UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
BEFORE THE ADMINISTRATOR
In the Matter of )
)
Urban Drainage and Flood ) Docket No. CWA-VIII-94-20-PII
Control District, and )
Kemp & Hoffman, Inc. )
)
Respondents )
INITIAL DECISION
Pursuant to Section 309(g) of the Clean Water Act ("CWA"), 33
U.S.C. §1319(g), the Respondent Urban Drainage and Flood Control
District is assessed a civil penalty of $75,000, and the Respondent
Kemp & Hoffman, Inc., is assessed a civil penalty of $5000 for
discharging fill into waters of the United States without having
obtained a permit pursuant to Section 404 of the CWA, 33 U.S.C.
§1344, constituting a violation of the CWA §301(a), 33 U.S.C.
§1311(a).
By: Andrew S. Pearlstein, Administrative Law Judge
Dated: June 24, 1998, Washington, D.C.
Appearances
For Complainant:
Elizabeth Suter Bohanon, Esq.
Enforcement Attorney
U.S. EPA Region 8
Denver, Colorado
For Respondents:
Edward J. Krisor, Esq.
Shoemaker, Wham, Krisor & Shoemaker
Denver, Colorado
Proceedings
The Region 8 Office of the United States Environmental
Protection Agency (the "Complainant" or the "Region") filed an
administrative Complaint, dated May 4, 1994, against three
respondents. The first respondent, the Urban Drainage and Flood
Control District (the "District"), is an independent government
agency headquartered in Denver, Colorado, that assists local
governments in the Denver metropolitan area in drainage and flood
control projects. The second respondent, Kemp & Hoffman, Inc.
("Kemp & Hoffman"), is an earthmoving and construction company
located in Northglenn, Colorado. The third respondent was the City
of Lafayette, Boulder County, Colorado (the "City"). The Complaint
charged those respondents with discharging fill into a navigable
water of the United States, Coal Creek, on property owned by the
City without having obtained the permit required by the Clean Water
Act ("CWA") §404, 33 U.S.C. §1344. The Complaint alleges that this
activity constituted a violation of the CWA §301(a), 33 U.S.C.
§1311(a). The Complaint proposed assessment of a class II civil
penalty of $125,000, jointly and severally, against the respondents
for this violation, pursuant to the CWA §309(g), 33 U.S.C.
§1319(g).
The respondents filed their respective Answers to the
Complaint on or about May 31, 1994. The Answer of the District
denied liability for the violation on the basis that the site of
the activity on Coal Creek was exempt from the individual permit
requirement under the CWA §404, as within the stream's "headwaters"
area. The Answer of the Kemp & Hoffman (originally represented by
different counsel than indicated above) denied liability primarily
on the basis that the District alone was responsible for CWA
permitting compliance. The respondents also contested the amount
of the proposed penalty, in the event a violation is found.
The Answer of the City also denied responsibility for any
violation. On February 14, 1995, the former Administrative Law
Judge ("ALJ") assigned to this case, Hon. Frank W. Vanderheyden,
granted a motion for accelerated decision by the City, dismissing
the City of Lafayette as a respondent in this proceeding. In an
order dated December 19, 1996, the undersigned ALJ denied the
District's and Region's respective motions for accelerated
decision.
The hearing in this matter convened before ALJ Andrew S.
Pearlstein in Denver, Colorado, on July 9-11 and July 30, 1997.
The Region produced seven witnesses. The respondents jointly also
produced seven witnesses. The record of the hearing consists of a
stenographic transcript of 761 pages, and 59 numbered exhibits, of
which 56 were received into evidence. The ALJ, along with
respective counsel and an additional representative of the Region
and District, also visited the site of the alleged violation, and
the locations of the Corps of Engineers' stream gauge and
headwaters point on Coal Creek, on the morning of July 11, 1998.
The parties each submitted post-hearing briefs and reply briefs.
The record of the hearing closed on December 12, 1997, upon the
ALJ's receipt of the reply briefs.
Findings of Fact
- Background and Chronology of Events
1. The Urban Drainage and Flood Control District (the
"District") is an independent governmental agency of the State of
Colorado, headquartered in Denver, Colorado. The District was
established by the Colorado legislature in 1969 to assist local
governments in the six-county Denver metropolitan area in the
planning, construction, restoration, and maintenance of drainage
and flood control facilities. The District is funded by a real
property tax levy on property in its jurisdiction. In 1997, the
District had assets of approximately $10 million, most of which was
in cash. (Ex. 1, p. 1; Tr. 271-272, 730).(1)
2. In the fall of 1992, representatives of the City of
Lafayette (the "City"), located in Boulder County about 20 miles
north of Denver, asked the District for help in stabilizing an
eroding stream bank along Coal Creek. The City feared the erosion
was encroaching on a fence bordering the City's storage and
maintenance facility, known as the City of Lafayette "shops",
situated adjacent to Coal Creek. The City's property includes the
entire affected area in and along Coal Creek. After a visit to the
site, the District agreed to place this project on its work program
for 1993. (Ex. 51; Tr. 628).
3. Coal Creek at that location flowed in a meander or oxbow
curving northward and then eastward and southeastward toward the
City shops. The unstable north and northeast bank of the meander
was about 7 to 10 feet high. Over the years, the City had dumped
concrete, asphalt, and rubble materials into the bank in an effort
to slow erosion. Since at least 1982, Coal Creek's course had
extended further northward in the meander below the City shops,
accelerating erosion of the stream bank. (Exs. 24, 24-A; Tr. 357,
635).
4. In March of 1993, David Bennetts, the District engineer
assigned to this project, visited the site with the District's
project inspector, Mike Sarmento. The parties desired to complete
the project before the late spring high runoff began. The project
was first envisioned to encompass regrading and rip-rapping about
400 feet of the eroding north bank of Coal Creek adjacent to the
City shops. However, upon further inspection of the site, Mr.
Bennetts observed a relatively clear swale area or depression,
about 210 feet long, that appeared to be a former channel of Coal
Creek. He determined that redirecting Coal Creek into this swale
would cut off flow into the meander, thus solving the erosion
problem. Mr. Bennetts and Mr. Sarmento also felt that this
alternative would involve less earthmoving and disruption to the
site as a whole, than would regrading and rip-rapping the eroding
bank. The District's chief of its maintenance program, Mark R.
Hunter, concurred in this decision. The project was thus converted
in the field from a bank stabilization to a channel relocation
project. (Tr. 629, 635, 638, 678-679, 684-685).
5. The project was then constructed from March 17, 1993 until
April 8, 1993, by redirecting the flow of Coal Creek into the swale
or apparent former channel. The District contracted with Kemp &
Hoffman, Inc. of Northglenn, Colorado ("Kemp & Hoffman"), to
perform the excavation and construction work. Kemp & Hoffman
performed the work completely under the direction and control of
the District. (Ex. 56; Tr. 715).
6. Kemp & Hoffman is a small construction company, with from
20 to 70 employees. The number of employees fluctuates seasonally
with the company's work load. As of December 1996, the company was
in a solid financial position, with a net worth of over $750,000,
and assets of $400,000, of which $250,000 was in cash. Kemp &
Hoffman had sales of over $4.8 million in 1996. However, Kemp &
Hoffman anticipates that its receipts in 1997 and 1998 could be
substantially reduced if and when its major client, Total
Petroleum, is acquired by another company, as expected. (Ex. 19;
Tr. 278-279, 717-720).
7. Kemp & Hoffman first placed a 42-inch pipe in Coal Creek,
and built a ramp across the creek. The ramp was built with fill
supplied by the City of Lafayette. Mr. Bennetts, with the
assistance of Mr. Sarmento, then determined the alignment, width
and depth of the new channel. Kemp & Hoffman constructed the new
channel as directed, excavating it to a depth of about 18 inches,
and a width of 10 to 15 feet. Coal Creek was then allowed to flow
in the new channel. Kemp & Hoffman then removed the culvert and
constructed a 250-foot long earth berm along the new alignment, and
installed rip-rap along the new channel banks. The berm varied in
height from 3 to 9 feet, and was 8 feet wide at the top. Two 18-inch high drop structures were installed in the new channel.
Finally, the disturbed areas were tilled and planted with a native
seed mix. The placement of the diversion berm entailed the
discharge of approximately 45 cubic yards of fill below the
ordinary high water mark of Coal Creek. Counting the riprap and
drop structures, the total fill placed in the creek was
approximately 238 cubic yards. (Exs. 49, 56, 31-p.4; Tr. 630-633,
659-660, 663-664, 693).
8. The Respondents' actions in cutting off the oxbow, and
straightening and shortening the Coal Creek channel eliminated 210
linear feet of natural benthic habitat. The placement of the berm
at either end of the oxbow eliminated about 2350 square feet of
wetland, although potential new wetland area was created along the
banks of the new channel. An area at the lower end of the meander
was covered with side-cast material from the excavation of the new
channel. The project actually directly disturbed a total area of
approximately a quarter of an acre or 10,000 square feet. The
total area potentially adversely affected by the project included
adjacent areas such as the area within the curve of the oxbow, and
covered approximately three-quarters of an acre, or 30,000 square
feet. (Exs. 9, 25; Tr. 590-592).
9. The project (without mitigation) reduced the overall
quality of wetland and upland riparian vegetation in the reach of
Coal Creek adjacent to the City of Lafayette shops. There was a
net loss of wetland and upland vegetation, and of natural stream
channel and banks, due to direct land disturbance and the channel
realignment. The loss of vegetative cover reduced the value of the
site for wildlife habitat. Left unmitigated, the abandoned channel
and adjacent wetland areas would continue to experience long-term
adverse effects and a succession to drier conditions. (Ex. 24, p.
13; Tr. 386, 391, 584-586).
