UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
In the Matter of
L&C Services, Inc., Docket No. VII-93-CAA- 112
Respondent
INITIAL DECISION
By: Carl Charneski
Administrative Law Judge
Issued: January 29, 1997
Washington, D.C.
Appearances
For Complainant:
Henry F. Rompage, Esq.
U.S. Environmental Protection Agency
Region VII
Kansas City, Kansas
For Respondent:
D.K. "Kirby" Wright, Jr., Esq.
Hintze & Wright
Seattle, Washington
I. Introduction
This civil penalty proceeding arises under Section 113(d)(2)(A) of the Clean Air Act, 42 U.S.C.
§ 7413(d)(2)(A) (the "Act"). The U.S. Environmental Protection Agency ("EPA") brought this
enforcement action against L&C Services, Inc. ("L&C"), alleging six violations of the National Emissions
Standards for Hazardous Air Pollutants ("NESHAP") for asbestos. In each instance, EPA contends that
L&C violated the asbestos NESHAP by not adequately wetting friable asbestos until it was collected for
disposal. EPA claims that this failure to adequately wet the asbestos constitutes a violation of 40 C.F.R.
§ 61.145(c)(6)(i).
A hearing was held in this matter on February 27 and 28, 1996, in Wichita, Kansas. For the
reasons that follow, it is held that EPA has failed to establish that L&C violated the asbestos NESHAP as
alleged in each of the six counts. Accordingly, the administrative complaint filed by EPA against L&C is
dismissed.
II. Regulatory Background
Section 112 of the Clean Air Act, 42 U.S.C. § 7412, authorizes the Administrator of EPA to
publish a list of air pollutants that EPA determines to be hazardous and to describe the emission
standards, known as NESHAPS, for those pollutants. Asbestos was so listed as a hazardous air pollutant
and a corresponding NESHAP was promulgated at 40 C. F. R. Part 61, Subpart M ("National Emission
Standard for Asbestos"). This NESHAP sets forth the procedures to be followed in the removal and
disposal of materials that contain asbestos.
In particular, 40 C. F. R. § 61.145, titled "Standard for demolition and renovation." applies
where there is at least 260 linear feet of regulated asbestos-containing material ("RACM") on pipes or at
least 160 square feet of RACM on other components of the facility. See § 61.145(a). 1 Where this
threshold for RACM has been met, Section 61.145(b) sets forth specific requirements regarding
notification to EPA of demolition or renovation activity by the owner or operator of the involved facility.
In addition, Section 61.145(c) lists certain procedures that must be followed in the asbestos
abatement process. For example, Section 61.145(c)(6)(i), the regulatory provision at issue in this case,
provides:
(c)Procedures for asbestos emission control. Each owner
or operator of a demolition or renovation activity to whom this
paragraph applies, according to paragraph (a) of this section,
shall comply with the following procedures:
* * * * * * *
(6) For all RACM including material that has been
removed or stripped:
(i) Adequately wet the material and ensure that it remains
wet until collected or treated in preparation for disposal....
Emphasis added.
In this case, EPA does not allege that L&C violated the asbestos NESHAP by not wetting RACM
during its removal. Rather, EPA charges that L&C violated the asbestos NESHAP by not keeping
RACM wet after its removal, and before its disposal.
III. Factual Background
The Williams Pipeline Company ("WPC") owned a largely abandoned, 440-acre oil
refinery in Augusta, Kansas ("the Augusta facility"). Tr. 42. WPC contracted with L&C for the
asbestos
abatement and demolition of the 400-acre abandoned portion of this refinery. Tr. 484, 509-510.2 The
asbestos abatement work performed by L&C at the Augusta facility included the removal of all RACM,
i.e., regulated asbestos-containing material. Tr. 480, 483-486.
