UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
In the Matter of )
)
Cytec Industries, Inc., ) Docket No. V-W-009-94
)
Respondent )
INITIAL DECISION
Pursuant to Section 3008(a) of the Resource, Conservation and
Recovery Act, 42 U.S.C. §6928(a), the Respondent Cytec Industries,
Inc., is assessed a total civil penalty in the amount of $36,500
for operating its Boiler #3 without an automatic hazardous waste
feed cutoff system, in violation of 40 CFR §266.103(g), and failing
to conduct Subpart BB monitoring of the equipment leading to the
boiler, as required by 40 CFR §266.103(a)(4)(viii).
Appearances
For Complainant:
Michael J. McClary, Esq.
Assistant Regional Counsel
U.S. EPA Region 5
Chicago, Illinois
For Respondent:
Kirk M. Minckler, Esq.
Sonnenschein Nath & Rosenthal
Chicago, Illinois
Proceedings
The Region 5 Office of the United States Environmental
Protection Agency (the "Complainant" or "EPA") commenced these
proceedings by filing an administrative Complaint, dated February
23, 1994, against Cytec Industries, Inc., (the "Respondent" or
"Cytec").(1) The Complaint charged Respondent with a series of
violations of the Hazardous Waste Burned in Boilers and Industrial
Furnaces ("BIF") regulations, 40 CFR Part 266, Subpart H, and the
interim status standards for owners and operators of hazardous
waste management facilities, 40 CFR Part 265, at its chemical
manufacturing facility in Kalamazoo, Michigan. Violations of these
regulations, which were promulgated pursuant to Section 3004(q) of
Resource Conservation and Recovery Act ("RCRA"), 42 U.S.C. §6924(q),
are subject to the assessment of civil penalties under the
authority of RCRA §3008(a)(1). The Complaint proposed a civil
penalty of $417,600 for the alleged violations, and also seeks
issuance of a compliance order on Respondent. In its Answer of
April 1, 1994, Cytec denied most of the material allegations of the
Complaint, raised certain defenses, and requested a hearing.
In an order dated July 31, 1996, the undersigned
Administrative Law Judge ("ALJ") ruled on the parties cross-motions
for accelerated decision. The Order entered the following rulings:
- dismissed Count I of the Complaint (failing to have an
adequate waste analysis plan, contingency plan, and closure plan
as required by 40 CFR §§266.103(a)(4), 265.13, 265.54, and
265.112), due to the Complainant's failure to comply with the
Paperwork Reduction Act, 44 U.S.C. §3501 et seq;
- barred the assessment of civil penalties under Count II
(waste analysis plan failing to adequately specify a test method
and frequency for the review or repetition of the initial waste
analysis, as required by 40 CFR §§265.13(b) and 266.103(a)(4)), for
failure to comply with the Paperwork Reduction Act, but denying
accelerated decision on liability and preserving this count for the
hearing with reference to the compliance order;
- dismissed Count IV, which alleged Cytec failed to adequately
specify a limit for the total feed rate of ash in its boiler's
certification of compliance, in violation of 40 CFR §266.103(c)(1);
- denied accelerated decision with respect to Count III,
alleging Cytec failed to monitor equipment for leaks, in violation
of 40 CFR §§266.103(a)(4)(viii), 265.1052, and 265.1057;
- granted accelerated decision finding Cytec liable for the
violation alleged in Count V, the failure to operate with an
adequate automatic waste feed cutoff system, in violation of 40 CFR
§266.103(g), reserving the issue of penalty for hearing; and,
- denied accelerated decision on Count VI, alleging Cytec
failed to adequately record feed rates of ash, total chlorine and
chloride to its boiler, in violation of 40 CFR §§266.103(b)(5),
266.103(c)(4), 266.103(j), and 266.103(k).
The Order thus reserved the following issues for hearing:
liability under Count II; liability and penalty under Count III;
penalty under Count V; and liability and penalty under Count VI.
These rulings had the effect of reducing the maximum total proposed
civil penalty to $261,575, apportioned as follows: Count III -
$199,500; Count V - $61,075; and Count VI - $1000.
The hearing in this matter convened on October 22 through
October 24, 1996, in Chicago, Illinois. The Region presented three
witnesses, and the Respondent presented two witnesses. The record
of the hearing consists of a stenographic transcript of 663 pages,
and 43 numbered exhibits, of which 38 were received into evidence.
The parties each submitted post-hearing briefs and reply briefs.
The record of the hearing closed on February 18, 1997, upon the
ALJ's receipt of the reply briefs.
Findings of Fact
1. Cytec operates a chemicals manufacturing facility at 2715
Miller Road in Kalamazoo, Michigan. The Kalamazoo plant
manufactures industrial chemicals used in the paper, mining, water
treatment, surface coating, and rubber industries. The plant's
butylated melamine resins manufacturing process produces a light
liquid material known as "spent alcohol" or "waste alcohol." (Ex.
20, p. B-2).(2)
2. Cytec's spent alcohol waste consists of approximately 40%
n-butanol, 40% methanol, 20% water, and trace amounts of
formaldehyde. Spent alcohol is classified a RCRA hazardous waste
by virtue of its ignitability, and assigned EPA Hazardous Waste
Number D001. It has a flashpoint of about 140F. Cytec's spent
alcohol is a relatively clean fuel. The waste analysis of this
material found non-detectable levels of all BIF parameters of
concern, except for lead and total chlorides. These were detected
at trace levels that did not raise any regulatory concern when
emissions were tested for the boiler's certifications of
precompliance and compliance. The fuel oil #6 that is sometimes
burned with the spent alcohol in the boiler contains generally
higher levels of BIF constituents than the hazardous waste,
particularly with respect to ash and chlorides. (Exs. 2, 3, 9; Tr.
101, 633).
3. Cytec operates Boiler #3 (the "boiler") to supply steam
that is used to provide plant heat and energy for the plant's
chemical processes. Boiler #3 is a 60,000 gallons per hour,
watertube type steam boiler. Cytec burns the spent alcohol as a
supplemental fuel in the boiler in conjunction with either natural
gas or No. 6 fuel oil. In Mode A operation, Cytec burns 95.2% No.
6 fuel oil and 4.8% spent alcohol. In Mode B, Cytec burns 81.5%
natural gas and 18.5% spent alcohol. Cytec operates in Mode B most
of the time, and uses the fuel oil only when natural gas is
unavailable. (Ex. 20, p. 2 of 5; Ex. 35, p. 2).
4. After its generation in the plant's manufacturing process,
the spent alcohol is transported in pipes to a 12,000-gallon
accumulation tank. Cytec stores the spent alcohol in that tank
before transporting it in feed lines to the boiler. Cytec stores
the spent alcohol in the tank for less than 90 days before it is
combusted in the boiler. (Ex. 20, p. C-54a).
5. The 90-day accumulation tank is located outdoors on a
concrete containment pad on the facility grounds. Waste feed lines
lead from the tank to the boiler, which is housed in a concrete
block building some 40 meters from the tank. There are pumps,
valves and flanges on the feed lines that control and regulate the
flow of spent alcohol from the tank to the boiler. The waste feed
lines are one inch in diameter near the tank, and narrow to one
half inch at the feed into the boiler. (Tr. Greene). This
equipment is in contact with the spent alcohol hazardous waste.
(Tr. 473-476; Exs. 18, 34).
6. There is also a currently unused pipe system that extends
from the 12,000-gallon tank to a truck loading dock. Cytec
formerly used that system to transport the spent alcohol to trucks
where it was loaded for offsite disposal. (Tr. 478; Ex. 34).