10. Under Section 404 of the Clean Water Act ("CWA"), persons
who discharge fill into a water of the United States must obtain a
permit for the proposed activity from the United States Army Corps
of Engineers (the "Corps"). Certain categories of activities are
covered under nationwide or regional permits, which do not
generally require advance notification and a permit application to
the Corps. Examples are Nationwide Permit 13, which applies to
bank stabilization projects, and Nationwide Permit 26, which
applies to projects in headwaters or isolated waters. To qualify
for these nationwide permits, the projects must not exceed certain
threshold criteria and must comply with general conditions to
minimize environmental impacts. Project sponsors must apply to the
Corps for issuance of individual permits for projects not
authorized by nationwide or regional permits. (33 CFR Parts 320-330; Tr. 60-64).
11. Individual permits may be issued, issued with conditions,
or denied, after public notice and comment by interested persons
and agencies. The Corps may also issue "after-the-fact" individual
or nationwide permits, in consultation with the EPA, after a person
is discovered to have conducted an activity in a water of the
United States without proper authorization under one of these
permit programs. (33 CFR Parts 320-330; Tr. 60-64).
12. The District had extensive contact with the Corps during
the years preceding these events. The District had built hundreds
of projects in the Denver area requiring either individual §404
permits or nationwide permit authorization from the Corps. The
District's usual practice was to seek an advance concurrence from
the Corps that a proposed activity would be covered by a nationwide
permit. The District was familiar with the Corps' permit programs,
since its chief business involved projects to improve drainage and
flood control facilities, which entailed regular contact with the
Corps of Engineers. (Exs. 6, 21; Tr. 65-66).
13. Prior to the events that are the subject of this
proceeding, the District had never been formally charged with a
violation of the Clean Water Act. The only prior enforcement
incident with the Corps occurred in 1987. In that year, the
District obtained an after-the-fact permit for emergency bank
stabilization work it had done on the South Platte River. Before
this proceeding, Kemp & Hoffman had never been charged with a
violation of the Clean Water Act. (Ex. 5; Tr. 716, 748).
14. The District did not seek or obtain a CWA §404 individual
permit, or a nationwide permit concurrence, from the Corps before
beginning construction of the Coal Creek channel realignment at the
City of Lafayette shops property. Kemp & Hoffman did not contact
the Corps concerning this project at any time. (Ex. 1, ¶26).
15. The District had worked often over the preceding 17 years
with Kemp & Hoffman, one of its regular contractors. In these
projects the District was responsible for obtaining all necessary
federal permits, such as Section 404 permits from the Corps. Kemp
& Hoffman was responsible for obtaining any necessary local
permits, such as road crossing rights-of-way. The contract between
the District and Kemp & Hoffman provided that the contractor was
responsible for obtaining all required permits and authorizations,
"unless otherwise provided by the District". At the beginning of
the job, Mr. Sarmento had told Calvin Hoffman, Kemp & Hoffman's
vice-president and general manager, that the District had obtained
the required CWA permit for the project. (Exs. 1, 56; Tr. 713,
723).
16. On April 2, 1993, a local resident telephoned the Corps'
Tri-Lakes office to register a complaint and ask if a permit had
been obtained for the work he observed being done in Coal Creek at
the City of Lafayette shops site. By this time, the channel
relocation had been essentially completed. The complaint was
received by Sandra Laney of the Corps' Tri-Lakes office in
Littleton, Colorado. On April 6, she telephoned Mr. Bennetts of
the District. Mr. Bennetts told her that the project was for bank
stabilization at the site, without making it clear that the channel
was also relocated. When Ms. Laney visited the site on April 7,
she observed, to her surprise, that the channel had been relocated,
and that the stabilized banks were along the new channel. (Ex. 3;
Tr. 40).
17. Ms. Laney then again telephoned Mr. Bennett, and informed
him that the project did not appear as previously described to her.
She told him that an after-the-fact individual permit would likely
be required. Mr. Bennetts indicated that paperwork requesting a
nationwide permit concurrence had been sent to the Corps. A letter
to that effect, with attachments, dated April 7, 1993, was sent by
Mr. Bennetts to Terry McKee of the Corps. (Exs. 3, 4; Tr. 642).
18. Ms. Laney then referred this matter to her supervisor,
Timothy Carey, manager of the Tri-Lakes Corps office. After
consultation with his supervisors in the Corps' district office in
Omaha, Nebraska, that office sent a letter, dated May 11, 1993, to
the District's Executive Director, L. Scott Tucker. The letter
stated that the investigation of the Coal Creek project showed that
the District had failed to comply with the Clean Water Act by
undertaking this project without having obtained an individual §404
permit. The letter also declared that the project site was
downstream of the creek's headwaters area and therefore did not
qualify for a nationwide permit. It further appeared that the
project would not have complied with the CWA §404(b)(1) guidelines,
since the alternative chosen, cutting off a stream meander, was not
the least environmentally damaging means to accomplish the
project's purpose. Therefore, the letter concluded by ordering the
District to restore the project area to preexisting conditions
within 45 days of receipt of the letter. The Corps notified the
EPA of this matter by sending Region 8 a copy of this
letter/restoration order as provided by the CWA §309. (Ex. 9; Tr.
106-112).
19. Mr. Tucker responded on behalf of the District in a
letter to Mr. Carey dated June 23, 1993. The District acknowledged
its error in not securing the required permit, but appealed the
restoration order. The District requested an on-site meeting to
consider alternative mitigation plans to restore lost environmental
benefits to the site as a whole, without having to restore the site
to preexisting conditions. (Ex. 10).
20. Representatives of the District, the Corps, the City, and
the Region met at the Coal Creek site at the City of Lafayette
shops on July 1, 1993. The Region confirmed that the District had
realigned the Coal Creek channel at that location. At that
meeting, and at follow-up meetings held over the next few months,
the parties discussed mitigating and resolving the project's
apparent violation of the Clean Water Act. As a result of those
meetings, the District retained a consultant, Greenhorne & O'Mara,
Inc., to prepare a detailed report. The report, dated October
1993, included a discussion of the site history and of the
restoration and mitigation alternatives for redressing the
situation. (Exs. 21, 23, 24; Tr. 308-310, 330-338).
21. The Greenhorne & O'Mara report recommended a mitigation
plan that would restore hydrology to the cut off oxbow, while
enhancing wetland vegetation in the area. This alternative would
allow the realigned channel to remain, thus resolving the erosion
problem along the north bank bordering the City shops, with minimal
impact to the Coal Creek stream system. The report included aerial
photographs that showed the migration of Coal Creek into the
meander, and increasing erosion, coinciding with increased
development of this part of Boulder County in the early 1980's.
(Ex. 24).
22. During the ensuing months, the District continued
discussions and correspondence with the Region and the Corps
concerning those agencies' enforcement responses and the proposed
mitigation work. The EPA Region 8 office had at this point assumed
lead agency status in the enforcement proceeding pursuant to its
agreement with the Corps. The basic outline of the proposed
mitigation plan remained as set forth in the Greenhorne & O'Mara
report. The Region expressed its desire for several additional
enhancements, including additional planting of willows, and
creation of additional wetland area. The District responded to
those items in a letter dated December 3, 1993, and filed its
responses to the Region's information request on January 21, 1994.
The District stated it was willing to construct the additional
enhancements, in return for some consideration in the penalty
assessment. (Exs. 16, 58; Tr. 352, 688-689).
23. The Region's next official response was the filing of a
Findings of Violation and Administrative Order for Compliance on
March 14, 1994. This document ordered the District to either
restore the site or apply to the Corps, after EPA review, for an
after-the-fact permit that would include the mitigation plan. The
District responded with a notification that it would apply for the
after-the-fact permit. The District submitted its draft permit
application for EPA review on April 21, 1994. The EPA responded
with comments on April 28, 1994. The District then submitted the
application formally to the Corps, which published the required
public notice on May 31, 1994. The Region submitted additional
comments on June 28, 1994. The Corps issued the after-the-fact
permit to the District on September 30, 1994. Also during this
period, on May 4, 1994, the Region filed its Complaints seeking an
administrative penalty against the respondents in this matter.
(Exs. 26, 27, 28, 29, 30, 31, 59).
24. The after-the-fact permit authorized the completed
realignment of Coal Creek, and required the District to carry out
the basic mitigation plan as proposed in the Greenhorne & O'Mara
report, in addition to several conditions proposed by the Region in
its comments. The original basic mitigation plan required
installation of a rock grade beam and culvert with a slide gate to
allow a trickle flow from the creek into the former channel
meander. Regrading of the downstream end of the meander, at its
confluence with Coal Creek, was required in order to allow ponding
in that area. The permit also required the District to regrade and
riprap a rundown, or small drainage channel, leading from the City
shops into the oxbow area. (Ex. 31).
25. The permit also ordered the District to comply with
several additional components and conditions that were proposed by
the Region in its comments. The additional required mitigation
included the removal of concrete rebar and asphalt rubble from the
banks of the old alignment; the planting of live willow stakes
along the banks of the creek; and the lowering of a mixed upland
area between the old and new channels to allow additional ponding
and wetland enhancement. The permit also included several special
conditions proposed by the Region. These included a requirement
for a monitoring period of at least 3 years or until the site met
success criteria of an 80% survival rate for plantings, 85% wetland
species coverage, and maximum 10% occurrence of noxious weeds. The
District was required to submit annual reports to the Corps
documenting the progress of the mitigation areas. Finally, the
permit required that a deed restriction be placed on the property
to prevent any man-made activities that could damage or eliminate
the mitigation wetlands on the site. (Ex. 31).
26. Following issuance of the permit, the District initially
took the position that it should not proceed with construction of
the mitigation project until the deed restriction had been recorded
by the City of Lafayette, the owner of the land. The Region urged
the District to proceed without waiting for the City to record the
restrictive covenant. The Region and District were aware that the
City's legal staff was working on the deed restriction language in
late 1994 and early 1995. The District then proceeded to perform
the mitigation work in March of 1995, although the deed restriction
had not been recorded. This was the next suitable time window for
successful planting of willows and wetland vegetation, before high
runoff later in the spring. The deed restriction still had not
been recorded as of the dates of the hearing in July 1997. (Exs.
