Annual Report 2002
Note: EPA no longer updates this information, but it may be useful as a reference or resource.
You will need Adobe Reader to view some of the files on this page. See EPA's PDF page to learn more.
Mine Waste Technology Program - 2002 Annual Report (PDF, 7.5M, 63 pp)
Prepared by:
MSE Technology Applications, Inc.
P.O. Box 4078
Butte , Montana 59702
Mine Waste Technology Program
Interagency Agreement Management Committee
IAG ID NO. DW89938870-01-0
Prepared for:
U.S. Environmental Protection Agency
Office of Research and Development
National Risk Management Research Laboratory
26 W. Martin Luther King Drive
Cincinnati, Ohio 46268
and
U.S. Department of Energy
National Energy Technology Laboratory
P.O. Box 10940
Pittsburgh, Pennsylvania 15236-0940
Contract No. DE-AC22-96EW96405
Table of Contents
Vision Statement for the Butte Mine Waste Technology Program
Program Manager's Executive Summary
Descriptions, Accomplishments, and Future Direction
Activity I Overview - Issues Identification
Activity II Overview - Quality Assurance
Activity III Overview - Pilot-Scale Demonstrations
Project 3 Sulfate-Reducing Bacteria Demonstration
Project 8 Underground Mine Source Control
Project 14 Biological Cover Demonstration
Project 15 Tailings Source Control
Project 16 Integrated Passive Biological Treatment Process Demonstration
Project 16A Sulfate-Reducing Bacteria-Driven Sulfide Precipitation Demonstration Project
Project 19 Site In Situ Mercury Stabilization Technologies
Project 21 Integrated Process for Treatment of Berkeley Pit Water
Project 22 Phosphate Stabilization of Mine Waste Contaminated Soils
Project 24 Improvements in Engineered Bioremediation of Acid Mine Drainage
Project 25 Passive Arsenic Removal Demonstration Project
Project 26 Prevention of Acid Mine Drainage Generation from Open-Pit Mine Highwalls
Project 29 Remediation Technology Evaluation at the Gilt Edge Mine
Project 33 Microencapsulation to Prevent Acid Mine Drainage
Project 34 Bioremediation of Pit Lakes (Guilt Edge Mine)
Project 36 Ceramic Microfiltration System Demonstration
Project 38 Contaminant Speciation in Riparian Soils Demonstration
Project 39 Long-Term Monitoring of Permeable Treatment Wall Demonstration
Project 40 Electrochemical Tailings Cover
Activity IV Overview - Bench-Scale Testing
Project 22 Organic Matter Degradation Rate in a Sulfate Reducing Wetland
Project 23 Sulfate Removal Technology Development
Project 24 Algal Bioremediation of the Berkeley Pit Lake System - Phase III
Activity V Overview - Technology Transfer
Activity VI Overview - Training and Education
Vision Statement for the Butte Mine Waste Technology Program
The Problem
Mining activities in the United States (not counting coal) produce between 1 and 2 billion tons of mine waste annually. These activities include extraction and beneficiation of metallic ores, phosphate, uranium, and oil shale. Over 130,000 of these noncoal mines, concentrated largely in nine western states, are responsible for polluting over 3,400 miles of streams and over 440,000 acres of land. About seventy of these sites are on the National Priority List for Superfund remediation. In the 1985 Report to Congress on the subject, the total noncoal mine waste volume was estimated at 50 billion tons, with 33% being tailings, 17% dump/heap leach wastes and mine water, and 50% surface and underground wastes. Since many of the mines involve sulfide minerals, the production of acid mine drainage (AMD) is a common problem from these abandoned mine sites. The cold temperatures in the higher elevations and heavy snows frequently prevent winter site access. The combinations of acidity, heavy metals, and sediment have severe detrimental environmental impacts on the delicate ecosystems in the West.
Philosophy / Vision
End-of-pipe treatment technologies, while essential for short-term control of environmental impact from mining operations, are a stopgap approach for total remediation. Efforts need to be made on improving the end-of-pipe technologies to reduce trace elements to low levels for applications in ultra-sensitive watersheds and for reliable operation in unattended, no power situations. The concept of pollution prevention, emphasizing at-source control and resource recovery, is the approach of choice for the long-term solution. Our objective in the Butte Mine Waste Technology Program is not to assess the environmental impacts of the mining activities, but it is to develop and prove technologies that provide satisfactory short- and long-term solutions to the remedial problems facing abandoned mines often in remote sites and the ongoing compliance problems associated with active mines, not only in Montana but throughout the United States.
