests on their systems. South Carolina E&G argues that there is 
merit to the concept of charging a processing fee that would increase 
with the duration of the requested service, to reduce the incentive to 
submit multiple self-competing requests.
---------------------------------------------------------------------------

    \357\ E.g., Bonneville and TVA.
    \358\ E.g., Alberta Intervenors, Snohomish, and South Carolina E&G.
---------------------------------------------------------------------------

    380. The majority of commenters were in favor of allowing, but not 
requiring, transmission providers to study requests for transmission 
service as a group, also known as clustering requests for transmission 
service.\359\ APPA and Bonneville suggest amending the pro forma OATT 
so that all requests received during a set time period are studied 
together. EEI argues that the Commission should not require the 
studying of transmission requests as a group, though transmission 
providers should continue to have the discretion to cluster 
transmission requests when it is efficient to do so. EPSA states that 
clustering should not be required, but may be considered as a customer 
option as part of a comprehensive planning process.
---------------------------------------------------------------------------

    \359\ E.g., EEI, EPSA, Nevada Companies, PacifiCorp, PNM-TNMP, 
Powerex, and Southern.
---------------------------------------------------------------------------

    381. Bonneville suggests that the Commission adopt two NAESB 
proposed business standards designed to reduce the number of self-
competing requests. In particular, Bonneville believes the Commission 
should adopt NAESB's proposed queue hoarding business practice and 
queue flooding business practice.
Discussion
    382. We agree with commenters who argue that requiring transmission 
providers to report the length of time they take to complete studies 
pursuant to sections 19 and 32 of the pro forma OATT would increase 
transparency and improve the ability of transmission customers and the 
Commission to detect undue discrimination. Therefore, we propose to 
require transmission providers to post on their OASIS sites metrics 
that track their performance in processing system impact studies and 
facilities studies associated with requests for transmission service. 
Transmission providers will be required to post the performance 
metrics, outlined below, for each calendar quarter. Transmission 
providers should begin tracking their performance upon the effective 
date of the final rule in this proceeding and keep the quarterly 
performance metrics posted on their OASIS sites for three calendar 
years. The transmission provider will be required to post the quarterly 
performance metrics within 15 days of the end of the quarter. The 
performance metrics outlined below should be calculated separately for 
affiliates' and non-affiliates' requests for short-term and long-term 
transmission service. A transmission provider also will be required to 
post performance metrics for studies that it conducts for RTOs.
    383. We propose to require transmission providers to post the 
following set of performance metrics on a quarterly basis:
    ? Process Time from Initial Service Request to Offer of 
System Impact Study Agreement pursuant to Sections 17.5, 19.1 and 32.1 
of the pro forma OATT
    ? Number of new System Impact Study Agreements delivered to 
Transmission Customers
    ? Number of new System Impact Study Agreements delivered to the 
Transmission Customer more than 30 days after the Transmission Customer 
submitted its request
    ? Average time (days) from request submittal to change in 
request status
    ? Average time (days) from request submittal to delivery of 
System Impact Study Agreement
    ? Number of new System Impact Study Agreements executed
    ? System Impact Study Processing Time pursuant to Sections 
19.3 and 32.3 of the pro forma OATT
    ? Number of System Impact Studies completed
    ? Number of System Impact Studies completed more than 60 days 
after receipt of executed System Impact Study Agreement
    ? Average time (days) from receipt of executed System Impact 
Study Agreement to date when completed System Impact Study made 
available to the Transmission Customer
    ? Average cost of System Impact Studies completed during the period
    ?  Service Requests Withdrawn from System Impact Study Queue
    ? Number of requests withdrawn from the System Impact Study queue
    ? Number of System Impact Studies withdrawn more than 60 days 
after receipt of executed System Impact Study Agreement
    ? Average time (days) from receipt of executed System Impact 
Study Agreement to date when request was withdrawn from the System 
Impact Study queue
    ? Process Time from Completed System Impact Study to Offer of 
Facilities Study pursuant to Sections 19.4 and 32.4 of the pro forma OATT
    ? Number of new Facilities Study Agreements delivered to 
Transmission Customers
    ? Number of new Facilities Study Agreements delivered to 
Transmission Customers more than 30 days after the completion of the 
System Impact Study
    ? Average time (days) from completion of System Impact Study to 
delivery of Facilities Study Agreement
    ? Number of new Facilities Study Agreements executed
    ?  Facilities Study Processing Time pursuant to Sections 19.4 and 32.4
    ? Number of Facilities Studies completed
    ? Number of Facilities Studies completed more than 60 days 
after receipt of executed Facilities Study Agreement
    ? Average time (days) from receipt of executed Facilities Study 
Agreement to date when completed Facilities Study made available to the 
Transmission Customer
    ? Average cost of Facilities Studies completed during the period
    ? Average cost of recommended upgrades for Facilities Studies 
completed during the period
    ?  Service Requests Withdrawn from Facilities Study Queue
    ? Number of requests withdrawn from the Facilities Study queue
    ? Number of Facilities Studies withdrawn more than 60 days 
after receipt of executed Facilities Study Agreement
    ? Average time (days) from receipt of executed Facilities Study 
Agreement to date when request was withdrawn from the Facilities Study 
queue
    384. We also propose to impose operational penalties when 
transmission providers routinely fail to meet the 60-

[[Page 32694]]

day due diligence deadlines prescribed in sections 19.3, 19.4, 32.3 and 
32.4 of the pro forma OATT. We propose to require a transmission 
provider to file a notice with the Commission in the event the 
transmission provider processes more than 20 percent of non-affiliates' 
studies outside of the 60-day due diligence deadlines in the pro forma 
OATT for two consecutive quarters. For the purposes of calculating this 
notification trigger, the transmission provider should aggregate all 
system impact studies and facilities studies that it completes during 
the quarter for non-affiliates.\360\ The transmission provider may 
explain in its notification filing that it believes there are 
extenuating circumstances that prevented it from meeting the deadlines 
in the pro forma OATT. The transmission provider then will be subject 
to an operational penalty if the transmission provider continues to be 
out of compliance with the deadlines prescribed in the pro forma OATT 
for each of the two quarters following its notification filing. The 
transmission provider will be deemed to be out of compliance if it 
completes 10 percent or more of non-affiliates' system impact studies 
and facilities studies outside of the deadlines prescribed in the pro 
forma OATT. The operational penalty will be assessed on a quarterly 
basis, starting with the quarter following the notification filing and 
continuing until the transmission provider completes at least 90 
percent of all studies within 60 days after the study agreement has 
been executed. For any system impact study or facilities study 
completed during that quarter and more than 60 days after the study 
agreement was executed, the penalty will equal $500 for each day the 
transmission provider takes to complete the study beyond 60 days. For 
any system impact study or facilities study that is still pending at 
the end of the quarter and that has been in the study queue for more 
than 60 days, the penalty will equal $500 for each day the study has 
been in the study queue beyond 60 days. Because of their independence, 
we do not believe that RTOs have an incentive to neglect their 
obligation to process applications for service in a timely fashion. As 
a result, we propose that RTOs will not be subject to this penalty regime.
---------------------------------------------------------------------------

    \360\ For instance, if the transmission provider completes 4 
non-affiliates' system impact studies during the quarter with 2 
completed more than 60 days after the system impact study agreement 
was executed and completes 2 non-affiliates' facilities studies 
during the quarter with none completed more than 60 days after the 
facilities study agreement was executed, then the transmission 
provider will be deemed to have completed 2 out of 6 (33 percent) 
studies outside of the deadlines in the pro forma OATT.
---------------------------------------------------------------------------

    385. In addition to the operational penalty described above, we 
propose to require transmission providers to post on their OASIS sites 
additional performance metrics after making a notification filing. 
Transmission providers will have to post these performance metrics 
until they process at least 90 percent of all system impact and 
facilities studies within 60 days after the study agreement has been 
executed. Starting the quarter following a notification filing, the 
transmission provider will be required to post: (1) The average, across 
completed system impact studies, of the employee-hours expended per 
completed system impact study; (2) the average, across completed 
facilities studies, of employee-hours expended per completed facilities 
study, (3) the number of employees devoted to processing system impact 
studies, and (4) the number of employees devoted to processing 
facilities studies. These additional performance metrics should be 
calculated separately for affiliates' and non-affiliates' requests for 
transmission service and for short-term and long-term transmission service.
    386. In addition to the operational penalties described above, we 
may order other remedial actions, consistent with the Enforcement 
Policy Statement. Any other remedial action will be determined on a 
case-by-case basis. The transmission provider will pay the operational 
penalty described above, consistent with the proposed rule discussed in 
Part V.C.4.b. The transmission provider cannot recover for ratemaking 
purposes any operational penalty it pays for failing to process 
transmission service studies on a timely basis.
    387. With respect to the problem of multiple, self-competing 
transmission service requests, we seek comment on a fee structure that 
could provide a disincentive for transmission customers to submit such 
duplicative requests without penalizing transmission customers that 
have legitimate requests for transmission service. We seek detailed 
recommendations, including any proposed tariff language, regarding the 
standards we would use to identify requests that would be subject to a 
fee. We also seek recommendations on the level of the fee that balances 
our policy goals to discourage requests for transmission service that 
the transmission customer does not intend to confirm while not 
discouraging legitimate requests for transmission service. Finally, we 
seek comment regarding the circumstances, if any, under which the 
processing fee would be refunded to or credited to the transmission 
customer.
    388. In Order No. 2003, we encouraged transmission providers to 
study interconnection requests in clusters.\361\ We likewise encourage 
transmission providers to study requests for transmission service in 
clusters, though we will not require transmission providers to cluster 
requests for transmission service for study purposes.\362\ As with 
interconnection requests, studying requests for transmission service in 
clusters allows the transmission provider to consider all requested 
uses of the transmission system at one time. We seek comment regarding 
whether transmission providers should be required to study requests for 
transmission service in a group if the transmission provider fails to 
complete studies on a timely basis; and, if so, we seek comment on the 
circumstances that should trigger such a requirement and the 
appropriate method of implementing the requirement. We further seek 
comment regarding whether transmission providers should be required to 
study requests for transmission service in a group if all the 
transmission customers in the group agree to cluster their requests. We 
also seek comment regarding how to select the requests that belong to a 
cluster so that transmission customers cannot ``cherry-pick'' clusters 
to avoid transmission system upgrade costs.
---------------------------------------------------------------------------

    \361\ Order No. 2003 at P 155.
    \362\ We note that we previously have allowed transmission 
providers to study requests for transmission service in a group. 
See, e.g., Southwest Power Pool, Inc., 110 FERC ] 61,028 at P 16 (2005).
---------------------------------------------------------------------------

    389. In Order No. 676, we incorporated by reference a number of 
NAESB business practices, including the business standards on queue 
hoarding and queue flooding.\363\ NAESB's queue hoarding business 
practice allows transmission providers to deny a transmission 
customer's identical requests for transmission service if the customer 
elects not to accept an initial offer of identical, or substantially 
identical, transmission service. NAESB's queue flooding business 
practice allows a transmission provider to invalidate the submission of 
additional identical requests for transmission service when the sum of 
all previously submitted identical requests for transmission service 
equals or exceeds the total transfer capability on the requested path 
for any time period during the duration of the requests. We would 
consider the decision by a transmission provider to

[[Page 32695]]

deny service under the queue hoarding business practice and the 
decision to invalidate requests under the queue flooding business 
practice to be an act of discretion under 18 CFR 37.6(g)(4) (2005). As 
a result, the transmission provider is to log the actions it takes 
under the queue flooding and queue hoarding business practices.
---------------------------------------------------------------------------

    \363\ See Order No. 676 at P 19.
---------------------------------------------------------------------------

b. Queue Processing Business Practices
    390. The set of uniform business practices adopted in Order No. 676 
relating to transmission service price negotiation and on improving 
interaction between transmission customers and transmission providers 
over OASIS nodes. These business practices include standards for the 
time limit within which (1) transmission providers must respond to 
requests for transmission service, (2) transmission customers must 
confirm service, and (3) transmission providers must respond to a rebid 
from a transmission customer.\364\ These business practices also 
include negotiation priority rules, including the terms under which a 
request can be pre-empted and under which a request has the right-of-
first-refusal.\365\
---------------------------------------------------------------------------

    \364\ Id., Standards 001-4.6 and 001-4.13.
    \365\ Id., Standards 001-4.14 and 001-4.16.
---------------------------------------------------------------------------

    391. In the NOI, the Commission sought comment regarding whether 
there are provisions of the pro forma OATT that need to be reformed to 
better define the obligations of public utility transmission providers 
in responding to requests for transmission service.
Comments
    392. Several commenters asked that the Commission require 
transmission providers to post standard business practices that 
describe how the transmission provider will process requests for 
transmission service.\366\ MidAmerican suggests that transmission 
providers should be required to post on their OASIS sites a business 
practice documenting how they process their queues, requests outside 
the queue, and expected completion times. Calpine believes that the 
processing of requests for transmission service, and the deadlines 
associated with that process, should be standardized for all 
transmission service providers. For example, Calpine notes that 
Entergy's OASIS business practices state that Entergy will respond to 
fixed, hourly non-firm transmission service requests ``within 30 
minutes of receiving the request for the requests received earlier than 
1 hour before the service is to commence.'' By comparison, Calpine 
continues, SPP's tariff explains that hourly, non-firm transmission 
service requests for the next hour may be submitted no later than 20 
minutes prior to the start of service.
---------------------------------------------------------------------------

    \366\ E.g., Calpine, MidAmerican, and TDU Systems.
---------------------------------------------------------------------------

Discussion
    393. Order No. 676 contains many of the business practices we 
expect transmission providers to follow when they process requests for 
transmission service, including the issue Calpine raises in its 
comments about discrepancies between Entergy's and SPP's processes for 
requests for hourly non-firm transmission service. Calpine's comment 
addresses the deadline for transmission customers to submit requests 
for non-firm hourly point-to-point service and the deadline for 
transmission providers to respond to requests for non-firm hourly 
point-to-point service. Standard 001-4.13 in Order No. 676 indicates 
that transmission providers should use their best efforts to respond to 
requests for non-firm hourly point-to-point service that are submitted 
less than an hour prior to start and transmission providers should 
respond within 30 minutes to requests that are submitted more than an 
hour before start. In addition, in this NOPR we have provided 
additional clarity regarding the calculation of ATC and requirements 
for processing rollover requests. We also provide general guidance 
regarding which business practices should be filed as part of a 
transmission provider's OATT and which should be posted on OASIS. Given 
this additional clarity and the business practices already mandated by 
Order No. 676, we seek comment on whether commenters believe additional 
standardization of request queue processing is necessary. If so, we 
seek comment on the specific issues commenters believe are not clearly 
prescribed in Order No. 676 or this NOPR and which require additional 
mandatory queue processing business practices.
c. Reservation Priority
    394. Section 13.2 of the pro forma OATT requires transmission 
providers to process requests for long-term firm point-to-point service 
on a first-come, first-served basis. In the NOI, we asked whether the 
first-come, first-served approach to reservation priorities has 
resulted in a fair and equitable means of allocating transmission 
capacity when the transmission system is oversubscribed. If not, we 
asked whether an alternative approach should be implemented.
Comments
    395. Most transmission providers and federal power agencies respond 
that the first-come, first-served approach to allocating transmission 
service is the best alternative available.\367\ Several merchant 
generators and public power entities concur that no better alternative 
exists.\368\ Several commenters suggest that the first-come, first-
served approach may provide an advantage to transmission customers who 
have the financial resources to purchase software and employ staff to 
continually monitor OASIS sites.\369\ Santa Clara states that entities 
that have superior software and are able to consistently procure 
capacity to the exclusion of other market participants may have an 
unfair advantage.
---------------------------------------------------------------------------

    \367\ E.g., Ameren, EEI, Nevada Companies, TVA, and WAPA.
    \368\ E.g., NRECA, Powerex, Public Power Council, Sempra, and 
TDU Systems.
    \369\ E.g., Bonneville and Santa Clara.
---------------------------------------------------------------------------

    396. For the short-term market, Bonneville contends, the first-
come, first-served approach has two defects: (1) It advantages larger 
and better-financed transmission customers, which can continually 
monitor OASIS sites and submit requests electronically the moment new 
ATC is posted; and (2) it results in arbitrary awards of transfer 
capability when one customer's submission precedes a second customer's 
submission by mere seconds. Bonneville suggests that the Commission 
modify the first-come, first-served rule for awarding short-term firm 
point-to-point service capacity so that all requests submitted within a 
given time-frame are considered simultaneously submitted.
    397. Several commenters propose some version of priority preference 
for requests for transmission service that are pre-confirmed.\370\ 
Bonneville states that transmission customers flood the queue with 
unconfirmed requests to force competitors with higher queue positions 
to extend the length of their requests to retain their queue positions.
---------------------------------------------------------------------------

    \370\ E.g., Bonneville, Entergy, and South Carolina E&G.
---------------------------------------------------------------------------

    398. Bonneville suggests that the Commission consider reducing the 
time transmission customers have to confirm requests for short-term 
transmission service after the transmission provider has accepted a 
request for short-term transmission service. Bonneville states that a 
shorter time-frame would clear the short-term firm transmission market 
more quickly and make it more difficult for transmission customers to 
tie up scarce transfer capability.

[[Page 32696]]

    399. Powerex suggests that the Commission clarify its reservation 
priority standards so that when transmission providers make use of 
discounts in short-term service, price (not to exceed the ceiling 
price) should be the third-level tie breaking mechanism, with higher-
priced requests of equal duration having greater priority and requests 
earlier in the open access same-time information system having right of 
first refusal to match subsequent requests. Powerex states that in the 
presence of discounting, the open access transmission tariff allows a 
higher value service (firm) to be sold at a lower price than a lower 
value service (non-firm) even in the same operating horizon, because 
price based displacement only applies to short-term non-firm 
transmission services.
Discussion
    400. In response to comments that transmission customers that have 
the financial resources to purchase software and employ staff to 
continually monitor OASIS sites have an unfair advantage under a first-
come, first-served approach, we seek comment regarding whether any such 
advantage would be mitigated if all requests submitted within a 5-
minute window, with duration as a tie breaker, were deemed to have been 
submitted simultaneously. We also seek comment on whether transmission 
customers could game a 5 minute equivalent priority standard to request 
transmission service only after another transmission customer has made 
a request. To the extent we adopt a 5 minute equivalent priority 
standard, we propose to allocate capacity on a pro rata basis, though 
we seek comment on other methods for allocating limited transmission 
capacity among equivalent priority requests of equal duration.
    401. We also propose to change the priority rules to give priority 
to pre-confirmed requests. As a result, a pre-confirmed short-term 
request for firm transmission service would preempt any non-pre-
confirmed short-term requests, regardless of duration. Similarly, a 
pre-confirmed request for long-term firm transmission service would 
preempt a request for long-term transmission service that is not pre-
confirmed. We seek comment on whether this change to the reservation 
priority rules will alleviate concerns commenters have expressed 
regarding the flooding or jamming of the transmission queue by transmission 
customers who submit multiple requests for transmission service.
    402. We propose to add price as a tie-breaker in determining 
reservation queue priority when the transmission provider is willing to 
discount transmission service. Price would serve as a tie-breaker after 
pre-confirmation for those requests that are not yet confirmed. As a 
result, a pre-confirmed request for short-term firm point-to-point 
service would preempt another pre-confirmed request for short-term firm 
point-to-point service that has an earlier queue time, and an equal or 
shorter duration but a lower offer price. However, a request for short-
term firm point-to-point service that is not pre-confirmed would not 
preempt a pre-confirmed request for short-term firm point-to-point 
service that has an earlier queue time, and an equal or shorter 
duration but a lower offer price.
6. Designation of Network Resources
a. Qualification as a Network Resource
    403. Taken together, the following sections of the pro forma OATT 
describe the resources a network customer can appropriately designate 
as a network resource. Section 30.1 of the pro forma OATT describes 
network resources as all generation owned or purchased by the network 
customer designated to serve network load under the tariff. Section 
30.1 also indicates that network resources may not include resources 
that are committed for sale to non-designated third-party load or 
otherwise cannot be called upon to meet the network customer's network 
load on a noninterruptible basis. Pursuant to section 30.7 of the pro 
forma OATT, the network customer must demonstrate that it owns or has 
committed to purchase generation pursuant to an executed contract in 
order to designate a generating resource as a network resource. 
Alternatively, the network customer may establish that execution of a 
contract is contingent upon the availability of network service. 
Section 29.2 requires the network customer to provide the following 
information about a power purchase agreement that is to serve as a new 
designated network resource: source of supply, control area location, 
transmission arrangements and delivery point(s) to the transmission 
provider's transmission system.
    404. The Commission has issued a number of orders that clarify 
which resources meet the criteria set out in sections 30.1 and 30.7 of 
the pro forma OATT. In MSCG, the Commission stated that network 
resources must be generating resources owned by the network customer or 
purchases of noninterruptible power under executed contracts that 
require the network customer to pay for the purchase.\371\ In WPPI, the 
Commission found that a network customer can designate as a network 
resource a system purchase that is not backed by a specific 
generator.\372\ The Commission found that Wisconsin Public Service 
Corporation (WPS) had appropriately designated a power purchase as a 
network resource, even though the power purchase agreement did not 
require WPS to take energy around the clock and allowed WPS to convert 
its energy purchase to a discounted product that could be 
interrupted.\373\ In addition, the Commission stated that because the 
pro forma OATT requires a power purchase to be noninterruptible, third-
party transmission arrangements to deliver the resource to the network 
have to be noninterruptible as well.\374\ In Illinois Power, the 
Commission found that a firm purchase need not be backed by a capacity 
purchase to qualify as a network resource.\375\
---------------------------------------------------------------------------

    \371\ Morgan Stanley Capital Group v. Illinois Power Co., 83 FERC ]
61,204 at 61,911-12 (1998), order on reh'g, 93 FERC ] 61,081 
(2000) (MSCG).
    \372\ Wisconsin Public Power Inc. v. Wisconsin Public Service 
Corp., 84 FERC ]
61,120 at 61,650-51 (1998) (WPPI).
    \373\ Id.
    \374\ Id. at 61,660.
    \375\ Illinois Power Co., 102 FERC ] 61,257 at P 14 (2003), 
reh'g denied, 108 FERC ] 61,175 (2004) (Illinois Power).
---------------------------------------------------------------------------

    405. In the NOI, the Commission sought comment regarding whether 
network resources consisting of firm contracts that do not specify 
generation sources until the energy is scheduled (so-called ``seller's 
choice contracts'') are a problem. The Commission also sought comment 
on the specific difficulties entities have experienced with designation 
of network resources and asked what reforms are needed to the 
designations provision in the pro forma OATT.
Comments
    406. A number of commenters indicate that firm contracts that do 
not specify generation sources are acceptable network resources as long 
as the network customer specifies enough information for the 
transmission provider to identify how the contract power will enter its 
control area.\376\ Bonneville suggests that the customer should be 
required to identify the point(s) of receipt on the transmission 
provider's system whenever it designates a network resource. EEI states 
that the designation of seller's choice contracts as network resources 
is only problematic if the seller's choice contract permits the seller 
to choose the

[[Page 32697]]

flowgate path over which the energy will be delivered. EEI further 
explains that no issue is present if the seller is limited to a single 
path or flowgate. On the other hand, PNM-TNMP argues that allowing 
seller's choice contracts to be considered network resources 
significantly complicates transmission planning, as virtually none of 
the information required by section 29.2 of the OATT can be provided.
---------------------------------------------------------------------------

    \376\ E.g., Bonneville, EEI, Nevada Companies, Public Power 
Council, and TVA.
---------------------------------------------------------------------------

    407. Several commenters cited specific difficulties with or 
suggested specific modifications to the network designation provisions 
of the tariff. APPA indicated that under the liquidated damages 
provisions in the EEI contract, it is the buyer's responsibility to go 
out into the market to purchase replacement supplies (cover), and the 
seller then pays the buyer the difference between the contract price 
and the cover price. APPA states that these provisions are not 
consistent with the concept of having to specify generation resources 
or contracts as network resources, since the actual source and supplier 
of generation may well change at a time when both wholesale power 
supplies and transmission capacity are at a premium. Ameren suggests 
that the Commission clarify that liquidated damages products cannot be 
designated network resources. Ameren states that a liquidated damages 
contract allows a supplier to walk away from a deal if it can obtain a 
price elsewhere high enough to offset the liquidated damages 
provisions. Ameren argues that liquidated damages contracts are 
financial instruments that produce no electricity. MidAmerican also 
contends that provisions for designating liquidated damages contracts 
as network resources should be eliminated. Southwestern urges the 
Commission to reform the OATT to make it clear that a firm purchased 
power contract with liquidated damages should be eligible to be 
considered a designated network resource.
Discussion
    408. We propose to maintain our current policy regarding the power 
purchase agreements that network customers may designate as network 
resources. In particular, a network customer will continue to be able 
to designate resources from system purchases not linked to a specific 
generating unit, provided the purchase power agreement is not 
interruptible for economic reasons, does not allow the seller to fail 
to perform under the contract for economic reasons, and the executed 
contract requires the network customer to pay for the purchase. In 
addition, third party transmission arrangements to deliver the purchase 
to the network have to be noninterruptible as well.
    409. In response to comments that seller's choice contracts are 
problematic because the network customer can provide limited, if any, 
information required by section 29.2 of the pro forma OATT, we 
reiterate that a request to designate a new network resource must 
include the information specified in section 29.2(v), including the 
source of supply, control area location, transmission arrangements, and 
delivery point(s) to the transmission provider's transmission system. 
When a network customer is designating a system purchase as a new 
network resource, the source information required in section 29.2(v) 
should identify that the resource is a system purchase and should 
identify the control area from which the power will originate. A power 
purchase agreement that is structured so that a network customer cannot 
specify all of the information required by section 29.2(v) cannot be 
designated as a network resource.
    410. In response to suggestions that liquidated damages products 
should not be designated network resources because they are 
interruptible for economic reasons, we clarify that network customers 
may not designate as network resources those power purchase agreements 
that give the seller a contractual right to compensate the buyer 
instead of delivering power even if the seller is able to deliver 
power. For instance, a network customer may not designate as a network 
resource a purchase agreement that allows the seller to interrupt 
service for reasons other than reliability, but allows the buyer to 
force delivery at a higher price. In addition, a network customer may 
not designate as a network resource a purchase agreement that requires 
a seller to pay the buyer's cost of replacement power when the seller 
chooses not to deliver energy for economic reasons.
b. Documentation for Network Resources
    411. Section 30.2 of the pro forma OATT stipulates that a network 
customer request the designation of a new network resource by a request 
for modification of service pursuant to an application under section 29 
of the pro forma OATT, and section 29.2 stipulates that the network 
customer must provide specified information about its designated 
network resources. The Commission found in WPPI that transmission 
customers may need to document compliance with specific requirements 
for obtaining tariff service, possibly including contractual 
terms.\377\ The Commission went on to state that it expected a 
transmission provider's merchant function to police its own compliance 
with tariff obligations.\378\
---------------------------------------------------------------------------

    \377\ WPPI at 61,660.
---------------------------------------------------------------------------

Comments
    412. LG&E suggests that the pro forma OATT require the transmission 
provider to have a process to verify that each load-serving entity has 
a contractual right to the resources they are designating. LG&E argues 
this would help eliminate concerns over double booking of resources by 
two parties. EPSA states that transmission providers have attempted to 
require customers to demonstrate that they have obtained contracts 
covering an annual period, rather than allowing customers to provide 
reasonable advance notice for each contract during the service period. 
EPSA asks the Commission to prohibit this practice.
---------------------------------------------------------------------------

    \378\ Id.
---------------------------------------------------------------------------

Discussion
    413. We clarify that transmission providers are not responsible for 
verifying that the generating units and power purchase agreements 
network customers designate as network resources satisfy the 
requirements in sections 30.1 and 30.7 of the pro forma OATT. While 
transmission providers are responsible for verifying that the network 
customer has provided all the information section 29.2 requires the 
network customer to provide, the transmission provider is not 
responsible for obtaining contractual terms to verify requirements in 
sections 30.1 and 30.7 of the pro forma OATT. The transmission provider 
continues to have the responsibility to verify that third-party 
transmission arrangements to deliver the purchase to the transmission 
provider's system are firm.
    414. We propose to require the transmission provider's merchant 
function as well as network customers to include a statement with each 
application to designate a new network resource that attests that: (1) 
The transmission customer owns or has committed to purchase the new 
designated network resource, and (2) the new designated network 
resource comports with the requirements for designated network 
resources. The network customer should include this attestation in the 
customer's comment section of the request when it confirms the request. 
Similarly, we propose that all entities that submit an application for 
network service be required to

[[Page 32698]]

include a statement with the application for service that attests that, 
for each network resource identified in the application for service: 
(1) The transmission customer owns or has committed to purchase the 
designated network resource, and (2) the designated network resource 
comports with the requirements for designated network resources.
    415. We propose that if the network customer does not include an 
attestation when it confirms its request, the transmission provider 
will notify the network customer within 15 days of confirmation that 
its request is deficient. Wherever possible, the transmission provider 
will attempt to remedy deficiencies in the request through informal 
communications with the network customer. If such efforts are 
unsuccessful, the transmission provider will terminate the network 
customer's request and change the status of the request on OASIS to 
``retracted.'' This termination will be without prejudice to the 
network customer submitting a new request that includes the required 
attestation. The network customer will be assigned a new priority 
consistent with the date of the new request.
    416. In the event that the transmission provider or any network 
customer designates a network resource that it does not own or has not 
committed to purchase or that does not comport with the requirements 
for designated network resources, we will deem the network customer to 
be in violation of the pro forma OATT and will consider assessing civil 
penalties on a case-by-case basis consistent with the Commission's 
Enforcement Policy Statement. We encourage the transmission provider 
and other market participants to use the Commission's Enforcement 
Hotline to report instances when they believe a network customer has 
designated as a network resource a resource that does not meet the 
criteria for network resources.
c. Undesignation of Network Resources
    417. Section 28.2 of the pro forma OATT requires the transmission 
provider, on behalf of its native load customers, to designate 
resources and loads in the same manner as any network customer under 
Part III of the pro forma OATT (Network Integration Transmission 
Service). The information provided by the transmission provider must be 
consistent with the information it uses to calculate ATC. Section 30.3 
of the pro forma OATT allows the network customer to terminate the 
designation of all or part of a generating resource as a network resource 
at any time, though the network customer should provide notification to 
the transmission provider as soon as reasonably practicable.
    418. In Order No. 888-B, the Commission clarified that the pro 
forma OATT allows network customers to designate network resources over 
shorter time periods. The Commission indicated that a network customer 
that seeks to engage in firm sales from its current designated network 
resources may terminate the generating resource (or a portion of it) as 
a network resource pursuant to section 30.3 of the pro forma OATT and 
request, as set forth in section 29 of the pro forma OATT, that the 
same generation resource be designated as a network resource effective 
with the end of its power sale.\379\
---------------------------------------------------------------------------