31, 32, 33, 34; Tr. 368-374, 406, 708-711).
27. Since the completion of the basic mitigation work in March
1995, the District has continued to maintain and monitor the site
as required by the after-the-fact permit. The basic purposes of
the mitigation plan - to restore water into the oxbow channel and
to enhance wetland benefits at the site - have been fulfilled. A
perennial flow of water has been restored to the natural oxbow
channel. Wetland species have become well established in the oxbow
channel and the enhanced wetland between the old and new channels.
The current site with the mitigation work now contains more area of
wetland than it did before the District began the realignment
project in 1993. (Exs. 17, 25, 36; Tr. 602-603, 667).
28. Several components of the mitigation plan have not been
fully successful. The chief problems have been the survival rate
of the willow stakes along the realigned channel, and the invasion
of noxious weeds in the upland area at the top of the bank along
the fence line. The District planted about 900 willow stakes
initially in 1995, and an additional 450 in 1996. High spring
flows in Coal Creek and shading by wetland vegetation prevented
some areas of willows from growing. The willow survival rate has
not met the 80% survival rate criterion as of the summer of 1997.
However, under normal conditions, five growing seasons are required
for willow communities to establish themselves optimally. (Exs.
17, 36; Tr. 386-390, 593-600, 617, 671-674).
29. Weeds, such as Russian thistle and knapweed persist in the
upland area along the top of the bank near the fence line. It is
likely that these weeds have germinated from seeds blown in from
off the site. The District has been mowing this area at times
recommended by its consultant, to suppress weed growth. (Exs. 17,
36; Tr. 388-390, 595-596).
30. The District has continued active maintenance of the
mitigation site. In addition to mowing weeds in the upland area,
these activities include maintaining the slide gate to the oxbow,
removing debris, and monitoring the growth of wetland vegetation.
(Ex. 17).
31. The cost to the District in constructing the mitigation
project at the site was about $35,000. The District incurred
annual site maintenance costs in 1996 of about $6500, of which
about $2000 is expected to be recurring. If those expenses are
considered to have been deferred from the time of the original
construction in March 1993, the District realized an economic
benefit from such deferral of approximately $10,500 as of December
1997. The District paid Kemp & Hoffman about $37,500 for its work
in performing the original channel realignment work, of which Kemp
& Hoffman retained about $1450 as its profit. If that is
considered a wrongful profit obtained in March 1993, its present
value in December 1997 would be about $2500. The combined economic
benefit to the respondents as a result of the Coal Creek
realignment, under this analysis, was thus approximately $13,000.
(Exs. 16, 17, 18, 20; Tr. 256-267).
- Hydrology and Headwaters of Coal Creek
32. In its Answer to the Complaint, filed on May 31, 1994, the
District took the position that the City of Lafayette shops site
was above the "headwaters" point on Coal Creek, as that term is
defined in the Corps' regulations at 30 CFR §330.2(d). The
District thus asserted that the Coal Creek project did not require
an individual CWA §404 permit, since the discharge of fill in
headwaters is authorized by Nationwide Permit 26. The District
took this position after investigation by its engineering
consultant, Kenneth Wright, P.E., indicated to the District that
there was a reasonable possibility that the average flow in Coal
Creek at the site was less than 5 cubic feet per second ("cfs").
This information led the District to reverse its earlier
acknowledgments, in correspondence to the Corps (dated June 23,
1993), and at a District Board of Directors meeting (on September
16, 1993), that it had failed to obtain the proper permit, and that
Coal Creek at that location was in fact a "5 cfs" stream. (Answer
of District, ¶32; Exs. 10, 41; Tr. 456-461).
33. Coal Creek originates on the east slope of the Front Range
of the Rocky Mountains about 20 miles southwest of Lafayette.
Beginning in small feeder creeks at elevations ranging up to 10,000
feet above sea level, it flows southeastward about seven miles
through the mountains and foothills in a narrow canyon. It then
leaves the mountains in the vicinity of a location known as
Plainview, at an elevation of 6540 feet. The course of Coal Creek
then turns generally northeastward across the rolling high plains
of Colorado between the cities of Boulder and Denver. It passes
the community of Louisville, and then, some 13 miles after its exit
from the mountains, reaches the City of Lafayette shops site at an
elevation of 5230 feet. Downstream, Coal Creek is tributary to
several other creeks, which, in turn, are tributary to the South
Platte River. The South Platte River flows into Nebraska, where it
joins the North Platte River, forming the Platte River. The Platte
flows into the Missouri River near Omaha. The Missouri is the
largest tributary to the Mississippi River, joining it near St.
Louis. The Mississippi River flows into the Gulf of Mexico south
of New Orleans. (Exs. 2, 13, 43; Tr. 481-482).(2)
34. The United States Army Corps of Engineers, as authorized
by the Clean Water Act §404(e), has established a series of
nationwide permit categories that do not require individual permit
applications. One of these categories is for the discharge of fill
in "headwaters" reaches of streams, or isolated waters, known as
Nationwide Permit 26. The Corps' regulations define "headwaters"
as "non-tidal rivers, streams, and their lakes and impoundments,
including adjacent wetlands, that are part of a surface tributary
system to an interstate or navigable water of the United States,
upstream of the point on a river or stream at which the average
annual flow is less than five cubic feet per second." The
regulations further state that the Corps' District Engineer "may
estimate this point from available data by using the mean annual
area precipitation, area drainage basin maps, and the average
runoff coefficient, or by similar means." 33 CFR §330.2(d).
35. The Corps has made such designations of headwaters points
on streams throughout the United States. For Colorado, the Omaha
District Office has printed a computer-generated list of all the
streams in the state over which the Corps has jurisdiction, with
their headwaters points. The headwaters point for Coal Creek was
determined by a now retired Corps employee, Bud Nelson, in 1982.
The headwaters for Coal Creek is listed as upstream of the point
where the creek crosses the south section line of Section 32,
Township 1, Range 70 West, in Boulder County, Colorado. This point
also coincides with the county line forming the boundary between
Jefferson and Boulder Counties. The headwaters point is about 3
miles downstream from Coal Creek's exit from the mountains, and
about 10 miles upstream from the City of Lafayette shops site.
(Exs. 2, 7, 8; Tr. 80-91, 165).
36. Interested persons may challenge the Corps' designations
of headwaters on a specific stream. In that event, the Corps may
review any new data and change its headwaters designation. No
party had ever challenged the headwaters designation for Coal Creek
before this proceeding. (Tr. 92-94, 141).
37. From 1961 until 1996, the United States Geological Survey
maintained a stream gage on Coal Creek at Plainview, virtually at
the point where the creek exits the mountains. The gage recorded
daily average flows for that period, except during some of the fall
and winter months of the years 1988 to 1995, when the gage did not
operate. The records also give the mean, or arithmetic average
flows, in cubic feet per second, for each month. The records are
organized by "water years," defined as from October of the prior
year to September of the cited year. (Ex. 14).
38. On the date that the District began construction of the
realignment of Coal Creek at the City shops, March 17, 1993, the
gage at Plainview was not yet operating since the preceding winter.
It began operation on March 22, 1993, when the average flow at
Plainview was recorded as 1.4 cfs. The flow increased gradually
each day to 5 cfs on March 31, and 12 cfs on April 8, 1993, the
date on which the work on Coal Creek was completed. (Ex. 14).
39. The gage records show that Coal Creek's flows fluctuate
greatly throughout each water year, and from year to year. The
flow is uniformly highest in the spring, coinciding with snowmelt
and peak runoff from the mountain drainage basin above the gage.
The highest mean flows are in May, at about 25 cfs, followed by
April and June, at about 13 and 10 cfs, respectively. The mean
flows drop sharply throughout the rest of the year, ranging from
2.8 cfs in March, down to 0.7 cfs in September. In several
Septembers, the gage recorded zero flow in Coal Creek. Because the
flow in Coal Creek fluctuates so greatly, and is extremely low for
much of the year, it is considered unable to support aquatic life
by the State of Colorado Board of Water Resources. (Ex. 13, Table
2; Tr. 208, 510).
40. The mean flow at the Plainview gage from 1960 to 1987, the
period of complete records, was 5.03 cfs. With interpolated
values inserted for the missing months from 1988 to 1996, the mean
flow from 1960 to 1996 was 4.78 cfs. The period from 1960 to
1981, providing the data available to the Corps at the time of its
1982 designation, was somewhat drier. The mean annual flow at the
gage during that period was 4.57 cfs. The average annual flow at
the gage changes from year to year, as each year's data is added.
Coal Creek's annual mean flows varied from a minimum of 0.55 cfs in
water year 1966 to a maximum of 14.75 in 1983. In the entire 37-year period, the annual mean flow at Plainview exceeded 5 cfs in 12
years, and was below 5 cfs in 25 years. The flow exceeded 10 cfs
in 5 water years. (Ex. 13, Tables 1 and 2; Ex. 14; Tr. 171, 208).
41. The area of the Coal Creek drainage basin above the
Plainview gage is approximately 15.1 square miles. The cumulative
drainage basin area above the headwaters point, at the Jefferson-Boulder County line, is about 19.6 square miles. The Coal Creek
drainage basin area above the City of Lafayette shops site is
approximately 35.8 square miles. One method of estimating average
stream flow is to assume that the flow increases downstream in
proportion to the increase in the area of the stream's drainage
basin. Calculated on that basis, Coal Creek's mean annual flow at
the headwaters point would be approximately 6.5 cfs, and at the
City shops, approximately 11.5 cfs. (Ex. 13; Tr. 154-163).
42. This drainage basin area extrapolation method was used by
the Region's consultant, James Reilly, P.E., of Stetson Engineers,
San Rafael, California, to estimate downstream flows in Coal Creek.
Mr. Reilly spoke with Bud Nelson, the retired Corps employee who
made the headwaters designation for Coal Creek in 1982. Mr. Nelson
told Mr. Reilly that he had used that method in determining the
headwaters point for Coal Creek. (Tr. 167-170).