Approach
There are priority areas for research, in the following order of importance:
Source Controls, Including In Situ Treatments and Predictive Techniques
It is far more effective to attack the problem at its source than to attempt to deal with diverse and dispersed wastes, laden with wide varieties of metal contaminants. At-source control technologies, such as sulfate-reducing bacteria; biocyanide oxidation for heap leach piles; transport control/pathway interruption techniques, including infiltration controls, sealing, grouting, and plugging by ultramicrobiological systems; and AMD production prediction and control techniques should strive toward providing a permanent solution, which of course is the most important goal of the program.Treatment Technologies
Improvements in short-term end-of-pipe treatment options are essential for providing immediate alleviation of some of the severe environmental problems associated with mining, and particularly with abandoned metal mines. Because immediate solutions may be required, this area of research is extremely important for effective environmental protection.Resource Recovery
In the spirit of pollution prevention, much of the mining wastes, both AMD (e.g., over 25 billion gallons of Berkeley Pit water) and the billions of tons of mining/beneficiation wastes, represent a potential resource as they contain significant quantities of heavy metals. While remediating these wastes, it may be feasible to incorporate resource recovery options to help offset remedial costs.
The Partnerships
In these days of ever-tightening budgets, it is important that we leverage our limited funding with other agencies and with private industry. The Bureau of Land Management and Forest Service actively participate by providing sites for demonstrations of the technologies. It is important where these technologies have application to active mining operations to achieve cost-sharing partnerships with the mining industry to test the technologies at their sites. Fortunately, the program has strong cooperation from industry. Within the U.S. Environmental Protection Agency (EPA), the Butte program is coordinated and teamed, where appropriate, with the Superfund Innovative Technology Evaluation (SITE) program to leverage the funding and maximize the effectiveness of both programs. We have strong interaction, cooperation, and assistance from the mining teams in the EPA Regional Offices, especially Regions 7, 8, 9, and 10. Several joint projects are underway, and more are planned.
A considerable resource and willing partner is the University system (such as Montana Tech of the University of Montana, University of Montana - Missoula, Montana State University - Bozeman, and the Center for Biofilm Engineering), which can conduct the more basic type of research related to kinetics, characterization, and bench-scale tests at minimal cost to the program, while at the same time providing environmental education that will be useful to the region and to the Nation. The Butte Mine Waste Technology Program supports cooperative projects between the educational system and the mining industry, where teams of students conduct research of mine site-specific problems, often with monetary support from the industry. The results are made available to the industry as a whole and to the academic community.
The Science
The research program is peer-reviewed annually by the Technical Integration Committee (TIC), who technically reviews all ongoing and proposed projects. The TIC is composed of technical experts from EPA and the cooperating agencies, academia, environmental stakeholders, and industry and their consultants. Final reports are additionally peer-reviewed in accordance with EPA's strict policy for scientific products.
Roger C. Wilmoth
Chief, Industrial Multimedia Branch
Sustainable Technology Division
National Risk Management Research Laboratory
Office of Research and Development
U.S. Environmental Protection Agency
(MS 445)
26 W. Martin Luther King Drive
Cincinnati, OH 45268
Return to the Table of Contents
Program Manager's Executive Summary
The Mine Waste Technology Program (MWTP) Annual Report for fiscal 2002 summarizes the results and accomplishments for the various activities within the Program. The MWTP has met its goals by providing assistance to the public and forming cooperative teams drawn from government, industry, and private citizens. The funds expended have returned tangible results, providing tools for those faced with mine waste remediation challenges.
After 12 years, everyone involved with the MWTP can look with pride to the Program's success. Technology development and basic research has proceeded successfully through the efforts of MSE Technology Applications, Inc. (MSE) and its prime subcontractor Montana Tech of the University of Montana (Montana Tech).
MSE has developed thirty-seven field-scale demonstrations, several of which are attracting attention from industry and public stakeholders involved in the cleanup of mine wastes.
Montana Tech has developed twenty-four bench-scale projects, six of which are ongoing during 2002. This cooperative effort provides cutting edge research for the program as well as educational opportunities.
Numerous activities are associated with the development of a field-scale demonstration. Among these activities is the need to acquire federal and state permits, secure liability limiting access agreements, develop and adhere to health and safety operation plans, and comply with the National Environmental Policy Act and other federal and state environmental oversight statutes.
The Program has received substantial support from state and federal agencies, the mining industry, environmental organizations, and numerous associations interested in mining and development of natural resources at state, regional, and national levels.
Montana Tech continued the post-graduate degree program with a mine waste emphasis. The quality of short courses offered by Montana Tech is becoming highly recognized by the mining industry and mine waste remediation community. Graduates of the program are fast becoming leaders for industry and government agencies helping to promote technology usage and acceptance worldwide.