7. The Cytec facility received an operating license from the
Michigan Department of Natural Resources ("MDNR"), under the
Michigan Hazardous Waste Management Act (Act 64), on January 11,
1989, concurrent with an EPA RCRA permit. This license authorized
Cytec to operate a hazardous waste drum storage unit at the
Kalamazoo facility. The drums stored used waste solvents for up to
one year. The license expiration date was January 11, 1994. (Ex.
36).
8. The EPA promulgated the Hazardous Wastes Burned in Boilers
and Industrial Furnaces ("BIF") rules, 40 CFR §266, Subpart H, on
February 21, 1991. These rules brought the burning of hazardous
wastes in boilers, such as Cytec's Boiler #3, into the RCRA
regulatory scheme. The BIF regulations established interim status
standards with which newly regulated boilers were required to
comply, effective August 21, 1991. (Ex. 25). In February 1992,
Cytec submitted its application for a RCRA permit renewal and
modification to add its boiler as a regulated unit. (Exs. 20, 21).
9. Pursuant to 40 CFR §266.103(b), Cytec submitted its
Certification of Precompliance ("COP") to the EPA on August 21,
1991. Cytec submitted its Certification of Compliance ("COC") on
March 4, 1993. These documents certified that, in test burns under
specified conditions, the operation of Boiler #3 discharged air
emissions that complied with the emission limits for particulates,
chlorine, metals, and other parameters set forth in the BIF rules.
The COC also established the boiler's maximum operating limits for
such parameters as total hazardous waste feed rate; feed rates for
ash, chlorides, total chlorine, and metals; carbon monoxide
concentration; steam production rate; combustion chamber
temperature; and flue gas temperature. The COC established the
boiler's operating limits using the adjusted Tier I model for
calculating emission rates. (Ex. 2, 3, 39).
10. Jae B. Lee, a boiler inspector for the Region, conducted
a routine annual inspection of Cytec's facility on April 29-30,
1993. Mr. Lee visually inspected the boiler and associated
equipment, and reviewed the COC and other documents supplied by
Cytec. He was accompanied during the inspection by Robert L.
Greene, Ph.D., Cytec's manager for environmental compliance. In
his inspection report Mr. Lee noted several "inspection findings
and observed problems." He discussed the inspection results in an
exit interview with Dr. Greene. (Exs. 4, 5).
11. At the exit interview, Mr. Lee definitively informed Mr.
Greene of one putative violation -- the lack of an automatic
hazardous waste feed cutoff ("AWFCO") keyed to the maximum feed rate
of total hazardous waste as established in the COC. (Ex. 5, p. 4).
At the time of the inspection, Cytec's boiler had a system that
automatically cut off the waste feed upon detecting deviations from
the COC's limits for carbon monoxide concentration, combustion
chamber temperature, spent alcohol feed pressure, and general
system failure. The flow of spent alcohol into the boiler was
restricted by the size of the orifice, which limited the flow to
180 gallons per hour, but there was no AWFCO for total hazardous
waste flow. (Ex. 42, p. 12; Tr. 576-580).
12. From the date of Cytec's submittal of its COC on March 5,
1993, until Mr. Lee's inspection on April 29-30, 1993, Cytec burned
hazardous wastes on a total of 23 days. (Tr. 362). On May 4,
1993, several days after Mr. Lee's inspection, Cytec installed a
hazardous waste feed interlock that automatically cuts off the flow
of hazardous waste when it exceeds a rate of 125 gallons per hour.
Cytec informed the Region of the installation of the AWFCO in a
letter dated June 11, 1993, that responded to the Region's
information request following the inspection. (Ex. 8, p. 14).
13. One of the problems noted by Mr. Lee concerned Cytec's
procedures for monitoring its boiler equipment for leaks. (Ex. 5,
p. 4). Cytec visually inspected its spent alcohol tank system for
leaks on a daily basis, following the procedures in Subpart J of 40
CFR Parts 264 and 265, applicable to "Tank Systems." This daily
visual Subpart J monitoring encompassed the tank itself, and all
ancillary equipment, including piping, pumps, valves, and flanges
between the process line that generated the waste and the boiler.
(Tr. 579). Cytec did not conduct monitoring under Subpart BB of 40
CFR Part 266, entitled "Air Emission Standards for Equipment Leaks."
That subpart requires equipment to be monitored for leaks by using
a portable instrument that is calibrated to detect leaks of
volatile organic compounds.
14. In July 1996, Cytec conducted a leak detection procedure
on its equipment including the tank system and boiler feed lines,
using a Vapor Analyzer as specified in then-proposed Subpart CC of
40 CFR Part 265. Subpart CC, applicable to tanks, was finally
adopted, after repeated delays, on December 6, 1996. 40 CFR
§255.1080 et seq. That monitoring detecting two small leaks, at
rates far below the 10,000 ppm standard in Subpart BB, which were
quickly repaired. (Tr. 592-594).
15. Another possible problem noted in Mr. Lee's inspection
report concerned Cytec's waste analysis plan. Mr. Lee noted that
the specified frequency for repeating a chemical analysis of
Cytec's hazardous waste may be inadequate. (Ex. 5, p. 4). Cytec's
waste analysis plan provides for recharacterization of the waste
alcohol "if process or operational changes occur." (Ex. 36, p. C-53). This has not occurred at least since 1989. (Ex. 35, p. 3).
16. The Region has charged Cytec with failing to specify a
test method for ash as part of its waste analysis plan. The test
method for ash was omitted in Cytec's table of test methods
submitted with its Class 3 permit modification application to the
EPA on February 17, 1992. (Ex. 6, Table C.4, p. C-57). A test
method for ash, ASTM D482, was, however, cited in Cytec's March
1993 COC. (Ex. 39, Appendix 3).
17. Another possible compliance problem noted by the Region
concerned Cytec's method of monitoring and recording the feed rates
of ash, chlorine, and chlorides during operation of the boiler, to
ensure conformance with the limits in the COC. At the time of Mr.
Lee's inspection, Cytec monitored the feed rate of spent alcohol
and the main fuel (natural gas or fuel oil #6) continuously on a
circular chart recorder. (Ex. 8, Waste Alcohol Recording Chart).
This method yielded separate circular graphs showing these flow
rates throughout each day (24-hour period) that hazardous waste was
burned. This method did not simultaneously provide values for the
feed rate of constituents such as ash, chlorine, and chlorides.
Those values could be readily calculated, however, by multiplying
the flow rate of the spent alcohol by the known constant
concentrations of those constituents. (Tr. 344-345).
18. Cytec performed calculations of these feed rates on a
daily basis after Mr. Lee's inspection, in response to the Region's
RCRA §3007 information request sent to Cytec on May 12, 1993. (Exs.
7, 12). Since the concentrations of ash, chlorine and chlorides
in the waste alcohol were very low or non-detectable, at no time
did the feed rates for those constituents approach the COC limits.
(Ex. 9, p. 6-9; Ex. 12, monthly reports). In April 1993, Cytec
installed a computer monitoring system that instantaneously
monitors and records the feed rates of those constituents. (Ex. 35,
p.4).
19. Mr. Lee conducted his regular annual inspections of
Cytec's Kalamazoo facility in 1994. He was replaced by John
Gaitskill, who conducted the 1995 inspection of Cytec. Mr.
Gaitskill conducted his next inspection of Cytec on October 10,
1996, less than two weeks before the start of the hearing in this
matter. He had originally been scheduled to conduct the Cytec
inspection on October 25, 1996, just after the scheduled conclusion
of the hearing. Mr. Gaitskill moved up the date of the inspection
on the request of the Region's counsel in the Cytec proceeding.
The Region then proffered Mr. Gaitskill as a witness in the
hearing, and offered photographs he took into evidence. The
inspection was conducted with the consent of Cytec's manager, Mr.
Greene. However, neither Respondent nor the ALJ was aware that Mr.
