UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
IN THE MATTER OF )
)
B. J. CARNEY INDUSTRIES, INC. ) DOCKET NO. [CWA]-1090-09-13-309(g)
)
RESPONDENT )
DECISION ON REMAND (1)
On June 9, 1997, the Environmental Appeals Board issued a Remand Order (CWA Appeal
No. 96-2), 1997 NPDES LEXIS 1, in this case. The case was remanded to the presiding officer
"for the limited purpose of determining: 1) how much of the $167,000 economic benefit accrued
within the limitations period, and 2) an appropriate penalty based upon all the factors required to
be considered under the Clean Water Act § 309 (g) (3), including the amount of B. J. Carney's
economic benefit within the limitations period." On October 3, 1997, a hearing was held and the
parties filed proposed findings on the issues on November 20, 1997 and replies on December 10,
1997. Complainant's direct testimony was submitted in writing on July 31, 1997 and respondent
replied on August 12, 1997. Respondent examined complainant's witness, Kimberly A. Zanier,
on her direct testimony at the oral hearing session.
The EAB points out in the remand order that the Clean Water Act (CWA) and the
agency's penalty policy require recapture of a violator's economic benefit from noncompliance.
The EAB observed that assessing a penalty that reflects a violator's economic benefit of
noncompliance serves two purposes: A penalty which is at least as large as the economic gain
realized by the violator deters violations by taking away the economic incentive to violate the law
and it ensures a level playing field among competitors. The purpose of the remand proceeding is
to include in the penalty assessment the economic benefit the respondent received from
noncompliance. And, in keeping with the EAB's remand order, the economic benefit
determination will exclude the economic benefit respondent received outside the statute of
limitations period.
During the initial hearing the complainant determined that respondent's economic benefit
from noncompliance was $167,000. The EAB upheld the process which complainant followed in
deriving that benefit. Complainant initiated its analysis by adopting the capital costs and annual
maintenance and operation costs estimated by respondent's consultant, CH2M Hill. CH2M Hill
determined that the capital cost of an evaporator to respondent in 1986 would have been $62,550
and that the annual maintenance and operation cost in 1986 would have been $1,550.
Complainant selected January 25, 1984 as the date on which respondent was in violation of the
pollution control requirements. In order to estimate the full economic benefit to respondent from
the time respondent was noncompliant, complainant deflated the 1986 CH2M Hill estimates to the
date of noncompliance in 1984. Applying a 16 % discount rate, complainant estimated that by the
time of the initial hearing in 1993, the respondent had derived an estimated economic benefit of
$167,000. (2)
The EAB held that complainant's estimate was inaccurate because it included economic
benefit derived by respondent during part of 1984 and 1985 when the statute of limitations
precluded enforcement against respondent for any violations of the pollution control
regulations. (3) The EAB remanded the hearing record to cure the problem presented by the
statute of limitations. In its remand instructions the EAB directed that the full economic benefit
should be reasonably approximated by "starting with [complainant's] calculation of $167,000, and
subtracting from it that portion of the benefit that accrued outside the five-year [statutory]
limitations period."
The issue had to be remanded, the EAB concluded, because it could not determine from
the record how much of the benefit occurred after October 1985 when the statute of limitations
did not bar enforcement of the Clean Water Act. The EAB believed from its review of the
existing record that it was possible, after excluding the "pre-limitations" period, the economic
benefit to the respondent would exceed the $125,000 maximum penalty permitted under the Clean
Water Act.
The EAB considered at length respondent's arguments about the discount rate used by
complainant. It concluded that there was no record support for respondent's contention that the
discount rate was unreasonable. Moreover, the EAB held that complainant could select a
discount rate as of the date of noncompliance, despite the fact that the pollution control
regulations could not have been enforced on that date because of the statute of limitations.
