Notice of Availability of Environmental Assessment and Finding of No Significant Impact for License Amendment to Source Materials License No. STC-133, for Unrestricted Release of the Defense Logistics Agency's Facility in Binghamton, New York

Note: EPA no longer updates this information, but it may be useful as a reference or resource.


 [Federal Register: February 15, 2007 (Volume 72, Number 31)]
[Notices]
[Page 7478-7480]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr15fe07-104]

-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION
[Docket No. 04000341]

Notice of Availability of Environmental Assessment and Finding of
No Significant Impact for License Amendment to Source Materials License
No. STC-133, for Unrestricted Release of the Defense Logistics Agency's
Facility in Binghamton, New York

AGENCY: Nuclear Regulatory Commission.
ACTION: Issuance of environmental assessment and finding of no
significant impact for license amendment.

-----------------------------------------------------------------------

FOR FURTHER INFORMATION CONTACT: Dennis Lawyer, Health Physicist,
Commercial and R&D Branch, Division of Nuclear Materials Safety, Region
I, 475 Allendale Road, King of Prussia, Pennsylvania; telephone 610-
337-5366; fax number 610-337-5393; or by e-mail: drl1@nrc.gov.

SUPPLEMENTARY INFORMATION:

I. Introduction

    The U.S. Nuclear Regulatory Commission (NRC) is considering the
issuance of a license amendment to Source Materials License No. STC-
133. This license is held by Defense Logistics Agency (the Licensee),
for its Defense National Stockpile Center Binghamton Depot, located at
Hoyt Avenue in Binghamton, New York (the Facility). Issuance of the
amendment would

[[Page 7479]]

authorize release of the Facility for unrestricted use. The Licensee
requested this action in a letter dated October 16, 2006. The NRC has
prepared an Environmental Assessment (EA) in support of this proposed
action in accordance with the requirements of Title 10, Code of Federal
Regulations (CFR), Part 51 (10 CFR Part 51). Based on the EA, the NRC
has concluded that a Finding of No Significant Impact (FONSI) is
appropriate with respect to the proposed action. The amendment will be
issued to the Licensee following the publication of this FONSI and EA
in the Federal Register.

II. Environmental Assessment

Identification of Proposed Action

    The proposed action would approve the Licensee's October 16, 2006,
license amendment request, resulting in release of the Facility for
unrestricted use. License No. STC-133 was issued on July 27, 1983,
pursuant to 10 CFR Part 40, and has been amended periodically since
that time. This license authorized the Licensee to use unsealed
byproduct material for purposes of storage, sampling, repackaging, and
transferring materials.
    The Facility is situated on 57 acres of land and consists of
warehouse and office space. The Facility is located in a mixed
residential/industrial area. Within the Facility, use of licensed
materials was confined to the fire station and warehouses 8, 10, 11,
12, 13, and 14. The area of use totaled approximately 34,000 square feet.
    On December 10, 2004, the Licensee ceased licensed activities and
initiated a survey and decontamination of the Facility. Based on the
Licensee's historical knowledge of the site and the conditions of the
Facility, the Licensee determined that only routine decontamination
activities, in accordance with their NRC-approved, operating radiation
safety procedures, were required. The Licensee was not required to
submit a decommissioning plan to the NRC because worker cleanup
activities and procedures are consistent with those approved for
routine operations. The Licensee conducted surveys of the Facility and
provided information to the NRC to demonstrate that it meets the
criteria in Subpart E of 10 CFR Part 20 for unrestricted release.

Need for the Proposed Action

    The Licensee has ceased conducting licensed activities at the
Facility, and seeks the unrestricted use of its Facility.

