1. ACTIVITIES PERFORMED DURING THE WEEKS ENDING 22 DEC. – 29 DEC.

  • Observed December 25, 2006 as a holiday
  • Continue to transport and disposal (T&D) of  COMM-97 soils to Marion landfill
  • Continue to T&D COMM-97 soils to Taunton landfill
  • Completed the T&D of Subtitle D oversize to TREE landfill, Rochester, NH
  • Continued to excavate the eastern cell of the Lagoon
  • Finalized cost proposal for  the Phase III remedial action
  • Commenced marsh and creek bed sampling north and south of the Hurricane Barrier
  • Received surface water sample analytical from the (3) locations within Boys Creek, (1) from standing water in the infiltration basin and (1) from standing water in the Commercial and Industrial Debris Area (CID)

Ongoing Site Activities:

  • Collected waste characterization soil samples from soils originating from the Lagoon Area for disposal profiling for off-site landfill disposal
  • Continue water handling activities
  • Continued to inspect trucks prior to exiting the site
  • Continued to provide flaggers to cross trucks across the bike paths along Adams and Tripp Streets
  • Continued stockpile management activities
  • Continue with air monitoring program

2. PROJECTED ACTIVITIES FOR THE WEEKS ENDING 5 JAN. – 12 JAN.

  • Observe January 1st as New Years holiday
  • Continue with excavation activities in the Lagoon Area
  • Backfill eastern cell of the Lagoon
  • Continued to T&D COMM-97 soils
  • Complete marsh and creek bed sampling north and south of the Hurricane Barrier
  • Collect waste characterization soil samples from soils originating from Lagoon Area

Ongoing Site Activities:

  • Continue to collect  pre and post excavation survey data of the excavations
  • Continue with stockpile management activities
  • Continue water handling activities
  • Continued to inspect trucks prior to exiting the site
  • Continued to provide flaggers to cross trucks across the bike paths along Adams and Tripp Streets
  • Continue with air monitoring program

3. AIR MONITORING INFORMATION

WESTON monitored for particulate (dust) during intrusive activities performed during this reporting period. WESTON recognizes EPA's level of concern for "PM10" to caution sensitive groups, including children, the elderly, and people with heart or lung disease, about exposure to coarse dust particles. The PM10 level of concern for sensitive groups is 150 µg/m3 for 24-hour average exposure.

Perimeter Air Monitoring is performed at up to (6) locations throughout a given work day. Readings are collected at 60 second intervals throughout the day and reported as a daily average.

If exceedances are identified, an increased effort of engineering controls (water suppression) will be utilized to adhere to the PM10 level of concern. If engineering controls appear to be inadequate, any dust generating activities will stop. Current dust control practices will be re-evaluated until concentrations are reduced to below the PM10 standard.

Results for 14 December – 27 December 2006 can be reviewed in the attached table

Weekly Dust Monitoring Summary
Week #22

The EPA's PM10 level of concern for sensitive groups is 150 µg/m3 for 24-hour average exposure

Date Pleasant Street (µg/m3) Adams Street (µg/m3) Tripp Street (µg/m3) Church Street (µg/m3)
12/14/2006 26 0 0 15
12/15/2006 Precip Precip Precip Precip
12/18/2006 Precip Precip Precip Precip
12/19/2006 0 0 3 0
12/20/2006 0 0 0 0
12/21/2006 0 0 0 0
12/22/2006 0 0 0 0
12/25/2006 Holiday Holiday Holiday Holiday
12/26/2006 Precip Precip Precip Precip
12/27/2006 0 0 0 0

Notes:
All readings reflect the daily average calculated over the course of the workday.
All readings collected with a Thermo Electron PDR 1000.
NSC: No sampling conducted; No intrusive work conducted in that area.
Precip: No sampling conducted due to precipitation.

4. T&D "BI-WEEKLY" SUMMARY

DATE
DESTINATION
WASTE DETERMINATION
TONS
STOCKPILES
28 Dec. 06 TAUNTON COMM-97-LINED   WF-02, 08, EA-38
27 Dec. 06 NO T&D ON THIS DAY
26 Dec. 06 NO T&D ON THIS DAY
22 Dec. 06 MARION COMM-97 494.30 WF-07, 09, 10
21 Dec. 06 MARION COMM-97 604.84 WF-07, 09, 10
20 Dec. 06 MARION COMM-97 626.16 WF-07, 09, 10
19 Dec. 06 MARION COMM-97 618.45 WF-07, 09, 10
18 Dec. 06 TREE SUB-D OVERSIZE 168.60 EA-20, 28, 37
15 Dec. 06 TREE SUB-D OVERSIZE 503.49 EA-20, 28, 37
14 Dec. 06 MARION COMM-97 857.79 WF-07, 09, 10
14 Dec. 06 TREE Subtitle-D/OVERSIZE 379.91 EA-20, 28, 37
13 Dec. 06 MARION COMM-97 517.78 WF-07, 09, 10
13 Dec. 06 TREE Subtitle-D/OVERSIZE 351.5 EA-20, 28, 37

5. T&D TOTAL SUMMARY

WK/E
DESTINATION
WASTE DETERMINATION
ORIGIN
TONS
29 Dec. 06 Marion COMM-97 NW-Fill TBD
29 Dec. 06 Taunton COMM-97-Lined NW-Fill TBD
22 Dec. 06 Marion COMM-97 NW-Fill 2343.75
15 Dec. 06 TREE Sub-D Oversize EAST FILL 1,040.00
15 Dec. 06 Marion COMM-97 NW-Fill 1,134.00
8 Dec. 06 TREE Sub-D Soils EAST FILL 1,805.81
8 Dec. 06 Marion COMM-97 NW-Fill/CID 1,143.58
1 Dec. 06 TREE Sub-D Soils CID/EAST/NW FILL 4,045.97
24 Nov. 06 TREE Sub-D Soils CID/ EAST FILL 1,590.00
17 Nov. 06 Bourne Sub-D Oversize CID/ EAST FILL 2,481.00
10 Nov. 06 TREE SUB-D CID 1,695.56
03 Nov. 06 Marion COMM-97 CID/EAST FILL 2,822.27
06 Oct. 06 Marion COMM-97 CID 1,264.56
29 Sept. 06 Marion COMM-97 CID 674.45
22 Sept. 06 Crapo COMM-97 CID 436.85
15 Sept. 06 Crapo COMM-97 CID 800.51
T&D TOTAL
23,278.31

 

6. EXCAVATION SUMMARY

WEEKS /E 12/22/06 – 12/29/06
TO DATE
ACTIVITIES INITIAL TOTAL QUANTITY INITIAL TOTAL QUANTITY
Commercial Area Excavation Complete 2,655 CY
C.I.D. Excavation None 7,083 CY
East Fill Excavation None 9,046 CY
NW-Fill Area None 8,612 CY
Lagoon Area 2,532 CY 2,532 CY
 