The EAB also held that the record did not support the respondent's claim that it spent
$240,000 in complying with the zero discharge requirement. The EAB found that, nevertheless,
respondent did benefit from that claim when Judge Head assessed the penalty. The EAB
determined that Administrative Law Judge Head gave weight to respondent's asserted compliance
efforts in two ways: First, Judge Head concluded that the violations resulted in only minor harm
to the environment and, second, he reduced the penalty by 50% because, among other reasons,
respondent exhibited good faith efforts at compliance. As a result of this, the EAB held, there
should not be any additional adjustment in the economic benefit based on respondent's claims of
compliance. The EAB also directed that the presiding officer, in assessing the penalty, should be
guided by the principle that compliance with the law is the primary objective of the environmental
statutes and regulations and that penalties play an important role in deterring violations.
Consideration of the justice, or equitable, factor by the presiding officer, the EAB stated, is
warranted only if the evidence of environmental good deeds is clear and unequivocal, and the
circumstances asserted are such that a reasonable person would easily agree that not giving some
form of credit would be a manifest injustice.
The Evidence On Remand
The complainant submitted additional testimony from Kimberly A. Zanier. Zanier is an
expert in economic benefit analysis and her testimony was the basis of the economic benefit
findings and conclusions at the initial hearing. Zanier calculated that respondent's economic
benefit from January 26, 1984, the date of noncompliance, through July 1, 1997 the hypothetical
date the penalty was paid, was $266,917. She estimated the economic benefit that accrued from
January 26, 1984, the date of noncompliance, through October 12, 1985, the date when the
statute of limitations no longer prohibited enforcement, to be $14,689. That amount represents
the difference between the required investment in 1984 of $48,158 and the total economic benefit
to respondent as of October 12, 1985 of $65,158. Zanier subtracted $14,689 from the total
economic benefit of $266,917 to arrive at the enforceable economic benefit from October 12,
1985 to July 1, 1997, of $252,228. If $14,689 is subtracted from the $167,242 economic benefit
found by Zanier at the initial hearing, the amount of economic benefit derived by the respondent
through October 19, 1993 would be $152,553.
Zanier applied the same set of variables as she did originally to determine economic benefit
from noncompliance outside the statute of limitations period. (4)
Her estimate of the 1984 Cash
Flow included investment at $48,158, the operation and maintenance costs of $687, and the
opportunity cost of capital of 1.11860. (Zanier derived her estimate of the opportunity cost of
capital by applying the following in 1984: 1984 Debt 6.59% (after tax) times 50.00% (weight)
1.11860.) According to Zanier, respondent received an accumulated economic benefit as of 12-84 of $54,638. Zanier estimated the accrual of benefit to respondent in 1984 was $6,480
($54,638 [which is the end of year accumulation] minus $48,158 [which is the beginning of period
capital requirement]). Her calculations of economic benefit as of 12-85 were as follows:
1985 Beginning of Year Cash $54,638
Current Year Cash Flow Adjustment $ 1,522
___________
Adjusted Cash Flow $56,160
Opportunity Cost of Capital 1.1601
___________
Economic Benefit As Of 12-85 $65,151
Zanier then adjusted the 1985 amount excluding the amount from 1-1-85 through 10-12-85. The
end of the year accumulation of economic benefit was $10,513 ($65,151 minus $54,638
$10,513). Since 78.0822 % (285 days [1-1-85 through 10-12-85]) of the benefit had to be
excluded because of the statute of limitations, Zanier excluded $8,209 of the economic benefit
accrued to the respondent in 1985. Zanier concluded that the amount to be excluded from
complainant's economic benefit calculations should be $6,480 for 1984 and $8,209 for 1985. Zanier then provided estimates of the accrued economic benefit to the respondent in every
year through July 1, 1997 as follows:
Economic Benefit to Respondent by Year
12-86 $77,380
12-87 $82,622
12-88 $89,693
12-89 $102,906
12-90 $117,330
12-91 $133,105
12-92 $151,000
10-19-93 $167,242
12-93 $171,303
12-94 $194,334
12-95 $220,462
12-96 $250,104
7-1-97 $266,917
The complainant estimates that the economic benefit to respondent of noncompliance from
10-12-85 to 10-19-93 is $152,553 and from 10-12-85 to 7-1-97 is $252,228. These amounts
exclude the benefit derived in 1984 and 1985 which were barred from recapture because of the
statute of limitations.
