Jump to main content.


WPSC Two Rivers MGP Site

Site Information
Contact Information

Community Involvement Coordinator
Susan Pastor (pastor.susan@epa.gov)
312-353-1325 or 800-621-8431, ext. 31325

Remedial Project Manager
Margaret Gielniewski
(gielniewski.margaret@epa.gov)
312-886-6244 or 800-621-8431, ext. 66244

On-Scene Coordinator
Brad Benning
(benning.bradley@epa.gov)
312-353-7613 or 800-621-8431, ext. 37613

Repositories

(where to view written records)

Lester Public Library
1001 Adams St.
Two Rivers, WI

Links for Wisconsin former MGPs

EPA Superfund Home Page
Region 5 Superfund

Agency for Toxic Substances & Disease Registry

Background

The Wisconsin Public Service Corp. site is located in Two Rivers, Wis., adjacent to the West Twin River. Currently, about half of the 5-acre former MGP plant is wetland near the river’s shore, accessible by water. The former MGP building and other structures and foundations have been demolished.  A fence was installed around the perimeter to prevent trespassing.
WPSC owned and operated the gas plant from 1925 to 1946 in an area that was historically industrial. Processes included coal carbonization and carbureted water gas. WPSC still owns the site today.

Under Wisconsin Department of Natural Resources oversight, various investigations have taken place since the 1990s. From 2003 to 2005, pilot tests were done to try a then-promising technology called in-place chemical oxidation to treat contaminated groundwater. Routine groundwater monitoring occurs annually.

Site Updates || Technical Documents || Legal Agreements


You will need the free Adobe Reader to view some of the files on this page. See EPA's PDF page to learn more.

Site Updates

August 2014

Short-term cleanup work at the former MGP site will run from August through the end of the year.  This includes securing the area, monitoring the air, excavating and disposing of the contaminated soil and sediment, and stabilizing any remaining contaminated soil on site.
The project has been separated into three areas:

Neighbors will probably notice engine noise from the equipment used in the stabilization process, extra truck traffic during the dig’n’haul activities, and air monitoring stations making sure excess dust isn’t released into the air.  Although the project is expected to be completed by December, workers may return in spring 2015 to reseed and regrade the property.

WPSC/Integrys is conducting and paying for the work under an EPA legal agreement called an administrative order on consent. 

In addition to this work, plans are underway for a long-term investigation and cleanup of sediment, groundwater and soil here as well as at five other MGP sites. This is taking place under another administrative order which was signed between WPSC and EPA in May 2006.

The agreement includes five other MGP sites in Green Bay, Manitowoc, Marinette, Oshkosh, and Stevens Point, Wisconsin. A separate agreement for another site, WPSC Campmarina MGP in Sheboygan, was signed between WPSC and EPA in January 2007.

Top of page

Technical Documents

Manufactured Gas Plants (MGPs)

Learn about MGPs

EPA Region 5 is working on former MGPs in Wisconsin and Illinois.

Top of page

Legal Agreements

Top of page


Local Navigation


Jump to main content.