Waste Site Cleanup & Reuse in New England

Atlas Tack Corporation Superfund Site
Weekly Demolition/Cleanup Activities Update

« Back to Atlas Tack Superfund Site Fact Sheet

Projected Activities for the Week of August 22 -- August 26

  • Complete demolition of Boiler Building
  • Continue to segregate and stockpile debris
  • Continue to ship wood / scrap metal offsite
  • Continue to ship asbestos roofing materials off site
  • Mobilize & construct 200 ton crane
  • Begin demolition of Boiler Building stack

Activities Performed During the Week of August 15 -- August 19

  • Neighborhood meeting on Thursday August 18th at the end of Tripp Street.
  • Begin demolition of Boiler Building
  • Ship metal debris off site for recycling
  • Ship asbestos roofing materials off site for disposal

Air Monitoring Information

Charter Environmental and Axiom, Inc. continue to monitor the four sampling locations during the 8 -hour day for dust particulate and asbestos.

The four perimeter sampling stations are set up in the following locations:

Station 1 – Site fence gate on Pleasant Street
Station 2 – Site fence on east end of Church Street
Station 3 – Site fence on bike path at Tripp Street
Station 4 – Site fence at bike path near Adams Street

The dust particulate and asbestos sampling results recorded at each station every hour in a monitoring log. These results are compared to the action levels established for each parameter. These action levels are concentrations at which it is deemed unsafe and work would have to stop and corrective measures would be taken.

Results of the air monitoring data has shown that exposure of unsafe conditions to workers in the exclusion zone and to the public is well below the actions levels.

Dust Particulate Monitoring – The National Ambient Air Quality standard for particulates is 150 micrograms per cubic meter (µg/m3) over an average of 24 hours. This value will be used, however, for a one hour period. Heavy metal presence is factored into determination of this action level. The average levels recorded at these locations range from 0 to 0.237 (µg/m3), with most readings valued at zero. The maximum level for this week is also recorded and ranges from 0 to 7.685 (µg/m3).

Asbestos Monitoring - Asbestos monitoring is conducted on a continuous basis as well. Readings are taken and recorded every hour. The personal space for asbestos workers is also monitored continuously.

The action level for asbestos is 0.010fibers per cubic centimeter (f/cc). Average readings range from 0 to 0.006 f/cc, well below the action level. Most readings were non-detectable. Samples from each location are also taken into the trailer for microscopic readings to verify the data.

Actual Data - Below are tables showing the average and maximum dust particulate and asbestos readings taken at each sampling location during the week of August 1 - 5.

 

Dust Particulate Results
Dust Particulate Sampling Location 1 - Pleasant Street Gate

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.009 0.237 0.005 0.000 0.000
Maximum 0.051 1.138 3.522 0.368 0.000
 
Dust Particulate Sampling Location 2 - Site Fence at East End of Church Street

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.038 0.000 0.084 0.000 0.000
Maximum 0.836 0.082 0.149 0.469 0.012
 
Dust Particulate Sampling Location 3 - Site Fence at Bike Path/Tripp Street

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.105 0.003 0.062 0.013 0.016
Maximum 0.433 0.569 0.236 1.366 7.685
 
Dust Particulate Sampling Location 4 - Site Fence at Bike Path/Adams Street

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.000 0.000 0.000 0.001 0.000
Maximum 0.000 0.080 0.085 0.278 0.071

 

Asbestos Results
Asbestos Sampling Location 1 - Pleasant Street Gate

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.001 0.001 0.003 0.001 0.002
Maximum 0.001 0.001 0.003 0.001 0.002
 
Asbestos Sampling Location 2 - Site Fence at East End of Church Street

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.002 0.003 0.002 0.003 0.003
Maximum 0.002 0.003 0.002 0.003 0.003
 
Asbestos Sampling Location 3 - Site Fence at Bike Path/Tripp Street

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.002 0.002 0.002 0.003 0.005
Maximum 0.002 0.002 0.002 0.003 0.005
 
Asbestos Sampling Location 4 - Site Fence at Bike Path/Adams Street

Readings are recorded as micrograms per cubic meter (µg/m3)

Time Thursday,
8/11
Friday,
8/12
Monday,
8/15
Tuesday,
8/16
Wednesday,
8/17
Average 0.003 0.003 0.002 0.003 0.006
Maximum 0.003 0.003 0.002 0.003 0.006

 

Samples for dust particulate were taken in the neighborhood on August 17, 2005. Results are shown below.

Readings are recorded as micrograms per cubic meter (µg/m3)

Sampling Location 85 Pleasant St. 2 Adams St. 97 Center St @ Adams St. 32 Adams At. @ Washington 70 Church St. @ Pleasant St.
Value 0.005 0.000 0.000 0.000 0.000
 

Monitoring for asbestos was conducted on August 17, 2005 at the end of Tripp Street. Results are shown below.

Readings are recorded as micrograms per cubic meter (µg/m3)

Wednesday 8/17        
Average 0.002        
Maximum 0.002        