The MWTP recognizes its major accomplishments and looks forward to providing new and innovative technologies; meeting the challenges of mine waste remediation; and providing economical, permanent solutions to the nation's mining waste problems.
Jeff LeFever
MSE MWTP Program Manager
Return to the Table of Contents
Introduction
Mining waste generated by active and inactive mining production facilities and its impact on human health and the environment are a growing problem for Government entities, private industry, and the general public. The nation's reported volume of mine waste is immense. Presently, there are more than sixty mining impacted sites on the U.S. Environmental Protection Agency's National Priorities List.
Environmental impacts associated with inactive and abandoned mines are common to mining districts around the country, as shown in Table 1.
Total estimated remediation costs for these states range from $4 to $45 billion.
Health effects from the predominate contaminants in mine waste range from mild irritants to proven human carcinogens, such as cadmium and arsenic. The large volume of mine wastes and consequential adverse environmental and human health effects indicates an urgency for cleanup of abandoned, inactive, and active mining facilities. The environmental future of the United States depends in part on the ability to deal effectively with mine waste problems of the past and present, and more importantly, to prevent mine waste problems in the future.
The fiscal year (FY) 1991 Congressional Appropriation allocated $3.5 million to establish a pilot program in Butte , Montana , for evaluating and testing mine waste treatment technologies. The Mine Waste Technology Program (MWTP) received additional appropriations of $3.5 million in FY91, $3.3 million in FY94, $5.9 million in FY95, $2.5 million in FY96, $7.5 million in FY97, $6.0 million in FY98 and FY99, $4.3 million in FY00, $3.9 million in FY01, and $3.9 million in FY02.
The projects undertaken by this Program focus on developing and demonstrating innovative technologies at both the bench- and pilot-scale that treat wastes to reduce their volume, mobility, or toxicity. Fifty percent of the budget is allocated to focus areas such as: 1) source control for preventing metal leaching and acid mine drainage; 2) techniques for treating low-flow metal laden/acid mine drainage in remote settings. To convey the results of these demonstrations to the user community, the mining industry, and regulatory agencies, MWTP includes provisions for extensive technology transfer and educational activities. This report summarizes the progress of the MWTP in FY02.
| State | Estimated Number of Sites or Land Areas | Classification and Estimated Number | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Alaska | 10,910 sites | mine dumps - 1,000 acres disturbed land - 27,680 acres mine openings - 500 hazardous structures - 300 |
||||||||||
| Arizona | 95,000 sites | polluted water - 2,002 acres mine dumps - 40,000 acres disturbed land - 96,652 acres mine openings - 80,000 |
||||||||||
| California | 11,500 sites | polluted water - 369,920 acres mine dumps - 171 acres mine openings - 1,685 |
||||||||||
| Colorado | 20,229 sites covering 26,584 acres |
polluted water - 830,720 acres mine dumps - 11,800 acres disturbed land - 13,486 acres mine openings - 20,229 hazardous structures - 1,125 |
||||||||||
| Idaho | 8,500 sites covering 18,465 acres |
polluted water - 84,480 acres mine dumps - 3,048 acres disturbed land - 24,495 acres mine openings - 2,979 hazardous structures - 1,926 |
||||||||||
| Michigan | 400-500 sites | Accurate information not available. | ||||||||||
| Montana | 19,751 sites covering 11,256 acres |
polluted water - 715,520 acres mine dumps - 14,038 acres disturbed land - 20,862 acres mine openings - 4,668 hazardous structures - 1,747 |
||||||||||
| Nevada | 400,000 sites | Accurate information not available. | ||||||||||
| New Mexico | 7,222 sites covering 13,585 acres |
polluted water - 44,160 acres mine dumps - 6,335 acres disturbed land - 25,230 acres mine openings - 13,666 hazardous structures - 658 |
||||||||||
| Oregon | 3,750 sites | polluted water - 140,800 acres mine dumps - 180 acres disturbed land - 61,000 acres mine openings - 3,750 hazardous structures - 695 |
||||||||||
| South Dakota | 4,775 acres | Accurate information not available. | ||||||||||
| Texas | 17,300 acres | Accurate information not available. | ||||||||||
| Utah | 14,364 sites covering 12,780 acres |
polluted water - 53,120 acres mine dumps - 2,369 acres disturbed land - 18,873 acres mine openings - 14,364 hazardous structures - 224 |
||||||||||
| Wisconsin | 200 acres | Accurate information not available. | ||||||||||
| Wyoming | 5,000 acres | Accurate information not available. | ||||||||||
| Information was collected from the following sources and is only an estimate of the acid mine drainage problem in the West. | ||||||||||||
|
||||||||||||
Return to the Table of Contents
Program Overfield
Fiscal 2002 Program
This Mine Waste Technology Program (MWTP) annual report covers the period from October 1, 2001 , through September 30, 2002 . This section of the report explains the MWTP organization and operation.
