U.S. Army Corps of Engineers, Philadelphia District; Crown Landing, LLC; Texas Eastern Transmission, L.P.; Notice of Availability of the Final Environmental Impact Statement for the Proposed Crown Landing LNG and Logan Lateral Projects
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
[Federal Register: May 5, 2006 (Volume 71, Number 87)]
[Notices]
[Page 26490-26491]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr05my06-57]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP04-411-000, COE Application #CENAP-OP-R-200500146; Docket No.
CP04-416-000, COE Application #CENAP-OP-R-200500145 and 200500146]
U.S. Army Corps of Engineers, Philadelphia District; Crown
Landing, LLC; Texas Eastern Transmission, L.P.; Notice of Availability
of the Final Environmental Impact Statement for the Proposed Crown
Landing LNG and Logan Lateral Projects
April 28, 2006.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) in cooperation with the U.S. Army Corps of Engineers (COE),
U.S. Coast Guard, U.S. Environmental Protection Agency (EPA), and
National Oceanic and Atmospheric Administration Fisheries has prepared
a final Environmental Impact Statement (EIS) for a liquefied natural
gas (LNG) import terminal (referred to as the Crown Landing LNG
Project) proposed by Crown Landing, LLC (Crown Landing), a BP Energy
Company (BP) affiliate, and natural gas pipeline facilities (referred
to as the Logan Lateral Project) proposed by Texas Eastern
Transmission, L.P. (Texas Eastern) in the above-referenced dockets.
The final EIS was prepared to satisfy the requirements of the
National Environmental Policy Act (NEPA). The staff concludes that
approval of the proposed projects with appropriate mitigating measures
as recommended, would have limited adverse environmental impact. The
final EIS also evaluates alternatives to the proposal, including system
alternatives, alternative sites for the LNG import terminal, and
pipeline alternatives.
The proposed LNG terminal would be located on the shoreline of the
Delaware River in Logan Township, Gloucester County, New Jersey, and
would consist of facilities capable of unloading LNG ships, storing up
to 450,000 cubic meters (m3\3\) of LNG (9.2 billion cubic feet of
natural gas equivalent), vaporizing the LNG, and sending out natural
gas at a baseload rate of 1.2 billion cubic feet per day (Bcfd) and a
maximum rate of 1.4 Bcfd (using spare equipment). Crown Landing
proposes to interconnect the LNG facilities onsite with three
pipelines. One interconnect would be with the new pipeline that Texas
Eastern proposes to construct and operate (i.e., Logan Lateral) between
its existing Chester Junction facility in Brookhaven Borough,
Pennsylvania and the proposed LNG terminal. The other two interconnects
would be with existing pipelines that currently cross the LNG terminal
site. One of these pipelines is owned and operated by Columbia Gas
Transmission Company (Columbia Gas). The other pipeline is owned and
operated by Transcontinental Gas Pipe Line Corporation (Transco). To
date, neither Columbia Gas nor Transco have filed applications with the
FERC to construct and operate the interconnects. The Crown Landing LNG
Project would have a maximum delivery capacity of 0.5 Bcfd to the
Columbia Gas pipeline system, 0.6 Bcfd to the Transco pipeline system,
and 0.9 Bcfd to the Texas Eastern pipeline system.
The proposed preferred project construction site, referenced above,
is approximately 175 acres in size (waterward of the low water line on
the Delaware River). Within the site there are uplands, wetlands
(federally regulated), and intertidal river shoreline (also federally
regulated). Construction of the proposed LNG terminal would involve the
dredging of shallow water riverbottom and the filling of a small area
of intertidal river shoreline for the installation of berthing
structures in the Delaware River. No permanent filling of federally
regulated wetlands is proposed for construction of the terminal
facilities. The proposed pipeline connection would involve the
installation of about 11.00 miles of new underground pipeline from the
storage and transfer facility in Gloucester County, New Jersey,
crossing Birch Creek, Raccoon Creek, Delaware River, Chester Creek, and
several smaller waterways on both sides of the Delaware River, to an
existing pipeline junction facility in Pennsylvania.
The Birch Creek, Raccoon Creek, Delaware River, and Chester Creek
crossings would all be accomplished by Horizontal Directional Drilling
(HDD) method. All smaller waterway crossings would be accomplished by
open-cut trenching. The rigging for the HDD crossing of the Delaware
River would be set-up on the Pennsylvania bank of the river in Chester.
The pipeline would be ``pulled under'' the river from the old Ferry
Road roadbed on the New Jersey side.
The following modifications to the project have been proposed since
the draft EIS was issued:
(1) Texas Eastern now proposes a contingency plan for constructing
the Chester Creek crossing by open-cut method if the HDD method fails.
(2) Crown Landing has submitted a minor modification to the
proposed design of the LNG terminal berthing configuration in order to
provide for an enhanced margin of safety in LNG carrier maneuvering.
The modified proposed design is evaluated in the final EIS. In
addition, Crown Landing has re-calculated the volume of material that
would result from the dredging for the proposed LNG terminal berthing
provisions in order to correct an error identified in the original
calculations and to provide for a customary 2 foot ``over-dredge''
volume. There is no change in the proposed dredging depth or dredged
material disposal.