Prior to commencing work at the Augusta facility, L&C filed an Asbestos Notification Form with
the Kansas Department of Health and Environment ("KDHE"). In this Asbestos Notification Form, L&C
stated that it was going to remove 128,000 lineal feet of friable asbestos from pipe surfaces, 10,000 lineal
feet of friable asbestos was to be left in place on pipe removed by dismantling, 40,000 square feet of
friable asbestos was to be removed from vessels, and 5,000 square feet of friable asbestos was to be left
in place on dismantled heaters and towers. Compl. Ex. 1.3
Essentially, L&C was to do the asbestos abatement work, demolish the tanks and structures, and level
the refinery to the ground. Tr. 47-48. From April 9, 1992, it was L&C's practice to clean the metal
jacketing from the pipelines and to encapsulate the jacketing to prevent the release of asbestos fibers. Tr. 59-60,
522-523. 4
EPA brings the present enforcement action alleging that on six different occasions L&C removed
RACM at the Augusta facility and that it failed to keep the RACM wet until removal in violation of
Section 61.145(c)(6)(i), an asbestos NESHAP work practice requirement. EPA filed an administrative
complaint against L&C based upon the results of on-site inspections conducted by the KDHE, Bureau of
Air and Radiation in the Air and Asbestos Compliance Section. Tr. 124. The circumstances surrounding
each alleged violation are set forth below.
Count I
On August 9, 1992, KDHE Inspector David Branscum inspected Zone 39 of the Augusta facility.5
Inspector Branscum testified that he observed the presence of dry residue on metal jacketing that had been
removed from pipe and placed on the ground. According to Inspector Branscum, this material had not
been wetted or bagged for disposal by L&C. Tr. 128, 210. During this August 9 inspection, Branscum
did not take a sample of the material he suspected to be regulated asbestos-containing material. Tr. 231.
See Resp. Ex. 21 (Inspection Report).
Count II
Inspector Branscum conducted another inspection of the Augusta facility on April 14, 1992.
During his inspection of Zones 31 and 39, Branscum noticed what he believed was RACM that had been
removed from pipes. The inspector explained to L&C that the metal jacketing had to be cleaned or
bagged for disposal at the time that it was removed, and that it could not be allowed to lay on the ground
in what the inspector believed was a dry condition. Tr. 129, 213. Inspector Branscum conducted no
sampling on his April 14 inspection. Tr. 230. See Resp. Ex. 22 (Inspection Report).
Count III
Inspector Branscum next inspected L&C's asbestos abatement and demolition activities on April
22, 1992. This inspection took place in Zone 39 of the Augusta facility. KDHE Inspector Russ
Brichacek, Branscum's supervisor, was also present during this inspection. Both Branscum and
Brichacek testified that they observed metal jacketing on the ground that contained dry residue.
Brichacek told L&C's representa- tive, Tom Waits, that the debris on the ground and the metal jacketing
had to be handled properly at the time that it was removed from the piping. Tr. 132, 333-334. Neither
Inspector Branscum, nor Inspector Brichacek, took a sample of the suspected RACM on this April 22
inspection. Tr. 230, 345. See Resp. Ex. 25 (Inspection Report).
Inspector Branscum also testified that during a subsequent inspection conducted on May 6, 1992,
he observed the same metal jacketing lying on the ground that he had observed on the April 22, 1992,
inspection. Branscum added that during the May 6 inspection he was told by L&C representative Waits
that the company had not as yet decided whether to salvage or to dispose of the metal jacketing. Tr. 133.
Count IV
The Augusta facility was next inspected by the Kansas Department of Health & Environment on
June 25, 1992. Inspector Branscum stated that on June 25 he once again observed metal jacketing
containing dry residue lying on the ground. During this inspection, Branscum took photographs of the
metal jacketing, as well as photographs of equipment. Tr. 142-147. Inspector Branscum also took samples of suspected RACM
during the June 25 inspection. See Compl. Ex. 2; see also, Resp. Ex. 27 (Inspection Report).
Count V
On August 28, 1992, Inspector Branscum inspected the boiler house area located in Zone 39. The
inspector observed debris in this area, including metal jacketing, which he stated contained dry residue.
The inspector took photographs during this inspection, and he took samples of suspected RACM. Tr.
152-157. See Compl. Ex. 2; see also, Resp. Ex. 31 (Inspection Report).
Count VI
The final count in EPA's complaint concerns an inspection of the Augusta facility conducted by
Inspector Branscum on August 31, 1992. During this inspection, Branscum instructed L&C to cease all
demolition and dismantling activities. Branscum testified that at that time he was still observing metal
jacketing containing dry residue which was not being disposed of properly. Tr. 157-159. Inspector
Branscum did not take any samples during the August 31 inspection. See Resp. Ex. 35 (Inspection
Report).
