Table 6-4. Projects that Together May Provide an Estimated 25 Percent Reduction in Sediment Yield
Est. Yield Reduction Scheduled
Project (ton/yr) Implementation
Forest Highway 22
Fill Stabilization 12 1991
Close Miner's Peak Road 83 1991
SF Road Reconstruction 150 1992
Road Closures Upper SF 25 1992
Basin Road Stabilization 9 1992
Upper SF Road (Kline Mt
Section) Obliteration/
Spot Stabilization 54 1992
NF Dollar Creek Road
Obliteration/Stabilization 28 1993
Curtis Creek Drainage
Spot Stabilization 40 1994
Temp Closure of
Buckhorn Road 200 1995
Two-Bit, Six-Bit Loop
Road Stabilization 55 1995
|