Gaitskill would be offered to testify in the hearing until the
Region provided a motion for a supplemental prehearing exchange to
that effect just before the start of the hearing. The ALJ allowed
the evidence to be presented, subject to any showing of prejudice
to Cytec.
Discussion
The following sections will discuss Cytec's liability and
appropriate civil penalties, if any, for each remaining count in
the Complaint.
- Count II - Frequency of Waste Reanalysis
Count II of the Complaint charges Cytec with failing to
develop an adequate waste analysis plan with respect to specifying
a test method for ash and a frequency for repeating the initial
waste analysis, as required by 40 CFR §265.13. Although no penalty
can be assessed for any violation under this count, due to the
EPA's failure to comply with the Paperwork Reduction Act, liability
remains an issue in the context of the proposed compliance order.
The interim status standards, at 40 CFR §265.13(b)(2), require
the owner or operator of a facility to specify the test methods
which will be used to test for each parameter that will provide the
necessary information to manage the hazardous waste. One of those
parameters for Cytec's waste alcohol is its ash content. Cytec's
original table listing its test methods for metals and chlorides,
submitted with its application to EPA for a Class 3 permit
modification on February 17, 1992 (Ex. 6, Table C.4, p. C-57),
omitted a citation to its test method for ash. However, Cytec did
specify its test method for ash, ASTM D482, in its COC of March
1993. (Ex. 39, Appendix 3, Finding of Fact or "FF" #16). The
Region's witness, Mr. Cunningham, testified that Cytec has
specified a test method for ash. (Tr. 390). The Region has not
argued in its post-hearing briefs that Cytec remains in violation
of this requirement. Therefore, Cytec is found in compliance with
40 CFR §265.13(b)(2) with respect to adequately specifying a test
method for ash. There is no need for a compliance order to that
effect.
Count II also alleges that Cytec failed to adequately specify
a frequency for repeating its waste analysis. The standards, at 40
CFR §265.13(a)(3), provide as follows:
"The analysis must be repeated as necessary to
ensure that it is accurate and up to date. At a minimum,
the analysis must be repeated:
(i) When the owner or operator is notified, or has
reason to believe, that the process or operation
generating the hazardous wastes . . . has changed; . . ."
The regulation further requires the waste analysis plan to specify
"[t]he frequency with which the initial waste analysis of the waste
will be reviewed or repeated to ensure that the analysis is
accurate and up to date." 40 CFR §265.13(b)(4).
Respondent's plan states only that the waste analysis will be
repeated "if process or operational changes occur." (FF #15).
Cytec does not specify a calendar-based frequency or regular
interval for repeating or reviewing its initial analysis of the
spent alcohol waste. Cytec's methylated resins process that
generates the spent alcohol has not changed since 1989.
The Region contends that §265.13 requires that the waste
analysis plan specify a calendar-based frequency for reviewing or
repeating the waste analysis. However, the plain language of the
regulation only requires that, at a minimum, the waste be
reanalyzed when the owner or operator has reason to believe that
the process generating the waste has changed. Cytec's waste
analysis plan tracks the regulation precisely in this respect.
The Region apparently believes that it would be preferable to
reanalyze the waste on a regular annual basis. The EPA recommended
that course in a workshop held on the BIF rules in January 1995.
In response to a question concerning a waste stream that does not
change, the EPA representative responded that annual reanalysis was
recommended, but that less frequent reviews could be worked out
with the region or state. (Ex. 17, p. B-3). This recommendation
cannot however substitute for the language of the rule itself for
the purposes of enforcement. The EPA could easily have required
reanalysis of the waste annually or at some other regular interval
by simply saying so in the rule.
This is not a situation where the language of the regulation
is susceptible to different reasonable interpretations in which
some deference could then be given to the interpretation of the
Agency. Here the regulation in effect defines "frequency" as, at
a minimum, whenever the owner or operator has reason to believe the
waste generating process has changed. This regulatory directive
supersedes the dictionary definition cited by the Region. Cytec's
waste analysis plan complies with the minimum requirement set forth
in §256.13 with respect to specifying a frequency for repeating its
waste analysis. Therefore there is no need for a compliance order
on this issue.
- Count VI - Monitoring and Recording Feed Rates of Ash and Chlorine/Chlorides
Count VI of the Complaint charges Cytec with failing to
adequately monitor and record the feed rates of ash, total
chlorides, and chlorine to its boiler. The primary regulation at
issue here is 40 CFR §266.103(j)(1), which states:
"The owner or operator must monitor and record the
following, at a minimum, while burning hazardous waste:
(i) Feed rates and composition of hazardous wastes,
other fuels, . . . , and feed rates of ash, metals, and
total chloride and chlorine as necessary to ensure
conformance with the certification of precompliance or
certification of compliance."
Under this count, the Region also cites Respondent in violation of
40 CFR §§266.103(b)(5), 266.103(c)(4), and 266.103(k). Sections
266.103(b)(5) and 266.103(c)(4) address the methods for monitoring
and recording these and other parameters during compliance testing
for the purposes of establishing operating limits in completing the
facility's certifications of precompliance and compliance ("COP" and
"COC"), respectively. Section 266.103(k), entitled Recordkeeping,
states "[t]he owner or operator must keep in the operating record
of the facility all information and data required by this section
until closure of the boiler or industrial furnace unit."
Cytec filed its COC in March 1993, which superseded the COP,
which had been filed in August 1991. The methods described in the
regulations for monitoring the parameters listed in §266.103(b)(3),
including ash, and chlorine/chlorides, for the purposes of the COP
and COC, are, however, virtually identical. (Compare 40 CFR
§266.103[b][5][i-iii] with §266.103[c][iv][A-D]). These
regulations require the owner or operator to determine the
facility's operating limits generally by either using a method that
monitors and records instantaneous limits or hourly rolling average
limits. With respect to establishing the feed rate limits for
metals, total chloride and chlorine, and ash for the COP and COC,
however, 40 CFR §266.103(b)(5)(iii) and §266.103(c)(iv)(D) both
provide as follows:
"Feed rate limits for metals, total chlorine and
chloride, and ash are established and monitored by
knowing the concentration of the substance (i.e., metals,
chloride/chlorine, and ash) in each feedstream and the
flow rate of the feedstream. To monitor the feed rate of
these substances, the flow rate of each feedstream must
be monitored under the continuous monitoring requirements
of paragraphs (b)(5)(i) and (ii) [(c)(4)(iv) (A) through
(C)] of this section."
This is the method that Cytec does in fact follow to monitor its
feed rates of ash and chlorine/chlorides. Cytec's circular chart
recorder in use at the time of Mr. Lee's inspection continuously
monitors the flow rate of the spent alcohol feedstream. The feed
rates of ash and chlorine/chlorides can then be calculated by
multiplying their concentrations by the waste feed rate. (FF #17).
The Region contends that Cytec is nevertheless in violation
because it did not separately record the feed rates of ash and
chlorine/chlorides, until after Mr. Lee's inspection in April 1993.
After the inspection Cytec performed the calculations of the feed
rates for each day that hazardous waste was burned, and sent them
to the Region in monthly reports. (Ex. 12). Those reports
confirmed that feed rates conformed with the operating limits set
in the COC, and resulted in air emissions far below the applicable
limits for these parameters. (FF #18).
Cytec did initially establish the feed rates for ash and
chlorine/chlorides for its COP and COC, however, in accord with the
methods specified in the regulations, 40 CFR §§260.103(b)(5)(iii)
and 260.103(c)(iv)(D), as described above. (Exs. 1, 3, and 39).
These documents indicated that the content of those parameters in
the waste was either non-detectable or so low that there was no
chance of exceeding the emission limits for any parameter so long
as the spent alcohol waste composition did not change. Since all
constants were known, a glance at the spent alcohol recording chart
sufficiently showed that the feed rates of ash and
chlorine/chloride continued in conformance with the COP and COC.