IV. Discussion
Each of the six counts at issue in this case involves an alleged violation of 40 C.F.R. § 61.145
(c)(6)(i). Section 61.145(c)(6)(i) is a work practice requirement of the asbestos NESHAP which provides
in part that regulated asbestos-containing material is to be kept wet until collected for disposal. L&C
admits that this work practice requirement applied to its asbestos removal and demolition activities at the
Augusta facility, but it denies that the six violations at issue occurred. Resp. Prop. Concl. Of Law at 2.
L&C's position is well-taken. As explained below, EPA has failed to carry its burden of proof with
respect to each of the six counts at issue.
Section 61.145(c)(6)(i) is the starting point for analysis of this case. Subparagraph (6) of this
section begins with the phrase, "[f]or all RACM", after which follows the requirement that the regulated
asbestos-containing material be kept wet following its removal. The plain wording of this standard shows
that it applies to RACM, and only to RACM. Therefore, the threshold inquiry here is whether the
material observed by Inspectors Branscum and Brichacek, and which serves as the basis for the six
counts at issue, was regulated asbestos-containing material,
As explained in 40 C.F.R. § 61.141, the term "regulated asbestos-containing material" includes
"friable asbestos material." It is friable asbestos-containing material which EPA claims was observed by
the KDHE inspectors at the Augusta facility. 6 Section 61.141 further explains that friable asbestos
material "means any material containing more than 1 percent asbestos as determined using the method
specified in appendix E, subpart E, 40 CFR part 763, section 1, Polarized Light Microscopy. " See ns. 1
and 3, supra.
Despite Section 61.141's reference to Polarized Light Microscopy, or "PLM", EPA called no
witnesses to explain this scientific process for determining the presence of asbestos. Only L&C's witness,
Richard Potter, testified on this critical subject.
Mr. Potter was qualified as an expert in the area of asbestos. Tr. 428. See Ex. H-6 and Tr. 422-427 for Potter's qualifications. According to Potter, PLM is the recommended EPA-method for
determining whether asbestos is present in a given material. Tr. 438. Potter explained that in the
Polarized Light Microscopy process tweezers are used to extract a small part of the sample. This
selected portion is first examined under a stereoscopic microscope, which is a low magnification
microscope. A physical description is made of the color, texture, and appearance of the sample. Tr. 438-439.
Next, needle-nosed tweezers are used to extract "a very small piece" of the sample which is
placed at three locations on a microscope slide. An optical liquid with a known refractive index is then added to
the sample and a cover slip is placed on the sample to forrn a seal. The slide is then placed under a
polarized light microscope. The polarized lens of the microscope allows for adjustment of the light so
that it shines as an even beam of polarized light in a given direction. Tr. 439.
Potter testified that because asbestos is a crystalline structure, with its molecules formed along
chains, a polarized microscope allows for the measurement of this fibrous crystalline material. According
to Potter, the PLM method involves measuring the optical properties of the fibrous crystalline material,
the refractive index, i.e., how the light is bent, and the angle of extinction, which shows how much
polarized light has been deflected. These findings are then compared with the optical properties of
asbestos for a determination of the presence of that material. Tr. 440.7
Application of the PLM method obviously can be made only when samples of suspected RACM
have been taken and are available for laboratory analysis. It is undisputed that in this case KDHE
Inspector Branscum collected samples of suspected RACM with respect to only two of the six counts at
issue, and that no samples were collected by Inspector Brichacek. Accordingly, analysis of this case can
be broken down along the lines of those counts which are not supported by sampling and laboratory
analysis, and those counts which are.
A. Counts Not Supported By Sampling And Laboratory Analysis
The KDHE did not take field samples with respect to Counts I, II, III, and VI. Accordingly, as to
these counts EPA was unable to conduct PLM analysis so as to determine whether more than 1 percent
asbestos was present in the suspected RACM. Given the particular facts of this case, EPA's failure to
sample is a fatal omission.