43. As indicated earlier, the Plainview gage is located at the
point where Coal Creek leaves the Rocky Mountain foothills and
enters the Great Plains. There are major physiological,
climatological, and hydrological differences in the
characteristics between Coal Creek's upper drainage basin, above
the gage, and its lower basin, between the gage and the City of
Lafayette. The Coal Creek upper basin is characterized by steep,
forested slopes and shallow soils overlying metamorphic bedrock.
Elevations in the upper basin range from 6500 to over 10,000 feet
above sea level, and average 8500 feet. In the lower basin,
elevations range 5200 and 6500 feet, and average 5800 feet. The
lower basin (except for a small area in the immediate vicinity of
the gage that consists of steep foothills) is characterized by
relatively flat or gently rolling grassland, with deep soils
overlying sedimentary rock. Precipitation in the upper basin
averages 20 inches per year. Precipitation in the lower basin
averages 16 inches per year. In short, the upper basin consists of
relatively well watered mountain terrain, while the lower basin is
a semiarid plain. (Ex. 43; Tr. 228-230, 481-483).
44. These differences between the upper and lower basins
result in a greater runoff coefficient in the upper basin than in
the lower basin. A greater proportion of precipitation per unit of
land area will appear in surface water streams in the upper basin
than in the lower basin. This means that the method of
extrapolating downstream flows, based on the Plainview gage records
and drainage basin area, will tend to overestimate flows downstream
of the gage, in the lower basin. (Tr. 230, 519, 542-544, 553).
45. The District's consultant, Kenneth R. Wright, P.E., of
Wright Water Engineers, Denver, Colorado, conducted a study in
which he endeavored to quantify the actual average flow in Coal
Creek, at the City shops, under both developed conditions and
natural conditions. Mr. Wright is an eminent hydrological engineer
with over 40 years of professional experience in the Denver and
Boulder areas, including extensive work on Coal Creek itself. The
effects on Coal Creek flow that Mr. Wright considered included,
generally: in-basin and out-of-basin diversions; wastewater
treatment plant effluent; lower basin inflow; and losses to
alluvium, to a deep aquifer, underflow, stream evaporation, and
transpiration by riparian vegetation. His study encompassed the
period of the Plainview gage records, beginning in 1960, until the
year of the alleged violation, 1993. (Exs. 44, 45).
46. Under "natural" conditions, i.e., without considering man-made diversions and development, Coal Creek loses some of its flow
in the lower basin due to hydrogeological factors that are typical
of streams in a semiarid environment. Coal Creek sustains a loss
of flow shortly after leaving the mountains to a thick gravel
deposit known as the Rocky Flats alluvium. Additional significant
losses occur downstream to the Fox Hill sandstone, a deep regional
aquifer. Coal Creek also loses flow to the uptake of water by
riparian vegetation, evaporation from its surface, and underflow to
the alluvium in its flood plain. The combined annual loss from
these natural conditions remains constant at about 732 acre feet,
or a bit more than one cfs per year.(3) (Ex. 44; Tr. 491-497).
47. Man-made development in the Coal Creek basin has created
sources of both losses and gains to the flow in the stream. The
chief source of losses are diversions taken directly from Coal
Creek by way of ditches constructed by water rights holders,
including farmers, ranchers, and municipalities. A series of such
ditches located about a half-mile downstream from the Plainview
gage conveys water from Coal Creek entirely out of its basin and
into the neighboring Big Dry basin, where it is stored in
reservoirs or otherwise used by the appropriators. None of this
water is returned to Coal Creek from these out-of-basin diversions.
The records of the Colorado State Engineer show large annual
variations in the amounts of water cumulatively taken from Coal
Creek for these out-of-basin diversions. The amounts vary from
2657 acre-feet in 1960 to none in several years. The average loss
from these out-of-basin diversions from 1960 to 1993 was at least
927 acre-feet per year, or approximately 1.28 cfs.(4) (Ex. 45; Tr.
484-489).
48. Further downstream are several additional ditches that
divert water from Coal Creek for irrigation within the lower basin.
It may be assumed that about half of that water will return to Coal
Creek after its use on crops in the basin. The amounts of these
diversions, which also vary widely from year to year, are also
recorded by the State Engineer. The annual average net effect on
Coal Creek from these in-basin diversions is a loss of about 479
acre-feet, or 0.66 cfs. (Ex. 45; Tr. 490).
49. A major source of gain to the flow of Coal Creek in the
lower basin is the discharge of effluent from the City of
Louisville Wastewater Treatment Plant, located about two and one-half miles upstream from the City of Lafayette shops. The
discharge from the Louisville plant has increased markedly in
recent years, as the population of Louisville has grown and the
plant's capacity was expanded. In the three most recent years
recorded by Mr. Wright, 1991-1993, the plant discharged an annual
average of 1880 acre-feet, or about 2.6 cfs, into Coal Creek. For
the entire period from 1960 to 1993, the plant's average annual
discharge into Coal Creek was approximately 771 acre-feet, or 1.06
cfs. (Ex. 45; Tr. 498-499).
50. The assessment of flows in Coal Creek must also include
direct inflow into the stream from precipitation falling in the
lower basin. Mr. Wright used a runoff coefficient of 0.04 in his
calculations for natural conditions, assuming no human development
in the 19.9-square mile lower basin. With an average precipitation
of 16 inches per year, the average annual inflow to Coal Creek
under natural conditions would be about 466 acre-feet, or 0.64 cfs.
Man-made development creates areas of relatively impervious
surfaces, such as streets and rooftops, that accelerate runoff and
increase the proportion that finds its way to surface streams.
Inflow to Coal Creek thus increases with the increase in developed
area within the basin. Mr. Wright used an average runoff
coefficient for urban areas of 0.28 to calculate the annual lower
basin inflow into Coal Creek under developed conditions. He used
aerial photographs to estimate the increases in developed area in
the basin during this period. This calculation indicated an
increase from about 706 acre-feet in 1960 to 953 acre-feet in 1993.
The average annual inflow for the entire period was 776 acre-feet,
or about 1.07 cfs. (Exs. 44, 45; Tr. 503, 543-546).
51. The analysis of Coal Creek's flow by Mr. Wright indicates
that the average discharge of the stream declines somewhat at the
City shops, relative to the Plainview gage, under both natural and
developed conditions. For the period from 1960 to 1993, under
natural conditions, the average annual flow at the City shops as
calculated by Mr. Wright was 4.3 cfs. Under developed conditions,
it was 3.9 cfs. The flow at the gage averaged 4.7 cfs during this
period. In some water years, however, particularly the more recent
ones, the average flow at the City shops exceeded that at the gage,
primarily due to increased inflow from the Louisville wastewater
treatment plant. (Exs. 44, 45).
Discussion
- Liability - Headwaters of Coal Creek
The parties have stipulated that Coal Creek and its adjacent
wetlands at the City of Lafayette shops site comprise "navigable
waters" as defined in the Clean Water Act §502(7), 33 U.S.C.
§1362(7), and "waters of the United States" as further defined at
33 CFR §328(a,b). The essential facts concerning the Respondents'
actions at the Coal Creek site are also not disputed. The Urban
Drainage and Flood Control District, through its contractor, Kemp
& Hoffman, Inc., discharged fill into Coal Creek and its adjacent
wetlands, in the course of rerouting the flow of Coal Creek into a
newly constructed channel. Neither the District nor Kemp & Hoffman
obtained an individual permit from the United States Army Corps of
Engineers, pursuant to Section 404 of the Clean Water Act, 33
U.S.C. §1344, before constructing this project.(5)
The Complaint alleges that the Respondents violated Section
301(a) of the Clean Water Act, 33 U.S.C. §1311(a). That statute
renders unlawful the discharge of any pollutant, except as in
compliance with several sections of the CWA, including Section 404,
33 U.S.C. §1344. The liability of the District turns on its
defense that it was not required to obtain an individual permit
under that section because its project was authorized under the
"headwaters" nationwide permit, known as Nationwide Permit 26. The
District is not precluded from raising this defense although it
became aware of it only after the construction of the Coal Creek
project. (See Finding of Fact, "FF," #32).
The District contends that the evidence it offered at the
hearing demonstrates that the City shops site was in the headwaters
area of Coal Creek. If that is so, the project would have
qualified under Nationwide Permit 26, and would have been exempt
from the requirement to obtain an individual permit under the CWA
§404. The Respondent bears the burden of proving the facts showing
the applicability of the nationwide permit. U.S. v. Cumberland
Farms of Connecticut, Inc., 826 F.2d 1151, 1157 (1st Cir., 1987).
While the District has informed the record with substantial factual
information on factors influencing flows in Coal Creek, it has not
succeeded in showing that its project qualified under the
headwaters nationwide permit. The District is therefore liable for
constructing this project without having obtained an individual
permit as required by the CWA §404.
Subsection (e) of the CWA §404, 33 U.S.C. §1344(e), authorizes
the Secretary of the Army to issue general permits on a State,
regional, or nationwide basis, for the discharge of fill into the
waters of the United States. Such general nationwide permits
("NWPs") may be issued for categories of activities determined to
cause only minimal adverse environmental effects. One of those
categories is that entitled Headwaters and Isolated Waters
Discharges, NWP 26. Nationwide Permit 26, at the time of the
construction of the Coal Creek project, allowed discharges of
dredged or fill material into headwaters and isolated waters
provided the discharge would not cause the loss of more than 10
acres of waters. The project sponsor was further required to
notify the District Engineer if the discharge would cause the loss
of more than 1 acre of waters of the United States.(6) 56 FR 59110,
November 22, 1991.