Cytec could easily have graphed those feed rates on the same
recording charts, but doing so would have been superfluous. The
record shows that Cytec's continuous monitoring and recording of
the waste alcohol flow rate in these circumstances was sufficient
to "to ensure conformance with the certification of compliance," as
required by the regulation. Therefore, Count VI will be dismissed,
and no penalty will be assessed for failure to adequately monitor
and record these feed rates.
- Count VI - Penalty for Lack of Automatic Waste Feed Cutoff
Cytec has already been found liable for the violation alleged
in Count VI of the Complaint. At the time of the inspection, Cytec
did not have an operating system to automatically cut off the feed
of hazardous waste to the boiler if the total flow exceeded the
limit established in the COC. Such an AWFCO is required by 40 CFR
§266.103(g) and §266.103(c)(1)(i). Cytec's system did cut off the
flow of hazardous waste to the boiler when other operating
conditions listed in §266.103(c)(1) deviated from those established
in the COC. (FF #11). Cytec installed an AWFCO interlocked to the
COC's total hazardous waste flow limit of 125 gallons per hour
several days after the inspection. (FF #12). The only issue
remaining with respect to Count VI is the appropriate amount of the
civil penalty to be assessed.
RCRA §3008(a)(3) provides for the assessment of civil
penalties of up to $25,000 per day of noncompliance with any
requirement of RCRA. This section also states that, "[i]n
assessing such a penalty, the Administrator shall take into account
the seriousness of the violation and any good faith efforts to
comply with applicable requirements."
The Region calculated its proposed civil penalty for Count V
by following the guidelines in the RCRA Civil Penalty Policy dated
October 1990 (Ex. 22, the "Penalty Policy"). The Penalty Policy is
designed to be consistent with §3008(a). Its purposes are "to
ensure that RCRA civil penalties are assessed in a fair and
consistent manner; that penalties are appropriate for the gravity
of the violation committed; that economic incentives for
noncompliance with RCRA requirements are eliminated; that penalties
are sufficient to deter persons from committing RCRA violations;
and that compliance is expeditiously achieved and maintained."
(Ex. 22, p. 5). The EPA Rules of Practice require the
Administrative Law Judge to consider such civil penalty guidelines
in determining the appropriate amount of the penalty, and to state
the reasons for the any decision that varies the amount from that
proposed in the complaint. 40 CFR §22.27(b).
The Penalty Policy establishes a method in which the proposed
penalty is derived through a sequential process. First, a gravity-based component is determined. For certain violations, a multi-day
component is then added. Adjustments may then be made to that
amount for various additional factors such as the violator's degree
of culpability, history of noncompliance, and economic benefit.
The gravity-based component is intended to measure the
seriousness of the violation. It is determined by examining two
factors: the potential for harm, and the extent of deviation from
the requirement. The first of those factors, the potential for
harm, is in turn based on two components: the risk of human or
environmental exposure to hazardous waste or hazardous
constituents, and the adverse effect on the RCRA regulatory
program. Both the potential for harm and extent of deviation are
rated either major, moderate or minor. The Penalty Policy then
constructs a matrix with a range of civil penalties for the gravity
component of the violation depending on the assessment of these two
factors. (Ex. 22, p. 19). A similar matrix is developed for
multi-day penalties. The addition of multi-day penalties is either
mandatory, presumed, or discretionary, depending on the extent of
the combined gravity component. (Ex. 22, p. 23-24).
In this case, the Region determined that the AWFCO violation
had a moderate potential for harm and a moderate extent of
deviation from the regulatory requirement. The Region then
assigned a penalty value in the middle of the range in the matrix
for a "moderate-moderate" determination: $6500. Since a moderate-moderate violation carries presumed multi-day penalties, the Region
then added the midrange multi-day value of $925 multiplied by the
number of days of violation after the first day (59), yielding a
total penalty of $61,075. (Ex. 23, Count 5).
Cytec challenges this penalty assessment on a number of bases.
Cytec stresses the clean nature of its spent alcohol hazardous
waste fuel and the other controls and cutoffs in place on its feed
into the boiler at the time of the inspection. Even if the feed
rate were to exceed the operating limit of 125 gallons per hour, as
it did on April 26, 1993, there would still be no risk that the
emission limit could be exceeded for any parameter. (Ex. 8, p. 14-15). The size of the hazardous waste feed line orifice physically
restricted the maximum flow of spent alcohol into the boiler to 180
gallons per hour. Cytec could have burned this waste at a rate of
1230 gph, almost ten times the operating limit, without exceeding
air emission limits. (Tr. 211-212). The Region did not present
any substantial evidence to contradict these facts concerning the
virtually non-existent risk to human health or the environment due
to Cytec's lack of an AWFCO. Cytec argues that the potential for
harm from this violation was so low that no penalty should be
assessed. If this were the only factor to be considered in the
gravity component, it would be determined to be minor.
However, the primary risk of harm from this violation is not
to human health or the environment, but to the integrity of the
RCRA regulatory program. The requirement for an operating limit on
feed rate of total hazardous waste in the COC is the first one
listed in 40 CFR §266.103(c)(i). The ability to automatically cut
off the flow of the hazardous waste when the waste feed rate limit
is exceeded is the most direct means to ensure compliance with the
established operating limits for all parameters. Even if there is
little risk of actual exposure to hazardous constituents due to an
exceedence, the limit on total hazardous waste flow represents the
cornerstone of the entire COC upon which all other operating limits
are based. As discussed above, it provides, for example, the basis
for calculating feed rates of ash and chlorides. Although the
hazardous waste Cytec burns happens to be relatively clean, the
failure to install the most basic cutoff device, on excess
hazardous waste flow, has a significant adverse effect on the
regulatory purpose for these RCRA requirements. (See Ex. 22, p.
15).
The Penalty Policy states that the overall "potential for harm"
factor in the gravity component is considered moderate if there is
a moderate risk of environmental exposure and/or there is a
significant adverse effect on the RCRA program. (Ex. 22, p. 15).
Here there was a minor risk of exposure to hazardous waste, but
moderate harm to the regulatory program. Although this is somewhat
of a borderline situation, the Region's determination will be
upheld. Under the Penalty Policy, the violation of failure to
install an AWFCO on total hazardous waste feed rate has an overall
moderate potential for harm.
Cytec did have automatic cutoff controls in place for
exceedences of the other applicable limits required by the
regulations: carbon monoxide concentration, temperature, production
rate, and waste feed pressure. (FF #11). The AWFCO for the
operating limit for feed rate of total hazardous waste, as
discussed above, is the most basic and direct means to ensure
compliance with all COC parameters. Therefore, the extent of
deviation from the regulatory requirement is also determined to be
moderate. Since all other required cut-offs were in place,
however, this is again a relatively less serious moderate
deviation.
This analysis confirms the Region's determination that this
violation merits a gravity component based on a moderate potential
for harm and a moderate extent of deviation. The Penalty Policy
matrix provides a range of penalties for such violations from $5000
to $7999. The Region chose the midpoint of $6500. However, the
lower end of this range represents a more appropriate value due to
the virtually nonexistent risk of human or environmental exposure
to hazardous wastes or constituents from this violation, and the
presence of the other required AWFCO triggers. Although the harm
to the regulatory program is considered moderate, the risk of
environmental harm is minor. The extent of deviation is also in
the low range of moderate since Cytec did have AWFCO triggers for
all other required parameters. These factors combined indicate
that the low figure in the range for moderate-moderate violations,
$5000, should be selected. (See Penalty Policy matrix, Ex. 22, p.
19).
