Silver Lake has a history of extensive contamination. PCBs have been detected in the lake's sediment, bank soils and surface water. Historic discharges of PCBs and other chemicals in process water and wastewater from GE's East Street Area II operations have been reported.
The Consent Decree requires that GE dredge 400 cyds of "hot spot" sediment adjacent to one of the historic GE outfalls, clean up contaminated bank soil, and place a cap on the entire bottom of the lake. Bench-Scale Testing and a 1-acre Pilot Study of capping techniques were completed in 2006. Sampling of the bank soil should be completed in 2007. Full-scale capping of the Lake is expected to begin in 2008, along with associated bank soil removal. More information and documents for Silver Lake are available under "The Site" on this Web site.