The respondent submits proposed findings about the gravity of its violations and the
factors it believes ameliorate the penalty assessment because of gravity. The initial decision was
largely not challenged in that regard and the EAB did not reverse the findings and conclusions of
the presiding officer in those areas. The EAB directed the presiding officer not to retry matters
already decided and reviewed. For that reason, no further consideration will be given to the
gravity factor.
Respondent concedes that the economic benefit it received from noncompliance was in
excess of the statutory maximum of $125,000. Nevertheless, respondent maintains that
complainant's exclusion of $14,689 from its estimation of economic benefit during the statute of
limitation period, from January 26, 1984 through October 12, 1985, was incomplete because there
was "compounding" of that amount in the years after October 12, 1985 in complainant's analysis.
Respondent has not demonstrated how complainant's analysis is inconsistent with the EAB's
finding about the application of the statute of limitation in this case. Respondent's argument is
also inaccurate in its characterization of complainant's estimate.
The statute of limitations in this case prohibits enforcing a rule or policy during the period
before October 12, 1985. It also requires that any economic benefit to respondent outside the
limitations period must be excluded from the determination of total economic benefit. It does not
mean that economic benefit accrued after October 12, 1985 may not be affected by factors arising
before that date during the period of noncompliance. The EAB explained that "[t]he statute of
limitations does not preclude a company from obtaining a benefit, it only precludes the Agency
from recovering that portion of the benefit that was realized more than five years before the
complaint was filed, outside the limitations period." The evidence demonstrates that the benefit
derived before October 12, 1985 was excluded. Respondent has not shown that the benefit
calculated after that date is not a reasonable approximation of its economic benefit from
noncompliance.
Respondent makes two other arguments about the complainant's economic benefit
showing which it claims undermine the reasonableness of complainant's estimate of economic
benefit. It argues that complainant did not exclude operating and maintenance costs after
respondent stopped operating the facility in 1990 and that a different weighted average cost of
capital rate should have been used after October 1993 since it was not established during the
initial hearing that the weighted average cost of capital rate used before that date would be
applicable thereafter. Complainant responds that it did exclude operating and maintenance costs
after 1990, as appendix A to Zanier's testimony clearly indicates. Respondent's second argument
is immaterial to computing the economic benefit in this proceeding. No matter what average cost
of capital rate complainant used after 1993, it would not reduce the economic benefit below the
statutory maximum since the maximum benefit had been received by respondent by 1993.
In the initial decision, Judge Head held that respondent should pay a $9,000 penalty. That
finding, insofar as it was appealed, has been reviewed by the EAB and will not be reconsidered in
this remand proceeding. The focus of the penalty assessment in this decision is on the economic
benefit derived by respondent from noncompliance, a factor Judge Head did not weigh in his
initial decision. The remand record establishes that after October 12, 1985, the respondent
realized an economic benefit in excess of the statutory maximum of $125,000. The respondent
under the gravity criteria must already pay a penalty of $9,000. However, because of the
statutory maximum, the full penalty respondent must pay is only $125,000.
Respondent argues that justice, or equitable, considerations require reducing the penalty
in this proceeding because it was badly treated by the complainant and because it undertook
compliance efforts. Those are issues that have already been reviewed. The EAB found that "the
Region exercised great patience and restraint by working with [Carney and the City of Sandpoint]
in an effort to achieve compliance." Respondent's argument that it has been denied justice is
contrary to the facts found by the EAB. The EAB explained that:
For almost five years, the Region urged Sandpoint to fulfill [its enforcement]
responsibility, all the while repeatedly advising Sandpoint about the Region's
concern that B. J. Carney was not complying with the applicable standard. It was
not until the Region was convinced that Sandpoint would not exercise its
enforcement authority that the Region initiated this action.
