Jump to main content.


Alaska Railroad Corporation--Construction and Operation Exemption--a Rail Line Extension to Port MacKenzie, AK

Note: EPA no longer updates this information, but it may be useful as a reference or resource.


PDF Version (7 pp, 71K, About PDF)

[Federal Register: July 17, 2009 (Volume 74, Number 136)]
[Notices]
[Page 34859-34865]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr17jy09-136]

-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Finance Docket No. 35095]

Alaska Railroad Corporation--Construction and Operation
Exemption--a Rail Line Extension to Port MacKenzie, AK

AGENCY: Lead: Surface Transportation Board. Cooperating: U.S. Army
Corps of Engineers, Alaska District; Federal Railroad Administration;
and United States Coast Guard.
ACTION: Notice of Availability of Final Scope of Study for the
Environmental Impact Statement (EIS).

-----------------------------------------------------------------------

SUMMARY: The Alaska Railroad Corporation (ARRC or Applicant) petitioned
the Surface Transportation Board (Board) pursuant to 49 U.S.C. 10502
for authority to construct and operate a new rail line from Matanuska-
Susitna Borough's (MSB) Port MacKenzie to ARRC's existing main line
between Wasilla and north of Willow, Alaska. The project would involve
the construction and operation of approximately 30 to 45 miles of new
rail to the main line track. Figure 1 shows ARRC's existing track and
the proposed rail line extension from Port MacKenzie to ARRC's existing
main line (All figures are available for viewing on the Board's Web
site at http://www.stb.dot.gov by going to ``Environmental Matters,''
then selecting ``Key Cases'' in the dropdown; and then when the next
page appears, clicking ``Alaska Railroad--Port MacKenzie Rail Extension).
    Because the construction and operation of this project has the
potential to result in significant environmental impacts, the Board's
Section of Environmental Analysis (SEA) has determined that the
preparation of an Environmental Impact Statement (EIS) is appropriate.
For further information about the Board's environmental review process
and the EIS, you may also visit a Board-sponsored project Web site at
http://www.stbportmacraileis.com. Exit Disclaimer
    To help determine the scope of the EIS, and as required by the
Board's regulations at 49 CFR 1105.10(a)(2), SEA published in the
Federal Register and mailed to the public on February 12, 2008, the
Notice of Availability of Draft Scope of Study for the EIS, Notice of
Scoping Meetings, and Request for Comments. SEA also prepared and
distributed to the public a fact sheet that introduced ARRC's Port
MacKenzie Rail Extension, announced SEA's intent to prepare an EIS,
requested comments, and gave notice of six public scoping meetings to
citizens; elected officials; Federal, state, and local agencies; tribal
organizations; and other potentially interested stakeholders. SEA held
six public scoping meetings in Knik, Big Lake, Willow, Houston, Wasilla,
and Anchorage, Alaska on March 3, 4, 5, 6, 10, and 11, 2008, respectively.
    The scoping comment period concluded March 21, 2008. The U.S. Army
Corps of Engineers, Alaska District (USACE); Federal Railroad
Administration (FRA); and United States Coast Guard (USGC) requested
and were granted cooperating agency status in preparation of the EIS.
After review and consideration of all comments received, this notice
sets forth the final scope of the EIS. The final scope reflects any
changes to the draft scope as a result of the comments, summarizes and
addresses the principal environmental concerns raised by the comments,
and briefly discusses pertinent issues concerning this project that
further clarify the final scope.

FOR FURTHER INFORMATION CONTACT:
David Navecky, Section of Environmental Analysis, Surface
Transportation Board, 395 E Street, SW., Washington, DC 20423-0001,
202-245-0294, or call SEA's toll-free number for the project at 1-888-
257-7560. Assistance for the hearing impaired is available through the
Federal Information Relay Service (FIRS) at 1-800-877-8339. The Web
site for the Surface Transportation Board is http://www.stb.dot.gov.
Serena Sweet, U.S. Army Corps of Engineers--P.O. Box 6898, Elmendorf
Air Force Base, AK 99506, 907-753-2819.
John Winkle, Passenger Programs Division, Federal Railroad

[[Page 34860]]

Administration, 1200 New Jersey Avenue, SE., Washington, DC 20590, 202-493-6067.
James Helfinstine, Seventeenth District, U.S. Coast Guard, P.O. Box
25517, Juneau, AK 99802-5517, 907-463-2268.