Mission
The mission of the MWTP is to provide engineering solutions to national environmental issues resulting from the past practices of mining and smelting metallic ores. In accomplishing this mission, the MWTP develops and conducts a program that emphasizes treatment technology development, testing and evaluation at bench- and pilot-scale, and an education program that emphasizes training and technology transfer. Evaluation of the treatment technologies focuses on reducing the mobility, toxicity, and volume of waste; implementability; short- and long-term effectiveness; protection of human health and the environment; community acceptance; and cost reduction.
The statement of work provided in the Interagency Agreement between the U.S. Environmental Protection Agency (EPA) and the U.S. Department of Energy identifies six activities to be completed by MWTP. The following descriptions identify the key features of each and the organization performing the activity
Activity I: Issues Identification
Montana Tech of the University of Montana (Montana Tech) is documenting mine waste technical issues and innovative treatment technologies. These issues and technologies are then screened and prioritized in volumes related to a specific mine waste problem. Technical issues of primary interest are Mobile Toxic Constituents - Water/Acid Generation; Mobile Toxic Constituents - Air, Cyanide, Nitrate, Arsenic, Pyrite, Selenium, and Thallium; and Pit Lakes. Wasteforms reviewed related to these issues include point- and nonpoint-source acid drainage, abandoned mine acid drainage, streamside tailings, impounded tailings, priority soils, and heap leach-cyanide/acid tailings. In addition, under this task Montana Tech produced a CD-ROM based summary of the Program in two volumes - Annual Report and Activities in Depth. The CDs can be obtained from the personnel listed in the Contacts Section of this report.
Activity II: Quality Assurance
The MWTP operates under an EPA approved Quality Management Plan (QMP). This plan provides specific instructions for data gathering, analyzing, and reporting for all MWTP activities.
Activity III: Pilot-Scale Demonstrations
Pilot-scale demonstration topics were chosen after a thorough investigation of the associated technical issue was performed, the specific wasteform to be tested was identified, peer review was conducted, and sound engineering and cost determination of the demonstration were formulated.
MSE continued eighteen field-scale demonstrations during fiscal 2002. Four field demonstrations were completed, i.e., Projects 12, 27, 31, and 35. Three projects were begun: 1) Contaminant Speciation in Riparian Soils; 2) Long-Term Monitoring of a Permeable Treatment Wall; and 3) Electrochemical Tailings Cover.
Activity IV: Bench-Scale Experiments
Montana Tech successfully completed seven projects during fiscal 2002, i.e., Projects 13, 14, and 16 through 20. Three projects were begun: 1) Organic Matter Degradation Rate in a Sulfate Reducing Wetland; 2) Sulfate Removal Technology Development; and 3) Algal Bioremediation of Berkeley Pit Lake System -Phase III.
Activity V: Technology Transfer
MSE is responsible for preparing and distributing reports for the MWTP. These include routine weekly, monthly, quarterly, and annual reports; technical progress reports; and final reports for all MWTP activities. MSE also publicizes information developed under MWTP in local, regional, and national publications. Other means of information transfer include public meetings, workshops, and symposiums.
Activity VI: Educational Programs
Montana Tech has developed a post-graduate degree program with a mine waste emphasis. The program contains elements of geophysical, hydrogeological, environmental, geochemical, mining and mineral processing, extractive metallurgical, and biological engineering.
Return to the Table of Contents
Organizational Structure
Management Roles and Responsibilities
Management of the Mine Waste Technology Program (MWTP) is specified in the Interagency Agreement. The roles and responsibilities of each organization represented are described below. The MWTP organizational chart is presented in Figure 1
U.S. Environmental Protection Agency
The Director of the National Risk Management Research Laboratory (NRMRL) in Cincinnati , Ohio , is the principal U.S. Environmental Protection Agency Office of Research and Development representative on the Interagency Agreement Management committee. NRMRL personnel are responsible for management oversight of technical direction, quality assurance, budget, schedule, and scope.
Department of Energy
The Director of the National Energy Technology Laboratory (NETL) is the principal U.S. Department of Energy (DOE) representative on the Interagency Agreement Management committee. NETL personnel provide contract oversight for the MWTP. MSE Technology Applications, Inc. (MSE) is responsible to NETL for adherence to environmental, safety and health requirements; regulatory requirements; National Environmental Protection Act requirements, and conduct of operations of all projects.
MSE Technology Applications, Inc.
