This Proposed Plan identifies the
Preferred Alternative for a final remedy to clean up contaminated ground
water in the bedrock at the Myers Property Site and provides the rationale
for this preference. In addition, this Plan includes summaries of other
cleanup alternatives evaluated for use at this site. An interim ground
water remedy has already been implemented at the site and is currently
operating, and contaminated soil, sediment, and shallow ground water at
the site have already been addressed. This document is issued by the U.S.
Environmental Protection Agency (EPA), the lead agency for site activities,
and the New Jersey Department of Environmental Protection (NJDEP), the
support agency. EPA, in consultation with NJDEP, will select a final remedy
for the site after reviewing and considering all information submitted
during the 30-day public comment period. EPA, in consultation with NJDEP,
may modify the Preferred Alternative or select another response action
presented in this Plan based on new information or public comments. Therefore,
the public is encouraged to review and comment on all the alternatives
presented in this Proposed Plan.
Information Repositories
For more information, see the Administrative Record at the following locations:
U.S. EPA Records Center
Region II
290 Broadway, 18th Floor.
New York, New York 10007-1866
(212) 637-3261
Hours: Monday-Friday,
9 am to 5 pmNorth County Branch Library
65 Halstead Street
Clinton, New Jersey 08809
(908) 730-6262
Hours: Monday, Friday, Saturday - 9 am to 5 pm;
Tuesday, Wednesday, Thursday - 9 am to 9 pm
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)