    \379\ Order No. 888-B at 62,093
---------------------------------------------------------------------------

    419. In the NOI, the Commission sought comment on whether network 
customers should be allowed to ``undesignate'' portions of their 
designated network resources on a short-term basis in order to make 
firm sales from these resources.
Comments
    420. Most commenters suggest that the Commission continue to allow 
network customers to undesignate a portion of their designated network 
resources on a short-term basis in order to make firm sales.\380\ APPA 
argues that the ability of network customers to undesignate their 
network resources on a short-term basis is an important aspect of Order 
No. 888-B and should be preserved. APPA states that the flexibility 
afforded to network resource customers allows them to lay off excess 
power supplies that they do not need to serve their designated loads 
during off-peak demand periods. APPA and EEI contend that this 
increases the number of wholesale sellers in the market during non-peak 
periods, and this supports wholesale competition for power supply sales.
---------------------------------------------------------------------------

    \380\ E.g., APPA, EEI, Entergy, Nevada Companies, Public Power 
Council, Southern, and TVA.
---------------------------------------------------------------------------

    421. Several commenters suggest that network customers should have 
the same right as transmission providers to undesignate network 
resources to make off-system sales.\381\ APPA states that the 
Commission should make explicit the requirement that the transmission 
provider must provide the same flexibility to its network customers as 
it does to its own merchant function in designating and terminating 
network resources.
---------------------------------------------------------------------------

    \381\ E.g., APPA, NRECA, and Public Power Council.
---------------------------------------------------------------------------

    422. NRECA asserts that public utility transmission providers must 
be required to undesignate resources or portions thereof in order to 
make firm sales out of generation fleets that they have designated as a 
network resource.
Discussion
    423. We propose to continue to allow network customers to 
undesignate a portion of their network resources on a short-term basis 
to make off-system sales. We reiterate that a network customer may 
redesignate the resource by making a request to designate a new network 
resource. In response to comments that the transmission provider also 
should be required to undesignate network resources when the 
transmission provider makes firm off-system sales, we reiterate that 
the transmission provider must abide by both the requirement in section 
28.2 of the pro forma OATT to designate its network resources in the 
same manner as network customers and the prohibition in section 30.1 of 
the pro forma OATT against making firm sales from its designated 
network resources. That is, the transmission provider and all network 
customers must designate their network resources and are prohibited 
from making firm sales from designated network resources. To the extent 
the transmission provider or a network customer wants to make a firm 
sale from a network resource, it must undesignate the resource pursuant 
to section 30.3 of the pro forma OATT. The network customer, including 
the transmission provider itself, can request to redesignate the 
resource by making a request to designate a new network resource 
pursuant to section 30.2 of the pro forma OATT.
    424. We seek comment on the amount of time prior to operation that 
the transmission provider and other network customers should be 
required to terminate a network resource to ensure that the appropriate 
set of network resources are included in the ATC calculation.
7. Clarifications Related to Network Service
Secondary Network Service
    425. Section 28.4 of the pro forma OATT allows a network customer 
to deliver economy energy purchases to its network load from non-
designated network resources on an as-available basis without 
additional charge. In Order No. 888, the Commission described economy 
energy purchases as energy that displaces firm network resources.\382\
---------------------------------------------------------------------------

    \382\ Order No. 888 at 21,751.
---------------------------------------------------------------------------

    426. The use of secondary network service to deliver purchased power

[[Page 32699]]

when a network customer is making off-system sales was raised in 
several Commission investigations and audits. In Idaho Power, the 
Commission accepted a settlement with Idaho Power related to Idaho 
Power's incorrect use of the native load priority to access its 
transmission system.\383\ In Idaho Power, the utility's wholesale 
merchant function purchased power outside of Idaho Power's control area 
to facilitate an off-system sale and used secondary network service to 
bring the purchases into Idaho Power's control area.\384\ In accepting 
the settlement, the Commission stated that ``[i]t is axiomatic that the 
native load priority cannot be used to complete sales that are not 
necessary to serve native load.'' \385\ In MidAmerican, the Commission 
issued an audit report that contained a finding that MidAmerican's 
wholesale merchant function used network service instead of point-to-
point service to deliver short-term energy purchases to its control 
area that were not used to serve MidAmerican's native load.\386\
---------------------------------------------------------------------------

    \383\ Idaho Power Co., 103 FERC ] 61,182 at P 2 (2003) (Idaho Power).
    \384\ Id. at P 4.
    \385\ Id.
    \386\ MidAmerican Energy Co., 112 FERC ] 61,346 at P 6 (2005).
---------------------------------------------------------------------------

Comments
    427. South Carolina E&G asks the Commission to clarify whether 
specific methods used to bring sellers and buyers together in the 
wholesale market are appropriate under the pro forma OATT in its 
current form. South Carolina E&G notes that as a utility's native load 
forecasts evolve into real-time conditions, the utility may need to 
sell off excess energy. South Carolina E&G notes further that, as 
inexpensive sources of power become available off-system, the utility 
may engage in economy purchases of power for native load. South 
Carolina E&G asserts that such practices clearly benefit the market and 
safeguard native load customers' interests by ensuring that economy 
purchases minimize the price of consumers' power and/or giving the 
utility a market outlet for excess energy, thus avoiding the uneconomic 
backing down of lower cost generating units while retaining higher cost 
prescheduled purchases. South Carolina E&G urges the Commission to 
support the continuation of such practices.
Discussion
    428. We propose to clarify that a network customer may not use 
secondary network service to bring energy onto its system to support an 
off-system sale if the purchased power does not displace the customer's 
own higher cost generation. We propose to modify the section 28.4 of 
the pro forma OATT to clarify that a network customer may use secondary 
network service to deliver economy energy and we propose to add a 
definition for ``economy energy'' to the pro forma OATT. We propose to 
define ``economy energy'' as energy purchased by a network customer 
that displaces the customer's own higher cost generation for the 
purpose of serving the customer's designated network loads.
    429. While we reiterate that secondary network service may be used 
only to serve a network customer's designated network load, we do not 
intend to discourage market participants from identifying opportunities 
to profitably purchase for resale. We simply intend to ensure that all 
market participants compete on a comparable basis and use point-to-
point service to complete all segments of a purchase for resale off-system.
    430. We also do not intend to discourage network customers from 
purchasing off-system energy to lower the cost of serving network 
loads. A network customer may use secondary network service in hours 
when it is also making off-system sales. However, the network customer 
may do so only to deliver purchases that qualify as economy energy 
purchases. In response to South Carolina E&G's observation that a 
utility's native load forecasts evolve in real-time to the point that 
the utility may need to sell off excess energy that was purchased off-
system, we note that our definition would allow a network customer to 
use network service to deliver off-system purchases when the network 
customer purchases the energy with the intent to serve native load.
    431. In enforcing this policy, we will apply the definition of 
``economy energy'' at the time the network customer commits to purchase 
energy. For instance, we will not take issue if a network customer uses 
secondary network service to deliver an hour-ahead purchase that costs 
less than the network customer's generation cost in the hour of 
operation. Similarly, we will not question the use of secondary network 
service by a network customer to deliver a day-ahead off-system 
purchase that costs less than the network customer's forecast 
generation cost, even if real-time system conditions evolve so that the 
realized generation cost is less than the cost of the purchased energy. 
We also would not take issue with a network customer that uses network 
service to deliver off-system block energy because the purchased energy 
is more economic than using its network resources, but makes off-system 
sales during some hours when the block energy purchase is scheduled. In 
other words, in enforcing this policy, we will apply the definition of 
``economy energy'' as it applies to the entire period covered by the 
block purchase and not to a single hour within the block.
``[O]n an As-Available Basis''
    432. Section 28.4 of the pro forma OATT allows a network customer 
to use secondary network service to deliver economy energy purchases to 
its network load from non-designated resources ``on an as-available 
basis.'' However, the current pro forma OATT does not specify how a 
network customer must arrange for secondary network service.
Discussion
    433. We propose to modify section 28.4 of the pro forma OATT by 
clarifying that a network customer need not file an application for 
network service to receive secondary network service, but that all 
other requirements of Part III of the pro forma OATT (except for 
transmission rates) apply to secondary network service. In other words, 
a network customer must request secondary network service on OASIS in a 
manner consistent with pro forma OATT sections 18.1 and 18.2 
(Procedures for Arranging Non-Firm Point-To-Point Transmission Service).
Redirect of Network Service
    434. The current pro forma OATT does not include any provision to 
change the point of receipt for an off-system designated network 
resource, in a manner similar to redirect of point-to-point service. 
However, we are aware that several transmission providers have posted 
business practices that allow network customers either to substitute an 
off-system non-designated network resource for a designated network 
resource or to redirect the point of receipt associated with an 
existing network resource.
Discussion
    435. We propose to clarify that network customers may not redirect 
network service in a manner comparable to the way customers redirect 
point-to-point service. Unlike point-to-point service that is based 
upon a contract-path model consisting of a designated point of receipt 
and point of delivery, network service involves no identified contract 
path and is therefore not a directable service. Rather, network

[[Page 32700]]

service provides for the integration of designated network resources 
and loads using the entire transmission grid in a manner comparable to 
the transmission provider's use of the transmission grid to serve its 
native load customers. When a network customer wants to substitute one 
designated network resource for another, it should terminate the 
designation of the existing network resource and designate a new 
network resource. The network customer can then request to redesignate 
its original network resource by making a request to designate a new 
network resource. Alternatively, a network customer could use secondary 
network service when it wants to substitute a non-designated network 
resource for a designated network resource on an as-available basis.
8. Transmission Curtailments
    436. Section 1.7 of the pro forma OATT defines curtailment as ``a 
reduction in firm or non-firm transmission service in response to a 
transmission capacity shortage as a result of system reliability 
conditions.'' Curtailment provisions for point-to-point service are set 
forth in sections 13.7 and 14.7 for firm and non-firm transmission 
services respectively and the curtailment provisions for network 
service are contained in section 33. Complaints regarding improper 
curtailment of service by transmission providers have been made in a 
variety of proceedings and the Commission has found cases of improper 
curtailment in the past.\387\
---------------------------------------------------------------------------

    \387\ See, e.g., Consolidated Edison Co. of N.Y. v. Public Serv. 
Elec. & Gen. Co., 108 FERC ] 61,120 (2004).
---------------------------------------------------------------------------

    437. In the NOI, the Commission asked whether there is evidence of 
improper curtailment practices by public utility transmission providers 
or customers that warrants reforms to the pro forma OATT. If there is, 
we requested that commenters provide specific examples of such 
practices. We also asked whether transmission providers engaging in 
improper curtailments should be subject to monetary penalties or other 
remedies for market manipulation.
Comments
    438. EEI argues that there do not appear to be many instances of 
improper curtailments and many utilities state that they are not aware 
of any improper curtailments by public utility transmission providers. 
For example, Southern states that curtailments are performed on a non-
discriminatory basis, in accordance with applicable OATT provisions. 
Ameren, KCP&L, and PNM-TNMP state that they are not aware of any 
improper practices that would warrant reforms to the pro forma OATT. 
APPA does not advocate changes to the pro forma OATT regarding 
curtailment, stating that its members express more concerns about the 
denial of service prior to and at the time of scheduling than they do 
regarding curtailment of service once it has commenced. However, APPA 
also notes that most of its members use firm service that is unlikely 
to be interrupted once it is scheduled. Public Power Council, 
Snohomish, MEAG and Salt River concur with APPA that OATT reforms are 
not needed for curtailments.
    439. Transmission customers, particularly IPPs, generally have a 
different view, arguing that the reasons for curtailment are difficult 
to discern, and that information is often insufficient to determine 
whether curtailments have been performed correctly. Northwest IPPs 
state curtailments frequently appear arbitrary. Powerex argues that 
incomplete postings on many transmission systems and the lack of 
transparency in curtailment data could mask improper curtailment. 
Calpine states that it is usually difficult to determine whether a 
curtailment of service is truly justified by system reliability factors 
because the operational facts underlying the utility's curtailment 
decision are unknown. It argues that the criteria for utility 
curtailment decisions are not standardized, making it difficult to 
determine the propriety of curtailment decisions, particularly when 
curtailment is internal to a single area and not performed through the 
NERC TLR process. Calpine recommends that the terms and conditions for 
curtailments be standardized by the new reliability organizations 
created by EPAct 2005, that such terms and conditions be made a formal 
part of the pro forma OATT and the OATTs of public, private and federal 
utilities, and that these be posted on the transmission provider's 
OASIS. Calpine further recommends that regional NERC organizations be 
requested to audit the curtailment practices of all utilities that are 
not members of an RTO/ISO. Constellation asserts that TLRs are a 
``blunt and inefficient mechanism'' for curtailment and calls for a 
requirement that transmission providers provide redispatch options.
    440. In reply to claims that vertically integrated utilities 
provide inadequate information on curtailments, Southern states that 
existing OASIS requirements already require utilities to post a 
considerable amount of information on curtailments, and that the 
information currently posted is adequate to meet customers' needs. 
Nevertheless, Southern also states that while those rules have been 
effective in achieving their intended purpose, incremental additions to 
the information that is available through OASIS could assure customers 
that they have all of the information they need to make prudent 
decisions about transmission service and that they are being treated in 
a fair, equitable, and non-discriminatory way.
    441. Commenters appear divided on the issue of whether there should 
be penalties for improper curtailments. The most common view, expressed 
by EEI and others, is that penalties for improper curtailments should 
be assessed only if the Commission finds that the transmission provider 
imposed the curtailment with the intent to treat a customer in an 
unduly discriminatory or preferential manner. Other commenters 
expressed a wide range of views. Alcoa states that improper 
curtailments should be the subject of monetary penalties. Santa Clara 
contends that transmission providers should be fully liable for any 
damages caused by improper curtailments. On the other hand, Southern 
argues that curtailment is a reliability issue and it would be unwise 
to subject transmission providers to after-the-fact assessments of 
their curtailment decisions. KCP&L notes that the responsibility for 
calling a TLR rests with the reliability coordinator, who makes 
decisions based on the NERC standard, so that penalties for improper 
curtailment activity should be a subject for the ERO.
Discussion
    442. The Commission reminds both transmission providers and 
customers that our regulations require posting of transmission 
curtailment information on OASIS. The OASIS regulations state:

    When any transaction is curtailed or interrupted, the 
Transmission Provider must post notice of the curtailment or 
interruption on the OASIS, and the Transmission Provider must state 
on the OASIS the reason why the transaction could not be continued 
or completed.
    (ii) Information to support any such curtailment or 
interruption, including the operating status of the facilities 
involved in the constraint or interruption, must be maintained and 
made available upon request, to the curtailed or interrupted 
customer, the Commission's Staff, and any other person who requests 
it, for three years.\388\
---------------------------------------------------------------------------

    \388\ We note that we are proposing to change this information 
retention period to five years, consistent with our other proposed 
changes to the OASIS information retention provisions.

---------------------------------------------------------------------------

[[Page 32701]]

    (iii) Any offer to adjust the operation of the Transmission 
Provider's system to restore a curtailed or interrupted transaction 
must be posted and made available to all curtailed and interrupted 
Transmission Customers at the same time.\389\
---------------------------------------------------------------------------

    \389\ 18 CFR 37.6(d)(3) (2005).

    443. Those commenting that they have inadequate information about 
curtailments do not clearly state whether the source of this deficiency 
lies in: (1) The inadequacy of our standards, (2) inadequate compliance 
with these standards, (3) difficulties in dealing with the way the 
information is provided, or (4) some other area. We are, however, 
mindful that objective review of curtailments can require a 
considerable amount of information, some of which may not be provided 
under the present OASIS regulations, or may be provided in an 
inefficient manner. For example, we recognize that it is difficult for 
a customer to determine what network resources were available to the 
transmission provider that could have been redispatched consistent with 
pro forma OATT sections 30.5 and 33.2 to relieve the transmission 
constraint that led to a transmission curtailment. Another example may 
be discerning which discrete transaction(s) could be curtailed on a 
non-discriminatory basis to effectively relieve the constraint 
consistent with pro forma OATT section 13.6. We seek comment on whether 
additional requirements would improve the transparency of transmission 
curtailment information and the ability of customers to make use of 
that information.
    444. With respect to the imposition of penalties, the Commission 
recognizes that the transmission curtailment decision is a reliability 
decision that should be based on applicable reliability standards. 
Moreover, we note that the need for transmission curtailment depends on 
many factors outside the control of an individual transmission 
provider, including loop flows throughout an interconnection. 
Accordingly, we will not propose generic penalties for improper 
transmission curtailments in this rulemaking. However, the absence of 
generic penalties should not be construed to mean that we will tolerate 
intentional behavior that subjects customers to unduly discriminatory 
or preferential actions. We remain vigilant in monitoring for intentionally 
discriminatory provision of transmission service, and stand ready to use 
our enforcement powers and penalty authority when needed.
9. Standardization of Rules and Practices
    445. In Order No. 888, the Commission required each public utility 
that owns, controls, or operates facilities used for transmitting 
electric energy in interstate commerce to file, pursuant section 205 of 
the FPA, a pro forma OATT under which it would provide open access 
transmission services. However, certain rules, standards and practices 
governing the provision of such transmission service (e.g., public 
utility business practices) are not reflected in the pro forma OATT. 
Only when a public utility adopts a rule, standard or practice that 
significantly affects its rates and services has the Commission 
required it to make a filing pursuant to FPA section 205 to amend its 
OATT.\390\ The Commission has applied this policy using a ``rule of 
reason'' test.\391\
---------------------------------------------------------------------------

    \390\ E.g., Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985).
    \391\ See, e.g., Public Serv. Comm'n of N.Y. v. FERC, 813 F.2d 
448, 454 (D.C. Cir. 1987) (holding that the Commission properly 
excused utilities from filing policies or practices that dealt only 
with matters of ``practical insignificance'' to serving customers); 
Midwest Independent Transmission System Operator, Inc., 98 FERC ]
61,137 at 61,401 (``It appears that the proposed Operating Protocols 
could significantly affect certain rates and service and as such are 
required to be filed pursuant to Section 205.''), order granting 
clarification, 100 FERC ] 61,262 (2002).
---------------------------------------------------------------------------

    446. The rule of reason test has arisen primarily with respect to 
protocols or operating procedures used by RTOs and ISOs. For example, 
the Commission has held that while the business practices manuals of 
the Midwest ISO implicate the Commission's jurisdiction because they 
generally involve ``the installation, operation, or use of facilities 
for the transmission or delivery of power * * * in interstate 
commerce,'' they do not require a FPA section 205 filing because ``they 
mostly involve general operating procedures.''\392\ In other cases, the 
facts have required the filing of the rule, standard or practice. For 
example, CAISO proposed to post certain, technical, operational and 
business standards related to dynamic scheduling on its Web site and 
include only the rates under its OATT. There, the Commission found that 
the details contained in the standards are practices that may affect 
the terms and conditions of service significantly, and therefore, under 
the Commission's ``rule of reason,'' must be filed under FPA section 
205.\393\
---------------------------------------------------------------------------

    \392\ Midwest Independent Transmission System Operator, Inc., 
108 FERC ] 61,163 at P 656, 658, order on reh'g, 109 FERC ] 61,157 
(2004), order on reh'g, 111 FERC ] 61,043, order on reh'g, 112 FERC ]
61,086 (2005); see also PJM Interconnection, L.L.C., 81 FERC ]
61,257 at 62,267 (1997) (finding no reason to require filing of the 
PJM Manuals but requiring that such manuals be available for public 
inspection on a permanent basis), order on reh'g, 92 FERC ] 61,282 (2000).
    \393\ California Independent System Operator Corp., 107 FERC ]
61,329 at P 21-22 (2004); see also Southwest Power Pool, Inc., 112 FERC ]
61,303 at P 25 (2005) (requiring that the SPP OATT provide 
sufficient information for market participants to fully understand 
SPP's implementation of an imbalance market), reh'g dismissed, 113 FERC ]
61,115 (2005); PJM Interconnection, L.L.C., 104 FERC ] 61,124 
at P 61 (requiring PJM to place all procedures, standards and 
requirements for proposing that a transmission owner construct a 
specific upgrade, and all procedures for charging customers, in its 
tariff, not in its manuals), order on reh'g, PJM Interconnection, 
L.L.C., 105 FERC ] 61,123 (2003).
---------------------------------------------------------------------------

    447. In the NOI, the Commission asked: (1) Whether all rules, 
standards and practices should be required to be included in public 
utilities' OATTs? (2) If not all, which of such rules, standards and 
practices should be included in public utilities' OATTs? and (3) Should 
rules, standards and practices not required to be included in public 
utilities' OATTs be required to be posted on OASIS to increase transparency?
Included in Open Access Transmission Tariffs
    448. Some commenters argue that the rules, standards and practices 
governing the provision of transmission service should be included in 
public utilities' OATTs.\394\ Occidental states that the inclusion of 
rules, standards and practices governing the provision of transmission 
service in public utilities' OATTs will add much needed clarity as to 
how transmission service is provided. EPSA states that while it may not 
be necessary, or desirable, to require all business practices to be 
incorporated into the OATT, there have been instances where 
transmission providers have adopted business practices that are 
inconsistent with their OATT requirements or that should have been 
filed as OATT amendments. Some commenters also support the inclusion of 
the NAESB standards in the OATT.\395\
---------------------------------------------------------------------------

    \394\ E.g., Occidental, TAPS, and Williams.
    \395\ E.g., Salt River and Snohomish.
---------------------------------------------------------------------------

    449. In contrast, some commenters oppose including rules, standards 
and practices in the OATT.\396\ EEI argues that rules, standards and 
practices should not be included as part of an OATT unless they 
significantly affect rates and service under the OATT. EEI states that 
this is consistent with the Commission's current practice for the 
inclusion of manuals in an OATT. Indicated New York Transmission Owners 
state that the inclusion of rules, standards and practices in the OATT is

[[Page 32702]]

unnecessary and would administratively encumber any future revisions to 
the practices and rules by requiring conforming tariff filings.
---------------------------------------------------------------------------

    \396\ E.g., BPA, EEI, MidAmerican, and Southern.
---------------------------------------------------------------------------

Posted on OASIS
    450. Several commenters believe it would be appropriate to post 
rules, standards and practices on public utilities' OASIS sites.\397\ 
For example, EEI states that it would be appropriate to post all rules, 
standards and practices that are not part of the OATT on a transmission 
provider's OASIS. APPA asserts that, in particular, transmission 
providers should post the methodologies they use to develop ATC and ATC 
calculations should be periodically verified by an independent third 
party.\398\
---------------------------------------------------------------------------

    \397\ E.g., APPA, BPA, EEI, EPSA, MidAmerican, and Southern.
    \398\ See supra Part V.A addressing posting requirements for ATC 
calculation.
---------------------------------------------------------------------------

    451. Other commenters contend that rules, standards and practices 
should be posted on public utilities' OASIS sites only when they are 
not required to be filed.\399\ TAPS argues that any rules, standards 
and practices not required to be filed must be publicly posted on the 
transmission provider's OASIS to provide needed transparency, because 
including essential terms in business practices that are not posted 
makes it very difficult for customers to understand if they are being 
treated fairly by the transmission provider. TDU Systems asserts that 
requiring posting on transmission providers' OASIS sites of any 
standards and practices not included in their OATTs would facilitate 
transactions across several transmission provider systems, especially 
where transmission providers are not participating in RTOs or 
ISOs.\400\ Williams goes one step further and recommends that the 
Commission require that transmission providers both file with the 
Commission and post on their OASIS sites, all policies, practices and 
interpretations used or relied upon to evaluate a request for 
transmission service.
---------------------------------------------------------------------------

    \399\ E.g., Progress Energy and TAPS.
    \400\ Suez Energy NA emphasizes that the posting of rules, 
standards, and practices on OASIS merely ensures that they are 
transparent, it does not ensure that they are non-discriminatory.
---------------------------------------------------------------------------

Discussion
    452. There appears to be broad consensus among the commenters that 
rules, standards and practices not required to be included in a 
transmission provider's pro forma OATT should be posted on the 
transmission provider's OASIS. We agree and propose to require 
transmission providers to post on OASIS all of their rules, standards 
and practices that relate to transmission services. We believe this 
proposal will provide greater transparency and mitigate the potential 
for undue discrimination against customers taking transmission service 
under the transmission provider's OATT.\401\ However, we seek comment 
on how to determine what ``relates'' to transmission service to 
facilitate a consistent interpretation and to minimize discretion on 
what rules, practices and standards should be posted on OASIS.\402\
---------------------------------------------------------------------------

    \401\ We clarify that posting rules, practices and standards on 
the transmission provider's OASIS--in lieu of filing such practices 
with the Commission as part of the transmission provider's pro forma 
OATT--neither insulates a transmission provider from complaints nor 
confers a just and reasonable presumption. We encourage customers to 
call the Commission's Enforcement Hotline with complaints about the 
application of such rules, standards and practices should they 
experience problems with their transmission providers. To the extent 
customers are not satisfied with responses from utilities, they 
should contact the Commission's Enforcement Hotline via telephone 
(202) 502-8390, toll-free 1-888-889-8030, fax (202) 208-0057, or at 
http://www.ferc.gov/cust-protect/enforce-hot.asp Exit Disclaimer.
    \402\ We note that certain rules and practices are already 
required to be posted on OASIS. See, e.g., Order No. 889; Open 
Access Same-Time Information Systems, Order No. 605, 64 FR 34117 
(Jun. 25, 1999), FERC Stats. and Regs. ] 31,075 (1999); Order No. 676.
---------------------------------------------------------------------------

    453. Commenters presented wide ranging positions on the issue of 
what rules, standards and practices to include in the OATT. We do not 
propose to modify our existing policy on this issue at this time.\403\ 
We agree with EPSA's concern that requiring transmission providers to 
include all of their rules, standards and practices in their OATTs 
could decrease a transmission provider's flexibility to change 
businesses practices and respond to the requests of customers. 
Additionally, we believe that requiring transmission providers to file 
all of their rules, standards and practices in their OATTs would be 
impractical and potentially administratively burdensome.\404\
---------------------------------------------------------------------------

    \403\ See supra notes 391-393 and accompanying text.
    \404\ Of course, we will require the filing of certain rules, 
standards and practices when circumstances require. In Order No. 
676, the Commission, among other things, incorporated certain 
business standards developed by NAESB by reference into the 
Commission's regulations and required public utilities to file 
revisions to their OATTs to include these standards. Order No. 676 at P 20.
---------------------------------------------------------------------------

    454. We propose to require, however, that creditworthiness and 
security requirements be included in a transmission provider's OATT. 
The creditworthiness provision in section 11 of the pro forma OATT 
authorizes transmission providers to require ``reasonable credit review 
procedures'' in accordance with ``standard commercial practices,'' to 
determine the ability of transmission customers to meet service 
obligations. Furthermore, to protect transmission providers from the 
risk of non-payment, the provision authorizes the transmission provider 
to require as security a letter of credit or other forms of security 
consistent with the Uniform Commercial Code. In the Creditworthiness 
Policy Statement, the Commission explained that non-RTO or -ISO 
transmission providers generally have not incorporated creditworthiness 
or security requirements into their OATTs.\405\ The Commission stressed 
that transparency of credit procedures and security requirements can 
enhance market certainty and liquidity by allowing customers to 
determine for themselves the information they need to demonstrate 
creditworthiness and the amount and type of security they need to 
receive transmission service. In interpreting the ``reasonable credit 
review procedures'' requirement in section 11 of the pro forma OATT, 
the Commission stated that it expected transmission providers to post 
on their OASIS sites the process and methodologies used to evaluate a 
potential customer's creditworthiness and calculate the necessary 
security.\406\ But it also stated that it would ``consider 
standardizing credit procedures through a generic rulemaking if 
necessary to prevent undue discrimination.'' \407\
---------------------------------------------------------------------------

    \405\ Policy Statement on Electric Creditworthiness, 109 FERC ]
61,186 at P 9 (2004) (Creditworthiness Policy Statement).
    \406\ Id. at P 12. The Commission explained that all 
transmission providers (including RTOs and ISO) were expected to 
``(1) make their credit-related practices more transparent and 
comprehensive; (2) post on their [OASIS sites] the procedures that 
they use to do their credit analyses; and (3) provide a customer 
with a written analysis setting forth how that entity applied its 
credit standards to that customer, if that customer is required to 
provide security.'' Id.
    \407\ Id. at P 15.
---------------------------------------------------------------------------

    455. Our preliminary conclusion is that a transmission provider's 
OATT should contain sufficient information about its credit process and 
requirements to enable customers to understand the information required 
to demonstrate creditworthiness and to determine for themselves the 
general amount and type of security they may need to provide in order 
to receive service. We therefore propose to amend section 11 of the pro 
forma OATT on creditworthiness to require each transmission provider to 
include its creditworthiness and security requirements in a new 
Attachment L to its OATT.

