Lead in Air
SIP Toolkit - NAAQS Implementation Schedules
You will need Adobe Acrobat Reader to view the Adobe PDF files on this page. See EPA's PDF page for more information about getting and using the free Acrobat Reader.
SIP Toolkit
- Designations
- NAAQS Implementation Schedules
- Infrastructure SIP
- NSR and PSD
- Emission Inventories
- Monitoring Air Quality
- Attainment Demonstrations and Air Quality Modeling
- Strategies and Technologies to Reduce Emissions
- Compliance and Enforcement
- Regulatory Actions & Guidance
- Training
- Related Links
- Glossary
What do the designated areas have to do to comply with the CAA? When do the areas have to comply?
Pb NAAQS Implementation Timing First Round
| Milestone | Date |
|---|---|
| Signature - Final Rule | October 15, 2008 |
| State Monitoring Network Plans to EPA |
July 1, 2009 plan must contain all source-oriented monitors |
| State Designation Recommendations to EPA |
No later than October 15, 2009 |
| Monitoring Network Implementation |
All source-oriented monitors operational by January 1, 2010 |
| For areas with existing monitoring networks and sufficient data: | |
| Final Designations | November 16, 2010 (effective date December 31, 2010) |
| Infrastructure SIPs | No later than October 15, 2011 (3 yrs max after Pb NAAQS rulemaking) |
| Atttainment Demonstration SIPs (including part D) |
June 30, 2012 (18 month max after designations effective date) |
| Attainment Date | December 31, 2015 (5 year max after designations effective date) |
Pb NAAQS Implementation Timing Second Round
| Milestone | Date |
|---|---|
| Signature - Final Rule | October 15, 2008 |
| State Monitoring Network Plans to EPA |
July 1, 2009 plan must contain all source-oriented monitors |
| State Designation Recommendations to EPA |
No later than October 15, 2009 |
| Monitoring Network Implementation |
All source-oriented monitors operational by January 1, 2010 |
| For areas with existing monitoring networks and sufficient data: | |
| Final Designations | Effective date December 31, 2011 |
| Infrastructure SIPs | No later than October 15, 2011 (3 yrs max after Pb NAAQS rulemaking) |
| Atttainment Demonstration SIPs (including part D) |
June 30, 2013 (18 month max after designations effective date) |
| Attainment Date | December 31, 2016 (5 year max after designations effective date) |
June 30, 2012, Attainment Demonstration for First Round
- Attainment demonstration SIPs are due eighteen months after the effective date of an areas designation. For the first round of designations the attainment SIPs are due June 30, 2012. For the second round of designations, the attainment SIPs are expected to be due June 30, 2013.
November 1, 2012, Control Measures for First Round
- In order for control measures to result in three years of monitored clean data by the attainment date, areas designated in the first round of designations (effective December 31, 2010, and requiring attainment demonstrations that show that the area will attain the standard as expeditiously as practicable, but no later than December 31, 2015) would need to have all necessary controls in place no later than November 1, 2012. EPA will consider on a case-by-case basis the approvability of attainment demonstration SIPs where control measures are scheduled to be operational after November 1, 2012.
Applies to all areas designated nonattainment in the second round:
June 30, 2013, Attainment Demonstration for Second Round
- Attainment demonstration SIPs are due eighteen months after the effective date of an areas designation. For the second round of designations, the attainment SIPs are expected to be due June 30, 2013.
November 1, 2013, Control Measures for Second Round
- In order for control measures to result in three years of monitored clean data by the attainment date, areas designated in the second round of designations (effective December 31, 2011, and requiring attainment demonstrations that show that the area will attain the standard as expeditiously as practicable, but no later than December 31, 2016) would need to have all necessary controls in place no later than November 1, 2013. EPA will consider on a case-by-case basis the approvability of attainment demonstration SIPs where control measures are scheduled to be operational after November 1, 2013.
December 31, 2015, Attainment Date for First Round
- Areas are required to attain the revised Lead standard as expeditiously as practicable, but no later than 5 years from the date the nonattainment designation became effective. The attainment date for the first round is December 31, 2015. The Clean Air Act precludes the Administrator from granting attainment date extensions for lead.
December 31, 2016, Attainment Date for Second Round
- Areas are required to attain the revised Lead standard as expeditiously as practicable, but no later than 5 years from the date the nonattainment designation became effective. The attainment date for the second round is expected to be December 31, 2016. The Clean Air Act precludes the Administrator from granting attainment date extensions for lead.
For more information see:
- The State Implementation Process