Drake Chemical
Site Progress
- Up to April 23, 1999, 100% of contaminated soil has
been treated and backfilled.
- Up to March 2, 1999, 90% of contaminated soil has been
treated and backfilled.
- Up to February 2, 1999, 85% of contaminated soil has
been treated and backfilled.
- Up to January 13, 1999, 80% of contaminated soil has
been treated and backfilled.
- Up to December 23, 1998, 75% of contaminated soil has
been treated and backfilled.
- Up to November 17, 1998, 65% of contaminated soil has
been treated and backfilled.
- Up to October 31, 1998, 60% of contaminated soil has
been treated and backfilled.
- Up to September 21, 1998, 50% of contaminated soil has
been treated and backfilled.
- Up to August 25, 1998, 40% of contaminated soil has been treated and backfilled.
- Up to July 7, 1998, 30% of contaminated soil has been
treated and backfilled.
- Up to June 30, 1998, 25% of contaminated soil has been
treated and backfilled.
- Up to the end of May 1998, 16% of contaminated soil
has been treated and backfilled.
- Up to the end of April 1998, 12% of contaminated soil
has been treated and backfilled.
- Up to the end of March 1998, 9% of contaminated soil
has been treated and backfilled.