[[Page 32703]]

    456. In the Creditworthiness Policy Statement, the Commission 
explained that, to assess an applicant's credit risk, transmission 
providers should use both qualitative factors, such as the local 
regulatory environment or the applicant's history and financial 
policies, and quantitative factors, such as information included on the 
applicant's financial statements.\408\ We propose to require the new 
Attachment L to include such quantitative and qualitative criteria to 
determine the level of secured and unsecured credit. We also propose to 
require the new Attachment L to include the following elements: (1) A 
summary of the procedure for determining the level of secured and 
unsecured credit; (2) a list of the acceptable types of collateral/
security; (3) a procedure for providing customers with reasonable 
notice of changes in credit levels and collateral requirements; (4) a 
procedure for providing customers, upon request, a written explanation 
for any change in credit levels or collateral requirements; (5) a 
reasonable opportunity to contest determinations of credit levels or 
collateral requirements; and (6) a reasonable opportunity to post 
additional collateral, including curing any non-creditworthy 
determination. We propose to allow these basic elements to be 
supplemented with a credit guide or manual to be posted on OASIS.
---------------------------------------------------------------------------

    \408\ Id. at P 13 & nn.13-14. An evaluation using both sets of 
factors would allow an applicant without a credit rating or a strong 
balance sheet, but with solid credit, to meet the creditworthiness 
criteria. Id. at P 14.
---------------------------------------------------------------------------

    457. Though we are proposing to require transmission providers to 
incorporate the creditworthiness and security methodologies into their 
OATTs, we recognize that there is a balance here between the burden on 
the transmission provider of adding these methodologies to its OATT and 
the need for Commission review and approval if methodologies frequently 
change. We seek comment on whether the proposal is unduly burdensome.
10. OATT Definitions
    458. In the NOI, the Commission requested comment on whether new or 
amended pro forma OATT definitions were necessary. The Commission also 
noted that new section 215(a)(4) of the FPA, which was adopted as part 
of EPAct 2005, defines the term ``reliable operation.'' \409\ We 
therefore asked whether this definition should be incorporated in the 
pro forma OATT.
---------------------------------------------------------------------------

    \409\ EPAct 2005 sec. 1211(a) (to be codified at FPA section 
215(a), 16 U.S.C. 824o). Section 215(a)(4) defines ``reliable 
operation'' as ``operating the elements of the bulk power system 
within equipment and electric system thermal, voltage, and stability 
limits so that instability, uncontrolled separation, or cascading 
failures of such system will not occur as a result of a sudden 
disturbance, including a cybersecurity incident, or unanticipated 
failure of system elements.''
---------------------------------------------------------------------------

    459. Though MidAmerican urges the Commission to incorporate the 
definition of ``reliable operation'' into the pro forma OATT, other 
commenters argue that the definition of reliable operation should not 
be included in the pro forma OATT.\410\ Southern argues that the 
definition of reliable operation included in section 215 of the FPA 
would impose a higher standard on transmission providers than is 
currently required by well-established NERC standards. Southern and EEI 
assert that the system is not planned to be able to guarantee that 
operations will not be impaired under any conditions. Southern argues 
that transmission providers should not be held to a higher standard of 
having to ensure that the system can continue to be operated even if a 
``sudden disturbance, including a cybersecurity incident or 
unanticipated failure of system elements'' occurs.
---------------------------------------------------------------------------

    \410\ E.g., EEI, Powerex, Snohomish, Southern, Suez Energy NA, 
and TAPS.
---------------------------------------------------------------------------

    460. Along with Southern, EEI contends that the ERO should 
establish standards related to reliable operation. EEI states that 
section 215 of the FPA simply gives the Commission jurisdiction over 
reliability standards, which are defined as standards for the reliable 
operation of the transmission system; it does not require transmission 
providers to meet a ``reliable operation'' standard. This is an 
important distinction, EEI continues, because while a transmission 
provider may adopt reasonable reliability standards, that does not 
guarantee that it will in all instances meet a ``reliable operation'' 
requirement, which would require the transmission provider to in all 
instances prevent instability, uncontrolled separation or cascading 
failures despite sudden disturbances, cybersecurity incidents, or 
unanticipated failures of system elements. EEI and Southern contend 
that because the ERO will implement the directives of Congress 
contained in section 215, the ERO will be best suited to establish the 
reliability standards that incorporate principles of reliable operation.
    461. TAPS suggests that what is more important than adding a 
``reliable operation'' definition is making explicit in the tariff what 
the Commission stated in its Policy Statement on Matters Related to 
Bulk Power System Reliability (Reliability Policy Statement) \411\--
that transmission provider obligations under the pro forma OATT are 
subject to an overriding ``Good Utility Practice'' requirement that 
includes compliance with NERC reliability standards or more stringent 
regional reliability council standards.
---------------------------------------------------------------------------

    \411\ Policy Statement on Matters Related to Bulk Power System 
Reliability, 107 FERC ] 61,052 at P 23, clarified, 108 FERC ] 61,288 
(2004); Supplement to Policy Statement on Matters Related to Bulk 
Power System Reliability, 110 FERC ] 61,096 (2005).
---------------------------------------------------------------------------

Discussion
    462. We propose to require transmission-owning public utilities to 
modify the definition of Good Utility Practice in their respective 
OATTs to reference the reliable operation definition adopted in section 
215 of the FPA. We propose to take this action for two reasons. First, 
the Commission indicated in the Reliability Policy Statement that it 
expects public utilities operating transmission facilities under the 
pro forma OATT to conform to prevailing reliability standards. The 
Commission finds that referencing the reliable operation definition in 
section 215 of the FPA satisfies our requirement that transmission 
providers provide safe and reliable transmission service to customers 
taking service under the pro forma OATT. Second, we are mindful of the 
obligation placed on ``all users, owners and operators of the bulk 
power system'' under section 215(b) of the FPA to ``comply with 
reliability standards'' that will take effect under this section. Those 
reliability standards must ``provide for reliable operation of the 
bulk-power system.'' \412\ When the ERO is certified by the Commission 
and we approve its reliability standards, those standards will be based 
on the same definition of reliable operation we propose to incorporate 
into the pro forma OATT. We agree with EEI and Southern that the ERO is 
best suited to develop reliability standards for the Commission's 
approval, but our proposal to incorporate the definition of reliable 
operation does not establish a reliability standard; rather, we believe 
it reflects Congress's benchmark for acceptable utility practice. It 
therefore belongs in our definition of Good Utility Practice in the pro 
forma OATT.
---------------------------------------------------------------------------

    \412\ Section 215(a)(3) of the FPA.
---------------------------------------------------------------------------

    463. In addition to amending the definition of Good Utility 
Practice, we propose to add a definition for ``non-firm sales'' to 
clarify section 30.4 of the pro forma OATT. A number of transmission 
providers have modified section 30.4 of the OATT to state that ``The 
Network Customer shall not operate its designated Network Resources 
located in the Network

[[Page 32704]]

Customer's or Transmission Provider's Control Area such that the output 
of those facilities exceeds its designated Network Load, plus non-firm 
sales delivered pursuant to Part II of the Tariff, plus losses'' 
(emphasis added). We propose to define ``non-firm sales'' as ``an 
energy sale for which delivery or receipt of the energy may be 
interrupted for any reason or for no reason, without liability on the 
part of either the buyer or seller.'' This is the definition of non-
firm sales used in a number of industry-standard master power sales 
agreements, including the EEI Master Purchase and Sale Agreement. We 
propose to clarify that, for the purposes of applying section 30.4 of 
the pro forma OATT, energy sales that can only be interrupted to 
maintain system reliability will be considered firm sales.
    464. We also propose to add two new definitions that are required 
to implement our proposed reforms. For example, we propose a definition 
of ``affiliate'' in section 1.1 of the revised pro forma OATT incident 
to our proposed change to the pricing of reassigned capacity. We also 
propose a new definition of ``pre-confirmed application'' in section 
1.40 of the revised pro forma OATT incident to our proposal to give 
priority to requests that are pre-confirmed.

E. Enforcement

1. General Policy
a. Compliance Review Regime
Comments
    465. A number of commenters indicate that a strong program to audit 
compliance with the pro forma OATT is crucial to preventing undue 
discrimination in the provision of transmission service. APPA argues 
that the Commission should establish a regime of systematic tariff 
compliance reviews because the OATT is at bottom a behavioral remedy 
rather than a structural one, so active Commission oversight is 
necessary. In addition, APPA notes that OATT transmission customers 
(especially network customers that are dependent upon the transmission 
systems of their neighboring public utility OATT transmission 
providers) are often reluctant to open the ``can of worms'' that filing 
a section 206 complaint against their transmission providers entails. 
Powerex urges the Commission to establish systematic tariff compliance 
audits as a monitoring tool because remedies and penalties alone are 
structurally ill-suited to address the myriad of idiosyncratic 
deviations from the Commission's policies and standards that currently 
exist. TAPS asserts that, while customer complaints are an indication 
that something is awry, the lack of transparency makes it very hard for 
customers to detect discrimination and tariff violations on the part of 
the transmission provider. TAPS suggests that customers often conclude 
that a complaint process is not cost effective because even if they 
ultimately prevail, they will have lost out on the purchase opportunity 
that prompted the complaint.
Discussion
    466. The Commission intends to maintain a strong audit program to 
determine whether transmission providers and transmission customers are 
in compliance with the new pro forma OATT. This audit program will 
include operational audits similar to the OATT compliance components of 
audits conducted by Commission staff in the past.
    467. These audits will determine compliance with specific 
provisions of the OATT. Staff's findings and recommendations will be 
detailed in public audit reports issued in accordance with the 
Commission's authority. If an audit is contested, it will be disposed 
of consistent with the Commission's final rule on disposition of 
contested operational audits. The Commission staff's compliance audits 
historically have included the collection of information regarding the 
audit target's overall operations. In this vein, the Commission staff's 
OATT compliance audits may also collect information regarding 
implementation of a transmission provider's OATT, with the intent that 
Commission staff may share the information it gathers with the 
Commission subject to all applicable ex parte rules.
b. Use of Independent Third Party Audits
Comments
    468. A number of commenters indicate that the Commission should not 
rely on third party audits as the primary means of ensuring compliance 
with the OATT. APPA states that if an OATT Transmission Provider 
retains and pays an ``independent reviewer'' to prepare compliance 
audit reports, someone will inevitably question the reviewer's 
independence. Therefore, APPA argues that it might be better for the 
Commission itself to prepare the reports, or to retain a consultant to 
do so. Southern suggests that the Commission's existing mechanisms, 
coupled with new rules that will ensure that all regulated entities 
subject to investigations or audits are afforded their full due process 
rights, should be adequate to ensure compliance with OATT provisions.
    469. A number of commenters also indicate that the Commission 
should require third party audits for frequent abusers. EEI suggests 
that a transmission provider that is found to have a systematic or 
continuing violation of the OATT could be required to hire an 
independent reviewer to monitor its future compliance for a period of 
time after the violation occurred. TVA suggests that, if a particular 
transmission provider repeatedly misapplies its OATT, the Commission 
should at that point consider requiring that transmission provider to 
hire an independent monitor for a defined period of time as a remedy 
for those actual infractions. NRECA argues that those transmission 
providers who are consistently in violation or who do not cure audit 
findings in a timely manner should see both an increase in frequency 
and further scrutiny from the audit process.
Discussion
    470. We propose to have Commission staff conduct audits of 
compliance with the new OATT. Commission staff is in a unique position 
to conduct OATT compliance audits and recommend remedial action 
consistent with previous audits. In addition, entities audited by 
Commission staff now have clear and assured due process rights as the 
result of Order No. 675.
    471. We may require third party audits as part of an individual 
compliance plan we order an audited party to undertake when we issue 
the Commission staff's audit report. The Commission staff monitors 
compliance with all of its audit recommendations as part of its regular 
practice. We may, in selected cases, decide to enhance this regular 
monitoring by requiring an audited party to hire an independent 
reviewer to continue compliance audits after the Commission staff's 
audit has ended. We could take such action in response to a number of 
circumstances, including, but not limited to, identification of 
systematic OATT violations, violations that require on-going 
monitoring, or a pattern of repeated OATT violations. Under these 
circumstances, the audited party should bear the burden of on-going 
compliance monitoring. If we decide to order independent OATT 
compliance audits as part of an individual audited party's compliance 
plan, we will specify the scope and duration of the audits.

[[Page 32705]]

2. Civil Penalties
a. Background
    472. The NOI observed that the existing OATT allows transmission 
providers to impose certain operational penalties on customers for 
tariff violations, but does not address the adverse consequences to a 
transmission provider who violates its OATT. It also summarized the 
broad variety of remedies and sanctions available for enforcement of 
its rules and regulations, including the enhanced civil penalty 
authority provided by EPAct 2005.\413\
---------------------------------------------------------------------------

    \413\ EPAct 2005 expanded the Commission's civil penalty 
authority under the FPA to encompass violations of all provisions of 
FPA Part II (EPAct 2005 section 1284(e)(1) (to be codified at 
section 316A of the FPA, 16 U.S.C. 825o-1)), and established the 
maximum civil penalty the Commission can assess under FPA Part II as 
$1 million per day per violation (EPAct 2005 section 1284(e)(2) (to 
be codified at section 316A of the FPA, 16 U.S.C. 825o-1)).
---------------------------------------------------------------------------

    473. In the NOI, the Commission asked for comments on whether we 
should address the issue of remedies or penalties against transmission 
providers as part of OATT reform. It also asked if transmission 
providers should be subject to revocation of their market-based rate 
authority for certain OATT violations, and if certain violatins should 
be considered market manipulation under the Market Behavior Rules \414\ 
and section 1283 of EPAct 2005.\415\
---------------------------------------------------------------------------

    \414\ Investigation of Terms and Conditions of Public Utility 
Market-Based Rate Authorizations, 105 FERC ] 61,218 (2003), order on 
reh'g, 107 FERC ] 61,175 (2004).
    \415\ NOI at P 15.
---------------------------------------------------------------------------

    474. Subsequent to the NOI, on October 20, 2005 the Commission 
issued its Enforcement Policy Statement, which discusses the factors 
the Commission will take into account in determining remedies and 
sanctions for violations, including civil penalties.\416\ Also, in 
EPAct 2005, Congress provided the Commission with specific anti-
manipulation authority.\417\ On January 19, 2006, to implement this new 
authority, the Commission issued Order No. 670 (Anti-manipulation 
Rule),\418\ adopting a new Part 1c of its regulations, under which it 
is ``unlawful for any entity, directly or indirectly, in connection 
with the purchase or sale of electric energy or the purchase or sale of 
transmission services subject to the jurisdiction of the Commission, 
(1) to use or employ any device, scheme, or artifice to defraud, (2) to 
make any untrue statement of a material fact or to omit to state a 
material fact necessary in order to make the statements made, in the 
light of the circumstances under which they were made, not misleading, 
or (3) to engage in any act, practice, or course of business that 
operates or would operate as a fraud or deceit upon any entity.'' \419\ 
The Anti-manipulation Rule made it unnecessary to retain Market 
Behavior Rules 2 or 6. Accordingly, on February 16, 2006, the 
Commission rescinded Market Behavior Rules 2 and 6 and codified the 
substance of Market Behavior Rules 1, 3, 4, and 5 in the Commission's 
regulations.\420\
---------------------------------------------------------------------------

    \416\ Enforcement of Statutes, Order, Rules and Regulations, 
Policy Statement on Enforcement, 113 FERC ] 61,068 at P 17-20 (2005) 
(Enforcement Policy Statement).
    \417\ EPAct 2005 sec. 1283 (to be codified at section 222 of the 
FPA, 16 U.S.C. 824v). Congress prohibited the use or employment of 
``any manipulative or deceptive device or contrivance'' in 
connection with the purchase or sale of electric energy or 
transmission services subject to the jurisdiction of the Commission. 
Congress directed the Commission to give these terms the same 
meaning as under the Securities Exchange Act of 1934, 15 U.S.C. 
78j(b) (2000).
    \418\ Prohibition of Energy Market Manipulation, Order No. 670, 
71 FR 4244 (Jan. 26, 2006), FERC Stats. & Regs. ] 31,202, reh'g 
denied, 114 FERC ] 61,300 (2006).
    \419\ Id., 71 FR 4244, 4258 (Jan. 26, 2006) (to be codified at 
18 CFR 1c.2(a)).
    \420\ Investigation of Terms and Conditions of Public Utility 
Market-Based Rate Authorizations, 114 FERC ] 61,165 (2005). The 
primary purpose of the Market Behavior Rules was to prohibit market 
manipulation by public utility sellers acting under market-based 
rate authority.
---------------------------------------------------------------------------

b. Whether Civil Penalties Should Be Specified in the OATT
Comments
    475. Commenters often did not distinguish between operational 
penalties and civil penalties in their comments about the need for 
additional penalties in the OATT. EEI and MidAmerican made the 
distinction, asserting that civil penalties should not be specified in 
the OATT. They and others contend that: enforcement actions, including 
civil penalties, should be reviewed on a case-by-case basis; \421\ 
civil penalties should be based upon the seriousness of the violation; 
\422\ penalties should require proof of intent or willfulness; \423\ 
penalties should only apply for repeated violations; \424\ and, penalty 
procedures should provide for due process.\425\
---------------------------------------------------------------------------

    \421\ E.g., Entergy, Santa Clara, Steel Manufacturers 
Association, WAPA, and Williams.
    \422\ Steel Manufacturers Association.
    \423\ E.g., EEI, KCP&L, Progress Energy, Public Power Council, 
Southern, and Xcel.
    \424\ E.g., Alberta Intervenors, Public Power Council, 
Snohomish, Suez Energy NA, and TDU Systems.
    \425\ E.g., Bonneville, EEI, Southern, and Nevada Companies.
---------------------------------------------------------------------------

Discussion
    476. The Commission intends to enforce OATT provisions in a firm 
but fair manner. For example, the Commission elsewhere is proposing 
that transmission providers as well as transmission customers be 
subject to specified operational penalties for violations of certain 
OATT provisions. However, aside from these operational penalties, the 
Commission does not intend to provide a schedule of enforcement 
remedies and sanctions in the OATT. Instead, the Commission prefers to 
examine violations and determine the appropriate response for a 
violation on a case-by-case basis. The Commission has a broad array of 
equitable remedies and sanctions for violations.\426\ Our enhanced 
civil penalties, as provided by EPAct 2005, are among the available 
sanctions for violations of the Commission's statutes, rules, 
regulations and orders, including instances of undue discrimination and 
market manipulation.
---------------------------------------------------------------------------

    \426\ Enforcement Policy Statement at P 4. The ``enhanced civil 
penalty authority will operate in tandem with our existing authority 
to require disgorgement of unjust profits obtained through 
misconduct and/or to condition, suspend, or revoke certificate 
authority or other authorizations, such as market-based rate 
authority for sellers of electric energy.'' Id. at P 12.
---------------------------------------------------------------------------

    477. Although we will look at violations on a case-by-case basis 
and not identify in this proposed rule specific penalties for different 
violations, the Enforcement Policy Statement provides guidance and 
regulatory certainty regarding enforcement and places entities subject 
to our jurisdiction on notice of the consequences of violations.\427\ 
As we noted, ``[I]t is important that we retain the discretion and 
flexibility to address each case on its merits, and to fashion remedies 
appropriate to the facts presented, including any mitigating factors.'' 
\428\
---------------------------------------------------------------------------

    \427\ Id. at P 1.
    \428\ Id. at P 13. Several commenters supported the application 
of the Enforcement Policy Statement to OATT violations. E.g., APPA, 
EEI, Midwest SATs, National Grid, and TAPS.
---------------------------------------------------------------------------

    478. As the facts of a specific matter warrant, we will seek 
disgorgement of unjust profits that are the result of a violation. 
Violators should not retain the gains acquired as the result of the 
violation. OATT violators will be expected to disgorge unjust profits 
whenever they can be determined or reasonably estimated.\429\ In 
addition, as warranted by the facts, civil penalties may also be 
assessed. Those penalties (up to $1 million per day per violation), 
however, can be mitigated by the factors set forth in the Enforcement 
Policy Statement, such as self-reporting, compliance programs, and 
cooperation

[[Page 32706]]

with staff from the Commission's Office of Enforcement.\430\
---------------------------------------------------------------------------

    \429\ Enforcement Policy Statement at P 19 and P 23.
    \430\ Id. at P 6 and P 21-27.
---------------------------------------------------------------------------

c. Whether Transmission Providers Should Be Subject to Revocation of 
Their Market-Based Rates for OATT Violations.
Comments
    479. In the NOI, the Commission also asked if transmission 
providers should be subject to revocation of their market-based rate 
authority for certain OATT violations.\431\ Some commenters agree that 
revocation of market-based rates could be an appropriate remedy.\432\ 
EPSA asserts that revocation of market-based rate authority should be 
among the penalties the Commission could impose for serious violations 
of the OATT, such as when more transmission capacity is set aside than 
is actually needed to serve native load, or undue preferences are 
extended to native load or affiliate transactions. TAPS states that 
where lack of ATC forecloses network customer access to alternatives, a 
transmission provider should not be able to make sales of electric 
power at market-based rates and should be required to offer embedded-
cost-based sales. APPA asserts that whether a transmission provider's 
violation of the OATT merits possible revocation of its market-based 
rate authority depends on the nature and severity of the violation. 
APPA argues that if the violation concerns practices that favor the 
transmission provider's own wholesale merchant function at the expense 
of its third-party competitors, and if that violation is willful or 
repeated, then revocation or conditioning of the market-based rate 
authority of the transmission provider's merchant function may be 
warranted.\433\
---------------------------------------------------------------------------

    \431\ NOI at P 15.
    \432\ E.g., Arkansas Cities, NRECA, Occidental, Snohomish, and Williams.
    \433\ APPA at 32.
---------------------------------------------------------------------------

    480. Other commenters argue that revocation of market-based rate 
authority should be reserved for market behavior violations, not OATT 
violations.\434\ EEI and MidAmerican argue that the Commission has 
separated public utilities' transmission functions from their marketing 
functions and, thus, penalties for violation of the OATT should be kept 
separate from penalties imposed for market behavior violations. 
PacifiCorp contends that the Commission's new penalty authority is 
sufficient to ensure compliance with the OATT and that there no longer 
is a need to consider revocation of market-based rate authority. 
Progress Energy states that the Commission should not penalize the 
utility's merchant function for violations of the OATT caused by the 
utility's transmission function. Ameren and Southern would add a 
``willful'' or ``intent'' requirement to revoking market-based rates 
for an OATT violation.
---------------------------------------------------------------------------

    \434\ E.g., EEI, MidAmerican, PacifiCorp, PNM-TNMP, and Progress Energy.
---------------------------------------------------------------------------

Discussion

    481. As discussed in the Enforcement Policy Statement, the better 
approach is to look at all of the facts and circumstances of each 
violation before deciding on any remedy or sanction.\435\ There may be 
OATT violations in circumstances that, after applying the factors in 
the Enforcement Policy Statement, merit revocation or limitation of 
market-based rate authority. However, before the Commission will 
consider revoking an entity's market-based rate authority for a 
violation of the OATT, there must be a nexus between the specific facts 
relating to the OATT violation and the entity's market-based rate 
authority. The Commission proposes that if it determines, as a result 
of a significant OATT violation, that the market-based rate authority 
of a transmission provider will be revoked within a particular market, 
each affiliate of the transmission provider that possesses market-based 
rate authority will have it revoked in that market on the effective date of 
revocation of the transmission provider's market-based rate authority.
---------------------------------------------------------------------------

    \435\ Enforcement Policy Statement at P 18. Among the factors 
examined are ``willfulness'' and ``intent'' of the violator. Id. at P 20.
---------------------------------------------------------------------------

d. Whether Certain OATT Violations Should Be Considered Market Manipulation 
Under the Market Behavior Rules and Section 1283 of EPAct 2005.
Comments
    482. In the NOI, the Commission asked if specific OATT violations 
should be considered market manipulation under the Market Behavior 
Rules and section 1283 of EPAct 2005.\436\ The Commission then 
suggested that one such type of violation might be when a transmission 
provider sets aside more transmission capacity than is needed to serve 
native load, but uses the capacity for third-party sales.\437\
---------------------------------------------------------------------------

    \436\ NOI at P 15. Section 1283 of EPAct 2005 establishes 
section 222 of the FPA (to be codified at 16 U.S.C. 824v).
    \437\ NOI at P 15.
---------------------------------------------------------------------------

    483. None of the commenters want specific violations identified in 
the OATT to be deemed per se market manipulation. Some commenters 
prefer to have the Commission approach these matters on case-by-case 
basis.\438\
---------------------------------------------------------------------------

    \438\ E.g., APPA, Entergy, Nevada Companies, Public Power 
Council, and Southern.
---------------------------------------------------------------------------

    484. Some commenters, like Constellation, identify OATT violations 
that may constitute market manipulation. Ameren, EEI, and Occidental 
argue that intentionally setting aside more transmission capacity than 
is needed to serve native load could constitute market manipulation. 
LG&E states that the key factor is ``intent.'' LG&E provides an example 
in which ATC becomes available as a result of less-than-expected native 
load requirements, and not because the transmission owner intentionally 
overstated native load requirements, and the transmission owner's 
affiliate followed proper reservation and scheduling protocol in a 
manner applicable to all potential transmission customers. Under these 
circumstances, LG&E contends, the Commission's imposition of a civil 
penalty would be inappropriate given the absence of intent to impart 
false or misleading information into the marketplace or hoard transmission.
    485. Occidental suggests that curtailments of firm transmission 
service designed to permit wholesale power sales by the merchant 
function of the transmission provider or an affiliate should also be 
considered market manipulation. Suez Energy NA argues that incidents of 
affiliate abuse by a transmission provider may be considered market 
manipulation pursuant to section 1283 of EPAct 2005. TAPS states that 
certain withholding of transmission capacity can rise to the level of a 
violation of the Commission's market behavior rules and its new anti-
manipulation authority if the withholding reduces the supply of both 
transmission and generation in a market, which artificially raises prices.
Discussion
    486. As explained above, we now are examining market manipulation 
in the context of Part 1c of our regulations. We do not propose to 
identify in the OATT specific conduct as per se market manipulation. As 
noted in Order No. 670, market manipulation is a fact-intensive 
determination.\439\ We do not want to restrict our fact-finding to 
specific types of violations. Although certain fraudulent or deceptive 
practices concerning the OATT could qualify as market manipulation 
under Order No. 670, the Commission declines to address such 
circumstances generically

[[Page 32707]]

in this rulemaking and instead will consider them on a case-by-case 
basis, if and when they arise, under the standards set forth in Order 
No. 670.
---------------------------------------------------------------------------

    \439\ Anti-manipulation Rule at P 72.
---------------------------------------------------------------------------

VI. Information Collection Statement

    487. The following collections of information contained in this 
proposed rule have been submitted to the Office of Management and 
Budget (OMB) for review under section 3507(d) of the Paperwork 
Reduction Act of 1995.\440\ OMB's regulations require OMB to approve 
certain information collection requirements imposed by agency rule.\441\
---------------------------------------------------------------------------

    \440\ 44 U.S.C. 3507(d) (2000).
    \441\ 5 CFR 1320.11 (2005).
---------------------------------------------------------------------------

    488. Comments are solicited on the need for this information, 
whether the information will have practical utility, ways to enhance 
the quality, utility, and clarity of the information to be collected, 
and any suggested methods for minimizing respondents' burden, including 
the use of automated information techniques.
    Burden Estimate: The public reporting and records retention burdens 
for the proposed reporting requirements and the records retention 
requirement are as follows.\442\
---------------------------------------------------------------------------

    \442\ These burden estimates apply only to this NOPR and do not 
reflect upon all of FERC-516 or FERC-717.

----------------------------------------------------------------------------------------------------------------
                                                     Number of       Number of       Hours per     Total annual
                 Data collection                    respondents      responses       response          hours
----------------------------------------------------------------------------------------------------------------
Part 35 (FERC-516):
Conforming tariff changes.......................             176               1              25           4,400
Revision of Imbalance Charges...................             176               1               5             880
ATC revisions...................................             176               1              40           7,040
Planning (Attachment K).........................             176               1             100          17,600
Congestion studies..............................             176               1             250          44,000
Attestation of network resource commitment......             176               1               1             176
Quarterly Reports for capacity reassignment.....             176               1              60          10,560
Operational Penalty annual filing...............             176               1              10           1,760
Creditworthiness--include criteria in the tariff             176               1              40           7,040
¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤
    Sub Total Part 35...........................  ..............  ..............  ..............          93,456
Part 37 (FERC-717):
ATC-related standards...........................
NERC/NAESB Team to develop......................               1               1           1,920           1,920
Review and comment by utility...................             176               1              20           3,520
Implementation by each utility..................             176               1              40           7,040
Mandatory data exchanges........................             176               1              80          14,080
Explanation of change of ATC values.............             176               1             100          17,600
Reevaluate CBM and post quarterly...............             176               1              20           3,520
Post OASIS metrics; requests accepted/denied....             176               1              80          14,080
Posting of metrics for System Impact Studies....             176               1             100          17,600
Post all rules to OASIS.........................             176               1               5             880
¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤
    Sub Total (Part 37).........................  ..............  ..............  ..............          80,240
¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤
        Total (Part 35 + Part 37)...............  ..............  ..............  ..............         173,696
¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤¤
Recordkeeping...................................             176               1              30           5,280
----------------------------------------------------------------------------------------------------------------

Total Annual Hours for Collection:
    Reporting + recordkeeping hours = 173,696 + 5,280 = 178,976 hours.
Cost to Comply:
Reporting = $19,801,344
hour), consultant ($150), technical ($80), and administrative support 
($25))
Recordkeeping = $1,392,160
$89,760
$1,302,400
Total costs = $21,193,504
    Labor $ ($19,801,344 + $89,760) + Recordkeeping Storage Costs 
($1,302,400)
    OMB's regulations require it to approve certain information 
collection requirements imposed by an agency rule. The Commission is 
submitting notification of this proposed rule to OMB. If the proposed 
requirements are adopted they will be mandatory requirements.
    Title: FERC-516, Electric Rate Schedules and Tariff Filings; FERC-
717 Standards for Business Practices and Communication Protocols for 
Public Utilities.
    Action: Proposed Collections.
    OMB Control Nos. 1902-0096 and 1902-0173.
    Respondents: Business or other for profit.
    Frequency of responses: On occasion.
    Necessity of the Information:
    489. The Federal Energy Regulatory Commission is proposing 
amendments to its regulations adopted in Order Nos. 888 and 889, and to 
the pro forma open access transmission tariff, to ensure that 
transmission services are provided on a basis that is just, reasonable 
and not unduly discriminatory or preferential. The purpose of this 
rulemaking is to strengthen the pro forma OATT to ensure that it 
achieves its original purpose--remedying undue discrimination--not to 
create new market structures. We propose to achieve this goal by 
increasing the clarity and transparency of the rules applicable to the 
planning and use of the transmission system and by addressing 
ambiguities and the lack of sufficient detail in several important 
areas of the pro forma OATT. The lack of specificity in the pro forma 
OATT creates opportunities for undue discrimination as well as making 
the undue discrimination that does occur more difficult to detect. To 
accomplish this we are proposing five objectives: (1) To improve 
transparency and

[[Page 32708]]

consistency in several critical areas, by providing for greater 
consistency in the calculation of ATC, (2) to reform the transmission 
planning requirements of the pro forma OATT to eliminate potential 
undue discrimination and support the construction of adequate 
transmission facilities to meet the needs of all load-serving entities, 
(3) to remedy certain portions of the pro forma OATT that may have 
permitted utilities to discriminate against new merchant generation, 
including intermittent generation, (4) to provide for greater 
transparency in the provision of transmission service to allow 
transmission customers better access to information to make their 
resource procurement and investment decisions, as well as to increase 
the Commission's ability to detect any remaining incidents of undue 
discrimination, and (5) to reform and provide greater clarity in areas 
that have generated recurring disputes over the past 10 years, such as 
rollover rights, ``redirects,'' and generation redispatch. The reforms 
proposed in this NOPR are intended to address deficiencies in the pro 
forma OATT that have become apparent since the implementation of Order 
No. 888 in 1996 and to facilitate improved planning and operation of 
transmission facilities.
    490. Interested persons may obtain information on the reporting 
requirements by contacting the following: Federal Energy Regulatory 
Commission, 888 First Street, NE., Washington, DC 20426, [Attention: 
Michael Miller, Office of the Executive Director, Phone: (202) 502-
8415, fax: (202) 273-0873, e-mail: michael.miller@ferc.gov.]
    491. For submitting comments concerning the collections of 
information and the associated burden estimate(s), please send your 
comments to the contact listed above and to the Office of Information 
and Regulatory Affairs, Office of Management and Budget, 725 17th 
Street, NW., Washington, DC 20503 [Attention: Desk Officer for the 
Federal Energy Regulatory Commission, phone (202) 395-4650, fax: (202) 
395-7285. Due to security concerns, comments should be sent 
electronically to the following e-mail address: 
oira_submission@omb.eop.gov. Please reference the docket number of this 
rulemaking in your submission.