The term "headwaters" is defined as follows at 33 CFR
§330.2(d):
Headwaters means non-tidal rivers, streams, and
their lakes and impoundments, including adjacent
wetlands, that are part of a surface tributary system to
an interstate or navigable water of the United States
upstream of the point on the river or stream at which the
average annual flow is less than five cubic feet per
second. The DE [District Engineer] may estimate this
point from available data by using the mean annual area
precipitation, area drainage basin maps, and the average
runoff coefficient, or by similar means. For streams
that are dry for long periods of the year, DEs may
establish the point where headwaters begin as that point
on the stream where a flow of five cubic feet per second
is equaled or exceeded 50 percent of the time.
The District Engineer in Omaha estimated the headwaters point on
Coal Creek in 1982, at a location approximately 10 miles upstream
from the City of Lafayette shops site. The record shows that this
was a reasonable estimate, in conformance with the regulatory
definition of headwaters.
The definition, in its use of the word "estimate," indicates
that precision is not required in making headwaters designations.
Indeed, precision would be impossible. The Corps explicitly
recognized as much in its re-promulgation of the headwaters
definition in 1991, as follows:
It should also be noted that precision is not required in
establishing the five cubic feet per second point. The
definition allows the DE to use approximate means to
compute it. The drainage area that will contribute an
average annual flow of five cubic feet per second can be
estimated by approximating the proportion of the average
annual precipitation that is expected to find its way
into the stream. Having the area that will produce this
flow, the five cubic feet per second point can be
approximated from drainage area maps. 56 FR 59112-59113,
November 22, 1991.
The mean annual flow in rivers and streams is naturally variable.
The Corps regulations recognize that flow rates can appropriately
be determined by estimating runoff per unit of drainage basin area.
The Region's consultant, James Reilly, followed the method
used by the Corps in determining the headwaters point. The
District's consultant, Kenneth Wright, used a more analytical
approach. Both expert witnesses, however, agreed that it was
appropriate to use the Plainview stream gage records as the
starting point for estimating flow in Coal Creek at downstream
locations. The actual flow records obviate the need to use a
runoff coefficient for the drainage basin above the gage, since the
actual drainage basin area and flow rate are known at that point on
the stream. The experts differed, however, in their methods for
estimating downstream flows.
Mr. Wright certainly took a more sophisticated and analytical
approach than did Mr. Reilly in his estimates. Mr. Reilly's
method, however, was more consistent with the intent of the Corps'
regulations. He computed the point by extrapolating flow rates
based on the creek's drainage basin area. Mr. Wright's analysis of
streamflow was also an approximation, albeit a more sophisticated
one. Even assuming the complete accuracy of his results, Coal
Creek at the City shops still had a mean annual flow greater than
4 cfs.
Mr. Wright's study is not however unimpeachable. He relied on
many assumptions and generalized calculations of stream loss, and
did not give ranges of values or margins of error for his
calculations. He did not survey wells or the water table in the
vicinity of the stream. This information could have indicated
whether groundwater baseflow may contribute to the flow in any
reaches of Coal Creek.(7) It is not clear whether certain of the
losses calculated by Mr. Wright might have been accounted for more
than once. (Tr. 537). In addition, Mr. Wright did not fully
account for the cumulative change in the nature of the drainage
basin as one proceeds downstream. (Tr. 546). But these points
are mere quibbles. There is no question that Mr. Wright's estimate
of the flow at the headwaters point or the City shops is closer to
the actual reality than that estimated by Mr. Reilly's
extrapolation method.
However, even if it is assumed that Mr. Wright's estimate is
fully accurate, the flows in Coal Creek between the gage and the
City shops were still in the range of 4 to 5 cfs. Neither party
provided a range of values nor a margin of error for their
calculations, although all values are estimates. Given the
variability in flow in Coal Creek, and the known fact that average
flows at the gage are approximately 5 cfs, the Corps' headwaters
determination must be considered reasonable and consistent with the
regulations.
The definition of headwaters at 33 CFR §330.2(d), including
its suggested method for determining headwaters points, is not
designed to be completely comprehensive or absolute. It does not
explicitly account for various types of streamflow regimes, such as
those, common in the arid West, that may lose flow downstream. The
Corps did, however, account for arid conditions in its definition
of headwaters. The last sentence of 33 CFR §330.2(d) recognizes a
category of streams that could be dry much of the year, again most
commonly in arid regions. For those streams, the headwaters point
is to be estimated as the median point where flows exceed 5 cfs,
rather than the point where mean flows exceed 5 cfs.
The designation of headwaters "upstream" from the 5 cfs point
assumes that streams will generally gain flow downstream. The
definition of headwaters only allows for a single headwaters point,
with the headwaters area upstream from that point, regardless of
downstream fluctuations in flow. Although some streams may lose
flow downstream, that will not necessarily affect the headwaters
determination. The Corps has recently affirmed its intent to
retain the current definition of headwaters in the regulations,
including its estimating methodology for determining the 5 cfs
point.(8)
The definition of headwaters also does not explicitly address
the effect of man-made diversions and contributions to the flow in
rivers and streams. However, the methods cited for estimating the
flow only refer to precipitation, drainage basin area and runoff
coefficients. These factors may be considered without reference to
man-made development. The record indicates that the Corps did not
consider man-made diversions in its estimates. A neutral reading
of the definition lends at least equal support to the Region's
position that such consideration of only "natural" conditions is
appropriate.(9)
The District undertook an arduous task in seeking to sustain
its burden of proving that the Corps' headwaters determination for
Coal Creek should be disregarded. Reviewing courts must accord
agency actions a presumption of regularity. See Citizens to
Preserve Overton Park, Inc., v. Volpe, 401 U.S. 402, 415 (1971).
The Administrative Procedure Act limits judicial review of agency
decisions to whether they are "arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law." 5 U.S.C.
§706(2). Courts will defer to federal agencies' decisions in
matters generally committed to their expertise and discretion,
unless an abuse of discretion is shown. See Avoyelles Sportsmen's
League, Inc. v. Marsh, 715 F.2d 897, 904 (5th Cir. 1983). These
review standards have been held to specifically apply to the Corps'
interpretations of the applicability of nationwide permits.
Orleans Audubon Society v. Lee, 742 F.2d 901, 907 (5th Cir. 1984).
Review in this proceeding, and by the Administrator of the EPA, of
a decision by a sister agency, the Corps of Engineers, should be
guided by the same principles.
The Corps is charged with the duty to determine headwaters
points on thousands of rivers and streams throughout the United
States.(10) It carries out this duty by using drainage basin maps,
precipitation data, and runoff coefficients. Where stream gage
data is available, that can be substituted for the use of runoff
coefficients. The Corps does not consider additional factors that
could influence flows, such as man-made diversions and
contributions, and hydrological conditions specific to each
stream. This interpretation is practical, reasonable and
consistent with the regulatory definition of headwaters in 33 CFR
§330.2(d), which provides for only a single headwaters point on
each stream. It would be impractical and inefficient for the Corps
to undertake a detailed hydrological study of each stream to
determine their headwaters areas.
The regulatory definition of headwaters at 33 CFR §330.2(d)
provides a suitable method for making headwaters determinations.
The Corps followed that method in determining the headwaters point
on Coal Creek. The Corps' headwaters determination for Coal Creek
was thus reasonable, and cannot be said to have been arbitrary and
capricious or an abuse of discretion.
It is unnecessary to speculate on what type of showing would
be required in order to justify disregarding a Corps' headwaters
determination. Many factors unique to each case would have to be
considered. Respondents are certainly not precluded from
attempting to show that a Corps' headwaters estimate was in error
to the extent that it was arbitrary and capricious, and should be
disregarded. In this case, however, the evidence shows that the
Corps' estimate was based on gaged flows averaging approximately
5 cfs. The determination of a headwaters point some three miles
downstream of the gage was reasonable and consistent with the
definition of headwaters at 33 CFR §330.2(d).
The decision in Cumberland Farms, supra, does not provide any
reason to alter this conclusion. The District asserts that that
case provides authority for the proposition that a respondent may
seek to establish the headwaters point with "pinpoint" accuracy.(11)
In Cumberland Farms, however, the Corps had apparently not made
specific headwaters determinations for the streams at issue on the
Cumberland Farms property. The Court upheld the district court's
finding that respondent had failed to meet its burden of showing
where on its property the flows fell below 5 cfs. 826 F.2d 1157.
In the district court, the discussion on methodology for locating
the headwaters points evinced an exclusive reliance on drainage
basin maps, based on a gaged flow downstream of the property.
United States v. Cumberland Farms of Connecticut, Inc., 647 F. Supp
1166, 1177 (D. Mass. 1986).
In this proceeding, where the Corps has already made a
headwaters determination on the subject stream, Respondent's burden
of proof is greater than the respondent's in Cumberland Farms. The
District must not only provide evidence on flows in Coal Creek, but
that evidence must also show that the Corps' determination was
arbitrary and capricious. The evidence here will not support such
a conclusion. Even assuming the complete accuracy of the
District's expert's conclusions, average flows exceeded 4 cfs and
approached 5 cfs at points upstream from the project site. The
mean annual flow at the gage itself was indisputably 5 cfs when
rounded to the nearest whole number, for any of the time periods
under consideration.
For these reasons, the Corps' determination of the headwaters
point on Coal Creek will not be disturbed. The District's
realignment of the channel of Coal Creek at the City of Lafayette
shops site took place 10 miles below the headwaters of Coal Creek.
Therefore Nationwide Permit 26 did not authorize this project. The
District is thus liable for the discharge of fill into the waters
of the United States without having obtained the required permit
pursuant to the CWA §404. This constitutes a violation of the CWA
§301(a), 33 U.S.C. §1311(a).
- Liability of Kemp & Hoffman
Violators of the Clean Water Act are held to a standard of
strict liability for civil violations. United States v. Earth
Sciences, Inc., 599 F.2d 368, 374 (10th Cir. 1979). Such civil
liability may be "predicated on either (1) performance, or (2)
responsibility for or control over performance of the work, in the
absence of the necessary federal permit." United States v. Board
Of Trustees of Florida Keys Community College, 531 F. Supp. 267,
274 (S.D. Fla. 1981). The Corps' enforcement regulations speak in
terms of "parties responsible for violations." See 33 CFR
§326.3(c).
