1. ACTIVITIES PERFORMED DURING THE WEEK OF SEPTEMBER 11 - SEPTEMBER 15

  • Completed the screening and sorting of oversize debris from the soils excavated from C.I.D.
  • Decontaminated all large boulders generated from the sorting of oversize debris
  • Placed screened soils in the stockpile staging area for off-site transport
  • Completed pre-excavation, topographic survey of the East Fill Area
  • Installed dedicated sump along the northeast boundary of East Fill Area
  • Began excavation of the East Fill Area (Wed 9/13)
  • Prepared COMM 97, stockpile 1-3, for Transportation and Disposal (T&D)
  • Consolidated COMM-97 soils in the stockpile staging area
  • Continued stockpile management activities, covering and securing tarpaulins
  • Collected confirmatory soil samples from excavations in the East Fill Area
  • Collected waste characterization soil samples originating from East Fill excavation for off-site landfilling and disposal profiling
  • Commenced COMM-97 T&D to the Crapo Landfill (Thurs 9/14)
  • Received C.I.D. re-excavation analytical results from C.I.D.; performed 2nd round of re-excavations in the C.I.D. (Friday-9/15)
  • Provided survey of post excavation limits in the C.I.D. and the East Fill Area
  • Continued to water the roads for dust control
  • Continue with air monitoring program

2. PROJECTED ACTIVITIES FOR THE WEEK OF SEPTEMBER 18 - SEPTEMBER 22

  • Stabilize 940-tons of failed TCLP lead (RCRA hazardous waste)soils
  • Complete pre-characterization soil sampling of the Lagoon Areas
  • Continue to T&D COMM-97 soils to the Crapo Landfill (stockpiles 7-10, 12, 13, 15, 16) (pending profile approval)
  • Construct additional haul roads out to the East Fill excavation locations (as needed)
  • Continue with East Fill excavation activities
  • Collect confirmatory soil samples from excavations in the East Fill Area
  • Collect waste characterization soil samples originating from East Fill excavation for off-site landfilling and disposal profiling
  • Screen soils originating from East Fill Area
  • Place soils in the stockpile staging area
  • Continue to water the haul roads for dust control
  • Continue to collect pre and post excavation survey data of the excavations
  • Continue water handling activities
  • Continue with air monitoring program

3. AIR MONITORING INFORMATION

WESTON monitored for particulate (dust) during intrusive activities performed during this reporting period. WESTON recognizes EPA's level of concern for "PM10" to caution sensitive groups, including children, the elderly, and people with heart or lung disease, about exposure to coarse dust particles. The PM10 level of concern for sensitive groups is 150 µg/m3 for 24-hour average exposure.

Perimeter Air Monitoring is performed at up to (6) locations throughout a given work day. Readings are collected at 60 second intervals throughout the day and reported as a daily average.

If exceedances are identified, an increased effort of engineering controls (water suppression) will be utilized to adhere to the PM10 level of concern. If engineering controls appear to be inadequate, any dust generating activities will stop. Current dust control practices will be re-evaluated until concentrations are reduced to below the PM10 standard.

Results for 7 September – 13 September 2006 can be reviewed in the table below.

Weekly Dust Monitoring Summary
Week #10: Results for Thursday through Wednesday**

The EPA's PM10 level of concern for sensitive groups is 150 µg/m3 for 24-hour average exposure

Date Pleasant Street (µg/m3) Adams Street (µg/m3) Tripp Street (µg/m3) Hurricane Barrier (µg/m3) Church Street 2 (µg/m3)
9/7/2006 0 0 0 0 0
9/8/2006 0 0 5 1 8
9/11/2006 5 10 24 1 27
9/12/2006 3 0 3 0 0
9/13/2006 *** *** *** *** ***

Notes:
All readings reflect the daily average calculated over the course of the workday.
All readings collected with a Thermo Electron PDR 1000.
NSC: No sampling conducted; No intrusive work conducted in that area.
Precip: No sampling conducted due to precipitation.
*: Monitoring conducted over 24-hour period.
**: No work and air monitoring occurs on weekend days
***: Data for 9/13 will be posted with the Week # 11 Update

4. QUANTITY SUMMARY

Report # 10 - SUMMARY
TO DATE
ACTIVITIES TOTAL QUANTITY TOTAL QUANTITY
C.I.D. Excavation (Re-Digs) 100 CY 6,174 CY
East Fill Excavation 838 CY 838 CY
Soil Screening (Oversize) 500 CY 6,371 CY
Soil Screening (East Fill) 500 CY 500 CY
Soil placed in Stockpile Staging Area 1,000 *9,729 CY

Notes:
CY = volume of soil/debris in cubic yards
GAL = gallons of water

* Reported volume includes 2,655 CY of soils excavated from Commercial Area Excavation