SUPPLEMENTARY INFORMATION:

Background

    Port MacKenzie is a deepwater facility on the west side of the Knik
Arm in upper Cook Inlet in south-central Alaska. At present, freight
truck is the only available surface mode of transportation to and from
Port MacKenzie. The Applicant has stated that the proposed rail line
would satisfy the need for an additional mode of transportation for the
movement of bulk materials, intermodal containers, and other freight to
and from Port MacKenzie. The proposed project is consistent with the
MSB's economic development plans and with ARRC's statutory goal to
foster and promote long-term economic growth in the State of Alaska.
The project would support the Port's continued development as a multi-
modal and bulk materials export and import facility. ARRC plans to
support commercial freight rail service needs with the proposed project.
    Major elements of the project would include:
    • Approximately 30 to 45 miles of new railroad track
depending on the alternative;
    • A 200-foot wide right-of-way (ROW);
    • Crossings (depending on the alternative) of the Little
Susitna River, Lake Creek, Goose Creek, Little Willow Creek, Fish
Creek, Rogers Creek, Lucile Creek, Little Meadow Creek, and Willow
Creek, along with many other small stream crossings;
    • Crossings of local roads and streets, including grade-separations;
    • Pipeline, utility, and recreational trail crossings,
including the Iditarod National Historic Trail;
    • Road closures and relocations;
    • Track sidings along the existing ARRC mainline;
    • A terminal reserve area (consists of yard sidings, storage
areas, and a terminal building to support train maintenance); and
    • Ancillary railroad support facilities including, but not
limited to, communications towers and facilities, maintenance, power,
signals, and access road.

Environmental Review Process

    The Board is the lead agency, pursuant to 40 CFR 1501.5. SEA is
responsible for ensuring that the Board complies with the National
Environmental Policy Act (NEPA), 42 U.S.C. 4321-4335, and related
environmental statutes, and for completing the environmental review
process. The NEPA review process is intended to assist the Board, the
cooperating agencies and the public in identifying and assessing the
potential environmental consequences of a proposed action and the
reasonable alternative before a decision is made.
    ICF International is serving as an independent third-party
contractor to assist SEA in the environmental review process. SEA is
directing and supervising the preparation of the EIS. The USACE, FRA,
and USCG are cooperating agencies, pursuant to 40 CFR 1501.6.
    The Federal agency actions considered in this EIS will include
decisions, permits, approvals and funding related to the proposed
action. The Board will decide whether to grant authority to ARRC to
construct and operate the rail line pursuant to 49 U.S.C. 10901 and
10502. The USACE will decide whether to issue permits pursuant to
Section 404 of the Clean Water Act (33 U.S.C. 1251-1376, as amended)
and/or Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.
403). The USCG will decide whether to issue authority to construct
bridges over navigable waters of the United States pursuant to the
Department of Transportation Act of 1966 (49 U.S.C. 1651-1659). The FRA
could provide funding to ARRC; however, the FRA would not provide
funding for a Board-authorized alternative, if any, that would require
the use of resources protected under Section 4(f) of the U.S.
Department of Transportation (USDOT) Act (23 CFR 774) if there is a
prudent and feasible alternative that does not use Section 4(f)
resources, unless the Secretary of Transportation determines that the
impacts to the protected resources would be de minimis in accordance
with Section 6009(a) of the Safe, Accountable, Flexible, Efficient
Transportation Equity Act: A Legacy for Users (SAFETEA-LU) amendment to
the Section 4(f) requirements, which do not require avoidance. The EIS
should include all of the information necessary for the decisions by
the Board and the cooperating agencies.
    SEA and the cooperating agencies are preparing a Draft EIS for the
proposed action. The Draft EIS will address those environmental issues
and concerns identified during the scoping process and detailed in this
final scope. It will also discuss a reasonable range of alternatives to
the proposed action, including a no-action alternative, and recommend
environmental mitigation measures, as appropriate.
    The Draft EIS will be made available upon its completion for public
review and comment. A Final EIS will then be prepared reflecting
further analysis by SEA and the cooperating agencies and the public and
agency comments on the Draft EIS. In reaching their decisions on this
case, the Board and the cooperating agencies will take into account the
full environmental record, including the DEIS, the Final EIS, and all
public and agency comments received.

Purpose and Need

    The Applicant has stated that the purpose of the Port MacKenzie
Rail Extension is to establish a rail link between Port MacKenzie (or
Port) and the ARRC rail system, providing Port customers and shippers
with rail transportation between the Port and Interior Alaska. The Port
is a deepwater facility on the west side of Knik Arm in upper Cook
Inlet, in south-central Alaska. At present, freight truck is the only
available surface mode of transportation to and from the Port.
    The Applicant has also stated that the proposed rail line would
satisfy the need for an additional mode of transportation for the
movement of bulk materials, intermodal containers, and other freight to
and from the Port. According to ARRC, the proposed project would
support ARRC's statutory goal to foster and promote long-term economic
growth and development in the State of Alaska and would be consistent
with the Port's economic development plans, which include the continued
development of the Port as a multi-modal and bulk materials export and
import facility.