MSE, under contract with DOE, is the principal performing contractor for MWTP. The MWTP Program Manager is the point of contact for all mine waste activities. The Program Manager is responsible for program management and coordination, program status reporting, funds distribution, and communications.
An MSE project manager has been assigned to each MWTP project and is responsible to the MWTP Program Manager for overall project direction, control, and coordination. Each project manager is responsible for implementing the project within the approved scope, schedule, and cost. MSE also provides all staff necessary for completing Activities II, III and V and oversight of Activities III, IV, and VI.
Montana Tech of the University of Montana
As a subcontractor to MSE, Montana Tech of the University of Montana is responsible to the MWTP Program Manager for all work performed under Activities I, IV, and VI. The responsibility for overall project direction, control, and coordination of the work to be completed by Montana Tech is assigned to the MWTP Montana Tech Project Manager.
Technical Integration Committee
The Technical Integration Committee (TIC) serves several purposes in the MWTP organization: 1) TIC reviews new proposals and ranks them at a meeting held in Butte, Montana; 2) it reviews progress in meeting the goals of the MWTP and alerts the Interagency Agreement Management Committee to pertinent technical concerns; 3) it provides information on the needs and requirements of the entire mining waste technology user community; and 4) it assists with evaluating technology demonstrations as well as technology transfer. This committee is comprised of representatives from both the public and private sectors.
View - Mine Waste Technology Program Organizational Structure (GIF, 34 Kb)
Return to the Table of Contents
Activities
Descriptions, Accomplishments, and Future Direction
This section describes the Mine Waste Technology Program (MWTP) Activities I through VI and includes project descriptions, major project accomplishments during fiscal 2002, and future project direction.
Return to the Table of Contents
Activity I Overview Issues Identification
This activity focuses on documenting mine waste technical issues and identifying innovative treatment technologies. Issues and technologies are screened and prioritized in volumes related to a specific mine waste problem/market.
Following completion of a volume, appendices are prepared. Each appendix links a candidate technology with a specific site where such a technology might be applied. The technology/site combinations are then screened and ranked.
Technical Issue Status
The status of the volumes approved for development includes:
- Volume 1, Mobile Toxic Constituents - Water and Acid Generation, complete.
- Volume 2, Mobile Toxic Constituents - Air, complete.
- Volume 3, Cyanide, complete.
- Volume 4, Nitrate, complete.
- Volume 5, Arsenic, complete.
- Volumes 1-5 Summary Report, complete.
- Volume 6, Pyrite, complete.
- Volume 7, Selenium, complete.
- Volume 8, Thallium, complete.
- Volume 9, Pit Lakes, in progress.
The status of the appendices for approved projects includes:
- Volume 1, Appendix A (Remote Mine Site), complete.
- Volume 1, Appendix B (Grouting), complete.
- Volume 1, Appendix C (Sulfate-Reducing Bacteria), complete.
- Volume 3, Appendix A (Biocyanide), complete.
- Volume 4, Appendix A (Nitrate), complete.
Return to the Table of Contents
Activity II Overview Quality Assurance
The objective of this activity is to provide support to individual MWTP projects by ensuring all data generated is legally and technically defensible and that it supports the achievement of individual project objectives. The primary means of carrying out this activity is the Quality Assurance Project Plan, which is written for each project. This plan specifies the quality requirements the data must meet, states the project objectives, describes all sampling and measurement activities, and contains standard operating procedures, when applicable. Other functions of this activity include reviewing technical systems, validating data, implementing corrective action, and reporting to project management.
The U.S. Environmental Protection Agency approved the MWTP Quality Management Plan in 200l.
View - Mine Waste Technology Quality Management Plan
Return to the Table of Contents
Activity IV Overview: Bench-Scale Testing
The objective of this activity is to develop, qualify, and screen techniques that show promise for cost-effective remediation of mine waste. The most promising and innovative techniques will undergo bench- or pilot-scale evaluations and applicability studies to provide an important first step to full-scale field demonstrations. Each experiment is assigned as an approved project with specific goals, budget, schedule, and principal team members.
Return to the Table of Contents
Activity IV, Project 22: Organic Matter Degradation Rate in a Sulfate Reducing Wetland
Project Overview
The primary objectives for this project were to determine the organic matter decay rate in sulfate reducing wetlands and improve the understanding of how natural wetlands function in metals-contaminated regions. The biodegradable organic matter serves as an indirect carbon and energy source for sulfate reducing bacteria that convert sulfate in the acid mine drainage to sulfide and bicarbonate, which precipitate heavy metals and neutralize acidity. To make quantitative predictions about long-term sulfate reduction rates in constructed wetlands and solid-substrate bioreactors, an effective mathematical model for the system must exist. Sulfate reduction is needed to precipitate heavy metals, and the sulfate reduction rate determines the rate of water treatment. The rate-limiting step in biogenic sulfide production is organic matter degradation. A first order rate coefficient and quantity of organic matter are needed to predict the organic matter replenishment interval that will keep the treatment system operating properly.
