Jump to main content.


North Carolina Proposed Title V Permits

The following permits have been submitted to EPA Region 4 as Proposed Title V permits. While EPA has the right to a 45-day review period for all Proposed Title V permits, EPA Region 4 targets only a subset of these permits for comprehensive review. To find out which permits have been targeted for EPA Region 4 review, please contact the Region 4 staff person(s) listed at the bottom of this page.

Title V Permits Undergoing Sequential Review*

State County Source Name
PA Permit Number
45-Day Review Ends (sequential)
Petition Deadline
           

Title V Permits Undergoing Parallel Review**
State County Source Name
PA Permit Number
45-Day Review Ends (parallel)
Petition Deadline
NC Forsyth Hanes Mill Road Sanitary Waste Landfill 00913-TV-5 3/14/2014 6/14/2014
NC Johnston May-Craft Fiberglass Products 08183T06 3/21/2014 6/19/2014
NC Catawba Prysmian Cables and Systems 07334T26 3/22/2014 6/20/2014
NC New Hanover CTI of North Carolina 05870T17 3/7/2014 6/20/2014
NC Wilson Saint-Gobain Containers 03713T32 3/29/2014 6/27/2014
NC McDowell Coats North America - Sevier Plant 01895T25(1) 3/29/2014 6/27/2014
NC Burke Saft America, Inc. 04595T15 3/30/2014 6/28/2014
NC Onslow Onslow County Landfill 09928T03 4/6/2014 7/5/2014
NC Rowan Plant Rowan County 08758T16 4/6/2014 7/5/2014
NC Catawba Blackburn Sanitary Landfill 08533T10 4/6/2014 7/5/2014
NC Hertford Nucor Steel Company 08680T18 4/10/2014 7/9/2014
NC Wayne Georgia-Pacific Wood Products, LLC 09268T17 4/12/2014 7/11/2014
NC Catawba HWS Company Hickory White 02796T19 4/13/2014 7/12/2014
NC Rowan Daimler Trucks North America 04625T32 4/13/2014 7/12/2014
NC Onslow Camp Lejuene 06591T33 4/20/2014 7/16/2014
NC Cumberland DAK Americas 04319T23 4/17/2014 7/16/2014
NC Cabarrus Concord Energy, LLC 09985T03 4/21/2014 7/20/2014
NC Hoke CBF Holdings, LLC 09593T08 4/25/2014 7/24/2014
NC Craven Hatteras Yachts 02742T14 4/25/2014 7/24/2014
NC Pitt DSM Pharmaceuticals 05754T93 4/28/2014 7/27/2014
NC Northampton West Fraser/International Paper - Seaboard 03937T21 5/30/2014 8/28/2014
NC Edgecombe Nomaco Inc - Tarboro 08559T16 5/18/2014 8/31/2014
NC Mecklenburg Charlotte Pipe and Foundry 14-01V-626 6/7/2014 9/1/2014
NC McDowell Coats North America - Sevier Plant 01895T25(2) 6/6/2014 9/4/2014
NC Mecklenburg Motiva Enterprises, LLC 14-01V-689 6/20/2014 9/15/2014
NC Carteret Slurry Pavers 00056T18 6/22/2014 9/20/2014
NC Wake NCSU Central Heat Plant 02977T22 6/23/2014 9/21/2014
NC Catawba Plastic Packaging, Inc. 04691T26 6/27/2014 9/25/2014
NC McDowell JELD-WEN, Inc. 06486T20 6/29/2014 9/28/2014
NC Hertford Nucor Steel Company 08680T19 7/13/2014 10/10/2014
NC Buncombe AMCOR Flexibles 11-539-14 7/13/2014 10/11/2014
NC Forsyth Ingredion 00732-TV-11 7/17/2014 10/15/2014
NC Davidson Kurz Transfer Products 06542T21 7/21/2014 10/19/2014
NC Chatham General Shale Brick, Inc 04384T37 7/26/2014 10/24/2014
NC New Hanover Progress Energy - Sutton Plant 01318T30 7/27/2014 10/25/2014
NC Bladen Smithfield Packaging Corporation 07221T17 8/2/2014 10/31/2014
NC Anson Piedmont Natural Gas - Lumberton Facility 10097T01 8/2/2014 10/31/2014
NC Chatham Performance Fibers 02657T29 8/4/2014 11/2/2014
NC Caldwell Pregis Innovation Packaging, Inc. 06552T08 8/7/2014 11/5/2014
NC Lenoir Masterbrand Cabinets 08804T11 8/10/2014 11/8/2014
NC Guilford Pactiv Corporation 06095T20 8/11/2014 11/9/2014
NC Graham Stanley Furniture Company 03794T26 8/11/2014 11/9/2014
NC Catawba Century Furniture 03749T18 8/16/2014 11/15/2014
NC Catawba Century Furniture 03749T18 8/16/2014 11/15/2014
NC Jackson Jackson Paper 04665T15 8/25/2014 11/23/2014
NC Martin Domtar Paper - Plymouth 04291T40 8/28/2014 11/26/2014
NC Craven Marine Corps Air Station Cherry Point 04069T35 8/30/2014 11/29/2014
NC Guilford Cone Mills Corp - White Oak Plant 03470T21 9/1/2014 11/30/2014
NC Mecklenburg Gerdau Long Steel 14-01V-567 8/30/2014 12/1/2014
NC Duplin Valley Proteins 05127T23 9/14/2014 12/13/2014
NC Chowan Regulator Marine 07132T11 9/15/2014 12/14/2014
NC Wake Cargill Inc - Raleigh 03840T39 9/17/2014 12/17/2014
NC Stokes Duke Energy - Belews Creek Steam Station 01983T29 9/22/2014 12/21/2014
NC McDowell Baxter Healthcare Corporation 05600T15 10/4/2014 1/2/2015
NC Hertford Perdue Grain and Oilseed, LLC 02875T31 10/5/2014 1/3/2015
     

* Sequential Review means the EPA 45-day review period does not begin until the 30-day public comment period ends. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends.

** Parallel Review means the EPA 45-day review period runs concurrently with the 30-day public comment period and ends no earlier than 15 days after the end of the public comment period. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends, calculated as if the Title V permit was under sequential review (i.e., the petition deadline will be the same regardless of whether Parallel or Sequential Review is followed.)

 

For information about the contents of this page please contact Lori Shepherd


Local Navigation


Jump to main content.