Environmental Impacts of the Proposed Action

    The historical review of licensed activities conducted at the
Facility shows that such activities involved use of the following
radionuclides with half-lives greater than 120 days: Natural uranium
and thorium. Prior to performing the final status survey, the Licensee
conducted decontamination activities, as necessary, in the areas of the
Facility affected by these radionuclides.
    The Licensee conducted a final status survey on November 7-10,
2005, June 15-23, 2006, July 4-6, 2006, and August 3 and 4, 2006. This
survey covered the areas of use as stated in the Final Status Survey
Plan, dated February 2006. The final status survey report was enclosed
with the Licensee's amendment request dated October 16, 2006, and an
additional information letter dated December 19, 2006. The Licensee
elected to demonstrate compliance with the radiological criteria for
unrestricted release as specified in 10 CFR 20.1402 by developing
derived concentration guideline levels (DCGLs) for its Facility. The
Licensee conducted site-specific dose modeling using input parameters
specific to the Facility and a conservative assumption that all
residual radioactivity is in equilibrium. Federal Guidance Report
Number 13 was used to modify the dose conversion factors because it is
based on an improved, more realistic dosimetry model. The selected
critical age group is adults as the expected future use of this
facility will be industrial. Based on the type of building, railroad
distribution, and truck access, there is no compelling evidence to
indicate that the building will be used for anything other than
industrial activities. The Licensee thus determined the maximum amount
of residual radioactivity on building surfaces, equipment, materials,
and soils that will satisfy the NRC requirements in Subpart E of 10 CFR
Part 20 for unrestricted release. The NRC previously reviewed the
Licensee's methodology and proposed DCGLs, and concluded that the
proposed DCGLs are acceptable for use as release criteria at the
Facility. The NRC's approval of the Licensee's proposed DCGLs was
published in the Federal Register on Tuesday, August 22, 2006, Volume
71, No. 162, pages 48952 and 48953. The Licensee's final status survey
results were below these DCGLs, and are thus acceptable.
    The NRC staff conducted a confirmatory survey June 15-16, 2006.
None of the confirmatory sample results exceeded the DCGLs established
for the Facility. Based on its review, the staff has determined that
the affected environment and any environmental impacts associated with
the proposed action are bounded by the impacts evaluated by the
``Generic Environmental Impact Statement in Support of Rulemaking on
Radiological Criteria for License Termination of NRC-Licensed Nuclear
Facilities'' (NUREG-1496) Volumes 1-3 (ML042310492, ML042320379, and
ML042330385). The staff finds there were no significant environmental
impacts from the use of radioactive material at the Facility. The NRC
staff reviewed the docket file records and the final status survey
report to identify any non-radiological hazards that may have impacted
the environment surrounding the Facility. No such hazards or impacts to
the environment were identified. The NRC has identified no other
radiological or non-radiological activities in the area that could
result in cumulative environmental impacts.
    The NRC staff finds that the proposed release of the Facility for
unrestricted use is in compliance with 10 CFR 20.1402. Based on its
review, the staff considered the impact of the residual radioactivity
at the Facility and concluded that the proposed action will not have a
significant effect on the quality of the human environment.

Environmental Impacts of the Alternatives to the Proposed Action

    Due to the largely administrative nature of the proposed action,
its environmental impacts are small. Therefore, the only alternative
the staff considered is the no-action alternative, under which the
staff would leave things as they are by simply denying the amendment
request. This no-action alternative is not feasible because it
conflicts with 10 CFR 40.42(d), requiring that decommissioning of
source material facilities be completed and approved by the NRC after
licensed activities cease. The NRC's analysis of the Licensee's final
status survey data confirmed that the Facility meets the requirements
of 10 CFR 20.1402 for unrestricted release. Additionally, denying the
amendment request would result in no change in current environmental
impacts. The environmental impacts of the proposed action and the no-
action alternative are therefore similar, and the no-action alternative
is accordingly not further considered.

Conclusion

    The NRC staff has concluded that the proposed action is consistent
with the NRC's unrestricted release criteria

[[Page 7480]]

specified in 10 CFR 20.1402. Because the proposed action will not
significantly impact the quality of the human environment, the NRC
staff concludes that the proposed action is the preferred alternative.

