Jump to main content or area navigation.

Contact Us

Superfund Innovative Technology Evaluation (SITE)

 EPA/540/A5-90/002

Note: EPA no longer updates this information, but it may be useful as a reference or resource.

 

CF Systems Organics Extraction Process New Bedford Harbor, Massachusetts
August 1990

The SITE Program Demonstration of the CF Systems organics extraction technology was conducted to obtain specific operating and cost information that could be used in evaluating the potential applicability of the technology to Superfund sites. The demonstration was conducted concurrently with dredging studies managed by the U.S. Army Corps of Engineers at the New Bedford Harbor Super-fund site in Massachusetts. Contaminated sediments were treated by CF Systems' Pit Cleanup Unit 0) that used a liquefied propane and butane mixture as the extraction solvent. The PCU was a trailer-mounted system with a design capacity of 1.5 gallons per minute (gpm), or 20 barrels per day (bbl/day). The technology extracts organics from contaminated soils based on solubility of organics in a mixture of liquefied propane and butane.

The objectives included an evaluation of (1) the unit's performance, (2) system operating conditions, (3) health and safety considerations, (4) equipment and system materials handling problems, and (5) projected system economics. The conclusions drawn from the test results and other available data are:

  • Polychlorinated biphenyl (PCB) extraction efficiencies of 90 percent were achieved for New Bedford Harbor sediments containing PCBs ranging from 350 to 2,575 parts per million (ppm). Concentrations of PCBs in the clean sediment were as low as 8 ppm.
  • Extraction efficiencies of 95 percent are demonstrated in the laboratory for volatile and semivolatile organics contained in aqueous and semisolid waste matrices.
  • Some operating problems occurred during the SITE tests, such as intermittant retention of solids in system hardware and foaming in the treated sediment collection tanks. Corrective measures were identified, and will be incorporated in the full-scale commercial unit.
  • Operation of the PCU at New Bedford did not present any threats to the health and safety of operators or the local community.
  • The projected cost of applying the technology to a full-scale cleanup at New Bedford Harbor ranges from $148 to $447 per ton. These projections include pre- and post-treatment costs, material handling costs, and costs for a spccializcd process configuration designed to remediate sediments, however the post-treatment cost did not include the final destruction of the concentrated extract.
  • Site specific pre- and post-treatment costs account for approximately one-third of the estimated costs.
  • The predicted onstream factor for the full-scale commercial unit is the variable that introduces the greatest uncertainty to the cost estimates.

Risk Mangement Research | Air and Climate Change Research | Water Research | Ecosystems Restoration Research | Land Risk Management Research | Technology: Sustainable Technologies Research, Environmental Technology Verification Program (ETV), and Technology Assessments

Jump to main content.