VII. Environmental Analysis

    492. The Commission is required to prepare an Environmental 
Assessment or an Environmental Impact Statement for any action that may 
have a significant adverse effect on the human environment.\443\ The 
Commission concludes that neither an Environmental Assessment nor an 
Environmental Impact Statement is required for this NOPR under section 
380.4(a)(15) of the Commission's regulations, which provides a 
categorical exemption for approval of actions under sections 205 and 
206 of the FPA relating to the filing of schedules containing all rates 
and charges for the transmission or sale subject to the Commission's 
jurisdiction, plus the classification, practices, contracts and 
regulations that affect rates, charges, classifications and services.\444\
---------------------------------------------------------------------------

    \443\ Regulations Implementing the National Environmental Policy 
Act, Order No. 486, 52 FR 47897 (Dec. 17, 1987), FERC Stats. & Regs. ]
30,783 (1987).
    \444\ 18 CFR 380.4(a)(15) (2005).
---------------------------------------------------------------------------

VIII. Regulatory Flexibility Act Analysis

    493. The Regulatory Flexibility Act of 1980 (RFA) \445\ generally 
requires a description and analysis of proposed rules that will have 
significant economic impact on a substantial number of small entities. 
This rule applies to public utilities that own, control or operate 
interstate transmission facilities, not to electric utilities per se. 
The total number of public utilities that, absent waiver, would have to 
modify their current OATTs by filing the revised pro forma OATT is 
176.\446\ Of these only six public utilities, or less than two percent, 
dispose of four million MWh or less per year.\447\ The Commission does 
not consider this a substantial number, and in any event, these small 
entities may seek waiver of these requirements.\448\ Moreover, the 
criteria for waiver that would be applied under this rulemaking for 
small entities is unchanged from that used to evaluate requests for 
waiver under Order Nos. 888 and 889. Thus, small entities who have 
received waiver of the requirements to have on file an open access 
tariff or to operate an OASIS would be unaffected by the requirements 
of this proposed rulemaking.
---------------------------------------------------------------------------

    \445\ 5 U.S.C. 601-612 (2000).
    \446\ The sources for this figure are FERC Form No. 1 and FERC 
Form No. 1-F data.
    \447\ Id.
    \448\ The Regulatory Flexibility Act defines a ``small entity'' 
as ``one which is independently owned and operated and which is not 
dominant in its field of operation.'' See 5 U.S.C. 601(3) and 
601(6)(2000); 15 U.S.C. 632(a)(1)(2000). In Mid-Tex Elec. Coop. v. 
FERC, 773 F.2d 327, 340-343 (D.C. Cir. 1985), the court accepted the 
Commission's conclusion that, since virtually all of the public 
utilities that it regulates do not fall within the meaning of the 
term ``small entities'' as defined in the Regulatory Flexibility 
Act, the Commission did not need to prepare a regulatory flexibility 
analysis in connection with its proposed rule governing the 
allocation of costs for construction work in progress (CWIP). The 
CWIP rules applied to all public utilities. The revised pro forma 
OATT will apply only to those public utilities that own, control or 
operate interstate transmission facilities. These entities are a 
subset of the group of public utilities found not to require 
preparation of a regulatory flexibility analysis for the CWIP rule.
---------------------------------------------------------------------------

IX. Comment Procedures

    494. The Commission invites interested persons to submit comments 
on the matters and issues proposed in this notice to be adopted, 
including any related matters or alternative proposals that commenters 
may wish to discuss. Comments are due August 7, 2006. Reply comments 
are due September 5, 2006. Comments must refer to Docket Nos. RM05-25-
000 and RM05-17-000, and must include the commenters' name, the 
organization they represent, if applicable, and their address in their 
comments. Comments may be filed either in electronic or paper format.
    495. To facilitate the Commission's review of the comments, 
commenters are requested to provide an executive summary of their 
position, not to exceed ten pages. Commenters are requested to identify 
each section of the NOPR that their discussion addresses and to use 
conforming headings. Additional issues the commenters wish to raise 
should be clearly identified in a separate section entitled ``Other 
Issues,'' which should be organized by the relevant pro forma OATT 
section (if applicable). Furthermore, we also request that commenters 
with specific tariff language suggestions submit a redline/strikeout 
version showing their proposed changes to the language that appears in 
the pro forma OATT attached to this NOPR.\449\ The commenters should 
double space their comments. To assist commenters in their review, the 
Commission has posted a copy of the proposed revised pro forma OATT 
with changes from the current version of the pro forma OATT shown in 
redline/strikeout on the following location on our Web site at 
http://www.ferc.gov/industries/electric/indus-act/oatt-reform.asp Exit Disclaimer.

---------------------------------------------------------------------------

    \449\ The pro forma OATT includes two amendments that have been 
made since the tariff was finalized in Order No. 888-B. First, the 
tariff was amended to include protocols for curtailment of multi-
system transactions and parallel flows. See North American 
Reliability Council, 85 FERC ] 61,353 (1998), reh'g denied, 87 FERC ]
61,161 (1999) and recently updated in North American Electric 
Reliability Council, 110 FERC ] 61,388 (2005). The second amendment 
incorporates standardized generator interconnection procedures. See 
Order No. 2003. The standardized generator interconnection 
procedures are not included in the pro forma OATT attached to this 
NOPR because we do not propose changes to them.
---------------------------------------------------------------------------

    496. Comments and reply comments may be filed electronically via the

[[Page 32709]]

eFiling link on the Commission's Web site at http://www.ferc.gov Exit Disclaimer. 
The Commission accepts most standard word processing formats and commenters 
may attach additional files with supporting information in certain 
other file formats. Documents created electronically using word 
processing software should be filed in the native application or print-
to-PDF format and not in a scanned format. This will enhance document 
retrieval for both the Commission and the public. Attachments that 
exist only in paper form may be scanned. Commenters filing 
electronically should not make a paper filing. Service of rulemaking 
comments is not required. Commenters that are not able to file comments 
electronically must send an original and 14 copies of their comments 
to: Federal Energy Regulatory Commission, Office of the Secretary, 888 
First Street, NE., Washington, DC 20426.
    497. All comments will be placed in the Commission's public files 
and may be viewed, printed, or downloaded remotely as described in the 
Document Availability section below. Commenters on this proposal are 
not required to serve copies of their comments on other commenters.

X. Document Availability

    498. In addition to publishing the full text of this document in 
the Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
Internet through the Commission's Home Page (http://www.ferc.gov) Exit Disclaimer and 
in the Commission's Public Reference Room during normal business hours 
(8:30 a.m. to 5 p.m. Eastern time) at 888 First Street, NE., Room 2A, 
Washington DC 20426.
    499. From the Commission's Home Page on the Internet, this 
information is available in the Commission's document management 
system, eLibrary. The full text of this document is available on 
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or 
downloading. To access this document in eLibrary, type ``RM05-25'' or 
``RM05-17'' in the docket number field.
    500. User assistance is available for eLibrary and the Commission's 
website during normal business hours. For assistance, please contact 
the Commission's Online Support at 1-866-208-3676 (toll free) or 202-
502-6652 (e-mail at FERCOnlineSupport@FERC.gov), or the Public 
Reference Room at 202-502-8371, TTY 202-502-8659 (e-mail at 
public.referenceroom@ferc.gov).

List of Subjects

18 CFR Part 35

    Electric power rates, Electric utilities, Reporting and 
recordkeeping requirements.

18 CFR Part 37

    Conflict of interests, Electric power plants, Electric utilities, 
Reporting and recordkeeping requirements.

    By direction of the Commission.
Magalie R. Salas,
Secretary.

    In consideration of the foregoing, the Commission proposes to amend 
parts 35 and 37, Chapter I, Title 18 of the Code of Federal 
Regulations, as follows:

PART 35--FILING OF RATE SCHEDULES AND TARIFFS

    1. The authority citation for part 35 continues to read as follows:

    Authority: 16 U.S.C. 791a-825r, 2601-2645; 31 U.S.C. 9701; 42 
U.S.C. 71-7352.

    2. Amend Sec.  35.28 as follows:
    a. paragraph (c) is revised.
    b. paragraphs (d)(i) and d(ii) are redesignated as d(1) and d(2).
    c. newly redesignated paragraph d(1) is revised.
    d. paragraph (e)(1) (introductory text) is revised.
    e. paragraph (e)(1)(ii) is revised.

Sec.  35.28  Non-discriminatory open access transmission tariff.

* * * * *
    (c) Non-discriminatory open access transmission tariffs.
    (1) Every public utility that owns, controls, or operates 
facilities used for the transmission of electric energy in interstate 
commerce must have on file with the Commission a tariff of general 
applicability for transmission services, including ancillary services, 
over such facilities. Such tariff must be the open access pro forma 
tariff contained in Order No. 888, FERC Stats. & Regs. ] 31,036, as 
revised by the open access pro forma tariff contained in Order No. ----
, FERC Stats. & Regs. ] ----, or such other open access tariff as may 
be approved by the Commission consistent with Order No. ----, FERC 
Stats. & Regs. ] ----.
    (i) Subject to the exceptions in paragraphs (c)(1)(ii), 
(c)(1)(iii), (c)(1)(iv) and (c)(1)(v) of this section, the pro forma 
tariff contained in Order No. 888, FERC Stats. & Regs. ]31,036, as 
revised by the open access pro forma tariff contained in Order No. ----
, FERC Stats. & Regs. ] ----, and accompanying rates, must be filed no 
later than 60 days prior to the date on which a public utility would 
engage in a sale of electric energy at wholesale in interstate commerce 
or in the transmission of electric energy in interstate commerce.
    (ii) If a public utility owns, controls, or operates facilities 
used for the transmission of electric energy in interstate commerce as 
of ----, it must file the revisions to the pro forma tariff contained 
in Order No. ----, FERC Stats. & Regs. ] ---- pursuant to section 206 
of the FPA and accompanying rates pursuant to section 205 of the FPA, 
no later than ----.
    (iii) If a public utility owns, controls, or operates transmission 
facilities used for the transmission of electric energy in interstate 
commerce as of ----, such facilities are jointly owned with a non-
public utility, and the joint ownership contract prohibits transmission 
service over the facilities to third parties, the public utility with 
respect to access over the public utility's share of the jointly owned 
facilities must file no later than ---- the revisions to the pro forma 
tariff contained in Order No. ----, FERC Stats. & Regs. ] ----, 
pursuant to section 206 of the FPA and accompanying rates pursuant to 
section 205 of the FPA.
    (iv) Any public utility whose transmission facilities are under the 
independent control of a Commission-approved ISO or RTO may satisfy its 
obligation under paragraph (c)(1) of this section, with respect to such 
facilities, through the open access transmission tariff filed by the 
ISO or RTO.
    (v) If a public utility obtains a waiver of the tariff requirement 
pursuant to paragraph (d) of this section, it does not need to file the 
pro forma tariff required by this section.
    (vi) Any public utility that seeks a deviation from the pro forma 
tariff contained in Order No. 888, FERC Stats. & Regs. ]31,036, as 
revised in Order No. ----, FERC Stats. & Regs. ] ----, must demonstrate 
that the deviation is consistent with the principles of Order No., ---- 
FERC Stats. & Regs. ] ----.
    (vii) Each public utility's open access transmission tariff must 
include the standards incorporated by reference in part 38 of this chapter.
    (2) Subject to the exceptions in paragraphs (c)(2)(i) and 
(c)(3)(iii) of this section, every public utility that owns, controls, 
or operates facilities used for the transmission of electric energy in 
interstate commerce, and that uses those facilities to engage in 
wholesale sales and/or purchases of electric energy, or unbundled 
retail sales of electric energy, must take transmission service for 
such sales and/or purchases under the open access tariff filed pursuant 
to this section.

[[Page 32710]]

    (i) For sales of electric energy pursuant to a requirements service 
agreement executed on or before July 9, 1996, this requirement will not 
apply unless separately ordered by the Commission. For sales of 
electric energy pursuant to a bilateral economy energy coordination 
agreement executed on or before July 9, 1996, this requirement is 
effective on December 31, 1996. For sales of electric energy pursuant 
to a bilateral non-economy energy coordination agreement executed on or 
before July 9, 1996, this requirement will not apply unless separately 
ordered by the Commission.
    (ii) [Reserved.]
    (3) Every public utility that owns, controls, or operates 
facilities used for the transmission of electric energy in interstate 
commerce, and that is a member of a power pool, public utility holding 
company, or other multi-lateral trading arrangement or agreement that 
contains transmission rates, terms or conditions, must have on file a 
joint pool-wide or system-wide open access transmission pro forma 
tariff, which tariff must be the open access pro forma tariff contained 
in Order No. 888, FERC Stats. & Regs. ] 31,036, as revised by the open 
access pro forma tariff contained in Order No. ----, FERC Stats. & 
Regs. ] ----, or such other open access tariff as may be approved by 
the Commission consistent with Order No. ----, FERC Stats. & Regs. ] 
--
--.
    (i) For any power pool, public utility holding company or other 
multi-lateral arrangement or agreement that contains transmission 
rates, terms or conditions and that is executed after July 9, 1996, 
this requirement is effective on the date that transactions begin under 
the arrangement or agreement.
    (ii) For any power pool, public utility holding company or other 
multi-lateral arrangement or agreement that contains transmission 
rates, terms or conditions and that is executed on or before July 9, 
1996, a public utility member of such power pool, public utility 
holding company or other multi-lateral arrangement or agreement that 
owns, controls, or operates facilities used for the transmission of 
electric energy in interstate commerce must file the revisions to its 
joint pool-wide or system-wide contained in Order No. ----, FERC Stats. 
& Regs. ] ----, pursuant to section 206 of the FPA and accompanying 
rates pursuant to section 205 of the FPA, no later than ----.
    (iii) A public utility member of a power pool, public utility 
holding company or other multi-lateral arrangement or agreement that 
contains transmission rates, terms or conditions and that is executed 
on or before July 9, 1996 must take transmission service under a joint 
pool-wide or system-wide pro forma tariff filed pursuant to this 
section for wholesale trades among the pool or system members.
    (4) Consistent with paragraph (c)(1) of this section, every 
Commission-approved ISO or RTO must have on file with the Commission a 
tariff of general applicability for transmission services, including 
ancillary services, over such facilities. Such tariff must be the open 
access pro forma tariff contained in Order No. 888, FERC Stats. & Regs. 
] 31,036, as revised by the open access pro forma tariff contained in 
Order No. ----, FERC Stats. & Regs. ] ----, or such other open access 
tariff as may be approved by the Commission consistent with Order No. 
----, FERC Stats. & Regs. ] ----.
    (i) Subject to paragraph (c)(4)(ii) of this section, a Commission-
approved ISO or RTO must file the revisions to the pro forma tariff 
contained in Order No. ----, FERC Stats. & Regs. ] ----, pursuant to 
section 206 of the FPA and accompanying rates pursuant to section 205 
of the FPA, no later than ----.
    (ii) If a Commission-approved ISO or RTO can demonstrate that its 
existing open access tariff is consistent with or superior to the 
revisions to the pro forma tariff contained in Order No. ----, FERC 
Stats. & Regs. ] ----, or any portions thereof, the Commission-approved 
ISO or RTO may instead set forth such demonstration in its filing 
pursuant to section 206 no later than ----.
    (d) Waivers. * * *
    (1) No later than ----, or
* * * * *
    (e) Non-public utility procedures for tariff reciprocity 
compliance. (1) A non-public utility may submit a transmission tariff 
and a request for declaratory order that its voluntary transmission 
tariff meets the requirements of Order No. 888, FERC Stats. & Regs. ]
31,036 and Order No. ----, FERC Stats. & Regs. ] ----.
    (i) * * *
    (ii) If the submittal is found to be an acceptable transmission 
tariff, an applicant in a Federal Power Act (FPA) section 211 or 211A 
proceeding against the non-public utility shall have the burden of 
proof to show why service under the open access tariff is not 
sufficient and why a section 211 or 211A order should be granted.
* * * * *

PART 37--OPEN ACCESS SAME-TIME INFORMATION SYSTEMS

    3. The authority citation for part 37 continues to read as follows:

    Authority: 16 U.S.C. 791-825r, 2601-2645; 31 U.S.C. 9701; 42 
U.S.C. 7101-7352.

    4. Amend Sec.  37.6 as follows:
    a. paragraph (a)(1) is revised.
    b. paragraph (b)(introductory text) is revised.
    c. paragraphs (b)(1)(v) through (b)(1)(viii) are added.
    d. paragraphs (b)(2)(i) and b(2)(ii) are revised.
    e. paragraph (b)(3) is revised.
    f. paragraph (c)(2) is revised.
    g. paragraphs (e)(1) and (e)(2)(ii) are revised.
    h. paragraph (e)(3)(ii) is revised.
    i. paragraphs (h) and (i) are added.

Sec.  37.6  Information to be posted on the OASIS.

    (a) * * *
    (1) Make requests for transmission services offered by Transmission 
Providers, Resellers and other providers of ancillary services, request 
the designation of a network resource, and request the termination of 
the designation of a network resource;
* * * * *
    (b) Posting transfer capability. The available transfer capability 
on the Transmission Provider's system (ATC) and the total transfer 
capability (TTC) of that system shall be calculated and posted for each 
Posted Path as set out in this section.
    (1) * * *
    (v) Available transfer capability or ATC means the transfer 
capability remaining in the physical transmission network for further 
commercial activity over and above already committed uses, or such 
definition as contained in Commission-approved Reliability Standards.
    (vi) Total transfer capability or TTC means the amount of electric 
power that can be moved or transferred reliably from one area to 
another area of the interconnected transmission systems by way of all 
transmission lines (or paths) between those areas under specified 
system conditions, or such definition as contained in Commission-
approved Reliability Standards.
    (vii) Capacity Benefit Margin or CBM means the amount of TTC 
preserved by the Transmission Provider for load-serving entities, whose 
loads are located on that Transmission Provider's system, to enable 
access by the load-serving entities to generation from interconnected 
systems to meet generation reliability requirements, or such definition 
as contained in Commission-approved Reliability Standards.
    (viii) Transmission Reliability Margin or TRM means the amount of 
TTC necessary to provide reasonable

[[Page 32711]]

assurance that the interconnected transmission network will be secure, 
or such definition as contained in Commission-approved Reliability 
Standards.
    (2) * * *
    (i) Information used to calculate any posting of ATC and TTC must 
be dated and time-stamped and all calculations shall be performed 
according to consistently applied methodologies referenced in the 
Transmission Provider's transmission tariff and shall be based on 
Commission-approved Reliability Standards as well as current industry 
practices, standards and criteria
    (ii) On request, the Responsible Party must make all data used to 
calculate ATC, TTC, CBM, and TRM for any constrained posted paths 
publicly available (including the limiting element(s) and the cause of 
the limit (e.g., thermal, voltage, stability)) in electronic form 
within one week of the posting. The information is required to be 
provided only in the electronic format in which it was created, along 
with any necessary decoding instructions, at a cost limited to the cost 
of reproducing the material. This information is to be retained for six 
months after the applicable posting period.
* * * * *
    (3) Posting. The ATC, TTC, CBM, and TRM for all Posted Paths must 
be posted in megawatts by specific direction and in the manner 
prescribed in this subsection.
    (i) Constrained posted paths--(A) For Firm ATC and TTC. (1) The 
posting shall show ATC, TTC, CBM, and TRM for a 30-day period. For this 
period postings shall be: By the hour, for the current hour and the 168 
hours next following; and thereafter, by the day. If the Transmission 
Provider charges separately for on-peak and off-peak periods in its 
tariff, ATC, TTC, CBM, and TRM will be posted daily for each period.
    (2) Postings shall also be made by the month, showing for the 
current month and the 12 months next following.
    (3) If planning and specific requested transmission studies have 
been done, seasonal capability shall be posted for the year following 
the current year and for each year following to the end of the planning 
horizon but not to exceed 10 years.
    (B) For Non-Firm ATC and TTC. The posting shall show ATC, TTC, CBM 
and TRM for a 30-day period by the hour and days prescribed under 
paragraph (b)(3)(i)(A)(1) of this section and, if so requested, by the 
month and year as prescribed under paragraph (b)(3)(i)(A) (2) and (3) 
of this section. The posting of non-firm ATC and TTC shall show CBM as 
zero.
    (C) Updating Posted Information for Constrained Paths. (1) The 
capability posted under paragraphs (b)(3)(i) (A) and (B) of this 
section must be updated when transactions are reserved or service ends 
or whenever the TTC estimate for the Path changes by more than 10 percent.
    (2) All updating of hourly information shall be made on the hour.
    (3) When the monthly and yearly capability posted under paragraphs 
(b)(3)(i)(A) and (B) are updated, the Transmission Provider shall post 
a brief, but specific, narrative explanation of the reason for the 
update. This narrative should include, if relevant, scheduling of 
planned outages and occurrence of forced transmission outages, de-
ratings of transmission facilities, scheduling of planned generation 
outages and occurrence of forced generation outages, changes in load 
forecast, changes in new facilities' in-service dates, or other events 
or assumption changes that caused the update.
    (ii) Unconstrained posted paths. (A) Postings of firm and nonfirm 
ATC, TTC, CBM, and TRM shall be posted separately by the day, showing 
for the current day and the next six days following and thereafter, by 
the month for the 12 months next following. If the Transmission 
Provider charges separately for on-peak and off-peak periods in its 
tariff, ATC, TTC, CBM, and TRM will be posted separately for the 
current day and the next six days following for each period. These 
postings are to be updated whenever the ATC changes by more than 20 
percent of the Path's TTC.
    (B) If planning and specific requested transmission studies have 
been done, seasonal capability shall be posted for the year following 
the current year and for each year following until the end of the 
planning horizon but not to exceed 10 years.
    (iii) Calculation of CBM.
    (A) The Transmission Provider must reevaluate its CBM needs at 
least quarterly.
    (B) The Transmission Provider must post its practices for 
reevaluating its CBM needs.
    (c) Posting Transmission Service Products and Prices.
    (1) * * *
    (2) Transmission Providers must provide a downloadable file of 
their complete tariffs in the same electronic format as the tariff that 
is filed with the Commission. Transmission Providers also must post all 
of their rules, standards and practices that relate to transmission services.
* * * * *
    (e) Posting specific transmission and ancillary service requests 
and responses--(1) General rules. (i) All requests for transmission and 
ancillary service offered by Transmission Providers under the pro forma 
tariff, including requests for discounts, and all requests to designate 
or terminate a network resource, must be made on the OASIS and posted 
prior to the Transmission Provider responding to the request, except as 
discussed in paragraphs (e)(1) (ii) and (iii) of this section. The 
Transmission Provider must post all requests for transmission service, 
for ancillary service, and for the designation or termination of a 
network resource comparably. Requests for transmission service, 
ancillary service, and to designate and terminate a network resource, 
as well as the responses to such requests, must be conducted in 
accordance with the Transmission Provider's tariff, the Federal Power 
Act, and Commission regulations.
    (ii) The requirement in paragraph (e)(1)(i) of this section, to 
post requests for transmission and ancillary service offered by 
Transmission Providers under the pro forma tariff, including requests 
for discounts, prior to the Transmission Provider responding to the 
request, does not apply to requests for next-hour service made during 
Phase I.
    (iii) In the event that a discount is being requested for ancillary 
services that are not in support of basic transmission service provided 
by the Transmission Provider, such request need not be posted on the OASIS.
    (iv) In processing a request for transmission or ancillary service, 
the Responsible Party shall post the same information as required in 
paragraphs (c)(4) and (d)(3) of this section, and the following 
information: the date and time when the request is made, its place in 
any queue, the status of that request, and the result (accepted, 
denied, withdrawn). In processing a request to designate or terminate 
the designation of a network resource, the Responsible Party shall post 
the date and time when the request is made.
    (v) For any request to designate or terminate a network resource, 
the Transmission Provider (at the time when the request is received), 
must post on the OASIS (and make available for download) information 
describing the request (including: name of requestor, identification of 
the resource, effective time for the designation or termination,

[[Page 32712]]

identification of whether the transaction involves the Transmission 
Provider's wholesale merchant function or any affiliate; and any other 
relevant terms and conditions) and shall keep such information posted 
on the OASIS for at least 30 days. A record of the transaction must be 
retained and kept available as part of the audit log required in Sec.  37.7.
    (vi) The Transmission Provider shall post a list of its current 
designated network resources and all network customers' current 
designated network resources on OASIS. The list of network resources 
should include the name of the resource, its geographic and electrical 
location, its total installed capacity, and the amount of capacity to 
be designated as a network resource.
    (2) * * *
    (ii) Information to support the reason for the denial, including 
the operating status of relevant facilities, must be maintained for 
five years and provided, upon request, to the potential Transmission 
Customer.
* * * * *
    (3) Posting when a transaction is curtailed or interrupted. (ii) 
Information to support any such curtailment or interruption, including 
the operating status of the facilities involved in the constraint or 
interruption, must be maintained and made available upon request, to 
the curtailed or interrupted customer, the Commission's Staff, and any 
other person who requests it, for five years.
* * * * *
    (h) Posting information summarizing the time to complete 
transmission service request studies. (1) For each calendar quarter, 
the Responsible Party must post the set of measures detailed in 
paragraph (h)(1)(i) through paragraph (h)(1)(vi) of this section 
related to the Responsible Party's processing of transmission service 
request system impact studies and facilities studies. The Responsible 
Party must calculate and post the measures in paragraph (h)(1)(i) 
through paragraph (h)(1)(vi) of this section separately for requests 
for short-term firm point-to-point transmission service, long-term firm 
point-to-point transmission service, and requests to designate a new 
network resource and must be calculated and posted separately for 
transmission service requests from Affiliates and transmission service 
requests from Transmission Customers who are not Affiliates. The 
Responsible Party is required to include in the calculations of the 
measures in paragraph (h)(1)(i) through paragraph (h)(1)(vi) of this 
section all studies the Responsible Party conducts of transmission 
service requests on another Transmission Provider's OASIS.
    (i) Process Time from Initial Service Request to Offer of System 
Impact Study Agreement.
    (A) Number of new system impact study agreements delivered during 
the reporting quarter to entities that request transmission service,
    (B) Number of new system impact study agreements delivered during 
the reporting quarter to entities that request transmission service 
more than thirty (30) days after the Responsible Party received the 
request for transmission service,
    (C) Mean time (in days), for all requests acted on by the 
Responsible Party during the reporting quarter, from the date when the 
Responsible Party received the request for transmission service to when 
the Responsible Party changed the transmission service request status 
to indicate that the Responsible Party could offer transmission service 
or needed to perform a system impact study,
    (D) Mean time (in days), for all system impact study agreements 
delivered by the Responsible Party during the reporting quarter, from 
the date when the Responsible Party received the request for 
transmission service to the date when the Responsible Party delivered a 
system impact study agreement, and
    (E) Number of new system impact study agreements executed during 
the reporting quarter.
    (ii) System Impact Study Processing Time. (A) Number of system 
impact studies completed by the Responsible Party during the reporting 
quarter,
    (B) Number of system impact studies completed by the Responsible 
Party during the reporting quarter more than 60 days after the 
Responsible Party received an executed system impact study agreement,
    (C) Mean time (in days), for all system impact studies completed by 
the Responsible Party during the reporting quarter, from the date when 
the Responsible Party received the executed system impact study 
agreement to the date when the Responsible Party provided the system impact 
study to the entity who executed the system impact study agreement, and
    (D) Mean cost of system impact studies completed by the Responsible 
Party during the reporting quarter.
    (iii) Transmission Service Requests Withdrawn from the System 
Impact Study Queue. (A) Number of transmission service requests 
withdrawn from the Responsible Party's system impact study queue during 
the reporting quarter,
    (B) Number of transmission service requests withdrawn from the 
Responsible Party's system impact study queue during the reporting 
quarter more than 60 days after the Responsible Party received the 
executed system impact study agreement, and
    (C) Mean time (in days), for all transmission service requests 
withdrawn from the Responsible Party's system impact study queue during 
the reporting quarter, from the date the Responsible Party received the 
executed system impact study agreement to date when request was 
withdrawn from the Responsible Party's system impact study queue.
    (iv) Process Time from Completed System Impact Study to Offer of 
Facilities Study. (A) Number of new facilities study agreements 
delivered during the reporting quarter to entities that request 
transmission service,
    (B) Number of new facilities study agreements delivered during the 
reporting quarter to entities that request transmission service more 
than thirty (30) days after the Responsible Party completed the system 
impact study,
    (C) Mean time (in days), for all facilities study agreements 
delivered by the Responsible Party during the reporting quarter, from 
the date when the Responsible Party completed the system impact study 
to the date when the Responsible Party delivered a facilities study 
agreement, and
    (D) Number of new facilities study agreements executed during the 
reporting quarter.
    (v) Facilities Study Processing Time. (A) Number of facilities 
studies completed by the Responsible Party during the reporting quarter,
    (B) Number of facilities studies completed by the Responsible Party 
during the reporting quarter more than 60 days after the Responsible 
Party received an executed facilities study agreement,
    (C) Mean time (in days), for all facilities studies completed by 
the Responsible Party during the reporting quarter, from the date when 
the Responsible Party received the executed facilities study agreement 
to the date when the Responsible Party provided the facilities study to 
the entity who executed the facilities study agreement,
    (D) Mean cost of facilities studies completed by the Responsible 
Party during the reporting quarter, and
    (E) Mean cost of upgrades recommended in facilities studies 
completed during the reporting quarter.
    (vi) Service Requests Withdrawn from Facilities Study Queue.