Port Activities

    The proposed rail line extension would end at a terminal reserve
(rail yard) approximately 2 or 3 miles, depending on the route, from
the existing Port docks. Rail facilities the Port might construct to
connect to the rail line extension would be particular to the specific
traffic needs and would be expected to be generally consistent with
Port master planning documents. These facilities might include
buildings, roads, industrial spurs, sidings, loading/unloading tracks,
and other ancillary facilities throughout the upland port district.
These facilities would be developed as the Port continued to grow, but
would be independent of the planned rail extension. At present, the MSB
is developing a bulk materials facility at the Port to accommodate the

[[Page 34861]]

need for expansion of Port facilities to handle bulk material cargo to
be transported to the Port by truck, independent of the planned rail
line extension to the Port. The MSB has stated that as it continues to
plan for the bulk materials facility and future Port development, it
will consider the location of ARRC's proposed rail extension in its
decision making. The bulk material facility is not part of the proposed
action, and a detailed environmental review of the bulk material
facility is not within the scope of this EIS. The bulk materials facility,
however, will be addressed in the cumulative impacts section of the EIS.

Proposed Action and Alternatives

    The NEPA regulations require Federal agencies to consider a
reasonable range of feasible alternatives to the proposed action. The
President's Council on Environmental Quality (CEQ), which oversees the
implementation of NEPA, has stated in Forty Most Asked Questions
Concerning CEQ's National Environmental Policy Act Regulations that
``[R]easonable alternatives include those that are practical or
feasible from the technical and economic standpoint and using common
sense * * *.'' In this EIS, SEA and the cooperating agencies are
considering a full range of alternatives that meet the purpose and need
of the project, as well as the no-action alternative. The reasonable
and feasible alternatives included for detailed analysis and
alternatives considered but not included in detailed study are
discussed in more detail below.

A. Alternatives

    Based on agency consultations, feedback from stakeholders, and a
constraints analysis based on engineering and environmental studies, in
January 2008 ARRC developed the Preliminary Environmental and
Alternatives Report, which presented eight possible alignment
configurations. All alignments start at a terminal reserve area near
Port MacKenzie at the southern end and connect to the existing ARRC
mainline to the north. The alignments are composed of a southern and
northern segment with a possible connector tying the segments together.
The southern segments, Mac West or Mac East, run either east or west of
the Point MacKenzie Agricultural Project. Just north of the Point
MacKenzie Agricultural Project, there are three main northern
segments--Willow, Houston, and Big Lake--with Houston having a north or
south variant. Connector segments link the north and south segments
together to create eight possible alignment configurations as listed
below and depicted in Figure 1.
    After reviewing the eight ARRC-proposed alignments and considering
all comments received during the scoping period, SEA and the
cooperating agencies have decided to carry all eight alignments forward
as alternatives for detailed analysis in the EIS. The no-action
alternative will also be considered. The eight alternatives are listed
below. Each would consist of a 200-foot right-of-way (ROW) for the
railroad and associated facilities.
    1. Mac West--Connector 1--Willow. This alternative would be 44.8
miles long and contains the segments farthest west.
    2. Mac West--Connector 1--Houston--Houston North. This alternative
would be 35.1 miles long, and is geographically one of the middle
alignments.
    3. Mac West--Connector 1--Houston--Houston South. This alternative
would be 34.5 miles, and is geographically one of the middle alternatives.
    4. Mac West--Connector 2--Big Lake. This alternative would be 35.8
miles. It includes the southern segment along the west side of the
Point MacKenzie Agricultural Project and the most eastern north segment
going towards Big Lake.
    5. Mac East--Connector 3--Willow. This alternative would be 45
miles and is the longest. It includes the southern segment along the
east side of the Point MacKenzie Agricultural Project and the most
western north segment going towards Willow.
    6. Mac East--Connector 3--Houston--Houston North. This alternative
would be 35.3 miles, and is geographically one of the middle alternatives.
    7. Mac East--Connector 3--Houston--Houston South. This alternative
would be 34.7 miles long, and is geographically one of the middle
alignments.
    8. Mac East--Big Lake. This alternative would be 31.8 miles long
and is the shortest alternative. It includes the southern segment along
the east side of the Point MacKenzie Agricultural Project and the most
eastern north segment going toward Big Lake.
    Descriptions of the individual segments that complete the eight
build alternatives for the EIS are provided below.