As noted, 40 C.F.R. § 61.145(c)(6)(i) applies only to RACM, or regulated asbestos-containing
material. Section 61.141 provides that the presence of asbestos is to be determined by Polarized Light
Microscopy. Without application of the PLM method, there is no way of knowing whether the material
suspected by the KDHE inspectors to be RACM actually was regulated asbestos-containing material. In
that regard, Inspector Branscum admitted on cross-examination that he was not capable of determining
whether suspected asbestos-containing material actually contained asbestos by visual observation alone.
Tr. 222. Branscum further conceded that the existence of asbestos in material can be confirmed only
through Polarized Light Microscopy. Tr. 223, 229. See Tr. 268, 275-276 (Inspector Branscum unable
to determine whether pipe cladding contained asbestos because samples were not taken.) Similarly,
Inspector Brichacek didn't know whether the material that he observed at the Augusta facility on April 22,
1992, was RACM. Tr. 346. Likewise, L&C's expert witness, Richard Potter, testified that the presence
of asbestos in a given material can be determined only through laboratory analysis, and not by means of
visual observation. Tr. 429, 431. See U.S. v. Midwest Suspension And Brake, 49 F.3d 1197, 1204 (6th
Cir. 1995)(Government expert witness testifying that it is impossible to observe particulate asbestos
fibers with the naked eye due to their microscopic size.)
Nonetheless, despite the fact that sampling of suspected RACM was not conducted as to Counts I,
II, III, and VI, and despite the fact that the presence of asbestos cannot be determined on the basis of
visual observation alone, EPA still maintains that the material observed by the KDHE inspectors in this
case was RACM.
The Size Of The Project Argument
First, EPA argues that because the Augusta project involved the removal of more than 260 lineal
feet of friable asbestos, more than 160 square feet of friable asbestos, and more than 35 cubic feet of
friable asbestos off facility components, "the requirements of 40 C.F.R. § 61.145(b) and (c) applied to
WPL and L&C and this demolition activity, pursuant to 40 C.F.R. § 61.145(a)(1)." Compl. Br.at 6. In
other words, EPA submits that because the NESHAP workplace requirements applied to the Augusta
facility project due to the amount of friable asbestos being removed, it can be concluded that the material
observed by the KDHE inspectors in this case was regulated asbestos-containing material. This case is
not so easily resolved.
EPA is correct in arguing that the asbestos NESHAP work practice requirements set forth in
Section 61.145(c) apply in this case. In fact, L&C concedes that very point. The issue to be resolved
here, however, is not whether these NESHAP work practice requirements apply, but whether L&C
violated the work practice requirement set forth in Section 61.145(c)(6)(i).
Again, Section 61.145(c)(6)(i) requires that RACM be kept wet after its removal and until its
disposal. As noted above, with respect to Counts I, II, III, and VI, EPA has failed to show, through
Polarized Light Microscopy that the material involved in each of those counts was regulated asbestos-containing material. EPA's suspicions of suspected RACM are not enough. Moreover, the mere fact that
respondent was engaged in an asbestos removal project of a size sufficient to qualify for the application
of the asbestos NESHAP work practice requirements does not make the suspect material in this case
RACM.
Nor is a different result dictated by the case law cited by EPA. In nearly all of the district court
cases relied upon by the complainant, unlike the facts underlying Counts 1, II, III, and VI, the government
collected samples of suspected RACM as part of its inspection. The fact that EPA conducted sampling in
those cases, and that analysis of the samples showed the presence of friable asbestos, was acknowledged
by the courts. See U.S. v. MPM Contractors, Inc., 767 F.Supp. 231, 233 (D.Kan. 1990)("[s]amples
taken from all three sites contained well over the required one percent asbestos"); United States v. Sealtite
Corporation, 739 F. Supp. 464, 467-68 (E.D.Ark. 1990)("testing and analyses of materials ... revealed
the presence of at least one percent asbestos by weight"); U.S. v. Hugo Key And Son, Inc., 731 F.Supp.
1135, 1139 (D.R.I. 1989)("the material was friable asbestos as defined by the asbestos NESHAP"); and
U.S. v. Tzavah Urban Renewal Corp., 696 F.Supp. 1013, 1015 (D.N.J. 1988)("five samples taken from
the facility and ... all contained friable asbestos"). These cases actually support L&C's position that
PLM analysis is a necessary prerequisite to establishing the presence of regulated asbestos-containing
material.