[[Page 32713]]

    (A) Number of transmission service requests withdrawn from the 
Responsible Party's facilities study queue during the reporting quarter,
    (B) Number of transmission service requests withdrawn from the 
Responsible Party's facilities study queue during the reporting quarter 
more than 60 days after the Responsible Party received the executed 
facilities study agreement, and
    (C) Mean time (in days), for all transmission service requests 
withdrawn from the Responsible Party's facilities study queue during 
the reporting quarter, from the date the Responsible Party received the 
executed facilities study agreement to date when request was withdrawn 
from the Responsible Party's facilities study queue
    (2) The Responsible Party is required to post the measures in 
paragraph (h)(1)(i) through paragraph (h)(1)(vi) of this section for 
each calendar quarter within 15 days of the end of the calendar 
quarter. The Responsible Party will keep the quarterly measures posted 
on OASIS for three calendar years.
    (3) The Responsible Party will be required to post on OASIS the 
measures in paragraph (h)(3)(i) through paragraph (h)(3)(iv) of this 
section in the event the Responsible Party, for two consecutive 
calendar quarters, completes more than twenty (20) percent of the 
studies associated with requests for transmission service from entities 
that are not Affiliates of the Responsible Party more than sixty (60) 
days after the Responsible Party delivers the appropriate study 
agreement. The Responsible Party will have to post the measures in 
paragraph (h)(3)(i) through paragraph (h)(3)(iv) of this section until 
it processes at least ninety (90) percent of all studies within 60 days 
after it has received the appropriate executed study agreement. For the 
purposes of calculating the percent of studies completed more than 
sixty (60) days after the Responsible Party delivers the appropriate 
study agreement, the Responsible Party should aggregate all system 
impact studies and facilities studies that it completes during the 
reporting quarter. The Responsible Party must calculate and post the 
measures in paragraph (h)(3)(i) through paragraph (h)(3)(iv) of this 
section separately for requests for short-term firm point-to-point 
transmission service, long-term firm point-to-point transmission 
service, and requests to designate a new network resource and must be 
calculated and posted separately for transmission service requests from 
Affiliates and transmission service requests from Transmission 
Customers who are not Affiliates.
    (i) Mean, across all system impact studies the Responsible Party 
completes during the reporting quarter, of the employee-hours expended 
per system impact study the Responsible Party completes during 
reporting period;
    (ii) Mean, across all facilities studies the Responsible Party 
completes during the reporting quarter, of the employee-hours expended 
per facilities study the Responsible Party completes during reporting 
period;
    (iii) The number of employees the Responsible Party has assigned to 
process system impact studies;
    (iv) The number of employees the Responsible Party has assigned to 
process facilities studies.
    (4) The Responsible Party is required to post the measures in 
paragraph (h)(3)(a) through paragraph (h)(3)(d) of this section for 
each calendar quarter within 15 days of the end of the calendar 
quarter. The Responsible Party will keep the quarterly measures posted 
on OASIS for five calendar years.
    (i) Posting data related to grants and denials of service. The 
Responsible Party is required to post data each month listing, by path 
or flowgate, the number of transmission service requests that have been 
accepted and the number of transmission service requests that have been 
denied during the prior month. This posting must distinguish between 
the length of the service request (e.g., short-term or long-term 
requests) and between the type of service requested (e.g., firm point-
to-point, non-firm point-to-point or network service). The posted data 
must show:
    (1) The number of non-Affiliate requests for transmission service 
that have been rejected,
    (2) The total number of non-Affiliate requests for transmission 
service that have been made,
    (3) The number of Affiliate requests for transmission service that 
have been rejected, and
    (4) The total number of Affiliate requests for transmission service 
that have been made.
    5. In Sec.  37.7, paragraph (b) is revised to read as follows:

Sec.  37.7  Auditing Transmission Service Information.

* * * * *
    (b) Audit data must remain available for download on the OASIS for 
90 days, except ATC/TTC postings that must remain available for 
download on the OASIS for 20 days. The audit data are to be retained 
and made available upon request for download for five years from the 
date when they are first posted in the same electronic form as used 
when they originally were posted on the OASIS.
---------------------------------------------------------------------------

    \450\ A ``*'' indicates that the commenter filed a notice of 
intervention only.

    Note: The following appendices will not be published in the Code 
---------------------------------------------------------------------------
of Federal Regulations.

Appendix A: Commenter Acronyms

              Initial Commenters in Docket No. RM05-25-000
------------------------------------------------------------------------
              Abbreviation                 RM05-25-000 Initial comments
------------------------------------------------------------------------
AEP....................................  American Electric Power System
                                          (AEP Texas North Company; AEP
                                          Texas Central Company;
                                          Appalachian Power Company;
                                          Columbus Southern Power
                                          Company; Indiana Michigan
                                          Power Company; Kentucky Power
                                          Company; Kingsport Power
                                          Company; Ohio Power Company;
                                          Public Service Company of
                                          Oklahoma; Southwestern
                                          Electric Power Company and
                                          Wheeling Power Company).
Alabama MEA............................  Alabama Municipal Electric
                                          Authority.
Alberta Intervenors....................  Alberta Intervenors
                                          (TransCanada Energy Ltd.;
                                          ENMAX Energy Marketing, Inc.;
                                          EPCOR Merchant and Capital,
                                          LP; and TransAlta
                                          Corporation).
Alberta System Operator................  Alberta Electric System
                                          Operator.
Alcoa..................................  Alcoa Inc. and Alcoa Power
                                          Generating Inc.
Alliance of State Leaders..............  Alliance of State Leaders
                                          Protecting Electricity
                                          Consumers.

[[Page 32714]]

Ameren.................................  Ameren Services Company
                                          (Central Illinois Light
                                          Company d/b/a AmerenCILCO;
                                          Central Illinois Public
                                          Service Company d/b/a
                                          AmerenCIPS; Illinois Power
                                          Company d/b/a AmerenIP; Union
                                          Electric Company d/b/a
                                          AmerenUE; Ameren Energy
                                          Marketing Company; Ameren
                                          Energy Generating Company; and
                                          AmerenEnergy Resources
                                          Generating Company).
American Forest and Paper* \450\.......  American Forest and Paper
                                          Association.
American Transmission..................  American Transmission Company
                                          LLC.
AMP-Ohio...............................  American Municipal Power-Ohio,
                                          Inc.
APPA...................................  American Public Power
                                          Association.
APS....................................  Arizona Public Service Company.
Arkansas Cities........................  Arkansas Cities and Cooperative
                                          (Conway Corporation; West
                                          Memphis Utilities Commission;
                                          City of Osceola, Arkansas;
                                          City of Prescott, Arkansas;
                                          Hope Water & Light Commission;
                                          and Farmers Electric
                                          Cooperative Cooperation).
Arkansas Commission....................  Arkansas Public Service
                                          Commission.
AWEA...................................  American Wind Energy
                                          Association.
BC Transmission........................  British Columbia Transmission
                                          Corporation.
Bonneville.............................  Bonneville Power
                                          Administration.
Bureau of Reclamation..................  U.S. Bureau of Reclamation.
CAISO..................................  California Independent System
                                          Operator Corporation.
California Commission..................  Public Utilities Commission of
                                          the State of California.
Calpine................................  Calpine Corporation.
Canadian Electricity Association.......  Canadian Electricity
                                          Association.
Chelan.................................  Public Utility District No. 1
                                          of Chelan County and Public
                                          Utility District No. 2 of
                                          Grant County.
Cinergy................................  Cinergy Services, Inc.
                                          (Cincinatti Gas & Electric
                                          Company; PSI Energy, Inc.; and
                                          Union Light, Heat and Power
                                          Company).
Constellation..........................  Constellation Energy Group,
                                          Inc.
Cottonwood.............................  Cottonwood Energy Company LP
                                          and Union Power Partners, LP.
Detroit Edison.........................  Detroit Edison Company.
Douglas................................  Public Utility District No. 1
                                          of Douglas County.
Duke...................................  Duke Energy Corporation.
East Texas Cooperatives................  East Texas Electric
                                          Cooperative, Inc.; Northeast
                                          Texas Electric Cooperative,
                                          Inc.; Sam Rayburn Generation
                                          and Electric Cooperative,
                                          Inc.; and Tex-La Electric
                                          Cooperative of Texas, Inc.
Edison Mission.........................  Edison Mission Energy, Edison
                                          Mission Marketing & Trading,
                                          Inc. and Midwest Generation
                                          EME, LLC.
EEI....................................  Edison Electric Institute.
ELCON..................................  Electricity Consumers Resource
                                          Council, American Iron and
                                          Steel Institute and American
                                          Chemistry Council.
Entergy................................  Entergy Services, Inc.
EPSA...................................  Electric Power Supply
                                          Association.
Exelon.................................  Exelon Corporation.
Fayetteville...........................  Public Works Commission of the
                                          City of Fayetteville, North
                                          Carolina.
FirstEnergy............................  FirstEnergy Service Company
                                          (FirstEnergy Solutions;
                                          American Transmission Systems,
                                          Inc.; Jersey Central Power and
                                          Light Company; Metropolitan
                                          Edison Company; and
                                          Pennsylvania Electric
                                          Company).
Florida Industrial Cogeneration          Florida Industrial Cogeneration
 Association.                             Association.
FMPA...................................  Florida Municipal Power Agency.
FP&L...................................  Florida Power & Light Company.
Hogan..................................  William H. Hogan.
HQ Energy..............................  HQ Energy Services (U.S.), Inc.
IECG*..................................  Industrial Energy Consumer
                                          Group.
Indicated New York Transmission Owners.  Indicated New York Transmission
                                          Owners (Central Hudson Gas &
                                          Electric Corp.; Consolidated
                                          Edison Company of New York,
                                          Inc.; New York State Electric
                                          & Gas Corp.; Orange and
                                          Rockland Utilities, Inc.;
                                          LIPA; New York Power
                                          Authority; and Rochester Gas
                                          and Electric Corp.).
International Transmission.............  International Transmission
                                          Company.
ISO New England........................  ISO New England, Inc. and New
                                          England Power Pool.
ISO/RTO................................  ISO/RTO Council.
KCP&L..................................  Kansas City Power & Light
                                          Company.
Kentucky Commission....................  Kentucky Public Service
                                          Commission.
Lafayette..............................  Lafayette Utilities System of
                                          the City and Parish of
                                          Lafayette, Louisiana;
                                          Mississippi Delta Energy
                                          Agency, Clarksdale Public
                                          Utilities Commission of the
                                          City of Clarksdale,
                                          Mississippi; and Public
                                          Service Commission of the City
                                          of Yazoo City, Mississippi.
LDWP...................................  City of Los Angeles Department
                                          of Water and Power.
LG&E...................................  LG&E Energy LLC (Louisville Gas
                                          and Electric Company and
                                          Kentucky Utilities Company).
LPPC...................................  Large Public Power Council.

[[Page 32715]]

MEAG...................................  MEAG Power.
Memphis Light..........................  Memphis Light, Gas & Water
                                          Division.
Metropolitan Water District............  Metropolitan Water District of
                                          Southern California.
MidAmerican............................  MidAmerican Energy Company.
Midwest Municipals.....................  Midwest Municipal Transmission
                                          Group.
Midwest SATs...........................  Midwest Stand-Alone
                                          Transmission Companies
                                          (American Transmission Company
                                          LLC; International
                                          Transmission Company; and
                                          Michigan Electric Transmission
                                          Company, LLC).
MISO...................................  Midwest Independent
                                          Transmission System Operator,
                                          Inc.
MISO States............................  Organization of MISO States.
Montana Alberta Tie....................  Montana Alberta Tie Ltd.
NARUC..................................  National Association of
                                          Regulatory Utility
                                          Commissioners.
National Grid..........................  National Grid USA.
NCPA...................................  Northern California Power
                                          Agency.
Nevada Commission......................  Public Utilities Commission of
                                          Nevada.
Nevada Companies.......................  Nevada Power Company and Sierra
                                          Pacific Power Company.
New York Commission....................  New York State Public Service
                                          Commission.
North Carolina Commission..............  North Carolina Utilities
                                          Commission; Public Staff of
                                          the North Carolina Utilities
                                          Commission; and the Attorney
                                          General of the State of North
                                          Carolina.
Northeast Utilities....................  Northeast Utilities Service
                                          Company (Connecticut Light and
                                          Power Company; Western
                                          Massachusetts Electric
                                          Company; Public Service
                                          Company of New Hampshire;
                                          Holyoke Water Power Company;
                                          and Holyoke Power and Electric
                                          Company).
Northwest IPPs.........................  Northwest Independent Power
                                          Producers Coalition (BP
                                          Energy; Calpine Corporation;
                                          EPCOR; National Energy Supply
                                          Company; Northwest Energy
                                          Development; Sempra
                                          Generation; Suez Energy North
                                          America, Inc.; and TransAlta
                                          Energy Marketing, (U.S.)
                                          Inc.).
Northwest Unregulated TUs..............  Northwest Unregulated
                                          Transmitting Utilities (Clark
                                          Public Utilities; Public
                                          Utility District No. 1 of
                                          Cowlitz County; Eugene Water
                                          and Electric Board; Public
                                          Utility District No. 2 of
                                          Grant County; Public Utility
                                          District No. 1 of Snohomish
                                          County; and Tacoma Power).
NorthWestern...........................  NorthWestern Corporation.
NPPD...................................  Nebraska Public Power District.
NRECA..................................  National Rural Electric
                                          Cooperative Association.
Occidental.............................  Occidental Chemical
                                          Corporation.
Ohio Commission........................  Public Utilities Commission of
                                          Ohio.
Oklahoma Commission....................  Oklahoma Corporation
                                          Commission.
Old Dominion...........................  Old Dominion Electric
                                          Cooperative.
PacifiCorp.............................  PacifiCorp.
PJM....................................  PJM Interconnection, L.L.C.
PNM-TNMP...............................  Public Service Company of New
                                          Mexico and Texas-New Mexico
                                          Power Company.
Portland General.......................  Portland General Electric
                                          Company.
Powerex................................  Powerex Corp.
PPL....................................  PPL Companies (PPL Electric
                                          Utilities Corporation; PPL
                                          EnergyPlus, LLC; PPL Montana,
                                          LLC; PPL Holtwood, LLC; Lower
                                          Mount Bethel Energy, LLC; PPL
                                          Maine, LLC; PPL Great Works,
                                          LLC; PPL Colstrip I, LLC; PPL
                                          Colstrip II, LLC; PPL Martins
                                          Creek, LLC; PPL Brunner
                                          Island, LLC; PPL Montour, LLC;
                                          PPL Susquehanna, LLC; PPL
                                          Wallingford Energy, LLC; PPL
                                          Southwest Generation Holdings,
                                          LLC; PPL University Park, LLC,
                                          PPL Shoreham Energy, LLC; and
                                          PPL Edgewood Energy, LLC).
Progress Energy........................  Progress Energy, Inc. (Carolina
                                          Power & Light Company d/b/a
                                          Progress Energy Carolinas and
                                          Florida Power Corporation, d/b/
                                          a Progress Energy Florida).
Public Power Council...................  Public Power Council.
Renewable Energy.......................  Renewable Energy and Public
                                          Interest Organizations
                                          (American Wind Energy
                                          Association; Citizens for
                                          Pennsylvania's Future
                                          (PennFuture); Minnesotans for
                                          an Energy Efficient Economy;
                                          Natural Resources Defense
                                          Council; Ohio Consumers'
                                          Council; Pace Energy Project;
                                          Project for Sustainable FERC
                                          Energy Policy; Renewable
                                          Northwest Project; The Stella
                                          Group, Ltd.; The Wind
                                          Coalition; and West Wind
                                          Wires).
Rural Utilities Service................  U.S. Department of Agriculture
                                          Rural Utilities Service.
Sacramento.............................  Sacramento Municipal Utility
                                          District.
Salt River.............................  Salt River Project Agricultural
                                          Improvement and Power
                                          District.
San Diego G&E..........................  San Diego Gas & Electric
                                          Company.
Santa Clara............................  City of Santa Clara, California
                                          d/b/a Silicon Valley Power.
Santee Cooper..........................  South Carolina Public Service
                                          Authority.
Sempra Global..........................  Sempra Global.
SEPA...................................  Southeastern Power
                                          Administration.

[[Page 32716]]

Snohomish..............................  Public Utility District No. 1
                                          of Snohomish County,
                                          Washington.
South Carolina E&G.....................  South Carolina Electric & Gas
                                          Company.
Southern...............................  Southern Company Services, Inc.
Southern Montana Coop..................  Southern Montana Electric
                                          Generation and Transmission
                                          Cooperative, Inc.
Southwest TDU Group....................  Southwest Transmission
                                          Dependent Utility Group
                                          (Aguila Irrigation District;
                                          Ak-Chin Energy Services;
                                          Buckeye Water Conservation and
                                          Drainage District; Central
                                          Arizona Water Conservation
                                          District; Electrical District
                                          No. 3; Electrical District No.
                                          4; Electrical District No. 5;
                                          Electrical District No. 6;
                                          Electrical District No. 7;
                                          Electrical District No. 8;
                                          Harquahala Valley Power
                                          District; Maricopa County
                                          Municipal Water District No.
                                          1; McMullen Valley Water
                                          Conservation and Drainage
                                          District; City of Needles;
                                          Roosevelt Irrigation District;
                                          City of Safford; Tonopah
                                          Irrigation District; Wellton-
                                          Mohawk Irrigation and Drainage
                                          District).
Southwestern Coop......................  Southwestern Electric
                                          Cooperative, Inc.
SPP....................................  Southwest Power Pool, Inc.
Steel Manufacturers Association........  Steel Manufacturers
                                          Association.
Suez Energy NA.........................  Suez Energy North America.
Tacoma.................................  Tacoma Power.
TANC...................................  Transmission Agency of Northern
                                          California.
TAPS...................................  Transmission Access Policy
                                          Study Group.
TDU Systems............................  Transmission Dependent
                                          Utilities Systems.
Tennessee Valley PPA...................  Tennessee Valley Public Power
                                          Association.
TransAlta..............................  TransAlta Energy Marketing
                                          (U.S.) Inc.
Trans-Elect............................  Trans-Elect, Inc.
TVA....................................  Tennessee Valley Authority.
WAPA...................................  Western Area Power
                                          Administration.
Williams...............................  Williams Power Company, Inc.
Wisconsin Commission...................  Public Service Commission of
                                          Wisconsin.
Wisconsin Electric.....................  Wisconsin Electric Power
                                          Company.
Wyoming Infrastructure*................  Wyoming Infrastructure
                                          Authority.
Xcel...................................  Xcel Energy Services, Inc.
------------------------------------------------------------------------


               Reply Commenters in Docket No. RM05-25-000
------------------------------------------------------------------------
              Abbreviation                 RM05-25-000 reply  comments
------------------------------------------------------------------------
Alberta Intervenors....................  Alberta Intervenors
                                          (TransCanada Energy Ltd.;
                                          ENMAX Energy Marketing, Inc.;
                                          EPCOR Merchant and Capital,
                                          LP; and TransAlta
                                          Corporation).
Anaheim................................  Cities of Anaheim, Azusa,
                                          Banning, Colton, Pasadena and
                                          Riverside, California.
APPA...................................  American Public Power
                                          Association.
BC Transmission........................  British Columbia Transmission
                                          Corporation.
Bonneville.............................  Bonneville Power
                                          Administration.
California Municipal Utilities           California Municipal Utilities
 Association.                             Association.
Cogeneration Association of California.  Cogeneration Association of
                                          California and Energy
                                          Producers and Users Coalition.
EEI....................................  Edison Electric Institute.
ElectriCities..........................  ElectriCities of North
                                          Carolina, Inc.
Entergy................................  Entergy Services, Inc.
EPSA...................................  Electric Power Supply
                                          Association.
Fallon.................................  City of Fallon, Nevada.
Fertilizer Institute...................  Fertilizer Institute.
FMPA...................................  Florida Municipal Power Agency.
FP&L...................................  Florida Power & Light Company.
Great Northern.........................  Great Northern Power
                                          Development, L.P.
Joint Commenters.......................  Joint Commenters (Duke Energy.
                                          Corporation, Progress Energy
                                          Corporation, South Carolina
                                          Public Service Authority and
                                          Southern Company Services,
                                          Inc.).
Lafayette\+ 451\.......................  Lafayette Utilities System of
                                          the City and Parish of
                                          Lafayette, Louisiana;
                                          Mississippi Delta Energy
                                          Agency, Clarksdale Public
                                          Utilities Commission of the
                                          City of Clarksdale,
                                          Mississippi; and Public
                                          Service Commission of the City
                                          of Yazoo City, Mississippi.
LDWP...................................  City of Los Angeles Department
                                          of Water and Power.
LPPC...................................  Large Public Power Council.
Mark Lively\+\.........................  Mark B. Lively.
MEAG...................................  MEAG Power.
Memphis Light..........................  Memphis Light, Gas & Water
                                          Division.

[[Page 32717]]

Midwest Municipals.....................  Midwest Municipal Transmission
                                          Group .
Midwest SATs...........................  Midwest Stand-Alone
                                          Transmission Companies
                                          (American Transmission Company
                                          LLC; International
                                          Transmission Company; and
                                          Michigan Electric Transmission
                                          Company, LLC).
NARUC..................................  National Association of
                                          Regulatory Utility
                                          Commissioners.
National Grid..........................  National Grid USA.
NCPA...................................  Northern California Power
                                          Agency.
Newmont Mining.........................  Newmont USA Limited, d/b/a
                                          Newmont Mining Corporation.
Northwest IPPs.........................  Northwest Independent Power
                                          Producers Coalition (BP
                                          Energy; Calpine Corporation;
                                          EPCOR; National Energy Systems
                                          Company; Northwest Energy
                                          Development; Sempra
                                          Generation; Suez Energy North
                                          America, Inc.; and TransAlta
                                          Energy Marketing, (U.S.)
                                          Inc.).
NRECA..................................  National Rural Electric
                                          Cooperative Association.
Occidental.............................  Occidental Chemical
                                          Corporation.
PacifiCorp.............................  PacifiCorp.
Powerex................................  Powerex Corp.
Progress Energy........................  Progress Energy, Inc. (Carolina
                                          Power & Light Company d/b/a
                                          Progress Energy Carolinas and
                                          Florida Power Corporation, d/b/
                                          a Progress Energy Florida).
Puget..................................  Puget Sound Energy, Inc.
Sacramento.............................  Sacramento Municipal Utility
                                          District.
Salt River.............................  Salt River Project Agricultural
                                          Improvement and Power
                                          District.
San Antonio............................  San Antonio City Public Service
                                          Board.
Seattle................................  City of Seattle--City Light
                                          Department.
South Carolina Regulatory Staff........  South Carolina Office of
                                          Regulatory Staff.
Southern...............................  Southern Company Services, Inc.
TANC...................................  Transmission Agency of Northern
                                          California.
TAPS...................................  Transmission Access Policy
                                          Study Group.
TDU Systems............................  Transmission Dependent
                                          Utilities Systems.
Truckee Donner.........................  Truckee Donner Public Utility
                                          District.
TVA....................................  Tennessee Valley Authority.
TVA Noticing Distributors\+\...........  TVA Noticing Distributors
                                          (Paducah Power Systems,
                                          Glasgow Electric Plant Board,
                                          Princeton Electric Plant Board
                                          and Hopkinsville Electric
                                          System).
Williams...............................  Williams Power Company, Inc.
------------------------------------------------------------------------


                        Commenters in RM05-17-000
------------------------------------------------------------------------
              Abbreviation                     RM05-17-000 Comments
------------------------------------------------------------------------
Allegheny..............................   Allegheny Power.
APPA...................................   American Public Power
                                          Association.
Bonneville.............................   Bonneville Power
                                          Administration.
CEOB...................................   California Electricity
                                          Oversight Board.
EEI....................................   Edison Electric Institute.
EPSA...................................   Electric Power Supply
                                          Association.
Exelon.................................   Exelon Corporation.
FTC....................................   Federal Trade Commission.
Generator Coalition....................   Generator Coalition
                                          (Cottonwood Energy Company LP;
                                          KGen Power Management Inc.;
                                          Suez Energy North America,
                                          Inc.; and Union Power
                                          Partners, LP).
International Transmission.............   International Transmission
                                          Company.
ISO/RTO................................   ISO/RTO Council.
LDWP...................................   City of Los Angeles Department
                                          of Water and Power.
MidAmerican............................   MidAmerican Energy Company.
MISO...................................   Midwest Independent
                                          Transmission System Operator,
                                          Inc.
NERC...................................   North American Electric
                                          Reliability Council.
NY Commission..........................   New York State Public Service
                                          Commission.
PG&E...................................   Pacific Gas and Electric
                                          Company.
PGP....................................   Public Generating Pool.
Powerex................................   Powerex Corp.
Southern...............................   Southern Company Services,
                                          Inc.
Southern California Edison.............   Southern California Edison
                                          Company.*
TANC...................................   Transmission Agency of
                                          Northern California.
TAPS...................................   Transmission Access Policy
                                          Study Group.
WestConnect............................   WestConnect Public Utilities.
------------------------------------------------------------------------

[[Page 32718]]

Pro Forma Open Access Transmission Tariff

Table of Contents

I. Common Service Provisions
---------------------------------------------------------------------------

    \451\ A ``+'' indicates that the commenter also filed 
supplemental comments.
---------------------------------------------------------------------------

    1 Definitions
    1.1 Affiliate
    1.2 Ancillary Services
    1.3 Annual Transmission Costs
    1.4 Application
    1.5 Commission
    1.6 Completed Application
    1.7 Control Area
    1.8 Curtailment
    1.9 Delivering Party
    1.10 Designated Agent
    1.11 Direct Assignment Facilities
    1.12 Economy Energy
    1.13 Eligible Customer
    1.14 Facilities Study
    1.15 Firm Point-To-Point Transmission Service
    1.16 Good Utility Practice
    1.17 Interruption
    1.18 Load Ratio Share
    1.19 Load Shedding
    1.20 Long-Term Firm Point-To-Point Transmission Service
    1.21 Native Load Customers
    1.22 Network Customer
    1.23 Network Integration Transmission Service
    1.24 Network Load
    1.25 Network Operating Agreement
    1.26 Network Operating Committee
    1.27 Network Resource
    1.28 Network Upgrades
    1.29 Non-Firm Point-To-Point Transmission Service
    1.30 Non-Firm Sale
    1.31 Open Access Same-Time Information System (OASIS)
    1.32 Part I
    1.33 Part II
    1.34 Part III
    1.35 Parties
    1.36 Point(s) of Delivery
    1.37 Point(s) of Receipt
    1.38 Point-To-Point Transmission Service
    1.39 Power Purchaser
    1.40 Pre-Confirmed Application
    1.41 Receiving Party
    1.42 Regional Transmission Group (RTG)
    1.43 Reserved Capacity
    1.44 Service Agreement
    1.45 Service Commencement Date
    1.46 Short-Term Firm Point-To-Point Transmission Service
    1.47 System Impact Study
    1.48 Third-Party Sale
    1.49 Transmission Customer
    1.50 Transmission Provider
    1.51 Transmission Provider's Monthly Transmission System Peak
    1.52 Transmission Service
    1.53 Transmission System
    2 Initial Allocation and Renewal Procedures
    2.1 Initial Allocation of Available Transfer Capability
    2.2 Reservation Priority for Existing Firm Service Customers
    3 Ancillary Services
    3.1 Scheduling, System Control and Dispatch Service
    3.2 Reactive Supply and Voltage Control from Generation Sources 
Service
    3.3 Regulation and Frequency Response Service
    3.4 Energy Imbalance Service
    3.5 Operating Reserve--Spinning Reserve Service
    3.6 Operating Reserve--Supplemental Reserve Service
    4 Open Access Same-Time Information System (OASIS)
    5 Local Furnishing Bonds
    5.1 Transmission Providers That Own Facilities Financed by Local 
Furnishing Bonds
    5.2 Alternative Procedures for Requesting Transmission Service
    6 Reciprocity
    7 Billing and Payment
    7.1 Billing Procedure
    7.2 Interest on Unpaid Balances
    7.3 Customer Default
    8 Accounting for the Transmission Provider's Use of the Tariff
    8.1 Transmission Revenues
    8.2 Study Costs and Revenues
    9 Regulatory Filings
    10 Force Majeure and Indemnification
    10.1 Force Majeure
    10.2 Indemnification
    11 Creditworthiness
    12 Dispute Resolution Procedures
    12.1 Internal Dispute Resolution Procedures
    12.2 External Arbitration Procedures
    12.3 Arbitration Decisions
    12.4 Costs
    12.5 Rights Under The Federal Power Act
II. Point-To-Point Transmission Service
    13 Nature of Firm Point-to-Point Transmission Service
    13.1 Term
    13.2 Reservation Priority
    13.3 Use of Firm Transmission Service by the Transmission 
Provider
    13.4 Service Agreements
    13.5 Transmission Customer Obligations for Facility Additions or 
Redispatch Costs
    13.6 Curtailment of Firm Transmission Service
    13.7 Classification of Firm Transmission Service
    13.8 Scheduling of Firm Point-To-Point Transmission Service
    14 Nature of Non-Firm Point-To-Point Transmission Service
    14.1 Term
    14.2 Reservation Priority
    14.3 Use of Non-Firm Point-to-Point Transmission Service by the 
Transmission Provider
    14.4 Service Agreements
    14.5 Classification of Non-Firm Point-To-Point Transmission 
Service
    14.6 Scheduling of Non-Firm Point-To-Point Transmission Service
    14.7 Curtailment or Interruption of Service
    15 Service Availability
    15.1 General Conditions
    15.2 Determination of Available Transfer Capability
    15.3 Initiating Service in the Absence of an Executed Service 
Agreement
    15.4 Obligation to Provide Transmission Service that Requires 
Expansion or Modification of the Transmission System
    15.5 Deferral of Service
    15.6 Other Transmission Service Schedules
    15.7 Real Power Losses
    16 Transmission Customer Responsibilities
    16.1 Conditions Required of Transmission Customers
    16.2 Transmission Customer Responsibility for Third-Party Arrangements
    17 Procedures for Arranging Firm Point-To-Point Transmission 
Service
    17.1 Application
    17.2 Completed Application
    17.3 Deposit
    17.4 Notice of Deficient Application
    17.5 Response to a Completed Application
    17.6 Execution of Service Agreement
    17.7 Extensions for Commencement of Service
    18 Procedures for Arranging Non-Firm Point-To-Point Transmission 
Service
    18.1 Application
    18.2 Completed Application
    18.3 Reservation of Non-Firm Point-To-Point Transmission Service
    18.4 Determination of Available Transfer Capability
    19 Additional Study Procedures for Firm Point-To-Point 
Transmission Service Requests
    19.1 Notice of Need for System Impact Study
    19.2 System Impact Study Agreement and Cost Reimbursement
    19.3 System Impact Study Procedures
    19.4 Facilities Study Procedures
    19.5 Facilities Study Modifications
    19.6 Due Diligence in Completing New Facilities
    19.7 Partial Interim Service
    19.8 Expedited Procedures for New Facilities
    19.9 Penalties for Failure to Meet Study Deadlines
    20 Procedures if the Transmission Provider is Unable to Complete 
New Transmission Facilities for Firm Point-to-Point Transmission Service
    20.1 Delays in Construction of New Facilities
    20.2 Alternatives to the Original Facility Additions
    20.3 Refund Obligation for Unfinished Facility Additions
    21 Provisions Relating to Transmission Construction and Services 
on the Systems of Other Utilities
    21.1 Responsibility for Third-Party System Additions
    21.2 Coordination of Third-Party System Additions
    22 Changes in Service Specifications
    22.1 Modifications on a Non-Firm Basis
    22.2 Modification on a Firm Basis
    23 Sale or Assignment of Transmission Service
    23.1 Procedures for Assignment or Transfer of Service
    23.2 Limitations on Assignment or Transfer of Service
    23.3 Information on Assignment or Transfer of Service
    24 Metering and Power Factor Correction at Receipt and Delivery Point(s)