The Penalty Policy states that there is a presumption in favor
of imposing multi-day penalties for violations with the gravity
designation of "moderate-moderate." (Ex. 22, p. 23). The multi-day
penalty matrix provides a range of $250 to $1600 per day of
continuing moderate-moderate violations. (Ex. 22, p. 24). Again,
however, the amount selected should be at the low end of the range,
for the reasons discussed above. Although Cytec is apparently a
relatively large and sophisticated company, the lack of an AWFCO
for total hazardous waste feed rate did not present any real
environmental or human health risk. Cytec demonstrated cooperation
by its prompt remediation of this deficiency immediately after the
inspection. The Penalty Policy provides for recognition of degree
of cooperation and promptness of remediation in consideration of
multi-day penalties. (Ex. 22, p. 25). Therefore, the lowest
value, $250, will be selected as the appropriate amount for Cytec's
multi-day penalty for this violation, rather than the middle amount
of $925 chosen by the Region.
The parties also differ over the appropriate number of days
that should be counted under this violation. The BIF rule, 40 CFR
§266.103(g), requires the AWFCO to be functioning "[d]uring the
compliance test . . . and upon certification of compliance." The
Region applied the multi-day penalty to the total of 59 days,
encompassing three days of compliance testing in September 1992,
and the additional 56 days following the submittal of Cytec's COC
on March 5, 1993, until the inspection of April 29-30, 1993. Cytec
contends, however, that only those days in which hazardous waste
was actually burned in the boiler should be counted. It is not
disputed that there were only 23 such days during these periods.
(FF #12).
The plain language of the regulation supports Cytec's
position. Section 266.103(g) requires an AWFCO for deviations from
all operating conditions specified in §266.103(c)(1). That
subsection states that the boiler "must be operated in accordance
with these operating limits . . . at all times when there is
hazardous waste in the unit." (emphasis added). Where the time
unit under consideration for penalty purposes is days, it follows
that Cytec can only be penalized on days when hazardous waste was
burned in the boiler. The penalty for this violation will
therefore be $5000 plus $250 for 22 additional days, for a total of
$11,500.
There is no basis in the record to adjust this penalty for any
of the adjustment factors listed in the Penalty Policy. The only
one that the parties addressed in their briefs was the issue of
Cytec's good faith efforts to comply. It is commendable that Cytec
came into compliance immediately after the inspection, by
installing an AWFCO for total hazardous waste feed rate. However,
this compliance after discovery of the violation is not sufficient
reason to adjust the penalty downward. The matrix values in the
Penalty Policy already assume good faith efforts to comply after
the EPA's discovery of a violation. (Ex. 22, p. 33). Cytec has
already been afforded the benefit of its prompt remediation of this
violation by designating the smallest amounts for penalties in the
matrices for this moderate gravity violation. Therefore, the
penalty for the AWFCO violation alleged in Count V of the Complaint
will remain at $11,500.
Cytec also argued that the penalty proposed for this violation
was unfairly out of proportion to others imposed for similar AWFCO
violations in Region 5, in the same enforcement initiative that
resulted in the Cytec complaint. Limited evidence of complaints
and penalty calculations were received into evidence for four other
proceedings ("comparables") that included a charge of deficient
AWFCOs. (Exs. 27-31). The proposed penalties in those cases
ranged from $1000 to $4000.
The evidence of the comparables did in fact provide a useful
cross-check, showing that the amount derived above is appropriate
for Cytec's violations. Without going into details, it is
sufficient to note that the other four had a relatively "minor"
gravity component, and none involved precisely the same violation
found here -- lack of a cutoff on total hazardous waste flow.
Cytec's violation was indeed more serious than those in the
comparable proceedings, but, for the reasons given above, not to
the magnitude proposed by the Region. The penalty assessed by this
decision, $11,500, is commensurately greater than those sought in
the comparable proceedings.
The penalty of $11,500 for this violation was derived wholly
based on the facts relating to Cytec's AWFCO system, consistent
with RCRA $3008(a) and the Penalty Policy. Cytec showed that its
violation of 40 CFR §266.103(g) should be assessed at the low end
of the range for "moderate-moderate" gravity violations, for days
when it burned hazardous waste.
- Count III - Subpart BB Monitoring
Count III of the Complaint alleges that Cytec failed to
monitor the pumps and valves connected to its boiler for vapor
leaks, as required by Subpart BB of 40 CFR Part 265. The BIF rule
provides that facilities operating under interim status(3) are
subject to specified provisions of Part 265, the interim status
standards for hazardous waste treatment, storage, and disposal
facilities. One of those provisions rendered applicable to newly
regulated boilers that burn hazardous waste is Subpart BB. The
regulation, 40 CFR §266.103(a)(4)(viii), states that:
"Owners and operators of boilers and industrial
furnaces that burn hazardous waste and are operating
under interim status are subject to the following
provisions of part 265 of this chapter, except as
provided otherwise in this section: . . .
(viii) Subpart BB (Air emission standards for
equipment leaks), except §265.1050(a)."
Subpart BB applies to equipment, including pumps and valves, that
contains or contacts hazardous wastes with organic concentrations
of at least 10 percent by weight. 40 CFR §§265.1050, 265.1052, and
265.1057. It is not disputed that Cytec's spent alcohol hazardous
waste has organic concentrations of at least 10 percent by weight.
The Subpart BB regulations require the owner or operator of a
regulated facility to monitor such equipment monthly for leaks,
using a portable leak detection instrument. 40 CFR §265.1063,
referring to 40 CFR Part 60, Method 21.
Cytec argues that it is not required to conduct such Subpart
BB monitoring since it stores its waste alcohol in a tank for less
than 90 days, before it is burned in the boiler. At the time of
the Region's inspection of Cytec in April 1993, such 90-day
accumulation tanks were exempt from all RCRA permit and interim
status standards, pursuant to 40 CFR §262.34, provided certain
conditions were satisfied. One of those conditions required
monitoring of the tank systems under Subpart J of Part 265.(4) Cytec
conducted such Subpart J, or daily visual monitoring of the tank
and waste feed lines, valves, and pumps, leading to the tank from
the process line, and from the tank to the boiler. (FF #13). The
exemption from Subpart BB for generators who store wastes in 90-day
tanks was explicitly preserved in a note that appears at the end of
40 CFR §265.1050.(5)
Cytec also argues that it is not required to conduct Subpart
BB monitoring because it is protected by the "permit-as-shield"
policy pursuant to 40 CFR §270.4, due to Cytec's RCRA permit for
its drum storage unit. That permit was in effect at the time of
the 1993 EPA inspection. (FF #7). Cytec further argues that the
EPA failed to provide adequate notice of its interpretation of
Subpart BB's application to BIF units, and should be precluded from
imposing a penalty for any such violation. These issues will be
addressed below.
-- Exemption for 90-day Tank Systems
Cytec contends that the exemption for generators who store
wastes in a tank for 90 days or less extends to its entire "tank
system," which includes the waste feed lines, pumps, and valves
between the tank and the boiler. The Region argues that the
exemption covers only the 90-day tank itself and the "upstream"
equipment leading into the tank, but not the "downstream" equipment
that conducts the hazardous waste from the tank into the boiler.
This decision finds that the Region's interpretation is more
consistent with the regulatory definitions and scheme of the BIF
rule. Therefore, Cytec is found liable for failure to comply with
Subpart BB monitoring of this equipment, as alleged in Count III of
the Complaint.
There is no significant dispute concerning the physical nature
of Cytec's spent alcohol management system. The entire system was
essentially depicted in a simple hand-drawn schematic diagram (Ex.
18). The waste is generated in the plant process line, then piped
to the 90-day tank, where it is stored until it is piped to Boiler
#3. It is then burned in the boiler, resulting in the generation
of steam energy and air emissions. There are pumps and valves on
the waste feed lines, both upstream and downstream of the tank.