Only in the case of U.S. v. Ben's Truck And Equipment, Inc., 25 ERC 1295 (E.D.Calif. 1986), did
the Court not specifically reference the fact that field samples of suspected RACM had been collected by
EPA. The Court simply did not mention sampling one way or the other. As such, Ben's Truck And
Equipment, Inc., lends little, if any, support to EPA's argument.
Finally, Inspector Branscum's supervisor, Inspector Brichacek, testified that he could not recall the
KDHE ever issuing a citation for failing to keep asbestos-containing material wet where the material
wasn't sampled. Tr. 355.
Accordingly, EPA's attempt to support Counts I, II, III, and VI on the basis of the amount of
friable asbestos which L&C contracted to remove from the Augusta facility must fail. EPA, and not
L&C, has the burden of proof on this issue. See Compl. Br. at 13. EPA's failure to sample for the
presence of asbestos ensured that it could not carry this burden given the facts of this case.
The DETI Survey
Next, EPA argues that enforcement samples were not necessary because sampling conducted at
the Augusta facility prior to the KDHE inspection already showed the presence of asbestos throughout the
facility. In making this argument, EPA is referring to the sampling performed for the Williams Pipeline
Company by Diversified Environmental Technologies, Inc. ("DETI"), prior to the time that L&C began
its asbestos abatement activities.
The purpose of the DETI survey was "to define the location of asbestos containing materials" at
the Augusta facility and "to assess and quantify the asbestos problem within the idled refining units and
areas." See Compl. Br., Attach. 1; see also, Tr. 42. As noted, the DETI survey was a preliminary step to
the asbestos abatement and demolition work performed at the facility by L&C. DETI compiled its
sampling results in a survey report dated May 11, 1990. Tr.44.
EPA's argument here is that inasmuch as the DETI survey detected quantities of asbestos at greater
than 1 percent throughout the Augusta facility, there was no need for Inspector Branscum "to continually
sample and analyze dry residue in the asbestos abatement areas where L&C was working or had worked."
Compl. Br. at 10. This argument is not persuasive.
First, EPA attempts to rely on the results of asbestos sampling even though it did not even seek to
introduce into evidence the laboratory results of the DETI survey. Despite the fact that several witnesses
referred to the DETI survey, EPA made no attempt to move this document into evidence at the hearing.
Instead, EPA sought to insert this information into the record by attaching the survey's laboratory
analysis results, "Appendix D. Analysis Data Table", to its post-hearing brief. L&C moved to strike this
attachment essentially arguing that if EPA wanted the DETI survey to be part of the record, it should
have offered the document into evidence at the hearing. By order dated May 30, 1996, L&C's motion to
strike the DETI survey laboratory results attachment was granted. Accordingly, the DETI survey results
cannot be relied upon for the purpose of showing that the suspect metal jacketing in this case actually was
asbestos-containing material. 8
Second, even assuming that the DETI survey showed the presence of substantial quantities of
asbestos as EPA represents, the testimony of DETI employee Rodney Hill establishes that the survey also
showed that there was almost as much non-asbestos material in the areas involved here as there was
asbestos-containing material. For example, Counts I, II, III, and VI all involve alleged violations
occurring in an area of the facility marked as Zone 39. See Exh. H-3. Rodney Hill, a DETI asbestos
consultant was called as a witness by EPA. Tr. 12. Hill stated that the DETI survey showed that 42
percent of the material sampled in Zone 39 did not contain asbestos. Tr. 65, 76; see Tr. 430.
More specifically, Hill testified that in the same zones where asbestos was found, there were
materials that did not contain asbestos. As Hill explained: "In some zones more, in other zones less." Tr.
45. In fact, Hill conceded that many of the pipelines in Zone 39 did not contain asbestos. Ibid.
Moreover, like Inspectors Branscum and Brichacek, and like Richard Potter, Hill testified that he could
not go on record stating what materials contained asbestos without the benefit of laboratory analysis. Tr.
45. Thus, despite the fact that the DETI survey was not introduced into evidence, to the extent that it was generally
referenced by the witnesses, particularly the testimony of Hill, the survey results are insufficient to
support a finding that the specific material observed with respect to Counts I, II, III, and VI was asbestos-containing material.