Southern Segments

Mac West Segment

    The Mac West Segment would begin in the terminal reserve area and
would proceed northwest across relatively flat terrain toward the
southwest corner of the Point MacKenzie Agricultural Project. The
segment would continue west of the agricultural area, traversing along
the eastern boundary of Susitna Flats State Game Refuge. The terminal
reserve area is proposed along the southern side of Mac West.

Mac East Segment

    The Mac East Segment would begin in the terminal reserve area and
would proceed north along the side of a ridge along the east side of
the Point MacKenzie Agricultural Project. Near Mile Post 4.7, the
segment would cross a ravine and then curve to the northeast along the
top of another ridge. North of Mile Post 6, the segment would follow
the alignment of Port MacKenzie Road, offset 200 feet or more to the
west. The segment would continue along undulating terrain before
reaching its junction with the Big Lake Segment or Connector Segment 3.
The terminal reserve area is proposed along the north side of Mac East.\1\
---------------------------------------------------------------------------

    \1\ Based on Port planning and development information and
additional field data collected during the summer of 2008, ARRC has
revised the proposed location for the terminal reserve area to serve
Mac East. This terminal reserve area is shifted slightly to the west
relative to the previous location. This change occurred after
issuance of ARRC's Preliminary Environmental and Alternatives Report
and the scoping period for the EIS.
---------------------------------------------------------------------------

    See Figure 2 for a detailed map of the southern segments and
terminal reserve area.

Connectors

Connector Segment 1

    This 4.1-mile-long segment would connect the Mac West Segment to
the Willow or Houston segments. From Mac West, this connector segment
would continue north along the eastern boundary of the Susitna Flats
State Game Refuge on level terrain. The segment would cross a tributary
of the Little Susitna River.

Connector Segment 2

    This 3.7-mile-long segment would connect the Mac West Segment to
the Big Lake Segment. At the northwestern end of the Point MacKenzie
Agricultural Project, this connector segment would turn due east and
travel along the southern boundary of the Point MacKenzie Correctional Farm.

Connector Segment 3

    This 4.5-mile-long segment would connect the Mac East Segment to
the Willow or Houston segments. At the northeastern end of the Point
MacKenzie Agricultural Project, this

[[Page 34862]]

connector segment would shift to the northwest and cross Ayrshire
Avenue and Farmers Road at grade. The segment would continue north of
My Lake and cross an adjacent ravine. The remaining mile of the segment
is nearly level.
    See Figure 3 for a detailed map of the connector segments.

North Segments

Willow Segment

    From Connector Segment 1 or 3, the Willow Segment would continue
northwest where it would immediately cross the Little Susitna River
(see Figure 4). Over the next 7 miles, the segment would continue north
through rolling terrain. The segment would cross Fish Creek, the outlet
for Red Shirt and Cow lakes. The Willow Segment would then proceed
north, generally following the west-facing slope of a glacial moraine
west of Red Shirt Lake. It would continue north through the Nancy Lake
State Recreation Area for approximately 0.5 mile. The Willow Segment
would cross the outlet for Vera Lake, continue over rolling terrain,
and cross Willow Landing Road at grade. The segment would then continue
through the Willow Creek State Recreation Area, where it would cross
Willow Creek. The segment would curve to the east and cross Parks
Highway with a grade separation, before connecting to the existing ARRC
main line near Mile Post 188.9 along the proposed rail line.

Houston Segment

    From Connector Segment 1 or 3, the Houston Segment would proceed
northeast, traveling through slightly undulating terrain with areas of
wetland (see Figure 5). The segment would pass between Papoose Twins
Lakes and Crooked Lake, traversing an area of hilly terrain. The
remaining 4 miles of the Houston Segment would be in a gradually rising
wetland area to a point near Muleshoe Lake and Little Horseshoe Lake,
where it would connect to either the Houston North Segment or the
Houston South Segment.

Houston North Segment \2\
---------------------------------------------------------------------------

    \2\ Based on environmental impact associated with the original
proposed connection with the main line as presented in the
Preliminary Environmental and Alternatives Report and considered
during the scoping period, ARRC shifted the connection point
approximately 1 mile southeast to its present location.
---------------------------------------------------------------------------

    From the Houston Segment, the Houston North Segment would continue
north (see Figure 5), crossing over the Castle Mountain Fault. The
Houston North Segment would cross the Cow Lake Trail, which is part of
the Houston Lake Loop Trail. It would continue through the Little
Susitna Recreation Area, where it would cross the Little Susitna River.
The segment would continue north on rolling terrain along the east side
of Houston and Little Houston lakes, descending gradually to lower
terrain adjacent to Lake Creek. The Houston North Segment would tie
into the existing ARRC main line near Mile Post 178 without crossing
the Parks Highway.