The draft EIS document indicated that 800,000 cubic yards of
material would be dredged in the construction of the proposed LNG
berthing terminal. Crown Landing now calculates that 1.24 million cubic
yards of material would be dredged: 60,000 cubic yards are added to the
original total from the safety modifications; 110,000 cubic yards are
added by the over-dredge allowance; and 270,000 cubic yards are added
from the error correction.
[[Page 26491]]
The final EIS addresses the potential environmental effects of the
construction and operation of the following LNG and natural gas
pipeline facilities:
? A ship unloading facility capable of receiving LNG ships
with capacities up to 200,000 m3;
? Three 150,000 m\3\ (net capacity) full-containment LNG
storage tanks, comprised of 9 percent nickel steel inner tank, pre-
stressed concrete outer tank, and a concrete roof;
? A closed-loop shell and tube heat exchanger vaporization system;
? Various ancillary facilities, including administrative
offices, warehouse/maintenance building, main control center,
guardhouse, and a pier control room;
? Three meter and regulation stations located on the
proposed LNG terminal site; and
? Approximately 11.00 miles of 30-inch-diameter natural gas
pipeline (4.92 miles in Pennsylvania and 6.08 miles in New Jersey), a
pig launcher and receiver facility at the beginning and end of the
pipeline, a mainline valve, and a meter and regulation station at the
end of the pipeline.
Crown Landing and Texas Eastern have applied concurrently to the
COE for two Department of the Army Individual Permits pursuant to
Section 404 of the Clean Water Act (33 U.S.C. 1344) and section 10 of
the Rivers and Harbors Act of 1899 (33 U.S.C. 403). The COE solicited
public comment on the applications in their public notice which was
included as part of the draft EIS notice for the projects published in
February 2005. The COE is now soliciting public comment on the two
modifications to the original proposal which are described above: (1)
Texas Eastern proposed open-cut contingency for the construction of the
proposed Chester Creek pipeline crossing and; (2) the Crown Landing
berthing terminal safety modification and related dredge volume
calculation.
The COE is soliciting comments from the public; Federal, State and
local agencies and officials; Indian Tribes; and other interested
parties in order to consider and evaluate any additional impacts
resulting from the proposed minor design modifications. Any comments
received will be considered by the COE to determine whether to issue,
modify, condition, or deny permits for these proposals as modified. To
make this decision, comments are used to assess impacts on endangered
species, historic properties, water quality, general environmental
effects, and the other public interest factors listed in the COE's
original notice included with the draft EIS. Comments are used in
determining the need for and the preparation of any necessary
supplemental NEPA documentation. Comments are also used to determine
the need for a public hearing on the proposed design modifications and
to determine the overall public interest of the proposed activities.
Please carefully follow these instructions to ensure that your comments
are received in time and properly recorded:
? Send an original and two copies of your letter on the
design modifications to: Magalie R. Salas, Secretary, Federal Energy
Regulatory Commission, 888 First St. NE.; Room 1A, Washington, DC 20426;
? Label one copy of the comments for the attention of Gas 1, PJ-11.1;
? Reference Docket Nos. (Crown Landing) CP04-411-000 and
(Texas Eastern) CP04-416-000;
? Mail your comments so that they will be received in Washington, DC
on or before June 27, 2006 (Copies will be provided to the COE).
The final EIS has been placed in the public files of the FERC and
is available for distribution and public inspection at: Federal Energy
Regulatory Commission, Public Reference Room, 888 First Street, NE.,
Room 2A, Washington, DC 20426, (202) 502-8371.
Copies are also available at the following locations:
Gloucester County Library, 415 Swedesboro Road, Gibbstown, NJ 08027.
Gloucester County Library, 101 Beckett Road, Logan Township, NJ 08085.
J. Lewis Crozier Library, 620 Engle Street, Chester, PA 19013.
Aston Public Library, 3720 Concord Road, Aston, PA 19014.
Brandywine Hundred Branch of the New Castle County Library, 1300 Foulk
Road, Wilmington, DE 19803.
U.S. Army Corps of Engineers, Regulatory Branch, John Wanamaker
Building, 100 Penn Square East, Philadelphia, PA 19107, 215-656-5940.
A limited number of copies are available from the Public Reference
Room identified above. In addition, copies of the final EIS have been
mailed to Federal, State, and local agencies; public interest groups;
individuals and affected landowners who requested a copy of the final
EIS; libraries; newspapers; and parties to this proceeding.
In accordance with the Council on Environmental Quality's (CEQ)
regulations implementing NEPA, no agency decision on a proposed action
may be made until 30 days after the EPA publishes a notice of
availability of a final EIS. However, the CEQ regulations provide an
exception to this rule when an agency decision is subject to a formal
internal process that allows other agencies or the public to make their
views known. In such cases, the agency decision may be made at the same
time the notice of the final EIS is published, allowing both periods to
run concurrently. Should the FERC issue Crown Landing and Texas Eastern
authorizations for the proposed projects, it would be subject to a 30-
day rehearing period.
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (http://www.ferc.gov)
using the eLibrary
link. Click on the eLibrary link, click on ``General Search'' and enter
the docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link on the FERC Internet Web site
also provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rulemakings.
Magalie R. Salas,
Secretary.
[FR Doc. E6-6854 Filed 5-4-06; 8:45 am]