Technology Description
Field tests were run in a constructed wetland at the Upper Blackfoot Mining Complex owned by ASARCO near Lincoln, Montana. The rate coefficient was measured by burying dialysis bags made of regenerated cellulose containing compost in a constructed wetland treating acid mine drainage at the Upper Blackfoot Mining Complex. For the laboratory investigation, two reactors (duplicate experiments) were filled with mushroom compost and solution containing 50milligrams iron per liter and 500 milligrams SO42 per liter and kept in an incubator in a laboratory at Montana Tech. Both total organic carbon (TOC) and chemical oxygen demand (COD) were measured over time in samples from the field wetland and laboratory reactors. Other parameters measured included percent volatile solids, carbohydrates, and nonacid soluble matter.
Status
This project continued from January through December 2002. No significant changes to any of five parameters (COD, TOC, volatile solids, carbohydrates, and nonacid soluble matter) characterizing compost composition occurred during the first year of the research optimization phase of a study on the degradation rate of compost in systems treating acid mine drainage through biological sulfate reduction. The same compost used in the first year will continue to be degraded and monitored in laboratory and field systems for the second year (or Phase II) of the project.
Return to the Table of Contents
Activity IV, Project 23: Sulfate Removal Technology Development
Project Overview
Numerous mine waters and process effluent waters contain elevated concentrations of sulfate above the Primary Drinking Water Standard (500 milligrams per liter) or the Secondary Drinking Water Standard (250 milligrams per liter). The objective of the sulfate removal technology project was to investigate the possibility of reducing sulfate to sulfide on a metallic surface (with subsequent precipitation of a metal sulfide) and to investigate the use of compound precipitation to remove sulfate through the formation of a solid phase. A limited number of technologies are presently used for removing sulfate from wastewater such as bioreduction of sulfate to sulfide and membrane exclusion. These technologies have several disadvantages in that they are relatively expensive to operate, require specialized equipment, require long residence time reactors (bioreduction), high pressure (membrane processes like reverse osmosis and nanofiltration), and have difficult solid/liquid separations and membrane fouling problems.
Technology Description
A total of two technological approaches for the lowering of sulfate were investigated for this project including metal reduction of sulfate and precipitation of sulfate bearing compounds. The goal of the experimental study was to achieve a sulfate concentration of less than 250 milligrams per liter.
Status
This project is currently ongoing and was recently granted an extension for completion. Various testing has been completed to investigate both the metal reduction and compound precipitation methods for removing sulfate from wastewater. To date, the compound precipitation portion of the overall study performed on synthetic waters was completed and a portion of the real waters have been exposed to optimized precipitation conditions. Solution samples from these tests are presently being analyzed by ion chromatography. Preliminary tests (i.e., oxidation/reduction scans) have also been completed to investigate the sulfate reduction system. Additional testing and data analysis is proceeding and a final report will be completed FY03.
Return to the Table of Contents
Activity IV, Project 24: Algal Bioremediation of the Berkeley Pit Lake System Phase III
Project Overview
The Berkeley Pit Lake is a former open-pit copper mine that operated between 1955 and 1982. In 1982, the mine’s dewatering pumps were shutoff, and the pit began filling with acidic water, which is currently rising at a rate of about 4 meters (m) per year. The Berkeley Pit Lake is approximately 542 m deep and 1.8 kilometers (km) across. In 1984, the Berkeley Pit was designated as a CERCLA Superfund site by the U.S. Environmental Protection Agency (EPA). Other important aspects of the Berkeley Pit Lake include low acidic pH values (pH 2.5 to 3.0) and high concentrations of various metals. Previous and ongoing Mine Waste Technology Program research has been investigating the intricacies of the microbial ecology of the Berkeley Pit Lake system such as the diversity of algae, protistans, fungi, and bacteria that inhabit the pit lake.
Technology Description
This project was to further investigate some of the previously isolated extremophiles (specifically algae) from the Berkeley Pit Lake system that may be used as a potential solution for bioremediation. More specifically, the project objectives were as follows: 1) to evaluate the bioremediative potential of the four most rapidly growing species in the Berkeley Pit Lake System; 2) to determine which combination of nutrients will stimulate growth of the best bioremediator of the four isolated species; 3) to determine a temperature profile for the four species to determine their optimal growth temperature; 4) to continue to isolate organisms and determine their bioremediative potential; and 5) monitor algal and bacterial counts from a profile of Pit Lake System waters.