Houston South Segment

    Also beginning between Muleshoe Lake and Little Horseshoe Lake,
this proposed segment would traverse northeast, passing just west of
Pear Lake (see Figure 5). The segment would traverse several gravel
ridges that parallel the lakes in this area. The segment would tie into
the existing mainline near Mile Post 174.0 without crossing the Parks Highway.

Big Lake Segment

    From the Mac East Segment or Connector Segment 2, the Big Lake
Segment would run northeast for approximately 3 miles, crossing Burma
Road at grade (see Figure 6). It would continue on rolling terrain,
crossing over Goose Creek, Fish Creek, Lucille Creek, and tributaries
of Lucille Creek and Little Meadow Creek. The segment would cross Burma
Road at grade and Big Lake Road, where it would be grade-separated
above Big Lake Road. The Big Lake Segment would continue north through
a residential area before crossing under Parks Highway. The Big Lake
Segment would connect with the existing ARRC main line near Mile Post
170.3 along the proposed rail line in a wetland area surrounding a
stream that feeds into Long Lake.
    The refined information collected during the 2008 summer field
season provided ARRC with better data to consider the tie-in location
for the Big Lake Segment. The following information supplements the
Preliminary Environmental and Alternatives Report (see Figure 6). These
refinements of the Big Lake Segment will be addressed in the EIS.
    • Construct an approximately 430-foot bridge on the Parks
Highway over the proposed rail line and an unnamed anadromous fish stream.
    • Relocate approximately 2,400 feet of unnamed anadromous
fish streams adjacent to the proposed rail line.
    • Relocate approximately 1,000 feet of Hawk Lane on the
south side of the Parks Highway (because of the new Parks Highway bridge).
    • Close approximately 865 feet of Cheri Lake Drive where it
crosses the existing main line and intersects with the Parks Highway.
    • Extend Ray Street approximately 1,405 feet from Loon
Street to the Parks Highway, which would include an at-grade crossing
of the existing ARRC main line.
    • Acquire eight recreational/residential parcels along Loon
Lake because access to the parcels would be permanently blocked due to
lack of access from the relocated road crossing (Cheri Lake Drive) and
the new siding.
    • Relocate the business on the southwest corner of the Parks
Highway and Cheri Lake Drive due to the Hawk Lane relocation.

B. Alternatives Considered But Not Included in Detailed Study

    Following review of scoping comments received and the potential
route alignments presented by ARRC in the Preliminary Environmental and
Alternatives Report, SEA asked ARRC to consider the feasibility of
making adjustments to the Willow, Big Lake, Mac West, and Houston North
Segments, and to consider a new segment to reduce potential
environmental impacts. The adjustments were proposed to reduce
potential impacts to state recreation areas and game refuges, a road
crossing, and wetlands. The proposed new segment would have utilized
already existing corridors. ARRC considered SEA's proposed changes and
explained that making these adjustments would create additional impacts
or the terrain would be unsuitable for railroad construction. For
example, SEA proposed shifting the Willow Segment west to avoid Willow
Creek State Recreation Area, but ARRC explained that this approach
would require closing or relocating the Willow Airport. In response to
ARRC's concerns about the feasibility of SEA's proposed changes, and
based on its own independent analysis, SEA determined that its proposed
modifications to the routes were not feasible.
    SEA also notes that rail across the proposed Knik Arm crossing
connecting Port MacKenzie to the ARRC main line in Anchorage was
considered, but determined impractical for several reasons. The Federal
Highway Administration (FHWA) determined this option to be financially
infeasible in the Knik Arm Crossing Final Environmental Impact
Statement. The nearly $1 billion cost (in 2005 dollars) estimated for
constructing this rail crossing would have exceeded the $600 million
limit for the Knik Arm Crossing project. In addition, a route to
Interior Alaska via the Knik Arm crossing would

[[Page 34863]]

have been considerably longer than the alternatives being analyzed and
would not meet the Applicant's stated purpose of providing a rail
connection suitable for shipment of bulk materials from Interior Alaska
to Port Mackenzie.

C. Public Participation

    As part of the environmental review process to date, SEA has
conducted broad public outreach activities to inform the public about
the proposed action and to facilitate public participation. SEA
consulted with and will continue to consult with Federal, state, and
local agencies; affected communities: and all interested parties to
gather and disseminate information about the proposal. SEA and the
cooperating agencies have also developed and implemented a Government-
to-Government Consultation and Coordination Plan to seek, discuss, and
consider the views of federally recognized Tribal Governments regarding
the proposed action and alternatives.

