CHAPTER V. SCHEDULE FOR APPLICATION REVIEW PROCESS OSWER Directive 9650.12 SUGGESTED PROCEDURES FOR REVIEW OF STATE UST APPLICATIONS May 1992

V. SCHEDULE FOR APPLICATION REVIEW PROCESS

Subtitle I requires that the Regional Administrator make a final determination on the application within 180 days from receipt of a complete application (Section 9004(d)). This section presents two proposed schedules for getting final approval: one for a streamlined process; and one for a more extended process within the allowable time period of 180 days. Note that even a streamlined schedule is estimated to take about 140 days. The dates in the schedules provided here are suggestions to the Regions for meeting the 180-day deadline. Regions are encouraged to shorten this schedule whenever possible.

A streamlined schedule for program approval is shown on pages 27 and 28. This schedule assumes that:

A second schedule, provided on pages 28-30, displays the approval process over a longer period of time as a result of outstanding issues and public comments. This schedule still meets the 180-day deadline.


OSWER DIRECTIVE 9650.12

STREAMLINED PROGRAM APPROVAL SCHEDULE

Calendar Days Approval Activities

1

Log and Transmit Complete Application

32

Review Team Completes Initial Review of Application

34

Review Team Closure Meeting To Discuss Recommendations on the Application

41

UST Program Manager Formulates An Overall Recommendation and Prepares Briefing For the Regional Administrator and Division Director

43

UST Program Manager Briefs Regional Administrator and Division Director on Approval Issues

44

UST Program Manager Notifies the State Program Contact of Outstanding Issues

45

UST Program Manager Meets With the Regional Administrator and the Division Director Regarding the Tentative Determination; Meets with the State Agency Director and State Program Contact As Necessary

52

Regional Administrator Makes Tentative Determination and Notifies UST Program Manager and State Agency Director

62

Regional Staff Complete Federal Register Notice of Tentative Decision and Obtain Regional Administrator's Concurrence

69

Publish Federal Register Notice and Public Comment Period Begins

99

Public Comment Period Closes

107

UST Program Manager Distributes Public Comments To the Review Team and State Program Contact

115

Review Team Meets To Discuss Response To Public Comments

122

UST Program Manager Briefs Regional Administrator and Division Director On Issues and Meets With the State Agency Director and State Program Contact If Necessary

129

Regional Administrator Makes Final Determination and Notifies Division Director, UST Program Manager and State Agency Director

139

Regional Staff Complete Final Action Memo and Federal Register Notice of Final Determination, Obtain Regional Administrator's Signature

143

Publish Federal Register Notice of Final Determination


OSWER DIRECTIVE 9650.12

EXTENDED APPROVAL SCHEDULE

Calendar Days Approval Activities

1

Log and Transmit Complete Application To Review Team

21

Review Team Completes Initial Review of Application

24

Regional Review Team Meets with UST Program Manager To Ascertain Need For Any Additional Information From the State

25

UST Program Manager Contacts State Program Contact To Discuss Additional Information (If Necessary)

39

State Program Contact Submits Additional Information (If Necessary)

53

Review Team Completes Final Review

58

Review Team Closure Meeting To Discuss Recommendations on the Application

65

UST Program Manager Formulates An Overall Recommendation and Prepares Briefing For the Regional Administrator and Division Director

67

UST Program Manager Briefs the Regional Administrator and Division Director on Approval Issues

68

UST Program Manager Notifies the State Program Contact of Outstanding Issues

69

UST Program Manager Briefs the Regional Administrator and the Division Director Regarding Issues on the Tentative Determination; Meets with the State Agency Director and the State Program Contact As Necessary

76

Regional Administrator Makes Tentative Determination and Notifies UST Program Manager and State Agency Director

86

Regional Staff Complete Federal Register Notice of Tentative Decision, and Obtain Regional Administrator's Signature

93

Publish Federal Register Notice and Public Comment Period Begins

123

Public Comment Period Closes

124

Public Hearing (If Necessary)

131

UST Program Manager Distributes Public Comments To the Review Team and the State Program Contact

138

UST Program Manager Meets With State Program Contact To Discuss Additional Information Needed to Respond To Public Comments

145

Review Team Meets To Discuss and Draft Agency Response To Public Comments

148

UST Program Manager Briefs Regional Administrator and Division Director On Issues and Recommendations For Final Determination; Meets With the State Agency Director and State Program Contact As Necessary

156

Regional Administrator Makes Final Determination and Notifies Division Director, UST Program Manager, and State Agency Director

162

Regional Staff Complete Final Action Memo and Federal Register Notice of Final Determination, and Obtain Regional Administrator's Signature

169

Publish Federal Register Notice of Final Determination

[ Directive 9650.12 Table of Contents ][ Chapter VI. ]