[[Page 32719]]

    24.1 Transmission Customer Obligations
    24.2 Transmission Provider Access to Metering Data
    24.3 Power Factor
    25 Compensation for Transmission Service
    26 Stranded Cost Recovery
    27 Compensation for New Facilities and Redispatch Costs
III. Network Integration Transmission Service
    28 Nature of Network Integration Transmission Service
    28.1 Scope of Service
    28.2 Transmission Provider Responsibilities
    28.3 Network Integration Transmission Service
    28.4 Secondary Service
    28.5 Real Power Losses
    28.6 Restrictions on Use of Service
    29 Initiating Service
    29.1 Condition Precedent for Receiving Service
    29.2 Application Procedures
    29.3 Technical Arrangements to be Completed Prior to 
Commencement of Service
    29.4 Network Customer Facilities
    29.5 Filing of Service Agreement
    30 Network Resources
    30.1 Designation of Network Resources
    30.2 Designation of New Network Resources
    30.3 Termination of Network Resources
    30.4 Operation of Network Resources
    30.5 Network Customer Redispatch Obligation
    30.6 Transmission Arrangements for Network Resources Not 
Physically Interconnected With the Transmission Provider
    30.7 Limitation on Designation of Network Resources
    30.8 Use of Interface Capacity by the Network Customer
    30.9 Network Customer Owned Transmission Facilities
    31 Designation of Network Load
    31.1 Network Load
    31.2 New Network Loads Connected With the Transmission Provider
    31.3 Network Load Not Physically Interconnected With the 
Transmission Provider
    31.4 New Interconnection Points
    31.5 Changes in Service Requests
    31.6 Annual Load and Resource Information Updates
    32 Additional Study Procedures for Network Integration 
Transmission Service Requests
    32.1 Notice of Need for System Impact Study
    32.2 System Impact Study Agreement and Cost Reimbursement
    32.3 System Impact Study Procedures
    32.4 Facilities Study Procedures
    32.5 Penalties for Failure to Meet Study Deadlines
    33 Load Shedding and Curtailments
    33.1 Procedures
    33.2 Transmission Constraints
    33.3 Cost Responsibility for Relieving Transmission Constraints
    33.4 Curtailments of Scheduled Deliveries
    33.5 Allocation of Curtailments
    33.6 Load Shedding
    33.7 System Reliability
    34 Rates and Charges
    34.1 Monthly Demand Charge
    34.2 Determination of Network Customer's Monthly Network Load
    34.3 Determination of Transmission Provider's Monthly 
Transmission System Load
    34.4 Redispatch Charge
    34.5 Stranded Cost Recovery
    35 Operating Arrangements
    35.1 Operation Under the Network Operating Agreement
    35.2 Network Operating Agreement
    35.3 Network Operating Committee
Schedule 1
    Scheduling, System Control and Dispatch Service
Schedule 2
    Reactive Supply and Voltage Control From Generation Sources Service
Schedule 3
    Regulation and Frequency Response Service
Schedule 4
    Energy Imbalance Service
Schedule 5
    Operating Reserve--Spinning Reserve Service
Schedule 6
    Operating Reserve--Supplemental Reserve Service
Schedule 7
    Long-Term Firm and Short-Term Firm Point-To-Point
Schedule 8
    Non-Firm Point-To-Point Transmission Service
Schedule 9
    Generator Imbalance Service
Attachment A
    Form of Service Agreement for Firm Point-To-Point Transmission Service
Attachment B
    Form of Service Agreement for Non-Firm Point-to-Point 
Transmission Service
Attachment C
    Methodology To Assess Available Transfer Capability
Attachment D
    Methodology for Completing a System Impact Study
Attachment E
    Index of Point-To-Point Transmission Service Customers
Attachment F
    Service Agreement for Network Integration Transmission Service
Attachment G
    Network Operating Agreement
Attachment H
    Annual Transmission Revenue Requirement for Network Integration 
Transmission Service
Attachment I
    Index of Network Integration Transmission Service Customers
Attachment J
    Procedures for Addressing Parallel Flows
Attachment K
    Transmission Planning Process
Attachment L
    Creditworthiness Procedures

I. Common Service Provisions

1 Definitions

1.1 Affiliate
    With respect to a corporation, partnership or other entity, each 
such other corporation, partnership or other entity that directly or 
indirectly, through one or more intermediaries, controls, is controlled 
by, or is under common control with, such corporation, partnership or 
other entity.
1.2 Ancillary Services
    Those services that are necessary to support the transmission of 
capacity and energy from resources to loads while maintaining reliable 
operation of the Transmission Provider's Transmission System in 
accordance with Good Utility Practice.
1.3 Annual Transmission Costs
    The total annual cost of the Transmission System for purposes of 
Network Integration Transmission Service shall be the amount specified 
in Attachment H until amended by the Transmission Provider or modified 
by the Commission.
1.4 Application
    A request by an Eligible Customer for transmission service pursuant 
to the provisions of the Tariff.
1.5 Commission
    The Federal Energy Regulatory Commission.
1.6 Completed Application
    An Application that satisfies all of the information and other 
requirements of the Tariff, including any required deposit.
1.7 Control Area
    An electric power system or combination of electric power systems 
to which a common automatic generation control scheme is applied in 
order to:
    1. Match, at all times, the power output of the generators within 
the electric power system(s) and capacity and energy purchased from 
entities outside the electric power system(s), with the load within the 
electric power system(s);
    2. Maintain scheduled interchange with other Control Areas, within 
the limits of Good Utility Practice;
    3. Maintain the frequency of the electric power system(s) within 
reasonable limits in accordance with Good Utility Practice; and
    4. Provide sufficient generating capacity to maintain operating 
reserves

[[Page 32720]]

in accordance with Good Utility Practice.
1.8 Curtailment
    A reduction in firm or non-firm transmission service in response to 
a transfer capability shortage as a result of system reliability conditions.
1.9 Delivering Party
    The entity supplying capacity and energy to be transmitted at 
Point(s) of Receipt.
1.10 Designated Agent
    Any entity that performs actions or functions on behalf of the 
Transmission Provider, an Eligible Customer, or the Transmission 
Customer required under the Tariff.
1.11 Direct Assignment Facilities
    Facilities or portions of facilities that are constructed by the 
Transmission Provider for the sole use/benefit of a particular 
Transmission Customer requesting service under the Tariff. Direct 
Assignment Facilities shall be specified in the Service Agreement that 
governs service to the Transmission Customer and shall be subject to 
Commission approval.
1.12 Economy Energy
    Energy purchased by a Network Integration Transmission customer 
that displaces that customer's own higher cost designated Network 
Resource(s) for the purpose of serving that customer's designated 
Network Load(s).
1.13 Eligible Customer
    i. Any electric utility (including the Transmission Provider and 
any power marketer), Federal power marketing agency, or any person 
generating electric energy for sale for resale is an Eligible Customer 
under the Tariff. Electric energy sold or produced by such entity may 
be electric energy produced in the United States, Canada or Mexico. 
However, with respect to transmission service that the Commission is 
prohibited from ordering by Section 212(h) of the Federal Power Act, 
such entity is eligible only if the service is provided pursuant to a 
state requirement that the Transmission Provider offer the unbundled 
transmission service, or pursuant to a voluntary offer of such service 
by the Transmission Provider.
    ii. Any retail customer taking unbundled transmission service 
pursuant to a state requirement that the Transmission Provider offer 
the transmission service, or pursuant to a voluntary offer of such 
service by the Transmission Provider, is an Eligible Customer under the 
Tariff.
1.14 Facilities Study
    An engineering study conducted by the Transmission Provider to 
determine the required modifications to the Transmission Provider's 
Transmission System, including the cost and scheduled completion date 
for such modifications, that will be required to provide the requested 
transmission service.
1.15 Firm Point-To-Point Transmission Service
    Transmission Service under this Tariff that is reserved and/or 
scheduled between specified Points of Receipt and Delivery pursuant to 
Part II of this Tariff.
1.16 Good Utility Practice
    Any of the practices, methods and acts engaged in or approved by a 
significant portion of the electric utility industry during the 
relevant time period, or any of the practices, methods and acts which, 
in the exercise of reasonable judgment in light of the facts known at 
the time the decision was made, could have been expected to accomplish 
the desired result at a reasonable cost consistent with good business 
practices, reliability, safety and expedition. Good Utility Practice is 
not intended to be limited to the optimum practice, method, or act to 
the exclusion of all others, but rather to be acceptable practices, 
methods, or acts generally accepted in the region, including those 
practices required by Federal Power Act section 215(a)(4).
1.17 Interruption
    A reduction in non-firm transmission service due to economic 
reasons pursuant to Section 14.7.
1.18 Load Ratio Share
    Ratio of a Transmission Customer's Network Load to the Transmission 
Provider's total load computed in accordance with Sections 34.2 and 
34.3 of the Network Integration Transmission Service under Part III the 
Tariff and calculated on a rolling twelve month basis.
1.19 Load Shedding
    The systematic reduction of system demand by temporarily decreasing 
load in response to transmission system or area capacity shortages, 
system instability, or voltage control considerations under Part III of 
the Tariff.
1.20 Long-Term Firm Point-To-Point Transmission Service
    Firm Point-To-Point Transmission Service under Part II of the 
Tariff with a term of one year or more.
1.21 Native Load Customers
    The wholesale and retail power customers of the Transmission 
Provider on whose behalf the Transmission Provider, by statute, 
franchise, regulatory requirement, or contract, has undertaken an 
obligation to construct and operate the Transmission Provider's system 
to meet the reliable electric needs of such customers.
1.22 Network Customer
    An entity receiving transmission service pursuant to the terms of 
the Transmission Provider's Network Integration Transmission Service 
under Part III of the Tariff.
1.23 Network Integration Transmission Service
    The transmission service provided under Part III of the Tariff.
1.24 Network Load
    The load that a Network Customer designates for Network Integration 
Transmission Service under Part III of the Tariff. The Network 
Customer's Network Load shall include all load served by the output of 
any Network Resources designated by the Network Customer. A Network 
Customer may elect to designate less than its total load as Network 
Load but may not designate only part of the load at a discrete Point of 
Delivery. Where a Eligible Customer has elected not to designate a 
particular load at discrete points of delivery as Network Load, the 
Eligible Customer is responsible for making separate arrangements under 
Part II of the Tariff for any Point-To-Point Transmission Service that 
may be necessary for such non-designated load.
1.25 Network Operating Agreement
    An executed agreement that contains the terms and conditions under 
which the Network Customer shall operate its facilities and the 
technical and operational matters associated with the implementation of 
Network Integration Transmission Service under Part III of the Tariff.
1.26 Network Operating Committee
    A group made up of representatives from the Network Customer(s) and 
the Transmission Provider established to coordinate operating criteria 
and other technical considerations required for implementation of 
Network Integration

[[Page 32721]]

Transmission Service under Part III of this Tariff.
1.27 Network Resource
    Any designated generating resource owned, purchased or leased by a 
Network Customer under the Network Integration Transmission Service 
Tariff. Network Resources do not include any resource, or any portion 
thereof, that is committed for sale to third parties or otherwise 
cannot be called upon to meet the Network Customer's Network Load on a 
non-interruptible basis.
1.28 Network Upgrades
    Modifications or additions to transmission-related facilities that 
are integrated with and support the Transmission Provider's overall 
Transmission System for the general benefit of all users of such 
Transmission System.
1.29 Non-Firm Point-To-Point Transmission Service
    Point-To-Point Transmission Service under the Tariff that is 
reserved and scheduled on an as-available basis and is subject to 
Curtailment or Interruption as set forth in Section 14.7 under Part II 
of this Tariff. Non-Firm Point-To-Point Transmission Service is 
available on a stand-alone basis for periods ranging from one hour to 
one month.
1.30 Non-Firm Sale
    An energy sale for which receipt or delivery may be interrupted for 
any reason or no reason, without liability on the part of either the 
buyer or seller.
1.31 Open Access Same-Time Information System (OASIS)
    The information system and standards of conduct contained in Part 
37 of the Commission's regulations and all additional requirements 
implemented by subsequent Commission orders dealing with OASIS.
1.32 Part I
    Tariff Definitions and Common Service Provisions contained in 
Sections 2 through 12.
1.33 Part II
    Tariff Sections 13 through 27 pertaining to Point-To-Point 
Transmission Service in conjunction with the applicable Common Service 
Provisions of Part I and appropriate Schedules and Attachments.
1.34 Part III
    Tariff Sections 28 through 35 pertaining to Network Integration 
Transmission Service in conjunction with the applicable Common Service 
Provisions of Part I and appropriate Schedules and Attachments.
1.35 Parties
    The Transmission Provider and the Transmission Customer receiving 
service under the Tariff.
1.36 Point(s) of Delivery
    Point(s) on the Transmission Provider's Transmission System where 
capacity and energy transmitted by the Transmission Provider will be 
made available to the Receiving Party under Part II of the Tariff. The 
Point(s) of Delivery shall be specified in the Service Agreement for 
Long-Term Firm Point-To-Point Transmission Service.
1.37 Point(s) of Receipt
    Point(s) of interconnection on the Transmission Provider's 
Transmission System where capacity and energy will be made available to 
the Transmission Provider by the Delivering Party under Part II of the 
Tariff. The Point(s) of Receipt shall be specified in the Service 
Agreement for Long-Term Firm Point-to-Point Transmission Service.
1.38 Point-To-Point Transmission Service
    The reservation and transmission of capacity and energy on either a 
firm or non-firm basis from the Point(s) of Receipt to the Point(s) of 
Delivery under Part II of the Tariff.
1.39 Power Purchaser
    The entity that is purchasing the capacity and energy to be 
transmitted under the Tariff.
1.40 Pre-Confirmed Application
    An Application that commits the Transmission Customer to execute a 
Service Agreement upon receipt of notification that the Transmission 
Provider can provide the requested Transmission Service.
1.41 Receiving Party
    The entity receiving the capacity and energy transmitted by the 
Transmission Provider to Point(s) of Delivery.
1.42 Regional Transmission Group (RTG)
    A voluntary organization of transmission owners, transmission users 
and other entities approved by the Commission to efficiently coordinate 
transmission planning (and expansion), operation and use on a regional 
(and interregional) basis.
1.43 Reserved Capacity
    The maximum amount of capacity and energy that the Transmission 
Provider agrees to transmit for the Transmission Customer over the 
Transmission Provider's Transmission System between the Point(s) of 
Receipt and the Point(s) of Delivery under Part II of the Tariff. 
Reserved Capacity shall be expressed in terms of whole megawatts on a 
sixty (60) minute interval (commencing on the clock hour) basis.
1.44 Service Agreement
    The initial agreement and any amendments or supplements thereto 
entered into by the Transmission Customer and the Transmission Provider 
for service under the Tariff.
1.45 Service Commencement Date
    The date the Transmission Provider begins to provide service 
pursuant to the terms of an executed Service Agreement, or the date the 
Transmission Provider begins to provide service in accordance with 
Section 15.3 or Section 29.1 under the Tariff.
1.46 Short-Term Firm Point-to-Point Transmission Service
    Firm Point-To-Point Transmission Service under Part II of the 
Tariff with a term of less than one year.
1.47 System Impact Study
    An assessment by the Transmission Provider of (i) the adequacy of 
the Transmission System to accommodate a request for either Firm Point-
To-Point Transmission Service or Network Integration Transmission 
Service and (ii) whether any additional costs may be incurred in order 
to provide transmission service.
1.48 Third-Party Sale
    Any sale for resale in interstate commerce to a Power Purchaser 
that is not designated as part of Network Load under the Network 
Integration Transmission Service.
1.49 Transmission Customer
    Any Eligible Customer (or its Designated Agent) that (i) executes a 
Service Agreement, or (ii) requests in writing that the Transmission 
Provider file with the Commission, a proposed unexecuted Service 
Agreement to receive transmission service under Part II of the Tariff. 
This term is used in the Part I Common Service Provisions to include 
customers receiving transmission service under Part II and Part III of 
this Tariff.
1.50 Transmission Provider
    The public utility (or its Designated Agent) that owns, controls, 
or operates facilities used for the transmission of electric energy in 
interstate commerce

[[Page 32722]]

and provides transmission service under the Tariff.
1.51 Transmission Provider's Monthly Transmission System Peak
    The maximum firm usage of the Transmission Provider's Transmission 
System in a calendar month.
1.52 Transmission Service
    Point-To-Point Transmission Service provided under Part II of the 
Tariff on a firm and non-firm basis.
1.53 Transmission System
    The facilities owned, controlled or operated by the Transmission 
Provider that are used to provide transmission service under Part II 
and Part III of the Tariff.

2 Initial Allocation and Renewal Procedures

2.1 Initial Allocation of Available Transfer Capability
    For purposes of determining whether existing capability on the 
Transmission Provider's Transmission System is adequate to accommodate 
a request for firm service under this Tariff, all Completed 
Applications for new firm transmission service received during the 
initial sixty (60) day period commencing with the effective date of the 
Tariff will be deemed to have been filed simultaneously. A lottery 
system conducted by an independent party shall be used to assign 
priorities for Completed Applications filed simultaneously. All 
Completed Applications for firm transmission service received after the 
initial sixty (60) day period shall be assigned a priority pursuant to 
Section 13.2.
2.2 Reservation Priority For Existing Firm Service Customers
    Existing firm service customers (wholesale requirements and 
transmission-only, with a contract term of five years or more), have 
the right to continue to take transmission service from the 
Transmission Provider when the contract expires, rolls over or is 
renewed. This transmission reservation priority is independent of 
whether the existing customer continues to purchase capacity and energy 
from the Transmission Provider or elects to purchase capacity and 
energy from another supplier. If at the end of the contract term, the 
Transmission Provider's Transmission System cannot accommodate all of 
the requests for transmission service, the existing firm service 
customer must agree to accept a contract term at least equal to the 
longer of a competing request by any new Eligible Customer or five 
years and to pay the current just and reasonable rate, as approved by 
the Commission, for such service. The existing firm service customer 
must provide notice to the Transmission Provider whether it will 
exercise its right of first refusal no less than one year prior to the 
expiration date of its transmission service agreement. This 
transmission reservation priority for existing firm service customers 
is an ongoing right that may be exercised at the end of all firm 
contract terms of five years or longer. Service agreements subject to a 
right of first refusal entered into prior to [the acceptance by the 
Commission of the Transmission Provider's Attachment K], unless 
terminated, will become subject to the five year/one year requirement 
on the first rollover date after [the acceptance by the Commission of 
the Transmission Provider's Attachment K].

3 Ancillary Services

    Ancillary Services are needed with transmission service to maintain 
reliability within and among the Control Areas affected by the 
transmission service. The Transmission Provider is required to provide 
(or offer to arrange with the local Control Area operator as discussed 
below), and the Transmission Customer is required to purchase, the 
following Ancillary Services (i) Scheduling, System Control and Dispatch, 
and (ii) Reactive Supply and Voltage Control from Generation Sources.
    The Transmission Provider is required to offer to provide (or offer 
to arrange with the local Control Area operator as discussed below) the 
following Ancillary Services only to the Transmission Customer serving 
load within the Transmission Provider's Control Area (i) Regulation and 
Frequency Response, (ii) Energy Imbalance, (iii) Operating Reserve--
Spinning, and (iv) Operating Reserve--Supplemental. The Transmission 
Customer serving load within the Transmission Provider's Control Area 
is required to acquire these Ancillary Services, whether from the 
Transmission Provider, from a third party, or by self-supply. The 
Transmission Customer may not decline the Transmission Provider's offer 
of Ancillary Services unless it demonstrates that it has acquired the 
Ancillary Services from another source. The Transmission Customer must 
list in its Application which Ancillary Services it will purchase from 
the Transmission Provider.
    If the Transmission Provider is a public utility providing 
transmission service but is not a Control Area operator, it may be 
unable to provide some or all of the Ancillary Services. In this case, 
the Transmission Provider can fulfill its obligation to provide 
Ancillary Services by acting as the Transmission Customer's agent to 
secure these Ancillary Services from the Control Area operator. The 
Transmission Customer may elect to (i) have the Transmission Provider 
act as its agent, (ii) secure the Ancillary Services directly from the 
Control Area operator, or (iii) secure the Ancillary Services 
(discussed in Schedules 3, 4, 5 and 6) from a third party or by self-
supply when technically feasible. The Transmission Provider shall 
specify the rate treatment and all related terms and conditions in the 
event of an unauthorized use of Ancillary Services by the Transmission 
Customer.
    The specific Ancillary Services, prices and/or compensation methods 
are described on the Schedules that are attached to and made a part of 
the Tariff. Three principal requirements apply to discounts for 
Ancillary Services provided by the Transmission Provider in conjunction 
with its provision of transmission service as follows: (1) Any offer of 
a discount made by the Transmission Provider must be announced to all 
Eligible Customers solely by posting on the OASIS, (2) any customer-
initiated requests for discounts (including requests for use by one's 
wholesale merchant or an affiliate's use) must occur solely by posting 
on the OASIS, and (3) once a discount is negotiated, details must be 
immediately posted on the OASIS. A discount agreed upon for an 
Ancillary Service must be offered for the same period to all Eligible 
Customers on the Transmission Provider's system. Sections 3.1 through 
3.6 below list the six Ancillary Services.
3.1 Scheduling, System Control and Dispatch Service
    The rates and/or methodology are described in Schedule 1.
3.2 Reactive Supply and Voltage Control From Generation Sources Service
    The rates and/or methodology are described in Schedule 2.
3.3 Regulation and Frequency Response Service
    Where applicable the rates and/or methodology are described in 
Schedule 3.
3.4 Energy Imbalance Service
    Where applicable the rates and/or methodology are described in 
Schedule 4.

[[Page 32723]]

3.5 Operating Reserve--Spinning Reserve Service
    Where applicable the rates and/or methodology are described in 
Schedule 5.
3.6 Operating Reserve--Supplemental Reserve Service
    Where applicable the rates and/or methodology are described in 
Schedule 6.

4 Open Access Same-Time Information System (OASIS)

    Terms and conditions regarding Open Access Same-Time Information 
System and standards of conduct are set forth in 18 CFR 37 of the 
Commission's regulations (Open Access Same-Time Information System and 
Standards of Conduct for Public Utilities) and 18 CFR 38 of the 
Commission's regulations (Business Practice Standards and Communication 
Protocols for Public Utilities). In the event available transfer 
capability as posted on the OASIS is insufficient to accommodate a 
request for firm transmission service, additional studies may be 
required as provided by this Tariff pursuant to Sections 19 and 32.

5 Local Furnishing Bonds

5.1 Transmission Providers That Own Facilities Financed by Local 
Furnishing Bonds
    This provision is applicable only to Transmission Providers that 
have financed facilities for the local furnishing of electric energy 
with tax-exempt bonds, as described in Section 142(f) of the Internal 
Revenue Code (``local furnishing bonds''). Notwithstanding any other 
provision of this Tariff, the Transmission Provider shall not be 
required to provide transmission service to any Eligible Customer 
pursuant to this Tariff if the provision of such transmission service 
would jeopardize the tax-exempt status of any local furnishing bond(s) 
used to finance the Transmission Provider's facilities that would be 
used in providing such transmission service.
5.2 Alternative Procedures for Requesting Transmission Service
    (i) If the Transmission Provider determines that the provision of 
transmission service requested by an Eligible Customer would jeopardize 
the tax-exempt status of any local furnishing bond(s) used to finance 
its facilities that would be used in providing such transmission 
service, it shall advise the Eligible Customer within thirty (30) days 
of receipt of the Completed Application.
    (ii) If the Eligible Customer thereafter renews its request for the 
same transmission service referred to in (i) by tendering an 
application under Section 211 of the Federal Power Act, the 
Transmission Provider, within ten (10) days of receiving a copy of the 
Section 211 application, will waive its rights to a request for service 
under Section 213(a) of the Federal Power Act and to the issuance of a 
proposed order under Section 212(c) of the Federal Power Act. The 
Commission, upon receipt of the Transmission Provider's waiver of its 
rights to a request for service under Section 213(a) of the Federal 
Power Act and to the issuance of a proposed order under Section 212(c) 
of the Federal Power Act, shall issue an order under Section 211 of the 
Federal Power Act. Upon issuance of the order under Section 211 of the 
Federal Power Act, the Transmission Provider shall be required to 
provide the requested transmission service in accordance with the terms 
and conditions of this Tariff.

6. Reciprocity

    A Transmission Customer receiving transmission service under this 
Tariff agrees to provide comparable transmission service that it is 
capable of providing to the Transmission Provider on similar terms and 
conditions over facilities used for the transmission of electric energy 
owned, controlled or operated by the Transmission Customer and over 
facilities used for the transmission of electric energy owned, 
controlled or operated by the Transmission Customer's corporate 
affiliates. A Transmission Customer that is a member of a power pool or 
Regional Transmission Group also agrees to provide comparable 
transmission service to the members of such power pool and Regional 
Transmission Group on similar terms and conditions over facilities used 
for the transmission of electric energy owned, controlled or operated 
by the Transmission Customer and over facilities used for the 
transmission of electric energy owned, controlled or operated by the 
Transmission Customer's corporate affiliates.
    This reciprocity requirement applies not only to the Transmission 
Customer that obtains transmission service under the Tariff, but also 
to all parties to a transaction that involves the use of transmission 
service under the Tariff, including the power seller, buyer and any 
intermediary, such as a power marketer. This reciprocity requirement 
also applies to any Eligible Customer that owns, controls or operates 
transmission facilities that uses an intermediary, such as a power 
marketer, to request transmission service under the Tariff. If the 
Transmission Customer does not own, control or operate transmission 
facilities, it must include in its Application a sworn statement of one 
of its duly authorized officers or other representatives that the 
purpose of its Application is not to assist an Eligible Customer to 
avoid the requirements of this provision.

7 Billing and Payment

7.1 Billing Procedure
    Within a reasonable time after the first day of each month, the 
Transmission Provider shall submit an invoice to the Transmission 
Customer for the charges for all services furnished under the Tariff 
during the preceding month. The invoice shall be paid by the 
Transmission Customer within twenty (20) days of receipt. All payments 
shall be made in immediately available funds payable to the 
Transmission Provider, or by wire transfer to a bank named by the 
Transmission Provider.
7.2 Interest on Unpaid Balances
    Interest on any unpaid amounts (including amounts placed in escrow) 
shall be calculated in accordance with the methodology specified for 
interest on refunds in the Commission's regulations at 18 CFR 
35.19a(a)(2)(iii). Interest on delinquent amounts shall be calculated 
from the due date of the bill to the date of payment. When payments are 
made by mail, bills shall be considered as having been paid on the date 
of receipt by the Transmission Provider.
7.3 Customer Default
    In the event the Transmission Customer fails, for any reason other 
than a billing dispute as described below, to make payment to the 
Transmission Provider on or before the due date as described above, and 
such failure of payment is not corrected within thirty (30) calendar 
days after the Transmission Provider notifies the Transmission Customer 
to cure such failure, a default by the Transmission Customer shall be 
deemed to exist. Upon the occurrence of a default, the Transmission 
Provider may initiate a proceeding with the Commission to terminate 
service but shall not terminate service until the Commission so 
approves any such request. In the event of a billing dispute between 
the Transmission Provider and the Transmission Customer, the 
Transmission Provider will continue to provide service under the 
Service Agreement as long as the Transmission Customer (i) continues to 
make all

[[Page 32724]]

payments not in dispute, and (ii) pays into an independent escrow 
account the portion of the invoice in dispute, pending resolution of 
such dispute. If the Transmission Customer fails to meet these two 
requirements for continuation of service, then the Transmission 
Provider may provide notice to the Transmission Customer of its 
intention to suspend service in sixty (60) days, in accordance with 
Commission policy.

8 Accounting for the Transmission Provider's Use of the Tariff

    The Transmission Provider shall record the following amounts, as 
outlined below.
8.1 Transmission Revenues
    Include in a separate operating revenue account or subaccount the 
revenues it receives from Transmission Service when making Third-Party 
Sales under Part II of the Tariff.
8.2 Study Costs and Revenues
    Include in a separate transmission operating expense account or 
subaccount, costs properly chargeable to expense that are incurred to 
perform any System Impact Studies or Facilities Studies which the 
Transmission Provider conducts to determine if it must construct new 
transmission facilities or upgrades necessary for its own uses, 
including making Third-Party Sales under the Tariff; and include in a 
separate operating revenue account or subaccount the revenues received 
for System Impact Studies or Facilities Studies performed when such 
amounts are separately stated and identified in the Transmission 
Customer's billing under the Tariff.

9 Regulatory Filings

    Nothing contained in the Tariff or any Service Agreement shall be 
construed as affecting in any way the right of the Transmission 
Provider to unilaterally make application to the Commission for a 
change in rates, terms and conditions, charges, classification of 
service, Service Agreement, rule or regulation under Section 205 of the 
Federal Power Act and pursuant to the Commission's rules and 
regulations promulgated thereunder.
    Nothing contained in the Tariff or any Service Agreement shall be 
construed as affecting in any way the ability of any Party receiving 
service under the Tariff to exercise its rights under the Federal Power 
Act and pursuant to the Commission's rules and regulations promulgated 
thereunder.

10 Force Majeure and Indemnification

10.1 Force Majeure
    An event of Force Majeure means any act of God, labor disturbance, 
act of the public enemy, war, insurrection, riot, fire, storm or flood, 
explosion, breakage or accident to machinery or equipment, any 
Curtailment, order, regulation or restriction imposed by governmental 
military or lawfully established civilian authorities, or any other 
cause beyond a Party's control. A Force Majeure event does not include 
an act of negligence or intentional wrongdoing. Neither the 
Transmission Provider nor the Transmission Customer will be considered 
in default as to any obligation under this Tariff if prevented from 
fulfilling the obligation due to an event of Force Majeure. However, a 
Party whose performance under this Tariff is hindered by an event of 
Force Majeure shall make all reasonable efforts to perform its 
obligations under this Tariff.
10.2 Indemnification
    The Transmission Customer shall at all times indemnify, defend, and 
save the Transmission Provider harmless from any and all damages, 
losses, claims, including claims and actions relating to injury to or 
death of any person or damage to property, demands, suits, recoveries, 
costs and expenses, court costs, attorney fees, and all other 
obligations by or to third parties, arising out of or resulting from 
the Transmission Provider's performance of its obligations under this 
Tariff on behalf of the Transmission Customer, except in cases of 
negligence or intentional wrongdoing by the Transmission Provider.