B. Counts Supported By Sampling And Laboratory Analysis
Of the six counts at issue in this case, only Counts IV and V are supported by KDHE field
samples taken at the Augusta facility. Specifically, Inspector Branscum took two samples on his June 25, 1992,
inspection and three samples on his August 28, 1992, inspection. All five samples were analyzed at the
KDHE laboratory in Topeka, Kansas. The samples were analyzed using polarized light microscopy in
conjunction with dispersion stating. See Compl. Ex. 2.9
The first sample taken on June 25, 1992, was taken from a piece of metal jacketing lying on the
ground near Zone 18. The results of the laboratory analysis showed this sample to be comprised of 70
percent chrysotile asbestos, 5 percent crocidolite asbestos, 5 percent cellulose, and 20 percent non-fibrous
material. The second sample taken on June 25 also was collected from a piece of metal jacketing lying on
the ground also near Zone 18. Tr. 244. The laboratory results for this sample showed that it was 60
percent chrysotile asbestos, 5 percent crocidolite asbestos, 5 percent cellulose, and 30 percent non-fibrous
material. Compl. Ex. 2.
Three samples were taken by Inspector Branscum on August 28, 1992, in Zone 39. Tr. 258, 262-263. One sample was collected from the floor of the boiler house. The laboratory results of this sample
showed the presence of 40 percent chrysotile asbestos, 20 percent amosite asbestos, 10 percent cellulose,
10 percent mineral wool, and 20 percent non-fibrous material. Another sample was taken from a valve on
the floor of the boiler house. This sample was made up of 30 percent chrysotile asbestos, 45 percent
amosite asbestos and 25 percent non-fibrous material. The last of these three samples was taken from
residue on the surface of metal jacketing lying on the ground to the North of the boiler. The laboratory
results of this sample were the same as those from the valve on the floor of the boiler house. Compl. Ex.
2.
EPA maintains that the samples collected on June 25, 1992, and August 28, 1992, establish that
the sampled metal jacketing was RACM. L&C challenges these KDHE laboratory test results on the
ground that the samples collected by Inspector Branscum were contaminated and, therefore, are invalid. 10
The Cross-Contamination Argument
L&C expert witness Richard Potter criticized the manner in which Inspector Branscum collected
the samples. The inspector testified that while he collected the samples with a pocket knife, he didn't
clean his knife between sample collections. The inspector stated that it was his practice not to clean the
knife in between samples when the material being sampled was homogenous. Insofar as this case is
concerned, Inspector Branscum conceded that he did not clean his knife in between his taking the two
samples on June 25, 1992. Tr. 238-239, 241.
Regarding this sampling procedure, Potter testified that Branscum's failure to clean the knife in
between taking samples was "completely inappropriate" and "probably guarantee[d]" that the second
sample was cross-contaminated by material remaining on the knife from the first sample. Tr. 437, 454.
Potter testified that the fear is that cross-contamination would lead to inaccurate laboratory results. Tr.
437. He explained that "the key to avoiding cross-contamination is to use clean tools, to use water, to use
cleaning between every step of the process." Tr. 434. Potter further explained: "...he's got material from
the first sample on the knife which he used to collect material from the second sample, so now he has
material from both samples on the knife and the chances are both of those ended up in the same
container." Tr. 454; see Tr. 455.
Despite Potter's challenge to the KDHE sampling procedures at the Augusta facility, Inspector
Branscum was not recalled as a witness to rebut this testimony and to defend his sampling technique.
Also, Inspector Brichacek, while called as a rebuttal witness, did not challenge Potter's theories of direct
and cross-contamination. This is so despite the fact that it was Inspector Brichacek who trained
Branscum on how to sample for asbestos. Tr. 330. 11
Given the testimony of the witnesses, it is established that Inspector Branscum did not clean his
knife in between taking samples on both June 25 and August 28. In addition, the testimony of Richard
Potter concerning cross-contamination raises substantial doubt as to the validity of the second sample
taken on June 25, and the second and third samples taken on August 28, so as to render those sample
results suspect. As such, the second sample taken on June 25 and the second and third samples taken on
August 28 are not sufficiently reliable to establish that L&C violated the asbestos NESHAP as alleged in
Counts IV and V.