Under these standards, the Respondent Kemp & Hoffman must also
be held liable for the violation at issue in this case. A
contractor has a responsibility to ensure that work it is doing is
authorized by the appropriate permits. Indeed, the contract
between the District and Kemp & Hoffman specifically provided as
much. (FF #15). The following reasoning in Florida Keys Comm.
College, supra, cannot be disputed:
Nor does the application of the statutes impose an
unreasonable burden on construction companies. The
companies may protect themselves merely by requiring a
copy of the necessary permits to be shown to them prior
to commencement of the work. 531 F. Supp. 274.
If Kemp & Hoffman had required the District to actually display a
copy of the Corps permit before commencing the work, this entire
violation might have been avoided.
It is not disputed here that Kemp & Hoffman completely relied
on the District's permitting in past projects, and was told that a
permit had been obtained for the Coal Creek work. (FF #15). This
does not completely absolve a contractor from all responsibility to
ensure that the proper permit has been obtained. In very similar
circumstances, a contractor was held liable for discharging fill
into a wetland without a permit although he had been told by the
landowner that the Corps permit had been obtained. United States
v. Van Leuzen, 816 F.Supp. 1171, 1175 (S.D. Texas, 1993).
Therefore, Kemp & Hoffman is also found liable for a violation
of the CWA §301(a) for discharging fill into a water of the United
States without a permit issued by the Corps pursuant to the CWA
§404. However, as in both Florida Keys Comm. College and Van
Leuzen, the contractor's degree of culpability was far lower than
that of the party controlling the conduct of the work, in this case
the District. The facts surrounding the parties' relative
culpability for the violation will be discussed below in the
context of determining their appropriate civil penalties.
- Civil Penalty
Having determined that the Respondents are liable for the
violation alleged, I turn to the determination of the appropriate
amounts of the civil penalties to be assessed. The CWA §309(g)(3)
sets forth the factors the Administrator must take into account in
assessing civil penalties for CWA violations in administrative
enforcement proceedings:
In determining the amount of any penalty assessed under
this subsection, the Administrator . . . shall take into
account the nature, circumstances, extent and gravity of
the violation, or violations, and, with respect to the
violator, ability to pay, any prior history of such
violations, the degree of culpability, economic benefit
or savings (if any) from the violation, and such other
matters as justice may require.
The Region has proposed that a civil penalty of $125,000, the
maximum for a Class II penalty under the CWA §309(g)(2)(B), be
assessed jointly and severally against the two Respondents in this
matter. The Respondents argue that, if they are found liable for
the violation, any penalty should be minimal or limited to the
costs already incurred for site mitigation.
The EPA Rules of Practice for administrative enforcement
proceedings require the Administrative Law Judge to consider any
civil penalty guidelines issued under the applicable Act. The EPA
has not promulgated any civil penalty guidelines specific to the
Clean Water Act. The Region does, however, cite two companion
documents promulgated to guide the EPA enforcement staff generally
in the assessment of civil penalties. These are entitled: Policy
on Civil Penalties (the "Penalty Policy"), and A Framework for
Statute-Specific Approaches to Penalty Assessments: Implementing
EPA's Policy on Civil Penalties (the "Penalty Framework"), both
dated February 16, 1984.
The "nature, circumstances, extent and gravity" of the
violation will be considered initially as the "gravity component"
of the violation, as committed by both Respondents. The remaining
statutory factors -- ability to pay, culpability, economic benefit,
prior violations, and other matters as justice may require -- will
be considered as "adjustment factors" with respect to the penalty
amount. The adjustment factors will be considered separately for
each Respondent. The overall approach, consistent with the Penalty
Framework, will be to derive a base penalty amount, based on the
gravity of the violation, which may then be modified and
apportioned between the two Respondents based on the adjustment
factors.
- Nature, Circumstances, Extent and Gravity
The nature, circumstances, extent, and gravity of the
violation focus essentially, on the seriousness of the violation.
The seriousness of the violation at issue here -- the discharge of
fill into waters of the United States without a permit -- depends
primarily on the actual or potential harm to the environment
resulting from the violation. The importance of the violated
requirement to the regulatory scheme must also be considered.
In the particular circumstances of the Coal Creek project, the
assessment of environmental harm arising from the violation alone
must be considered first. The ultimate analysis of the gravity of
the violation, however, must also encompass a consideration of the
degree of success and timeliness of the mitigation plan. The
District performed the mitigation work pursuant to an after-the-fact ("ATF") permit that authorized the original relocation of the
channel of Coal Creek at the site. The violation and its
mitigation should be considered together in ultimately determining
the environmental impact of the violation and gravity component of
the penalty.
The nature of the Respondents' violation in this case is
clear. They relocated the channel of a creek without obtaining the
required individual permit from the Corps pursuant to Section 404
of the Clean Water Act. The Respondents discharged fill into the
actual creek itself and adjacent wetlands, cutting off a meandering
reach of the channel. This activity shortened the length of Coal
Creek, and eliminated natural benthic habitat and a 2350-square
foot area of wetland. The total impacted area was about 30,000
square feet, or three quarters of an acre. (FF #8).
The violation of diverting a natural stream channel without a
permit is, by its nature, a relatively serious one. The Corps
witness, Timothy Carey, testified that the Corps would not normally
grant a permit for such a project, as it would not generally be the
least environmentally damaging alternative for accomplishing the
applicant's objective. (FF #18; Tr. 105-106). In this case, the
goal of halting erosion of the bank below the City shops could have
been accomplished through regrading and reinforcing the natural
meander bank. The District's own consultant, Mary Powell, stated
that, left unmitigated, the site would suffer long term adverse
effects from the channel realignment, and a succession to drier
conditions. (FF #9; Ex. 24; Tr. 608).
On the other hand, the Region produced little substantial
evidence of any specific adverse environmental impacts caused by
the project. The Region's John Brink testified that wildlife
appeared more abundant upstream and downstream from the site, but
he could not say whether that condition existed before construction
of the project. (Tr. 426). The Region did not produce any
eyewitness or expert witness who could compare conditions on Coal
Creek at the City of Lafayette site before and after the stream
channel realignment. It seems probable that the site previously
had a somewhat reduced value for wildlife in any event due to its
close proximity to the City shops maintenance facilities. The City
shops facility is an active light industrial land use. Also, after
the channel relocation but before the construction of the
mitigation plan, some water remained in the oxbow and adverse
impacts did not yet appear significant. (Tr. 586).
In addition, the amount of fill and the size of the impacted
waters and wetlands were relatively small. In one administrative
proceeding where a $125,000 penalty was assessed, the respondent
flooded 75 acres of wetlands, by constructing dikes without a
permit. In re Marshall C. Sasser, 3 E.A.D. 703 (CWA Appeal 91-1,
CJO, November 21, 1991).(12) In another proceeding, in which a
$100,000 total penalty was ultimately assessed, the respondent
filled approximately 6 acres of wetlands without a permit. In re
The Hoffman Group, 3 E.A.D. 408 (CWA Appeal 89-2, CJO, November 19,
1990). The District here filled only about 1/20 of an acre of
wetlands. The entire affected area between the new and old
channels consists of less than an acre. (FF #8). The diversion of
a stream from its natural channel is qualitatively different from
the filling (or flooding) of wetlands. The relocation of a stream
channel and the destruction of wetlands cannot be directly compared
with respect to the magnitude of the violations, or the potential
or actual environmental impacts. Nevertheless, the relative
magnitude of this violation, in the context of the potential
universe of discharges of fill into waters, whether wetlands or
streams, is not at the maximum end of the penalty spectrum.
The ultimate determination on the environmental impacts of
this violation must also include a consideration of the effects of
the mitigation work. One of the elements in this analysis is the
duration of the violation. The violation of the unpermitted
discharge of fill into waters of the United States continues as
long as the illegal fill remains in place. U.S. v. Reaves, 923
F.Supp. 1530 (D. Fla. 1996). In this case, that is from March 1993
when the Coal Creek channel was relocated, until March 1995 when
the District constructed the mitigation plan pursuant to the after-the-fact permit. The Region argues that the violation thus
continued for a period of approximately two years. Since the CWA
§309(g)(2)(B) authorizes penalties of up to $10,000 per day, the
Region argues that the proposed amount of $125,000 is easily
justified.
The concept of daily penalties for continuing violations is
not however meaningful in assessing the gravity of this type of
violation. Any discharge of fill into wetlands or waters will, as
a practical matter, tend to remain for at least the twelve and one
half days required to reach the maximum penalty of $125,000 at
$10,000 per day. The period at issue here, over 700 days, is not
atypical for completion of mitigation work after the unpermitted
filling of a wetland or water of the United States.(13) Rather than
focus on the number of days, the gravity of the violation should be
assessed in the context of the statutory maximum of $125,000. Is
the violation serious enough to merit assessment of the maximum
penalty? The length of time from the violation until remediation
will be discussed further, and in more detail, below in relation to
the District's degree of cooperation.
As mentioned above, the ultimate determination on
environmental impacts and the gravity component of this violation
must also include consideration of the degree of success of the
mitigation plan. The mitigation plan here was completed pursuant
to an ATF permit that authorized the Coal Creek channel relocation,
provided the District completed the specified mitigation work.
It is not disputed that the District carried out all required
elements of the mitigation plan in a competent manner. It is also
not disputed that the basic purpose of the mitigation plan -- the
restoration of wetland hydrology to the oxbow and adjacent areas --
has been accomplished successfully. The site now contains more
high quality wetland than it did before the District relocated the
Coal Creek channel in March 1993. (FF #27).
The only problems with the mitigation work have been the
failure to meet criteria for the survival of willow stakes in some
areas, and for the proportion of weeds in the upland area above the
bank. (FF ##28, 29). These elements of the mitigation plan,
however, are enhancements that augment the environmental values of
the mitigated site. They were not intended to restore or replace
conditions that existed before the violation occurred. (Tr. 429).