11 Creditworthiness

    The Transmission Provider will specify its Creditworthiness 
procedures in Attachment L.

12 Dispute Resolution Procedures

12.1 Internal Dispute Resolution Procedures
    Any dispute between a Transmission Customer and the Transmission 
Provider involving transmission service under the Tariff (excluding 
applications for rate changes or other changes to the Tariff, or to any 
Service Agreement entered into under the Tariff, which shall be 
presented directly to the Commission for resolution) shall be referred 
to a designated senior representative of the Transmission Provider and 
a senior representative of the Transmission Customer for resolution on 
an informal basis as promptly as practicable. In the event the 
designated representatives are unable to resolve the dispute within 
thirty (30) days [or such other period as the Parties may agree upon]
by mutual agreement, such dispute may be submitted to arbitration and 
resolved in accordance with the arbitration procedures set forth below.
12.2 External Arbitration Procedures
    Any arbitration initiated under the Tariff shall be conducted 
before a single neutral arbitrator appointed by the Parties. If the 
Parties fail to agree upon a single arbitrator within ten (10) days of 
the referral of the dispute to arbitration, each Party shall choose one 
arbitrator who shall sit on a three-member arbitration panel. The two 
arbitrators so chosen shall within twenty (20) days select a third 
arbitrator to chair the arbitration panel. In either case, the 
arbitrators shall be knowledgeable in electric utility matters, 
including electric transmission and bulk power issues, and shall not 
have any current or past substantial business or financial 
relationships with any party to the arbitration (except prior 
arbitration). The arbitrator(s) shall provide each of the Parties an 
opportunity to be heard and, except as otherwise provided herein, shall 
generally conduct the arbitration in accordance with the Commercial 
Arbitration Rules of the American Arbitration Association and any 
applicable Commission regulations or Regional Transmission Group rules.
12.3 Arbitration Decisions
    Unless otherwise agreed, the arbitrator(s) shall render a decision 
within ninety (90) days of appointment and shall notify the Parties in 
writing of such decision and the reasons therefor. The arbitrator(s) 
shall be authorized only to interpret and apply the provisions of the 
Tariff and any Service Agreement entered into under the Tariff and 
shall have no power to modify or change any of the above in any manner. 
The decision of the arbitrator(s) shall be final and binding upon the 
Parties, and judgment on the award may be entered in any court having 
jurisdiction. The decision of the arbitrator(s) may be appealed solely 
on the grounds that the conduct of the arbitrator(s), or the decision 
itself, violated the standards set forth in the Federal Arbitration Act 
and/or the Administrative Dispute Resolution Act. The final decision of 
the arbitrator must also be filed with the Commission if it affects 
jurisdictional rates, terms and conditions of service or facilities.

[[Page 32725]]

12.4 Costs
    Each Party shall be responsible for its own costs incurred during 
the arbitration process and for the following costs, if applicable:
    1. The cost of the arbitrator chosen by the Party to sit on the 
three member panel and one half of the cost of the third arbitrator 
chosen; or
    2. One half the cost of the single arbitrator jointly chosen by the 
Parties.
12.5 Rights Under the Federal Power Act
    Nothing in this section shall restrict the rights of any party to 
file a Complaint with the Commission under relevant provisions of the 
Federal Power Act.

II. Point-To-Point Transmission Service

Preamble

    The Transmission Provider will provide Firm and Non-Firm Point-To-
Point Transmission Service pursuant to the applicable terms and 
conditions of this Tariff. Point-To-Point Transmission Service is for 
the receipt of capacity and energy at designated Point(s) of Receipt 
and the transfer of such capacity and energy to designated Point(s) of 
Delivery.

13 Nature of Firm Point-To-Point Transmission Service

13.1 Term
    The minimum term of Firm Point-To-Point Transmission Service shall 
be one hour and the maximum term shall be specified in the Service 
Agreement.
13.2 Reservation Priority
    (i) Long-Term Firm Point-To-Point Transmission Service shall be 
available on a first-come, first-served basis, i.e., in the 
chronological sequence in which each Transmission Customer has 
requested service. However, Pre-Confirmed Applications for service will 
receive priority over earlier-submitted requests that are not Pre-
Confirmed. Within classes of requests (Pre-Confirmed or not confirmed), 
the highest price offered by the Eligible Customer is the first 
tiebreaker, followed by the date and time of the request.
    (ii) Reservations for Short-Term Firm Point-To-Point Transmission 
Service will be conditional based upon the length of the requested 
transaction. However, Pre-Confirmed Applications for Short-Term Point-
To-Point Transmission Service will receive priority over earlier-
submitted requests that are not Pre-Confirmed. Within classes of 
requests (Pre-Confirmed or not confirmed), duration is the first 
tiebreaker, followed by the highest price offered by the Eligible 
Customer, followed by the date and time of the request.
    (iii) If the Transmission System becomes oversubscribed, requests 
for longer term service may preempt requests for shorter term service 
up to the following deadlines: one hour before the commencement of 
hourly service, one day before the commencement of daily service, one 
week before the commencement of weekly service, and one month before 
the commencement of monthly service. Before the conditional reservation 
deadline, if available transfer capability is insufficient to satisfy 
all Applications, an Eligible Customer with a reservation for shorter 
term service has the right of first refusal to match any longer term 
reservation before losing its reservation priority. A longer term 
competing request for Short-Term Firm Point-To-Point Transmission 
Service will be granted if the Eligible Customer with the right of 
first refusal does not agree to match the competing request within 24 
hours (or earlier if necessary to comply with the scheduling deadlines 
provided in section 13.8) from being notified by the Transmission 
Provider of a longer-term competing request for Short-Term Firm Point-
To-Point Transmission Service. After the conditional reservation 
deadline, service will commence pursuant to the terms of Part II of the 
Tariff.
    (iv) Firm Point-To-Point Transmission Service will always have a 
reservation priority over Non-Firm Point-To-Point Transmission Service 
under the Tariff. All Long-Term Firm Point-To-Point Transmission 
Service will have equal reservation priority with Native Load Customers 
and Network Customers. Reservation priorities for existing firm service 
customers are provided in Section 2.2.
13.3 Use of Firm Transmission Service by the Transmission Provider
    The Transmission Provider will be subject to the rates, terms and 
conditions of Part II of the Tariff when making Third-Party Sales under 
(i) agreements executed on or after August 7, 2006 or (ii) agreements 
executed prior to the aforementioned date that the Commission requires 
to be unbundled, by the date specified by the Commission. The 
Transmission Provider will maintain separate accounting, pursuant to 
Section 8, for any use of the Point-To-Point Transmission Service to 
make Third-Party Sales.
13.4 Service Agreements
    The Transmission Provider shall offer a standard form Firm Point-
To-Point Transmission Service Agreement (Attachment A) to an Eligible 
Customer when it submits a Completed Application for Long-Term Firm 
Point-To-Point Transmission Service. The Transmission Provider shall 
offer a standard form Firm Point-To-Point Transmission Service 
Agreement (Attachment A) to an Eligible Customer when it first submits 
a Completed Application for Short-Term Firm Point-To-Point Transmission 
Service pursuant to the Tariff. Executed Service Agreements that 
contain the information required under the Tariff shall be filed with 
the Commission in compliance with applicable Commission regulations.
13.5 Transmission Customer Obligations for Facility Additions or 
Redispatch Costs
    In cases where the Transmission Provider determines that the 
Transmission System is not capable of providing Firm Point-To-Point 
Transmission Service without (1) degrading or impairing the reliability 
of service to Native Load Customers, Network Customers and other 
Transmission Customers taking Firm Point-To-Point Transmission Service, 
or (2) interfering with the Transmission Provider's ability to meet 
prior firm contractual commitments to others, the Transmission Provider 
will be obligated to expand or upgrade its Transmission System pursuant 
to the terms of Section 15.4. The Transmission Customer must agree to 
compensate the Transmission Provider for any necessary transmission 
facility additions pursuant to the terms of Section 27. To the extent 
the Transmission Provider can relieve any system constraint more 
economically by redispatching the Transmission Provider's resources 
than through constructing Network Upgrades, it shall do so, provided 
that the Eligible Customer agrees to compensate the Transmission 
Provider pursuant to the terms of Section 27. Any redispatch, Network 
Upgrade or Direct Assignment Facilities costs to be charged to the 
Transmission Customer on an incremental basis under the Tariff will be 
specified in the Service Agreement prior to initiating service.
13.6 Curtailment of Firm Transmission Service
    In the event that a Curtailment on the Transmission Provider's 
Transmission System, or a portion thereof, is required to maintain 
reliable operation of such

[[Page 32726]]

system and the system directly and indirectly interconnected with 
Transmission Provider's Transmission system. Curtailments will be made 
on a non-discriminatory basis to the transaction(s) that effectively 
relieve the constraint. Transmission Provider may elect to implement 
such Curtailments pursuant to the Transmission Loading Relief 
procedures specified in Attachment J. If multiple transactions require 
Curtailment, to the extent practicable and consistent with Good Utility 
Practice, the Transmission Provider will curtail service to Network 
Customers and Transmission Customers taking Firm Point-To-Point 
Transmission Service on a basis comparable to the curtailment of 
service to the Transmission Provider's Native Load Customers. All 
Curtailments will be made on a non-discriminatory basis, however, Non-
Firm Point-To-Point Transmission Service shall be subordinate to Firm 
Transmission Service. When the Transmission Provider determines that an 
electrical emergency exists on its Transmission System and implements 
emergency procedures to Curtail Firm Transmission Service, the 
Transmission Customer shall make the required reductions upon request 
of the Transmission Provider. However, the Transmission Provider 
reserves the right to Curtail, in whole or in part, any Firm 
Transmission Service provided under the Tariff when, in the 
Transmission Provider's sole discretion, an emergency or other 
unforeseen condition impairs or degrades the reliability of its 
Transmission System. The Transmission Provider will notify all affected 
Transmission Customers in a timely manner of any scheduled Curtailments.
13.7 Classification of Firm Transmission Service
    (a) The Transmission Customer taking Firm Point-To-Point 
Transmission Service may (1) change its Receipt and Delivery Points to 
obtain service on a non-firm basis consistent with the terms of Section 
22.1 or (2) request a modification of the Points of Receipt or Delivery 
on a firm basis pursuant to the terms of Section 22.2.
    (b) The Transmission Customer may purchase transmission service to 
make sales of capacity and energy from multiple generating units that 
are on the Transmission Provider's Transmission System. For such a 
purchase of transmission service, the resources will be designated as 
multiple Points of Receipt, unless the multiple generating units are at 
the same generating plant in which case the units would be treated as a 
single Point of Receipt.
    (c) The Transmission Provider shall provide firm deliveries of 
capacity and energy from the Point(s) of Receipt to the Point(s) of 
Delivery. Each Point of Receipt at which firm transmission capacity is 
reserved by the Transmission Customer shall be set forth in the Firm 
Point-To-Point Service Agreement for Long-Term Firm Transmission 
Service along with a corresponding capacity reservation associated with 
each Point of Receipt. Points of Receipt and corresponding capacity 
reservations shall be as mutually agreed upon by the Parties for Short-
Term Firm Transmission. Each Point of Delivery at which firm transfer 
capability is reserved by the Transmission Customer shall be set forth 
in the Firm Point-To-Point Service Agreement for Long-Term Firm 
Transmission Service along with a corresponding capacity reservation 
associated with each Point of Delivery. Points of Delivery and 
corresponding capacity reservations shall be as mutually agreed upon by 
the Parties for Short-Term Firm Transmission. The greater of either (1) 
the sum of the capacity reservations at the Point(s) of Receipt, or (2) 
the sum of the capacity reservations at the Point(s) of Delivery shall 
be the Transmission Customer's Reserved Capacity. The Transmission 
Customer will be billed for its Reserved Capacity under the terms of 
Schedule 7. The Transmission Customer may not exceed its firm capacity 
reserved at each Point of Receipt and each Point of Delivery except as 
otherwise specified in Section 22. The Transmission Provider shall 
specify the rate treatment and all related terms and conditions 
applicable in the event that a Transmission Customer (including Third-
Party Sales by the Transmission Provider) exceeds its firm reserved 
capacity at any Point of Receipt or Point of Delivery or uses 
Transmission Service at a Point of Receipt or Point of Delivery that it 
has not reserved.
13.8 Scheduling of Firm Point-To-Point Transmission Service
    Schedules for the Transmission Customer's Firm Point-To-Point 
Transmission Service must be submitted to the Transmission Provider no 
later than 10 a.m. [or a reasonable time that is generally accepted in 
the region and is consistently adhered to by the Transmission Provider]
of the day prior to commencement of such service. Schedules submitted 
after 10 a.m. will be accommodated, if practicable. Hour-to-hour 
schedules of any capacity and energy that is to be delivered must be 
stated in increments of 1,000 kW per hour [or a reasonable increment 
that is generally accepted in the region and is consistently adhered to 
by the Transmission Provider]. Transmission Customers within the 
Transmission Provider's service area with multiple requests for 
Transmission Service at a Point of Receipt, each of which is under 
1,000 kW per hour, may consolidate their service requests at a common 
point of receipt into units of 1,000 kW per hour for scheduling and 
billing purposes. Transmission customers may also batch requests and 
schedules for hourly firm service to be provided on the same day. 
Scheduling changes will be permitted up to twenty (20) minutes [or a 
reasonable time that is generally accepted in the region and is 
consistently adhered to by the Transmission Provider] before the start 
of the next clock hour provided that the Delivering Party and Receiving 
Party also agree to the schedule modification. The Transmission 
Provider will furnish to the Delivering Party's system operator, hour-
to-hour schedules equal to those furnished by the Receiving Party 
(unless reduced for losses) and shall deliver the capacity and energy 
provided by such schedules. Should the Transmission Customer, 
Delivering Party or Receiving Party revise or terminate any schedule, 
such party shall immediately notify the Transmission Provider, and the 
Transmission Provider shall have the right to adjust accordingly the 
schedule for capacity and energy to be received and to be delivered.

14 Nature of Non-Firm Point-To-Point Transmission Service

14.1 Term
    Non-Firm Point-To-Point Transmission Service will be available for 
periods ranging from one (1) hour to one (1) month. However, a 
Purchaser of Non-Firm Point-To-Point Transmission Service will be 
entitled to reserve a sequential term of service (such as a sequential 
monthly term without having to wait for the initial term to expire 
before requesting another monthly term) so that the total time period 
for which the reservation applies is greater than one month, subject to 
the requirements of Section 18.3.
14.2 Reservation Priority
    Non-Firm Point-To-Point Transmission Service shall be available 
from transfer capability in excess of that needed for reliable service 
to Native Load Customers, Network Customers and other Transmission 
Customers taking Long-Term and Short-Term Firm Point-To-Point 
Transmission Service. A higher priority will be assigned first to Pre-
Confirmed Applications and second

[[Page 32727]]

to reservations with a longer duration of service. In the event the 
Transmission System is constrained, competing requests of the same Pre-
Confirmation status and equal duration will be prioritized based on the 
highest price offered by the Eligible Customer for the Transmission 
Service. Eligible Customers that have already reserved shorter term 
service have the right of first refusal to match any longer term 
reservation before being preempted. A longer term competing request for 
Non-Firm Point-To-Point Transmission Service will be granted if the 
Eligible Customer with the right of first refusal does not agree to 
match the competing request: (a) Immediately for hourly Non-Firm Point-
To-Point Transmission Service after notification by the Transmission 
Provider; and, (b) within 24 hours (or earlier if necessary to comply 
with the scheduling deadlines provided in section 14.6) for Non-Firm 
Point-To-Point Transmission Service other than hourly transactions 
after notification by the Transmission Provider. Transmission service 
for Network Customers from resources other than designated Network 
Resources will have a higher priority than any Non-Firm Point-To-Point 
Transmission Service. Non-Firm Point-To-Point Transmission Service over 
secondary Point(s) of Receipt and Point(s) of Delivery will have the 
lowest reservation priority under the Tariff.
14.3 Use of Non-Firm Point-To-Point Transmission Service by the 
Transmission Provider
    The Transmission Provider will be subject to the rates, terms and 
conditions of Part II of the Tariff when making Third-Party Sales under 
(i) agreements executed on or after August 7, 2006 or (ii) agreements 
executed prior to the aforementioned date that the Commission requires 
to be unbundled, by the date specified by the Commission. The 
Transmission Provider will maintain separate accounting, pursuant to 
Section 8, for any use of Non-Firm Point-To-Point Transmission Service 
to make Third-Party Sales.
14.4 Service Agreements
    The Transmission Provider shall offer a standard form Non-Firm 
Point-To-Point Transmission Service Agreement (Attachment B) to an 
Eligible Customer when it first submits a Completed Application for 
Non-Firm Point-To-Point Transmission Service pursuant to the Tariff. 
Executed Service Agreements that contain the information required under 
the Tariff shall be filed with the Commission in compliance with 
applicable Commission regulations.
14.5 Classification of Non-Firm Point-To-Point Transmission Service
    Non-Firm Point-To-Point Transmission Service shall be offered under 
terms and conditions contained in Part II of the Tariff. The 
Transmission Provider undertakes no obligation under the Tariff to plan 
its Transmission System in order to have sufficient capacity for Non-
Firm Point-To-Point Transmission Service. Parties requesting Non-Firm 
Point-To-Point Transmission Service for the transmission of firm power 
do so with the full realization that such service is subject to 
availability and to Curtailment or Interruption under the terms of the 
Tariff. The Transmission Provider shall specify the rate treatment and 
all related terms and conditions applicable in the event that a 
Transmission Customer (including Third-Party Sales by the Transmission 
Provider) exceeds its non-firm capacity reservation. Non-Firm Point-To-
Point Transmission Service shall include transmission of energy on an 
hourly basis and transmission of scheduled short-term capacity and 
energy on a daily, weekly or monthly basis, but not to exceed one 
month's reservation for any one Application, under Schedule 8.
14.6 Scheduling of Non-Firm Point-To-Point Transmission Service
    Schedules for Non-Firm Point-To-Point Transmission Service must be 
submitted to the Transmission Provider no later than 2 p.m. [or a 
reasonable time that is generally accepted in the region and is 
consistently adhered to by the Transmission Provider] of the day prior 
to commencement of such service. Schedules submitted after 2 p.m. will 
be accommodated, if practicable. Hour-to-hour schedules of energy that 
is to be delivered must be stated in increments of 1,000 kW per hour 
[or a reasonable increment that is generally accepted in the region and 
is consistently adhered to by the Transmission Provider]. Transmission 
Customers within the Transmission Provider's service area with multiple 
requests for Transmission Service at a Point of Receipt, each of which 
is under 1,000 kW per hour, may consolidate their schedules at a common 
Point of Receipt into units of 1,000 kW per hour. Scheduling changes 
will be permitted up to twenty (20) minutes [or a reasonable time that 
is generally accepted in the region and is consistently adhered to by 
the Transmission Provider] before the start of the next clock hour 
provided that the Delivering Party and Receiving Party also agree to 
the schedule modification. The Transmission Provider will furnish to 
the Delivering Party's system operator, hour-to-hour schedules equal to 
those furnished by the Receiving Party (unless reduced for losses) and 
shall deliver the capacity and energy provided by such schedules. 
Should the Transmission Customer, Delivering Party or Receiving Party 
revise or terminate any schedule, such party shall immediately notify 
the Transmission Provider, and the Transmission Provider shall have the 
right to adjust accordingly the schedule for capacity and energy to be 
received and to be delivered.
14.7 Curtailment or Interruption of Service
    The Transmission Provider reserves the right to Curtail, in whole 
or in part, Non-Firm Point-To-Point Transmission Service provided under 
the Tariff for reliability reasons when, an emergency or other 
unforeseen condition threatens to impair or degrade the reliability of 
its Transmission System or the systems directly and indirectly 
interconnected with Transmission Provider's Transmission System. 
Transmission Provider may elect to implement such Curtailments pursuant 
to the Transmission Loading Relief procedures specified in Attachment 
J. The Transmission Provider reserves the right to Interrupt, in whole 
or in part, Non-Firm Point-To-Point Transmission Service provided under 
the Tariff for economic reasons in order to accommodate (1) a request 
for Firm Transmission Service, (2) a request for Non-Firm Point-To-
Point Transmission Service of greater duration, (3) a request for Non-
Firm Point-To-Point Transmission Service of equal duration with a 
higher price, or (4) transmission service for Network Customers from 
non-designated resources. The Transmission Provider also will 
discontinue or reduce service to the Transmission Customer to the 
extent that deliveries for transmission are discontinued or reduced at 
the Point(s) of Receipt. Where required, Curtailments or Interruptions 
will be made on a non-discriminatory basis to the transaction(s) that 
effectively relieve the constraint, however, Non-Firm Point-To-Point 
Transmission Service shall be subordinate to Firm Transmission Service. 
If multiple transactions require Curtailment or Interruption, to the 
extent practicable and consistent with Good Utility Practice, 
Curtailments or Interruptions will be made to transactions of the 
shortest term (e.g., hourly non-firm transactions will be Curtailed or

[[Page 32728]]

Interrupted before daily non-firm transactions and daily non-firm 
transactions will be Curtailed or Interrupted before weekly non-firm 
transactions). Transmission service for Network Customers from 
resources other than designated Network Resources will have a higher 
priority than any Non-Firm Point-To-Point Transmission Service under 
the Tariff. Non-Firm Point-To-Point Transmission Service over secondary 
Point(s) of Receipt and Point(s) of Delivery will have a lower priority 
than any Non-Firm Point-To-Point Transmission Service under the Tariff. 
The Transmission Provider will provide advance notice of Curtailment or 
Interruption where such notice can be provided consistent with Good 
Utility Practice.

15 Service Availability

15.1 General Conditions
    The Transmission Provider will provide Firm and Non-Firm Point-To-
Point Transmission Service over, on or across its Transmission System 
to any Transmission Customer that has met the requirements of Section 16.
15.2 Determination of Available Transfer Capability
    A description of the Transmission Provider's specific methodology 
for assessing available transfer capability posted on the Transmission 
Provider's OASIS (Section 4) is contained in Attachment C of the 
Tariff. In the event sufficient transfer capability may not exist to 
accommodate a service request, the Transmission Provider will respond 
by performing a System Impact Study.
15.3 Initiating Service in the Absence of an Executed Service Agreement
    If the Transmission Provider and the Transmission Customer 
requesting Firm or Non-Firm Point-To-Point Transmission Service cannot 
agree on all the terms and conditions of the Point-To-Point Service 
Agreement, the Transmission Provider shall file with the Commission, 
within thirty (30) days after the date the Transmission Customer 
provides written notification directing the Transmission Provider to 
file, an unexecuted Point-To-Point Service Agreement containing terms 
and conditions deemed appropriate by the Transmission Provider for such 
requested Transmission Service. The Transmission Provider shall 
commence providing Transmission Service subject to the Transmission 
Customer agreeing to (i) compensate the Transmission Provider at 
whatever rate the Commission ultimately determines to be just and 
reasonable, and (ii) comply with the terms and conditions of the Tariff 
including posting appropriate security deposits in accordance with the 
terms of Section 17.3.
15.4 Obligation To Provide Transmission Service That Requires Expansion 
or Modification of the Transmission System
    If the Transmission Provider determines that it cannot accommodate 
a Completed Application for Firm Point-To-Point Transmission Service 
because of insufficient capability on its Transmission System, the 
Transmission Provider will use due diligence to redispatch its own 
resources or expand or modify its Transmission System to provide the 
requested Firm Transmission Service, consistent with its planning 
obligations in Attachment K, provided the Transmission Customer agrees 
to compensate the Transmission Provider for such costs pursuant to the 
terms of Section 27. The Transmission Provider will conform to Good 
Utility Practice and its planning obligations in Attachment K, in 
determining the need for new facilities and in the design and 
construction of such facilities. The obligation applies only to those 
facilities that the Transmission Provider has the right to expand or 
modify. To the extent a Transmission Provider cannot redispatch its own 
resources to provide the requested Firm Transmission Service, it shall 
identify generators in other control areas that could relieve the 
constraint and allow the Transmission Customer to seek redispatch with 
Transmission Providers in adjacent Control Areas.
15.5 Deferral of Service
    The Transmission Provider may defer providing service until it 
completes construction of new transmission facilities or upgrades 
needed to provide Firm Point-To-Point Transmission Service whenever the 
Transmission Provider determines that providing the requested service 
would, without such new facilities or upgrades, impair or degrade 
reliability to any existing firm services.
15.6 Other Transmission Service Schedules
    Eligible Customers receiving transmission service under other 
agreements on file with the Commission may continue to receive 
transmission service under those agreements until such time as those 
agreements may be modified by the Commission.
15.7 Real Power Losses
    Real Power Losses are associated with all transmission service. The 
Transmission Provider is not obligated to provide Real Power Losses. 
The Transmission Customer is responsible for replacing losses 
associated with all transmission service as calculated by the 
Transmission Provider. The applicable Real Power Loss factors are as 
follows: [To be completed by the Transmission Provider].

16 Transmission Customer Responsibilities

16.1 Conditions Required of Transmission Customers
    Point-To-Point Transmission Service shall be provided by the 
Transmission Provider only if the following conditions are satisfied by 
the Transmission Customer:
    (a) The Transmission Customer has pending a Completed Application 
for service;
    (b) The Transmission Customer meets the creditworthiness criteria 
set forth in Section 11;
    (c) The Transmission Customer will have arrangements in place for 
any other transmission service necessary to effect the delivery from 
the generating source to the Transmission Provider prior to the time 
service under Part II of the Tariff commences;
    (d) The Transmission Customer agrees to pay for any facilities 
constructed and chargeable to such Transmission Customer under Part II 
of the Tariff, whether or not the Transmission Customer takes service 
for the full term of its reservation;
    (e) The Transmission Customer provides the information required by 
the Transmission Provider's planning process established in Attachment 
K; and
    (f) The Transmission Customer has executed a Point-To-Point Service 
Agreement or has agreed to receive service pursuant to Section 15.3.
16.2 Transmission Customer Responsibility for Third-Party Arrangements
    Any scheduling arrangements that may be required by other electric 
systems shall be the responsibility of the Transmission Customer 
requesting service. The Transmission Customer shall provide, unless 
waived by the Transmission Provider, notification to the Transmission 
Provider identifying such systems and authorizing them to schedule the 
capacity and energy to be transmitted by the Transmission Provider 
pursuant to Part II of the Tariff on behalf of the Receiving Party at 
the Point of Delivery or the Delivering Party at the Point of Receipt. 
However, the Transmission Provider will undertake

[[Page 32729]]

reasonable efforts to assist the Transmission Customer in making such 
arrangements, including without limitation, providing any information 
or data required by such other electric system pursuant to Good Utility 
Practice.