D. Response to Comments

    SEA and the cooperating agencies reviewed and considered the
comments received on the draft scope (130 comments with approximately
1,332 signatures) in preparing this final scope of the EIS. The final
scope reflects any changes to the draft scope as a result of comments.
Other changes in the final scope were made for clarification or as a
result of additional analysis. Additions and modifications reflected in
the final scope include:
    • Analysis of impacts on fisheries and fish habitat,
specifically anadromous streams. Federal and state agencies provided
comments on the potential impacts on fish and fish habitat. As a point
of clarification, the EIS will consider project-related effects on fish
resources including impacts from rail and road construction, types and
locations of water crossings and the accommodation of ice formation.
    • Analysis of impacts on nesting waterfowl and eagles.
Comments stated concerns about the potential impacts on nesting
waterfowl and eagles, as well as migrating waterfowl, including cranes
and grebes. As a point of clarification, the analysis in the EIS will
consider the locations of eagle nests and migrating waterfowl near
proposed alignments.
    • Analysis of impacts on moose and other wildlife. Comments
stated that moose strikes by trains are among the greatest wildlife
concerns. Comments also indicated that other mammals that reside in the
area could be affected. To clarify, the EIS will address wildlife
habitat impacts, including potential impacts to moose.
    • Analysis of socioeconomic impacts. Comments recommend that
the EIS consider the impacts of the proposed project on property
values, land access and use (i.e., agricultural), and quality of life.
Comments also stated concerns about the potential negative affects on
income generated from recreation tourism. The EIS will consider
potential project-related effects on local services as potential land
use impacts.
    • Analysis of impacts on water resources. Comments requested
that the EIS evaluate the potential loss of wetland habitat. Comments
also stated concerns regarding the potential project impacts on
watersheds (i.e., rail embankment acting as a barrier that would
disrupt natural drainage systems). Comments also recommended the study
of possible impacts of the Little Susitna River overflowing its banks
and the compounded effect of a possible spill on this interconnected
hydrologic system. The EIS will consider these potential impacts.
    • Analysis of impacts on cultural resources. Comments stated
concerns over potential impacts to known and unidentified cultural
resources (e.g., Iditarod Trail and native sites). Comments also stated
concerns over loss of subsistence resources. The EIS will address
cultural resources and subsistence.
    • Analysis of rail safety. Comments stated concerns over
rail and highway safety related to hazardous materials transport, at-
grade crossings, fire hazards, and crossing seismic zones (i.e.,
crossing fault lines). In addition, comments stated concerns about the
safety of potential rail crossings at recreational trails. The EIS will
examine the potential safety impacts of the proposed action.
    • Analysis of noise and vibration impacts. Comments stated
concerns over noise and vibration impacts near residential and
wilderness areas. The EIS will consider noise and vibration impacts
including potential project-related impacts to sensitive receptors.
    • Analysis of recreation and access. Comments requested that
the EIS address the potential impacts on recreation areas, access to
these areas, and safety. Concerns specifically addressed the potential
loss of access to recreational trails including the Iditarod, Junior
Iditarod, and Iron Dog trails. Comments noted that many trails are
unmarked through most recreation areas. Concerns were also raised about
undisturbed state and Federal parks. Analysis of these issues will be
included in the EIS.
    • Analysis of land use impacts. Comments stated concerns
about impacts to private properties as well as Federal, state and
borough public lands. Analysis of these issues will be included in the EIS.
    • Analysis of geology and soils. Comments stated concerns
about the Castle Mountain fault, which would be crossed by one of the
proposed alternatives. This issue will be addressed in the EIS.

E. Environmental Impact Analysis

Proposed New Construction
    Analysis in the EIS will address the proposed activities associated
with construction and operation of new rail facilities and their
potential environmental impacts, as appropriate.
Impact Categories
    The EIS will analyze potential impacts from construction and
operation of new rail facilities on the human and natural environment
for each alternative, or in the case of the no-action alternative, the
potential impacts of these activities not occurring. Impact areas
addressed will include the categories of geology and soils, water
resources including wetlands and other waters of the U.S., biological
resources, cultural and historic resources, subsistence, air quality,
noise and vibration, energy resources, transportation safety and delay,
navigation, land use, socioeconomics as they relate to physical changes
in the environment, and environmental justice. The EIS will include a
discussion of each of these categories as they currently exist in the
project area and will address the potential impacts of each alternative
on each category as described as follows:
1. Geology and Soils
    The EIS will:
    a. Describe the geology, soils, and seismic conditions found within
the project area, including unique or problematic geologic formations
or soils, prime farmland, prime and unique soils, and hydric soils and
analyze the potential impacts on these resources resulting from the
various alternatives for construction of a new rail line.
    b. Propose mitigative measures to minimize or eliminate potential
project impacts to geology and soils, and seismic hazards, as appropriate.
2. Water Resources
    The EIS will:
    a. Describe the existing surface water and groundwater resources within
the project area, including lakes, rivers, streams, ponds, wetlands, and

