Tonolli Corporation

Eastern Landfill Embankment Construction

Looking north at eastern landfill enbankment before start of Remedial Action.
Looking north at eastern landfill enbankment before start of Remedial Action.

Moving waste coal from eastern embankment area
Moving waste coal from eastern embankment area.

Looking north at eastern landfill embankment after first lift of soil has been placed and compacted.
Looking north at eastern landfill embankment after first lift of soil has been placed and compacted.

Looking north at eastern landfill embankment after second lift of soil has been placed and compacted.
Looking north at eastern landfill embankment after second lift of soil has been placed and compacted.

Looking north at eastern landfill embankment during placement of next lift of soil.
Looking north at eastern landfill embankment during placement of next lift of soil.

Placing last soil lift along the eastern landfill embankment.
Placing last soil lift along the eastern landfill embankment.

Eastern landfill embankment at final grading.
Eastern landfill embankment at final grading.

Eastern landfill embankment with grass begining to grow.
Eastern landfill embankment with grass begining to grow.

Eastern landfill embankment showing final grass cover on 04/24/2002.
Eastern landfill embankment showing final grass cover on 04/24/2002.