Agencies and Persons Consulted

    NRC provided a draft of this Environmental Assessment to the State
of New York's Department of Environmental Conservation for review on
December 27, 2006. On January 29, 2007, New York State responded by
electronic mail. The State agreed with the conclusions of the EA, and
otherwise had no comments.
    The NRC staff has determined that the proposed action is of a
procedural nature, and will not affect listed species or critical
habitat. Therefore, no further consultation is required under Section 7
of the Endangered Species Act. The NRC staff has also determined that
the proposed action is not the type of activity that has the potential
to cause effects on historic properties. Therefore, no further
consultation is required under Section 106 of the National Historic
Preservation Act.

III. Finding of No Significant Impact

    The NRC staff has prepared this EA in support of the proposed
action. On the basis of this EA, the NRC finds that there are no
significant environmental impacts from the proposed action, and that
preparation of an environmental impact statement is not warranted.
Accordingly, the NRC has determined that a Finding of No Significant
Impact is appropriate.

IV. Further Information

    Documents related to this action, including the application for
license amendment and supporting documentation, are available
electronically at the NRC's Electronic Reading Room at http://
www.nrc.gov/reading-rm/adams.html. From this site, you can access the
NRC's Agencywide Document Access and Management System (ADAMS), which
provides text and image files of NRC's public documents. The documents
related to this action are listed below, along with their ADAMS
accession numbers.
    1. NUREG-1757, ``Consolidated NMSS Decommissioning Guidance;''
    2. Title 10 Code of Federal Regulations, Part 20, Subpart E,
``Radiological Criteria for License Termination;''
    3. Title 10, Code of Federal Regulations, Part 51, ``Environmental
Protection Regulations for Domestic Licensing and Related Regulatory
Functions;''
    4. NUREG-1496, ``Generic Environmental Impact Statement in Support
of Rulemaking on Radiological Criteria for License Termination of NRC-
Licensed Nuclear Facilities;''
    5. ``Radiological Historical Site Assessment Report, Defense
National Stockpile Center, Binghamton Deport, Binghamton, NY'' dated
February 2006 [ML060730408];
    6. ``Final Status Survey Plan, DNSC, Binghamton Depot, Binghamton,
NY'' dated February 2006 [ML060730389];
    7. ``Notice of Availability of Environmental Assessment and Finding
of No Significant Impact for License Amendment to Source Materials
License No. STC-133 Authorizing the Use of Site-Specific Derived
Concentration Guideline Levels for Unrestricted Release of the Defense
Logistics Agency, Defense Nuclear Supply Center Depot in Binghamton,
NY'' published in the Federal Register Volume 71, Number 162 on August
22, 2006, pages 48952 and 48953;
    8. Defense Logistics Agency, Submittal of Final Status Survey
Report for the Defense National Stockpile, Binghamton, NY Depot dated
October 16, 2006 [ML062970211];
    9. Defense Logistics Agency, Deficiency Response Letter dated
December 19, 2006 [ML063540612]; and
    10. Defense Logistics Agency, Deficiency Response Facsimilie dated
January 3, 2007 [ML070040099].
    If you do not have access to ADAMS, or if there are problems in
accessing the documents located in ADAMS, contact the NRC Public
Document Room (PDR) Reference staff at 1-800-397-4209, 301-415-4737, or
by e-mail to pdr@nrc.gov. These documents may also be viewed
electronically on the public computers located at the NRC's PDR, O 1
F21, One White Flint North, 11555 Rockville Pike, Rockville, MD 20852.
The PDR reproduction contractor will copy documents for a fee.

    Dated at Region 1, 475 Allendale Road, King of Prussia, this 5th
day of February 2007.

    For the Nuclear Regulatory Commission.
James P. Dwyer,
Chief, Commercial and R&D Branch, Division of Nuclear Materials Safety,
Region 1.