The spent alcohol hazardous waste is in contact with all of this
equipment. (FF #5).
In order to determine the extent of the exemption from Subpart
BB monitoring for this equipment at Cytec's facility, it is first
necessary to examine the definitions at the beginning of the RCRA
regulations, found at 40 CFR §260.10. Cytec maintains that the
exemption for 90-day accumulation facilities encompasses its "tank"
and entire "tank system." Section 260.10 defines tank system as "a
hazardous waste storage or treatment tank and its associated
ancillary equipment and containment system." The key definition is
that of "ancillary equipment."
"Ancillary equipment means any device including, but
not limited to, such devices as piping, fittings,
flanges, valves, and pumps, that is used to distribute,
meter, or control the flow of hazardous waste from its
point of generation to a storage or treatment tank(s),
between hazardous waste storage and treatment tanks to a
point of disposal onsite, or to a point of shipment for
disposal off-site." 40 CFR §260.10.
Under this definition, it is clear that the pipes, pumps, and
valves between the Cytec facility's process line and the 90-day
storage tank are ancillary equipment and part of the tank system.
Downstream of the tank, however, the equipment must lead to a
treatment tank, to an onsite disposal unit, or to a point of
shipment for off-site disposal. Boiler #3 does not qualify as any
of those destinations for the hazardous waste. Therefore, the
exemption for 90-day accumulation tank systems does not extend to
the equipment between Cytec's storage tank and the boiler.
The definitions confirm that Cytec's Boiler #3 is a "boiler"
that conducts "treatment" but not "disposal" of the hazardous waste.
"Disposal means discharge, deposit, injection,
dumping, spilling, leaking, or placing of any solid waste
or hazardous waste into or on any land or water so that
such solid waste or hazardous waste or any constituent
thereof may enter the environment or be emitted into the
air or discharged into any waters, including ground
waters." 40 CFR §260.10.
Although the burning of the spent alcohol in Cytec's boiler results
in air emissions, the passage of the waste into the boiler is not
its "placing . . . into or on any land or water." Rather,
paraphrasing the definition of "treatment," it there undergoes a
"process designed to change its physical and chemical character so
as to recover energy from the waste." 40 CFR §260.10. Of course,
the unit where this takes place also conforms to that section's
definition of "boiler." The regulatory definitions thus verify that
Cytec's 90-day accumulation tank system does not include the
pipelines, pumps, and valves between the tank and the boiler.
This conclusion is also consistent with the basic purpose and
logic behind the BIF rule. The EPA intended, on the effective date
of the rule (August 21, 1991) to "expand controls on hazardous
waste combustion to regulate air emissions from the burning of
hazardous wastes in boilers and industrial furnaces." As an
adjunct to this basic purpose, "the rules subject owners and
operators of these devices to the general facility standards
applicable to hazardous waste treatment, storage, and disposal
facilities." (Ex. 25, 56 FR 7134). Once the hazardous waste
leaves Cytec's 90-day storage tank, it is dedicated to treatment in
the boiler that is brought under regulation by the BIF rule. The
waste at that point is no longer merely stored on a short-term
basis for disposal or further treatment in a tank. The requirement
for Subpart BB monitoring for equipment leaks in
§266.103(a)(4)(viii) would have little import if it did not apply
to the equipment feeding hazardous waste directly into newly
regulated boilers.
-- Permit-as-Shield
Cytec also contends that it was not required to comply with
Subpart BB monitoring at the time of the inspection, because it was
shielded from enforcement by its RCRA permit. Respondent cites 40
CFR §270.4(a), known as the "permit-as-shield" provision. That
section states that "[c]ompliance with a RCRA permit during its
term constitutes compliance, with for purposes of enforcement, with
subtitle C of RCRA . . ," with certain exceptions. On December 6,
1994, this section was amended to add a specific exemption,
§270.4(a)(4), for requirements promulgated under Subparts AA, BB,
and CC of Part 265. This exception was not of course in effect at
the time of the Region's inspection of Cytec in April 1993. The
effect of the permit-as-shield provision is to preclude EPA from
enforcing RCRA provisions that do not appear in a facility's RCRA
permit. When a permit is modified or renewed, any omitted or newly
applicable additional requirements can then be incorporated. Shell
Oil Company v. EPA, 950 F.2d 741, 765 (D.C. Cir. 1991).
The requirement to conduct Subpart BB monitoring is found in
the interim status standards for boilers, 40 CFR §266.103. As
stated in the preceding section, §266.103(a)(4)(viii) requires such
boilers to comply with Subpart BB of Part 265. Cytec does not
dispute that its Boiler #3 was an "existing" boiler, in operation
on August 21, 1991, subject to the interim status standards until
a permit is issued, pursuant to §266.103(a)(1)(i) and (ii).
Cytec's claim would extend the scope of the permit-as-shield
rule far beyond its intent. The shield can only protect an area as
broad as the permit on which it is based. This basic permitting
principle is expressed in 40 CFR §270.1(c)(4), as follows:
"Permits for less than an entire facility. EPA may
issue or deny a permit for one or more units at a
facility without simultaneously issuing or denying a
permit to all of the units at the facility. The interim
status of any unit for which a permit has not been issued
or denied is not affected by the issuance or denial of a
permit to any other unit at the facility."
Cytec's RCRA permit was issued only for its drum storage unit in
1989. (FF #7). The definition of "facility" in 40 CFR §260.10
similarly states that "[a] facility may consist of several
treatment, storage, or disposal operational units." Cytec's Boiler
#3 came under interim status on the effective date of the BIF
regulation, August 21, 1991. Its permitting, and any enforcement,
may be pursued completely separately from the permitting and any
enforcement concerning the drum storage unit.(6)
Cytec cites the preamble to the notice of the Subpart BB
regulation, published on June 21, 1990, at 55 FR 25490. (Ex. 15).
The permit-as-shield policy as applied to the new organic air
emission standards for hazardous waste units was also addressed in
an EPA Seminar Publication on the topic, dated August 1992. (Ex.
33, p. 60). In these documents, the EPA expressly recognized that
the permit-as-shield policy would apply to permitted facilities,
with respect to the new Subpart BB rules, until the anticipated
Phase II revision to the hazardous waste air emission standards.
(Ex. 33, p. 63; also see note 4 above). However, this policy must
be read in light of the principle of separate hazardous waste
management unit permitting. The permit-as-shield certainly would
have applied to Cytec's drum storage unit in 1993 if it had any
equipment subject to Subpart BB monitoring. It has no application,
however, to Cytec's boiler which, in June 1990, had no permit or
interim status, before promulgation of the BIF rule. Once the
boiler acquired interim status it was subject to the interim status
standards set forth in 40 CFR §266.103.
This precise question was in fact answered by the EPA in the
1992 Seminar Publication, as follows:
"Question -- If a manufacturing facility has both
final and interim status units, does the rule apply?
Answer -- The rule applies to interim status units;
final permit units are shielded." (Ex. 33, p. 63).
Subpart BB thus applied to Cytec's interim status Boiler #3,
despite the fact that Cytec had a final permit for its drum storage
unit.
Cytec's argument, taken to its full logical extent, would
actually preclude any enforcement action concerning the boiler,
including all counts in the Complaint, simply because Cytec had a
pre-existing permit for its drum storage unit. Cytec has never
challenged the fact that the boiler acquired interim status on the
effective date of the BIF rule. That fact is stated in Cytec's own
permit renewal application, by its witnesses, and is evident in its
entire course of conduct in completing the necessary certifications
of precompliance and compliance required by §266.103. (See e.g.,
Ex. 20, p. D-8; Tr. 595). Cytec was acting in compliance with the
timetable for obtaining the certifications of compliance and
submitting permit applications as required by 40 CFR §270.42(g) for
a an existing newly regulated interim status BIF unit. This
schedule is set forth in EPA's Technical Implementation Document
for the BIF rule. (Ex. 19, p. 10-5). Cytec falls within the
category of a facility with a permitted non-BIF unit, and a newly
regulated BIF. The boiler unit acquired interim status on the
effective date of the BIF rule, August 21, 1991.