As a matter of current permit compliance, the District is certainly
obligated to ensure adequate survival of the willows and to control
weeds. Complete success in meeting these criteria is not expected
anyway, this soon after planting. (FF #28). These requirements
are integral to the proper functioning of the mitigated site as a
whole. The gravity component of the civil penalty should be based
primarily, however, on the overall effect on the wetland and
riparian values that were adversely affected originally by the
violation.
The weight of the evidence, consistent with the testimony both
of the District's Ms. Powell and the Region's Mr. Brink, shows that
the project with the mitigation plan has not resulted in
significant adverse environmental effects to the site. The
restoration of a perennial flow into the oxbow and excavation to
wetland elevations of the adjacent area has increased the site's
wetland area and enhanced its wetland benefits.(14) (FF #27).
In consideration of all these factors, the base gravity
component for the violation here should be in the upper range of
potential penalties, but not at the maximum of $125,000. The
discharge of fill to relocate a stream channel without a permit is
by its nature a serious violation that strikes at the heart of the
Section 404 permit program. The Corps would not ordinarily grant
a permit for such a project. This type of alteration of a natural
stream channel has the potential to cause significant environmental
harm. A significant penalty may be imposed on the basis of
potential environmental risk without necessarily demonstrating
actual adverse effects. U.S. v. Smithfield Foods, Inc., 972
F.Supp. 338, 344 (E.D.Va., 1997).
The gravity of Section 404 violations may be classified as
minor, moderate, or major. Under such a scheme, the violation here
would be a major violation. In terms of dollars, the amount should
therefore be roughly in upper third of the possible range, or
between $75,000 and $125,000. Due to the relatively small size of
the project and the ultimate lack of actual significant adverse
environmental effects with the mitigation plan, the gravity
component of the penalty should be at the low end of the major
violation range. In consideration of all these factors, the
gravity component of the civil penalty for this violation will be
$80,000.
- Culpability
- The Urban Drainage and Flood Control District
The District is the Respondent primarily culpable for
proceeding with the Coal Creek project without obtaining the
required Section 404 permit. Even if the project had remained as
originally conceived, as stabilization of the oxbow bank, the
District proceeded without following its usual procedure of seeking
an advance concurrence from the Corps that the project would be
authorized by a nationwide permit. The District's Mr. Bennetts
then made the decision in the field to relocate the channel of Coal
Creek, also without notifying the Corps in advance. The District
did not notify the Corps until after the Corps first contacted the
District in response to a citizen complaint. In addition, in that
initial telephone conversation, Mr. Bennetts did not make it clear
to Ms. Laney of the Corps that the project had involved a channel
relocation. (FF #16).
The District's actions in this regard can, at best, be
ascribed to a high degree of negligence. Mr. Bennetts testified
that he believed the project was still authorized by Nationwide
Permit 13, for bank stabilization, even after the channel was
relocated. This still does not explain why the District did not
seek a nationwide concurrence in advance, according to its usual
practice. However, the Corps regulations do not require an
applicant to seek such advance concurrence. The District has
acknowledged that it was concerned that the project be constructed
before the onset of high spring runoff. The District's Executive
Director, Scott Tucker, denied, however, that being in a hurry led
the District to deliberately bypass the permit requirement. (FF
#4; Tr. 747-748).
The District and its project supervisors were, or should have
been, fully conversant with CWA permit requirements due to their
extensive experience in the field. In these circumstances, while
I will not infer intentional misconduct, the District has offered
no reasonable excuse for constructing this project without Corps
approval. The headwaters defense was admittedly an afterthought,
asserted for the first time in response to the administrative
Complaint in this proceeding. (FF #32). The circumstances
indicate a combination of expediency and simple inadvertence. The
District was concerned that the project be constructed before the
onset of spring runoff, and simply took the most expedient course
by proceeding without notifying the Corps or following its normal
procedures.
In summary, the District was relatively highly culpable, but
short somewhat of the highest degree of culpability, which would be
intentional disregard of the requirements. In other administrative
proceedings, assessment of the maximum penalty has been based, in
part, on a finding of the respondent's wilful disregard of the
permit process or Clean Water Act requirements.(15) The high degree
of negligence here might justify some increase in the base penalty
amount. However, as discussed below, any such increase would be
offset by the District's degree of cooperation and willingness to
perform mitigation work on the site.
- Kemp & Hoffman
It is not disputed that Kemp & Hoffman had absolutely no input
in the decision to relocate the channel of Coal Creek or control
over the course of the project in any way. Kemp & Hoffman was
simply the contractor retained by the District to carry out the
District's project for the City of Lafayette. The company's only
error was to rely on the District's past practice and verbal
assurances that the appropriate federal permit had been obtained,
rather than insisting on seeing the permit.
As discussed above, the law does, however, render a contractor
liable for the discharge of fill into a water of the United States
without a permit in these circumstances. The law will, however,
recognize the difference in the culpability between the project
supervisor and the contractor, in the assessment of penalties.
Federal courts have assessed significantly lower penalties against
contractors than against project sponsors in similar
circumstances.(16)
The degree of culpability of Kemp & Hoffman was a full order
of magnitude below that of the District in the circumstances here.
Therefore the civil penalty should be apportioned between them so
that the penalty paid by the District is more than ten times that
paid by Kemp & Hoffman. The assessment of the $80,000 civil
penalty will thus be apportioned as follows: $75,000 for the
District and $5000 for Kemp & Hoffman.
- Economic Benefit
Civil penalties should, at a minimum, recoup any economic
benefit the violator has accrued as a result of the violation. The
Region presented an expert witness, James Fagan, who derived the
economic benefit accruing to both Respondents as a result of this
violation. Mr. Fagan estimated the gain to the District as a
result of its deferred compliance and maintenance costs incurred in
relation to the mitigation plan. For Kemp & Hoffman, he calculated
the current value of its profit earned on the Coal Creek project.
(FF #31). These methods of calculating economic benefit from
violations have been recognized as valid by the Environmental
Appeals Board and federal courts.(17) Although Mr. Fagan's analysis
was not fully disclosed to Respondents before the hearing, they had
ample opportunity to respond, and were not prejudiced by his
testimony.
One reason Respondents are not prejudiced by the economic
benefit analysis is that it will not lead to any increase in the
penalty. Mr. Fagan found an economic benefit to the District of
about $10,500, and to Kemp & Hoffman of $2500. The respective
gravity-based penalties of $75,000 and $5000 for the Respondents
are already sufficiently in excess of their economic benefit, such
that no further adjustment on this basis is warranted.
- Prior History of Violations
In over 20 years of working with the Corps and EPA in
constructing projects governed by the Clean Water Act, the District
has not previously paid a civil penalty or been subject to a formal
enforcement proceeding. Until this proceeding, the only blemish on
its record was the issuance of an ATF permit in 1987 for "emergency
bank stabilization" on the South Platte River. (FF #13).
The Penalty Framework lists the following factors for
consideration in determining any adjustment to a civil penalty for
prior violations: similarity of the previous violation(s); their
recency; number of prior violations; and the violator's responses
or corrections of previous problems. (Penalty Framework, p. 21).
While there may be some similarity between the 1987 ATF permit and
the violation in this case that also resulted in issuance of an ATF
permit, the other factors militate against increasing the
District's penalty on this basis. This single possible violation,
which took place some six years before the instant one, does not
indicate any pattern of non-compliance. Indeed, in view of
District's extensive work under the Clean Water Act, the 1987
incident, as well as the instant violation, are more logically
viewed as aberrations.
In addition, the record does not include a full description of
the circumstances of the 1987 ATF permit.(18) On its face, the
project entailed emergency bank stabilization work. The record
does not disclose whether the District had some justification for
proceeding with the project before obtaining a permit, due to
emergency conditions. In any event, the EPA did not initiate any
enforcement action on the basis of the 1987 ATF permit for the
District's bank stabilization work on the South Platte River. The
District promptly responded by obtaining the appropriate ATF permit
and, so far as is known, complying with its conditions. In view of
all these factors, the single ATF permit issued to the District in
1987 does not provide sufficient reason to increase the proposed
civil penalty.
Kemp & Hoffman had no prior history of any type of violation
of the Clean Water Act. Hence this factor will have no effect on
the penalty assessed against this Respondent.
- Ability to Pay
The District has ample funds and assets that will enable it to
pay a penalty of the magnitude here proposed. (FF #1). In view of
this ability to pay, no special consideration will be given to the
fact that the District is a public, taxpayer-funded, agency that
provides beneficial services in the Denver metropolitan area.
Kemp & Hoffman also has sufficient ability to pay the smaller
penalty assessed by this decision. (FF #6).
Other Factors - Degree of Cooperation
The CWA §309(g)(3) cites "other factors as justice may
require" as a final consideration in assessing a civil penalty for
administrative violations. One of those factors is the
respondent's degree of cooperation with the EPA in rectifying its
violations. The Agency will recognize a respondent's cooperative
attitude and willingness to correct environmental problems, in
mitigation of civil penalty amounts. (See Penalty Framework, p.
19-20).
In this proceeding, the Region and District took opposing
views of the District's degree of cooperation in implementing the
mitigation plan to correct the environmental problems caused by the
Coal Creek channel relocation project. The Region argues that the
District was recalcitrant and delayed the final implementation of
the mitigation plan. The District responds that it did complete
the mitigation plan in an expeditious manner, consistent with its
obligations as a taxpayer-funded public agency. An objective
overview of the course of dealing between the two parties reveals
essentially a normal arms-length negotiation process, in which each
party sought to reach a mutually satisfactory resolution. The
District at no time took a recalcitrant tone or intimated it was
not willing to perform appropriate mitigation at the site.(19)
The record does not support the Region's contention that the
letter from the District of December 3, 1993 created a real
"impasse" in negotiations, as believed by the Region's John Brink.