17 Procedures for Arranging Firm Point-To-Point Transmission Service

17.1 Application
    A request for Firm Point-To-Point Transmission Service for periods 
of one year or longer must contain a written Application to: 
[Transmission Provider Name and Address], at least sixty (60) days in 
advance of the calendar month in which service is to commence. The 
Transmission Provider will consider requests for such firm service on 
shorter notice when feasible. Requests for firm service for periods of 
less than one year shall be subject to expedited procedures that shall 
be negotiated between the Parties within the time constraints provided 
in Section 17.5. All Firm Point-To-Point Transmission Service requests 
should be submitted by entering the information listed below on the 
Transmission Provider's OASIS. Prior to implementation of the 
Transmission Provider's OASIS, a Completed Application may be submitted 
by (i) transmitting the required information to the Transmission 
Provider by telefax, or (ii) providing the information by telephone 
over the Transmission Provider's time recorded telephone line. Each of 
these methods will provide a time-stamped record for establishing the 
priority of the Application.
17.2 Completed Application
    A Completed Application shall provide all of the information 
included in 18 CFR 2.20 including but not limited to the following:
    (i) The identity, address, telephone number and facsimile number of 
the entity requesting service;
    (ii) A statement that the entity requesting service is, or will be 
upon commencement of service, an Eligible Customer under the Tariff;
    (iii) The location of the Point(s) of Receipt and Point(s) of 
Delivery and the identities of the Delivering Parties and the Receiving 
Parties;
    (iv) The location of the generating facility(ies) supplying the 
capacity and energy and the location of the load ultimately served by 
the capacity and energy transmitted. The Transmission Provider will 
treat this information as confidential except to the extent that 
disclosure of this information is required by this Tariff, by 
regulatory or judicial order, for reliability purposes pursuant to Good 
Utility Practice or pursuant to RTG transmission information sharing 
agreements. The Transmission Provider shall treat this information 
consistent with the standards of conduct contained in Part 37 of the 
Commission's regulations;
    (v) A description of the supply characteristics of the capacity and 
energy to be delivered;
    (vi) An estimate of the capacity and energy expected to be 
delivered to the Receiving Party;
    (vii) The Service Commencement Date and the term of the requested 
Transmission Service;
    (viii) The transmission capacity requested for each Point of 
Receipt and each Point of Delivery on the Transmission Provider's 
Transmission System; customers may combine their requests for service 
in order to satisfy the minimum transmission capacity requirement;
    (ix) A statement indicating whether the Transmission Customer 
commits to a Pre-Confirmed Request, i.e., will execute a Service 
Agreement upon receipt of notification that the Transmission Provider 
can provide the requested Transmission Service; and
    (x) Any additional information required by the Transmission 
Provider's planning process established in Attachment K.
    The Transmission Provider shall treat this information consistent 
with the standards of conduct contained in Part 37 of the Commission's 
regulations.
17.3 Deposit
    A Completed Application for Firm Point-To-Point Transmission 
Service also shall include a deposit of either one month's charge for 
Reserved Capacity or the full charge for Reserved Capacity for service 
requests of less than one month. If the Application is rejected by the 
Transmission Provider because it does not meet the conditions for 
service as set forth herein, or in the case of requests for service 
arising in connection with losing bidders in a Request For Proposals 
(RFP), said deposit shall be returned with interest less any reasonable 
costs incurred by the Transmission Provider in connection with the 
review of the losing bidder's Application. The deposit also will be 
returned with interest less any reasonable costs incurred by the 
Transmission Provider if the Transmission Provider is unable to 
complete new facilities needed to provide the service. If an 
Application is withdrawn or the Eligible Customer decides not to enter 
into a Service Agreement for Firm Point-To-Point Transmission Service, 
the deposit shall be refunded in full, with interest, less reasonable 
costs incurred by the Transmission Provider to the extent such costs 
have not already been recovered by the Transmission Provider from the 
Eligible Customer. The Transmission Provider will provide to the 
Eligible Customer a complete accounting of all costs deducted from the 
refunded deposit, which the Eligible Customer may contest if there is a 
dispute concerning the deducted costs. Deposits associated with 
construction of new facilities are subject to the provisions of Section 
19. If a Service Agreement for Firm Point-To-Point Transmission Service 
is executed, the deposit, with interest, will be returned to the 
Transmission Customer upon expiration or termination of the Service 
Agreement for Firm Point-To-Point Transmission Service. Applicable 
interest shall be computed in accordance with the Commission's 
regulations at 18 CFR ? 35.19a(a)(2)(iii), and shall be calculated from 
the day the deposit check is credited to the Transmission Provider's 
account.
17.4 Notice of Deficient Application
    If an Application fails to meet the requirements of the Tariff, the 
Transmission Provider shall notify the entity requesting service within 
fifteen (15) days of receipt of the reasons for such failure. The 
Transmission Provider will attempt to remedy minor deficiencies in the 
Application through informal communications with the Eligible Customer. 
If such efforts are unsuccessful, the Transmission Provider shall 
return the Application, along with any deposit, with interest. Upon 
receipt of a new or revised Application that fully complies with the 
requirements of Part II of the Tariff, the Eligible Customer shall be 
assigned a new priority consistent with the date of the new or revised 
Application.
17.5 Response to a Completed Application
    Following receipt of a Completed Application for Firm Point-To-
Point Transmission Service, the Transmission Provider shall make a 
determination of available transmission capability as required in 
Section 15.2. The Transmission Provider shall notify the Eligible 
Customer as soon as practicable, but not later than thirty (30) days 
after the date of receipt of a Completed Application either (i) if it 
will be able to provide service without performing a System Impact 
Study or (ii) if such a study is needed to evaluate the impact of the 
Application pursuant to Section 19.1. Responses by the Transmission

[[Page 32730]]

Provider must be made as soon as practicable to all completed 
applications (including applications by its own merchant function) and 
the timing of such responses must be made on a non-discriminatory 
basis.
17.6 Execution of Service Agreement
    Whenever the Transmission Provider determines that a System Impact 
Study is not required and that the service can be provided, it shall 
notify the Eligible Customer as soon as practicable but no later than 
thirty (30) days after receipt of the Completed Application. Where a 
System Impact Study is required, the provisions of Section 19 will 
govern the execution of a Service Agreement. Failure of an Eligible 
Customer to execute and return the Service Agreement or request the 
filing of an unexecuted service agreement pursuant to Section 15.3, 
within fifteen (15) days after it is tendered by the Transmission 
Provider will be deemed a withdrawal and termination of the Application 
and any deposit submitted shall be refunded with interest. Nothing 
herein limits the right of an Eligible Customer to file another 
Application after such withdrawal and termination.
17.7 Extensions for Commencement of Service
    The Transmission Customer can obtain up to five (5) one-year 
extensions for the commencement of service. The Transmission Customer 
may postpone service by paying a non-refundable annual reservation fee 
equal to one-month's charge for Firm Transmission Service for each year 
or fraction thereof. If during any extension for the commencement of 
service an Eligible Customer submits a Completed Application for Firm 
Transmission Service, and such request can be satisfied only by 
releasing all or part of the Transmission Customer's Reserved Capacity, 
the original Reserved Capacity will be released unless the following 
condition is satisfied. Within thirty (30) days, the original 
Transmission Customer agrees to pay the Firm Point-To-Point 
transmission rate for its Reserved Capacity concurrent with the new 
Service Commencement Date. In the event the Transmission Customer 
elects to release the Reserved Capacity, the reservation fees or 
portions thereof previously paid will be forfeited.

18 Procedures for Arranging Non-Firm Point-To-Point Transmission Service

18.1 Application
    Eligible Customers seeking Non-Firm Point-To-Point Transmission 
Service must submit a Completed Application to the Transmission 
Provider. Applications should be submitted by entering the information 
listed below on the Transmission Provider's OASIS. Prior to 
implementation of the Transmission Provider's OASIS, a Completed 
Application may be submitted by (i) transmitting the required 
information to the Transmission Provider by telefax, or (ii) providing 
the information by telephone over the Transmission Provider's time 
recorded telephone line. Each of these methods will provide a time-
stamped record for establishing the service priority of the Application.
18.2 Completed Application
    A Completed Application shall provide all of the information 
included in 18 CFR 2.20 including but not limited to the following:
    (i) The identity, address, telephone number and facsimile number of 
the entity requesting service;
    (ii) A statement that the entity requesting service is, or will be 
upon commencement of service, an Eligible Customer under the Tariff;
    (iii) The Point(s) of Receipt and the Point(s) of Delivery;
    (iv) The maximum amount of capacity requested at each Point of 
Receipt and Point of Delivery; and
    (v) The proposed dates and hours for initiating and terminating 
transmission service hereunder.
    In addition to the information specified above, when required to 
properly evaluate system conditions, the Transmission Provider also may 
ask the Transmission Customer to provide the following:
    (vi) The electrical location of the initial source of the power to 
be transmitted pursuant to the Transmission Customer's request for 
service; and
    (vii) The electrical location of the ultimate load.
    The Transmission Provider will treat this information in (vi) and 
(vii) as confidential at the request of the Transmission Customer 
except to the extent that disclosure of this information is required by 
this Tariff, by regulatory or judicial order, for reliability purposes 
pursuant to Good Utility Practice, or pursuant to RTG transmission 
information sharing agreements. The Transmission Provider shall treat 
this information consistent with the standards of conduct contained in 
Part 37 of the Commission's regulations.
    (viii) A statement indicating whether the Transmission Customer 
commits to a Pre-Confirmed Request, i.e., will execute a Service 
Agreement upon receipt of notification that the Transmission Provider 
can provide the requested Transmission Service.
18.3 Reservation of Non-Firm Point-To-Point Transmission Service
    Requests for monthly service shall be submitted no earlier than 
sixty (60) days before service is to commence; requests for weekly 
service shall be submitted no earlier than fourteen (14) days before 
service is to commence, requests for daily service shall be submitted 
no earlier than two (2) days before service is to commence, and 
requests for hourly service shall be submitted no earlier than noon the 
day before service is to commence. Requests for service received later 
than 2:00 p.m. prior to the day service is scheduled to commence will 
be accommodated if practicable [or such reasonable times that are 
generally accepted in the region and are consistently adhered to by the 
Transmission Provider].
18.4 Determination of Available Transfer Capability
    Following receipt of a tendered schedule the Transmission Provider 
will make a determination on a non-discriminatory basis of available 
transfer capability pursuant to Section 15.2. Such determination shall 
be made as soon as reasonably practicable after receipt, but not later 
than the following time periods for the following terms of service (i) 
thirty (30) minutes for hourly service, (ii) thirty (30) minutes for 
daily service, (iii) four (4) hours for weekly service, and (iv) two 
(2) days for monthly service. [Or such reasonable times that are 
generally accepted in the region and are consistently adhered to by the 
Transmission Provider].

19 Additional Study Procedures for Firm Point-To-Point Transmission 
Service Requests

19.1 Notice of Need for System Impact Study
    After receiving a request for service, the Transmission Provider 
shall determine on a non-discriminatory basis whether a System Impact 
Study is needed. A description of the Transmission Provider's 
methodology for completing a System Impact Study is provided in 
Attachment D. If the Transmission Provider determines that a System 
Impact Study is necessary to accommodate the requested service, it 
shall so inform the Eligible Customer, as soon as practicable. In such 
cases, the Transmission Provider shall within thirty (30) days of 
receipt of a Completed Application, tender a System Impact Study 
Agreement pursuant to

[[Page 32731]]

which the Eligible Customer shall agree to reimburse the Transmission 
Provider for performing the required System Impact Study. For a service 
request to remain a Completed Application, the Eligible Customer shall 
execute the System Impact Study Agreement and return it to the 
Transmission Provider within fifteen (15) days. If the Eligible 
Customer elects not to execute the System Impact Study Agreement, its 
application shall be deemed withdrawn and its deposit, pursuant to 
Section 17.3, shall be returned with interest.
19.2 System Impact Study Agreement and Cost Reimbursement
    (i) The System Impact Study Agreement will clearly specify the 
Transmission Provider's estimate of the actual cost, and time for 
completion of the System Impact Study. The charge shall not exceed the 
actual cost of the study. In performing the System Impact Study, the 
Transmission Provider shall rely, to the extent reasonably practicable, 
on existing transmission planning studies. The Eligible Customer will 
not be assessed a charge for such existing studies; however, the 
Eligible Customer will be responsible for charges associated with any 
modifications to existing planning studies that are reasonably 
necessary to evaluate the impact of the Eligible Customer's request for 
service on the Transmission System.
    (ii) If in response to multiple Eligible Customers requesting 
service in relation to the same competitive solicitation, a single 
System Impact Study is sufficient for the Transmission Provider to 
accommodate the requests for service, the costs of that study shall be 
pro-rated among the Eligible Customers.
    (iii) For System Impact Studies that the Transmission Provider 
conducts on its own behalf, the Transmission Provider shall record the 
cost of the System Impact Studies pursuant to Section 20.
19.3 System Impact Study Procedures
    Upon receipt of an executed System Impact Study Agreement, the 
Transmission Provider will use due diligence to complete the required 
System Impact Study within a sixty (60) day period. The System Impact 
Study shall identify any system constraints and redispatch options, 
including an estimate of the number of hours of redispatch that may be 
required to accommodate the request for Transmission Service and a 
preliminary estimate of the cost of redispatch, additional Direct 
Assignment Facilities or Network Upgrades required to provide the 
requested service. In the event that the Transmission Provider is 
unable to complete the required System Impact Study within such time 
period, it shall so notify the Eligible Customer and provide an 
estimated completion date along with an explanation of the reasons why 
additional time is required to complete the required studies. A copy of 
the completed System Impact Study and related work papers shall be made 
available to the Eligible Customer. The Transmission Provider will use 
the same due diligence in completing the System Impact Study for an 
Eligible Customer as it uses when completing studies for itself. The 
Transmission Provider shall notify the Eligible Customer immediately 
upon completion of the System Impact Study if the Transmission System 
will be adequate to accommodate all or part of a request for service or 
that no costs are likely to be incurred for new transmission facilities 
or upgrades. In order for a request to remain a Completed Application, 
within fifteen (15) days of completion of the System Impact Study the 
Eligible Customer must execute a Service Agreement or request the 
filing of an unexecuted Service Agreement pursuant to Section 15.3, or 
the Application shall be deemed terminated and withdrawn.
19.4 Facilities Study Procedures
    If a System Impact Study indicates that additions or upgrades to 
the Transmission System are needed to supply the Eligible Customer's 
service request, the Transmission Provider, within thirty (30) days of 
the completion of the System Impact Study, shall tender to the Eligible 
Customer a Facilities Study Agreement pursuant to which the Eligible 
Customer shall agree to reimburse the Transmission Provider for 
performing the required Facilities Study. For a service request to 
remain a Completed Application, the Eligible Customer shall execute the 
Facilities Study Agreement and return it to the Transmission Provider 
within fifteen (15) days. If the Eligible Customer elects not to 
execute the Facilities Study Agreement, its application shall be deemed 
withdrawn and its deposit, pursuant to Section 17.3, shall be returned 
with interest. Upon receipt of an executed Facilities Study Agreement, 
the Transmission Provider will use due diligence to complete the 
required Facilities Study within a sixty (60) day period. If the 
Transmission Provider is unable to complete the Facilities Study in the 
allotted time period, the Transmission Provider shall notify the 
Transmission Customer and provide an estimate of the time needed to 
reach a final determination along with an explanation of the reasons 
that additional time is required to complete the study. When completed, 
the Facilities Study will include a good faith estimate of (i) the cost 
of Direct Assignment Facilities to be charged to the Transmission 
Customer, (ii) the Transmission Customer's appropriate share of the 
cost of any required Network Upgrades as determined pursuant to the 
provisions of Part II of the Tariff, and (iii) the time required to 
complete such construction and initiate the requested service. The 
Transmission Customer shall provide the Transmission Provider with a 
letter of credit or other reasonable form of security acceptable to the 
Transmission Provider equivalent to the costs of new facilities or 
upgrades consistent with commercial practices as established by the 
Uniform Commercial Code. The Transmission Customer shall have thirty 
(30) days to execute a Service Agreement or request the filing of an 
unexecuted Service Agreement and provide the required letter of credit 
or other form of security or the request will no longer be a Completed 
Application and shall be deemed terminated and withdrawn.
19.5 Facilities Study Modifications
    Any change in design arising from inability to site or construct 
facilities as proposed will require development of a revised good faith 
estimate. New good faith estimates also will be required in the event 
of new statutory or regulatory requirements that are effective before 
the completion of construction or other circumstances beyond the 
control of the Transmission Provider that significantly affect the 
final cost of new facilities or upgrades to be charged to the 
Transmission Customer pursuant to the provisions of Part II of the Tariff.
19.6 Due Diligence in Completing New Facilities
    The Transmission Provider shall use due diligence to add necessary 
facilities or upgrade its Transmission System within a reasonable time. 
The Transmission Provider will not upgrade its existing or planned 
Transmission System in order to provide the requested Firm Point-To-
Point Transmission Service if doing so would impair system reliability 
or otherwise impair or degrade existing firm service.
19.7 Partial Interim Service
    If the Transmission Provider determines that it will not have 
adequate transfer capability to satisfy the full amount of a Completed 
Application for Firm Point-To-Point Transmission Service, the Transmission

[[Page 32732]]

Provider nonetheless shall be obligated to offer and provide the 
portion of the requested Firm Point-To-Point Transmission Service that 
can be accommodated without addition of any facilities and through 
redispatch. However, the Transmission Provider shall not be obligated 
to provide the incremental amount of requested Firm Point-To-Point 
Transmission Service that requires the addition of facilities or 
upgrades to the Transmission System until such facilities or upgrades 
have been placed in service.
19.8 Expedited Procedures for New Facilities
    In lieu of the procedures set forth above, the Eligible Customer 
shall have the option to expedite the process by requesting the 
Transmission Provider to tender at one time, together with the results 
of required studies, an ``Expedited Service Agreement'' pursuant to 
which the Eligible Customer would agree to compensate the Transmission 
Provider for all costs incurred pursuant to the terms of the Tariff. In 
order to exercise this option, the Eligible Customer shall request in 
writing an expedited Service Agreement covering all of the above-
specified items within thirty (30) days of receiving the results of the 
System Impact Study identifying needed facility additions or upgrades 
or costs incurred in providing the requested service. While the 
Transmission Provider agrees to provide the Eligible Customer with its 
best estimate of the new facility costs and other charges that may be 
incurred, such estimate shall not be binding and the Eligible Customer 
must agree in writing to compensate the Transmission Provider for all 
costs incurred pursuant to the provisions of the Tariff. The Eligible 
Customer shall execute and return such an Expedited Service Agreement 
within fifteen (15) days of its receipt or the Eligible Customer's 
request for service will cease to be a Completed Application and will 
be deemed terminated and withdrawn.
19.9 Penalties for Failure To Meet Study Deadlines
    Sections 19.3 and 19.4 require a Transmission Provider to use due 
diligence to meet 60-day study completion deadlines for System Impact 
Studies and Facilities Studies.
    (i) The Transmission Provider is required to file a notice with the 
Commission in the event that more than twenty (20) percent of non-
Affiliates' System Impact Studies and Facilities Studies completed by 
the Transmission Provider in any two consecutive calendar quarters are 
not completed within the 60-day study completion deadlines. Such notice 
must be filed within thirty (30) days of the end of the calendar 
quarter triggering the notice requirement.
    (ii) For the purposes of calculating the percent of non-Affiliates' 
System Impact Studies and Facilities Studies processed outside of the 
60-day study completion deadlines, the Transmission Provider shall 
consider all System Impact Studies and Facilities Studies that it 
completes for non-Affiliates during the calendar quarter. The 
percentage should be calculated by dividing the number of those studies 
which are completed on time by the total number of completed studies. 
The Transmission Provider may provide an explanation in its 
notification filing to the Commission if it believes there are 
extenuating circumstances that prevented it from meeting the 60-day 
study completion deadlines.
    (iii) The Transmission Provider is subject to an operational 
penalty if it completes ten (10) percent or more of non-Affiliates' 
System Impact Studies and Facilities Studies outside of the 60-day 
study completion deadlines for each of the two calendar quarters 
immediately following the quarter that triggered its notification 
filing to the Commission. The operational penalty will be assessed for 
each calendar quarter for which an operational penalty applies, 
starting with the calendar quarter immediately following the quarter 
that triggered the Transmission Provider's notification filing to the 
Commission. The operational penalty will continue to be assessed each 
quarter until the Transmission Provider completes at least ninety (90) 
percent of all non-Affiliates' System Impact Studies and Facilities 
Studies within the 60-day deadline.
    (iv) For penalties assessed in accordance with subsection (iii) 
above, the penalty amount for each System Impact Study or Facilities 
Study shall be equal to $500 for each day the Transmission Provider 
takes to complete that study beyond the 60-day deadline.

20 Procedures if the Transmission Provider Is Unable To Complete New 
Transmission Facilities for Firm Point-To-Point Transmission Service

20.1 Delays in Construction of New Facilities
    If any event occurs that will materially affect the time for 
completion of new facilities, or the ability to complete them, the 
Transmission Provider shall promptly notify the Transmission Customer. 
In such circumstances, the Transmission Provider shall within thirty 
(30) days of notifying the Transmission Customer of such delays, 
convene a technical meeting with the Transmission Customer to evaluate 
the alternatives available to the Transmission Customer. The 
Transmission Provider also shall make available to the Transmission 
Customer studies and work papers related to the delay, including all 
information that is in the possession of the Transmission Provider that 
is reasonably needed by the Transmission Customer to evaluate any 
alternatives.
20.2 Alternatives to the Original Facility Additions
    When the review process of Section 20.1 determines that one or more 
alternatives exist to the originally planned construction project, the 
Transmission Provider shall present such alternatives for consideration 
by the Transmission Customer. If, upon review of any alternatives, the 
Transmission Customer desires to maintain its Completed Application 
subject to construction of the alternative facilities, it may request 
the Transmission Provider to submit a revised Service Agreement for 
Firm Point-To-Point Transmission Service. If the alternative approach 
solely involves Non-Firm Point-To-Point Transmission Service, the 
Transmission Provider shall promptly tender a Service Agreement for 
Non-Firm Point-To-Point Transmission Service providing for the service. 
In the event the Transmission Provider concludes that no reasonable 
alternative exists and the Transmission Customer disagrees, the 
Transmission Customer may seek relief under the dispute resolution 
procedures pursuant to Section 12 or it may refer the dispute to the 
Commission for resolution.
20.3 Refund Obligation for Unfinished Facility Additions
    If the Transmission Provider and the Transmission Customer mutually 
agree that no other reasonable alternatives exist and the requested 
service cannot be provided out of existing capability under the 
conditions of Part II of the Tariff, the obligation to provide the 
requested Firm Point-To-Point Transmission Service shall terminate and 
any deposit made by the Transmission Customer shall be returned with 
interest pursuant to Commission regulations 35.19a(a)(2)(iii). However, 
the Transmission Customer shall be responsible for all prudently 
incurred costs by the Transmission Provider through the time 
construction was suspended.

[[Page 32733]]

21 Provisions Relating to Transmission Construction and Services on the 
Systems of Other Utilities

21.1 Responsibility for Third-Party System Additions
    The Transmission Provider shall not be responsible for making 
arrangements for any necessary engineering, permitting, and 
construction of transmission or distribution facilities on the 
system(s) of any other entity or for obtaining any regulatory approval 
for such facilities. The Transmission Provider will undertake 
reasonable efforts to assist the Transmission Customer in obtaining 
such arrangements, including without limitation, providing any 
information or data required by such other electric system pursuant to 
Good Utility Practice.
21.2 Coordination of Third-Party System Additions
    In circumstances where the need for transmission facilities or 
upgrades is identified pursuant to the provisions of Part II of the 
Tariff, and if such upgrades further require the addition of 
transmission facilities on other systems, the Transmission Provider 
shall have the right to coordinate construction on its own system with 
the construction required by others. The Transmission Provider, after 
consultation with the Transmission Customer and representatives of such 
other systems, may defer construction of its new transmission 
facilities, if the new transmission facilities on another system cannot 
be completed in a timely manner. The Transmission Provider shall notify 
the Transmission Customer in writing of the basis for any decision to 
defer construction and the specific problems which must be resolved 
before it will initiate or resume construction of new facilities. 
Within sixty (60) days of receiving written notification by the 
Transmission Provider of its intent to defer construction pursuant to 
this section, the Transmission Customer may challenge the decision in 
accordance with the dispute resolution procedures pursuant to Section 
12 or it may refer the dispute to the Commission for resolution.

22 Changes in Service Specifications

22.1 Modifications on a Non-Firm Basis
    The Transmission Customer taking Firm Point-To-Point Transmission 
Service may request the Transmission Provider to provide transmission 
service on a non-firm basis over Receipt and Delivery Points other than 
those specified in the Service Agreement (``Secondary Receipt and 
Delivery Points''), in amounts not to exceed its firm capacity 
reservation, without incurring an additional Non-Firm Point-To-Point 
Transmission Service charge or executing a new Service Agreement, 
subject to the following conditions.
    (a) Service provided over Secondary Receipt and Delivery Points 
will be non-firm only, on an as-available basis and will not displace 
any firm or non-firm service reserved or scheduled by third-parties 
under the Tariff or by the Transmission Provider on behalf of its 
Native Load Customers.
    (b) The sum of all Firm and non-firm Point-To-Point Transmission 
Service provided to the Transmission Customer at any time pursuant to 
this section shall not exceed the Reserved Capacity in the relevant 
Service Agreement under which such services are provided.
    (c) The Transmission Customer shall retain its right to schedule 
Firm Point-To-Point Transmission Service at the Receipt and Delivery 
Points specified in the relevant Service Agreement in the amount of its 
original capacity reservation.
    (d) Service over Secondary Receipt and Delivery Points on a non-
firm basis shall not require the filing of an Application for Non-Firm 
Point-To-Point Transmission Service under the Tariff. However, all 
other requirements of Part II of the Tariff (except as to transmission 
rates) shall apply to transmission service on a non-firm basis over 
Secondary Receipt and Delivery Points.
22.2 Modification on a Firm Basis
    Any request by a Transmission Customer to modify Receipt and 
Delivery Points on a firm basis shall be treated as a new request for 
service in accordance with Section 17 hereof, except that such 
Transmission Customer shall not be obligated to pay any additional 
deposit if the capacity reservation does not exceed the amount reserved 
in the existing Service Agreement. While such new request is pending, 
the Transmission Customer shall retain its priority for service at the 
existing firm Receipt and Delivery Points specified in its Service 
Agreement.

23 Sale or Assignment of Transmission Service

23.1 Procedures for Assignment or Transfer of Service
    Subject to Commission approval of any necessary filings, a 
Transmission Customer may sell, assign, or transfer all or a portion of 
its rights under its Service Agreement, but only to another Eligible 
Customer (the Assignee). The Transmission Customer that sells, assigns 
or transfers its rights under its Service Agreement is hereafter 
referred to as the Reseller. Compensation to Resellers that are 
Affiliates of the Transmission Provider shall not exceed the higher of 
(i) the original rate paid by the Reseller, (ii) the Transmission 
Provider's maximum rate on file at the time of the assignment, or (iii) 
the Reseller's opportunity cost capped at the Transmission Provider's 
cost of expansion. Compensation to Resellers that are not Affiliates of 
the Transmission Provider shall be at rates established by agreement 
with the Assignee. If the Assignee does not request any change in the 
Point(s) of Receipt or the Point(s) of Delivery, or a change in any 
other term or condition set forth in the original Service Agreement, 
the Assignee will receive the same services as did the Reseller and the 
priority of service for the Assignee will be the same as that of the 
Reseller. A Reseller should notify the Transmission Provider as soon as 
possible after any assignment or transfer of service occurs but in any 
event, notification must be provided prior to any provision of service 
to the Assignee. The Assignee will be subject to all terms and 
conditions of this Tariff. If the Assignee requests a change in 
service, the reservation priority of service will be determined by the 
Transmission Provider pursuant to Section 13.2.
23.2 Limitations on Assignment or Transfer of Service
    If the Assignee requests a change in the Point(s) of Receipt or 
Point(s) of Delivery, or a change in any other specifications set forth 
in the original Service Agreement, the Transmission Provider will 
consent to such change subject to the provisions of the Tariff, 
provided that the change will not impair the operation and reliability 
of the Transmission Provider's generation, transmission, or 
distribution systems. The Assignee shall compensate the Transmission 
Provider for performing any System Impact Study needed to evaluate the 
capability of the Transmission System to accommodate the proposed 
change and any additional costs resulting from such change. The 
Reseller shall remain liable for the performance of all obligations 
under the Service Agreement, except as specifically agreed to by the 
Parties through an amendment to the Service Agreement.

[[Page 32734]]

23.3 Information on Assignment or Transfer of Service
    In accordance with Section 4, Resellers may use the Transmission 
Provider's OASIS to post transmission capacity available for resale.

24 Metering and Power Factor Correction at Receipt and Delivery Points(s)

24.1 Transmission Customer Obligations
    Unless otherwise agreed, the Transmission Customer shall be 
responsible for installing and maintaining compatible metering and 
communications equipment to accurately account for the capacity and 
energy being transmitted under Part II of the Tariff and to communicate 
the information to the Transmission Provider. Such equipment shall 
remain the property of the Transmission Customer.
24.2 Transmission Provider Access to Metering Data
    The Transmission Provider shall have access to metering data, which 
may reasonably be required to facilitate measurements and billing under 
the Service Agreement.
24.3 Power Factor
    Unless otherwise agreed, the Transmission Customer is required to 
maintain a power factor within the same range as the Transmission 
Provider pursuant to Good Utility Practices. The power factor 
requirements are specified in the Service Agreement where applicable.

25 Compensation for Transmission Service

    Rates for Firm and Non-Firm Point-To-Point Transmission Service are 
provided in the Schedules appended to the Tariff: Firm Point-To-Point 
Transmission Service (Schedule 7); and Non-Firm Point-To-Point 
Transmission Service (Schedule 8). The Transmission Provider shall use 
Part II of the Tariff to make its Third-Party Sales. The Transmission 
Provider shall account for such use at the applicable Tariff rates, 
pursuant to Section 8.

26 Stranded Cost Recovery

    The Transmission Provider may seek to recover stranded costs from 
the Transmission Customer pursuant to this Tariff in accordance with 
the terms, conditions and procedures set forth in FERC Order No. 888. 
However, the Transmission Provider must separately file any specific 
proposed stranded cost charge under Section 205 of the Federal Power Act.

27 Compensation for New Facilities and Redispatch Costs

    Whenever a System Impact Study performed by the Transmission 
Provider in connection with the provision of Firm Point-To-Point 
Transmission Service identifies the need for new facilities, the 
Transmission Customer shall be responsible for such costs to the extent 
consistent with Commission policy. Whenever a System Impact Study 
performed by the Transmission Provider identifies capacity constraints 
that may be relieved more economically by redispatching the 
Transmission Provider's resources than by building new facilities or 
upgrading existing facilities to eliminate such constraints, the 
Transmission Customer shall be responsible for the redispatch costs to 
the extent consistent with Commission policy.

III. Network Integration Transmission Service

Preamble

    The Transmission Provider will provide Network Integration 
Transmission Service pursuant to the applicable terms and conditions 
contained in the Tariff and Service Agreement. Network Integration 
Transmission Service allows the Network Customer to integrate, 
economically dispatch and regulate its current and planned Network 
Resources to serve its Network Load in a manner comparable to that in 
which the Transmission Provider utilizes its Transmission System to 
serve its Native Load Customers. Network Integration Transmission 
Service also may be used by the Network Customer to deliver economy 
energy purchases to its Network Load from non-designated resources on 
an as-available basis without additional charge. Transmission service 
for sales to non-designated loads will be provided pursuant to the 
applicable terms and conditions of Part II of the Tariff.

28 Nature of Network Integration Transmission Service

28.1 Scope of Service
    Network Integration Transmission Service is a transmission service 
that allows Network Customers to efficiently and economically utilize 
their Network Resources (as well as other non-designated generation 
resources) to serve their Network Load located in the Transmission 
Provider's Control Area and any additional load that may be designated 
pursuant to Section 31.3 of the Tariff. The Network Customer taking 
Network Integration Transmission Service must obtain or provide 
Ancillary Services pursuant to Section 3.
28.2 Transmission Provider Responsibilities
    The Transmission Provider will plan, construct, operate and 
maintain its Transmission System in accordance with Good Utility 
Practice and its planning obligations in Attachment K in order to 
provide the Network Customer with Network Integration Transmission 
Service over the Transmission Provider's Transmission System. The 
Transmission Provider, on behalf of its Native Load Customers, shall be 
required to designate resources and loads in the same manner as any 
Network Customer under Part III of this Tariff. This information must 
be consistent with the information used by the Transmission Provider to 
calculate available transfer capability. The Transmission Provider 
shall include the Network Customer's Network Load in its Transmission 
System planning and shall, consistent with Good Utility Practice and 
Attachment K, endeavor to construct and place into service sufficient 
transfer capability to deliver the Network Customer's Network Resources 
to serve its Network Load on a basis comparable to the Transmission 
Provider's delivery of its own generating and purchased resources to 
its Native Load Customers.
28.3 Network Integration Transmission Service
    The Transmission Provider will provide firm transmission service 
over its Transmission System to the Network Customer for the delivery 
of capacity and energy from its designated Network Resources to service 
its Network Loads on a basis that is comparable to the Transmission 
Provider's use of the Transmission System to reliably serve its Native 
Load Customers.
28.4 Secondary Service
    The Network Customer may use the Transmission Provider's 
Transmission System to deliver Economy Energy to its Network Loads from 
resources that have not been designated as Network Resources. Such 
energy shall be transmitted, on an as-available basis, at no additional 
charge. Secondary Service shall not require the filing of an 
Application for Network Integration Transmission Service under the 
Tariff. However, all other requirements of Part III of the Tariff 
(except for transmission rates) shall apply to Secondary Service. 
Deliveries from resources other than

[[Continued on page 32735]] 

 
 


Local Navigation


Jump to main content.