The Board, after reviewing the penalty assessment in the initial decision, concluded that it would
not be "appropriate in this case based upon any past expenditures on compliance costs" by
respondent to adjust the economic benefit downward.
The complainant accurately points out that all of the arguments that respondent makes in
its brief were made and rejected by the EAB in its opinion. There are some additional arguments
that respondent now makes about the initial hearing which it failed to raise initially before the
EAB. Those arguments are beyond the scope of the remand and will not be considered. Finally,
the EAB points out that justice seldom requires reducing a penalty. A good deed warrants a
reduction in penalty only if the evidence of the good deed is "clear and unequivocal" and " the
circumstances must be such that a reasonable person would easily agree that not giving some form
of credit would be a manifest injustice." There are no facts asserted by respondent in this
proceeding that meet that test. The record establishes that a just and reasonable penalty is the full
statutory maximum of $125,000.
ACCORDINGLY, IT IS ORDERED that respondent B. J. Carney IS ASSESSED a civil
penalty of $125,000 for the violations of the Clean Water Act.
Payment of the full amount of the civil penalty assessed must be made within sixty (60)
days of the service date of the final order by submitting a certified check or cashier's check
payable to Treasurer, United States of America, and mailed to:
U. S. EPA, Region X
(Regional Hearing Clerk)
Mellon Bank
P.O. Box 36090M
Pittsburgh, PA 15251
A transmittal letter identifying the subject case and the EPA docket number, plus
respondent's name and address must accompany the check.
Failure by respondent to pay the penalty within the prescribed statutory time frame after
entry of the final order may result in the assessment of interest on the civil penalty. 31 U.S.C. §
3717; 4 C.F.R. § 102.13.
Pursuant to 40 C.F.R. § 22.27 (c), this initial decision shall become the final order of the
Environmental Appeals Board within forty-five (45) days after its service upon the parties and
without further proceeding unless (1) an appeal to the Environmental Appeals Board is taken
from it by a party to this proceeding or (2) the Environmental Appeals Board elects, sua sponte,
to review this initial decision. If an appeal is taken, it must comply with § 22.30. A notice of
appeal and an accompanying brief must be filed with the Environmental Appeals Board and all
other parties within twenty (20) days after this decision is served upon the parties.
______________________________________
Edward J. Kuhlmann
Administrative Law Judge
January 5, 1998
Washington, D. C.
1. The complainant was represented in the remand proceeding by
Mark A. Ryan, Esq. and the respondent was represented by Jeffrey
L. Supinger, Esq. Administrative Law Judge Daniel M. Head
issued the initial decision on March 11, 1996. Judge Head had
retired by the time the EAB issued its remand order and, therefore,
the case was reassigned.
2. The EAB found that complainant had assumed in its calculation of
avoided costs that respondent had taken some of the compliance
steps identified in the CH2M Hill report. This assumption was
made even though the hearing record reflected that respondent took
none of the steps recommended in the CH2M Hill report. Overall,
the EAB concluded, complainant's calculations resulted in a
conservative estimate of avoided costs.
3. In making that finding, the EAB found that the presiding officer had
raised the limitations issue in his decision and that the parties had
not had an opportunity to address the issue. The complainant
requested that the EAB remand the case in order that it might
demonstrate what economic benefit the respondent enjoyed outside
the statutory limitations period.
4. Zanier applied the following factors in her analysis: The date on
which noncompliance began was 1-26-84, the date on which the
statute of limitations did not bar enforcement was 10-12-85, the
date on which respondent ceased operation was 7-1-90, a
hypothetical date that respondent paid the penalty 7-1-97, capital
investment avoided expressed in 1986 dollars was $62,500, annual
operating and maintenance costs avoided in 1986 dollars $1,550,
salvage value of equipment as of 7-1-90 was $0, inflation rate for
capital expenditures varies annually from 1.234% to 3.52%,
weighted average cost of capital was 16.01%, tax rates- Idaho
which vary from 0 to 8%, Federal rates of tax which vary from 0 to
48%, and resulting benefit $252,228.
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)