In defending its sampling process, however, EPA maintains the laboratory results are valid because
the samples taken in this case were "homogenized" prior to the PLM analysis. Compl. Br. at 22. The
process of homogenization generally has been described as simply mixing the sample's contents before a
portion of the sample is extracted for PLM analysis. Tr. 473-474. EPA appears to argue that because of
this homogenization the laboratory analysts would not by "pure chance" select the contaminated portion
as Richard Potter had theorized.
The problem with EPA's argument concerning homogenization is that it lacks record support.
Here, Potter testified as to improper sampling methods employed by Inspector Branscum and as to the
resulting contamination of some of the samples taken. EPA's posthearing argument that homogenization
of the samples makes it improbable that any contaminated portion would be selected for PLM analysis
simply must fail in light of the testimony of Potter, the only asbestos expert to testify in this case.
Still, while these subsequent samples are suspect, the validity of the initial samples taken on June
25 and August 28, both of which showed the presence of greater than 1 percent asbestos, must
nonetheless be addressed. Even Richard Potter concedes that cross-contamination is not an issue with
respect to the first samples taken. Tr. 454.
The Direct Contamination Argument
L&C challenges Inspector Branscum's initial samples taken on June 25 and August 28, essentially
arguing that the inspector was sloppy in his sampling procedure and also that he failed to take necessary
safety precautions, such as misting the area of the suspected asbestos, before collecting the samples. In
addition, L&C believes that the inspector's inability to recall whether he had visited another inspection
site prior to inspecting the Augusta facility on August 28 is significant. Apparently, respondent is
suggesting that the inspector's knife could have been contaminated by sampling conducted at another
inspection site prior to his sampling at the Augusta facility on August 28.
On questioning from counsel for L&C, however, Inspector Branscum testified that it was his
practice to clean his knife after sampling at a site had been completed. In that regard, even though the
inspector didn't clean the sampling instrument in between samples believed to be homogeneous, the
inspector clearly stated that he did clean his knife "[a]t the end of taking a sample." Tr. 238-239.
Accordingly, to the limited extent that the record addresses this point, it establishes that it was Inspector
Branscum's practice to clean his knife after all the samples had been collected. L&C has not shown
otherwise. L&C's challenge to the initial samples taken on June 25 and August 28, on the ground that
they may have been contaminated, therefore, is wide of the mark.
Still, even though the samples taken on June 25 and August 28 were shown to contain greater
than 1 percent asbestos, EPA must show more to prove that L&C violated the asbestos NESHAP. As
explained earlier, in order to establish a violation of Section 61.145(c)(6)(i), EPA must show that the
RACM, or regulated asbestos-containing material, was not kept wet during its removal or disposal. As a
preliminary matter, before EPA can focus its case on showing that the suspect material was not kept wet,
it must first establish that the material was RACM. Section 61.141 provides that one of the ways to
establish that material is RACM is to show that the material is "friable asbestos material". Indeed, this is
what EPA alleges here. Section 61.141 provides a two-step approach for establishing friability.
The first step is to show by way of Polarized Light Microscopy that the material contains more
than 1 percent asbestos. EPA has done this with respect to the initial samples taken on June 25, 1992,
and August 28, 1992. The second step is to show that this material "when dry, can be crumbled,
pulverized, or reduced to powder by hand pressure." It is this step upon which EPA stumbles.
With respect to the initial sample collected on June 25, Inspector Branscum testified that this
sample "had no appearance of being wet in that there was no matting to it." Tr. 165. He added that the
sample gave no indication of containing moisture, that it didn't stick together, and that he "couldn't
squeeze any water out of it." Tr. 165-166. This testimony is insufficient to support a finding that the
initial sample collected on June 25, 1992, was friable. While the inspector may have been convinced that
the suspect material was not wet, he apparently did not investigate further to determine whether it also
could "be crumbled, pulverized, or reduced to powder by hand pressure." Without this determination,
EPA cannot show that the material was friable within the regulatory definition provided by Section
61.141. If EPA cannot prove that the material was friable, it also cannot prove that it was RACM. As
recited at the outset of this opinion, 40 C.F.R. § 61.145(c)(6)(i) requires that only RACM be kept wet
until disposal. Material which is not regulated asbestos material is not covered by this regulation.
