Site Summary Profile
EPA ID: SCD991279324
Location: Rock Hill, York County, SC
Lat/Long: 34.851660, -080.904160
Congressional District: 05
NPL Status: Proposed: 09/08/83; Final: 9/21/84
Affected Media: Ground water, Liquid Waste, Soil
Cleanup Status: Construction Underway - Physical cleanup activities have started.
Site Reuse/Redevelopment: Potential for Industrial or Residential
Site Manager: Robert West (west.robert@epa.gov)


Site Background

The 7-acre Leonard Chemical Company site, located in Rock Hill, York County, South Carolina, began operating as a hazardous waste treatment facility in the late 1960s. The primary treatment method used by the facility was distillation, and the resulting recovery residues were placed in various locations on the site. When plant operations ceased in 1982, approximately 3,400 drums and 11,500 gallons of various chemicals were left on the site. Materials included solvents, volatile organic compounds (VOCs), printing inks, polyester solids, still bottom residues, and filters for paint, water, and fiberglass.

Approximately 5,900 people live within a 4-mile radius of the site; 240 people live within one mile.

Top of page

Threats and Contaminants

Numerous spills and leaks from former site activities and abandoned waste materials occurred at the site, resulting in soil and ground water contamination with metals, polycyclic aromatic hydrocarbons, and VOCs. Abandoned equipment and machines remained at the site, numerous sludges lay on the ground, and vegetation was spotty where chemical wastes and still bottom residues had been used as fill material.

Top of page

Site Cleanup Plan

The Record of Decision (ROD) for the site was issued in 2001. Major cleanup elements for the site included:

EPA issued an Explanation of Significant Differences (ESD) on February 13, 2003 to modify the remedy selected in the 2001 ROD. The primary reason for the ESD was to update the remedial goals for subsurface soil constituents based on site-specific leach tests conducted by the potentially responsible parties (PRPs) and reviewed by EPA. In addition, two typographical errors were corrected.

Top of page

Cleanup Progress

In 1983, the PRPs retained a contractor to remove wastes from the site, under the oversight of the South Carolina Department of Health and Environmental Control. Approximately 80% of surface wastes were removed in this removal action.

The PRP group conducted a remedial investigation of the site including monitoring well installation and sampling, subsurface soil sampling, and stream and sediment sampling. Additional field work was conducted to determine the extent of ground water contamination both on and off site.

The final remedial design was completed in March 2009 and a remedial action workplan was submitted to EPA in summer 2009. Remedial action activities will commence once EPA approves the workplan.

Top of page

Enforcement Activities

Under a 1983 court order, Leonard Chemical Company cannot resume site operations without prior approval of the South Carolina Department of Health and Environmental Control.

On December 13, 1990, EPA issued an Administrative Order on Consent to the PRPs for performance of a remedial investigation and feasibility study.

In July 1991, a Consent Decree was entered by the Court triggering the initialization of field investigations by PRP contractors

Top of page

Community Involvement

EPA has conducted a range of community involvement activities at the Leonard Chemical Company, Inc. site to solicit community input and to ensure that the public remains informed about site activities throughout the site cleanup process. Outreach activities have included public notices, interviews, and public meetings on cleanup activities and updates.

Top of page

Future Work

EPA approved the remedial design and RA schedule in May 2009. The PRP propose to divide up the RA into two phases, both of which include the installation/operation of soil vapor extraction and air sparging wells to address subsurface contamination.  Phase I was completed in October 2010 and it is anticipated to take 12 to 18 months to complete Phase I of the remedial action.  Phase II scheduled to begin in May 2012 and be completed in December 2013. 

Top of page

Site Administrative Documents

Site Repository

For more information or to view any site-related documents, please visit the site information repository at the following location. As new documents are generated, they will be placed in the information repository for public information.

York County Library
138 E. Black Street
Rock Hill, SC 29731

For documents not available on the website, please contact the Region 4 Freedom of Information Office.

Top of page


Local Navigation



Jump to main content.