Basement of main building being cleared of debris. The basement will be filled in using on-site, clean material.

Basement of main building being cleared of debris. The basement will be filled in using on-site, clean material.

Interior photo of main building after removal of burned and contaminated material.

Interior photo of main building after removal of burned and contaminated material.

Cleaned area under the

Cleaned area under the "office area" of the main burned building.

April 2009

The 13th Street side of the building showing the original building

The 13th Street side of the building showing the original building "office."

Part of the fire damaged building with cleanup in progress.

Part of the fire damaged building with cleanup in progress.

Site contaminated material storage containers and debris.

Site contaminated material storage containers and debris.

The Madge Youtz Branch Library, 2921 Mahoning Road, Canton. The site Information Repository is located within this building. In addition, it is often used as the site public meeting location.

The Madge Youtz Branch Library, 2921 Mahoning Road, Canton. The site Information Repository is located within this building. In addition, it is often used as the site public meeting location.

An EPA contractor working in protective suit due to the asbestos and silica quartz contamination. Wearing the suit is a normal safety procedure.

An EPA contractor working in protective suit due to the asbestos and silica quartz contamination. Wearing the suit is a normal safety procedure.

The EPA and contractor work trailer is located across the street from the site. The work trailer is open during normal day work hours. EPA employees are available to answer questions from the public.

The EPA and contractor work trailer is located across the street from the site. The work trailer is open during normal day work hours. EPA employees are available to answer questions from the public.

ERRS removing a transformer from the

ERRS removing a transformer from the "rear" of the building.

Preparing staging pads to receive drums and totes.

Preparing staging pads to receive drums and totes.

ERRS cleaning sand and debris from inside the complex. This part of the site will remain for reuse.

ERRS cleaning sand and debris from inside the complex. This part of the site will remain for reuse.

The main drum and tote storage area. These containers will later by removed to a properly licensed facility.

The main drum and tote storage area. These containers will later by removed to a properly licensed facility.

Team removing asbestos contaminated materials from inside the fire-damaged structure.

Team removing asbestos contaminated materials from inside the fire-damaged structure.

Asbestos contaminated material being consolidated for removal to an approved landfill.

Asbestos contaminated material being consolidated for removal to an approved landfill.

Part of the burned area of the building.

Part of the burned area of the building.

Debris being consolidated in preparation for removal.

Debris being consolidated in preparation for removal.

Stained ground near some equipment. Often this

Stained ground near some equipment. Often this "leaking oil" is contaminated with PCBs.

Unknown liquids leaking from 55-gallon drums. When a drum is too damaged to be moved, it may be

Unknown liquids leaking from 55-gallon drums. When a drum is too damaged to be moved, it may be "over-packed" (placing a larger drum around the damaged drum) and then consolidated for removal.