A similar results obtains with respect to the August 28 sample. Inspector Branscum admitted that
he never physically touched the sample collected on that date in order to determine whether the material
was even wet or dry, let alone friable. Tr. 265-266. In light of the inspector's admission, EPA is unable
to point to any testimony, or other record evidence, establishing that the asbestos sampled on August 28
met the friability test of Section 61.141.
Given the fact that EPA has been unable to prove that the asbestos-containing material initially
sampled on both June 25, 1992, and August 28, 1992, was friable asbestos, it cannot prove a violation of
the NESHAP work practice requirements of 40 C.F.R. § 61.145(c)(6)(i). As a result, EPA cannot establish
the violations alleged in Counts IV and V.
ORDER
For the reasons set forth in this opinion, the Environmental Protection Agency's complaint
alleging that L&C Services, Inc., committed six violations of 40 C.F.R. § 61.145(c)(6)(i) is dismissed.
Carl C. Charneski
Administrative Law Judge
1 40 C.F.R. § 61.141 provides the following definition:
Regulated asbestos-containing material (RACM) means (a) Friable
asbestos material, (b) Category I nonfriable ACM that has become friable, (c)
Category I nonfriable ACM that will be or has been subjected to sanding,
grinding, cutting, or abrading, or (d) Category II nonfriable ACM that has
a high probability of becoming or has become crumbled, pulverized or
reduced to powder by the forces expected to act on the material in the
course of demolition or renovation operations regulated by this subpart.
Emphasis added.
2 WPC was named in the complaint as a respondent along with L&C. Prior to the hearing, however,
WPC entered into a settlement agreement with EPA.
3 The term "friable asbestos" is defined in 40 C.F.R. § 61.141 as follows:
Friable asbestos material means any material containing more than 1
percent asbestos as determined using the method specified in appendix
E, subpart E, 40 CFR part 763, section 1, Polarized Light Microscopy,
that, when dry, can be crumbled, pulverized, or reduced to powder by
hand pressure. If the asbestos content is less than 10 percent as determined
by a method other than point counting by polarized light microscopy (PLM),
verify the asbestos content by point counting using PLM.
4 The metal jacketing, or cladding, was strapped to the pipe and it wrapped all the way around the pipe
insulation. Tr. 91.
5 Exhibit H-3 is a map which sets forth the various work areas, or zones, of the Augusta facility. As
discussed, infra, Exhibit H-3 was prepared by a company hired by WPL to do a pre-demolition asbestos
survey of the Augusta facility. Tr. 42-43. Throughout the course of the hearing, this map was referenced
by the witnesses.
6 In addition to arguing that the subject material was not friable, L&C argues that it also was not
Category II asbestos-containing material likely to become friable. L&C Br. at 11. However, inasmuch as
EPA alleges only that the suspect material was friable, L&C's Category II argument need not be
addressed. See EPA Proposed Findings of Fact, Nos. 7 and 23; see also, EPA Reply Br. at 11 ("Here the
pipe insulation and other vessel insulation was never Category II material.")
7 As noted, EPA called no witnesses either to explain the PLM method, or to dispute the explanation
offered by L&C's expert witness.
8 EPA's failure to move the DETI survey into evidence denied L&C the opportunity to challenge the
sampling procedure followed, as well as the sampling results. For example, L&C expert witness Richard
Potter criticized the survey because it allegedly did not include the analysis of pipe that was insulated with
glass fiber or with other materials not suspected as containing asbestos. Tr. 430.
9 Polarized Light Microscopy, or PLM, was discussed earlier. The EPA witnesses, however, did not
explain the KDHE laboratory's reference to dispersion staining.
10 L&C raises other defenses such as a failure to establish a proper chain of custody for the samples. In
light of the holding in this case, these defenses are not addressed.
11 On direct examination, Inspector Brichacek did state that there was nothing that would lead him to
conclude that Inspector Branscum's sampling techniques were improper. Tr. 338. Brichacek, however,
provided no details to support this testimony.
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)