[[Page 34864]]

floodplains and analyze the potential impacts on these resources
resulting from each alternative.
    b. Describe the permitting requirements applicable to wetlands,
stream and river crossings, water quality, floodplains, and erosion control.
    c. Propose mitigative measures to avoid, minimize, or compensate
for potential project impacts to water resources, as appropriate.
    d. Identify and evaluate potential impacts to the Su-Knik
Mitigation Bank along the Big Lake Segment.

    Note: The Big Lake Segment would go through two mitigation bank
parcels that are part of the Su-Knik Mitigation Bank. Use of these
two mitigation bank parcels for the proposed rail line could require
concurrence from the entities that created the mitigation bank or
ROW acquisition by ARRC through eminent domain.

3. Biological Resources
    The EIS will:
    a. Evaluate the existing biological resources within the project
area, including vegetative communities, wildlife and fisheries, and
Federal and state threatened or endangered species and the potential
impacts to these resources resulting from each alternative.
    b. Describe any wildlife sanctuaries, refuges, national or state
parks, forests, or grasslands and evaluate the potential impacts to
these resources resulting from each alternative.
    c. Propose mitigative measures to avoid, minimize, or compensate
for potential impacts to biological resources, as appropriate.
4. Cultural and Historic Resources
    The EIS will:
    a. Analyze the potential project-related impacts to historic
structures or districts previously recorded and determined potentially
eligible, eligible, or listed on the National Register of Historic
Places within or immediately adjacent to the right-of-way for the
proposed rail alignments.
    b. Evaluate the potential impacts of each alternative to
archaeological sites previously recorded and either listed as
unevaluated or determined potentially eligible, eligible, or listed on
the National Register of Historic Places within the right-of-way for
the alternative rail alignments and the no-action alternative.
    c. Analyze the potential impacts to historic structures or
districts or archaeological sites identified by ground survey and
determined potentially eligible, eligible, or listed on the National
Register of Historic Places within or immediately adjacent to the
right-of-way for the alternative rail alignments.
    d. Evaluate the potential general impacts to paleontological resources
in the project area due to project construction, if necessary and required.
    e. Propose mitigative measures to minimize or eliminate potential
project impacts to cultural and historic resources, as appropriate.
5. Subsistence
    The EIS will:
    a. Analyze the potential impacts of the project alternatives on
subsistence activities in the project area.
    b. Propose mitigative measures to minimize or eliminate potential
project impacts on subsistence activities, as appropriate.
6. Air Quality
    The EIS will:
    a. Evaluate air emissions from rail operations, if the alternative
would affect a Class I or non-attainment or maintenance area as
designated under the Clean Air Act.
    b. Describe the potential air quality impacts resulting from new
rail line construction activities.
    c. Propose mitigative measures to minimize or eliminate potential
project impacts to air quality, as appropriate.
7. Noise and Vibration
    The EIS will:
    a. Describe the potential noise and vibration impacts during new
rail line construction.
    b. Describe the potential noise and vibration impacts of rail line
operations over new and existing rail lines.
    c. Propose mitigative measures to minimize or eliminate potential
project impacts to sensitive noise receptors, as appropriate.
8. Energy
    The EIS will:
    a. Describe and evaluate the potential impact of the new rail line
on the distribution and use of energy resources in the project area for
each alternative, including petroleum and gas pipelines and overhead
electric transmission lines.
    b. Propose mitigative measures to minimize or eliminate potential
project impacts to energy resources, as appropriate.
9. Transportation
    The EIS will:
    a. Evaluate the potential impacts of each alternative, including
new rail line construction and operation, on the existing
transportation network in the project area, including vehicular delays
at grade crossings.
    b. Describe existing road/rail grade crossing safety and analyze
the potential for an increase in accidents related to the new rail
operations, as appropriate.
    c. Describe existing rail operations and analyze the potential for
increased probability of train accidents, as appropriate.
    d. Evaluate the potential for disruption and delays to the movement
of emergency vehicles due to new rail line construction and operation
for each alternative.
    e. Propose mitigative measures to minimize or eliminate potential
project impacts to transportation systems, as appropriate.
10. Navigation
    The EIS will:
    a. Identify existing navigable waterways within the project area and
analyze the potential impacts on navigability resulting from each alternative.
    b. Describe the permitting requirements for the various
alternatives concerning navigation.
    c. Propose mitigative measures to minimize or eliminate potential
impacts to navigation, as appropriate.
11. Land Use
    The EIS will:
    a. Evaluate potential impacts of each alternative on existing land
use patterns within the project area and identify those land uses that
would be potentially impacted by new rail line construction.
    b. Analyze the potential impacts associated with each alternative
to land uses identified within the project area. Such potential impacts
could include incompatibility with existing land uses and conversion of
land to railroad uses.
    c. Propose mitigative measures to minimize or eliminate potential
impacts to land use, as appropriate.
    d. Evaluate existing conditions and the potential impacts of the
alternatives on recreational opportunities in the project area.
    e. Propose mitigative measures to minimize or eliminate potential
project impacts on recreational opportunities, as appropriate.
    f. Identify and evaluate potential impacts to resources protected
under the U.S. Department of Transportation (USDOT) regulation known as
``Section 4(f).'' (Note: The STB is an independent agency and is not
subject to Section 4(f) requirements). 23 Code of Federal Regulations
(CFR) 774 and 49 U.S.C. 303 mandate that the Secretary of
Transportation shall not approve any