Cytec's Boiler #3, as a newly regulated BIF interim status
unit, was subject to the interim status standards, including the
requirement to conduct Subpart BB monitoring pursuant to 40 CFR
§266.103(a)(4)(viii). The permit-as-shield rule does not apply to
enforcement concerning Cytec's BIF unit, Boiler #3.
-- Adequate Notice of Applicability of Subpart BB
Cytec argues that, if the Region's interpretation of Subpart
BB applicability is upheld, it should not be penalized because the
EPA did not provide adequate notice of its interpretation to Cytec
and the regulated community. Cytec cites the case of General
Electric Company v. U.S. EPA, 53 F.3d 1324 (D.C. Cir. 1995). That
decision held that fundamental principles of due process require
that a regulated party receive "fair notice" of a regulatory
interpretation in order for the agency to assess a civil penalty
for a violation of the regulation. "Fair notice" requires that "a
regulated party, acting in good faith, would be able to identify,
with 'ascertainable certainty,' the standards with which the agency
expects parties to conform." Id. at 1328, citing Diamond Roofing
Co. v. OSHRC, 528 F.2d 645, 649 (5th Cir. 1976).
The standard here -- the applicability of Subpart BB
monitoring to BIF units that are fed by exempt 90-day waste
accumulation tanks -- is hardly a paragon of clarity.
Nevertheless, the EPA's interpretation is reasonably ascertainable
from a reading of the regulations. There was some disagreement and
confusion evident among the EPA witnesses and technical documents.
For example, Mr. Lee and Mr. Cunningham disagreed on whether the
exemption encompassed just the "tank" or the entire "tank system."
This issue was complicated by a "decision tree" in an EPA technical
document that referred to an exemption for "tank systems." (See Tr.
144, 381; Ex. 14, p. 3-12). These witnesses' opinions are not
accorded any weight to the extent they encompass purely legal
issues. Nevertheless, no EPA witness advanced the position
asserted by Cytec -- that Subpart BB was not applicable to any of
its equipment leading to the regulated boiler.
The regulatory definitions provided sufficient fair notice
that the 90-day tank system did not extend to the feed lines
leading from the tank to the boiler. Thus, assuming the exemption
covered the entire tank system, it did not cover the equipment
feeding hazardous waste from the tank to the boiler. Therefore,
Cytec is subject to a civil penalty for its failure to monitor that
equipment pursuant to Subpart BB.
It would have been preferable for EPA to have included in the
BIF rule, or in an accompanying revision of the definitions, an
explicit statement of the limits of the exempt 90-day tank system
when used in a facility in conjunction with a newly regulated BIF
unit. Instead, the BIF rule was superimposed on pre-existing
definitions that did not expressly contemplate these precise
circumstances. Indeed, the principle behind the definition of
"tank system" is to encompass pipelines, pumps, and valves both
upstream and downstream of the tank itself. It is not a completely
unreasonable reach to consider the burning of the hazardous waste
in the boiler as disposal rather than treatment. There is no
apparent or expressed reason why Subpart BB monitoring of the
equipment leading from the tank to the boiler should be required,
while such monitoring the upstream equipment, transporting the same
hazardous waste, is not. The environmental or human health risks
of vapor leaks would be the same whether the leak occurred upstream
or downstream of the tank. At the EPA seminar on the BIF rule held
in January 1995, the speaker, Ginger Gotliffe, confirmed that 90-day tanks or tank systems were "outside the universe" of the rule,
without further defining the physical extent of the exemption in
facilities with both 90-day tanks and BIF units. (Ex. 17, p. 18).
These considerations fall short of the standard to prevent a
imposition of a penalty articulated in General Electric: where the
"regulations and policy statements are unclear, where the
petitioner's interpretation is reasonable, and where the agency
itself struggles to provide a definitive reading of the regulatory
requirements." The requirement for Subpart BB monitoring appeared
in the BIF rule, and all the relevant definitions appeared in the
regulations from the rule's inception. Cytec should have been on
notice that Subpart BB monitoring of equipment leading directly to
the boiler was required, despite its exempt 90-day tank system.
The agency never struggled to the extent of considering this
equipment exempt. There is no reason however to believe that Cytec
acted in other than good faith in believing it was exempt from
Subpart BB. These circumstances may be considered in relation to
the determining the appropriate amount of the civil penalty for
this violation, but will not prevent the assessment of any penalty.
-- Civil Penalty for Subpart BB Violation
The Region proposed a civil penalty of $199,500 for Cytec's
violation of failure to conduct Subpart BB monitoring on the pumps
and valves on the feed lines to the boiler. (Ex. 23, Count 3).
The Region followed the Penalty Policy described above. (Ex. 22).
The Region determined that the violation represented a moderate
potential for harm and a major extent of deviation. Under the
Penalty Policy matrix, the range for "moderate-major" violations is
from $8000 to $10,999. The Region then assigned the value at the
midpoint of that range, $9500, and multiplied it by 21 days of
violation, representing 21 months of failure to conduct the
required Subpart BB monthly inspections. This resulted in the
calculated penalty of $199,500.
The record supports a reduction in the extent of deviation for
this violation from major to moderate. The Region calculated this
penalty without considering the fact that Cytec conducted Subpart
J monitoring of its entire tank system, and all equipment feeding
the boiler. (Tr. 319). Although Subpart J visual monitoring might
not detect vapor leaks that Subpart BB monitoring could detect,
Subpart J monitoring is done on a daily basis. Such monitoring
provided a significant benefit since the waste alcohol was in
liquid, rather than gaseous form. In addition, the lack of clarity
over the extent of the 90-day tank system exemption during the
early days of the BIF rule should be considered. Where it was not
entirely clear what type of monitoring was required for which
components of the facility's equipment, the extent of deviation
from the standard may be considered reduced.
The Region's determination of a moderate potential for harm
will be upheld for the purposes of this decision. The Region did
not show substantial risk to the environment or human health as a
specific result of Cytec's failure to conduct Subpart BB
monitoring. The only alleged risk is a general one to the
atmosphere due to the cumulative effects of excess organic
emissions. (Tr. 305). Cytec did show again that its spent alcohol
is relatively benign in terms of its potential emissions, and that
its lines are relatively leak-tight. Subpart CC monitoring
performed in 1996 did reveal two small vapor leaks, at levels far
below those that would have been detected or regulated under
Subpart BB. It remains possible however that vapor leaks occurred
earlier that were not detected by Cytec due to its lack of Subpart
BB monitoring. This constitutes a moderate, if general, risk to
the environment or human health.
In addition, there is moderate harm from this violation to the
integrity of the BIF regulatory program. The intent of the program
was to impose Subpart BB monitoring on regulated boilers and their
associated equipment. The Respondent failed to comply with this
standard for a 21-month period. The range for "moderate-moderate"
violations is $5000 to $7999, with a midpoint of $6500.
The Region derived its proposed penalty by using the main
matrix amount of $9500 as the basis for the multi-day penalty,
rather than the multi-day matrix. (Ex. 22, p. 24). This is an
apparent departure from the Penalty Policy that was not explained
by the Region, and results in a much higher penalty than if the
multi-day matrix is used. In the totality of the circumstances
here, particularly the lack of any specific substantial risk to
human health or the environment, and the lack of clarity of the
Subpart BB requirement, the lower multi-day penalty matrix should
be used. This would accord with the Penalty Policy itself which
contemplates the use of the multi-day grid in most circumstances.