Status
Applicable testing and data analysis is proceeding in accordance with the project objectives, and a final report will be completed FY03. Various on-going data collection activities include separating bacteria from algae by washing through a filter and centrifugation; determining metal/element uptake potential by measuring dissolved metal concentrations before and after adding microorganisms to Berkeley Pit Lake water using inductively coupled plasma atomic emission spectrometry (ICP-AES); isolating algae from soil to determine which species are present; isolating/identifying bacteria and moss from soil samples; and evaluating techniques for the rapid isolation and growth of protonema.
Return to the Table of Contents
Activity V Overview—Technology Transfer
This activity consists of making technical information developed during Mine Waste Technology Program (MWTP) activities available to industry, academia, and government agencies. Tasks include preparing and distributing MWTP reports, presenting information about MWTP to various groups, publications in journals and magazines, holding Technical Integration Committee meetings, sponsoring mine waste conferences, and working to commercialize treatment technologies.
Fiscal Year Highlights
- The MWTP Annual Report was published summarizing fiscal year accomplishments. A similar report will be published each year.
- Several MWTP professionals appeared at varied meetings to discuss the Program with interested parties. Many mine waste conferences, as well as mining industry meetings, were attended.
Return to the Table of Contents
Activity VI Overview Training and Education
Through its education and training programs, the Mine Waste Technology Program (MWTP) continues to educate professionals and the general public about the latest information regarding mine and mineral waste cleanup methods and research.
As a result of rapid technology and regulatory changes, professionals working in the mine- and mineral-waste areas often encounter difficulties in upgrading their knowledge and skills in these fields. In recent years, the environmental issues related to the mining and mineral industries have received widespread public, industry, and political attention. While knowledge of current research and technology is vital for dealing with mine and mineral wastes, time and costs may prevent companies from sending employees back to the college classroom.
Through short courses, workshops, conferences, and video outreach, Activity VI of MWTP educates professionals and the general public and brings the specific information being generated by bench-scale research and pilot-scale technologies to those who work in mine- and mineral-waste remediation.
Fiscal 2002 Highlights
- Hardrock Mining 2002, conducted in May 2002, was an opportunity to
examine and discuss current and future environmental issues shaping
the mining industry with an emphasis on case study analysis and technology
verification. The U.S. Environmental Protection Agency’s (EPA)
Office of Research and Development and EPA’s National Risk Management
Research Laboratory (NRMRL) sponsored the 3-day event. MWTP provided
funding and sponsorship.
Attendees exchanged scientific information serving to enhance remediation and cleanup of both legacy and current mining wastes and to contribute to a sustainable U.S. modern mining industry. NRMRL’s Technology Transfer staff completed a CD that includes the conference materials, presentations, posters, and transcripts of plenary speakers. Call (513) 560-7804 to obtain the CD. - The Mine Design, Operations, and Closure Conference 2002, conducted in April 2002 continued last year's interagency cooperation. The 5-day event was cosponsored by the U.S. Forest Service; U.S. Bureau of Land Management; Montana Department of State Lands; MSE Technology Applications, Inc.; Haskell Environmental Research Studies Center; several other private companies; and Montana Tech. During the conference, experts presented overviews on such topics as predictive chemical modeling for acid mine drainage, mine water quality source control, state-of-the-art containment technologies, and innovative pit reclamation. Over 130 mineoperators, consultants, and professionals from the private and public sectors attended the conference.
- The Mine and Mineral Waste Emphasis Program has an enrollment of 10 students with all of them receiving funding from MWTP. This is an interdisciplinary graduate program that allows students to major in their choice of a wide variety of technical disciplines while maintaining an emphasis in mining and mineral waste.
- A group of Mine and Mineral Waste Emphasis graduate students attended the Mine Design, Operations, and Closure Conference 2002.
- A cooperative agreement is in place for work with the Haskell Environmental Research Studies Center at Haskell Indian Nations University.
- Graduate students in the Mine and Mineral Waste Emphasis Program are working on projects in Activities IV.
- As part of the Native American Initiative, Montana Tech presented five short courses: Mining and the Environment at Fort Belknap, and Acid Rock Drainage at both Fort Belknap and Salish Kootenai College. An environmental learning community was set up to house the short courses and Web courses to make them accessible to Native American communities around the country. One Web course, Environmental Planning for Small Communities, is on-line.
