Jump to main content.


 

Palos Verdes Shelf

Pilot Capping Project: Summary of Activities

Objectives

Map showing three pilot capping sites (red rectangles) close to Los Angeles County Sanitation District sewer outfalls

The Palos Verdes Shelf Pilot Capping Project will evaluate the short-term results of capping the DDT-contaminated sediment with clean sediment. It will also determine how these results are affected by variables such as cap material, placement method and water depth. The results from the pilot project, along with other relevant information, will be used by the EPA in deciding whether or not to propose full-scale capping as a cleanup action for the site.

Specific objectives to be addressed in the pilot project include:

Cap Placement

The following table summarizes capping activity that was conducted as part of the pilot project:

Area of Pilot Capping
Three capping cells with a total area of 135 acres (45 acres/cell), northwest of the Los Angeles County Sanitation District outfall system

Capping Scenarios

Cell Water Depth Cap Material Placement Method Projected Cap Thickness/Area No. of Loads Approx. Total Volume (cy)
LU Shallow (150 ft) Queens Gate Conventional 15 - 45 cm (6 - 18") over entire cell 71 91,315
LD Shallow (150 ft) Borrow Site Spreading < 10 cm in center lane only 9 13,505
Shallow (150 ft) Queens Gate Pumpout thru drag arm n/a (1 load only) 1 390
SU Deep (200 ft) Queens Gate Conventional 15 cm in center portion of cell 21 29,835

Totals

102

135,045

Schedule
The first load of capping material was placed on August 2, 2000 and all cap placement activity was completed by September 14, 2000. The field work for the baseline monitoring in the pilot capping cells was started in mid-May, and the final post-cap monitoring activity was completed September 15th, a few days after the last load was placed in cell LU. A final report is expected in Novermber, 2001.

Monitoring
The environmental monitoring program collected data before, during and after cap placement to address key questions about the feasibility of capping on the Palos Verdes Shelf. The EPA used a variety of approaches and technologies to monitor and to assess the impacts of cap construction, including:

Sediment prior to pilot cap construction. Portions of the burrows created by sediment-dwelling organisms are visible.

Photo of:

Sediment partway through pilot project. Clean gray cap sediment from the Queen's Gate channel covers original sediment. Cap thickness shown is about 1 1/2 inches. A worm that lives in the sediment is visible.

Photo of:

Sediment partway through pilot project. Clean yellow sand cap sediment from a borrow site outside of the LA/Long Beach harbor breakwater covers original sediment. Cap thickness shown is about 2 1/2 inches.

The monitoring program during cap placement involved 59 trips by survey vessels, with as many as three survey vessels on site at any one time.

Region 9 Topics and Programs | A-Z Index


Local Navigation


Jump to main content.