(Ex. 16; Tr. 352). From the District's point of view, the Region's
changing demands represented something of a moving target. In the
December 3, 1993 letter, the District actually offered to perform
all new components of the mitigation plan, if some consideration
would be given with regard to the civil penalty assessment. This
can hardly be considered an unreasonable negotiating position that
should create an impasse. In the exercise of its discretion, the
Region responded with the compliance order some three months later,
rather than with a counterproposal. (FF ##22, 23; Ex. 26). The
delay during this period cannot be blamed solely on the negotiating
stance of the District.
In reviewing the entire chronology of events from the time of
the violation until the completion of the mitigation plan, it is
difficult to see how the entire process could have been
significantly accelerated in any event. The initial meeting on the
site took place several months after the construction, as soon as
all parties were respectively available. (FF #20). The District
then promptly retained a consultant who recommended the basic
outline of the mitigation plan. (FF ##20, 21). Further
negotiations ensued in November and December 1993, as described
above, that resulted in additional components to the plan. (FF
#22).
Then, after the Region issued a compliance order, the
District applied for an after-the-fact permit from the Corps. Due
to the required period for public notice and comment, the permit
process took the necessary six additional months. (FF #23). As a
result of that process, some additional elements were required in
the mitigation plan. (FF ##24, 25). The District was initially
reluctant to begin the mitigation work due to the City of
Lafayette's failure to record the required deed restriction. (FF
#26). This cannot be said to have been an unreasonable position
for a public agency to take. Nevertheless, at the Region's urging,
the District constructed the mitigation project during the next
available window of time suitable for such work, in March of 1995.
(FF #26).
This review of the chronology leads to the conclusion that the
District was reasonably cooperative in negotiating and implementing
the mitigation plan. The two-year delay until the mitigation was
completed cannot be ascribed solely to the District. The overall
pace of meetings, reports, and negotiations, for which all parties,
including the Corps, were responsible, could hardly have allowed
for a more rapid response. It is the nature of the beast that
these things are not usually resolved very rapidly. The ATF permit
process alone consumed six months. This type of wetland creation
and planting project then requires several years for the vegetation
to become established. The District could perhaps have immediately
acceded to all demands by the Region. But even that might not have
significantly accelerated the process, since the Region proposed
new elements for the mitigation plan as late as June 1994. The ATF
permit was then not issued until September 1994. Despite the
concern over the lack of the required deed restriction, the
District then constructed the mitigation project in March 1995, the
next suitable window of time for successful planting. (FF #26).
The Penalty Framework (p. 20) states that penalty reductions
may be granted for prompt correction of environmental violations,
even if the amount of the penalty remains in litigation. In this
case, any such reduction will however be offset by what would be an
equivalent increase for the District's high degree of culpability
in committing the violation in the first place. Therefore, there
will be no adjustment to the gravity based penalty assessed by this
decision of $80,000, of which $75,000 is apportioned to the
District and $5000 to Kemp & Hoffman.
Conclusions of Law
1. The Urban Drainage and Flood Control District discharged
fill into a water of the United States without a permit required by
the Clean Water Act §404, 33 U.S.C. §1344, thereby violating the
CWA §301(a), 33 U.S.C. §1311(a).
2. The site of the violation, Coal Creek at the City of
Lafayette shops, is located below the headwaters area on Coal
Creek, as determined by the U.S. Army Corps of Engineers pursuant
to the CWA §404(e), 33 U.S.C. §1344(e) and 33 CFR §330.2(d).
Hence, the District's project on Coal Creek was not authorized by
Nationwide Permit 26 and was not exempt from the requirement to
obtain an individual permit under Section 404.
3. The District's contractor, Kemp & Hoffman, Inc., is also
liable for the violation of discharge of fill into a water of the
United States without a permit. However, Kemp & Hoffman was far
less culpable than the District in committing this violation.
4. In consideration of the civil penalty factors set forth in
the CWA §309(g), 33 U.S.C. §1319(g), an appropriate civil penalty
for this violation is $80,000. The payment of the penalty should
be apportioned as follows: $75,000 payable by the District, and
$5000 payable by Kemp & Hoffman.
Order
1. The Respondent, Urban Drainage and Flood Control District,
is assessed a civil penalty of $75,000.
2. The Respondent, Kemp & Hoffman, Inc., is assessed a civil
penalty of $5000.
3. Payment of the full amount of these civil penalties must be
made within 60 days of service of this order by submitting
respective certified or cashier's checks in the above amounts,
payable to the Treasurer, United States of America, and mailed to:
EPA - Region 8, P.O. Box 360859, Pittsburgh, PA 15251-6859. The
checks must be accompanied by transmittal letters identifying the
case, docket number, and Respondent's name and address.
4. Respondents may be assessed interest on these civil
penalties if they are not paid within the prescribed period.
5. Pursuant to 40 CFR §22.27(c), this Initial Decision will
become the final order of the Agency unless an appeal is taken
pursuant to 40 CFR §22.30, or the Environmental Appeals Board
elects to review this decision sua sponte.
_______________________________
Andrew S. Pearlstein
Administrative Law Judge
Dated: June 25, 1998
Washington, D.C.
1. References to the exhibits ("Ex.") and stenographic transcript of the
hearing ("Tr.") are representative only, and not intended to be exhaustive.
2. Official notice is taken of the full drainage course of Coal Creek's
waters to the Gulf of Mexico. The parties stipulated that Coal Creek is a
"water of the United States" and a "navigable water" as those terms are defined
in the CWA §502 and 33 CFR §328.3(a) and (b). (Ex. 1, ¶7).
3. An acre-foot is the area of an acre, 43,560 square feet, covered by
water to a depth of one foot. A discharge of one cubic foot per second for
one year will yield approximately 724 acre-feet. (Tr. 507, 529).
4. The records of the State Engineer were not complete for one of the
ditches. In several years, the records indicated water was diverted, but the
amounts were not given. For the purpose of calculating the total, the values
for the missing data were assumed to be zero, or no diversions from that ditch
for those years.
5. The discussion in this section generally refers primarily to the
liability of the District. Kemp & Hoffman's liability is discussed separately
in the following section of the Discussion.
6. The Corps has since reduced the thresholds for authorization under NWP
26, and for notification, respectively to 3 acres and 1/3 acre, on an interim
basis. 61 FR 65874, 65891, December 13, 1996.
7. Mr. Wright may well have assumed, based on his experience and the
evidence of the single well testified about, that the water table was below
the elevation of the bed of Coal Creek throughout the basin. This was not
however clearly expressed in the record. (See Tr. 550).
8. 61 FR 65894, December 13, 1996.
9. On Coal Creek, man-made contributions to the flow, by the Louisville
wastewater treatment plant, especially in recent years, actually often
exceeded diversions, and resulted in enhanced flows. (FF #51). Flows at the
City of Lafayette shops, shortly downstream, are probably often heavily
influenced by the discharge from that plant. The record does not reflect the
source of the water used by the City of Louisville, but this finding assumes
that the source was outside the Coal Creek drainage basin. There may also
have been some "double counting" of runoff that finds its way into the
Louisville sewer system. This illustrates the difficulty in attempting to
empirically analyze all the factors affecting flow to a stream.
10. The Corps has made 265 headwaters determinations in Colorado alone.
(Ex. 7).
11. See Respondent's brief, p. 4, citing Cumberland, supra, 826 F.2d 1157.
12. The respondent in Sasser also wilfully disregarded the Section 404
permit process and refused to obey compliance orders to remove the offending
dikes. These distinctions provide further reason to assess less than the
maximum penalty in this proceeding, as further discussed below.
13. See, e.g., In re Britton Construction Company, et al, Docket No. CWA-III-096
(Initial Decision, May 21, 1997), pp. 4-5 (findings of fact indicating a
several year period between respondents' filling a wetland without a permit
and constructing a mitigation plan).
14. These conclusions, as indicated, are based solely on the record of
the hearing and not on my site visit. The site visit was undertaken over the
Region's objection. The Respondents have referred to it in their brief.
(Respondent's Closing Brief, p. 23). As stated on the record, I visited the
site in order to obtain a better context in which to understand the evidence,
and not to become, in effect, a witness myself. (Tr. 438). It is interesting
to note, however, that the District Judge in Cumberland Farms freely and
extensively discussed his own observations during his site visit in that case,
while noting that they corroborated facts drawn from the record. See
Cumberland Farms, supra, 647 F.Supp. 1166, 1173-1174.
15. See In re Sasser, supra, 3 E.A.D. 703, 708 (wilful disregard of permit
process and refusal to comply with restoration orders); and In re Labarge, Inc.,
Docket No. CWA-91-W-0078 (Initial Decision, March 26, 1997), p. 8 (continued
discharge violations despite repeated notices).
16. See Florida Keys Comm. College, supra, 531 F.Supp. 267, 275 (contractor fined
$3000, while college landowner fined $15,000 and required to perform
mitigation or restoration of site); and Van Leuzen, supra, 816 F.Supp. 1171, 1175,
1181-1184 (contractor fined $900; landowner required to restore site and
establish a fund for restoration costs and for payment of a civil penalty, by
paying $350 per month for at least eight, but not more than twelve years, for
a minimum payment of $33,600).
17. See In re B.J. Carney Industries, Inc., CWA Appeal No. 96-2 (EAB, June 9, 1997),
p. 51; and Smithfield Foods, supra, 972 F.Supp. 338, 349.
18. Initially the exhibit concerning the 1987 prior violation was
excluded as too remote. Later, I reversed that ruling and received it. The
District's Executive Director, Scott Tucker, who signed the 1987 ATF permit
application, could then have been examined concerning his knowledge of the
circumstances; however, neither party pursued such examination. (Ex. 5; Tr.
70-71, 725-726, 748-749).
19. Most of the negotiations concerning the mitigation plan took place in
late 1993 and early 1994, before the filing of the Complaints in this matter,
and the District's adoption of the defense that it was not liable due to the
headwaters nationwide permit exemption. Even after it took the position that
it was not liable, the District continued to comply with all requirements of
the mitigation plan and after-the-fact permit.
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)