Jump to main content.


Weyerhaeuser Company Plymouth Wood Treating Plant

Photos/Multimedia

Site photo goes here.
- Additional Site Photos
- Site Video

Additional Resources
Site Summary Profile
EPA ID: NCD991278540
Location: Plymouth, Martin County, NC
Lat/Long: 35.674485, -076.785495
Congressional District: 01
NPL Status: Superfund Alternative Site
Affected Media: Fish tissue, Ground water, Sediment, Soil
Cleanup Status: Construction Complete – Physical cleanup activities have been completed.
Site Reuse/Redevelopment: Continued Industrial Use – An active wood and paper products manufacturing facility.
Site Manager: Randy Bryant (bryant.randy@epa.gov)


Site Background

The 2,400-acre Weyerhaeuser Company Plymouth Wood Treating Plant site is an active wood and paper products manufacturing facility located near the confluence of Welch Creek and the Roanoke River in Plymouth, Martin County, North Carolina. The site began operations under the Kieckhefer-Eddy Company in 1937, was managed by the Weyerhaeuser Company from 1957 until 2007, and is currently owned and operated by Domtar Corporation.

The site is not listed on the National Priorities List (NPL), but is considered to be an NPL-caliber site and is being addressed through the Superfund Alternative Approach. This approach uses the same investigation and cleanup process and standards that are used for sites listed on the NPL.

Top of page

Threats and Contaminants

Site operations have resulted in the contamination of soil, sediments, and ground water with dioxins, dibenzofurans, metals, and volatile organic compounds (VOCs). Site-related compounds have also been found in tissue of fish and other biota that inhabit surface waters near the site. The areas of the plant that are being investigated include: 1) the Former Chlorine Production Plant, which has contributed to mercury contamination in soil and ground water; 2) the Former Landfill No.1, the former disposal areas for mercury cells from the Chlorine Production Plant; and 3) Welch Creek, which has received pre-permitted discharge of wastewater.

Top of page

Site Cleanup Plan

The cleanup plan for the Weyerhaeuser site covered four operable units (OUs): OU-1 (Landfill No. 1 Area), OU-2 (Lower Roanoke River), OU-3 (Former Chlorine Plant Area), and OU-4 (Welch Creek Area).

The Record of Decision (ROD) for OU-1 was issued in 2002. Major elements of the cleanup plan included:

The ROD for OU-2 was issued in 2008. Major elements of the cleanup plan included:

The ROD for OU-3 was issued in 2003. Major elements of the cleanup plan included:

The ROD for OU-4 was issued in 2007. Major elements of the cleanup plan included:

Top of page

Cleanup Progress

The geotextile and soil landfill cover specified in the remedy for OU-1 was completed in December 2005 and presently covers an area of approximately 82 acres. Long-term monitoring of ground water and soil along the adjacent wetlands is ongoing.

In October 2001, the State’s fish consumption advisory for dioxin was lifted for sport fish, but remains in effect for catfish and carp. Dioxin levels have declined between five- and tenfold in wood duck eggs and catfish since the mid-1990s. Since 2006, there has been a fish consumption advisory for mercury in all state waters. Fish consumption advisories will continue until the State of North Carolina guidelines have been met. Deed restrictions at the Weyerhaeuser property and institutional controls will also be used where appropriate.

Construction of the remedy for OU-3 began in March 2006 and was completed in August 2006. Mercury-contaminated soil has been contained, contamination hotspots have been excavated and disposed of off site, and long-term ground water monitoring is ongoing.

The potentially responsible parties (PRPs) have begun work on the remedial design for OU-4 and will collect some additional data in Welch Creek during 2009. The design should be completed by the spring of 2010.

Site cleanup activities are being led primarily by PRPs with oversight by EPA.

Top of page

Enforcement Activities

In March 1998, EPA and the PRP entered into an Administrative Order on Consent (AOC) to implement the remedial investigation and feasibility study for OU-1, OU-3, and OU-4.

In August 2003, EPA and the PRP entered into a Consent Decree for the remedial design and remedial action for OU-1.

In January 2009, EPA and the PRP entered into a Consent Decree for the remedial design and remedial action for OU-4.

Top of page

Community Involvement

EPA has conducted a range of community involvement activities at the Weyerhaeuser Company site to solicit community input and to ensure that the public remains informed about site activities throughout the site cleanup process. Outreach activities have included public notices, interviews, and public meetings on cleanup activities and updates.

Top of page

Future Work

EPA and the PRP are currently negotiating a Consent Decree for the long-term monitoring for OU-2. The Consent Decree is expected to be entered with the court system by the end of 2009.

Top of page

Site Administrative Documents

Site Repository

For more information or to view any site-related documents, please visit the site information repository at the following location. As new documents are generated, they will be placed in the information repository for public information.

Washington County Public Library
201 E. 3rd Street
Plymouth, NC 27962-1319

Administrative Record Index

For documents not available on the website, please contact the Region 4 Freedom of Information Office.

Top of page

For information about the contents of this page please contact Donna Bledsoe.


Local Navigation


Jump to main content.