The range for moderate-moderate violations is $250 to $1600,
with a midpoint of $925. The total penalty for the Subpart BB
violation will thus be $6500 plus $925 for the 20 additional days
of violation, for a total of $25,000. This happens to be the same
as the maximum amount for a single violation of RCRA, which is
appropriate in the totality of the circumstances. No other
adjustments are applicable. This is a sufficient amount to
constitute adequate deterrence and recognition of the violation,
but is not unduly punitive. No compliance order is necessary with
reference to this count, since Cytec recognizes that it is now
subject to Subpart BB monitoring for its entire tank system as well
as the boiler equipment, under the recent amendments.
- Other Considerations Raised by Respondent
Cytec argues that the Region acted improperly in delaying the
prosecution of this proceeding beyond the timetable guidelines set
forth in the Penalty Policy. Cytec also claims that the October
1996 inspection by Mr. Gaitskill amounted to deceptive and
unauthorized discovery. The parties also dispute whether Cytec's
Mr. Greene informed the Region's inspector, Mr. Lee, at the
conclusion of his 1993 inspection, of Cytec's belief that it was
exempt from Subpart BB monitoring. However, in view of the penalty
assessed by this decision, which is substantially lower than that
proposed by the Complaint, no further adjustments are warranted by
any of these factors.
There was unquestionably an element of deception in the
Region's moving up the date of Mr. Gaitskill's 1996 inspection, at
the request of Regional counsel, from its originally scheduled date
after the hearing, to before the hearing. (FF #19). The Region
did this without informing Cytec or this court that Mr. Gaitskill
might testify and present photographic evidence. In these
circumstances it is not credible that this idea occurred to the
Region only after Mr. Gaitskill's inspection. Although Mr. Greene
consented to the inspection, Cytec's counsel was not informed.
However, Mr. Gaitskill's testimony and evidence was not
significantly prejudicial to Cytec. For the reasons given above,
the total penalty here is already reduced substantially, and no
further adjustment is warranted for any deception or misconduct by
the Region.
Cytec also points out that the prosecution of this proceeding
was somewhat delayed beyond the timetables set forth in EPA's RCRA
Enforcement Response Policy (Ex. 26) and BIF Enforcement Strategy
(Ex. 11). Those documents establish enforcement goals. For
example, the agency is supposed to initiate action against medium
priority violators within 120 days of the discovery of a violation.
These are by no means mandatory deadlines, however, but only
enforcement goals for the use of EPA enforcement personnel. They
are not binding and create no rights on behalf of the regulated
community. There is no allegation that the Region here did not
proceed with this matter within a reasonable time, as required by
the Administrative Procedure Act §555(b). There is thus no basis
to reduce the penalty or Cytec's liability for any delay in the
prosecution of this proceeding.
Cytec also claims it was not provided any notice by Mr. Lee,
at the conclusion of his inspection, of the Subpart BB violation.
Mr. Greene testified that he told Mr. Lee that the tank system was
exempt because it was a 90-day accumulation tank. (Tr. 577). Mr.
Lee's report states that Cytec stated Subpart BB was not
applicable, but "could not demonstrate why Subpart BB is not
applicable." (Ex. 9, p. 4). This dispute is however of no
substantial significance to the decision. The alleged violations
took place from August 1991 until the April 1993 day of the
inspection. Whether the 90-day exemption was sufficiently
explained by Mr. Greene and understood by Mr. Lee has no bearing on
Cytec's liability or even on the penalty considerations, which are
based on the period before the inspection. The record as a whole
does show that Cytec believed it was exempt, regardless of the
content of the exit interview between Mr. Greene and Mr. Lee. This
decision finds that the exemption did not in any event encompass
the equipment between the tank and the boiler. Therefore, no
adjustment of the determinations on liability and penalty will be
made concerning the notice to Cytec after the inspection.
Conclusions of Law
1. The Respondent, Cytec, had an adequate waste analysis plan
with respect to specifying a test method for ash and a frequency
for repeating its initial waste analysis, for its Kalamazoo
facility. Hence, Cytec did not violate 40 CFR §265.13 as alleged
in Count II of the Complaint. That charge is therefore dismissed.
2. Cytec adequately monitored and recorded the feed rates of
ash, chlorine, and total chlorides into its boiler, as necessary to
ensure conformance with its certification of compliance. Hence,
Cytec did not violate 40 CFR §§266.103(j)(1), 266.103(b)(5),
266.103(c)(4), or 266.103(k) as alleged in Count VI of the
Complaint. That count is therefore dismissed.
3. Cytec did not monitor its equipment between its 90-day
accumulation tank and its Boiler #3, following the procedures set
forth in Subpart BB of 40 CFR Part 265, as required by 40 CFR
§266.103(a)(4)(viii). Hence, Cytec committed this violation,
alleged in Count III of the Complaint. An appropriate civil
penalty for this violation is $25,000.
4. As found in an earlier decision, Cytec failed to have an
automatic cutoff for total hazardous waste flow in excess of the
limit in its certification of compliance, as required by 40 CFR
§§266.103(g) and 266.103(c)(1)(i). Cytec thus committed the
violation alleged in Count VI of the Complaint. An appropriate
civil penalty for this violation is $11,500.
Order
1. The Respondent, Cytec Industries, Inc., is assessed a civil
penalty in the amount of $36,500.
2. Payment of the full amount of this civil penalty must be
made within 60 days of service of this order by submitting a
certified or cashier's check in the amount of $36,500, payable to
the Treasure, United States of America, mailed to:
EPA - Region 5
P.O. Box 70753
Chicago, IL 60673
3. A transmittal letter identifying the subject case and
docket number, and Respondent's name and address, must accompany
the check. Respondent may be assessed interest on the civil
penalty if it is not paid within the prescribed period.
Appeal Rights
Pursuant to 40 CFR §§22.27(c) and 22.30, this Initial Decision
shall become the final order of the Agency, unless an appeal is
filed with the Environmental Appeals Board within 20 days of
service of this order, or the Board elects to review this decision
sua sponte.
Andrew S. Pearlstein
Administrative Law Judge
Dated: December 23, 1997
Washington, D.C.
1. The Complaint originally named American Cyanamid Company as the
Respondent. In an order of January 26, 1996, the name of the Respondent was
changed in the caption to reflect the parties' acknowledgment that Cytec
Industries, Inc., which was formerly part of American Cyanamid, is the proper
Respondent for the violations alleged in the Complaint.
2. References to the record are for the convenience of the reviewer.
They are representative only, and not intended to be exhaustive. "Ex." refers
to a numbered hearing exhibit, and "Tr." refers to a numbered page of the
stenographic transcript of the hearing.
3. The question of whether Cytec's boiler was operating under interim
status at the time of the Region's inspection in 1993 is discussed below in
the section on the "permit-as-shield" issue.
4. As most recently amended on December 6, 1996, 40 CFR §262.34(a)(1)(ii)
now requires generators who store waste in tanks for 90 days or less to comply
with Subparts J, AA, BB and CC of Part 265.
5. In its post-hearing brief, the Region at first argued that the entire
exemption for 90-day accumulation tanks was removed by the exception of
§265.1050(a) to the applicability of §266.103(a)(4)(viii). (See quote above,
p. 15). Without further examining the nuances of this convoluted argument, it
is noted that it is contrary to the testimony of the Region's own witnesses,
and would directly contradict the note at the end of §265.1050. The Region
did not mention this argument, and thus appeared to abandon it, in its reply
brief.
6. In February 1992, Cytec, following normal EPA permitting practice,
submitted an application for a permit renewal and revision that would add the
hazardous waste boiler as a newly regulated unit into a single combined
permit. (FF #8; Exs. 20, 21). EPA has not yet acted on that permit
application. Hence, this permit application has no effect as a shield.
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)