[[Page 34865]]

transportation project requiring the use of publicly owned parks,
recreation areas or wildlife and waterfowl refuges, or significant
historic sites, regardless of ownership, unless there is no prudent and
feasible alternative to using that land, and the program or project
includes all possible planning to minimize harm to the public park,
recreation area, wildlife or waterfowl refuge, or significant site,
resulting from that use. Because FRA is a USDOT agency, they could not
provide funding for the project if the Board authorizes construction
and operation of an alternative that requires the use of resources
protected under Section 4(f) of the USDOT Act if there is a prudent and
feasible alternative that does not use Section 4(f) resources, unless
the use would result in de minimis impacts to Section 4(f) resources,
which do not require avoidance.

    Note: The Willow-Connector 1-Mac West alternative would traverse
the Willow Creek State Recreation Area, Nancy Lake State Recreation
Area, Little Susitna Recreation River, and Susitna Flats State Game
Refuge. The Houston North Segment would cross the Little Susitna
Recreation River. These recreation and refuge areas are all Section
4(f) resources and FRA funding for any rail line alternative
affecting these resources could be prohibited.

    g. Identify sites in the proposed project area that are known to or
might have been contaminated by hazardous materials, identify sites
that are regulated hazardous waste facilities, and describes the
potential impacts of constructing and operating the proposed rail line
on or near known hazardous materials and waste sites.
12. Socioeconomics
    The EIS will:
    a. Analyze the effects of a potential influx of construction
workers and the potential increase in demand for local services
interrelated with natural or physical environmental effects.
    b. Propose mitigative measures to minimize or eliminate potential
project adverse impacts to social and economic resources, as appropriate.
13. Environmental Justice
    The EIS will:
    a. Evaluate the potential impacts of each alternative, including
construction and operation of the rail lines, on local and regional
minority populations and low-income populations.
    b. Propose mitigative measures to minimize or eliminate potential
project impacts on environmental justice issues, as appropriate.
Cumulative Impacts
    The EIS will analyze cumulative impacts for the alternatives for
the proposed construction and operation of new rail facilities on the
human and natural environment, or in the case of the no-action
alternative, of the lack of these activities. SEA will analyze the
potential additive effects of the proposed action and alternatives to
the effects on applicable resources of relevant past, present, and
reasonably foreseeable projects or actions in the area of the proposed
action. SEA will determine appropriate time and geographic boundaries
for applicable resource-specific analyses in order to focus the
cumulative impacts analysis on truly meaningful effects. Resources
addressed may include the categories of geology and soils, water
resources including wetlands and other waters of the U.S., biological
resources, cultural and historic resources, subsistence, air quality,
noise and vibration, energy resources, transportation safety and delay,
navigation, land use, socioeconomics as they relate to physical changes
in the environment, and environmental justice. The EIS will review all
relevant past, concurrent, and reasonably foreseeable actions that
could result in collectively significant impacts to each of the
categories of impacts listed above, and to any other categories of
impacts that may be addressed as a result of comments received during
the scoping process or the Draft EIS comment period.

    By the Board, Victoria Rutson, Chief, Section of Environmental
Analysis.
Kulunie L. Cannon,
Clearance Clerk.
[FR Doc. E9-17018 Filed 7-16-09; 8:45 am]
BILLING CODE 4915-01-P

 
 


Local Navigation


Jump to main content.