Return to the Table of Contents
Financial Summary
Total expenditures during the period October 1, 2001, through September 30, 2002, were $3,687,532, including both labor and non-labor expense categories. Individual activity accounts are depicted on the performance graph in Figure 26
Figure 26. Mine Waste Technology Program Fiscal 2002 performance graph, costs per activity.
Return to the Table of Contents
Completed Activities
For information on the following completed Mine Waste Technology Program activities, refer to the web site: http://www.epa.gov/ORD/NRMRL/std/mwt/
| Project Number | Project Name |
|---|---|
| Project 1 | Remote Mine Site Demonstration |
| Project 2 | Clay-Based Grouting Demonstration |
| Project 4 | Nitrate Removal Demonstration |
| Project 5 | Biocyanide Demonstration |
| Project 6 | Pollutant Magnet |
| Project 7 | Arsenic Oxidation |
| Project 9 | Arsenic Removal |
| Project 10 | Surface Waste Piles --- Source Control |
| Project 11 | Cyanide Heap Biological Detoxification Demonstration |
| Project 12 | Sulfate-Reducing Bacteria Reactive Wall Demonstration |
| Project 12A | Calliope Mine Internet Monitoring System |
| Project 13 | Hydrostatic Bulkhead with Sulfate-Reducing Bacteria |
| Project 17 | Lead Abatement Demonstration |
| Project 18 | Gas-Fed Sulfate-Reducing Bacteria Berkeley Pit Water Treatment |
| Project 20 | Selenium Removal/Treatment Alternatives |
| Project 27 | Remediating Soil and Groundwater with Organic Apatite |
| Project 31 | Remote Autonomous Mine Monitor |
| Project 35 | Biological Prevention of Acid Mine Drainage (Gilt Edge Mine) |
| Project Number | Project Name |
|---|---|
| Project 1 | Berkeley Pit Water Treatment |
| Project 2 | Sludge Stabilization |
| Project 3 | Photoassisted Electron Transfer Reactions Research |
| Project 3A | Photoassisted Electron Transfer Reactions for Metal-Complexed Cyanide |
| Project 3B | Photoassisted Electron Transfer Reactions for Berkeley Pit Water |
| Project 4 | Metal Ion Removal from Acid Mine Wastewaters by Neutral Chelating Polymers |
| Project 5 | Removal of Arsenic as Storable Stable Precipitates |
| Project 7 | Berkeley Pit Innovative Technologies Project |
| Project 8 | Pit Lake System Characterization and Remediation for the Berkeley Pit |
| Project 9 | Pit Lake System Deep Water Sediment/Pore Water Characterization and Interactions |
| Project 10 | Pit Lake System Biological Survey of Berkeley Pit Water |
| Project 11 | Pit Lake System Characterization and Remediation for Berkeley Pit Phase II |
| Project 12 | An Investigation to Develop a Technology for Removing Thallium from Mine Wastewaters |
| Project 13 | Sulfide Complexes Formed from Mill Tailings Project |
| Project 14 | Artificial Neural Networks as an Analysis Tool for Geochemical Data |
| Project 16 | Pit Lake System Characterization and Remediation for Berkeley Pit ¾ Phase III |
| Project 17 | Mine Dump Reclamation Using Tickle Grass Project |
| Project 18 | Investigation of Natural Wetlands Near Abandoned Mine Sites |
| Project 19 | Removing Oxyanions of Arsenic & Selenium
from Mine Wastewaters Using Galvanically Enhanced Cementation Technology |
| Project 20 | Algal Bioremediation of Berkeley Pit Water, Phase II |
Return to the Table of Contents
Key Contacts
| U.S. Environmental Protection
Agency: Roger C. Wilmoth U.S. Environmental Protection Agency Office of Research and Development National Risk Management Research Laboratory 26 W. Martin Luther King Drive Cincinnati, OH 45268 Telephone: (513) 569-7509 Fax: (513) 569-7471 wilmoth.roger@epa.gov |
MSE Technology Applications,
Inc.: Jeff LeFever, Program
Manager MSE Technology Applications, Inc. P.O. Box 4078 Butte, MT 59702 Telephone: (406) 494-7358 Fax: (406) 494-7230 jlefever@mse-ta.com |
| U.S. Department of Energy: Madhav Ghate U.S. Department of Energy National Energy Technology Laboratory P.O. Box 880 3610 Collins Ferry Road Morgantown, WV 26507-0880 Telephone: (304) 285-4638 Fax: (304) 285-4135 mghate@netl.doe.gov |
Montana Tech: Karl E. Burgher, Montana Tech MWTP Project Manager Montana Tech of the University of Montana 1300 West Park Street Butte, MT 59701-8997 Telephone: (406) 496-4311 Fax: (406) 496-4116 kburgher@mtech.edu |